Next Article in Journal
A Method Based on CNN–BiLSTM–Attention for Wind Farm Line Fault Distance Prediction
Previous Article in Journal
Influences of the Stiffness and Damping Parameters on the Torsional Vibrations’ Severity in Petroleum Drilling Systems
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Mid- to Long-Term Distribution System Planning Using Investment-Based Modeling

by
Hosung Ryu
,
Wookyu Chae
,
Hongjoo Kim
and
Jintae Cho
*
KEPCO Research Institute (KEPRI), 105 Munji-ro, Yuseong-gu, Daejeon 34056, Republic of Korea
*
Author to whom correspondence should be addressed.
Energies 2025, 18(14), 3702; https://doi.org/10.3390/en18143702
Submission received: 23 June 2025 / Revised: 10 July 2025 / Accepted: 11 July 2025 / Published: 14 July 2025
(This article belongs to the Section F2: Distributed Energy System)

Abstract

This study presents a practical and scalable framework for the mid- to long-term distribution network planning that reflects real-world infrastructure constraints and investment requirements. While traditional methods often rely on simplified network models or reactive reinforcement strategies, the proposed approach introduces an investment-oriented planning model that explicitly incorporates physical elements such as duct capacity, pole availability, and installation feasibility. A linear programming (LP) formulation is adopted to determine the optimal routing and sizing of new facilities under technical constraints including voltage regulation, power balance, and substation capacity limits. To validate the model’s effectiveness, actual infrastructure and load data were used. The results show that the model can derive cost-efficient expansion strategies over a five-year horizon by prioritizing existing infrastructure use and flexibly adapting to spatial limitations. The proposed approach enables utility planners to make realistic, data-driven decisions and supports diverse scenario analyses through a modular structure. By embedding investment logic directly into the network model, this framework bridges the gap between high-level planning strategies and the engineering realities of distribution system expansion.

1. Introduction

In recent years, the electric power industry has witnessed substantial transformations driven by increasing electricity demand, widespread urban development, and the global shift toward cleaner and decentralized energy systems [1]. Among the many challenges facing power utilities, the need to secure long-term infrastructure reliability and economic investment efficiency has placed growing importance on mid- to long-term distribution network planning [2,3,4]. This type of planning involves systematically preparing the distribution grid for expected changes over a time horizon typically ranging from five to fifteen years.
The primary objectives of mid- to long-term distribution planning include ensuring power supply stability, identifying economically viable infrastructure investments, and facilitating the integration of emerging technologies such as distributed energy resources (DERs), electric vehicles (EVs), and energy storage systems (ESS) [5]. Traditionally, distribution systems have been planned based on short-term load growth and reactive reinforcement strategies [6]. However, the increasing complexity and uncertainty in energy demand and supply have rendered such approaches inadequate for anticipating future challenges [7,8,9].
In this context, long-term planning must incorporate not only accurate demand forecasting, but also physical and operational constraints associated with the distribution infrastructure [10,11]. This includes assessing the capacity of substations, overhead and underground lines, duct availability, and pole configurations. Moreover, as new residential areas, industrial complexes, and public infrastructure continue to expand—particularly in rapidly growing urban environments such as new towns or special administrative regions—planning tools must evolve to reflect both spatial and temporal constraints [12,13].
While several methodologies have been proposed for long-term distribution planning, many rely on simplified system models that lack sufficient granularity in physical network representation. Existing approaches often focus on feeder-level abstraction and overlook critical aspects such as the availability of existing ducts, pole occupancy, or installation feasibility along candidate routing paths. As a result, there is a clear gap between academic optimization models and the detailed engineering realities faced by utility planners.
To address these limitations, this study proposes a practical and scalable planning framework that combines physical network modeling with investment-based optimization. The core contribution of this work lies in the development of a distribution network model tailored for long-term investment planning, in which physical constraints and existing infrastructure availability are explicitly modeled. This framework allows planners to identify feasible routing paths, calculate costs based on actual installation units, and optimize network reinforcement while minimizing overall investment costs.
To solve the planning problem, this study adopts a linear programming (LP) formulation, which enables the efficient computation of optimal investment strategies under technical constraints such as voltage limits, substation capacity, and power flow restrictions [14,15]. The proposed model is implemented using IBM CPLEX Optimization Studio and validated through a case study of Sejong City, South Korea—a newly developed urban area characterized by fast-growing electricity demand and complex planning requirements.
The remainder of this paper is organized as follows: Section 2 describes the architecture and key features of the proposed investment-oriented network model. Section 3 formulates the linear programming model, detailing the objective function and technical constraints. Section 4 presents a real-world case study, demonstrating the model’s applicability and analyzing the resulting investment plans. Section 5 concludes by summarizing this study’s contributions, highlighting the practical value of the proposed planning methodology and its foundation on a realistic, infrastructure-based system model.

2. Mid- to Long-Term Distribution Planning Model

2.1. Distribution System Modeling

Mid- to long-term distribution planning is a strategic process typically conducted over a planning horizon of 5 to 15 years. It is designed to address growing electricity demand and the increasing integration of distributed energy resources (DERs) by systematically identifying the optimal strategies for expanding and reinforcing the distribution network [16,17]. The ultimate objective is to ensure power supply stability, reliability, and cost-effectiveness through demand forecasting, evaluation of existing capacity, and prioritization of infrastructure investments.
Unlike transmission system planning, traditional distribution system planning has typically involved passive investments. When new customers or distributed energy resources (DERs) request grid connections, utilities review the network and expand facilities as needed. However, this reactive approach does not ensure cost-effective or optimal infrastructure development.
In recent years, with the increasing construction of data centers and large-scale photovoltaic plants—both of which demand significant power capacity—it has become essential to proactively assess supply capability and investment requirements. Conventional planning methods, which often rely on comparing only a few manually defined scenarios, are insufficient for such complexity. This calls for the adoption of a systematic and data-driven approach to distribution network planning.
To support this planning process, it is essential to construct a distribution system model that accurately reflects the current network configuration and evaluates its capacity for future expansion. Unlike conventional line-based models, mid- to long-term planning requires a more advanced model that incorporates physical infrastructure constraints—such as duct availability, pole locations, and right-of-way feasibility.
The core objective of this modeling effort is to determine the optimal placement and sizing of new facilities while accounting for the limitations and layout of the existing system. To achieve this, the model must incorporate two key types of information:
  • First, information about candidate paths for line routing. This refers to whether overhead or underground lines can physically be installed along each potential route.
  • Second, information regarding the capacity of existing infrastructure along these candidate paths. For example, if the duct capacity in a given path is already fully utilized, no additional underground cables can be installed along that route.
To incorporate this information, the conventional line-segment-based models are insufficient. A new model that considers physical infrastructure such as ducts and poles is required. Therefore, the system model for mid- to long-term planning should integrate all existing and potential line segments within the same candidate path into a unified representation, enabling route-level analysis and planning.
Figure 1 shows an example of a distribution system. The feeder extending from the substation consists of underground cables and overhead lines. The corresponding distribution network is abstracted into the planning model presented in Figure 2.
Figure 2 presents the distribution system model used for planning purposes. The network is composed of nodes and branches and may appear structurally simple at first glance. However, it is important to emphasize that this model is based on a node/branch framework, which captures the physical configuration of the distribution system, including ducts, poles, and cable installations.
This modeling approach differs from the conventional bus/line model commonly used in power flow analysis, where each bus represents an electrical point and each line is characterized primarily by electrical parameters such as impedance. In contrast, the node/branch model enables the explicit representation of physical installation constraints—such as the number of available ducts or overhead line positions—which are essential considerations in mid- to long-term distribution planning.
Each branch includes key attributes such as the number of overhead lines, spare overhead positions, number of underground cables, and available duct spaces. The detailed configuration of each branch depicted in Figure 2 is summarized in Table 1 below.
As shown in Table 1, Branch1 currently uses three out of nine available ducts, leaving six spare ducts for potential future cable installations. Even though no overhead lines are currently installed in this branch, if further expansion is required, additional ducts must be constructed.
In Branch2, two overhead lines are already installed and both the upper and lower sides of the pole are in use, leaving no space for further overhead lines. Therefore, any future expansion in this branch would require underground cable installation via newly constructed ducts.
In Branch3, one overhead line is installed, leaving one more overhead line available. Additional installations beyond this would require underground expansion as well.

2.2. Load Modeling

In mid- to long-term distribution planning, the future load must be forecasted and incorporated into the network model. This study classifies load modeling into two categories.
First, the projected load growth of existing customers is considered. This is estimated by applying utilization rates to the contracted demand, taking into account the industrial sector of each customer [18].
Second, the expected load from new, planned customers is incorporated. If future developments such as industrial complexes or residential areas are already planned and their expected demand is known, this information is included in the model to more accurately reflect anticipated system expansion requirements.
The future load of each existing customer is projected by applying an annual growth rate based on their industry classification. The forecasted load for customer i in year y is given by the following:
L i , y e x = L i , 0 e x   · ( 1 + r s ( i ) e x ) y
where
  • L i , y e x : projected load of existing customer i in year y;
  • L i , 0 e x : base-year load of existing customer i;
  • r s ( i ) e x : annual load growth rate for existing customers in industry type s(i);
  • y : number of years after the base year.
For newly planned customers, the forecasted load is calculated by multiplying the contracted demand by a time-dependent weight factor associated with the customer’s industry type. The weight factor increases annually but is capped at a predefined maximum. The load in year y is expressed as follows:
L j , y n e w = D j   · m i n ( w s j , 0 + w s j · y , w s ( j ) m a x ) y
where
  • L j , y n e w : projected load of planned new customer j in year y;
  • D j : contracted demand of new customer j;
  • w s j , 0 : initial load weight factor for industry type s(j);
  • w s j : annual increment of weight factors for industry type s(j);
  • w s ( j ) m a x : maximum allowable weight factor for industry type s(j).
The total load at each node is calculated as the sum of the projected loads from both existing and planned new customers connected to that node. Existing customers follow an industry-specific annual growth rate, while new customers are modeled using time-dependent weight factors based on their contracted demand and industry type. The total load at node n in year y is given by the following:
L n , y = i C e x ( n ) L i , y e x + j C n e w ( n ) L j , y n e w
where
  • L n , y : total load at node n in year y;
  • C e x ( n ) : set of existing customers at node n;
  • C n e w ( n ) : set of planned new customers at node n.

2.3. PV Modeling

In mid- to long-term distribution planning, the PV output is modeled as a fraction of the installed capacity using a weight factor Yi, which reflects long-term solar potential at each location [19]. The expected PV generation at node n is given by the following:
P n P V = C n P V · γ n
where C n P V denotes the installed capacity (in kW) of the n-th photovoltaic (PV) installation and γ n [ γ n m i n , γ n m a x ] represents the range of possible generation outcomes under the worst- and best-case solar conditions.

3. Problem Formulation

3.1. Objective Function

The objective of mid- to long-term distribution planning is to minimize future investment costs in response to anticipated load growth, taking into account the existing system configuration. The major cost components include overhead lines, utility poles, underground cables, and underground ducts. Each cost is calculated proportionally to the length of each branch, as expressed in the following formulas:
C o s t _ O L b = l b · ( C l i n e + C o h s w )    
C o s t _ p o l e b = l b · N p o l e · C p o l e
C o s t _ U C b = l b · ( C c a b l e + C u g s w )
C o s t _ d u c t b = l b · ( C d u c t + C m h )
where
  • l b : length of branch b;
  • C l i n e : unit cost per km of overhead line;
  • C o h s w : cost of overhead switch;
  • N p o l e : number of poles required per km;
  • C p o l e : cost of overhead pole;
  • C c a b l e : unit cost per km of underground cable;
  • C u g s w : cost of underground switch;
  • C d u c t : cost of duct installation (e.g., corrugated conduit);
  • C m h : cost of manhole installation.
Equation (5) represents the investment cost for overhead line installation, including both line material and switch. Equation (6) accounts for the cost of utility pole installation, calculated based on the number of poles required per unit length. Equation (7) denotes the cost of underground cable installation, incorporating both the cable and associated underground switch. Equation (8) refers to the cost of constructing the underground duct infrastructure, including conduit and manhole installation.
Based on these cost components, the objective function is formulated as follows:
O b j . F u n c : min Z = y = 1 Y b = 1 B ( C o s t _ O L b + C o s t _ p o l e b + C o s t _ U C b + C o s t _ d u c t b )  
This objective function minimizes the total investment cost of the new distribution infrastructure across all planning years and for all branches under consideration.

3.2. Constraints

3.2.1. Power Balance Constraint

Optimization is subject to power flow constraints that ensure the physical laws of energy balance across the entire network. At each node, the incoming and outgoing power flows must be equal [20]. This condition can be mathematically expressed as follows:
s . t .   i j = 1 J ( f i j f j i ) S i + D i = 0 )   ( i j )
where
  • f i j : the power flows from node i to node j;
  • S i : power supplied by the substation at node i;
  • D i : load at node i.
In this model, power flow is defined as positive when flowing from the sending node to the receiving node. All power quantities are expressed in megawatts (MWs).
Given the scope of mid- to long-term planning and the scale of the network, solving full AC power flow equations would result in a substantial computational burden. Therefore, this study adopts a simplified linear approximation, assuming a constant power factor (PF) across all branches. As such, reactive power is not explicitly modeled, and the active power flow is considered proportional to the apparent power. This assumption enables efficient optimization while maintaining adequate accuracy for infrastructure planning purposes.

3.2.2. Maximum Power Flow Constraint

The model includes maximum power flow constraints to ensure that no branch exceeds its rated thermal capacity [21].
s . t . i ( f i j F i j m a x )   ( i j )
where
  • F i j m a x : maximum power flow between node i and node j.

3.2.3. Voltage Constraint

The system is subject to voltage drop constraints to ensure that all node voltages remain within acceptable limits.
V m i n V i V m a x ,   i
where
  • V i : voltage at node i;
  • V m i n : lower bound of acceptable voltage range;
  • V m a x : upper bound of acceptable voltage range.

3.2.4. Substation Capacity Constraint

A substation capacity constraint is imposed to ensure that the total power supplied from each substation does not exceed its rated limit [22].
P s P s m a x ,   s
where
  • P s : active power output of substation at node s;
  • P s m a x : maximum active power output of the substation at node s.

3.2.5. New Customer Supply Constraints

In accordance with utility design practices, newly contracted loads exceeding a predefined threshold L t h must be supplied through dedicated new distribution feeders. This constraint ensures that large customer loads do not overload the existing infrastructure and are instead supported by newly constructed lines. The threshold value can be flexibly set depending on the utility’s planning standards or regional policies.
The corresponding constraint is formulated as follows:
δ j L j n e w L t h ,   j
δ j 0 ,   j
L j s u b δ j ,   j
where
  • L t h : predefined threshold load [MVA];
  • δ j : auxiliary variable representing the excess demand beyond the threshold;
  • L j s u b : substation feeder capacity newly allocated to node j.

3.2.6. Physical Infrastructure Constraints

In real-world distribution systems, the physical infrastructure such as utility poles and underground ducts imposes limitations on the installation of new feeders and cables. These constraints must be considered in the planning process to ensure that proposed expansion plans are feasible and comply with structural and spatial restrictions.
The following equations formulate the physical expansion constraints associated with overhead lines and underground cables.
N b O H N b O H , m a x ,           b   B    
N b U G N b U G , m a x ,           b   B  
where
  • N b O H : number of overhead lines installed on branch b;
  • N b O H , m a x : maximum number of overhead lines allowed on branch b;
  • N b U G : number of underground cables installed on branch b;
  • N b U G , m a x : maximum number of underground cables allowed on branch b.
Equations (17) and (18) define the maximum installation limits for overhead lines and underground cables on each branch. Once a branch reaches its installation capacity, no further expansion is permitted on that branch.

3.3. Solution Approach Using Linear Programming

To solve the mid- to long-term distribution network planning problem, this study adopts a linear programming (LP) approach. LP is particularly effective for optimization problems in which both the objective function and all constraints are linear [23,24,25,26,27]. It enables the use of deterministic algorithms such as the simplex and interior-point methods, offering high computational efficiency and scalability, which are crucial for large-scale grid planning.
In the proposed model, all constraints—such as power balance, line capacity limits, voltage constraints, and substation output limits—are formulated as linear equalities or inequalities. This allows the model to fully comply with the LP framework and benefit from efficient solver performance.
Moreover, the LP formulation enables the interpretation of dual variables, including shadow prices, which offer insights into the marginal value of constrained resources. For instance, a nonzero shadow price for substation capacity or duct availability reveals the economic benefit of relaxing such constraints, thereby aiding investment prioritization.
The model was implemented using IBM CPLEX Optimization Studio and solved using its LP solver. The platform provides fast and reliable solutions and supports extensive scenario analysis involving variations in load growth and DER penetration. Thus, the LP-based approach offers both theoretical rigor and practical utility for planners seeking cost-effective and scalable long-term distribution strategies. Table 2 summarizes the main advantages of using LP in this context [28].

3.4. Overall Distribution Planning Work

The planning process proposed in this study is structured into three sequential phases: modeling, strategy, and optimization. In the modeling phase, the existing distribution system is reformulated into a planning-oriented network model. This model incorporates key physical infrastructure data such as duct capacity, pole availability, and candidate routing paths. Unit investment costs for various equipment—such as overhead lines, poles, underground cables, and ducts—are also defined for use in cost estimation. The strategy phase focuses on scenario development based on planning objectives. For example, different weighting combinations can be applied to represent high-load/low-PV or low-load/high-PV conditions. This phase configures assumptions for load growth, PV generation scaling, and technical constraints such as voltage and capacity limits. Finally, in the optimization phase, a linear programming (LP) model is formulated and solved using IBM CPLEX Optimization Studio to identify the cost-minimizing expansion strategy under the defined assumptions.
An overview of this three-phase framework is illustrated in Figure 3.

4. Case Study

The proposed distribution system modeling and linear programming formulation were implemented in Advanced Distribution Planning System (ADPS), a platform developed by KEPCO for mid- to long-term distribution planning. The modeling components including physical infrastructure representation, load and PV modeling, and investment cost structures were customized according to the framework proposed in this study. The optimization module within the ADPS also integrates the LP-based problem solution developed by the authors.
A case study based on this implementation is presented in Section 4 to validate the effectiveness and practicality of the proposed approach.

4.1. Case Study System Description

This study targets a city-scale distribution system, which is a typical scope for mid- to long-term distribution planning due to the scale and complexity of required investments. The distribution system of Sejong City, South Korea, was selected as the case study because of its unique characteristics as a newly developed urban area with a rapidly increasing electricity demand. Sejong’s continuous growth in residential and administrative facilities provides a realistic and challenging testbed for validating the proposed planning framework.
The proposed distribution system is illustrated in Figure 4.
Figure 4 illustrates the topology of the distribution system in Sejong City. In the figure, red circles indicate the locations of substations, blue lines represent overhead line sections, and red lines indicate underground cable sections. The system consists of six substations labeled A through F. These substations collectively supply 1052.48 MVA of capacity to the city’s network. The initial year total load is 540 MVA, and demand is expected to increase by approximately 300 MVA over the next five years due to rapid urban development. The supply capacity of each substation is detailed in Table 3. These substations collectively form the backbone of the Sejong distribution system and serve as the primary sources for power delivery throughout the network.
The projected load increase consists of two components: the natural growth of existing loads and newly contracted customer demands.
Approximately 247.89 MVA is attributed to newly contracted loads, while 52.70 MVA accounts for natural growth. The detailed year-by-year breakdown of the load increase is provided in Table 4.
The annual growth rates presented in Table 4 are derived from Korea’s Basic Plan of Long-term Electricity Supply and Demand, published biennially by the government. These values serve as official national projections for electricity demand growth and are commonly used in distribution planning [29].
The weight factors w s j , 0 were derived by analyzing AMI data from Sejong City, categorized by industrial sectors. For each sector, a probabilistic normal distribution of the daily load profile was constructed, and the upper 5% quantile was used to represent typical peak load conditions. This methodology is consistent with the approach presented in Korea Electric Power Corporation’s “Electricity Consumption Behavior Analysis Report” [30].
A total of nine new customer connections have been confirmed for future integration into the distribution system, including six industrial complexes, two residential developments, and one large-scale manufacturing facility. These newly contracted loads represent a significant portion of the projected demand growth and are scheduled to be commissioned progressively over the five-year planning horizon. Table 5 summarizes the total contracted capacities by customer type and presents the annual allocation of these loads from N + 1 to N + 5, where N denotes the base year.
Accurate estimation of the investment costs requires the definition of standardized unit costs for each distribution component. In this study, ACSR 160 sq conductors are adopted as the standard specification for overhead lines, and CNCE-W AL 400 sq cables are used for underground lines. Both types of lines are designed to accommodate a maximum power transfer capacity of 10 MVA, ensuring consistent modeling across installation methods. Table 6 summarizes the unit investment costs of the major components utilized in the proposed distribution planning model.

4.2. Optimization Results

The proposed optimization model was applied to the distribution system model using the data and assumptions described in Section 4.1. The objective function aimed to minimize the total investment cost while satisfying forecasted load growth, physical infrastructure constraints (e.g., spare duct and pole availability), and technical constraints such as voltage drop and substation capacity.
The linear programming model was solved using IBM ILOG CPLEX Optimization Studio 22.1 with an Intel Xeon 3.6 GHz processor and 64 GB RAM, running on Windows 11. The test system consisted of 2510 nodes and 3132 branches, and the entire five-year planning simulation was completed in 3 min and 32 s, demonstrating the model’s scalability and computational efficiency.
The solution yielded a year-by-year expansion strategy for the five-year planning horizon (N + 1 to N + 5). Over the entire planning horizon, a total of 27 new feeders are introduced, extending more than 85 km of overhead lines and 250 km of underground cables, with a cumulative investment cost of approximately USD 97.8 million.
To reflect practical planning practices, this study introduces a design constraint based on load magnitude. A threshold value, denoted as L t h , is defined to represent the minimum load capacity that warrants a dedicated distribution feeder. In this model, L t h is set to 0.5 MVA, aligning with typical utility guidelines. Accordingly, any newly contracted load exceeding L t h must be supplied via a new feeder. Based on this condition, as detailed in Table 7, a total of nine new feeders were introduced in year N + 1, each exclusively serving newly connected customers. No additional feeders were required to accommodate the growth of existing loads, as their increase remained within the capacity of the current infrastructure.
Figure 5 illustrates the optimized distribution system configuration for the planning year N + 1 as below.
Figure 5 presents the optimization results for the year N + 1. The red lines in the figure indicate sections where the new feeders are installed. As proposed in this study, the optimization process identifies available space within the existing infrastructure and minimizes investment costs accordingly.
According to the results, two new feeders are drawn from Substation A, supplying an additional load of approximately 18.16 MVA. Substation B accommodates the largest expansion, with five new feeders and a total capacity of 49.82 MVA. Substation C also expands with two new feeders, supplying an additional 18.16 MVA.
From years N + 2 to N + 4, the system responds to increasing demand from both newly contracted and existing customers through the optimal expansion of distribution lines. In year N + 5, although only five new feeders are required and most of the areas suitable for cost-effective overhead line installation have already been utilized. Consequently, the remaining demand must be met using underground cables, resulting in the highest investment cost across the five-year planning horizon.

4.3. Discussion

The optimization results obtained from the proposed LP-based mid- to long-term distribution planning model offer several practical insights.
First, the model successfully identifies cost-effective expansion strategies by leveraging available physical infrastructure. For instance, in the early planning years (N + 1 to N + 3), the model prioritizes the use of spare duct spaces and available overhead pole capacity to minimize total investment costs. This demonstrates the importance of including existing structural information—such as pole and duct availability—into the planning model.
Second, as observed in year N + 5, when the existing overhead line routes become saturated, the model naturally shifts toward more expensive underground installations. Although only five new feeders were introduced in N + 5, the lack of remaining overhead capacity led to the highest annual investment cost over the five-year horizon. This result highlights a common challenge in mature or densely developed areas, where above-ground expansion becomes increasingly constrained.
Another noteworthy observation relates to the use of the new customer connection constraint. By setting a threshold load (e.g., 0.5 MVA) above which a new dedicated feeder must be introduced, the model more accurately reflects practical utility planning standards. While this constraint increases total investment, it ensures that large customers are supplied with sufficient capacity and reliability. The flexibility of treating this threshold as a parameter also allows for sensitivity analysis in future studies.
Moreover, the planning framework allows for diverse scenario configurations by adjusting growth rates and PV weights. This strategic flexibility enables planners to test best- and worst-case assumptions regarding load expansion and renewable penetration without altering the underlying system structure. It reflects a key strength of using a linear model: the scalability and transparency of the planning logic.
Lastly, the application of this model within the Advanced Distribution Planning System (ADPS) framework further validates its feasibility for real-world utility planning. The integration of actual system data from Sejong City and the use of practical investment unit costs confirm that the model is not only computationally efficient but also realistically implementable in the field.
In a pilot study based on actual planning data, the proposed model demonstrated the potential to reduce the five-year distribution planning budget—originally estimated at USD 572,595,000—by approximately 5% (USD 28,629,950). In addition, improvements in task automation and process efficiency were shown to reduce labor-related costs by an additional USD 1,856,000 [31].
Since current distribution planning processes are largely carried out manually by expert engineers without the support of a standardized optimization tool, direct comparisons with existing methods are limited. Nonetheless, these results suggest that the proposed model is not only theoretically effective but also practically beneficial in large-scale utility operations.
These results suggest that the proposed framework can serve as a reliable decision-support tool for distribution utilities seeking to optimize infrastructure investment over a multi-year horizon while accounting for technical and physical constraints.

5. Conclusions

This study presents a mid- to long-term distribution planning framework based on a newly structured, investment-oriented network model. By incorporating physical constraints—such as available ducts, pole locations, and candidate routing paths—the proposed model enables realistic and cost-effective expansion strategies that reflect the actual conditions of urban power systems.
The optimization problem was formulated as a linear program (LP) and solved using IBM CPLEX to minimize total investment costs while satisfying technical constraints. These include voltage regulation, substation capacity limits, and line flow constraints, all of which were expressed as linear relationships. The LP formulation enabled efficient computation and scalability to large-scale planning problems.
The case study of Sejong City demonstrated that the proposed model can effectively leverage existing infrastructure and guide optimal system expansion over a five-year horizon. For example, the model identified when and where overhead line additions were feasible and when higher-cost underground installations were necessary due to spatial limitations. These results validate the model’s capability to reflect practical trade-offs in long-term investment planning.
The main contribution of this work lies in the development of a planning-oriented network model that integrates investment decision-making directly into the system configuration. Unlike traditional topological models, this approach allows planners to assess infrastructure constraints and routing feasibility early in the planning phase—thereby supporting proactive and data-driven decisions.
In addition, the proposed framework is designed to be modular and flexible. Utility planners can easily incorporate additional constraints—such as feeder installation thresholds or service reliability criteria—based on internal standards or regulatory requirements. This adaptability ensures the model’s applicability across a wide range of real-world planning environments.
As a future research direction, uncertainty in key planning parameters—such as load growth, DER output, and construction costs—could be addressed through stochastic programming approaches. Among these, the value at risk (VaR) methodology provides a practical means of quantifying investment risk, allowing planners to define acceptable risk thresholds under uncertainty [32].
In addition, the proposed model could be further extended using mixed-integer nonlinear programming (MINLP) to incorporate more complex operational constraints and resilience-oriented objectives, such as fault-tolerant configurations, equipment redundancy, and adaptive network reconfiguration under extreme conditions [33].

Author Contributions

Conceptualization, H.R. and J.C.; methodology, H.R. and J.C.; software, H.R. and H.K.; validation, H.R. and W.C.; formal analysis, H.R. and H.K.; resources, W.C. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Korea Institute of Energy Technology Evaluation and Planning (KETEP) and the Ministry of Trade, Industry & Energy (MOTIE) of the Republic of Korea (No. 20225500000060, R22DG02).

Data Availability Statement

The data supporting the findings of this study are available from the corresponding author upon reasonable request and with approval from KEPCO. Although the full dataset cannot be publicly shared due to confidentiality restrictions, the database schema (e.g., table structures, field names, and data formats) can be provided upon request to support reproducibility and transparency of the model development process.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Liu, C.; Li, B.; Zhang, Y.; Jiang, Q.; Liu, T. The LCC type DC grids forming method and fault ride-through strategy based on fault current limiters. Int. J. Electr. Power Energy Syst. 2025, 170, 110843. [Google Scholar] [CrossRef]
  2. Akhtar, I.; Kirmani, S.; Jameel, M. Reliability assessment of power system considering the impact of renewable energy sources integration into grid with advanced intelligent strategies. IEEE Access 2021, 9, 32485–32497. [Google Scholar] [CrossRef]
  3. Kihara, M.; Lubello, P.; Millot, A.; Akute, M.; Kilonzi, J.; Kitili, M.; Pye, S. Mid-to long-term capacity planning for a reliable power system in Kenya. Energy Strategy Rev. 2024, 52, 101312. [Google Scholar] [CrossRef]
  4. Vahidinasab, V.; Tabarzadi, M.; Arasteh, H.; Alizadeh, M.I.; Beigi, M.M.; Sheikhzadeh, H.R.; Sepasian, M.S. Overview of electric energy distribution networks expansion planning. IEEE Access 2020, 8, 34750–34769. [Google Scholar] [CrossRef]
  5. De Lima, T.D.; Franco, J.F.; Lezama, F.; Soares, J. A specialized long-term distribution system expansion planning method with the integration of distributed energy resources. IEEE Access 2022, 10, 19133–19148. [Google Scholar] [CrossRef]
  6. Varathan, G. A review of uncertainty management approaches for active distribution system planning. Renew. Sustain. Energy Rev. 2024, 205, 114808. [Google Scholar]
  7. International Energy Agency (IEA). World Energy Outlook 2022; International Energy Agency (IEA): Paris, France, 2022. [Google Scholar]
  8. Scott, I.J.; Carvalho, P.M.; Botterud, A.; Silva, C.A. Long-term uncertainties in generation expansion planning: Implications for electricity market modelling and policy. Energy 2021, 227, 120371. [Google Scholar] [CrossRef]
  9. Mohseni, S.; Brent, A.C.; Kelly, S.; Browne, W.N. Demand response-integrated investment and operational planning of renewable and sustainable energy systems considering forecast uncertainties: A systematic review. Renew. Sustain. Energy Rev. 2022, 158, 112095. [Google Scholar] [CrossRef]
  10. Iweh, C.D.; Gyamfi, S.; Tanyi, E.; Effah-Donyina, E. Distributed generation and renewable energy integration into the grid: Prerequisites, push factors, practical options, issues and merits. Energies 2021, 14, 5375. [Google Scholar] [CrossRef]
  11. Nadeem, T.B.; Siddiqui, M.; Khalid, M.; Asif, M. Distributed energy systems: A review of classification, technologies, applications, and policies. Energy Strategy Rev. 2023, 48, 101096. [Google Scholar] [CrossRef]
  12. Farivar, M.; Low, S.H. Branch flow model: Relaxations and convexification—Part I. IEEE Trans. Power Syst. 2013, 28, 2554–2564. [Google Scholar] [CrossRef]
  13. Aschidamini, G.L.; da Cruz, G.A.; Resener, M.; Ramos, M.J.; Pereira, L.A.; Ferraz, B.P.; Pardalos, P.M. Expansion planning of power distribution systems considering reliability: A comprehensive review. Energies 2022, 15, 2275. [Google Scholar] [CrossRef]
  14. Dantzig, G.B. Linear Programming and Extensions; Princeton University Press: Princeton, NJ, USA, 2016; 656p, ISBN 9781400884179. [Google Scholar]
  15. Morais, H.; Kádár, P.; Faria, P.; Vale, Z.A.; Khodr, H.M. Optimal scheduling of a renewable micro-grid in an isolated load area using mixed-integer linear programming. Renew. Energy 2010, 35, 151–156. [Google Scholar] [CrossRef]
  16. Elkadeem, M.R.; Abd Elaziz, M.; Ullah, Z.; Wang, S.; Sharshir, S.W. Optimal planning of renewable energy-integrated distribution system considering uncertainties. IEEE Access 2019, 7, 164887–164907. [Google Scholar] [CrossRef]
  17. Cho, G.J.; Kim, C.H.; Oh, Y.S.; Kim, M.S.; Kim, J.S. Planning for the future: Optimization-based distribution planning strategies for integrating distributed energy resources. IEEE Power Energy Mag. 2018, 16, 77–87. [Google Scholar] [CrossRef]
  18. Taylor, J.W. Short-term load forecasting with exponentially weighted methods. IEEE Trans. Power Syst. 2011, 27, 458–464. [Google Scholar] [CrossRef]
  19. Son, N.; Jung, M. Analysis of meteorological factor multivariate models for medium-and long-term photovoltaic solar power forecasting using long short-term memory. Appl. Sci. 2020, 11, 316. [Google Scholar] [CrossRef]
  20. Zhou, S.; Han, Y.; Yang, P.; Mahmoud, K.; Lehtonen, M.; Darwish, M.M.; Zalhaf, A.S. An optimal network constraint-based joint expansion planning model for modern distribution networks with multi-types intermittent RERs. Renew. Energy 2022, 194, 137–151. [Google Scholar] [CrossRef]
  21. Ryu, H.S.; Kim, M.K. Combined economic emission dispatch with environment-based demand response using WU-ABC algorithm. Energies 2020, 13, 6450. [Google Scholar] [CrossRef]
  22. Wei, Y.; Ye, Q.; Ding, Y.; Ai, B.; Tan, Q.; Song, W. Optimization model of a thermal-solar-wind power planning considering economic and social benefits. Energy 2021, 222, 119752. [Google Scholar] [CrossRef]
  23. Dantzig, G.B.; Thapa, M.N. Linear Programming: Theory and Extensions; Springer: New York, NY, USA, 2003; Volume 2. [Google Scholar]
  24. Conejo, A.J.; Carrión, M.; Morales, J.M. Decision Making Under Uncertainty in Electricity Markets; Springer: New York, NY, USA, 2010; Volume 1, pp. 376–384. [Google Scholar]
  25. Bixby, R.E. A brief history of linear and mixed-integer programming computation. Doc. Math. 2012, 2012, 107–121. [Google Scholar]
  26. Wood, A.J.; Wollenberg, B.F.; Sheblé, G.B. Power Generation, Operation, and Control; John Wiley & Sons: Hoboken, NJ, USA, 2013. [Google Scholar]
  27. Momoh, J.A. Smart Grid: Fundamentals of Design and Analysis; John Wiley & Sons: Hoboken, NJ, USA, 2012; Volume 33. [Google Scholar]
  28. Benidris, M.; Elsaiah, S.; Mitra, J. An emission-constrained approach to power system expansion planning. Int. J. Electr. Power Energy Syst. 2016, 81, 78–86. [Google Scholar] [CrossRef]
  29. Ministry of Trade, Industry and Energy (MOTIE). The 10th Basic Plan for Long-Term Electricity Supply and Demand (2022–2036); MOTIE: Sejong, Republic of Korea, 2022. (In Korean) [Google Scholar]
  30. Korea Electric Power Corporation (KEPCO). Electricity Consumption Behavior Analysis Report 2022; KEPCO: Naju, Republic of Korea, 2022. (In Korean) [Google Scholar]
  31. KEPCO. A Research of Advanced Distribution Planning System for Mid-Long Term; Korea Electric Power Corporation: Naju, Republic of Korea, 2024. (In Korean) [Google Scholar]
  32. Ryu, H.S.; Kim, M.K. Two-stage optimal microgrid operation with a risk-based hybrid demand response program considering uncertainty. Energies 2020, 13, 6052. [Google Scholar] [CrossRef]
  33. An, S.; Qiu, J.; Lin, J.; Yao, Z.; Liang, Q.; Lu, X. Planning of a multi-agent mobile robot-based adaptive charging network for enhancing power system resilience under extreme conditions. Appl. Energy 2025, 395, 126252. [Google Scholar] [CrossRef]
Figure 1. An illustration of an example of a distribution system.
Figure 1. An illustration of an example of a distribution system.
Energies 18 03702 g001
Figure 2. Distribution network planning model structure.
Figure 2. Distribution network planning model structure.
Energies 18 03702 g002
Figure 3. Overall framework for mid- to long-term distribution planning.
Figure 3. Overall framework for mid- to long-term distribution planning.
Energies 18 03702 g003
Figure 4. Topology of the Sejong city distribution system.
Figure 4. Topology of the Sejong city distribution system.
Energies 18 03702 g004
Figure 5. Optimized distribution system configuration for the year N + 1.
Figure 5. Optimized distribution system configuration for the year N + 1.
Energies 18 03702 g005
Table 1. Infrastructure configuration by branch.
Table 1. Infrastructure configuration by branch.
Branch Info.
Branch1Branch2Branch3
Number of overhead lines-21
Number of spare overhead lines-01
Number of underground cables300
Number of spare duct spaces600
Table 2. Advantages of linear programming (LP) in distribution network planning.
Table 2. Advantages of linear programming (LP) in distribution network planning.
AdvantageDescription
Computational efficiency [23]LP problems can be solved efficiently using deterministic algorithms, which is suitable for large-scale grid planning.
Scalability [24]LP models scale well with network size and complexity, which is essential in distribution planning.
Solver compatibility [25]LP is supported by various robust solvers such as CPLEX, Gurobi, and GLPK.
Interpretability [26]Results such as shadow prices and dual variables can provide useful economic and technical insights.
Flexibility in scenario analysis [27]The LP framework allows easy incorporation of different load growth and DER penetration scenarios.
Table 3. Substation information.
Table 3. Substation information.
123456
Substation LabelABCDEF
Supply Capacity182.16182.16182.16141.68182.16182.16
LocationNorthCentralCentralEastSoutheastSouthwest
Table 4. Load growth over the planning horizon.
Table 4. Load growth over the planning horizon.
YearNN + 1N + 2N + 3N + 4N + 5
Existing loads539.93550.73561.20571.86582.15592.63
Newly loads083.59111.34155.47199.11247.90
Total loads539.93634.32672.54727.33781.26840.53
Table 5. Summary of newly contracted loads.
Table 5. Summary of newly contracted loads.
FeatureTotal Contracted Capacity (MVA)N + 1
(MVA)
N + 2
(MVA)
N + 3
(MVA)
N + 4
(MVA)
N + 5
(MVA)
Manufacturing Facility8.58.50.00.00.00.0
Industrial Complex #12.81.00.30.30.30.7
Industrial Complex #212.34.61.51.51.51.5
Industrial Complex #38.23.11.01.01.02.1
Industrial Complex #40.80.30.10.10.10.2
Industrial Complex #512.44.71.61.61.63.1
Industrial Complex #619.97.52.52.52.55.0
Residential development #1173.452.017.334.734.734.7
Residential development #29.61.93.42.41.90
Table 6. Unit costs of major distribution components.
Table 6. Unit costs of major distribution components.
ComponentRated CapacityUnit CostUnit
Overhead Line10 MVAUSD 57,992USD/km
Underground Cable10 MVAUSD 186,085USD/km
Overhead Switch-USD 8608USD/km
Underground Switch-USD 102,918USD/km
Pole-USD 2569USD/unit
Duct-USD 139,416USD/km
Manhole-USD 45,735USD/km
Table 7. Detail annual optimization results.
Table 7. Detail annual optimization results.
YearNew Feeders (unit)Overhead Line Extension (km)Underground Cable Extension (km)Duct
Installation (km)
Investment Cost (USD)
N + 1965.28158.27430.61626.623 M
N + 233.65310.5539.6894.848 M
N + 341.1934.33812.00212.545 M
N + 466.21867.41521.71724.292 M
N + 559.51679.45333.64129.453 M
Total2785.858250.033107.66597.762 M
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Ryu, H.; Chae, W.; Kim, H.; Cho, J. Mid- to Long-Term Distribution System Planning Using Investment-Based Modeling. Energies 2025, 18, 3702. https://doi.org/10.3390/en18143702

AMA Style

Ryu H, Chae W, Kim H, Cho J. Mid- to Long-Term Distribution System Planning Using Investment-Based Modeling. Energies. 2025; 18(14):3702. https://doi.org/10.3390/en18143702

Chicago/Turabian Style

Ryu, Hosung, Wookyu Chae, Hongjoo Kim, and Jintae Cho. 2025. "Mid- to Long-Term Distribution System Planning Using Investment-Based Modeling" Energies 18, no. 14: 3702. https://doi.org/10.3390/en18143702

APA Style

Ryu, H., Chae, W., Kim, H., & Cho, J. (2025). Mid- to Long-Term Distribution System Planning Using Investment-Based Modeling. Energies, 18(14), 3702. https://doi.org/10.3390/en18143702

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop