2.1. State of the Art
The most common measure for comparing sources of energy is the LCOE, which is the ratio of lifetime OpEx and CapEx to total lifetime energy output. During the first several decades of wind energy development, the LCOE decreased impressively [
13]. Most of these improvements stem from increases in individual WTG size, rotor diameter, and nominal power output, as well as overall WF sizes [
14], which all directly enhance the productivity of wind energy while only increasing overall expenditures at a relatively lower rate. This is particularly true for offshore wind energy compared with onshore [
15], leading to comparatively increased interest in offshore wind despite its overall lower LCOE. While this trend is expected to continue [
14,
16], other solutions for decreasing LCOE are also being explored through cost-lowering strategies.
The overall cost of wind energy consists of approximately two-thirds CapEx, including costs related to project development, decommissioning, and financial expenses [
3]. While the WT itself has become more expensive recently due to rising commodity prices and higher interest rates [
17,
18], efforts are ongoing to improve other aspects of CapEx. The increased popularity of green financing [
19], the derisking of wind development projects [
20], and the creation of wind energy project auctions [
21] are all contributing to a better financial situation for the wind industry.
The number of WFs nearing their end of life is increasing [
22], leading to greater scrutiny of the decommissioning phase and interest in improving the overall life-cycle costs of the WT. Since WT blades are the largest components, sustainable and recyclable blades are being developed [
23]. Other blade materials are being analyzed for their recyclability and increased circularity [
24]. Some WFs have not experienced the level of stress that the WTs were designed for, enabling lifetime extensions and increasing the useful life of these sites [
22]. Similarly, designs are being made to improve the natural lifetime of the towers [
25].
However, most CapEx optimizations will only be performed once for each new WT. Improvements in WT installation, project development, and design enhancements can only be applied to future wind energy projects and will not benefit existing WFs. This is not the case for end-of-life improvements, but these are also one-time improvements for the decommissioning phase.
On the other hand, OpEx covers one-third of the total costs considered in the LCOE of offshore wind energy [
3], and improvements to OpEx operations can be applied more widely and readily. Any enhancement in an OpEx process can be implemented in existing WFs and may also compound throughout the WF’s lifetime, given that the process is performed continuously. This applies to general maintenance and servicing of the WFs. Additionally, by optimizing the maintenance of the WFs, the reliability, availability, and productivity improve, further enhancing the LCOE.
Given the significant share of OpEx in the LCOE of wind energy, it is a prime target for cost reduction and optimizations, which has been steadily occurring for onshore wind energy [
26]. While the overall OpEx developments for offshore wind energy are less clear [
17], there certainly seems to be potential [
27,
28]. This is due to the significant differences in OpEx between sites caused by varying complexities of operations among OWFs, and the generally low availability of information on OpEx for offshore wind projects. This further emphasizes the need for a generalized approach to predictive maintenance evaluation that can be applied across the diverse operational conditions of OWFs.
OpEx most often consists of cost elements related to O&M, insurance, land rent, taxes, and management [
29]. Of these, O&M is by far the single largest expenditure, taking up to 60% of total OpEx [
3,
30], being comparatively higher for offshore wind energy because of offshore logistical complexity [
31]. O&M is also the most readily improvable aspect, as it consists of many separate processes, like the supply chain of spare parts, general maintenance, WT operations, etc. Each of these can provide optimization opportunities.
Tendencies within improvements of O&M for wind energy follow the traditional methodology for O&M regimes. Many improvements are gained from improved reliability through condition monitoring and maintenance optimization [
32]. Through increasingly sophisticated sensor technology, inspection techniques, and data acquisition systems, operators have better control over the assets and can improve maintenance operations. An example is the inspection of blades’ surfaces by drone and utilizing computer vision models for the detection of blade faults [
33,
34,
35]. Similarly, simulation models of erosion of the blade leading edge are developed to improve protection of blades [
36], and prognostic failure models are developed for internal components [
37,
38]. Less specific and more top-down risk-based maintenance frameworks are designed in [
39,
40].
While the data collection and analysis have improved markedly, improvements to the actual logistics and supply chain management are in focus as well [
41]. For OWFs, this is especially the case because of the complex logistics [
42]. In [
43], a spare parts inventory is optimized in tandem with an O&M strategy, and a strategic level preventive maintenance and planning system is described considering several objectives in [
44,
45], where elements such as costs and reliability are optimized by considering asset degradation over time and failure rates. When planning the schedule for a specific maintenance campaign, several methods and approaches are available [
46], and examples can be found in [
11,
47]. While the methods are well described, the impact and benefits they can provide are evaluated from a strategic life-cycle perspective or are not considered at all.
Taking all the above into account, it is clear that efforts are put into improving the LCOE of wind energy in many different ways; however, we identified the following research gaps on the topic of predictive maintenance for OWFs. While there are separate and numerous sources for both predictive/preventive/reactive maintenance applications for OWFs, there is a poor understanding of how to apply these approaches in tandem. In particular, we found that the available strategic life-cycle cost analysis on the implementation of predictive maintenance suffers from a lack of knowledge of the short-term cost–benefits of predictive maintenance. Because of these gaps, we seek to investigate a specific methodology aimed at formulating a short-term cost–benefit analysis approach associated with predictive maintenance strategy implementation. Furthermore, while the risk-based maintenance strategies are explored from a macro perspective in the literature, this methodology will be validated in a case study of service mission planning with pre-existing preventive maintenance to better present the marginal impacts of predictive maintenance.
2.2. Maintenance Strategies
Three archetypes of maintenance strategies exist for maintaining OWFs [
48,
49,
50], which can also be mixed in their actual implementation. These are reactive, preventive, and predictive maintenance.
Reactive maintenance in OWFs involves responding to equipment failures or malfunctions that occur unexpectedly. This may include repairing damaged components, replacing faulty parts, or addressing issues arising from unforeseen events such as severe weather or equipment breakdowns. Since it involves emergency situations, it is never planned. The advantage is that there is a low likelihood of unnecessary maintenance, and the amount of maintenance is kept to a minimum. Moreover, the implementation of reactive maintenance is easy. However, the disadvantages include longer downtimes, the potential for more severe failures, the requirement for having spare parts always available, the need for teams and vessels to always be on standby, and potential damage to secondary components. These disadvantages make this maintenance strategy very expensive.
Preventive maintenance in OWFs involves regular prescheduled inspections, servicing, and upkeep of the WTs and associated infrastructure. This includes tasks such as checking for corrosion, inspecting blades for damage, testing electrical components, and performing scheduled maintenance activities to ensure that the WTs are operating efficiently and reliably. Maintenance operations are preplanned on a set time basis, such as every year, allowing for better scheduling based on available weather windows, vessel fleet, and service teams’ availability. Furthermore, preventive maintenance is best utilized once failure rates are known, and average failure intervals can be predicted accurately. If the interval is too short, it results in increased operational costs, wasted production time, and unnecessary replacements of components in good condition. Conversely, if the interval is too long, unexpected failures could occur between maintenance operations, requiring reactive maintenance.
Predictive maintenance in OWFs utilizes data from sensors, monitoring systems, and historical operational data to predict potential equipment failures before they occur. This maintenance strategy involves analyzing trends in WT operations and failures for specific WTs, monitoring key parameters such as vibration, temperature, and oil conditions, and using predictive analytics algorithms to forecast when maintenance is needed. Consequently, since the nature of the problem is known beforehand, the proper spare parts and appropriate tools can be brought to the WT, resulting in minimal downtimes as the repair is scheduled before a complete malfunction. The disadvantages of predictive maintenance include the need for sensor technology and the potential for poor predictive modeling leading to false alarms and over-maintenance. Furthermore, it should be noted, that smart sensing demands online communication based on wireless technologies between the monitoring station and the WT, so the current conditions and operations of the WT can be received.