Next Article in Journal
Research on the Intake Port of a Uniflow Scavenging GDI Opposed-Piston Two-Stroke Engine
Next Article in Special Issue
Operational Data Analysis of a Battery Energy Storage System to Support Wind Energy Generation
Previous Article in Journal
Minimum-Cost Fast-Charging Infrastructure Planning for Electric Vehicles along the Austrian High-Level Road Network
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Resilience-Oriented Framework for Microgrid Planning in Distribution Systems

1
Department of Electrical Engineering, Dongshin University, Naju 58245, Korea
2
Department of Electrical Engineering, Kangwon National University, Samcheok 25913, Korea
3
Department of Electrical Energy Engineering, Keimyung University, Daegu 42601, Korea
*
Author to whom correspondence should be addressed.
Energies 2022, 15(6), 2145; https://doi.org/10.3390/en15062145
Submission received: 9 February 2022 / Revised: 7 March 2022 / Accepted: 10 March 2022 / Published: 15 March 2022

Abstract

:
Recently, it has been suggested that microgrids (MGs) can improve the resilience of distribution systems. However, predictions about future faults are uncertain. This makes calculating the exact value of the benefits of system resilience enhancement close to impossible at the time of MG planning. Therefore, this paper proposes a framework for MG planning, which focuses on resilience estimation. To consider the uncertainties of future failure events, the proposed method for estimating the resilience utilized the Monte Carlo simulation. In addition, an optimal scenario was estimated using a cost–benefit analysis and constraints on the expected value of resilience enhancement. In the case study, an actual MG installation at D-university was evaluated to obtain the optimal MG planning scenario. The results show that the capacity and installation locations of the distributed generators (DGs) impact the resilience enhancement. The proposed method can effectively derive the optimal MG planning scenario by evaluating the possibility of future operations based on the segmentation of both the system configuration and type of DG to improve the resilience of distribution systems.

1. Introduction

Power system resiliency is defined as the ability to prepare for, adapt to, and recover rapidly from disruptive events [1]; it considers high-impact low-frequency events such as natural disasters and deliberate attacks [2]. Even a single occurrence of an event such as a natural disaster can cause critical problems in the power system. However, it is impossible to reduce the intensity of a natural disaster [3]. For this reason, the resilience enhancement of power systems is being increasingly researched.
In previous studies on resilience assessment, frameworks for resilience assessment with various goals were proposed to respond to natural disasters [4], including a specific disaster (typhoon) [5]. Moreover, the importance of a resilience metric for power systems has been highlighted [6]. Especially, rapid recovery is considered the most important feature of a resilience metric [7]. In this regard, microgrids (MGs), which operate the distributed generators (DGs), have been projected as a potential solution for supporting the rapid recovery of the resilience of a distribution system [8].
Existing studies on MG planning based on economic feasibility have considered the problem of DG sizing [9,10]. However, MG planning considering the resilience must involve the assessment process of the resilience of a distribution system to disruptive events. Hence, not only long-term planning but also short-term planning and operations should be reflected in the framework for MG planning [11].
In previous studies on resilience-oriented operation with MG, the categorization of DGs and sectionalization of systems were established as methods for rapidly recovering from failures [12]. An optimization method based on the maximum allowable load loss was proposed for minimizing the investment costs [13].
In addition, a three-level model based on the multi-objective optimization problem was proposed in a previous study on resilience-oriented long-term planning with MG [14]. In the model, load profile uncertainty and some contingencies were considered, and the results proved a trade-off relationship between cost and resilience. In another study, multiple objective functions that maximize the critical load and minimize the capacity of dispatchable DGs were proposed for cost-effective MG planning [15]. A framework that incorporated resilience was developed for the economic assessment of MGs [16]. The cost–benefit analysis (CBA) in this framework comprised three steps and provided benefits of enhancement in the resilience and reliability through MG installation.
As mentioned in previous studies, to realize the success of long-term planning efforts, including MG installation, it is crucial to establish a framework that integrates various methods, such as that for system configuration, with the measurement criteria including that for the critical load. Nevertheless, owing to the uncertainty of events (type and intensity of disasters, number and location of failures, and time of failure occurrence and repair for each system), the uncertainty of various contingencies rather than the load profile uncertainty should be preferentially reviewed in the framework.
To address the problem of power distribution system reinforcement while avoiding the above issues, the resilience considering uncertainties was probabilistically evaluated using a Monte Carlo simulation (MCS) and the results were used as constraints for feasibility analysis [17]. To apply these prior studies to a real-world system, a more intuitive presentation of the effect of resilience enhancement is required for the system operator, and various types of components, such as DGs, should be applied in the system.
Thus, this study proposes a resilience-oriented framework for MG planning. The framework consists of a probabilistic resilience estimation method, expected value of resilience enhancement (EoRE) estimation method, and CBA method. In the process, the post-contingency uncertainties are considered, and the various output characteristics of the DGs are reflected. As a case study, the MG planning of D-university was conducted using the proposed framework. The proposed method provides both the EoRE and CBA results, enabling the system operators in charge of MG planning or the MG operators to make an informed and reasonable judgment of the amount of resilience enhancement that should be set as a priority.

2. Framework of Microgrid Planning

MG planning is generally conducted based on the economic evaluation using load analysis, power generation forecasting, and system configuration [9,10]. In the case of MG planning considering the reliability, formulaic indices such as system average interruption duration index (SAIDI) and loss of load expectation (LOLE) are used [18]. In addition, the economic value of the reliability is estimated in terms of the outage costs per year according to the type of customers using the customer damage function [19]. However, owing to the uncertainty of contingencies in the future, determining a single value that reflects the benefit of resilience enhancement in MG planning is difficult. Furthermore, frameworks for MG planning including the generalized resilience indices are under development in various viewpoints.
With the objective of reducing the investment required for resilience enhancement in a contingency, this paper proposes a framework for MG planning, which comprises three steps, as shown in Figure 1.
In step I, the various scenarios are established according to the purpose of the MG planner. In this step, the capacity as well as the type and location of the DG should be considered for each scenario, not only to maximize the economic benefits but also to improve the resilience of the system. The specific information of the established scenario is used to estimate the resilience enhancement in step II and cost-effectiveness in step III. In step II, the probabilistic evaluation of the resilience is conducted. In step III, the results of the probabilistic resilience are utilized to select the scenarios that satisfy the resilience constraints, and the optimal scenario is provided based on the commonly used CBA.

3. Estimation Method for Probabilistic Resilience

The probabilistic estimation of resilience, mentioned in step II of Figure 1, is illustrated in Figure 2 [17]. This method utilized MCS to derive the results of the probabilistic resilience, considering the post-contingency uncertainty in the development phase of MG planning. MCS is an inferential statistical technique that estimates an unknown value based on several simulations. It is used to derive a specific numerical value or probability distribution through the repeated random sampling of random variables. This study sets several random variables (e.g., location and occurrence time of failure and recovery time) for the event uncertainties to derive a probability distribution of the system’s resilience performance.
As depicted in Figure 2, the probabilistic estimation process of resilience comprises three sub-steps of step II. In particular, the resilience curve is estimated in step II-1, considering the fault and recovery information for post-contingency. Thereafter, the resilience index (RI) is calculated in step II-2 for resiliency evaluation, and the RI results are fitted to the empirical distribution function (EDF) in step II-3. The MCS is completed when the EDF(RI) satisfies the convergence range ( ϵ ). The MCS was applied to all the MG planning scenarios ( j T ).

3.1. Estimating the Resilience Curve (Step II-1)

In this study, the resilience curve was defined as the “time-varying performance of the system.” An example of the estimation method used to establish the resilience curve is shown in Figure 3.
Figure 3a specifically explains the concept of distribution system resilience. Figure 3b illustrates an example to relate the fault situation in a distribution system to the resilience concept. In Figure 3b, the locations of the DGs were set to nodes 3 and 8 in the preparation process of long-term planning, and the failure locations were assumed to be lines 4–9 and 3–4 in the withstand process. In the adapt process, the system was sectionalized via circuit breakers (CBs). DGs were contributed to supply power to each section. Figure 3c describes the resilience curve for Figure 3b. The diagram shows the system’s resilience performance at each of the following time points: the moment of equipment failure at the time of the event ( t 1 , t 3 ), the moment when the system is sectionalized via a CB ( t 2 , t 4 ), the moment when power is supplied using the DG in each section ( t 5 ), and the moment when the equipment is restored through repair or replacement ( t 6 , t 7 ).
To estimate the resilience curve in this manner, the sectionalization of the system in event situations and a method to derive the nodes where power can be supplied using a DG are needed. This study proposes the resilience curve estimation process shown in Figure 4.
In this study, the topology χ of a particular distribution system is defined as a set of nodes expressed in Equation (1):
N 1 , N 2 , , N n χ ,
where N n represents the nth node, and the pre-failure topology χ of a single power system is a set that comprises all the nodes as elements.
When the events occur in a particular distribution system, the sections are separated via CBs and can be expressed as a subset of the topology χ as follows:
χ S χ ,
where χ S represents the sth section of the topology separated by an event.
In Figure 4, the fault condition consists of the number, type, and location of the failed equipment and the failure and recovery time for each piece of equipment. Based on this condition, the nodes ( N n ) included in each section are organized according to time (t), as depicted in Figure 5a.
As depicted in Figure 5, the nodes ( N n ) in each section ( χ S t ) are physically connected but power outages may occur owing to the loss of power supply. This means that the available nodes (ANs) in each section χ S t along with the time-variant section χ S A N t comprising the ANs, shown in Figure 5b, must be determined.
Thus, the objective function was applied as expressed in Equation (3) with the constraints expressed in Equations (4)–(9). The proposed method evaluates the adequacy of the capability (available capacity) by using the peak load for each node and the capacity of each DG [20]. These equations are equally applied to each χ S t to select the optimal χ S A N t containing the ANs.
max N A N R N ξ
N A N L N P f e e d e r + D G P D G
D G P D G = C D G P C D G + N D G P N D G + E S S P E S S
P N D G = ω N D G · P N D G i f   E N D G E E S S 0 o t h e r w i s e
E N D G = N D G ω N D G · P N D G · T
ω N D G = a t N D G 24
P E S S = E E S S T         i f   E E S S T P P C S P P C S         o t h e r w i s e
Equation (3) represents the objective function used to determine the AN value that maximizes the sum of the resilience performance ( N A N R N ξ ) for χ S A N t . In this case, ξ represents the performance metrics, which can be applied specifically according to the measurement criteria that the system operator intends to evaluate, such as the peak load of the AN, number of customers, and number of critical customers of AN.
In Equation (4), N A N L N is the sum of the peak loads of the ANs and must be less than or equal to the sum of the capabilities ( P f e e d e r + D G P D G ) of the feeder and DG.
In Equation (4), if only the non-controllable DGs (NDGs) dependent on the natural environment are present in a specific section, e.g., photovoltaic (PV) and wind turbines (WT), they can cause an interruption in future operations. Equation (5) expresses the output characteristics of a DG divided into NDG and controllable DG (CDG), and the energy storage system (ESS) is included separately as it can charge as well as discharge power.
For Equation (6), the capability of each NDG ( P N D G ) is calculated using ω N D G · P N D G when the energy produced from NDG ( E N D G ) [kWh] can be controlled using E E S S [kWh] during the time between the occurrence of disaster and recovery (T). However, if this is not feasible, P N D G is calculated as “0,” assuming that curtailment occurs by manipulating the inverter for each NDG.
Equation (7) depicts the evaluation of E N D G used in Equation (6). As expressed, E N D G can be calculated by using the weighting factor ( ω N D G ) and time of occurrence of failure (T), where ω N D G is calculated using the average daily production time for NDG ( a t N D G ), as shown in Equation (8). In Equation (9), P E S S is used when the dischargeable capacity over time for ESS ( E E S S / T ) is less than the power conversion system capacity of ESS ( P P C S ). Otherwise, P P C S is used.
The sections satisfying Equations (3)–(9) are represented as χ S A N t . Equation (10) represents the time-varying performance of the distribution system [17].
R T ξ t = N n A N s R N ξ t
R T ξ t from Equation (10) represents the time-varying performance of the system, whereas R N ξ t represents the time-varying performance of each node.

3.2. Calculating the Resilience Index (Step II-2)

The resilience index ( R I ξ ) used in this study is expressed in Equation (11) [21].
R I ξ = T R T ξ t T R T 0 ξ t
In Equation (11), R T ξ t and R T 0 ξ t represent the resilience curve assuming that a failure occurred and did not occur, respectively.

3.3. Fitting EDF for RI (Step II-3)

As mentioned above, R I ξ comprises the various sets ( R I ξ , j ) expressed in Equation (12) according to the criteria for performance measurement and the scenarios of MG planning.
R I ξ , j = R I 1 , ξ , j , , R I i , ξ , j
The set of RI is fitted as an EDF. This study expresses the probability density function (PDF) as P D F R I ξ , j . The cumulative distribution function (CDF) is calculated as shown in Equation (13) [17,22].
C D F R I ξ , j = 0 R I ξ , j P D F R I ξ , j d R I ξ , j

4. Optimal MG Planning Considering Resilience Based on Cost–Benefit Analysis

To determine the optimal MG planning scenario, this section presents the CBA and resilience constraints. As this study considers the resilience of the distribution system during the MG planning process, the costs and benefits in the CBA are applied from the perspectives of the utility and MG operators.

4.1. Cost–Benefit Analysis

In this study, the method for determining the optimal MG planning scenario is de-scribed based on the benefit–cost (B–C) ratio among the various methodologies for CBA. Generally, there is an investment value of B–C ratios greater than or equal to 1, and there is a decreased investment value when the B–C ratio is less than 1.
In this study, the scenario achieves the maximum B–C ratio, which is expressed as Equation (14).
max B T j C T j
The elements of B and C in Equation (14) are expressed in Equations (15)–(16); these are estimated from parameters such as life cycle and power output forecasting for each DG [9,10].
B T j = B M G j + B U t i l i t y j + B e n v i r o m e n t j
C T j = C M G j + C U t i l i t y j
In Equation (15), the benefit (B) is categorized into the benefit from the perspective of the environment and those from the perspectives of the MG operators and utilities, and the calculations for each benefit category are expressed in Equations (17)–(19). On the contrary, the cost (C) presented in Equation (16) is divided into the costs for MG operators and utilities and is subdivided as shown in Equations (20) and (21).
B M G j = B E S j + B s e l l j
B U t i l i t y j = B A C j + B A E j
B e n v i r o m e n t j = E D G j · e · U C C O 2
C M G j = C c a p i t a l j + C O & M j + C D G . f u e l j
C U t i l i t y j = C R F j + C b u y j

4.2. Resilience Constraint

As the constraints of power balancing and DG capacity were considered during resilience calculation, this section focuses on the resilience constraints.
In this study, the effect of resilience enhancement through MG installation is calculated as in Equation (22) below:
E o R E ξ , j = E R I ξ , j E R I ξ , R e f . ,
where EoRE denotes the expected value of the resilience enhancement, and E R I ξ , j indicates the expected value of the RI for the respective MG installation scenarios. E R I ξ , R e f . denotes the comparison criteria for E R I ξ , j , which can be set considering the objectives, e.g., prior to MG implementation or increased DG capacity for MG. Using the CDF(RI) that was derived above, EoRE can be calculated as shown in Equation (23) below [23,24].
E o R E ξ , j = 0 1 C D F 1 R I C D F 2 R I d R I
In Equation (23), C D F 1 R I denotes ( C D F R I ξ , R e f . ), a function serving as the comparison criteria, and C D F 2 R I indicates the function of each scenario ( C D F R I ξ , j ).
An example of EoRE based on Equation (23) is presented in Figure 6 below.
Figure 6 shows that the proposed method allows the estimation of the difference from the expected value of the RI, thus providing intuitive results for the degree of resilience enhancement through MG installation.
The resilience constraint is set as in Equation (24).
E o R E ξ , j C R
In Equation (24), CR represents the constraint of resilience, which is the minimum allowable value of EoRE obtained through discussions between the utility and MG operators. Since the scenarios of the MG planning that satisfy the CR are provided, the proposed framework can avoid the calculation process of the benefit (B) for resilience enhancement in CBA.

5. Case Study

5.1. Simulation Condition

5.1.1. System Configuration

Figure 7 is the system configuration at D-university in Korea with the MGs in operation. The information regarding the peak load for each node in the system (Figure 7) is organized in Table A1 (Appendix A).

5.1.2. Scenarios of MG Planning (Step I)

The scenarios for MG planning, which consider the capacities of the DGs as well as their installation locations, are listed in Table 1. Table A1 (Appendix A) shows the DG capacity for each node in scenarios 10, 11, 15, and 16, assuming that the DGs in Table 1 are installed at different locations.
Table 2 shows the ratios calculated to minutely review the distribution of the DGs. Each ratio was calculated based on the following criteria:
ⓐ:
Ratio of DG capacity to peak load
ⓑ:
Ratio of controllable DGs (CHP) to peak load
ⓒ:
Ratio of controllable DGs (CHP) to total DGs
In Table 1 and Table 2, scenarios 1–3 assume the same DG capacity but different DG installation locations (nodes 2, 10, or 18). Scenarios 4–6 have the same total DG capacity as that in scenarios 1–3 but with different ratios of the DG composition. Scenarios 7–11 have the same total DG capacity as that installed in D-university. Scenario 10 represents the actual MG in D-university, and it is the calculation result of the DG capacity to maximize the economic feasibility without consideration of resilience. To ensure resilience enhancement, the total DG capacity in scenarios 12–16 is larger than that in scenarios 7–11, and a large ratio of the CDG to peak load is assumed.

5.1.3. Simulation Condition for Estimating the Probabilistic Resilience (Step II)

To consider the various post-contingency uncertainties, the simulation conditions were examined with the following limitations [25]:
Type of failed facility: line, transformer, etc.
Fault occurrence time of each failed facility
:
Random in 0–1 h
Recovery time
:
Random in 4–24 h for each failed facility

5.1.4. Simulation condition for CBA (Step III)

The unit price for each cost and benefit element is presented in Table A2 (Appendix A).

5.2. Simulation Result

5.2.1. Resilience Enhancement

Figure 8 shows the E-CDF result for each scenario of the three failed facilities. Table 3 shows the EoRE results for one to four failed facilities. The intermediate results (resilience curve) obtained for calculating the EoRE are presented in Figure A1 (Appendix A).
In Figure 8, the E-CDF results for the scenarios with the same total capacity are similar, except for scenarios 12–16. This means that when ⓐ (the ratio of the DG capacity to peak load) in scenarios 1–11, as listed in Table 2, is small, the variation in the enhancement of resilience according to the installation locations of the DGs is negligible.
Meanwhile, although ⓐ of scenarios 7–11 is larger than ⓐ of scenarios 1–6 in Table 2, the enhancements in the resilience in scenarios 7–11 and 1–6 are similar. This is because the ratio of CDGs (ⓑ, ⓒ) in scenarios 7–11 in Table 2 is low, indicating that controllable DGs such as CHP contribute to enhancing the resilience more than the other DG types.
In Table 3, the variation in the EoRE according to changes in the number of failed facilities was significant for scenarios 12–16, which had relatively large DG capacities. Nevertheless, Scenario 12 showed a lower EoRE than scenarios 13–16 because the DGs in scenario 12 were located next to the feeder at node 2, as shown in Figure 7. These results indicate that when a failure occurs in the line connecting nodes 2 and 10 in the distribution system of Figure 7, it is more advantageous for the DGs to be installed at nodes 10 and 18 (scenarios 13 and 14) than at node 2 (scenario 12).

5.2.2. Optimal scenario based on the CBA and resilience constraint

The following resilience constraint was set to review the optimal scenario. The condition for the number of failed facilities was limited to three.
  • Resilience constraint ( C R ): 0.05
Figure 9 shows the EoRE and B–C ratio for all scenarios, as well as the baseline C R . Table 4 presents the B–C ratios for scenarios that satisfy the resilience constraint.
Table 4 shows that scenario 8, where the capacity of the NDG was relatively large, was an optimal scenario. It shows that the NDG and ESS can contribute to improving the resilience in a distribution system when the ESS capacity is more than twice the PV capacity.
However, when the reference value of the resilience constraint is set to be greater than 0.1 in Figure 9, scenario 15 (B–C ratio: 0.86) can be derived as an optimal result. This shows that the resilience (EoRE) enhancement and cost (B–C ratio) are in a trade-off relationship.
The proposed framework for MG planning can provide a cost-effective scenario by selecting scenarios that satisfy the conditions for enhancing resilience. The estimation method of probabilistic resilience included in this process provides the EoRE that considers not only the DG capacity and type but also the installation location.

6. Conclusions

This study developed a framework for MG planning considering the resilience of a distribution system as described in Section 2. In Section 3, the estimation method of the resilience curve considering the system configuration and output characteristics of the DG was presented, and the method for calculating the RI and EDF was described. In this process, the post-contingency uncertainties were considered based on the MCS. In Section 4, the CBA model was presented for various cost and benefit elements, and the EoRE was proposed to intuitively express the degree of resilience enhancement.
To consider the realistic situation of the distribution system, a case study was conducted at the D-university with an installed MG. The results in the case study showed that the proposed method for estimating the resilience could consider not only the capacity of the DGs but also their type and installation location. In addition, the proposed framework provided an optimal scenario that satisfied the resilience constraints (CR) and maximized the B–C ratio.
When the proposed framework is verified through various real systems, it could contribute to establishing a more resilient system using MG in long-term planning. Especially, the framework could be usefully utilized to establish MG of the distribution system that is oriented toward resilience enhancement, such as customers of hospitals and military and industrial facilities, because the scenarios of the MG planning that satisfy the resilience constraint are provided.

Author Contributions

Conceptualization, D.-M.K.; methodology, E.-T.S. and D.-M.K.; software, E.-T.S. and I.-S.B.; validation, E.-T.S., I.-S.B., S.-Y.K. and D.-M.K.; formal analysis, E.-T.S.; investigation, E.-T.S. and I.-S.B.; resources, D.-M.K.; data curation, E.-T.S. and S.-Y.K.; writing—original draft preparation, E.-T.S.; writing—review and editing, S.-Y.K. and D.-M.K.; visualization, E.-T.S., I.-S.B. and S.-Y.K.; supervision, D.-M.K.; project administration, D.-M.K.; funding acquisition, D.-M.K. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the National Research Foundation of Korea (NRF) under Grant 2020R1F1A1070029.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

The following nomenclatures are used in this manuscript:
i Number of iterations in the Monte Carlo simulation
j Number of scenarios in MG planning
j T Total number of scenarios in MG planning
ϵ Convergence range of the MCS
R I Value of the resilience index
χ Topology of the distribution system
χ s sth section of the topology
t Time [h]
N n nth node in the distribution system
A N Available node
ξ Measurement criteria for resilience performance
R N Resilience performance of each node
R T Resilience performance of system
R T 0 Comparison value of R T
L N Peak load of each node [kW]
P f e e d e r Capability of feeder [kW]
P D G Capability of distributed generators (DG) [kW]
P C D G Capability of controllable DG (CDG) [kW]
P N D G Capability of non-controllable DG (NDG) [kW]
P E S S Capability of energy storage system (ESS) [kW]
ω N D G Weighting factor for capability of NDG
E N D G Energy produced from NDG [kWh]
E E S S Dischargeable energy of ESS [kWh]
P P C S Capability of power conversion system (PCS) [kW]
T Time period from fault occurrence to recovery [h]
a t N D G Average of daily production time for NDG [h]
RISet of R I
P D F R I Probability density function for R I
C D F R I Cumulative distribution function for R I
C T Total cost [$]
C M G Cost of MG [$]
C U t i l i t y Cost of utility [$]
C c a p i t a l Capital cost of MG [$]
C O & M O&M cost of MG [$]
C D G . f u e l Fuel cost for each DG in MG [$]
C R F Reinforcement cost for facilities in a utility [$]
C b u y Cost of buying the surplus energy from an MG [$]
B T Total benefit [$]
B M G Benefit to MG [$]
B U t i l i t y Benefit to utility [$]
B e n v i r o m e n t Benefit to environment [$]
B S E Benefit of energy saving in MG [$]
B s e l l Benefit of selling the surplus energy in MG [$]
B A C Benefit of avoiding the capacity of the utility [$]
B A E Benefit of avoiding the energy at the utility [$]
e Conversion coefficient for CO2 emission [tCO2/ kWh]
UC C O 2 Unit price per unit CO2 emission [tCO2]
E o R E Expected value of resilience enhancement
E R I j Expected value of RI for each scenario
E R I R e f . Comparison value of E R I j
CR Constraint value of resilience enhancement

Appendix A

Figure A1. Resilience curves for Scenarios 1, 6, 7, and 8.
Figure A1. Resilience curves for Scenarios 1, 6, 7, and 8.
Energies 15 02145 g0a1
Table A1. Peak load at D-university and DG capacity for Scenarios 10, 11, 15, and 16.
Table A1. Peak load at D-university and DG capacity for Scenarios 10, 11, 15, and 16.
NodePeak Load
[kW]
Scenario
10111516
2500PV 76PV 76
ESS 152
ESS 750
3400PV 62PV 62
ESS 124
PV 50PV 50
ESS 150
4600PV 243PV 182
ESS 364
PV 100PV 100
ESS 300
5750PV 96PV 61
ESS 122
6650PV 86PV 96
ESS 192
PV 100PV 100
ESS 300
7800PV 20PV 86
ESS 172
8600 PV 20
ESS 40
9900
10500PV 86
ESS 2000
PV 86
ESS 172
ESS 750
11300
12400 PV 50PV 50
ESS 150
13300
14450PV 58PV 58
ESS 116
15400PV 50PV 50
ESS 100
PV 50PV 50
ESS 150
16300 PV 50PV 50
ESS 150
17250PV 223
CHP 115
PV 223
ESS 446
CHP 115
PV 100
CHP 3000
PV 100
ESS 300
CHP 3000
18300
Total840031155000
Table A2. Unit price of cost and benefit elements [26].
Table A2. Unit price of cost and benefit elements [26].
CategoryElementsUnit Price
CCMGCcapitalPV173.8 $/kW
CHP1042.9 $/kW
ESS (∼300[kWh])608.4 $/kWh
ESS (300[kWh]∼)521.5 $/kWh
EMS (H/W, S/W)26,073.4 $
CO&MPV4.3 $/kW/year
CHP11.3 $/kW/year
ESS8.7 $/kW/year
EMS434.6 $/year
CDG,fuelCHP (1[kWh] = 3.6[MJ])0.0013 $/MJ
ESS0.1 $/kWh
CUtilityCRFCB2607.3 $/set
LS1738.2 $/set
Cbuy0.1 $/kWh
BBMGBES0.1 $/kWh
Bsell0.2 $/kWh
Benviroment (1[kWh] = 0.000459 [tCO2])19.6 $/tCO2
BUtilityBAC32.6 $/kW/year
BAE0.1 $/kWh

References

  1. White House, Presidential Policy Directive-21—Critical Infrastructure Security and Resilience. Available online: https://obamawhitehouse.archives.gov/ (accessed on 8 February 2022).
  2. North American Electric Reliability Corporation (NERC). High-Impact, Low-Frequency Event Risk to the North American Bulk Power System; 2010. Available online: https://www.energy.gov/ (accessed on 8 February 2022).
  3. Panteli, M.; Mancarella, P. Influence of extreme weather and climate change on the resilience of power systems: Impacts and possible mitigation strategies. Electr. Power Syst. Res. 2015, 127, 259–270. [Google Scholar] [CrossRef]
  4. Berkeley, A.R., III; Wallace, M. A Framework for Establishing Critical Infrastructure Resilience Goals; Final Report Recommendations; National Infrastructure Advisory Council: Gaithersburg, MD, USA, 2010; pp. 1–83. Available online: https://www.dhs.gov/ (accessed on 8 February 2022).
  5. Wang, Y.; Huang, T.; Li, X.; Tang, J.; Wu, Z.; Mo, Y.; Xue, L.; Zhou, Y.; Niu, T.; Sun, S. A resilience assessment framework for distribution systems under typhoon disasters. IEEE Access 2021, 9, 155224–155233. [Google Scholar] [CrossRef]
  6. Panteli, M.; Mancarella, P.; Trakas, D.N.; Kyriakides, E.; Hatziargyriou, N.D. Metrics and Quantification of Operational and Infrastructure Resilience in Power Systems. IEEE Trans. Power Syst. 2017, 32, 4732–4742. [Google Scholar] [CrossRef] [Green Version]
  7. Cimellaro, G.P.; Reinhorn, A.M.; Bruneau, M. Framework for analytical quantification of disaster resilience. Eng. Struct. 2010, 32, 3639–3649. [Google Scholar] [CrossRef]
  8. International Electrotechnical Commission (IEC). Microgrids for Disaster Preparedness and Recovery: With Electricity Continuity Plans and Systems. 2014; pp. 1–85. Available online: https://www.preventionweb.net/ (accessed on 8 February 2022).
  9. Nam, Y.-H.; Lee, H.-D.; Kim, Y.-R.; Marito, F.; Kim, M.-Y.; Rho, D.-S. Economic evaluation algorithm of island micro-grid for utility and independent power producer. Trans. Korean Inst. Electr. Eng. 2017, 66, 1032–1038. [Google Scholar] [CrossRef]
  10. IEEE Standards Board. 2030.9-2019—IEEE Recommended Practice for the Planning and Design of the Microgrid; IEEE: Piscataway, NJ, USA, 2019; pp. 1–45. [Google Scholar] [CrossRef]
  11. Mahzarnia, M.; Moghaddam, M.P.; Baboli, P.T.; Siano, P. A Review of the Measures to Enhance Power Systems Resilience. IEEE Syst. J. 2020, 14, 4059–4070. [Google Scholar] [CrossRef]
  12. Wang, Z.; Wang, J. Self-Healing Resilient Distribution Systems Based on Sectionalization into Microgrids. IEEE Trans. Power Syst. 2015, 30, 3139–3149. [Google Scholar] [CrossRef]
  13. Wu, X.; Wang, Z.; Ding, T.; Wang, X.; Li, Z.; Li, F. Microgrid planning considering the resilience against contingencies. IET Gener. Transm. Distrib. 2019, 13, 3534–3535. [Google Scholar] [CrossRef]
  14. Wang, Y.; Rousis, A.O.; Strbac, G. A Three-Level Planning Model for Optimal Sizing of Networked Microgrids Considering a Trade-Off Between Resilience and Cost. IEEE Trans. Power Syst. 2021, 36, 5657–5669. [Google Scholar] [CrossRef]
  15. Borghei, M.; Ghassemi, M. A Multi-Objective Optimization Scheme for Resilient, Cost-Effective Planning of Microgrids. IEEE Access 2020, 8, 206325–206341. [Google Scholar] [CrossRef]
  16. Weng, D. Microgrid techno-economic assessment. In Proceedings of the IRED Conference, Niagara Falls, NY, USA, 24 October 2016; Available online: https://www.osti.gov/biblio/1525094-microgrid-techno-economic-assessment-presentation (accessed on 8 February 2022).
  17. Son, E.-T.; Bae, I.-S.; Kim, S.-Y.; Kim, D.-M. Facility Reinforcement Planning of Distribution System Considering Resilience. IEEE Access 2021, 9, 94272–94280. [Google Scholar] [CrossRef]
  18. Che, L.; Zhang, X.; Shahidehpour, M.; AlAbdulwahab, A.; Abusorrah, A. Optimal Interconnection Planning of Community Microgrids with Renewable Energy Sources. IEEE Trans. Smart Grid 2017, 8, 1054–1063. [Google Scholar] [CrossRef]
  19. Billinton, R. Evaluation of reliability worth in an electric power system. Reliab. Eng. Syst. Saf. 1994, 46, 15–23. [Google Scholar] [CrossRef]
  20. Wu, X.; Shi, S.; Wang, Z. Microgrid planning considering the supply adequacy of critical loads under the uncertain formation of sub-microgrids. Sustainability 2019, 11, 4683. [Google Scholar] [CrossRef] [Green Version]
  21. Son, E.-T.; Bae, I.-S.; Kim, S.-Y.; Kim, W.-W.; Kim, D.-M. A Study on the Analysis of Resilience Enhancement for the Distribution System using Microgrids. Trans. Korean Inst. Electr. Eng. P 2021, 70, 843–851. [Google Scholar] [CrossRef]
  22. Shorack, G.R.; Wellner, J.A. Empirical Processes with Applications to Statistics New York; Wiley: New York, NY, USA, 1986; ISBN 0-471-86725-X. [Google Scholar]
  23. Mood, A.M.; Graybill, F.A.; Boes, D.C. Introduction to the Theory of Statistics, 3rd ed.; McGraw Hill Book Company: New York, NY, USA, 1973; pp. 175–218. ISBN 100070854653. [Google Scholar]
  24. Holland, P.W. Two measures of change in the gaps between the CDFs of test-score distribution. J. Educ. Behav. Stat. 2002, 27, 3–17. [Google Scholar] [CrossRef]
  25. Allan, R.; Billinton, R.; Sjarief, I.; Goel, L.; So, K. A reliability test system for educational purposes-basic distribution system data and results. IEEE Trans. Power Syst. 1991, 6, 813–820. [Google Scholar] [CrossRef]
  26. PG&E. Unit Cost Guide. Available online: https://www.pge.com/pge_global/common/pdfs/for-our-business-partners/interconnection-renewables/Unit-Cost-Guide.pdf (accessed on 8 February 2022).
Figure 1. MG planning framework.
Figure 1. MG planning framework.
Energies 15 02145 g001
Figure 2. Probabilistic estimation process of resilience based on MCS.
Figure 2. Probabilistic estimation process of resilience based on MCS.
Energies 15 02145 g002
Figure 3. Example of resilience curve estimation.
Figure 3. Example of resilience curve estimation.
Energies 15 02145 g003
Figure 4. Estimation process of the resilience curve.
Figure 4. Estimation process of the resilience curve.
Energies 15 02145 g004
Figure 5. Venn diagrams of nodes of time-varying topologies and sections.
Figure 5. Venn diagrams of nodes of time-varying topologies and sections.
Energies 15 02145 g005
Figure 6. Example of EoRE.
Figure 6. Example of EoRE.
Energies 15 02145 g006
Figure 7. System configuration at D-university.
Figure 7. System configuration at D-university.
Energies 15 02145 g007
Figure 8. Results of E-CDF for various scenarios in failure of three facilities.
Figure 8. Results of E-CDF for various scenarios in failure of three facilities.
Energies 15 02145 g008
Figure 9. Results of EoRE and B–C ratio for each scenario in the failure of three facilities.
Figure 9. Results of EoRE and B–C ratio for each scenario in the failure of three facilities.
Energies 15 02145 g009
Table 1. Simulation condition of each Scenario for MG planning.
Table 1. Simulation condition of each Scenario for MG planning.
ScenarioDG CapacityDG Location
PV
[kW]
ESS
[kWh]
CHP
[kW]
Total
13004008001500Node 2
2Node 10
3Node 18
4800300400Node 2
5Node 10
6Node 18
7100020001153115Node 2
8Node 10
9Node 18
10Ref. to Table A1
11
12500150030005000Node 2
13Node 10
14Node 18
15Ref. to Table A1
16
Table 2. Ratio considering the DG types.
Table 2. Ratio considering the DG types.
Scenarioⓐ [%]ⓑ [%]ⓒ [%]
1–318953
4–6527
7–113714
12–16603660
Table 3. Results of EoRE.
Table 3. Results of EoRE.
ScenarioNumber of Failed Facilities
1234
10.0090.0140.0170.020
20.0180.0260.0340.042
30.0240.0330.0400.045
40.0050.0060.0080.009
50.0090.0120.0160.019
60.0140.0190.0230.026
70.0190.0240.0280.032
80.0370.0460.0540.058
90.0420.0490.0490.050
100.0330.0410.0510.057
110.0370.0460.0510.052
120.0280.0480.0590.073
130.0480.0770.1010.124
140.0530.0800.0940.105
150.0510.0820.1030.122
160.0540.0830.1040.121
Table 4. CBA result that satisfied CR.
Table 4. CBA result that satisfied CR.
ScenarioEoRETotal Cost [$]Total Benefit [$]B–C Ratio
80.0542,289,1913,849,5121.68
100.051
110.0512,467,6913,849,5121.56
120.05910,704,4788,754,9330.82
130.101
140.094
150.103
160.10410,929,4788,754,9330.80
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Son, E.-T.; Bae, I.-S.; Kim, S.-Y.; Kim, D.-M. Resilience-Oriented Framework for Microgrid Planning in Distribution Systems. Energies 2022, 15, 2145. https://doi.org/10.3390/en15062145

AMA Style

Son E-T, Bae I-S, Kim S-Y, Kim D-M. Resilience-Oriented Framework for Microgrid Planning in Distribution Systems. Energies. 2022; 15(6):2145. https://doi.org/10.3390/en15062145

Chicago/Turabian Style

Son, Eun-Tae, In-Su Bae, Sung-Yul Kim, and Dong-Min Kim. 2022. "Resilience-Oriented Framework for Microgrid Planning in Distribution Systems" Energies 15, no. 6: 2145. https://doi.org/10.3390/en15062145

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop