Next Article in Journal
Harmonic Source Location and Characterization Based on Permissible Current Limits by Using Deep Learning and Image Processing
Previous Article in Journal
Prediction of Solid Conversion Process in Direct Reduction Iron Oxide Using Machine Learning
Previous Article in Special Issue
A Data-Driven Framework for FDI Attack Detection and Mitigation in DC Microgrids
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Toward Models of Impact and Recovery of the US Western Grid from Earthquake Events

by
Riley Weinmann
,
Eduardo Cotilla-Sanchez
and
Ted K. A. Brekken
*
School of Electrical Engineering & Computer Science, Oregon State University, Corvallis, OR 97331, USA
*
Author to whom correspondence should be addressed.
Energies 2022, 15(24), 9275; https://doi.org/10.3390/en15249275
Submission received: 4 November 2022 / Revised: 28 November 2022 / Accepted: 29 November 2022 / Published: 7 December 2022
(This article belongs to the Special Issue Resilience, Modeling, and Control of Electrical Power Systems)

Abstract

:
A Cascadia Subduction Zone (CSZ) earthquake will cause widespread damage to numerous lifelines and infrastructure along the northern US west coast. The goal of the presented research is to provide a bottom up estimate of the impact on and subsequent recovery of a Cascadia Subduction Zone earthquake on the US western grid to supplement and enhance the expert opinion estimates provided to date. The scope is limited to only consideration of shaking damage to utility substation equipment components of a power system model. The analysis utilizes probabilistic models of damage and recovery for substation power system assets, along with graph techniques for modeling connectivity, and Monte Carlo quasi steady state power flow solutions. The results show that a conservative estimate of the initial damage and loss of load is approximately 4000 MW, with a recovery estimate of 230 days.

1. Introduction

The Cascadia Subduction Zone (CSZ)—shown in Figure 1—is an approximately 1000 km long offshore fault, stretching from Cape Mendocino in northern California through the states of Oregon and Washington to the Brooks Peninsula in southern British Columbia [1,2,3,4]. The fault is part of a ring of of subduction zones that surrounds the Pacific Ocean, creating a formation called the “Ring of Fire”. The fault bears many similarities to its geological mirror, the large subduction fault east of Japan that released the +9M Tohoku earthquake and tsunami in 2011, which killed nearly 20,000 people, cost up to $220 billions of USD in damage [5], and left approximately 4 million homes without power in the immediate aftermath [6].
It is estimated–based on geological observations–the last CSZ earthquake and tsunami occurred around 1700 AD [1]. Considering the geological record further back to 8000 BC, the mean time between CSZ earthquakes is around 300 years, but with a fair degree of variability, in which some earthquake events may be separated by 100 years, and some by more than 500 years. The calculated odds that the next earthquake will occur in the next 50 years range from 7% to 15% for a “great” earthquake affecting the entire PNW to about 37% for a “very large” earthquake affecting southern Oregon and northern California [1].
What is certain is that a CSZ earthquake and accompanying tsunami will damage or destroy many lifeline systems along the coast: transportation, communication, water, sewer, etc, and the electrical system. A CSZ magnitude 9 earthquake would induce several minutes of shaking along nearly the entire northern and central west coast, with surface Peak Ground Accelerations (PGA) reaching 1 g and higher–much higher in some localized cases. The severe shaking will induce highly damaging stresses in electrical bushings and connections (i.e., circuit breakers, switches, and transformers), equipment support structures, and substation bus-work, and can damage auxiliary generation systems. The shaking will also induce liquefaction and landslides that threaten transmission towers and distribution poles.
In 2011, the Oregon legislature passed House Resolution 3 to understand the full extent of the impact that this hazard can pose to the state and devise a plan to make the state more resilient. This effort resulted in the Oregon Resilience Plan (ORP) [1]. The ORP estimates that electrical services could be out for up to 6 months on the coast after a CSZ earthquake. This estimate is provided by expert opinion.
This paper aims to provide a more comprehensive estimate of the electrical impacts of a CSA earthquake, and subsequent recovery, using a detailed Monte Carlo damage study of the entire US western grid. The goal is to provide a bottom up estimate of the impact on and subsequent recovery of a Cascadia Subduction Zone earthquake on the US western grid to supplement and enhance the expert opinion estimates provided to date.

2. Background

There are extensive resources on modeling earthquake and other natural disaster impacts to structures and systems, including electrical infrastructure [7,8,9,10,11,12,13,14,15]. IEEE Standard 693 focuses purely on requirements and certification of seismic hazard compliant substation equipment [16]. Additionally, there are numerous reconnaissance reports on earthquake impacts to electricity systems, particularly through databases such as the Multidisciplinary Center for Earthquake Engineering Research (MCEER) at the University of Buffalo [6,17,18,19,20,21,22,23]. Much of this work focuses on the impact to an individual component of a substation or aggregates expected component damage to estimate damage to a substation. However, research that connects electrical system structural modeling to power system model connectivity and power flow solutions is limited.
The methodology used in this paper is similar to that used in [24] where the power system bus-branch model resolution is improved with the addition of electrical bays. This paper uses multiple substation archetypes, adding redundancy at each bus. Additionally this paper uses fragility functions and restoration functions created for specific substation components e.g., circuit breakers. This further improves the model and allows for failure and restoration evaluation with improved resolution. Both methods improve on the BB model by analyzing the connectivity of the substations represented by each bus.

3. Western US Grid Model

The ACTIVSg10k test case is a synthetic bus-branch model of the US western grid interconnect [25]. A diagram of the model is shown in Figure 2. The model is an open source synthetic model and is used to enable open dissemination of research methodologies and results.
The ACTIVSg10k case has 10,000 buses, 12,706 branches and 2485 generators. Generation data comes from the U.S. Energy Information Administration. The 10,000 buses are mapped to 4762 geographic locations in the Western United States, and the load for each bus is estimated from US government census data. A summary of the system is provided in Table 1.
The impact of a CSZ earthquake will be focused on a sub-region of the model in the the Pacific Northwest region of the United States, defined as the region from the coast to the 121st meridian between the 49th and 39th parallels, which is approximately the rectangle bounded by the US-Canada border in the north, Bend OR in the west, and Mendocino County CA in the south. This area will be referred to as the Damage Zone. In the ACTIVSg10k model the Damage Zone region includes 728 geographic locations for a total of 1459 buses, which is approximately 15% of the baseline model.

4. Fragility, Restoration, and Metrics

To properly use the ACTIVSg10k model for this study, each of the thousands of assets in the model requires an associated fragility and restoration function to provide the likelihood of damage and subsequent recovery. This section details the functions and data sources used to model seismic fragility and subsequent restoration, as well as the metrics used to quantify the system damage and recovery.

4.1. Fragility Functions

Fragility functions represent the probability that a component will be in failed or damaged state after experiencing a certain level of exogenous excitation, which is usually expressed as Peak Ground Acceleration (PGA). In this research, we use power system component fragility functions from Hazus [12], which are classified for transformers, circuit breakers, and disconnect switches for three voltage levels: 34.5 kV to 150 kV (low voltage); 150 kV to 350 kV (medium voltage), 350 kV to 765 kV (high voltage). The low voltage level is extended down to 13.2kV, the lowest voltage in the ACTIVSg10k model. An example fragility function is shown in Figure 3.
Transmission and distribution towers and poles were not included in the analysis, as historically those components generally perform well with regards to shaking stress and damage. (The greater threat to towers and poles is not shaking, but landslides and liquefaction [17,22], which are not modeled here. Please see Section 5.5 for further discussion).
To assess the damage status of a component, first the PGA experienced by component at that location is determined from a PGA map for a specific seismic event. The PGA maps are traditionally determined by civil and geotechnical engineers by modeling the amount of energetic release from an earthquake fault and subsequent propagation of the energy through the bedrock and overlying soil.
The M9.0 Cascadia Subduction Zone scenario shakemaps produced by Wirth et al. [27] were utilized for estimates of peak ground acceleration for each bus and substation for the regional analysis. Rather than consider only one rupture scenario, these estimates of ground motions were derived from a logic tree approach considering multiple earthquake rupture scenarios, which were produced by Frankel et al. [28], in order to account for uncertainty. Wirth et al. applied adjustments for site response based on the soil and geologic conditions based on mapped Vs30 estimates produced by Heath et al. [29]. Amongst a variety of products produced, the US Geological Survey provides rasters of both the log of the mean PGA and the uncertainty (log of standard deviation) spatially mapped across the western US. Distant locations outside of the raster boundaries that are still part of the electric grid network were assumed to experience no significant shaking given that the PGA values converge to 0 g at the edges of the raster.
As an example for visualization, the PGA map for the M9.0 Cascadia Subduction Zone scenario is shown in Figure 4.

4.2. Restoration Functions

As part of this study, we conducted a survey of electric utility industry experts in the United States Pacific Northwest region to determine approximate restoration time tables for each component at various voltage levels. Survey respondents provided a time frame for restoration or replacement of severely damaged or destroyed components. Using these survey responses and a log-normal fit, we generate curves describing the probability that an asset would be recovered on a given day post-earthquake. Respondents were asked to assume that necessary personnel were available and each site was accessible, therefore considerations of road or workforce inaccessibility, damage to access roads, and damage to other lifelines (e.g., communications systems) is not factored into the analysis. Therefore the restoration results from the current version of the proposed model based on these survey results should be considered as a best-case scenario. It is very likely that cross-lifeline failures and other unmodeled factors will cause additional delays to repairs beyond the estimates used in this analysis. Because these additional delays and interactions are very difficult or impossible to estimate at this point in time, the analysis will proceed without them. Future planned work will increase the resolution of the model by considering not only delays and infrastructure interactions but also the lifecycle of the components.
An example restoration function is shown in Figure 5. Restoration functions are used to probabilistically establish the recovery day after the earthquake event for each failed component. After determining that an asset is in a damaged or failed state via the asset fragility function, a random number is drawn from a uniform distribution and is associated with the cumulative probability on the y-axis, which then indicates the number of days until restoration via the corresponding value on the x-axis. As an example using Figure 5, a uniform random number sample of 0.60 would indicate a given high-voltage transformer will be recovered on approximately day 430 after the earthquake. The recovery times of all damaged assets are determined at the start of the iteration.

4.3. Resilience Metrics

A core set of resilience quantifiers [30,31] can be derived from the function of the system performance vs. time, as shown in Figure 6.
The variable P represents some measure of system performance. In the case of a power system, a typical choice would be amount of power successfully delivered to system load over time.
A damaging event occurs at time t d b and causes damage to the system until time t d e . There is then a period of assessment in which resources are collected and restoration actions and strategies are planned. Restoration then takes place over the time t r b to t r e , at which point the system enters a new steady state, likely with a different level of performance than before.
From this performance trajectory, several resilience metrics can be derived.
Φ = P d P 0 t d e t d b ( rate   of   performance   decrease )
Λ = P 0 P d ( amplitude   of   performance   decrease )
E = t r b t d e ( time   in   damage   state )
Π = P e P d t r e t r b ( rate   of   performance   increase )
R = 0 t f P ( t ) d t P 0 · t f ( resilience )

5. Analysis Method

Damage and recovery from a CSZ earthquake was modeled using a Quasi Steady-State (QSS) Monte Carlo methodology. Figure 7 shows a flow diagram of the simulation architecture.
Prior to beginning the simulation, the bus-branch model resolution is improved by an extended bus-branch (xBB) model that models each bus as a graph of connected components. See Section 5.1 for details. For each iteration of the simulation, first damage is inflicted on the components of the xBB model using component fragility functions. Then, the damage to the xBB model is translated to the bus-branch model for power flow analysis. Immediately following damage phase the system begins recovery. For each damaged component in the xBB model a restoration function determines the day that component will be recovered. The simulation then steps through each day of restoration. After each simulated day of restoration, the total connected load and status of system assets are logged. Additionally, the largest island is extracted from the BB model and a power flow solution is calculated and logged, if convergent.

5.1. Extended Bus Branch Model

To improve on the resolution of the BB model we create an extended bus-branch (xBB) model by associating each bus in the ACTIVSg10k test case with a graph. Graph connectivity is determined according to the four substation archetypes described in [32] and the number of feeders connected to each bus. The xBB model, which includes a graph for each bus, provides substation component level resolution allowing for partial functionality of buses, which would not be possible in a traditional BB model.
For the purpose of creating the substation graph, we count feeders as any BB asset connected to the bus. Buses with two feeders are considered Single Bus Single Breaker (SBSB), buses with three or four feeders are modeled as a Ring Bus (RB), buses with five or more feeders are modeled as Breaker and a Half (BAH). Any bus connected to a generator is modeled as Double Bus Double Breaker (DBDB). For example, a bus that in the BB model has two generators, one load, and two branches would have five feeders and be modeled as a DBDB configuration due to the presence of generation at the bus.
In a given graph, nodes represent bus-branch (BB) level assets (e.g., generator, load, branch) and edges represent the series connected components connecting each asset according the substation archetype. Connections between BB assets are assumed to be the series connection of a two switched disconnects (SD) and a circuit breaker (CB). This SD-CB-SD grouping is considered a switch group (SG) which is modeled by an edge in the xBB substation graph. Figure 8 shows an example of a substation graph with 5 nodes and 6 edges. This graph models a DBDB configured substation with 3 feeders, connected by 12 SDs and 6 CBs.

5.2. Damage Implementation

Damage is implemented in two stages. First, components of the xBB model are damaged using PGAs sampled from a log-normal distribution of a M9.0 CSZ earthquake PGAs and asset failure functions as discussed in Section 4.1. Component failure results in the removal of corresponding edge in the substation graph. Second, the connectivity of each substation graph is evaluated and nodes with a degree of zero have the corresponding BB asset removed from service.

5.3. Damage Recovery

Recovery begins immediately after the CSZ event and continues for 1000 days. Components that were not damaged during the damage state are considered to be recovered on day zero. At each time step components with a day of restoration occurring on that day are recovered. Once all of the components in a switch-group (SG) have been recovered (on that day or previously) the corresponding edge is returned to the substation graph. At the end of each day the connectivity of each substation graph is evaluated. If the degree of a node is no longer zero, the asset corresponding to that node is returned to service. A substation is said to be functionally connected once the degree of all nodes is greater than zero. This indicates that a viable connection exists between all assets in the BB model. For a substation to return to full service, all damaged components must be recovered.

5.4. Power Flow Analysis

At the end of each recovery day the number of assets out of service and the total load connected to the system is logged. In addition, an attempt is made to find a power flow solution using MATPOWER [33]. To improve the probability of finding a converging solution, the power flow is calculated for the largest island in the system. This island is assumed to be the interconnected portion of the WECC system still intact following a CSZ earthquake. As recovery progresses eventually only one island will remain containing all 10,000 buses. If a solution converges, the load served is calculated by summing power demanded at each bus and generation available calculated as the sum of the maximum generation at each bus.

5.5. Assumptions and Limitations

Modeling and predicting the damage and subsequent restoration of electrical system components in a large earthquake is exceedingly complicated, and dependent on many correlated factors. To enable a first-order approximate analysis, several simplifications were made.
  • The analysis only considers shaking damage to electrical substation components of the power system model, as is typical with tools such as Hazus [12]. Determining failure functions to landslides and liquefaction is highly site specific and difficult to model. Nonetheless the research team has developed tools for modeling landslide damage to transmission and distribution poles and towers, and will include those methods in future analyses.
  • Damage to the load is not modeled, only its connection to the grid through substation equipment. The load is not monolothic, but a complex aggregation of infrastructure. Modeling its fragility at a high resolution would be beyond the computational scope of the study. Other studies in the area have also neglected load damage modeling, on the historical observation that the distribution system is often quickly repaired, and is not the dominant factor in delaying recovery of the system [34]. Additional details on distribution system damage can be found in Park et al. 2006 [18].
  • Transmission and distribution towers and poles were not included in the analysis, as historically those components generally perform well with regards to shaking stress and damage. The greater threat to towers and poles is liquefaction and landslides, which are not modeled here. Additional discussion can be found in Eidinger and Kempner 2012 [35], Eidinger et al. 2016 [36], and Eidinger 2018 [37].
  • Restoration times did not explicitly include damage to roads and transportation lifelines in the same area, or the impacts of damage to communication and fuel systems—i.e., no interdependent lifeline failures were modeled—and restoration times assumed qualified technicians and engineers were available immediately after the earthquake. (i.e., there was no delay to the beginning of the restoration process and therefore the assessment time of Figure 6 is 0 days). Both Burhenn et al. 1992 [34] and Eidinger et al. 2016 [36] provide historical examples in which the mobilization of resources and their access to damaged areas were strong shortly after large earthquakes.
  • Equipment lead times (and therefore the restoration timelines) are determined from industry expert survey results which are based on typical non-emergency lead-times. In the case of an earthquake, lead-times may be impacted by the large simultaneous demand for many types of the same equipment, as well as emergency supplies provided from utilities across the country.
  • Federal emergency response, which may accelerate repair and restoration, was not modeled.
All considered, it is therefore very likely that the results presented in this paper represent an optimistic scenario. The authors consider that the expected extent of damage, and the restoration time, would likely exceed the median scenarios presented here, and thus the authors recommend consideration of the 95th percentile results as a conservative estimate of the likely damage and recovery.

6. Results

6.1. Earthquake Impact and Recovery Overview

Significant shaking is confined to the region extending east from the coast to the 121st meridian between the 49th and 39th parallels, which is approximately the rectangle bounded by the US-Canada border in the north, Bend OR in the west, and Mendocino County CA in the south. Outside of this region shaking is expected to be slight to none–and therefore no significant damage–beyond this region. This affected sub-area of the model will be referred to as the Damage Zone, and some of the results in this section will be presented with respect to this sub-area of the WECC. Note that, because the ACTIVSg10k model is a synthetic model, the bus locations shown do not necessarily correspond to actual physical substations. Instead, the results shown should be interpreted as indicative of trends over a wide geographical area of similar expected extent as the actual WECC grid.
The initial earthquake impact in terms of load and generation lost, and subsequent recovery, is shown in Figure 9 and Figure 10.
It can be seen that the most significant rate of recovery occurs between 1 and 3 months, with a large majority of recovery by 6 months, and nearly complete recovery within a year.
The recovery can be further visualized in Figure 11, which shows the median and 95th percentile full restoration time of substations in the ACTIVSg10k model.
Generally, it can be observed that substations located closer to the coast will have longer recovery times compared to those located further inland. It is shown that the median time to recover full substation functionality (i.e., service) is approximately 100 to 200 days, and the 95th percentile time to recover full functionality is approximately 6 months. It is noted that time to reach a lower function of service, in which the minimum breakers and switches required for any level of substation function are replaced or repaired, will be less.
More detailed metrics are calculated in the next section.

6.2. Analysis Metrics

In this section we deploy the metrics defined in Section 4.3. The performance metric P ( t ) , as shown in Figure 6, is defined as load connected in the Damage Zone sub-area of the system, normalized to the undamaged load in the same zone. The performance metric result, including the median and 5th and 95th percentile results, is shown in Figure 12.
From the curve, we calculate the metrics defined in Section 4.3. Because the load recovers asymptotically, we have selected a recovery to 99% of the pre-earthquake load as the criteria for which the system is recovered: P e = 0.99 · P 0 . For calculating and comparing the resilience metric R, the final time t f is set to the recovery end time of the 95th percentile.
In addition to the metrics of Table 2, we utilize the results shown in Figure 12 to calculate the total load not served, shown in Table 3.

6.3. Simulation Convergence

The Quasi Steady-State Monte Carlo (QSSMC) simulation was run for 2500 iterations. In total the simulation run time on a standard PC workstation was approximately 38 h. Each iteration simulates a CSZ event (day 0), and the following 1000 days of restoration. The simulation generates a probability distribution of load served for each day. Figure 13 shows the median and 5th and 95th percentile load served on day 0 cumulatively up to iteration 2500, as well as the variance in the distribution. The figure shows the probabilistic results stabilize from 100 iterations on, which justifies our choice of 2500 iterations as sufficient for having strong confidence in the Monte Carlo results.

6.4. Power Flow Results

The power flow results are more difficult to obtain as the heavily damaged system shortly after the earthquake is often non-convergent. Therefore the analysis proceeds as above, with gradual recovery of the system until it reaches a state with a stable solution.
The plots below, Figure 14 and Figure 15, show the median size of the largest island, as reported by MATPOWER, as well as the median convergent power flow load served at the soonest day a convergent result is available.
The results show that initially a convergent power flow solution is not attainable. When a convergent solution is available, it generally verifies the delivery of load equal to the load connected to the main island as shown in Figure 12.
This illustrates the limitations in using a regular power flow solver to assess system status, as even light damage to a large complex power flow case can cause non-convergence. Thus, additional tools and metrics are required to quantify system status.

6.5. Summary and Analysis

This paper presents a methodology for estimating the impact and subsequent recovery of the US western grid to a Cascadia Subduction Zone earthquake. The methodology uses Monte Carlo analysis to account for the probability of shaking, damage, and recovery of each component of the system from the bottom up. The methodology also utilizes a novel graph-based sub-methodology to determine the functionality of substations.
The results show that overall damage to the affected sub-area of the western grid (i.e., the Damage Zone) is estimated to cause a 95th percentile approximate loss of 4000 MW immediately after the earthquake, with a subsequent recovery of approximately 230 days. The 95th percentile estimate of energy lost is 7,680,000 MWh. Further study could link these loss and recovery estimates to economic impact [38], but a full treatment of that is considered out of this study scope. However, it is noted that the possibly similarly sized Tohoku 2011 event had an estimated economic impact of $220 billion USD [5]. The area of damage is largely limited to the sub-region of the model from the coast to the 121st meridian between the 49th and 39th parallels, which is approximately the rectangle bounded by the US-Canada border in the north, Bend OR in the west, and Mendocino County CA in the south.
In terms of power flow, the system is initially split into approximately 30 islands–one large island and many small islands–and is gradually recovered to one system again in approximately 1 year. The largest island is often not convergent until nearly 3 months or more of recovery, thus illustrating a high degree of sensitivity in solving power flows on large, complex power system models in a heavily damaged state. This illustrates the need for islanded power flow system metrics and quantifiable measures beyond power flows for heavily damaged systems.
It is important to note the various assumptions made in this study, as discussed in Section 5.5.
The authors wish to thank the following for their support and advisement in this research: Mike Olsen, Armin Stuedlein, and Eve Lathrop of Oregon State University; Jay Landstrom of Portland General Electric; Shamus Gamache of Central Lincoln PUD; Leon Kempner and David Glennon of the Bonneville Power Administration; and Vishvas Chalishazar of Pacific Northwest National Laboratories.

Author Contributions

Conceptualization, R.W., E.C.-S. and T.K.A.B.; methodology, R.W., E.C.-S. and T.K.A.B.; analysis, R.W.; writing—original draft preparation, R.W., E.C.-S., T.K.A.B.; writing—review and editing, R.W., E.C.-S. and T.K.A.B.; supervision, E.C.-S. and T.K.A.B.; project administration, E.C.-S. and T.K.A.B.; funding acquisition, E.C.-S. and T.K.A.B. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Science Foundation, award number 1933217.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
CSZCascadia Subduction Zone
PGAPeak Ground Acceleration
BBBus Branch power system model
xBBextended Bus Branch power system model
SBSBsingle bus single breaker
RBring bus
BAHbreaker and a half
DBDBdouble bus double breaker
CBcircuit breaker
SDswitch disconnect
SGswitch group

References

  1. The Oregon Resilience Plan. Technical Report; 2013. Available online: https://www.oregon.gov/oem/documents/oregon_resilience_plan_final.pdf (accessed on 28 November 2022).
  2. Exercise Scenario Document: Cascadia Subduction Zone Catastrophic Earthquake and Tsunami. Technical Report; 2015. Available online: https://www.oregon.gov/oem/Documents/Cascadia_Rising_Exercise_Scenario.pdf (accessed on 28 November 2022).
  3. Cascadia Subduction Zone Earthquakes: A Magnitude 9.0 Earthquake Scenario. Technical report; 2013. Available online: https://www.dnr.wa.gov/publications/ger_ic116_csz_scenario_update.pdf (accessed on 28 November 2022).
  4. Goldfinger, C.; Morey, A.E.; Johnson, J.E.; Patton, J.R.; Karabanov, E.B.; Gutierrez-Pastor, J.; Eriksson, A.T.; Gracia, E.; Dunhill, G.; Enkin, R.J.; et al. Turbidite Event History–Methods and Implications for Holocene Paleoseismicity of the Cascadia Subduction Zone; Technical report; U.S. Geological Survey: Reston, VA, USA, 2012. [CrossRef]
  5. UNESCO/IOC. Summary Statement from the Japan–UNESCO–UNU Symposium on the Great East Japan Tsunami on 11 March 2011 and Tsunami Warning Systems. Technical report. 2012. Available online: https://unesdoc.unesco.org/ark:/48223/pf0000216072 (accessed on 28 November 2022).
  6. Kazama, M.; Noda, T. Damage statistics (Summary of the 2011 off the Pacific Coast of Tohoku Earthquake damage). Soils Found. 2012, 52, 780–792. [Google Scholar] [CrossRef] [Green Version]
  7. Pires, J.; Ang, A.; Villaverde, R. Seismic reliability of electrical power transmission systems. Nucl. Eng. Des. 1996, 160, 427–439. [Google Scholar] [CrossRef]
  8. Zareei, S.A.; Hosseini, M.; Ghafory-Ashtiany, M. Evaluation of power substation equipment seismic vulnerability by multivariate fragility analysis: A case study on a 420 kV circuit breaker. Soil Dyn. Earthq. Eng. 2017, 92, 79–94. [Google Scholar] [CrossRef]
  9. Oikonomou, K.; Constantinou, M.; Reinhorn, A.; Kempner, L. Seismic Isolation of High-Voltage Electrical Power Transformers; Technical Report MCEER-16-0006, MCEER: Buffalo, NY, USA, 2016. [Google Scholar]
  10. Huo, J.; Hwang, H. Seismic Fragility Analysis of Equipment and Structures in a Memphis Electric Substation; Technical Report NCEER-95-0014, National Center for Earthquake Engineering Research (NCEER): Buffalo, NY, USA, 1995. [Google Scholar]
  11. Ersoy, S.; Feizi, B.; Ashrafi, A.; Saadeghvaziri, M.A. Seismic Evaluation and Rehabilitation of Critical Components of Electrical Power Systems; Technical Report MCEER-08-0011, MCEER: Buffalo, NY, USA, 2008. [Google Scholar]
  12. Hazus 5.1: Hazus Earthquake Model Technical Manual; Technical report; FEMA: Hyattsville, MD, USA, 2022.
  13. Rojahn, C. Seismic Vulnerability and Impact of Disruption of Lifelines in the Conterminous United States; Technical Report ATC-25; FEMA: Hyattsville, MD, USA, 1991.
  14. Hines, P.; Apt, J.; Talukdar, S. Trends in the history of large blackouts in the United States. In Proceedings of the 2008 IEEE Power and Energy Society General Meeting–Conversion and Delivery of Electrical Energy in the 21st Century, Pittsburgh, PA, USA, 20–24 July 2008; pp. 1–8. [Google Scholar] [CrossRef]
  15. Wang, Y.; Chen, C.; Wang, J.; Baldick, R. Research on Resilience of Power Systems Under Natural Disasters—A Review. IEEE Trans. Power Syst. 2016, 31, 1604–1613. [Google Scholar] [CrossRef]
  16. IEEE. IEEE Standard 693: Recommended Practice for Seismic Design of Substations; Technical report; IEEE: Piscataway, NJ, USA, 2019. [Google Scholar] [CrossRef]
  17. Kwasinski, A.; Eidinger, J.; Tang, A.; Tudo-Bornareld, C. Performance of electric power systems in the 2010–2011 Christchurch, New Zealand, Earthquake Sequence. Earthq. Spectra 2014, 30, 205–230. [Google Scholar] [CrossRef]
  18. Park, J.; Nojima, N.; Reed, D. Nisqually Earthquake Electric Utility Analysis. Earthq. Spectra 2006, 22, 491–509. [Google Scholar] [CrossRef]
  19. Asfura, A. The Quindio, Columbia Earthquake of 25 January 1999: Reconnaissance Report; Technical report; Multidisciplinary Center for Earthquake Engineering Research (MCEER): Buffalo, NY, USA, 1999. [Google Scholar]
  20. Goltz, J. The Northridge, California Earthquake of 17 January 1994: General Reconnaissance Report; Technical Report NCEER-94-0005, National Center for Earthquake Engineering Research: Buffalo, NY, USA, 1994. [Google Scholar]
  21. Schiff, A. The Loma Prieta, California, Earthquake of 17 October 1989—Lifelines; Technical report; U.S. Geological Survey: Reston, VA, USA, 1998.
  22. Lee, G. The Chi-Chi, Taiwan Earthquake of 21 September 1999: Reconnaissance Report; Technical Report MCEER-00-0003, Multidisciplinary Center for Earthquake Engineering Research (MCEER): Buffalo, NY, USA, 2000. [Google Scholar]
  23. Cimellaro, G.; Chiriatti, M.; Reinhorn, A.; Tirca, L. Emilia Earthquake of 20 May 2012 in Northern Italy: Rebuilding a Community Resilient to Multiple Hazards; Technical Report MCEER-13-0006, Multidisciplinary Center for Earthquake Engineering Research (MCEER): Buffalo, NY, USA, 2013. [Google Scholar]
  24. Villamarin-Jacome, A.; Moreno, R. Seismic Resilience Assessment of Electric Power Systems Using a Substation Bay-level Model. In Proceedings of the 2022 17th International Conference on Probabilistic Methods Applied to Power Systems (PMAPS), Manchester, UK, 12–15 June 2022; pp. 1–6. [Google Scholar] [CrossRef]
  25. Birchfield, A.B.; Xu, T.; Gegner, K.M.; Shetye, K.S.; Overbye, T.J. Grid Structural Characteristics as Validation Criteria for Synthetic Networks. IEEE Trans. Power Syst. 2017, 32, 3258–3265. [Google Scholar] [CrossRef]
  26. Birchfield, A.B.; Xu, T.; Overbye, T.J. Power Flow Convergence and Reactive Power Planning in the Creation of Large Synthetic Grids. IEEE Trans. Power Syst. 2018, 33, 6667–6674. [Google Scholar] [CrossRef]
  27. Wirth, E.A.; Grant, A.; Marafi, N.A.; Frankel, A.D. Ensemble ShakeMaps for Magnitude 9 Earthquakes on the Cascadia Subduction Zone. Seismol. Res. Lett. 2020, 92, 199–211. [Google Scholar] [CrossRef]
  28. Frankel, A.; Wirth, E.; Marafi, N.; Vidale, J.; Stephenson, W. Broadband synthetic seismograms for magnitude 9 earthquakes on the Cascadia megathrust based on 3D simulations and stochastic synthetics, part 1: Methodology and overall results. Bull. Seismol. Soc. Am. 2018, 108, 2347–2369. [Google Scholar] [CrossRef]
  29. Heath, D.; Wald, D.; Worden, C.; Thompson, E.; Smoczyk, G. A global hybrid Vs30 map with a topographic slope-based default and regional map insets. Earthq. Spectra 2020, 36, 1570–1584. [Google Scholar] [CrossRef]
  30. Panteli, M.; Mancarella, P.; Trakas, D.; Kyriakides, E.; Hatziargyriou, N. Metrics and Quantification of Operational and Infrastructure Resilience in Power Systems. IEEE Trans. Power Syst. 2017, 32, 4732–4742. [Google Scholar] [CrossRef] [Green Version]
  31. Panteli, M.; Trakas, D.N.; Mancarella, P.; Hatziargyriou, N. Power Systems Resilience Assessment: Hardening and Smart Operational Enhancement Strategies. Proc. IEEE 2017, 105, 1202–1213. [Google Scholar] [CrossRef] [Green Version]
  32. Chalishazar, V.; Johnson, B.; Cotilla-Sanchez, E.; Brekken, T.K. Augmenting the Traditional Bus-Branch Model for Seismic Resilience Analysis. In Proceedings of the 2018 IEEE Energy Conversion Congress and Exposition (ECCE), Portland, OR, USA, 23–27 September 2018; pp. 1133–1137. [Google Scholar] [CrossRef]
  33. Zimmerman, R.D.; Murillo-Sánchez, C.E.; Thomas, R.J. MATPOWER: Steady-State Operations, Planning, and Analysis Tools for Power Systems Research and Education. IEEE Trans. Power Syst. 2011, 26, 12–19. [Google Scholar] [CrossRef] [Green Version]
  34. Burhenn, T.; Hawkins, H.; Ostrom, D.; Richau, E. The earthquake vulnerability of a utility system. In Proceedings of the American Power Conference, Chicago, IL, USA, 13–15 April 1992; pp. 224–227. [Google Scholar]
  35. Eidinger, J.M.; Kempner, J.L. Risk Assessment of Transmission System under Earthquake Loading. In Electrical Transmission and Substation Structures; American Society of Civil Engineers: Reston, VA, USA, 2012; pp. 183–192. Available online: https://ascelibrary.org/doi/pdf/10.1061/9780784412657.016 (accessed on 28 November 2022). [CrossRef]
  36. Eidinger, J.; Tang, A.K.; Fujisaki, E.; Sun, J.; Trinh, R. Seismic Fragility of Power Distribution Systems. In International Collaboration in Lifeline Earthquake Engineering; American Society of Civil Engineers: Reston, VA, USA, 2016; pp. 212–218. [Google Scholar] [CrossRef]
  37. Eidinger, J. Fragility of the Electric Power Grid; Technical report; G and E Engineering Systems: Olympic Valley, CA, USA, 2018. [Google Scholar]
  38. Adibi, M.M.; Martins, N. Impact of power system blackouts. In Proceedings of the 2015 IEEE Power & Energy Society General Meeting, Denver, CO, USA, 26–30 July 2015; pp. 1–15. [Google Scholar] [CrossRef]
Figure 1. The Cascadia Subduction Zone, which has the capacity to release a +9M earthquake. (Image from [3]).
Figure 1. The Cascadia Subduction Zone, which has the capacity to release a +9M earthquake. (Image from [3]).
Energies 15 09275 g001
Figure 2. The geographical layout of the ACTIVSg10k synthetic test case. The blue rectangle denotes the Damage Zone: the area most strongly impacted by a Cascadia Subduction Zone earthquake. Colors indicate transmission line nominal voltage: green 765 kV, orange 500 kV, red 345 kV, purple 230 kV, and black <200 kV. Image adapted from [26].
Figure 2. The geographical layout of the ACTIVSg10k synthetic test case. The blue rectangle denotes the Damage Zone: the area most strongly impacted by a Cascadia Subduction Zone earthquake. Colors indicate transmission line nominal voltage: green 765 kV, orange 500 kV, red 345 kV, purple 230 kV, and black <200 kV. Image adapted from [26].
Energies 15 09275 g002
Figure 3. Transformer fragility functions, plotted with parameters from [12].
Figure 3. Transformer fragility functions, plotted with parameters from [12].
Energies 15 09275 g003
Figure 4. PGA map for a magnitude 9 CSZ event. Image from the US Geological Survey (USGS) Earthquake Hazards Program website. The PGA values in the legend along the bottom of the figure are in % of 1 g.
Figure 4. PGA map for a magnitude 9 CSZ event. Image from the US Geological Survey (USGS) Earthquake Hazards Program website. The PGA values in the legend along the bottom of the figure are in % of 1 g.
Energies 15 09275 g004
Figure 5. Transformer restoration functions, created with log-normal fit of survey data.
Figure 5. Transformer restoration functions, created with log-normal fit of survey data.
Energies 15 09275 g005
Figure 6. An example system response to a damaging event at time t d b . The variable P is some performance quantity of the system. In a power system case, it could typically be power delivered to load. (Image adapted from [30,31].).
Figure 6. An example system response to a damaging event at time t d b . The variable P is some performance quantity of the system. In a power system case, it could typically be power delivered to load. (Image adapted from [30,31].).
Energies 15 09275 g006
Figure 7. Overall analysis and simulation structure. Each iteration is a quasi-steady state solution over 1000 days, for 2500 iterations total.
Figure 7. Overall analysis and simulation structure. Each iteration is a quasi-steady state solution over 1000 days, for 2500 iterations total.
Energies 15 09275 g007
Figure 8. Example graph representation of a double-bus double-breaker substation, with feeder 1 connected to a generator, feeder 2 connected to another substation, and feeder 3 connected to a load.
Figure 8. Example graph representation of a double-bus double-breaker substation, with feeder 1 connected to a generator, feeder 2 connected to another substation, and feeder 3 connected to a load.
Energies 15 09275 g008
Figure 9. Restoration of load vs time, including the 5th and 95th percentile cases.
Figure 9. Restoration of load vs time, including the 5th and 95th percentile cases.
Energies 15 09275 g009
Figure 10. Restoration of generation vs time, including the 5th and 95th percentile cases.
Figure 10. Restoration of generation vs time, including the 5th and 95th percentile cases.
Energies 15 09275 g010
Figure 11. The median and 95th percentile time for each substation in the synthetic model to reach full service (i.e., the full restoration of every asset in the substation).
Figure 11. The median and 95th percentile time for each substation in the synthetic model to reach full service (i.e., the full restoration of every asset in the substation).
Energies 15 09275 g011
Figure 12. Load still connected to the main system within the Damage Zone.
Figure 12. Load still connected to the main system within the Damage Zone.
Energies 15 09275 g012
Figure 13. Median, 5th, and 95th percentile load lost as calculated after each of 2500 iterations, as well as the variance.
Figure 13. Median, 5th, and 95th percentile load lost as calculated after each of 2500 iterations, as well as the variance.
Energies 15 09275 g013
Figure 14. Number of islands, and size of the largest island for the entire western grid model.
Figure 14. Number of islands, and size of the largest island for the entire western grid model.
Energies 15 09275 g014
Figure 15. Cumulative distribution function of power flow convergence over the 1000 day restoration period for 2500 iterations.
Figure 15. Cumulative distribution function of power flow convergence over the 1000 day restoration period for 2500 iterations.
Energies 15 09275 g015
Table 1. ACTIVSg10k system summary.
Table 1. ACTIVSg10k system summary.
BusesGen. Capacity [MW]Load [MW]
ACTIVSg10k10,000209,420150,917
Damage Zone145920,14023,122
Table 2. Resilience metrics.
Table 2. Resilience metrics.
MetricMetric Description5%50% (Median)95%
P 0 Initial performance [MW]23,12223,12223,122
P d Damaged performance [MW]20,16919,60919,018
P e Recovered performance [MW]22,89122,89122,891
t d b Damage start time [day]000
t r e Recovery end time [day]130171237
Λ Performance decrease [MW]295335124104
Π Rate of recovery [MW/day]20.919.216.3
RResilience0.9620.9510.937
Table 3. Load not served.
Table 3. Load not served.
5%50% (Median)95%
Load not served [MWh]4,224,0005,712,0007,680,000
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Weinmann, R.; Cotilla-Sanchez, E.; Brekken, T.K.A. Toward Models of Impact and Recovery of the US Western Grid from Earthquake Events. Energies 2022, 15, 9275. https://doi.org/10.3390/en15249275

AMA Style

Weinmann R, Cotilla-Sanchez E, Brekken TKA. Toward Models of Impact and Recovery of the US Western Grid from Earthquake Events. Energies. 2022; 15(24):9275. https://doi.org/10.3390/en15249275

Chicago/Turabian Style

Weinmann, Riley, Eduardo Cotilla-Sanchez, and Ted K. A. Brekken. 2022. "Toward Models of Impact and Recovery of the US Western Grid from Earthquake Events" Energies 15, no. 24: 9275. https://doi.org/10.3390/en15249275

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop