Next Article in Journal
Stamp-Charged Coke-Making Technology—The Effect of Charge Density and the Addition of Semi-Soft Coals on the Structural, Textural and Quality Parameters of Coke
Next Article in Special Issue
Utilizing Rooftop Renewable Energy Potential for Electric Vehicle Charging Infrastructure Using Multi-Energy Hub Approach
Previous Article in Journal
Vital Factors Stimulating Development and Competitiveness of Design and Construction Enterprises of Photovoltaic Farms
Previous Article in Special Issue
Decentral Energy Generation Potential of Anaerobic Digestion of Black Water and Kitchen Refuse for Eco-District Planning
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Planning of Electricity-Natural Gas Coupling System Considering Power to Gas Facilities

1
College of Information Science and Technology, Donghua University, Shanghai 201620, China
2
School of Electronic and Electrical Engineering, Shanghai University of Engineering Science, Shanghai 201620, China
*
Author to whom correspondence should be addressed.
Energies 2021, 14(12), 3400; https://doi.org/10.3390/en14123400
Submission received: 12 April 2021 / Revised: 12 May 2021 / Accepted: 7 June 2021 / Published: 9 June 2021
(This article belongs to the Special Issue Development and Implementation of Clean Energy Hubs)

Abstract

:
Bidirectional coupling systems for electricity and natural gas composed of gas units and power-to-gas (P2G) facilities improve the interactions between different energy systems. In this paper, a combined optimization planning method for an electricity-natural gas coupling system with P2G was studied. Firstly, the characteristics of the component model of the electricity-natural gas coupling system were analyzed. The optimization planning model for the electricity-natural gas coupling system was established with the goal of minimizing the sum of the annual investment costs and the annual operation costs. Based on the established model, the construction statuses for different types of units, power lines, and pipelines and the output distribution values for gas units and P2G stations were optimized. Then, the immune algorithm was proposed to solve the optimization planning model. Finally, an electricity-natural gas coupling system composed of a seven-node natural gas system and a nine-node power system was taken as an example to verify the rationality and effectiveness of the model under different scenarios.

Graphical Abstract

1. Introduction

Under the increasingly severe conditions regarding global resources and the environment, achieving greenhouse gas reduction targets requires an increased share of renewable energy sources in energy systems [1]. The development of efficient and clean energy systems has become the core of energy policies across all countries. Electricity-natural gas coupling systems consisting of gas generation units and power-to-gas (P2G) facilities improve the interactions of different energy systems and facilitates renewable energy integration [2,3].
Power-to-gas (P2G) is the process whereby electricity is used to produce hydrogen (H2) or synthetic natural gas (SNG). In the first type of P2G process, hydrogen is formed through the process of water electrolysis. Hydrogen can be used for fuel cell electric vehicles (FCEV) [1], can supply the gas load, and can also increase the environmental performance of microturbines [4]. As a second P2G process, the SNG gas methane is produced via the methanation of electrolytic hydrogen [5]. With P2G, hydrogen or synthetic natural gas is produced via water electrolysis and can be flexibly stored or injected into the natural gas network [6,7].
Before the application of P2G, the linkage between the gas and electricity networks mainly occurred through a gas-fired generator. In some studies, gas-fired generators have been used as coupling components of electricity-gas systems to achieve combined dispatching in operation. One study [8] investigated how the uncertainty in wind forecasts affects the operation of power systems, and in particular gas-fired generators. In [9], an integrated approach to the operation of gas and electricity networks was investigated to improve the security of gas and electricity supply. In [10], it was demonstrated that operating gas and electricity as a coupled system resulted in about 7% savings in operational costs. However, gas-fired generators only realize the unidirectional coupling of gas-electric systems. P2G technology can convert the original unidirectional coupling systems into bidirectional energy flow between gas and electricity systems.
With the development of P2G technology, dozens of P2G demonstration projects have been built in Europe. The Solar Fuel company in Germany uses wind power to produce methane, which is directly supplied to the natural gas load through the natural gas network. Greenpeace Energy and other electricity to gas companies have also started P2G projects. P2G commercial applications are beginning. Therefore, the idea of operation optimization with gas-fired generators and P2G stations has attracted more attention. In [11], an integrated model was developed for the simulation of operational interdependences between the two networks by considering P2G. The work modeled P2G with power system requirements and integrated this with gas network modeling. In [12], considering the different response times of gas and power systems, the transient gas flow and steady-state power flow were combined to formulate the dynamic optimal energy flow in integrated gas and power systems. In [13], the value of flexibility technologies, such as P2G, was quantified in the operation of integrated gas and electricity systems in Great Britain 2030 energy scenarios for different renewable generation penetration levels. In [14], the efficacy of three options were evaluated, namely flexible gas-fired plants, electricity storage, and a power-to-gas system, in order to compensate for the intermittency of wind generation. Another study [15] showed that P2G was capable of reducing wind curtailment in high wind cases and of decreasing the overall costs of operating the gas and electricity network. In [16], the authors proposed a two-layer optimal scheduling model for the power-gas coupling system, which considered the optimal operation of the natural gas system and used P2G to absorb the excess wind power. All of the above studies show that, although P2G technology has a high cost at present, it has high flexibility in absorbing wind power and improving system operation costs.
The above research has mainly focused on the optimization of the combined operation of an electricity-gas coupling system with gas-fired generators and the P2G technique. Planning is the basis of operation, and the planning scheme will affect the operation. A previous study [17] established the source network coordination optimization programming model for an electricity-natural gas coupling system, which was decoupled into one upper level involving an investment optimization model and two lower levels involving safety and economic operation optimization models. The optimal solution satisfying the constraints was produced by iterations between the upper and lower levels of these models. Another study [18] proposed a power flow calculation method suitable for radial natural gas networks and verified the computational efficiency of the proposed method in the combined planning of a large-scale electricity-natural gas coupling system. In [19], the co-planning process was modeled as mixed-integer nonlinear programming, the objective of which was to maximize the net present value (NPV) of the social welfare of the combined gas and power infrastructure. In [17,18,19], a reduction in wind curtailment was not considered. In [20], a combined gas and electricity network expansion planning model was developed to minimize gas and electricity operational and network expansion costs. The model was used to analyze the gas and electricity infrastructure expansion requirements for Great Britain. The application scenario of a low-carbon energy system had a projected installed wind capacity of 15.5 GW by 2030. In [21], flexibility options, such as battery storage, demand-side response, and gas-fired generators, were considered in a combined gas and electricity network expansion planning model, and the optimal investment approach was investigated.
In the above studies, the role of P2G stations is not fully considered in the planning of coupling systems. However, from the above literature review, it can be found that the P2G technique can affect the operation of electricity-natural gas systems. Therefore, this study further analyzed the effects of P2G station planning on the network structure of coupling systems. Compared with the small proportion of hydrogen injection, methane is less affected by this limitation. The P2G approach mentioned in the rest of this paper refers to the conversion of electricity to methane.
Based on the above background, the planning of the P2G station was considered in the planning model for the electricity-natural gas coupling system. The model considers the construction state and operation output of P2G plants, gas-fired generators, natural gas pipelines, and power transmission lines. The aim was to minimize the sum of annual investment costs and annual operation costs for the coupling system. The effect of wind curtailment was also considered in this study. The rest of this paper is structured as follows. Section 2 discusses the principles of the electric–gas coupling system model. The models of coupling elements are also described in this section. Section 3 outlines the planning model for the electricity-natural gas coupling system with the goal of minimizing the sum of the annual investment costs and the annual operation costs. The model takes the construction statuses of different types of units, power lines, and pipelines and the output power values of the gas unit and P2G plant station as the optimization variants. The immune algorithm is proposed to solve the optimization model. Section 4 exemplifies the application of the model through case studies on an nine–node power system and a seven-node gas system. Section 5 contains the concluding remarks. Details on the gas network analysis model are shown in Appendix A.

2. Electricity-Natural Gas Coupling System

In this section, the principles of the electric-gas coupling system model and the coupling element model are described.

2.1. Power System Model

P2G systems can absorb excess wind energy and reduce wind curtailment [22]. In order to improve the operation economy of the coupling system, wind farms were considered in the model and connected to the power system as PV nodes. The power flow equation is as follows:
P i ele + P i wind V i j i V j G i j cos θ i j + B i j sin θ i j   = 0
Q i ele V i j i V j G i j sin θ i j B i j cos θ i j   = 0
where P i ele and Q i ele are the active power and reactive power injected by the generator in node i; P i wind is the active power injected by the wind farm in node i; V i is the voltage amplitude of node i; θ i j is the voltage phase angle difference between node i and node j; G i j and B i j are the real and imaginary parts of the nodal admittance matrix, respectively; j i represents all nodes j directly connected to node i.

2.2. Gas System Model

The natural gas system is mainly composed of a natural gas well (gas source), transmission pipeline, pressurization station, gas storage station, and natural gas load. The compressor in the pressurization station is used to compensate for the pressure loss caused by friction when the gas is transmitted in the pipeline. It consumes less natural gas, accounting for about 3–5% of the transmission volume [23]. This paper focuses on the economic planning with P2G, and mainly establishes the pipeline air transport model. The operating cost of the compressor only accounts for a small proportion, so it was ignored in the modeling.
The direction of gas transmission in the pipeline depends on the pressure at both ends of the pipeline. The flow always flows from the node with high pressure to the node with low pressure. The flow size not only depends on the pressure at both ends of the pipeline but is also related to the diameter, length, operating temperature, and other factors of the pipeline. Steady-state pipeline flow can be calculated using the Weymouth equation [19]:
f u v = sgn π u π v × C u v π u 2 π v 2 sgn π u π v   =   1 π u π v 1 π u < π v
where f u v is the flow rate in the uv section of the pipeline; C u v is the constant relative to the uv segment of the pipe; π u and π v are the pressures of natural gas network nodes u and v, respectively; sgn π u π v is a symbolic constant, representing the flow direction of gas in the pipeline.

2.3. Power-to-Gas Model

The P2G process consists of two main steps: water electrolysis (2H2O → 2H2 + O2) [24] and hydrogen methanation (CO2 + 4H2 → CH4 + 2H2O) [25]. Hydrogen produced by the electrolysis of water can be stored and transported to supply hydrogen loads (such as hydrogen fuel vehicles). The model mainly includes the following three parts: electrolytic cell, storage unit, and methane reactor [22].
Electrolytic cells, according to different technologies, mainly consist of three types: alkaline water electrolytic cells, proton exchange membrane electrolytic cells, and solid oxide cells. Among the three types of electrolytic cells, proton exchange membrane electrolytic cells have the highest current density, fast response speeds, and use the most mature technology [5]. This work modeled the proton exchange membrane electrolytic cells as follows [22]:
V T R , n , t H 2 = μ T R , n f P T R , n , t P T R , n , r a t e d S T R , n
f P T R , n , t P T R , n , r a t e d = α T R , n P T R , n , t P T R , n , r a t e d 2 + β T R , n P T R , n , t P T R , n , r a t e d +   γ T R , n
P T R , n , t min P T R , n , t P T R , n , t max
where V T R , n , t H 2 is the hydrogen production at time t of the electrolytic cell at the nth plant station in the P2G plant station set TR; μ T R , n represents the start and stop states of the electrolytic cell, whereby 1 represents the start state and 0 represents the stop state; f P T R , n , t P T R , n , r a t e d is the efficiency function of the electrolytic cell; P T R , n , t is the input power of the electrolytic cell at time t; S T R , n is the rated capacity of the electrolytic cell; P T R , n , r a t e d is the rated value of the input electric power of the electrolytic cell; α T R , n , β T R , n , and γ T R , n are the coefficients of the efficiency function; P T R , n , t max and P T R , n , t min are the upper and lower limits of the input power of the electrolytic cell, respectively.
The storage unit has both the functions of compressing and storing hydrogen. Since the hydrogen load was not considered in this study and all the hydrogen produced by the electrolytic cell is used to produce methane, this part of the modeling was ignored.
In practical operation, the efficiency of the methane reactor is not fixed due to the influence of the gas composition, temperature, pressure, and other conditions. This part of this model was built as follows:
P T R , n , t = η T R , n , t V T R , n , t H 2 H g k M
V T R , n , t H 2 , min V T R , n , t H 2 V T R , n , t H 2 , max
Q T R , n , t = P T R , n . t H g
where η T R , n , t is the operating efficiency of the methane reactor at time t; H g is the calorific value of natural gas; M is the mass of natural gas per cubic meter under standard conditions; k is the coefficient of conversion from hydrogen to natural gas in molar mass; V T R , n , t H 2 , max and V T R , n , t H 2 , min are the upper and lower limits of the input volume of hydrogen in the methane reactor, respectively; Q T R , n , t is the output natural gas flow.
Since the dynamic characteristics of P2G equipment were not considered in the planning stage of this study, the time interval of P2G output optimization was set as 1 h, and the time scale was large. The climbing constraint of P2G equipment has little influence on the optimization results. Therefore, this study temporarily ignored the climbing constraints of the P2G equipment and gas unit. The conversion efficiency of each part of the P2G system was regarded as a fixed value. The simplified P2G equipment uses a linear efficiency conversion model:
Q T R , n = η T R , n P T R , n / H g
where η T R , n is the energy conversion efficiency of the P2G plant station.

2.4. Gas Generator Model

As gas loads in the natural gas system, the gas unit converts natural gas into electric energy and injects it into the power system. It acts as the power source in the power system at the same time:
P P S , e = η P S , e Q P S , e H g
where P P S , e is the output of the eth unit in the PS set of gas-fired generating sets to be selected; η P S , e is the energy conversion efficiency of the unit; Q P S , e is the natural gas load of the corresponding node of the unit in the natural gas system.

3. Combined Optimization Planning Model for Electricity-Natural Gas Coupling System Considering P2G

The P2G co-planning model of the electricity-natural gas coupling system established in this work aimed to minimize the sum of the annual investment cost and operation cost:
min R total = r 1 + r T 1 + r T 1 R inv + R op
where T is the investment recovery period, for which 15 years was selected in this study; r is the interest rate; R inv is the total cost of investment; R op is the annual operating cost.

3.1. Total Cost of Investment

The total cost of investment is shown as follows:
R inv = e P S C P S e x e + l E L C E L l y l + p G L C G L p z p + n T R C T R n m n
where PS, EL, GL, and TR are the sets of generators, transmission lines, gas transmission pipelines, and power-to-gas plants to be selected; C P S e , C E L l , C G L p , and C T R n are the investment costs of the generator e, transmission line l, gas transmission pipeline p, and power-to-gas plant station n, respectively; x e , y l , z p , and m n respectively represent the construction state variables of the generator e, transmission line l, gas transmission pipeline p, and power-to-gas plant station n, where “1” represents construction and “0” represents no construction.

3.2. Annual Operating Cost

Annual operating costs include fuel costs for coal-fired generating units, gas well output costs, wind farm output costs, and wind curtailment costs. Since the actual annual operation or maintenance cost of the P2G plant station is only about 5% of the fixed investment cost, the P2G operation cost is not considered for the time being. The model is shown as follows:
R op = N days a A S t = 1 24 U A S , a op P A S , a ( t ) + b W S t = 1 24 U W S , b op Q W S , b ( t ) + c W D t = 1 24 U W D , c op P W D , c ( t ) + U W D , c c u t P W D , c max ( t ) P W D , c ( t )
where N days is the number of days per year; AS, WS, and WD are the sets of coal-fired generating units, gas wells, and wind farms, respectively; P A S , a ( t ) , Q W S , b ( t ) , and P W D , c ( t ) represent the output of generator a, gas well of gas source point b, and wind farm c at the time t of a typical day; U A S , a op , U W S , b op , and U W D , c op represent the unit output costs of generator a, gas source point b, and wind farm c; U W D , c c u t is the unit wind curtailment cost of the wind farm; P W D , c max ( t ) is the forecast output of the wind farm at time t [16].
After planning, the gas generator set is regarded as the gas load in the natural gas network. Its fuel cost is included in the gas well output cost. Since the natural gas system model established in this study does not consider the characteristics of compressor and pipe storage, and also since the P2G and gas unit provide and consume natural gas respectively in the natural gas system, the total output of the gas source is the sum of the natural gas load from all nodes:
b W S Q W S , b ( t ) = Q load ( t ) + e P S x e Q P S , e ( t ) n T R m n Q T R , n ( t )
where Q P S , e ( t ) is the natural gas flow rate consumed by the eth unit in the gas generator set PS at time t in a typical day; Q T R , n ( t ) is the natural gas flow rate output by the nth plant station in the P2G plant station set TR at time t in a typical day; Q load ( t ) represents the sum of the flows of other natural gas load nodes at time t in a typical day.

3.3. Model Constraints

The model constraints include generator output constraints, gas source output constraints, P2G plant output constraints, power flow balance constraints and safety constraints of electric–gas coupling system, and wind farm output constraints:
P A L , a min P A L , a ( t ) P A L , a max A L = A S P S
Q W S , b min Q W S , b ( t ) Q W S , b max
V i min V i ( t ) V i max P i j min P i j ( t ) P i j max π u min π u ( t ) π u max f u v min f u v ( t ) f u v max
0 P W D , c ( t ) P W D , c max ( t )
where AL is the collection of all generating sets; P A L , a max and P A L , a min are the upper and lower limits of the output of the generator a in set AL; Q W S , b max and Q W S , b min are the upper and lower output limits of the gas well at the gas source point b in the gas well set WS; V i max and V i min are the upper and lower limits of voltage amplitude of node i in the power system; P i j max and P i j min are the upper and lower limits of active power in transmission line ij; π u max and π u min are the upper and lower limits of pressure of node u in the natural gas system; f u v max and f u v min are the upper and lower limits of the pipeline flow of gas transmission pipeline uv. The power flow balance constraints of the coupled system are shown in Equations (1)–(3), (10) and (11). In addition, the actual output of the wind farm at every moment is not greater than its predicted value. The difference between them is the curtailed electricity of the wind farm.

3.4. Solving Algorithm

In this study, the immune algorithm was used to solve the established model. The immune algorithm is an intelligent optimization algorithm that simulates the immune mechanism of biology and combines the evolutionary mechanism of genes [26]. It has been widely used to solve all kinds of optimization problems, such as TSP [27], the topology optimization problem, and the job shop scheduling problem [28]. The algorithm can generate new individuals continuously through immune operation and a population refresh operator. By referring to the diversity preservation mechanism of the biological immune system, the algorithm introduces the calculation and evaluation method of antibody concentration to suppress the occurrence of repeated or similar individuals. Therefore, it can ensure the global search ability of the algorithm [29]. In order to improve the solving speed of the model, a decoupled power flow calculation method was used to verify the security of the power network and natural gas network. For the natural gas network, the power flow calculation method of the radial gas network proposed in [18] was adopted.
The solving process for the model is shown in Figure 1. The model solving method in this paper can be divided into two stages. The planning optimization stage is the first stage. In this stage, the network structure satisfying all constraints of the model is generated randomly. The operating optimization stage is the second stage. In this stage, based on the network formed in the planning optimization stage, the optimal outputs for all units are solved by the immune algorithm. In the flowchart shown in Figure 1, stage 1 represents the planning optimization stage, and stage 2 represents the operating optimization stage. In each iteration, the new total cost is calculated by summation of the optimization results from stage 1 and stage 2. Then, by comparing the new cost with the previous minimum cost, the optimal cost and the relevant data are retained. At the end of each iteration, a judgment is made on whether it meets the number of maximum iterations; then, the optimal result is output. The detailed calculation steps for the two stages are described below.
Stage 1 (planning optimization stage):
(1) Number of gas units and P2G plant stations of different types to be selected. Randomly generate the location and type of the new power supply and P2G plant station. For example, (G1, G2, P1, P2) = (2, 1, 1, 0) means that gas units #2 and #1 are added at the location of G1 and G2. P2G station #1 is added at P1, and there is no P2G station at P2;
(2) Randomly generate the planning natural gas pipelines and power lines that are connected between new coupling units in the system. Use the 0-1 variable to indicate whether a pipeline or line is built or not. For example, “1” means built and “0” means not built;
(3) Randomly generate other new lines of the power network and pipelines of the natural gas network, expressed as 0-1 variables. Calculate the decoupled power flow of the planning system. When checking the safety of the network, all loads are set as their maximum values, and the generator and P2G stations are set as the full load;
(4) Calculate the total investment cost using (13) and convert it to the equivalent annual value using (12).
Stage 2 (operating optimization stage):
(1) Randomly generate antibodies representing the unit’s output, whereby the range of outputs is from 0% to 100%. Carry out network security verification. Individuals meeting the verification threshold are put into the initial antibody group;
(2) Calculation of the antibody concentration, antibody affinity, and excitation degree values. The antibody concentration is an indicator of the diversity of the antibody population. A higher concentration means more closely related individuals, which is not conducive to global optimization. Therefore, it is necessary to suppress the individuals with a high concentration. Antibody affinity is the corresponding operating cost. The lower the cost means the higher the affinity. The excitation degree is the difference between affinity and concentration. The higher the excitation, the higher the selection rate;
(3) Sequence the antibodies by their excitation degrees. The first half of the antibody population is selected for immunization. Firstly, the selected antibodies are cloned and copied. Then, the copied antibodies are mutated in the replicating population to carry out local optimization. Finally, the mutation results are selected to inhibit the antibodies with low affinity and retain the mutation results with high affinity;
(4) Population refresh. The new antibodies that meet the constraints are generated randomly to replace the antibodies with a low excitation degree in the original population. The replaced antibodies are then combined with the antibodies after immunization operation to form a new population to continue the immune cycle operation;
(5) After decoding, the optimal values of the unit power and the annual operating costs are output.

4. Case Study

In this paper, an electricity-natural gas coupling system composed of a nine-node natural gas network and a nine-node MATPOWER power system was taken as an example, as shown in Figure 2. MATPOWER is a package of MATLAB M-files for solving power flow and optimal power flow problems.
In Figure 2, the network shown in blue is the gas network, and the network shown in green is the power network. A–E are nodes of the natural gas network, while 1–9 and 10 and 11 are existing nodes and candidate nodes in the power system network, respectively. WS1 and WS2 are natural gas sources. G1–G3 are gas units to be selected. P1 and P2 are P2G plant stations to be selected. There was one wind power plant in node three and two coal-fired units in node one and node two. The dotted lines represent the candidate pipelines, power lines, and units to be built, while the solid lines represent the existing devices that have been built. The two networks were bidirectionally coupled through the P2G plant station and the gas unit to be selected. The wind curtailment rate of the wind farm was 20%. All curtailed wind power could be absorbed after the P2G plant station was set. The typical daily load curve was drawn according to the natural gas load data in [30]. The actual data curves of the daily power load, daily natural gas load, and daily wind power generation are shown in Appendix A Figure A1, Figure A2 and Figure A3, respectively. Other parameters are shown in Appendix A Table A1, Table A2, Table A3, Table A4, Table A5 and Table A6. In order to verify the correctness of the model and analyze the economy of the P2G system in terms of planning and operation at the same time, this work set two scenarios to solve the model. Scenario 1: Excluding optimized planning of the P2G plant station, the wind energy consumption rate was 80%. Scenario 2: Including optimized planning of the P2G plant station, the wind energy consumption rate was 100%.
The parameters of the algorithm were selected according to the general range proposed in [31,32]. Within these ranges, the parameters in this study were determined by trying them many times. The optimal values of parameters that were most apt to solve the proposed combined planning model were selected. The maximum number of immune iterations of the immune algorithm was set at 100 times. The number of clones was set at 10, and the mutation probability was set as 0.7. The lower and upper limits of the outputs of all units were set as 0% and 100%, respectively. The optimal value was generally obtained after one immune cycle with 40 iterations. The algorithm had good convergence in the solution of the unit output optimization problem.
The planning grids obtained under the two scenarios are shown in Figure 3 and Figure 4, where the dotted lines represent the facilities to be built after the planning. In Figure 4, the P2G plant station P1 was built in the natural gas system to meet part of the load in node C, so there was no need to expand original pipelines B–E and C–E. In Figure 4, power lines 1–4 and 2–7 needed to be built instead of power lines 2–8 in Figure 3.
The operation cost for each hour in a typical load day was calculated by the proposed immune evolution method. The convergence trends are very close. Therefore, in order to give a clear picture, only the immune evolution curves at 12:00 and 00:00 were selected and drawn in Figure 5 to validate the convergence characteristics of the algorithm. It can be seen that the immune algorithm had good convergence characteristics in terms of unit output optimization. The correctness of the algorithm parameters was also validated.
In this study, the data for the power line, pipeline, and unit investment costs were taken from [33]. The planning results and cost comparisons obtained under the two scenarios are shown in Table 1 and Table 2, respectively.
The annual investment cost is the total cost for the gas pipelines, power lines, gas units, and P2G plant stations, which was converted into an equivalent annual investment value. It can be seen from Table 2 that the annual investment cost in scenario 2 with P2G was higher compared with the planning scheme in scenario 1 without P2G. Among these, the investment cost for the natural gas pipeline in scenario 2 was significantly reduced. The reason is that P2G served as a gas source in the natural gas system to meet part of the load in node C. After planning, the original pipelines B–E and C–E could still transport natural gas to meet the demands of the remaining load of node C, so there was no need for expansion. In scenario 2, P2, the candidate plant of P2G, was located far away from load nodes in the natural gas system, and its establishment did not affect the natural gas volume to be transported by other pipelines; therefore, it was not built. In addition to the pipeline investment costs, the investment costs for the power lines and units under scenario 2 were higher. This was because the P2G investment cost was higher, and the new P2G installation required greater spending. At the same time, the P2G factory station provided a larger electric load in the power system. Therefore, in order to meet the trend of the security constraints, more lines and generator capacity expansion were needed.
Compared with scenario 1, scenario 2 showed lower annual operating costs. This was because the construction of the P2G plant station absorbed the curtailed wind energy of the wind farm and reduced the output of the natural gas wells. At the same time, the bidirectional coupled system composed of the P2G and gas unit had a large space for output regulation. Therefore, the operation cost can be reduced by optimizing the output of the unit. A day representing the average daily load for future years is selected as the typical day [34]. The hourly operating costs for typical days in the system under the two scenarios were compared as shown in Figure 6. Detailed hourly unit output distribution values are listed in Appendix A Table A7 and Table A8.
As shown in Figure 6, between 01:00 and 05:00, the P2G plant’s consumption of curtailed wind energy satisfied part of the natural gas load and reduced the output costs of the gas source. However, due to the low demand for the electric load and gas load, the output optimization of the P2G plant and gas unit has little impact on the operating cost. Therefore, there was little difference in the operating costs between the two scenarios. Between 06:00 to 00:00, scenario 2 showed lower operation costs. This is because in scenario 2, the P2G factory building could absorb the curtailed wind and the bidirectional coupling system consisting of the unit and gas have a larger output power distribution space. With the increase in the electric load and load requirements, the coordination and optimization of different units can effectively reduce the operation cost. It should be highlighted that there was no curtailed wind power in the wind farm between 09:00 and 19:00. During this period, the output of the P2G plant station reduces the gas output from the natural gas source, which was the main reason for the reduction in the operating costs.
In Figure 6, 12:00 and 20:00 are two moments with peak daily operating costs in the typical day. The operating cost differences between the two scenarios are also the biggest at these two moments. As can be seen from the load curve, the peak values for the electric load and gas load demands in the whole day are at 20:00. The electric load at 12:00 is at its secondary peak value across the whole day. It can be seen that when the load demand was high, the coordinated optimization of the P2G plant station and gas unit output could effectively reduce the system operation costs, resulting in greater economic benefits.
It can be seen from the analysis that reasonable planning of the P2G location can effectively reduce the investment costs of the natural gas pipeline. P2G technology has developed rapidly in recent years, which could improve the interactivity of power and natural gas systems. However, under the existing technical conditions, the investment and construction costs for the P2G plant station were still high, meaning such systems are not yet economically feasible. With the gradual maturity of P2G technology, the decrease in investment cost, and the improvement of operation efficiency, the method proposed in this paper could improve the economic benefits from the planning and operation of electricity-gas coupling systems and help to absorb large-scale renewable energy.

5. Conclusions

In this study, the P2G approach was considered in an optimization planning model of an electricity-natural gas coupling system. The effects of P2G station planning on the network structure of the coupling system were deeply analyzed. The combined optimization model used the construction statuses of different types of units, power lines, and pipelines and the output power from the gas unit and P2G plant station as optimization variants. It aimed to minimize the sum of annual investment costs and annual operation costs for the system without wind curtailment. The immune algorithm was proposed to solve the power-gas coupling optimization planning problem, involving P2G and gas units.
Through case studies, it was found that the investment costs for P2G plant stations and the supporting expansion equipment were relatively high. However, the reasonable planning of a P2G location could effectively reduce the investment cost of the natural gas network pipeline. For the regions that need to spend a lot of money in building many natural gas network pipelines to satisfy the future gas load, investment in P2G plant stations could be taken as an optional solution. Additionally, in the power–natural gas coupling system composed of P2G and gas units, the operation costs of the system can be effectively reduced by adjusting the output distribution of the gas units and P2G plant station. When the load demand is high, the economic benefits brought about by output optimization are more significant.
The commercial application of P2G technology is only just beginning, meaning the optimal planning method proposed in this paper can be initially applied to small-scale, user-side regional energy supply systems, optimizing the allocation of units and improving the planning economy. The annual operating costs calculated in this paper do not consider the carbon capture costs of the P2G approach. With the development of a low-carbon economy, the carbon capture function of the P2G approach could provide a carbon emission option, which will further improve the operating costs in the future.

Author Contributions

Conceptualization, J.X. and P.W.; methodology, J.X. and P.W.; software, P.W.; validation, J.X. and P.W.; formal analysis, J.X. and P.W.; investigation, J.X. and P.W.; resources, P.W.; data curation, P.W.; writing—original draft preparation, J.X.; writing—review and editing, P.W.; visualization, J.X.; supervision, P.W.; project administration, P.W. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Data sharing not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

Figure A1, Figure A2 and Figure A3 are typical daily power load, typical daily natural gas load, and typical daily wind power generation, respectively. These data were used as inputs for planning in case study of Section 4.
Figure A1. Typical daily power load for planning.
Figure A1. Typical daily power load for planning.
Energies 14 03400 g0a1
Figure A2. Typical daily natural gas load for planning.
Figure A2. Typical daily natural gas load for planning.
Energies 14 03400 g0a2
Figure A3. Typical daily wind power generation for planning.
Figure A3. Typical daily wind power generation for planning.
Energies 14 03400 g0a3
Table A1, Table A2, Table A3, Table A4, Table A5 and Table A6 contain the modeling parameters. Table A1 contains gas pipeline parameters [30]; Table A2 contains nodal parameters of natural gas network [30]; Table A3 contains data of gas generators and P2G plants to be selected [30,33]; Table A4 and Table A5 contain the length and cost of pipelines in gas system and lines in power system [30,33]; Table A6 contains other parameters, such as natural gas price, unit cost of coal-fired generator, wind farm output cost, and so on [16,33].
Table A1. Gas pipeline parameters. Reproduced from [30], IEEE Transactions on Power Systems: 2009.
Table A1. Gas pipeline parameters. Reproduced from [30], IEEE Transactions on Power Systems: 2009.
Gas PipePipe Constant
Starting NodeEnding Node
AB50.6
B D40
DG50.1
CE43.5
BE37.5
EF45.3
Table A2. Nodal parameters of natural gas network. Reproduced from [30], IEEE Transactions on Power Systems: 2009.
Table A2. Nodal parameters of natural gas network. Reproduced from [30], IEEE Transactions on Power Systems: 2009.
NodePressure Low Limit
(PSIA)
Pressure High Limit
(PSIA)
A30200
B80200
C30200
D80200
E80200
F80200
G30200
Table A3. Data of gas-fired generators and P2G plants to be selected. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
Table A3. Data of gas-fired generators and P2G plants to be selected. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
PlantsTypeCapacity (MW)Cost Per Unit Capacity (M$)
Gas Generator#11001.1
#21501.0
#31800.9
P2G Station#11201.5
#21801.3
Table A4. Length and cost of pipelines to be selected in the natural gas system. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
Table A4. Length and cost of pipelines to be selected in the natural gas system. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
Starting NodeEnding NodePipe Length (km)Building Cost (M$)
AB3060
BD3060
DG3060
CE3060
BE3060
EF4590
AG11020
CG12040
EG31020
FG32040
BG21020
D G2 10 20
Table A5. Length and cost of lines to be selected in the power system. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
Table A5. Length and cost of lines to be selected in the power system. Reproduced from [30,33], IEEE Transactions on Power Systems: 2009 and Proceedings of the Chinese Society of Electrical Engineering: 2017.
Starting NodeEnding NodeLine Length (km)Building Cost (M$)
5101515
3111515
272020
281515
294040
141515
452020
563030
673232
783535
633030
493333
8 9 35 35
Table A6. Other data. Reproduced from [16,33], Proceedings of the Chinese Society of Electrical Engineering: 2018 and 2017.
Table A6. Other data. Reproduced from [16,33], Proceedings of the Chinese Society of Electrical Engineering: 2018 and 2017.
Input Parameters for PlanningValue
Natural gas price1.35 $/kcf
Cost per unit of power generation for coal-fired unit8 $/MW
Maximum output of Node 1 coal-fired unit200 MW
Rated output of Node 2 coal-fired unit100 MW
Maximum grid-connected power of wind power without P2G200 MW
Wind farm output cost8 $/MW
Wind farm curtailed wind cost7 $/MW
Table A7 and Table A8 contain the optimization results that are not shown in the main body of text, which were also obtained by model calculation.
Table A7. Hourly output of gas-fired generators in Scenario 1.
Table A7. Hourly output of gas-fired generators in Scenario 1.
Time (h)Scenario 1
Gas Generator (%)
G1: #2G2: #1G3: #2
100100
200100
30098
400100
50298
6274100
7706100
89330100
910040100
1010067100
1110098100
12100100100
138446100
149246100
1510056100
1610076100
179890100
18100100100
19100100100
20100100100
219867100
22780100
23200100
2430100
Table A8. Hourly output of gas-fired generators and P2G plants in Scenario 2.
Table A8. Hourly output of gas-fired generators and P2G plants in Scenario 2.
Time(h)Scenario 2
Gas Generator (%)P2G Station (%)
G1: #3G2: #3G3: #3P1: #1
1570100100
2460100100
3280100100
4400100100
5700100100
610022100100
710048100100
810077100100
910076100100
1010098100100
1110099100100
1210093100100
1310071100100
1410079100100
1510085100100
16100100100100
17100100100100
18100100100100
1910092100100
2010010010029
2110098100100
2210065100100
2310020100100
24570100100

References

  1. Welder, L.; Ryberg, D.S.; Kotzur, L.; Grube, T.; Robinius, M.; Stolten, D. Spatio-temporal optimization of a future energy system for power-to-hydrogen applications in Germany. Energy 2018, 158, 1130–1149. [Google Scholar] [CrossRef]
  2. Yan, X.; Zhang, X.; Gu, C.; Li, F. Power to gas: Addressing renewable curtailment by converting to hydrogen. Front. Energy 2018, 12, 560–568. [Google Scholar] [CrossRef]
  3. Nastasi, B.; Mazzoni, S.; Groppi, D.; Romagnoli, A.; Garcia, D.A. Solar power-to-gas application to an island energy system. Renew. Energy 2021, 164, 1005–1016. [Google Scholar] [CrossRef]
  4. Santoli, L.D.; Basso, G.L.; Barati, S.; D’Ambra, S.; Fasolilli, C. Seasonal Energy and Environmental Characterization of A Micro Gasturbine Fueled with H2NG Blends. Energy 2020, 193, 1–19. [Google Scholar] [CrossRef]
  5. Xing, X.; Lin, J.; Song, Y.; Zhou, Y.; Mu, S.; Hu, Q. Modeling and operation of the power-to-gas system for renewables integration: A review. CSEE J. Power Energy Syst. 2018, 4, 168–178. [Google Scholar] [CrossRef]
  6. Walker, S.; Al-Zakwani, S.; Maroufmashat, A.; Fowler, M.; Elkamel, A. Multi-Criteria Examination of Power-to-Gas Pathways under Stochastic Preferences. Energies 2020, 13, 3151. [Google Scholar] [CrossRef]
  7. Maroufmashat, A.; Fowler, M. Transition of Future Energy System Infrastructure; through Power-to-Gas Pathways. Energies 2017, 10, 1089. [Google Scholar] [CrossRef] [Green Version]
  8. Xydas, E.; Qadrdan, M.; Marmaras, C.; Cipcigan, L.; Jenkins, N.; Ameli, H. Probabilistic wind power forecasting and its application in the scheduling of gas-fired generators. Appl. Energy 2017, 192, 382–394. [Google Scholar] [CrossRef] [Green Version]
  9. Ameli, H.; Qadrdan, M.; Strbac, G. Value of gas network infrastructure flexibility in supporting cost effective operation of power systems. Appl. Energy 2017, 202, 571–580. [Google Scholar] [CrossRef]
  10. Ameli, H.; Qadrdan, M.; Strbac, G. Coordinated operation strategies for natural gas and power systems in presence of gas-related flexibilities. IET Energy Syst. Integr. 2019, 1, 3–13. [Google Scholar] [CrossRef]
  11. Clegg, S.; Mancarella, P. Integrated Modeling and Assessment of the Operational Impact of Power-to-Gas (P2G) on Electrical and Gas Transmission Networks. IEEE Trans. Sustain. Energy 2015, 6, 1234–1244. [Google Scholar] [CrossRef]
  12. Fang, J.; Zeng, Q.; Ai, X.; Chen, Z.; Wen, J. Dynamic Optimal Energy Flow in the Integrated Natural Gas and Electrical Power Systems. IEEE Trans. Sustain. Energy 2018, 9, 188–198. [Google Scholar] [CrossRef]
  13. Ameli, H.; Qadrdan, M.; Strbac, G. Coordinated Operation of Gas and Electricity Systems for Flexibility Study. Front. Energy Res. 2020, 8, 1–17. [Google Scholar] [CrossRef]
  14. Qadrdan, M.; Ameli, H.; Strbac, G.; Jenkins, N. Efficacy of options to address balancing challenges: Integrated gas and electricity perspectives. Appl. Energy 2017, 190, 181–190. [Google Scholar] [CrossRef] [Green Version]
  15. Qadrdan, M.; Abeysekera, M.; Chaudry, M.; Wu, J.; Jenkins, N. Role of power-to-gas in an integrated gas and electricity system in Great Britain. Int. J. Hydrogen Energy 2015, 40, 5763–5775. [Google Scholar] [CrossRef]
  16. Zhang, R.F.; Jiang, T.; Li, G.Q.; Chen, H.H.; Li, X.; Ning, R.X. Bi-Level Optimization Dispatch of Integrated Electricity-Natural Gas Systems Considering P2G for Wind Power Accommodation. Proc. CSEE 2018, 38, 5668–5678. [Google Scholar]
  17. Zhang, X.; Shahidehpour, M.; AlAbdulwahab, A.S.; Abusorrah, A. Security-Constrained Co-Optimization Planning of Electricity and Natural Gas Transportation Infrastructures. IEEE Trans. Power Syst. 2015, 30, 2984–2993. [Google Scholar] [CrossRef]
  18. Barati, F.; Seifi, H.; Sepasian, M.S.; Nateghi, A.; Shafie-Khah, M.; Catalão, J.P.S. Multi-Period Integrated Framework of Generation, Transmission, and Natural Gas Grid Expansion Planning for Large-Scale Systems. IEEE Trans. Power Syst. 2015, 30, 2527–2537. [Google Scholar] [CrossRef]
  19. Qiu, J.; Dong, Z.Y.; Zhao, J.H.; Xu, Y.; Zheng, Y.; Li, C.; Wong, K.P. Multi-Stage Flexible Expansion Co-Planning Under Uncertainties in a Combined Electricity and Gas Market. IEEE Trans. Power Syst. 2015, 30, 2119–2129. [Google Scholar] [CrossRef]
  20. Chaudry, M.; Jenkins, N.; Qadrdan, M.; Wu, J. Combined gas and electricity network expansion planning. Appl. Energy 2014, 113, 1171–1187. [Google Scholar] [CrossRef]
  21. Ameli, H.; Qadrdan, M.; Strbac, G.; Ameli, M.T. Investing in flexibility in an integrated planning of natural gas and power systems. IET Energy Syst. Integr. 2020, 2, 101–111. [Google Scholar] [CrossRef]
  22. Zhu, L.; Wang, J.; Tang, L.J.; Shen, L.; Chao, H. Robust Stochastic Optimal Dispatching of Integrated Energy Systems Considering Refined Power-to-Gas Model. Power System Technol. 2019, 43, 116–126. [Google Scholar]
  23. Qiu, J.; Dong, Z.Y.; Zhao, J.H.; Meng, K.; Zheng, Y.; Hill, D.J. Low Carbon Oriented Expansion Planning of Integrated Gas and Power Systems. IEEE Trans. Power Syst. 2014, 30, 1035–1046. [Google Scholar] [CrossRef]
  24. Grüger, F.; Hoch, O.; Hartmann, J.; Robinius, M.; Stolten, D. Optimized electrolyzer operation: Employing forecasts of wind energy availability, hydrogen demand, and electricity prices. Int. J. Hydrogen Energy 2019, 44, 4387–4397. [Google Scholar] [CrossRef]
  25. Moskalenko, N.; Lombardi, P.A.; Komarnicki, P. Multi-criteria optimization for determining installation locations for the power-to-gas technologies. In Proceedings of the 2014 IEEE PES General Meeting|Conference & Exposition, Washington, DC, USA, 27–31 July 2014; pp. 1–5. [Google Scholar]
  26. Hu, F.; Lv, H.; Tuzikov, A.V. Multi-objective cooperative control based on evolutionary process optimization of immune algorithm. Serv. Oriented Comput. Appl. 2020, 14, 153–160. [Google Scholar] [CrossRef]
  27. Pan, G.; Li, K.; Ouyang, A.; Li, K. Hybrid immune algorithm based on greedy algorithm and delete-cross operator for solving TSP. Soft Comput. 2014, 20, 555–566. [Google Scholar] [CrossRef]
  28. Liang, X.; Huang, M.; Ning, T. Flexible job shop scheduling based on improved hybrid immune algorithm. J. Ambient Intell. Humaniz. Comput. 2018, 9, 165–171. [Google Scholar] [CrossRef]
  29. Dai, Y.S.; Li, Y.Y.; Wei, L.; Junling, W.; Deling, Z. Adaptive Immune-Genetic Algorithm for Global Optimization to Multivariable Function. J. Syst. Eng. Electron. 2007, 18, 655–660. [Google Scholar]
  30. Liu, C.; Shahidehpour, M.; Fu, Y.; Li, Z. Security-Constrained Unit Commitment With Natural Gas Transmission Constraints. IEEE Trans. Power Syst. 2009, 24, 1523–1536. [Google Scholar] [CrossRef]
  31. Ramachandran, B.; Srivastava, S.K.; Edrington, C.S.; Cartes, D.A. An Intelligent Auction Scheme for Smart Grid Market Using a Hybrid Immune Algorithm. IEEE Trans. Ind. Electron. 2011, 58, 4603–4612. [Google Scholar] [CrossRef]
  32. Carrano, E.; Guimaraes, F.G.; Takahashi, R.; Neto, O.M.; Campelo, F. Electric Distribution Network Expansion Under Load-Evolution Uncertainty Using an Immune System Inspired Algorithm. IEEE Trans. Power Syst. 2007, 22, 851–861. [Google Scholar] [CrossRef]
  33. Hu, Y.; Bie, Z.H.; Li, G.F.; Ding, T.; Lian, H. Integrated Planning of Natural Gas Network and Composite Power System. Proc. CSEE 2017, 37, 45–54. [Google Scholar]
  34. Hu, X.; Zhang, H.; Chen, D.; Li, Y.; Wang, L.; Cheng, H. Multi-objective planning for integrated energy systems considering both exergy efficiency and economy. Energy 2020, 197, 117155. [Google Scholar] [CrossRef]
Figure 1. The flow chart of the algorithm.
Figure 1. The flow chart of the algorithm.
Energies 14 03400 g001
Figure 2. Example structure.
Figure 2. Example structure.
Energies 14 03400 g002
Figure 3. Planning grid under scenario 1.
Figure 3. Planning grid under scenario 1.
Energies 14 03400 g003
Figure 4. Planning grid under scenario 2.
Figure 4. Planning grid under scenario 2.
Energies 14 03400 g004
Figure 5. Immune evolution verification curves at 12:00 and 00:00.
Figure 5. Immune evolution verification curves at 12:00 and 00:00.
Energies 14 03400 g005
Figure 6. Hourly operation cost comparison.
Figure 6. Hourly operation cost comparison.
Energies 14 03400 g006
Table 1. Comparisons of planning results.
Table 1. Comparisons of planning results.
Planning Units and LinesScenario 1Scenario 2
Additional units(G1, G2, G3) = (#2, #1, #2)(G1, G2, G3, P1) = (#3, #3, #3, #1)
The new line2–8, 4–92–7, 1–4, 4–9
The new pipeA and B, B–D, B–E, D–G, C–E, E–F, A–G1, D–G2, E–G3A and B, B–D, D–G, E–F, A–G1, D–G2, E–G3
Table 2. Comparisons of planning costs (units: million $).
Table 2. Comparisons of planning costs (units: million $).
Planning CostsScenario 1Scenario 2
Total investment cost of gas pipelines450330
Total investment cost of power lines480830
Total investment cost of gas unit and P2G plant station6941446
Annual investment cost114.8179.1
Annual operating cost115.9110.5
Annual total cost230.7289.6
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Xing, J.; Wu, P. Optimal Planning of Electricity-Natural Gas Coupling System Considering Power to Gas Facilities. Energies 2021, 14, 3400. https://doi.org/10.3390/en14123400

AMA Style

Xing J, Wu P. Optimal Planning of Electricity-Natural Gas Coupling System Considering Power to Gas Facilities. Energies. 2021; 14(12):3400. https://doi.org/10.3390/en14123400

Chicago/Turabian Style

Xing, Jie, and Peng Wu. 2021. "Optimal Planning of Electricity-Natural Gas Coupling System Considering Power to Gas Facilities" Energies 14, no. 12: 3400. https://doi.org/10.3390/en14123400

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop