Next Article in Journal
System Design and Energy Management for a Fuel Cell/Battery Hybrid Forklift
Previous Article in Journal
Solving the Multi-Objective Optimal Power Flow Problem Using the Multi-Objective Firefly Algorithm with a Constraints-Prior Pareto-Domination Approach
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Integrated Optimal Dispatch of a Rural Micro-Energy-Grid with Multi-Energy Stream Based on Model Predictive Control

1
College of Information and Electrical Engineering, China Agricultural University, Beijing 100083, China
2
School of Information Engineering, Inner Mongolia University of Science & Technology, Baotou 014010, China
3
State Grid Gansu Electric Power Company, Lanzhou 730050, China
*
Author to whom correspondence should be addressed.
Energies 2018, 11(12), 3439; https://doi.org/10.3390/en11123439
Submission received: 13 November 2018 / Revised: 3 December 2018 / Accepted: 5 December 2018 / Published: 8 December 2018

Abstract

:
Due to the randomness of the intermittent distributed energy output and load demand of a micro-energy-grid, micro-sources cannot fully follow the day-ahead micro-energy-grid optimal dispatching plan. Therefore, a micro-energy-grid is difficult to operate steadily and is challenging to include in the response dispatch of a distribution network. In view of the above problems, this paper proposes an integrated optimal dispatch method for a micro-energy-grid based on model predictive control. In the day-ahead optimal dispatch, an optimal dispatch model of a micro-energy-grid is built taking the daily minimum operating cost as the objective function, and the optimal output curve of each micro-source of the next day per hour is obtained. In the real-time dispatch, rolling optimization of the day-ahead optimal dispatching plan is implemented based on model predictive control theory. The real-time state of the system is sampled, and feedback correction of the system is implemented. The influence of uncertain factors in the system is eliminated to ensure steady operation of the system. Finally, the validity and feasibility of the integrated optimal dispatching method are verified by a case simulation analysis.

1. Introduction

With the gradual depletion of energy and increasingly salient environmental problems, the proportion of renewable energy consumption is increasing. All the countries in the world give an increased importance to renewable energy technology research. Renewable energy technology has become a hot topic in the energy field [1,2,3,4]. American futurist Jeremy Rifkin proposes the concept of the energy Internet [5]. Scholars promote the transformation of smart grids to the energy Internet [6,7,8,9], focusing not only on the clean utilization of electricity but also on the integrated utilization of cooling-–heating-electricity-gas energy [10,11,12,13,14,15]. Then, the concept of micro-energy-grid is proposed. The micro-energy-grid is the natural extension of the microgrid. As a subsystem of the energy Internet, the micro-energy-grid is composed mainly of an electric power grid, a cooling and heating energy grid, a gas grid and other energy streams. The micro-energy-grid is applied in urban communities, industrial parks, rural areas and other areas. The micro-energy-grid uses electricity-heating-cooling storage and achieves conversion of cooling-heating-electricity-gas multi-energy, which is the main way to consume renewable energy [16,17]. Rural areas in China are rich in biomass energy, which has caused serious environmental pollution. At the same time, the utilization efficiency of biomass energy is low. Renewable energy is abundant in rural areas of China, but the existing rural power grid is weak, and photovoltaic (PV) and wind power poverty alleviation facilities are insufficient. Therefore, the study of the rural micro-energy-grid optimal dispatch can achieve local rational utilization of biomass energy and renewable energy and improve the rural environment. Therefore, the micro-energy-grid is of great significance to the construction and development of new countryside.
Researchers working on the optimal dispatch of the microgrid have conducted substantial research [18,19,20,21,22,23,24]. For example, in [18], a bilevel optimal algorithm for microgrid clusters based on the alternating direction method of multipliers is proposed to achieve coordinated optimization for a multi-microgrid. In [19], a multi-objective optimal dispatching method for an isolated microgrid considering flexibility is proposed to improve the ability of the system to address the uncertainty of PV and wind power. In [20,21], the optimal operation methods for a microgrid are proposed based on the improved adaptive evolutionary algorithm and swarm optimization algorithm. In [22], considering the uncertain factors of renewable energy generation and price, a dispatching method of a reconfigurable microgrid based on uncertainty risk is proposed to achieve the benefit maximization of microgrid operators. In [23], an alternating direction method of multipliers based distributed algorithm is proposed to solve the economic dispatch model of the islanded microgrids. In [24], considering the random charging influence of electric vehicles on the microgrid, a multi-objective optimal dispatching model based on improved particle swarm optimization is proposed. Three different dispatching scenarios are established, and the corresponding dispatching results are discussed. Finally, the validity of the model is verified by case study. However, the above references focus on electric energy. The typical scenario of a cooling-heating-electricity-gas multi-energy stream micro-energy-grid is not considered. In [25], the day-ahead optimal dispatching model of the micro-energy-grid based on an energy hub is built to achieve optimal operation of the cooling-heating-electricity-gas multi-energy stream. In [26], a non-cooperative game model of micro-energy-grid and user is established based on game theory, and a method for solving the game model is proposed to achieve the economic operation of the micro-energy-grid. In [27], a two-stage stochastic mixed-integer linear programming model is proposed for the optimal dispatch of the micro-energy-grid. In [28], considering the demand-side response, a bilevel optimal scheduling model of the micro energy network based on the load aggregator business is proposed and verified by simulation. In [29,30], the optimal dispatching model of a PV agricultural greenhouse micro-energy-grid is proposed to simultaneously maximize the PV energy consumption and heat the greenhouse. Although the abovementioned references have achieved the day-ahead optimal dispatch of the cooling-heating-electricity-gas micro-energy-grid, the micro-sources cannot fully follow the day-ahead optimal dispatching plan of the micro-energy-grid due to the randomness of the intermittent distributed energy output and load demand. Thus, the operating results may not match the actual operation of the system. The micro-energy-grid is difficult to operate smoothly, and participation of the grid in the response dispatch of the distribution network is challenging.
In general, the recent studies have the following problems. (1) The research objective relates to the single-energy network represented by electrical energy. The demand of coordinated utilization of cooling-heating-electricity-gas multi-energy stream is difficult to satisfy. (2) Some of the above references study cooling-heating-electricity-gas multi-energy stream and achieve the day-ahead optimal dispatch of the cooling-heating-electricity-gas micro-energy-grid. However, due to the randomness of the intermittent distributed energy output and load demand, the micro-sources cannot fully follow the day-ahead optimal dispatching plan of the micro-energy-grid. Thus, the operating results may not match the actual operation of the system. The micro-energy-grid is difficult to operate smoothly, and participation in the response dispatch of the distribution network is challenging. (3) The research on rural micro-energy-grids is beneficial for achieving local rational utilization of biomass energy and renewable energy. However, few studies of micro-energy-grids in rural areas of China have been reported.
In response to the above problems, this paper makes the following contributions:
(1)
The energy-supply architecture of the micro-energy-grid, including wind, PV, micro-turbine, and other micro-sources, is built, and the demand of cooling-heating-electricity load is considered.
(2)
An integrated optimal dispatching method based on model predictive control for the micro-energy-grid, which divides the optimal dispatching process into the day-ahead optimal dispatch and the real-time optimal dispatch, is proposed. In the day-ahead optimal dispatch, the optimal dispatch model of the micro-energy-grid is built taking the daily minimum operating cost as the objective function, and the hourly optimal output curve of each micro-source in the next day is obtained. In the real-time optimal dispatch, based on the model predictive control theory, taking the day-ahead optimal dispatching results as the reference values, intraday multi-period rolling optimization and sampling real-time system state for feedback correction are conducted.
(3)
In this study, the energy-supply architecture of the proposed energy grid is suitable for the rural areas of China. Biogas, PV energy and other biomass and renewable energy sources are used to achieve the integrated utilization of all kinds of resources in rural areas.
The remainder of this paper is structured as follows: Section 2 establishes the energy-supply architecture of the micro-energy-grid and presents the components and operating mechanism of the micro-energy-grid. In Section 3, an integrated dispatching framework of the micro-energy-grid is built based on model predictive control, and the integrated dispatching method of the micro-energy-grid is outlined. In Section 4, an integrated optimal dispatching model of the micro-energy-grid, including the day-ahead and real-time optimal dispatching model, is built. In Section 5, a case study is used to validate the proposed model. The full paper is summarized and future work is predicted in Section 6. The general workflow of the integrated optimal dispatch of the rural micro-energy-grid with multi-energy stream based on model predictive control is shown in Figure 1.

2. Components and Energy-Supply Mechanism of Rural Micro-Energy-Grid

In this paper, the cooling-heating-electricity-gas multi-energy stream micro-energy-grid includes wind and PV power generation system, micro-turbine, biogas-fired boiler, heat-recovery boiler, lithium-bromide absorption-type refrigerators, battery storage device, cooling and heating storage device, and air-source heat pump. The energy-supply architecture of the system is shown in Figure 2.
The micro-energy-grid is connected to the external distribution network. When the electricity energy supply of the micro-turbine, wind and PV power generation system is larger than the internal electrical load, electrical energy is sold to the external distribution network, and the battery is charged. When the electricity energy supply of the abovementioned device is less than the internal electrical load, electrical energy is purchased from the external distribution network, and the battery storage is discharged. The function of the battery storage device is peak load shifting. The heating load is satisfied by the heat-recovery boiler, biogas-fired boiler and air-source heat pump. The raw material of the heating device is provided by the biogas generated by biomass waste and rural natural air. When the heating energy supply of the micro-energy-grid exceeds the internal heating load, the heating storage device is charged. When the heating energy supply of the micro-energy-grid is less than the internal heating load, the heating storage device is discharged. The function of the heating storage is peak load shifting. The cooling load is satisfied by the lithium-bromide absorption-type refrigerator and air-source heat pump. When the cooling energy supply of the micro-energy-grid exceeds the internal cooling load, the cooling storage device is charged. When the cooling energy supply of the micro-energy-grid is less than the internal cooling load, the cooling storage device is discharged. The function of the cooling storage is peak load shifting.

3. Integrated Optimal Dispatching Framework of the Micro-Energy-Grid Based on Model Predictive Control

The accurate curves of the intermittent renewable energy output and load demand are built by the accurate prediction. However, as the predictive time scale increases, the predictive accuracy of the wind and PV power generation system decreases, as well as the load, resulting in a large deviation between the day-ahead optimal dispatching strategy and actual operation, which cannot satisfy the actual dispatching requirement of the system. Thus, an integrated optimal dispatching method for the micro-energy-grid based on model predictive control is proposed in this paper. The integrated optimal dispatch includes the day-ahead optimal dispatch and real-time optimal dispatch. The integrated optimal dispatching framework of the micro-energy-grid is shown in Figure 3.
(1) Day-ahead optimal dispatch
Based on the day-ahead predictive curve of the wind and PV power generation system as well as load, and considering the characteristics of each micro-source and the relevant constraints, the daily minimum operating cost of the micro-energy-grid is taken as the objective function. The hourly optimal output curve of each micro-source in the next day is obtained. The charge and discharge curves of the energy storage device and the hourly power exchange curve of the micro-energy-grid and the distribution network in the next day are also obtained.
(2) Real-time optimal dispatch
Rolling optimization of the intraday real-time optimal dispatching plan is performed by taking 5 min as a period to eliminate the actual intraday operating deviation caused by the large predictive error, and the ultra-short-term predictive information of the wind and PV power generation system as well as load is considered simultaneously. Based on model predictive control theory, the correction plans of all the micro-sources in the time window (the time window includes many periods) are obtained. In each time segment, the corrected dispatching plan of the next period is issued. In the next 5-min period, the above-mentioned process will be repeated, and the operating state of the system is sampled in real time to implement the feedback correction of the system.

4. Integrated Optimal Dispatching Model of the Rural Micro-Energy-Grid

4.1. Day-Ahead Optimal Dispatching Model

In this study, the biogas is provided by the rural biogas supply station. The sources of the raw materials are rural straw, animal waste and other kinds of biomass waste. Therefore, the daily operating cost of the proposed rural micro-energy-grid includes mainly the cost of purchasing electricity from the distribution network and selling electricity to the distribution network, the converting cost of environment pollution, the maintenance cost of the system, and the cost of purchasing biogas. The daily minimum operating cost of the micro-energy-grid is taken as the objective function in the day-ahead optimal dispatch. The objective function is as follows:
min C = min ( C elertri + C maintain + C pollution + C gas + C estor )
C elertri = t = 1 24 ( e 1 ( t ) + e 2 ( t ) 2 P ex ( t ) + e 1 ( t ) e 2 ( t ) 2 | P ex ( t ) | e 3 ( t ) ( P PV ( t ) + P WT ( t ) ) e 4 ( t ) P MT ( t ) )
C maintain = t = 1 24 C mEB P EB ( t ) + t = 1 24 C mGB P GB ( t ) + t = 1 24 C mWT P WT ( t ) + t = 1 24 C mAC P AC ( t ) + t = 1 24 C mASHP P CASHP ( t ) + t = 1 24 C mcstor | P cstor ( t ) | + t = 1 24 C mMT P MT ( t ) + t = 1 24 C mPV P PV ( t ) + t = 1 24 C mASHP P HASHP ( t ) + t = 1 24 C mhstor | P hstor ( t ) |
C pollution = y = 1 m ( C y + D y ) B y ( P MT ( t ) + P GB ( t ) )
C gas = C fuel ( P MT ( t ) + P GB ( t ) )
C estor = t = 1 24 ( C mestor 1 + C mestor 2 ) | P estor ( t ) |
The constraint conditions that must be satisfied by the day-ahead optimal dispatch are as follows:
(1)
Electrical power balance constraint condition:
P estor ( t ) + P MT ( t ) + P ex ( t ) = P electriload ( t ) + P ASHP ( t ) P WT ( t ) P PV ( t )
(2)
Heating power balance constraint condition:
P HASHP ( t ) + P EB ( t ) + P GB ( t ) + P hstor ( t ) = P heatingload ( t )
(3)
Cooling power balance constraint condition:
P CASHP ( t ) + P AC ( t ) + P cstor ( t ) = P coolingload ( t )
(4)
Micro-turbine constraint conditions:
0 P MT ( t ) P MT max
R MT down P MT ( t ) P MT ( t 1 ) R MT up
(5)
Heat-recovery boiler constraint conditions:
P EB ( t ) = P MT ( t ) ( 1 η e η 1 ) η rec η EB η e
0 P EB ( t ) P EB max
(6)
Biogas-fired boiler constraint conditions:
0 P GB ( t ) P GB max
R GB down P GB ( t ) P GB ( t 1 ) R GB up
(7)
Lithium-bromide absorption-type refrigerator constraint conditions:
P AC ( t ) = P MT ( t ) ( 1 η e η 1 ) η rec η AC η EB η e
0 P AC ( t ) P AC max
(8)
Cooling-heating-electricity storage device constraint conditions:
Because the functions and principles of the battery storage device and the cooling and heating storage device are similar, their general models are as follows:
S stor ( t ) = S stor ( t 1 ) ( 1 δ ) + Δ T P ch ( t ) η ch / E tstor Δ T P dis ( t ) / ( η dis E tstor )
S stor min S stor ( t ) S stor max
S stor ( 0 ) = S stor ( T )
0 P dis ( t ) P dmax
0 P ch ( t ) P cmax
P stor ( t ) = { P ch ( t ) , P stor ( t ) 0 P dis ( t ) , P stor ( t ) < 0
(9)
Air-source heat pump constraint conditions:
P HASHP ( t ) = D HASHP P ASHP ( t )
P CASHP ( t ) = D CASHP P ASHP ( t )
0 P ASHP ( t ) P ASHP max
(10)
Power exchange between the micro-energy-grid and the distribution network constraint condition:
P ex min P ex ( t ) P ex max
(11)
Reserve power constraint condition:
P WT max + P PV max + P MT max + P ex max P electriload ( t ) ( 1 + Y res )

4.2 Real-Time Optimal Dispatching Model

Model predictive control is a closed-loop optimal control method that includes model prediction, rolling optimization and feedback correction. This strategy includes the following steps. (1) At current time k and current state x ( k ) , the future state of the system is predicted based on the predictive model. Based on the above analytical results, considering the current and future constraints, the control order sequence of the future time k + Δ t , k + 2 Δ t , ... , k + N Δ t is obtained by solving the optimization control objective function. (2) The first value of the control instruction sequence is applied to the control system. (3) At time k + Δ t , the state is updated to x ( k + Δ t ) , and the above steps are repeated. In this paper, an intraday real-time optimal dispatching model is built to achieve the optimal coordinated intraday dispatch of each micro-source based on model predictive control theory.

4.2.1. Predictive Model

The control variables are obtained by solving the rolling optimization model. The output curves of the micro-source and storage are predicted in the future time-limited region. The specific predictive model is as follows:
{ P EB ( k + n Δ t ) = P EB ( k ) + t = Δ t n Δ t Δ P EB ( k + t ) P GB ( k + n Δ t ) = P GB ( k ) + t = Δ t n Δ t Δ P GB ( k + t ) P AC ( k + n Δ t ) = P AC ( k ) + t = Δ t n Δ t Δ P AC ( k + t ) P MT ( k + n Δ t ) = P MT ( k ) + t = Δ t n Δ t Δ P MT ( k + t ) P ASHP ( k + n Δ t ) = P ASHP ( k ) + t = Δ t n Δ t Δ P ASHP ( k + t ) P estor ( k + n Δ t ) = P estor ( k ) + t = Δ t n Δ t Δ P estor ( k + t ) P cstor ( k + n Δ t ) = P cstor ( k ) + t = Δ t n Δ t Δ P cstor ( k + t ) P hstor ( k + n Δ t ) = P hstor ( k ) + t = Δ t n Δ t Δ P hstor ( k + t ) S estor ( k + n Δ t ) = ( 1 σ estor ) S estor ( k + ( n 1 ) Δ t ) Δ T η estor E testor P estor ( k + n Δ t ) S cstor ( k + n Δ t ) = ( 1 σ cstor ) S cstor ( k + ( n 1 ) Δ t ) Δ T η cstor E tcstor P cstor ( k + n Δ t ) S hstor ( k + n Δ t ) = ( 1 σ hstor ) S hstor ( k + ( n 1 ) Δ t ) Δ T η hstor E thstor P hstor ( k + n Δ t ) P ex ( k + n Δ t ) = P ex ( k ) t = Δ t n Δ t Δ P MT ( k + t ) t = Δ t n Δ t Δ P estor ( k + t ) t = Δ t n Δ t Δ P WT ( k + t ) t = Δ t n Δ t Δ P PV ( k + t ) + t = Δ t n Δ t Δ P electriload ( k + t ) + t = Δ t n Δ t Δ P ASHP ( k + t ) n = 1 , 2 , , N

4.2.2. Objective Function (Rolling Optimization)

In this paper, the minimum variations in the intraday power exchange between the micro-energy-grid and the distribution network, the state of charge of the cooling-heating-electricity storage device, and the energy-supply units are taken as the objective function. The real-time optimal dispatching model is built based on model predictive control. The objective function is as follows:
min J = t = Δ t N Δ t ( P ex ( k + t ) P ex ( k + t ) ) 2 + t = Δ t N Δ t ( S estor ( k + t ) S estor ( k + t ) ) 2 + t = Δ t N Δ t ( S cstor ( k + t ) S cstor ( k + t ) ) 2 + t = Δ t N Δ t ( S hstor ( k + t ) S hstor ( k + t ) ) 2 + t = Δ t N Δ t ( P estor ( k + t ) P estor ( k + t ) ) 2 + t = Δ t N Δ t ( P cstor ( k + t ) P cstor ( k + t ) ) 2 + t = Δ t N Δ t ( P hstor ( k + t ) P hstor ( k + t ) ) 2 + t = Δ t N Δ t ( P EB ( k + t ) P EB ( k + t ) ) 2 + t = Δ t N Δ t ( P GB ( k + t ) P GB ( k + t ) ) 2 + t = Δ t N Δ t ( P AC ( k + t ) P AC ( k + t ) ) 2 + t = Δ t N Δ t ( P MT ( k + t ) P MT ( k + t ) ) 2 + t = Δ t N Δ t ( P ASHP ( k + t ) P ASHP ( k + t ) ) 2
When rolling optimization is performed, the system state is sampled in real time, which is equivalent to a certain amount of feedback correction effect. The constraint conditions that must be satisfied by the real-time optimal dispatch are as follows:
(1) The controllable unit constraint conditions:
{ Δ P EB min Δ P EB ( k + t ) Δ P EB max Δ P GB min Δ P GB ( k + t ) Δ P GB max Δ P AC min Δ P AC ( k + t ) Δ P AC max Δ P MT min Δ P MT ( k + t ) Δ P MT max Δ P ASHP min Δ P ASHP ( k + t ) Δ P ASHP max 0 P EB ( k + n Δ t ) P EB max 0 P GB ( k + n Δ t ) P GB max 0 P AC ( k + n Δ t ) P AC max 0 P MT ( k + n Δ t ) P MT max 0 P ASHP ( k + n Δ t ) P ASHP max n = 1 , 2 , , N
(2) The electricity–cooling–heating storage device constraint conditions:
{ Δ P estor min Δ P estor ( k + t ) Δ P estor max Δ P cstor min Δ P cstor ( k + t ) Δ P cstor max Δ P hstor min Δ P hstor ( k + t ) Δ P hstor max P estor min P estor ( k + n Δ t ) P estor max P cstor min P cstor ( k + n Δ t ) P cstor max P hstor min P hstor ( k + n Δ t ) P hstor max S estor min S estor ( k + n Δ t ) S estor max S cstor min S cstor ( k + n Δ t ) S cstor max S hstor min S hstor ( k + n Δ t ) S hstor max n = 1 , 2 , , N

4.3. Integrated Optimal Dispatching Model Solution

The solution steps of the integrated optimal dispatch of rural micro-energy-grid based on model predictive control are shown in Figure 4.
(1)
The daily minimum operating cost of the rural micro-energy-grid is taken as the objective function, and the day-ahead optimal dispatching model of the rural micro-energy-grid is built. The problem is solved using the particle swarm algorithm, and the hourly optimal dispatching output curves in the next day are obtained for each micro-source.
(2)
The power output curves of the micro-sources in the day-ahead optimal dispatch are taken as the reference values. The real-time optimal dispatching model is built based on model predictive control. The active power output variations of the micro-sources in the next N time are obtained by the sequential quadratic programming algorithm.
(3)
The power output variations of the micro-sources at time k + Δ t are issued, and the active power output curves of the micro-sources at time k + Δ t are obtained.
(4)
The actual power output curves of the micro-sources at time k + Δ t are taken as the initial values of the real-time optimal dispatching model. The process then returns to Step 2, and a new round of optimization is performed.

5. Case Study

A village in western China was taken as a case. According to the actual situation of the region, electrical and heating energy are supplied in winter, and electrical and cooling energy are supplied in summer. The electricity price of the power grid is based on the time-of-use electrical price issued by Gansu Province Development and Reform Commission in China. Electricity is sold to the distribution network at a price of 0.65 (RMB·(kW·h)−1). The purchasing price of biogas is 0.35 (RMB·(kW·h)−1). The value of the power generation efficiency of the micro-turbine η e is 0.26, the value of the heating loss coefficient of the micro-turbine η 1 is 0.03, and the value of the recovery efficiency of the flue gas waste heat η rec is 0.55 [31]. The lithium battery storage device was adopted in this case study. The cost for storing energy in lithium battery is 0.2 (RMB·(kW·h)−1). The parameters of the energy-supply device [32,33] are shown in Table 1. The maintenance costs [32,34,35] for the energy-supply device are shown in Table 2. The parameters of the electricity–cooling–heating storage device [32] are shown in Table 3. The electricity selling prices of the PV, wind and micro-turbine power generation system are shown in Table 4. The electricity selling price of the PV and wind power generation system contains government subsidy. The related parameters of environmental pollution are in [35]. The time-of-use electrical price of the power grid is shown in Figure 5. The predictive data of the wind and PV power generation system and the cooling-heating-electricity load were obtained by Monte Carlo simulation [36,37] of the day-ahead optimal dispatch. The predictive results of the day-ahead optimal dispatch are shown in Figure 6. To reflect the universality of the test parameters, the intraday ultra-short-term prediction data are the sum of the day-ahead predictive value and the predictive error, which has a normal distribution. The intraday ultra-short-term predictive results of the real-time optimal dispatch are shown in Figure 7. The parameters of the particle swarm algorithm were as follows: number of particles, 20; number of iterations, 50; learning factor, 2; period of the day-ahead optimal dispatch, 1 h; predictive and control times, 60 min; and period of rolling optimal dispatch, 5 min.

5.1. The Results of Day-Ahead Optimal Dispatch

The electrical load balance curves of a typical day in winter (Figure 8a) and summer (Figure 8b) under day-ahead optimal dispatching mode are shown in Figure 8. The output power curves of the micro-sources in winter and summer are similar. Therefore, Figure 8a is taken as an illustrative example. According to Figure 8a, during Periods 23–24 and 0–7, because the price of electricity is at the lowest point and is lower than the price of biogas, wind energy and the electricity purchased from the distribution network are used to satisfy the electrical load demand, and the battery storage device is fully charged. Battery storage is used to improve the economy of the system. In Periods 7–23, the price of electricity price is at the highest and exceeds the price of the biogas. The electricity purchasing cost of the micro-energy-grid is relatively high. Therefore, the micro-turbine, PV and wind power generation system become the main electricity-supply units. The battery storage device is discharged to satisfy the electrical load demand if the above units cannot satisfy the demand. The battery storage device is charged during periods of low electricity prices and low loads. The battery storage device is discharged in periods of high electricity prices and high loads. The function of the battery storage device, which is peak load shifting, is achieved, and the economy of the system is improved.
The heating load balance curves of a typical day in winter (Figure 9a) and the cooling load balance curves of a typical day in summer (Figure 9b) under day-ahead optimal dispatching mode are shown in Figure 9. The output power curves of the micro-sources for the heating load in winter are similar to those of the micro-sources for the cooling load in summer. Therefore, Figure 9a is taken as an illustrative example. According to Figure 9a, during Periods 23–24 and 0–7, the price of electricity is at the lowest point of the day. The air-source heat pump and biogas-fired boiler are used to satisfy the heating load demand, and the heating storage device is fully charged. During Periods 7–23, the price of electricity is at the highest point of the day, and the heat-recovery boiler becomes the main heating-supply unit because insufficient electricity is supplied by the heating storage device and biogas-fired boiler. The heating storage device is charged during periods of low electricity prices and discharged during periods of high electricity prices to satisfy the demand of the system.

5.2. The Results of Real-Time Optimal Dispatch

The electrical load balance curves of a typical day in winter (Figure 10a) and summer (Figure 10b) under real-time optimal dispatching mode are shown in Figure 10. According to Figure 8, the day-ahead optimal dispatch plan takes an hour as the time scale, but the dispatch is extensive. The predictive error of renewable energy and electrical load and the influence of unplanned instantaneous power fluctuation on the control of the micro-energy-grid are not fully reflected. The system cannot respond to fluctuations in the renewable energy and load in time. According to Figure 10, the day-ahead optimal dispatch is improved upon by the real-time optimal dispatch. The real-time optimal dispatch is more accurate than the day-ahead optimal dispatch, and the output power of each electricity-supply unit has small fluctuation. The real-time optimal dispatch is more in line with the actual situation. Because the power of each electricity-supply unit has only a small change, safe operation of the system is guaranteed; meanwhile, the renewable energy and electrical load fluctuation are considered. Therefore, the micro-energy-grid can operate smoothly.
The heating load balance curves of a typical day in winter (Figure 11a) and the cooling load balance curves of a typical day in summer (Figure 11b) under real-time optimal dispatching mode are shown in Figure 11. Similar to Figure 10, the state of the energy-supply units related to the heating load (Figure 11a) in winter and cooling load (Figure 11b) in summer follows the operating strategy of the day-ahead optimal dispatch. Compared with the day-ahead optimal dispatch in Figure 9, the output power of each energy-supply unit is accurate, and the power variation of each energy-supply unit is smaller. Thus, safe operation of the system is guaranteed. The system can respond quickly to changes in cooling and heating loads, thereby further improving the applicability of the system.

5.3. Comparison of Optimal Results between the Day-Ahead Optimal Dispatch and the Real-Time Optimal Dispatch

The comparison of electricity-supply units (Figure 12a) and heating-supply units (Figure 12b) in winter between the day-ahead optimal dispatch and real-time optimal dispatch are shown in Figure 12. The comparison of electricity-supply units (Figure 13a) and cooling-supply units (Figure 13b) in summer between the day-ahead optimal dispatch and real-time optimal dispatch are shown in Figure 13. Compared with the day-ahead predictive data for the wind and PV power generation system, and the cooling-heating-electricity load in Figure 6, the intraday ultra-short-term predictive data for the wind and PV power generation system, and the cooling-heating-electricity load in Figure 7 has small fluctuations. The day-ahead predictive data are used in the day-ahead optimal dispatch, and the intraday ultra-short-term predictive data are used in the real-time optimal dispatch. According to the comparison of optimal results between the day-ahead optimal dispatch and the real-time optimal dispatch in Figure 12 and Figure 13, the energy-supply units in the real-time optimal dispatch can respond to the power variations of the wind and PV power generation system, and the cooling-heating-electricity load in real time. The validity of proposed method in this paper is further verified.

6. Conclusions

An integrated optimal dispatching method based on model predictive control for a rural micro-energy-grid is proposed in this paper to address the randomness of the intermittent distributed energy output and load demand. The integrated optimal dispatching method includes the day-ahead optimal dispatch and real-time optimal dispatch. In the day-ahead optimal dispatch, the optimal dispatch model of the micro-energy-grid is built taking the daily minimum operating cost as the objective function, and the output power curve of each micro-source is obtained on an hourly time scale. In the real-time optimal dispatch, the rolling optimization of the day-ahead optimal dispatching plan is implemented based on model predictive control theory. The real-time state of the system is sampled, and feedback correction of the system is implemented to achieve smooth operation of the system. According to the simulated case study, the state of the energy-supply units in the micro-energy-grid maintains the operating strategy of the day-ahead optimal dispatch. The output power of each energy-supply unit is accurate, and output power variables of the units are small. The safe operation of the system is guaranteed, and the system can respond rapidly to fluctuations in the output power of renewable energy and the electricity-cooling-heating load. The applicability of the system is further extended.
In the next step, intraday ultra-short-term renewable energy generation and prediction of electricity-cooling-heating load are strengthened, and the optimal dispatching model of the micro-energy-grid is more detailed. The operating dispatching plan more closely fits the actual operating conditions of the system to promote the rapid development of micro-energy-grid technology.

Author Contributions

J.Y. and M.Z. proposed the topic of the study and designed the research framework. T.J. and X.Z. established mathematical model of study and performed case simulation. W.W. analyzed the data. X.Z. wrote the final paper.

Funding

This research was funded by the Headquarters Science and Technology Projects from the State Grid Corporation of China (Grant No. 5227221600KQ).

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

Variables
C electri difference between the cost of purchasing electricity and the income of selling electricity for the micro-energy-grid
C maintain maintenance cost of the micro-energy-grid
C pollution cost of environmental pollution
C gas cost of purchasing biogas
e 1 ( t ) electricity purchasing price of the micro-energy-grid
e 2 ( t ) electricity selling price of the micro-energy-grid
P ex ( t ) power exchange between the micro-energy-grid and the distribution network (purchasing electricity power is positive, and selling electricity power is negative)
P EB ( t ) heating power of the heat-recovery boiler
P GB ( t ) heating power of the biogas-fired boiler
P estor ( t ) electrical power of the battery storage device (discharge is negative and charge is positive)
P MT ( t ) electrical power of the micro-turbine
P PV ( t ) electrical power of the PV power generation system
P WT ( t ) electrical power of the wind power generation system
P AC ( t ) cooling power of the lithium-bromide absorption-type refrigerator
P hstor ( t ) heating power of the heating storage device (discharge is negative, and charge is positive)
P cstor ( t ) cooling power of the cooling storage device (discharge is negative, and charge is positive)
P electriload ( t ) electrical load
P ASHP ( t ) electrical power of the air-source heat pump
P CASHP ( t ) cooling power of the air-source heat pump
P HASHP ( t ) heating power of the air-source heat pump
P heatingload ( t ) heating load
P coolingload ( t ) cooling load
C fuel biogas price
C y penalty of pollutant gas y
D y environmental value of pollutant gas y
B y emission value of pollutant gas y
m type of pollutant gas
C mEB maintenance cost of the heat-recovery boiler
C mGB maintenance cost of the biogas-fired boiler
C mestor 1 cost for storing energy in the battery storage device
C mestor 2 daily manual maintenance cost of the battery storage device
C mMT maintenance cost of the micro-turbine
C mPV maintenance cost of the PV power generation system
C mWT maintenance cost of the wind power generation system
C mAC maintenance cost of the lithium-bromide absorption-type refrigerators
C mASHP maintenance cost of the air-source heat pump
C mhstor maintenance cost of the heating storage device
C mcstor maintenance cost of the cooling storage device
P MT max maximum electrical power of the micro-turbine
P EB max maximum heating power of the heat-recovery boiler
P GB max maximum heating power of the biogas-fired boiler
P AC max maximum cooling power of the lithium-bromide absorption-type refrigerator
R MT down downward climbing speed of the micro-turbine
R MT up upward climbing speed of the micro-turbine
R GB down downward climbing speed of the biogas-fired boiler
R GB up upward climbing speed of the biogas-fired boiler
η e value of the power generation efficiency of the micro-turbine
η 1 value of the heating loss coefficient of the micro-turbine
η rec value of the recovery efficiency of the flue gas waste heat
η EB efficiency of the heat-recovery boiler
η AC efficiency of the lithium-bromide absorption-type refrigerator
S stor ( t ) state of charge of the cooling–heating–electricity storage device
δ self-discharging efficiency of the cooling–heating–electricity storage device
P ch ( t ) charging power of the cooling–heating–electricity storage device
P dis ( t ) discharging power of the cooling–heating–electricity storage device
η ch charging efficiencies of the cooling–heating–electricity storage device
η dis discharging efficiencies of the cooling–heating–electricity storage device
Δ T dispatching period
E tstor total capacity of the cooling–heating–electricity storage device
S stor min minimum state of charge of the cooling–heating–electricity storage device
S stor max maximum state of charge of the cooling–heating–electricity storage device
P cmax maximum charging power of the cooling–heating–electricity storage device
P dmax maximum discharging power of the cooling–heating–electricity storage device
P stor charging and discharging power of the cooling–heating–electricity storage device
D CASHP cooling efficiency of the air-source heat pump
D HASHP heating efficiency of the air-source heat pump
P ASHP max maximum electrical power of the air-source heat pump
P ex min minimum power exchange between the micro-energy-grid and the distribution network
P ex max maximum power exchange between the micro-energy-grid and the distribution network
Y res system reserve rate
Δ P EB ( k + t ) power variation in the heat-recovery boiler
Δ P GB ( k + t ) power variation in the biogas-fired boiler
Δ P AC ( k + t ) power variation in the lithium-bromide absorption-type refrigerator
Δ P MT ( k + t ) power variation in the micro-turbine
Δ P ASHP ( k + t ) power variation in the air-source heat pump
Δ P WT ( k + t ) power variation in the wind power generation system
Δ P PV ( k + t ) power variation in the PV generation system
Δ P electriload ( k + t ) power variation in the electrical load
C estor cost for storing energy in the battery storage device
e 3 ( t ) electricity selling price of the PV and wind power generation system
e 4 ( t ) electricity selling price of the micro-turbine
P ex ( k + t ) power exchange between the micro-energy-grid and the distribution network in the day-ahead optimal dispatch
P estor ( k + t ) charging and discharging power of the battery storage device in the day-ahead optimal dispatch
S estor ( k + t ) state of charge of the battery storage device in the day-ahead optimal dispatch
P cstor ( k + t ) charging and discharging power of the cooling storage device in the day-ahead optimal dispatch
S cstor ( k + t ) state of charge of the cooling storage device in the day-ahead optimal dispatch
P hstor ( k + t ) charging and discharging power of the heating storage device in the day-ahead optimal dispatch
S hstor ( k + t ) state of charge of the heating storage device in the day-ahead optimal dispatch
P EB ( k + t ) power of the heat-recovery boiler in the day-ahead optimal dispatch
P GB ( k + t ) power of the biogas-fired boiler in the day-ahead optimal dispatch
P AC ( k + t ) power of the lithium-bromide absorption-type refrigerator in the day-ahead optimal dispatch
P MT ( k + t ) power of the micro-turbine in the day-ahead optimal dispatch
P ASHP ( k + t ) power of the air-source heat pump in the day-ahead optimal dispatch
Δ P EB min minimum power variation in the heat-recovery boiler
Δ P EB max maximum power variation in the heat-recovery boiler
Δ P GB min minimum power variation in the biogas-fired boiler
Δ P GB max maximum power variation in the biogas-fired boiler
Δ P AC min minimum power variation in the lithium-bromide absorption-type refrigerator
Δ P AC max maximum power variation in the lithium-bromide absorption-type refrigerator
Δ P MT min minimum power variation in the micro-turbine
Δ P MT max maximum power variation in the micro-turbine
Δ P ASHP min minimum power variation in the air-source heat pump
Δ P ASHP max maximum power variation in the air-source heat pump
Δ P estor min minimum charging and discharging power variation in the battery storage device
Δ P estor max maximum charging and discharging power variation in the battery storage device
Δ P cstor min minimum charging and discharging power variation in the cooling storage device
Δ P cstor max maximum charging and discharging power variation in the cooling storage device
Δ P hstor min minimum charging and discharging power variation in the heating storage device
Δ P hstor max maximum charging and discharging power variation in the heating storage device
P estor max maximum charging and discharging power of the battery storage device
P estor min minimum charging and discharging power of the battery storage device
P cstor max maximum charging and discharging power of the cooling storage device
P cstor min minimum charging and discharging power of the cooling storage device
P hstor max maximum charging and discharging power of the heating storage device
P hstor min minimum charging and discharging power of the heating storage device
S estor min minimum state of charge of the battery storage device
S estor max maximum state of charge of the battery storage device
S cstor min minimum state of charge of the cooling storage device
S cstor max maximum state of charge of the cooling storage device
S hstor min minimum state of charge of the heating storage device
S hstor max maximum state of charge of the heating storage device
E testor total capacity of electricity storage device
E tcstor total capacity of cooling storage device
E thstor total capacity of heating storage device
σ estor self-discharging efficiency of the battery storage device
σ cstor self-discharging efficiency of the cooling storage device
σ hstor self-discharging efficiency of the heating storage device
η estor charging and discharging efficiency of the battery storage device
η cstor charging and discharging efficiency of the cooling storage device
η hstor charging and discharging efficiency of the heating storage device
Abbreviations
PVphotovoltaic

References

  1. He, Y.B.; Yan, M.Y.; Shahidehpour, M.; Li, Z.Y.; Guo, C.X.; Wu, L.; Ding, Y. Decentralized optimization of multi-area electricity-natural gas flows based on cone reformulation. IEEE Trans. Power Syst. 2018, 33, 4531–4542. [Google Scholar] [CrossRef]
  2. Rashidi, H.; Khorshidi, J. Exergoeconomic analysis and optimization of a solar based multigeneration system using multiobjective differential evolution algorithm. J. Clean. Prod. 2018, 170, 978–990. [Google Scholar] [CrossRef]
  3. Li, Y.; Yang, Z.; Li, G.Q.; Zhao, D.B.; Tian, W. Optimal scheduling of an isolated microgrid with battery storage considering load and renewable generation uncertainties. IEEE Trans. Ind. Electron. 2019, 66, 1565–1575. [Google Scholar] [CrossRef]
  4. Hosseinzadeh, M.; Salmasi, F.R. Fault-tolerant supervisory controller for a hybrid ac/dc micro-grid. IEEE Trans. Smart Grid 2018, 9, 2809–2823. [Google Scholar] [CrossRef]
  5. Jeremy, R. Third Industrial Revolution: How Lateral Power Is Transforming Energy, the Economy, and the World; Palgrave Macmillan Trade: New York, NY, USA, 2011; pp. 33–72. [Google Scholar]
  6. Fu, X.Q.; Zhang, X.R. Failure probability estimation of gas supply using the central moment method in an integrated energy system. Appl. Energy 2018, 219, 1–10. [Google Scholar] [CrossRef]
  7. Li, Z.M.; Xu, Y. Optimal coordinated energy dispatch of a multi-energy microgrid in grid-connected and islanded modes. Appl. Energy 2018, 210, 974–986. [Google Scholar] [CrossRef]
  8. Mi, Y.; Liu, H.Y.; Song, G.X.; Li, Z.Q.; Fu, Y.; Li, Z.K. Two-layer power optimization allocation of multi-energy local networks oriented to energy internet. Power Autom. Equip. 2018, 38, 1–10. [Google Scholar]
  9. Ding, T.; Mu, C.L.; Bie, Z.H.; Du, P.W.; Fan, Z.Y.; Zou, Z.X.; Yang, Y.H.; Wu, Z.Y.; Xu, Y.; Tang, B.G. Review of energy internet and its operation. Proc. CSEE 2018, 38, 4318–4328. [Google Scholar]
  10. Chen, S.; Wei, Z.N.; Sun, G.G.; Sun, Y.L.; Zang, H.X.; Zhu, Y. Optimal power and gas how with a limited number of control actions. IEEE Trans. Smart Grid 2018, 9, 5371–5380. [Google Scholar] [CrossRef]
  11. Habibollahzade, A.; Gholamian, E.; Ahmadi, P.; Behzadi, A. Multi-criteria optimization of an integrated energy system with thermoelectric generator, parabolic trough solar collector and electrolysis for hydrogen production. Int. J. Hydrog. Energy 2018, 43, 14140–14157. [Google Scholar] [CrossRef]
  12. Qiu, J.; Zhao, J.H.; Yang, H.M.; Wang, D.X.; Dong, Z.Y. Planning of solar photovoltaics, battery energy storage system and gas micro turbine for coupled micro energy grids. Appl. Energy 2018, 219, 361–369. [Google Scholar] [CrossRef]
  13. Meesenburg, W.; Ommen, T.; Elmegaard, B. Dynamic exergoconomic analysis of a heat pump system used for ancillary services in an integrated energy system. Energy 2018, 152, 154–165. [Google Scholar] [CrossRef]
  14. Li, S.X.; Hu, M.H.; Gong, C.C.; Zhan, S.; Qin, D.T. Energy Management Strategy for Hybrid Electric Vehicle Based on Driving Condition Identification Using KGA-Means. Energies 2018, 11, 1531. [Google Scholar] [CrossRef]
  15. Hosseinzadeh, M.; Salmasi, F.R. Robust Optimal Power Management System for a Hybrid AC/DC Micro-Grid. IEEE Trans. Sustain. Energy 2015, 6, 675–687. [Google Scholar] [CrossRef]
  16. Zhang, X.; Yang, J.H.; Wang, W.Z.; Jing, T.J.; Zhang, M. Optimal operation analysis of the distribution network comprising a micro energy grid based on an improved grey wolf optimization algorithm. Appl. Sci. 2018, 8, 923. [Google Scholar] [CrossRef]
  17. Chan, D.; Cameron, M.; Yoon, Y. Implementation of micro energy grid: A case study of a sustainable community in China. Energy Build. 2017, 139, 719–731. [Google Scholar] [CrossRef]
  18. Wang, H.; Ai, Q.; Wu, J.H.; Xie, Y.Z.; Zhou, X.Q. Bi-level distributed optimization for microgrid clusters based on alternating direction method of multipliers. Power Syst. Technol. 2018, 42, 1718–1727. [Google Scholar]
  19. Yang, L.J.; Li, H.Q.; Yu, X.Y.; Zhao, J.S.; Liu, W.Y. Multi-objective day-ahead optimal scheduling of isolated microgrid considering flexibility. Power Syst. Technol. 2018, 42, 1432–1440. [Google Scholar]
  20. Bharothu, J.N.; Sridhar, M.; Rao, R.S. Modified adaptive differential evolution based optimal operation and security of AC-DC microgrid systems. Int. J. Electr. Power Energy Syst. 2018, 103, 185–202. [Google Scholar] [CrossRef]
  21. Gao, R.; Wu, J.; Hu, W.; Zhang, Y. An improved ABC algorithm for energy management of microgrid. Int. J. Comput. Commun. Control 2018, 13, 477–491. [Google Scholar] [CrossRef]
  22. Hemmati, M.; Mohammadi-Ivatloo, B.; Ghasemzadeh, S.; Reihani, E. Risk- based optimal scheduling of reconfigurable smart renewable energy based microgrids. Int. J. Electr. Power Energy Syst. 2018, 101, 415–428. [Google Scholar] [CrossRef]
  23. Chen, G.; Yang, Q. An ADMM-based distributed algorithm for economic dispatch in islanded microgrids. IEEE Trans. Ind. Inform. 2018, 14, 3892–3903. [Google Scholar] [CrossRef]
  24. Lu, X.H.; Zhou, K.L.; Yang, S.L.; Liu, H.Z. Multi-objective optimal load dispatch of microgrid with stochastic access of electric vehicles. J. Clean. Prod. 2018, 195, 187–199. [Google Scholar] [CrossRef]
  25. Ma, T.F.; Wu, J.Y.; Hao, L.L. Energy flow modeling and optimal operation analysis of the micro energy grid based on energy hub. Energy Convers. Manag. 2017, 133, 292–306. [Google Scholar] [CrossRef]
  26. Lin, K.J.; Wu, J.Y.; Hao, L.L.; Liu, D.; Li, D.Z.; Yan, H.G. Optimization of operation strategy for micro-energy grid with cchp systems based on non-cooperative game. Autom. Electr. Power Syst. 2018, 42, 25–32. [Google Scholar]
  27. Ghasmi, A.; Banejad, M.; Rahimiyan, M. Integrated energy scheduling under uncertainty in a micro energy grid. IET Gener. Transm. Distrib. 2018, 12, 2887–2896. [Google Scholar] [CrossRef]
  28. Li, D.Z.; Wu, J.Y.; Shi, K.; Ma, T.F.; Zhang, Y.; Zhang, R.Y. Bi-level optimal dispatch model for micro energy grid based laod aggregator business. In Proceedings of the 2017 IEEE Conference on Energy Internet and Energy System Integration (EI2), Beijing, China, 26–28 November 2017; pp. 643–648. [Google Scholar]
  29. Wang, W.Z.; Liu, F.C.; Zheng, J.J.; Yanf, Y.; Zhang, J.H.; Yang, J.H.; Jing, T.J. Optimal regulation on micro energy grid based on time-shifting agricultural load. In Proceedings of the 2017 IEEE Conference on Energy Internet and Energy System Integration (EI2), Beijing, China, 26–28 November 2017; pp. 42–47. [Google Scholar]
  30. Wang, Y.Z.; Niu, H.N.; Yang, L.; Wang, W.Z.; Liu, F.C. An optimization method for local consumption of photovoltaic powr in a facility agriculture micro energy network. Energies 2018, 11, 1503. [Google Scholar] [CrossRef]
  31. Wu, X.; Wang, X.L.; Bie, Z.H.; Wang, J.X. Economic operation of microgrid with combined heat and power system. Electr. Power Autom. Equip. 2013, 33, 1–6. [Google Scholar]
  32. Xu, Q.S.; Zeng, A.D.; Wang, K.; Jiang, L. Day-ahead optimized economic dispatching for combined cooling, heating and power in micro energy-grid based on hessian interior point method. Power Syst. Technol. 2016, 40, 1657–1665. [Google Scholar]
  33. Zhao, J.; Yang, H.H.; Ye, D.F.; Qing, W.C. Research on energy system based on CCHP coupled with energy storage. Energy Convers. Technol. 2016, 34, 120–124. [Google Scholar]
  34. Wang, C.; Gu, W.; Wu, Z. Economic and optimal operation of a combined heat and power micro grid with renewable energy resources. Autom. Electr. Power Syst. 2011, 35, 22–27. [Google Scholar]
  35. Ma, X.Y.; Wu, Y.W.; Fang, H.L.; Sun, Y.Z. Optimal sizing of hybrid solar-wind distributed generation in an islanded microgrid using improved bacterial foraging algorithm. Proc. CSEE 2011, 31, 17–25. [Google Scholar]
  36. Xian, X.; Fan, C.G.; Wen, S.S.; Wang, Y.C.; Chen, C.; Liu, X. Optimal deployment for island microgrid considering probabilistic factors of renewable energy generations. Eng. J. Wuhan Univ. 2016, 49, 101–104. [Google Scholar]
  37. Pazouki, S.; Haghifam, M.R.; Moser, A. Uncertainty modeling in optimal operation of energy hub in presence of wind, storage and demand response. Int. J. Electr. Power Energy Syst. 2014, 61, 335–345. [Google Scholar] [CrossRef]
Figure 1. General workflow for the integrated optimal dispatch of the rural micro-energy-grid with multi-energy stream based on model predictive control.
Figure 1. General workflow for the integrated optimal dispatch of the rural micro-energy-grid with multi-energy stream based on model predictive control.
Energies 11 03439 g001
Figure 2. Energy-supply architecture of the micro-energy-grid.
Figure 2. Energy-supply architecture of the micro-energy-grid.
Energies 11 03439 g002
Figure 3. Integrated optimal dispatching framework of the rural micro-energy-grid.
Figure 3. Integrated optimal dispatching framework of the rural micro-energy-grid.
Energies 11 03439 g003
Figure 4. Integrated optimal dispatching solution workflow of the rural micro-energy-grid.
Figure 4. Integrated optimal dispatching solution workflow of the rural micro-energy-grid.
Energies 11 03439 g004
Figure 5. Time-of-use electrical price curve of the power grid.
Figure 5. Time-of-use electrical price curve of the power grid.
Energies 11 03439 g005
Figure 6. The day-ahead predictive data of the wind and PV power generation system, and the cooling-heating-electricity load in: winter (a); and summer (b).
Figure 6. The day-ahead predictive data of the wind and PV power generation system, and the cooling-heating-electricity load in: winter (a); and summer (b).
Energies 11 03439 g006aEnergies 11 03439 g006b
Figure 7. Intraday ultra-short-term predictive data of the wind and PV power generation system, and the cooling-heating-electricity load in: winter (a); and summer (b).
Figure 7. Intraday ultra-short-term predictive data of the wind and PV power generation system, and the cooling-heating-electricity load in: winter (a); and summer (b).
Energies 11 03439 g007
Figure 8. The electrical load balance curves of a typical day in winter (a) and summer (b) under day-ahead optimal dispatching mode.
Figure 8. The electrical load balance curves of a typical day in winter (a) and summer (b) under day-ahead optimal dispatching mode.
Energies 11 03439 g008
Figure 9. The heating load balance curves of a typical day in winter (a) and the cooling load balance curves of a typical day in summer (b) under day-ahead optimal dispatching mode.
Figure 9. The heating load balance curves of a typical day in winter (a) and the cooling load balance curves of a typical day in summer (b) under day-ahead optimal dispatching mode.
Energies 11 03439 g009
Figure 10. The electrical load balance curves of a typical day in winter (a) and summer (b) under real-time optimal dispatching mode.
Figure 10. The electrical load balance curves of a typical day in winter (a) and summer (b) under real-time optimal dispatching mode.
Energies 11 03439 g010
Figure 11. The heating load balance curves of a typical day in winter (a) and the cooling load balance curves of a typical day in summer (b) under real-time optimal dispatching mode.
Figure 11. The heating load balance curves of a typical day in winter (a) and the cooling load balance curves of a typical day in summer (b) under real-time optimal dispatching mode.
Energies 11 03439 g011
Figure 12. Comparison of electricity-supply units (a) and heating-supply units (b) in winter between the day-ahead optimal dispatch and the real-time optimal dispatch.
Figure 12. Comparison of electricity-supply units (a) and heating-supply units (b) in winter between the day-ahead optimal dispatch and the real-time optimal dispatch.
Energies 11 03439 g012
Figure 13. Comparison of electricity-supply units (a) and cooling-supply units (b) in summer between the day-ahead optimal dispatch and real-time optimal dispatch.
Figure 13. Comparison of electricity-supply units (a) and cooling-supply units (b) in summer between the day-ahead optimal dispatch and real-time optimal dispatch.
Energies 11 03439 g013aEnergies 11 03439 g013b
Table 1. Parameters of the energy-supply device of the micro-energy-grid.
Table 1. Parameters of the energy-supply device of the micro-energy-grid.
DeviceParameterValue
Micro turbine(six)Maximum generated power (kW·one−1)100
Rated efficiency0.26
Climbing speed (kW·min−1)Upward 30, Downward 20
Heat-recovery boilerMaximum input power (kW)900
Rated efficiency0.9
Lithium-bromide absorption-type refrigeratorMaximum input power (kW)900
Rated efficiency1.2
Biogas-fired boilerMaximum input power (kW)500
Rated efficiency0.8
Climbing speed (kW·min−1)Upward 30, Downward 20
Air-source heat pumps for heating and cooling exchangeMaximum heating and cooling exchange power (kW)1000
Heating and cooling efficiency parameter3.7
Power exchange between micro-energy-grid with external power gridMaximum exchange power (kW)1000
PV power generation systemMaximum generated power (kW)300
Wind power generation systemMaximum generated power (kW)100
Table 2. Maintenance costs of the energy-supply device.
Table 2. Maintenance costs of the energy-supply device.
DeviceMaintenance Cost (RMB·(kW·h)−1)
Micro turbine0.03
Heat-recovery boiler0.02
Lithium-bromide absorption-type refrigerator0.025
Biogas-fired boiler0.02
Air-source heat pump0.02
PV power generation system0.03
Wind power generation system0.03
Battery storage device0.03
Heating storage device0.02
Cooling storage device0.02
Table 3. Parameters of electricity–cooling–heating storage device.
Table 3. Parameters of electricity–cooling–heating storage device.
Storage Device ParameterElectricity-Cooling-Heating EfficiencySelf-Discharging Efficiency of Cooling-Heating-ElectricityState of Charge of Cooling-Heating-ElectricityCapacity (kW·h)
Max ChargeMax DischargeMaximumMinimum
Battery storage device0.20.20.020.90.21000
Heating storage device0.20.20.030.90.11000
Cooling storage device0.20.20.030.90.11000
Table 4. Electricity selling price of the PV, wind and micro-turbine power generation system.
Table 4. Electricity selling price of the PV, wind and micro-turbine power generation system.
DevicePrice (RMB·(kW·h)−1)
Micro turbine0.2610 (23:00–24:00, 00:00–07:00)
0.5100 (07:00–08:00, 11:00–18:00)
0.7590 (08:00–11:00, 18:00–23:00)
PV and wind power generation system0.8610 (23:00–24:00, 00:00–07:00)
1.1100 (07:00–08:00, 11:00–18:00)
1.3590 (08:00–11:00, 18:00–23:00)

Share and Cite

MDPI and ACS Style

Zhang, X.; Yang, J.; Wang, W.; Zhang, M.; Jing, T. Integrated Optimal Dispatch of a Rural Micro-Energy-Grid with Multi-Energy Stream Based on Model Predictive Control. Energies 2018, 11, 3439. https://doi.org/10.3390/en11123439

AMA Style

Zhang X, Yang J, Wang W, Zhang M, Jing T. Integrated Optimal Dispatch of a Rural Micro-Energy-Grid with Multi-Energy Stream Based on Model Predictive Control. Energies. 2018; 11(12):3439. https://doi.org/10.3390/en11123439

Chicago/Turabian Style

Zhang, Xin, Jianhua Yang, Weizhou Wang, Man Zhang, and Tianjun Jing. 2018. "Integrated Optimal Dispatch of a Rural Micro-Energy-Grid with Multi-Energy Stream Based on Model Predictive Control" Energies 11, no. 12: 3439. https://doi.org/10.3390/en11123439

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop