Previous Article in Journal
On the Aerodynamic Characteristics of the Aurel Persu Car
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Proceeding Paper

Increasing Renewable Energy Penetration Using Energy Storage †

by
Alexandros Angeloudis
,
Angela Peraki
,
Yiannis Katsigiannis
* and
Emmanuel Karapidakis
Department of Electrical and Computer Engineering, Hellenic Mediterranean University, 71410 Heraklion, Greece
*
Author to whom correspondence should be addressed.
Presented at the 6th International Conference on Communications, Information, Electronic and Energy Systems, Ruse, Bulgaria, 26–28 November 2025.
Eng. Proc. 2026, 122(1), 27; https://doi.org/10.3390/engproc2026122027 (registering DOI)
Published: 21 January 2026

Abstract

Greenhouse gas emissions are a primary contributor to climate change and the observed rise in global temperatures. To reduce these emissions, renewable energy sources (RESs) must replace fossil fuels in power generation. Because of the mismatch between production and demand, the increase in RES is limited. To address this phenomenon, the addition of renewable energy generation should be accompanied by storage systems. In this paper, the island of Crete is examined for various renewable energy generations and storage capacities using the PowerWorld Simulator software. Four main scenarios are studied in which the installed renewable energy generation is increased to reach substation limits. For every scenario, different renewable energy generation mixes are considered between wind farms and photovoltaics. Furthermore, for all sub-scenarios, different storage capacities are considered, ranging from 1.6 GWh to 12.8 GWh. This study proves that storage systems are mandatory to increase renewable energy penetration. In certain scenarios, a battery energy storage system can further increase renewable energy penetration from 6.15% to 28.07%. Although the battery energy storage system enhanced renewable penetration, increasing transmission line capacities should also be considered regarding the scenario.

1. Introduction

Climate change is a global issue and a top priority for both the European Union and Greece. In order to reduce the impact of climate change, greenhouse gas (GHG) emissions must be minimized. Greece’s Ministry of Environment and Energy have a long-term goal to decrease total emissions to about 13 Mt CO2eq until 2050 [1]. According to recent data, in Greece, total GHG emissions were 70.6 Mt CO2eq in 2023. More specifically, the power industry sector accounted for 20.68% of the total GHG emissions [2]. In the same year, fossil fuels contributed 42.97% of the total energy mix with 10.13% from lignite and 32.84% from natural gas [3]. It is also important to mention that by 2028 energy production from lignite would be discontinued. For the reasons outlined above, the increased use of renewable energy sources (RESs) is of utmost importance for electricity production. Due to stability issues and their intermittent nature, RES expansion is limited. To address this, RES growth should be accompanied by the installation of energy storage systems (ESSs).
One of the main challenges associated with RES is the mismatch in timing between renewable energy generation and energy demand. With regard to energy storage, the power system not only achieves greater stability and reliability but also enhances efficiency by saving potential wasted energy from RES. According to a study concerning the power system of Jeju Island, South Korea, covering the period from 2015 to 2019, with the addition of 50 MW battery energy storage system (BESS) to a power system with 580 MW installed RES capacity, it has been demonstrated that renewable energy curtailment was reduced by 15% [4]. Over the years, a variety of energy storage technologies have been developed, including lithium-ion batteries, hydrogen-based storage and pumped hydro storage.
Chemical batteries are the leading technology for grid-scale energy storage applications, with efficiency levels reaching 95% [5]. However, serious concerns have been raised regarding the environmental impacts at the end of their lifecycle [6]. Regarding green hydrogen, excess energy from RES is utilized to generate hydrogen via water electrolysis and then the produced hydrogen is stored under appropriate pressure and temperature conditions. Subsequently, using a fuel cell, the hydrogen is converted back to electricity [7]. Although it produces almost zero emissions, such a process is considerably less efficient than accumulating energy in a chemical battery. An additional energy storage technology is pumped hydro storage, in which surplus electricity is used to pump water into the hydropower reservoir, enabling the generation of electricity when needed, through hydroelectric power [8]. Regarding Greece’s energy storage development, it is planned to have 1.5 GW of installed storage capacity by the end of 2030 mainly focused on pumped hydro storage according to International Energy Agency [9].
In this study, the island of Crete is examined due to its unique characteristics in the Greek power system. As a result of its location, Crete has significant wind and solar potential. However, despite these resources, RES deployment in Crete has still not reached its peak for reasons mentioned above. To address this, two interconnections with Greek mainland are being implemented. The first (small) interconnection connects Chania with the Peloponnese region; this interconnection is the deepest HVAC submarine line in the world and has a capacity of 2 × 200 MVA. The second (big) interconnection will connect Athens with Heraklion via an HVDC line with capacity of 2 × 500 MW. The small interconnection is currently being operated with a 150 MW limit, and the big interconnection is expected to be partially operated in the first months of 2026. Figure 1 shows these two interconnections, the high-voltage (HV) substations of the island (triangles with solid lines), as well as the planned new substations (triangles with dotted lines) [10].
The main objective of this paper is to highlight the need for further integration of RES into the Greek power system in order to reduce GHG emissions. Equally important is demonstrating how and why ESSs are essential to achieving this goal. A key challenge lies in determining which RES technology photovoltaic or wind power should be prioritized and to what extent. By carrying out this analysis, the study identifies the most suitable combination of RES technologies and ESS characteristics for effective and sustainable integration into the power system.
In the following section, four main scenarios are evaluated using the PowerWorld Simulator’s optimal power flow (OPF) algorithm for Crete’s HV power system over a one-year period. More specifically, the scenarios assume that installed RES capacity accounts for 35%, 50%, 75%, and 100% of the substation’s total power capacity, respectively. For each scenario, four sub-scenarios are evaluated: the first scenario reflects the current photovoltaic (PV) to wind turbine (WT) ratio; the second considers a 1:1 ratio; the third emphasizes PV capacity; and the fourth prioritizes WT capacity. For each sub-scenario, RES penetration is first assessed without battery storage. Battery storage is then introduced, and its capacity is progressively increased up to 12.8 GWh. Furthermore, several representative scenarios will be selected and simulated in the PowerWorld simulator (educational license, v.23, Champaign, IL, USA) using time step simulation, focusing on technical constraints and additional losses.

2. Methodology

2.1. Description of Cretan Power System

Before proceeding, it is important to clarify the concept of energy curtailment and the role of energy storage in reducing it. Figure 2 presents the load curve for a period between 22 March and 23 March 2023. This figure also illustrates the energy production from 200 MW PV parks and 600 MW wind farms (WFs) as well as the combined output from both RES. The PVs produce energy between 05:00 and 17:00, while wind energy exhibits a more irregular pattern. When RES generates less energy than the demand, all available RES output is fully utilized. However, when RES production exceeds demand, as observed during hours 4–13 and 29–37, the surplus energy must be curtailed. With the addition of ESS, when storage capacity is available, excess electricity is stored. Subsequently, during periods when the demand needs exceed RES production, the stored energy can be discharged to cover demand, thereby reducing the need for conventional generation and increasing RES penetration. It should be noted that technical limitations such as line and transformer capacities or system stability constraints are not considered, which could further influence curtailment levels. If these limitations were considered, ESS would further facilitate RES penetration.
As previously discussed in the Introduction, the electrical power system of Crete will be examined. The following tables and graphical representations provide important data regarding Crete’s power system. In Figure 3, Crete’s load duration curve is illustrated for the year 2023. The previous figure also depicts the duration curve of both WFs and PVs.
In Table 1, data for Crete’s nineteen substations are presented. These data include the nominal power of high- or medium-voltage (MV) transformers, peak load, and the installed capacity for both PVs and WTs. In Table 2, data refer to Crete’s seven power plants (PPs). It is important to mention that each PP is composed of smaller sub-power plants of the same technology but with lower nominal power. The total nominal power is calculated by adding the total nominal power of each sub-power plant. On the other hand, the technical minimum results from the sub-power plant with the least technical minimum power.

2.2. Considered Scenarios

As mentioned above, four main scenarios will be examined which are focused on the installed RES capacity. The capacity considered is 35%, 50%, 75%, and 100% of total substation installed power. As of 2025, the installed RES capacity is 19.25%. The rationale behind not exceeding installed power capacity of substations is to prevent energy from remaining unutilized energy due to transformer limitations. For each one of these four scenarios, four sub-scenarios are analyzed, examining the impact of the different mix between PV and WTs and taking into account the differences in their generation profile. The mixes that are considered in installed power between PVs and WTs are as follows: 50–50%, 20–80%, 80–20%, and 65–35% (which is the current mix). Furthermore, for each of the developed sub-scenarios, more cases are considered regarding the BESS installation. First, the system will be analyzed without a BESS. In all subsequent cases, a BESS with a power rating of 1.6 GW—equal to the total substations’ capacity—will be considered. The BESS discharge duration will gradually increase from 1 h to 8 h, resulting in total battery capacities ranging from 1.6 GWh to 12.8 GWh, in increments of 1.6 GWh. It is also important to mention that the BESS that is assessed is a Li-ion battery with an efficiency of 95% [5].
In Figure 4, the amount of energy produced by RES is calculated at any given time. The RES generates sufficient energy to cover as much of the load as possible. In cases where surplus energy is available and the battery has remaining capacity, RES produces additional energy to fully charge the battery. The load does not represent the actual electrical demand of Crete, but a slightly lower value, as a small part of the load must be provided by conventional power plant due to stability reasons. The aforementioned load is calculated to be approximately 50 MW and is supplied by the Atherinolakos power station.
Figure 5 shows the computed battery energy level at each time step. Charging occurs whenever there is available storage capacity and when there is excess energy from the RES at the same time, whereas discharging takes place when PV is insufficient to satisfy the load demand.
In Figure 6, the battery losses are calculated, specifically the losses arising throughout charging and discharging. It is worth noting that the battery losses were modeled as the total discharging losses.
Figure 7 illustrates how energy is drawn from the small interconnection to meet Crete’s electrical demand. The small interconnection does not supply the entire remaining load on its own; instead, it operates in combination with local power plants. In this analysis, the load is assumed to be shared equally (50–50%) between the two sources. However, it should be noted that the current maximum transfer capacity of the small interconnection is 150 MW.
Figure 8 presents the contribution of Crete’s local power plants in fulfilling the electrical demand. The local power plants supply the remaining load after the initial utilization of the RES, followed by the batteries and finally the small interconnection. The total power of power plants is consistently sufficient to meet the demand; thus, monitoring generation limits is not required.
In Figure 9, the electrical energy curtailments are determined for conditions in which the RES output surpasses load demand as well as the available battery storage capacity.
After completing the previous algorithms, the results from the selected scenarios will be used as inputs to the PowerWorld Simulator. PowerWorld simulator is a software tool specialized in modeling and analysis of power systems’ operation. In this research, Crete’s HV system will be modeled with the addition of BESS. Figure 10 presents the HV system of Crete Island, which contains the 19 buses described in Table 1, as well as the other small interconnection bus that is located in Peloponnese (top left corner). Furthermore, a yearly simulation will be implemented through PowerWorld simulator’s time step simulation feature using the OPF algorithm in each iteration, which calculates the most cost-effective unit commitment under specific technical constraints (including power and voltage limits). By employing the PowerWorld simulator and OPF algorithm, the grid topology is considered, demonstrating a more realist approach since it accounts for fuel curves of PPs and the system’s technical limitations such as line capacities.
The scenarios that will be implemented in the PowerWorld simulator will be based on different installed RES capacities with the optimal ESS. Moreover, the share between WFs and PV parks will be chosen based on which option maximizes RES penetration.

3. Results and Discussion

This section presents the results of the above scenarios. The following figures illustrate the RES penetration under different energy mix scenarios, the impact of BESS on curtailment reduction, the associated energy losses, and the loading of transmission lines. The first set of figures (Figure 11, Figure 12, Figure 13 and Figure 14) presents the RES percentage on total electricity generation for various storage capacities and different RES combinations between PVs and WFs. It is worth mentioning that the first set of figures does not account for the renewable energy generation in northern Greece, which is supplied to Crete’s power system via the small interconnection. The share of energy supplied through this interconnection ranges from 2% to 20% to Crete’s total demand, depending on the scenario. Considering that approximately 40% of this imported energy is produced from RES [3], the total renewable energy contribution can be increased by a maximum of 16%, depending on scenario.
In Figure 11, the first scenario is presented. In this scenario, the impact of energy storage is minimal since the energy produced from RES is almost always lower than the energy demand. The energy mix that focuses on WFs (red line) has an overall better penetration which can be attributed to its power generation curves, as previously illustrated in Figure 2. Additionally, in Figure 11, the current energy penetration from RES is also depicted (light blue line).
In Figure 12, the second scenario is presented, which illustrates the impact of BESS in RES penetration. An ESS with a capacity of 1.6 GWh can reduce energy rejections and further increase the RES penetration by 6% in the sub-scenario that emphasizes generation via PV (blue line). Moreover, increasing the BESS capacity beyond this point yields only marginal improvements in RES penetration and is therefore not economically justified when considering the associated installation, operation, and maintenance costs. It is also important to note that, as in the previous scenario, the sub-scenario that focuses on wind energy (red line) rather than solar energy (blue line) can increase RES penetration by 13% for reasons that were mentioned in Scenario 1.
Figure 13 presents the results for Scenario 3. There are two key differences between Scenarios 2 and 3. First, a 6.4 GWh BESS is identified as optimal due to the higher levels of energy curtailment. Second, in this scenario, a wind-dominated energy mix is no longer clearly the most effective configuration. All the sub-scenarios have comparable RES penetration levels when BESSs are included, except for the sub-scenario that focuses on PV (blue line) which shows significantly lower penetration than the rest of sub-scenarios. This suggests that, in order to increase RES penetration in Crete’s energy mix, the installation of RES technologies should primarily focus on WFs, followed by additional PV capacity expansion.
In Figure 14, the final scenario is depicted. In this scenario, the RES penetration converges to approximately 82%, regardless of the sub-scenario. The optimal storage capacity ranges between 6.4 GWh and 9.6 GWh. The BESS installation has more impact on the sub-scenario that focuses on solar energy (blue line), leading to a further 28.07% increase in RES penetration. It is important to note that RES penetration cannot exceed approximately 85% due to system stability reasons and the requirement for reactive power, which is primarily provided by synchronous generators such as conventional units. WFs and PV systems cannot supply sufficient inertia and are almost incapable of generating reactive power.
Furthermore, to better understand the effect of storage capacity on renewable energy utilization, Figure 15 presents the curtailed energy of Scenario 3. In this figure, the impact of BESS in reducing energy curtailment can be observed, as a 9.6 GWh BESS has the potential to store and utilize up to 700 GWh of energy that would otherwise be dissipated.
In the following figures, energy losses and transmission constraints will be depicted based on six specific cases. Two cases were implemented for each of Scenario 1, Scenario 2, and Scenario 3. The first case of each scenario does not include a BESS, while the second incorporates a BESS with optimal capacity. The corresponding optimal capacities were 1.6 GWh, 3.2 GWh, and 6.4 GWh for Scenarios 1, 2, and 3, respectively, as determined from results presented in Figure 11, Figure 12 and Figure 13. In all cases, the generation mix emphasizes wind power, reflecting the higher penetration of RES.
Figure 16 presents the system loss results obtained from the PowerWorld simulator. In all simulation cases, the addition of a BESS reduced transmission losses, as expected [11]. However, despite the decrease in transmission losses, the total system losses increased due to higher utilization of the storage system.
After analyzing the system losses under different cases, the next step focuses on the loading of transmission lines, as illustrated in Table 3. The line loading for each case was calculated via PowerWorld’s time step simulation analysis. The table represents the number of instances where the line exceeds specific thresholds, such as 80% and 90% of their rated capacity. When a line loading exceeds 80% of its capacity, there is an increased risk for faults; more specifically, the lines can sag and potentially short-circuit with adjacent lines [12]. In Table 3, it is also calculated when the line limits exceed 100%. In the PowerWorld simulation environment, it is possible to analyze instances where the line loading surpasses 100% without immediately considering it as a fault. This approach helps identify situations where a line may require an increase in capacity in future system planning.
In Table 3, it can be observed that increasing RES installations without a BESS reduces the number of instances in which line loading exceeds 80%. However, when a BESS is included, these instances increase, as the power flow is altered to store excess RES energy in other buses. In Case 6, this increase is particularly pronounced. This behavior was expected because the energy produced by RES is abundant, and the power system must accommodate it. Moreover, the system is primarily designed to transfer energy from conventional power plants to the loads, rather than from RES generation dispersed across the island.
In Figure 17, a screenshot from PowerWorld simulation is represented in August 2023 at 13:00. In this figure, the lines connecting Moires–Ag. Varavara–Linoperamata, and Siteia–Atherinolakos–Iraklio II are the ones that are overloaded. These lines are the ones that become overloaded in the simulation, due to the abundant RES generation in Siteia, Moires, and Ag. Varvara. More precisely, RES generation exceeds both consumption and local BESS capacities, which results in excess energy directed towards the city of Heraklion (capital of Crete), covering the large loads and charging the local batteries to mitigate feature instabilities. In other words, the excess energy is transmitted through certain lines that do not have adequate capacity, leading to their overloading.

4. Conclusions

The increase in renewable energy generation is mandatory to fight climate change. Energy storage systems should accompany this increase with optimized capacities. In this research, the island of Crete was examined via the PowerWorld simulator. Different cases were constructed for different RES power generation, for various renewable generation mixes and different storage capacities. These cases proved that the increase in RES generation minimizes the need for conventional generation up to 28%, thus reducing GHG emissions. Moreover, it has been proven that the growth of RES should be complemented by energy storage systems. Their optimal capacities, which depend on the level of RES penetration, range from 1.6 GWh to 6.4 GWh per HV substation. Furthermore, Crete’s power system should prioritize wind energy, followed by solar energy. Additionally, the capacities of specific transmission lines must be carefully considered to accommodate the anticipated growth in renewable energy generation. Future research could also include the big interconnection in Crete’s power system and consider exporting energy to mainland Greece through both interconnections. Another aspect that could be examined is the effect of different RES technologies, such as green hydrogen, for both generation and energy storage.

Author Contributions

Conceptualization, E.K. and Y.K.; methodology, E.K.; software, E.K. and Y.K.; validation, A.A. and A.P.; formal analysis, A.A. and A.P.; investigation, A.A. and A.P.; resources, E.K. and Y.K.; data curation, E.K. and Y.K.; writing—original draft preparation, A.A. and A.P.; writing—review and editing, Y.K.; visualization, A.A., A.P. and Y.K.; supervision, E.K.; project administration, E.K.; funding acquisition, E.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research project was supported by the European Union’s Lump Sum MGA under grant agreement No. 101144027 (SEBCoVE Project).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

The following abbreviations are used in this manuscript:
RESRenewable energy sources
GHGGreenhouse gases
ESSEnergy storage system
BESSBattery energy storage system
HVHigh voltage
OPFOptimal power flow
PV Photovoltaic
WFWind farm
WTWind turbine
MVMedium voltage
PPPower plant

References

  1. Ministry of the Environment and Energy. National Long-Term Strategy (LTS)—Report 2020; Ministry of the Environment and Energy: Athens, Greece, 2020.
  2. Crippa, M.; Guizzardi, D.; Pagani, F.; Banja, M.; Muntean, M.; Schaaf, E.; Quadrelli, R.; Risquez Martin, A.; Taghavi-Moharamli, P.; Köykkä, J.; et al. GHG Emissions of All World Countries—2025 Report; Publications Office of the European Union: Luxembourg, 2025; p. JRC143227. [Google Scholar]
  3. IPTO. Yearly Press Release 2023. Available online: https://www.admie.gr/sites/default/files/news/attached-files/2024/01/YEARLY_PRESS%20RELEASE_2023.pdf (accessed on 27 September 2025).
  4. Lee, C.; Im, S.; Jung, J.; Lee, B. BESS Deployment Strategy in Jeju Carbon-Free Islands for Reducing Renewable Energy Curtailment. Energies 2020, 13, 6082. [Google Scholar] [CrossRef]
  5. Mahadevan, V.; Raja, S.S.; Rusho, M.A.; Yishak, S. Critical review of energy storage systems: A comparative assessment of mechanisms, advantages, challenges, and integration with renewable energy. Results Eng. 2025, 26, 105589. [Google Scholar] [CrossRef]
  6. Hasan, M.M.; Haque, R.; Jahirul, M.I.; Rasul, M.G.; Fattah, I.M.R.; Hassan, N.M.S.; Mofijur, M. Advancing energy storage: The future trajectory of lithium-ion battery technologies. J. Energy Storage 2025, 120, 116511. [Google Scholar] [CrossRef]
  7. Kourougianni, F.; Arsalis, A.; Olympios, A.; Yiasoumas, G. A comprehensive review of green hydrogen energy systems (GHES). Renew. Energy 2024, 231, 120911. [Google Scholar]
  8. Rehman, S.; Al-Hadhrami, L.M.; Alam, M.M. Pumped hydro energy storage system: A technological review. Renew. Sustain. Energy Rev. 2015, 44, 586–598. [Google Scholar] [CrossRef]
  9. International Energy Agency (IEA). Greece 2023: Energy Policy Review; IEA: Paris, France, 2023; Available online: https://www.iea.org/reports/greece-2023 (accessed on 29 September 2025).
  10. Karapidakis, E.; Tsikalakis, A.; Paspatis, A.; Fotakis, E.; Stavrakakis, G.; Chatzipoulka, C.; Zervas, P. Grid Operation Assessment under a Specific EV Chargers Deployment Plan in the City of Heraklion. Electronics 2021, 10, 2831. [Google Scholar] [CrossRef]
  11. Alzahrani, A.; Alharthi, H.; Khalid, M. Minimization of power losses through optimal battery placement in a distributed network with high penetration of photovoltaics. Energies 2019, 13, 140. [Google Scholar] [CrossRef]
  12. International Energy Agency (IEA). Learning from the Blackouts: Transmission System Security in Competitive Electricity Markets; OECD Publishing: Paris, France, 2005. [Google Scholar]
Figure 1. Crete’s HV power system.
Figure 1. Crete’s HV power system.
Engproc 122 00027 g001
Figure 2. Electric load and production from both PV plants and WFs in Crete during 22 March to 23 March 2023.
Figure 2. Electric load and production from both PV plants and WFs in Crete during 22 March to 23 March 2023.
Engproc 122 00027 g002
Figure 3. Crete’s duration curve including wind and solar power production for 2023.
Figure 3. Crete’s duration curve including wind and solar power production for 2023.
Engproc 122 00027 g003
Figure 4. Utilization flowchart of renewable energy sources.
Figure 4. Utilization flowchart of renewable energy sources.
Engproc 122 00027 g004
Figure 5. Battery storage flowchart.
Figure 5. Battery storage flowchart.
Engproc 122 00027 g005
Figure 6. Battery loss flowchart.
Figure 6. Battery loss flowchart.
Engproc 122 00027 g006
Figure 7. Small interconnection power generation flowchart.
Figure 7. Small interconnection power generation flowchart.
Engproc 122 00027 g007
Figure 8. Conventional power plant power generation flowchart.
Figure 8. Conventional power plant power generation flowchart.
Engproc 122 00027 g008
Figure 9. System rejection flowchart.
Figure 9. System rejection flowchart.
Engproc 122 00027 g009
Figure 10. Crete’s HV system modeled in the PowerWorld simulator.
Figure 10. Crete’s HV system modeled in the PowerWorld simulator.
Engproc 122 00027 g010
Figure 11. RES penetration for 560 MW installed RES capacity under different energy mix scenarios and storage capacities.
Figure 11. RES penetration for 560 MW installed RES capacity under different energy mix scenarios and storage capacities.
Engproc 122 00027 g011
Figure 12. RES penetration for 800 MW installed RES capacity under different energy mix scenarios and storage capacities.
Figure 12. RES penetration for 800 MW installed RES capacity under different energy mix scenarios and storage capacities.
Engproc 122 00027 g012
Figure 13. RES penetration for 1200 MW installed RES capacity under different energy mix scenarios and storage capacities.
Figure 13. RES penetration for 1200 MW installed RES capacity under different energy mix scenarios and storage capacities.
Engproc 122 00027 g013
Figure 14. RES penetration for 1600 MW installed RES capacity under different energy mix scenarios and storage capacities.
Figure 14. RES penetration for 1600 MW installed RES capacity under different energy mix scenarios and storage capacities.
Engproc 122 00027 g014
Figure 15. System rejections for 1200 MW RES installed capacity.
Figure 15. System rejections for 1200 MW RES installed capacity.
Engproc 122 00027 g015
Figure 16. System losses for the selected scenarios.
Figure 16. System losses for the selected scenarios.
Engproc 122 00027 g016
Figure 17. Screenshot showing power flow from the PowerWorld simulation for Case 6, recorded on August 2023, at 13:00.
Figure 17. Screenshot showing power flow from the PowerWorld simulation for Case 6, recorded on August 2023, at 13:00.
Engproc 122 00027 g017
Table 1. Data per substation.
Table 1. Data per substation.
SubstationHV/MV Transformers (MVA)Peak Load (MW)WTs (MW)PVs (MW)
Kastelli2 × 2524.5518.244.52
Agya2 × 5060.2910.804.30
Chania3 × 5096.79-9.66
Vrysses2 × 2518.18-2.24
Rethymno2 × 25 + 3 × 5065.84.8018.58
Spili2 × 2515.1116.80-
Linoperamata1 × 5013.76--
Ag. Varvara1 × 5013.6214.15-
Stalida2 × 5070.02-3.25
Iraklio 32 × 5038.695.953.78
Iraklio 23 × 5084.46-8.55
Iraklio 12 × 5065.3-2.17
Moires2 × 2527.8617.4516.27
Pretoria2 × 2520.995.9510.89
Ierapetra2 × 2524.78-8.04
Atherinolakos1 × 500--
Maronia1 × 50034.10-
Siteia2 × 25 + 1 × 5018.9556.779.82
Ag. Nikolaos2 × 5039.7611.905.61
Total1600649.51 1200.81108.4
1 The total peak load is Crete’s island maximum demand, which is measured due to load diversity.
Table 2. Power plant data.
Table 2. Power plant data.
Power PlantTotal Nominal Power (MW)Technical Minimum (MW)Number of Sub-Power Plants
Diesel Atherinolakos102252
Steam turbine Atherinolakos88222
Steam turbine Linoperamata10646
Diesel Linoperamata4434
Gas Turbine Linoperamata11535
Combined Cycle Chania132351
Gas Turbine Chania21636
Table 3. Line capacities.
Table 3. Line capacities.
CaseInstances of Line Loadings Between 80–90%Instances of Line Loadings Between 90–100%Instances of Line Loadings over 100%
Case 1: Scenario 11600
Case 2: Scenario 1 BESS1600
Case 3: Scenario 21300
Case 4: Scenario 2 BESS3400
Case 5: Scenario 3800
Case 6: Scenario 3 BESS2408648
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Angeloudis, A.; Peraki, A.; Katsigiannis, Y.; Karapidakis, E. Increasing Renewable Energy Penetration Using Energy Storage. Eng. Proc. 2026, 122, 27. https://doi.org/10.3390/engproc2026122027

AMA Style

Angeloudis A, Peraki A, Katsigiannis Y, Karapidakis E. Increasing Renewable Energy Penetration Using Energy Storage. Engineering Proceedings. 2026; 122(1):27. https://doi.org/10.3390/engproc2026122027

Chicago/Turabian Style

Angeloudis, Alexandros, Angela Peraki, Yiannis Katsigiannis, and Emmanuel Karapidakis. 2026. "Increasing Renewable Energy Penetration Using Energy Storage" Engineering Proceedings 122, no. 1: 27. https://doi.org/10.3390/engproc2026122027

APA Style

Angeloudis, A., Peraki, A., Katsigiannis, Y., & Karapidakis, E. (2026). Increasing Renewable Energy Penetration Using Energy Storage. Engineering Proceedings, 122(1), 27. https://doi.org/10.3390/engproc2026122027

Article Metrics

Back to TopTop