Next Article in Journal
Analysis of Ultrasonic Wave Dispersion in Presence of Attenuation and Second-Gradient Contributions
Previous Article in Journal
Study on Bearing Characteristics of DMJ Group Pile Composite Foundation Under Embankment Loading
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Monetizing Environmental Impacts into Environmental Costs During Prefabricated Building Construction: A 5D BIM-Enabled Analysis

1
State Grid Fujian Economic Research Institute, Fuzhou 350013, China
2
Building Information Modeling Research Center, School of Ocean and Civil Engineering, Shanghai Jiao Tong University, Shanghai 200240, China
3
Shanghai Key Laboratory for Digital Maintenance of Buildings and Infrastructure, School of Ocean and Civil Engineering, Shanghai Jiao Tong University, Shanghai 200240, China
*
Author to whom correspondence should be addressed.
CivilEng 2025, 6(3), 36; https://doi.org/10.3390/civileng6030036
Submission received: 28 April 2025 / Revised: 12 June 2025 / Accepted: 24 June 2025 / Published: 2 July 2025

Abstract

Although prefabricated buildings offer environmental advantages, their construction process inevitably generates environmental impacts. However, current research on prefabricated buildings focuses on the environmental impact level, and there is a lack of intelligent tools for analyzing their spatial and temporal dimensions. Therefore, this study develops a framework using 5D building information modeling (BIM) to monetize environmental impacts into environmental costs for prefabricated building construction. This framework includes defining boundaries and indicators, obtaining a resource inventory using the 5D BIM coding system, calculating environmental impact results, and converting environmental impacts into environmental costs. Taking a prefabricated substation as a case study, its environmental costs are 172.81 CNY/m2, with these costs caused by climate change accounting for the largest proportion (91.2%). This study unifies different environmental impacts into a single monetary form, providing stakeholders with intuitive indicators. It also expands 5D BIM applications from conventional costs to environmental costs, which can display their spatiotemporal changes.

1. Introduction

The construction industry accounts for nearly 40% of global raw material consumption, 36% of energy consumption, 40% of solid waste generation, and 40% of greenhouse gas emissions [1]. To mitigate the environmental impacts of construction projects, prefabricated buildings, characterized by industrialized production methods [2,3], have emerged as a growing trend in the construction industry [4].
Nevertheless, the construction process of prefabricated buildings still inevitably exerts environmental impacts [5,6]. For example, the production, transportation, and assembly of prefabricated components consume energy and generate pollutant emissions, such as greenhouse gas emissions, ozone layer depletion, and particulate matter formation [7]. These environmental impacts not only cause damage to ecosystems but also pose potential threats to human health and socioeconomic development [8,9]. To evaluate these environmental impacts, some studies compared prefabricated buildings with conventional buildings [10,11,12,13] and also explored the impact of different assembly rates [14].
However, current research on prefabricated buildings is still confined to environmental impact assessment. The units of these environmental impacts vary; for example, greenhouse gas emissions are measured in kgCO2 [12,15], energy use in MJ [16], and particulate matter formation in kgPM10 [13]. This unit disparity makes it difficult to standardize different environmental impacts to a common benchmark. More importantly, without monetizing these environmental impacts, stakeholders cannot intuitively understand their negative economic effects.
On the other hand, building information modeling (BIM) provides a more efficient and accurate tool for the environmental impact assessment of prefabricated buildings [7]. Additionally, 5D BIM technology has effectively facilitated quantity surveying and cost management, aiding in the traditional accounting of economic costs [17,18,19]. Despite these remarkable advantages of BIM, the environmental cost analysis of prefabricated buildings lacks an effective 5D BIM coding system to incorporate spatial and temporal dimensions.
Therefore, this study develops a 5D BIM-based framework to monetize environmental impacts into environmental costs in the construction process of prefabricated buildings, aiming to address the aforementioned issues. The innovations and significance of this study are as follows:
  • Monetizing environmental impacts into environmental costs: By introducing environmental economics theories, environmental impacts are quantified as monetary environmental costs. This monetization approach standardizes environmental impacts by a unified measure, which offers an intuitive indicator for stakeholders.
  • Introducing 5D BIM technology for environmental cost analysis: This study extends the application of 5D BIM from conventional economic costs to environmental costs. This new tool also presents spatial and temporal changes in terms of environmental costs.

2. Literature Review

2.1. Environmental Impacts of Prefabricated Buildings

In recent years, some research has advanced in the environmental impact assessment of prefabricated buildings, as shown in Table 1. Among these studies, life cycle assessment (LCA) is the most prevalent methodology [12,16,20]. According to ISO 14040 [21], LCA comprises four steps: (1) goal and scope definition; (2) inventory analysis; (3) impact assessment; (4) interpretation. Numerous studies focused on comparing the environmental performance of prefabricated buildings with conventional buildings [10,11,12,13]. Wang & Sinha also explored the environmental impacts under different prefabrication rates [14]. On this basis, scenario analysis was used to simulate their environmental impacts under different circumstances [22], while sensitivity analysis focused on the changes in input parameters on environmental impact results [23]. Additionally, the introduction of BIM has provided a more efficient and accurate tool for environmental impact assessment [7].
In these studies, the involved environmental indicators are diverse, including climate change potential (CCP), acidification potential (AP), eutrophication potential (EP), and so on. In terms of building types, the research involves residential buildings [14,16,20], school buildings [10], commercial buildings [22], office buildings [13], hospital buildings [6,24], and industrial buildings [23]. Geographically, these studies cover multiple countries, such as the United States [11,22], China [7,20], Italy [15,23], Spain [10], Germany [25], Sweden [14], Denmark [5], Malaysia [16], and Sri Lanka [13,24].
Table 1. Key studies on the environmental impacts of prefabricated buildings.
Table 1. Key studies on the environmental impacts of prefabricated buildings.
FocusEnvironmental IndicatorBuilding TypeRegionRef.
Comparing prefabricated and non-prefabricated technologyMaterials weight, PED, CCP, ET, HT, material intensity, WRD, solid waste, recycled material, recyclable materialPrefabricated school buildingCatalonia, Spain[10]
Scenario analysisEcoIndicator99, CCPPrefabricated commercial buildingSan Francisco, California, USA[22]
Comparing modular and conventional buildingCCP, AP, carcinogens HT, non-cancer HT, criteria pollutants, EP, ET, POF, WRD, ODPModular homesThe United States[11]
Sensitivity of input parametersCCP, PEDPrefabricated industrial buildingsItalian[23]
Input and output flows on factory levelCCP, ODP, AP, EP, PMF, ADP, renewable PED, non-renewable PEDPrefabricated timber housesGermany[25]
Energy performances by non-steady state simulationCCP, ODP, AP, EP, POF, ADP, PEDPrefabricated simply temporary housingMessina, Italy[15]
Comparing modular and conventional methods by analytic hierarchy processCCP, AP, human health, EP, PFM, ODP, PED, ETModular homesOkanagan, British Columbia, Canada[12]
Comparing concrete and steel prefabricated prefinished volumetric constructionCCP, non-renewable PED, PMF, LO, ADPPrefabricated residential buildingMalaysia[16]
Automated building information modeling approachADP, AP, EP, freshwater ET, CCP, HT, marine ET, ODP, POF, terrestrial ET, renewable PED, non-renewable PEDModular high-rise buildingsHong Kong, China[7]
Comparing different prefabricated ratesCCP, ODP, IR, ODP, human health, PFM, ODP, terrestrial ecosystems, terrestrial AP, freshwater EP, marine EP, terrestrial ET, freshwater ET, marine ET, carcinogenic ET, non-carcinogenic ET, LO, ADP, PED, WRDPrefabricated residential buildingStockholm royal seaport, Sweden[14]
Comparing different geographical contexts in absolute measuresCCP, ODP, EP, PDF, freshwater ETModular buildingsAustralia and Denmark[5]
Cradle-to-cradle for recyclability planHuman health, ecosystem, CCP, resourcesModular residential buildingChangsha, China[20]
Comparing prefabricated and conventional constructionCCP, terrestrial AP, freshwater EP, marine EP, PMF, HT, freshwater ET, marine ET, PEDPrefabricated office buildingSri Lanka[13]
Circular economy strategiesCCP, terrestrial AP, freshwater EP, HT, POF, PMF, terrestrial ET, freshwater ET, marine ET, agricultural LO, ADP, PEDModular infectious disease buildingSri Lankan[24]
Comparing prefabricated volumetric modular buildings with seismic-resistantAgricultural LO, CCP, PED, freshwater ET, freshwater EP, HT, IR, marine ET, marine EP, ADP, natural soil transformation, ODP, PMF, POF, terrestrial AP, terrestrial ET, urban LO, WRDOutpatient hospital buildingQuito, Ecuador[6]
However, current research on prefabricated buildings remains at the level of environmental impact assessment. The units of these environmental impacts vary; for example, CCP is measured in kgCO2 [12,15], PED in MJ [16], and PMF in kgPM10 [13]. This disparity in units makes it impossible to standardize different environmental impacts to a common benchmark. Moreover, without monetizing these indicators, it is challenging for stakeholders in prefabricated building projects to understand the negative economic effects of environmental impacts.

2.2. From 5D BIM to nD BIM

BIM (building information modeling) is a digital tool that conveys information across the building lifecycle [26,27]. As shown in Table 2, BIM has gradually expanded from the initial 3D model to 4D, 5D, and even nD, which incorporates more dimensions to achieve more efficient project management.
Three-dimensional BIM is essentially a geometric and spatial model [43] which captures the geometric information and spatial relationships of buildings [44,45]. The visual design of 3D BIM intuitively displays the overall facade and internal structure of buildings, offering relevant personnel a clearer understanding [28]. Additionally, its collision detection function can automatically check for conflicts between different professional models, such as pipes passing through beams, to identify and resolve design contradictions in advance [30].
Four-dimensional BIM introduces the time dimension based on 3D BIM and is mainly used for construction schedule management [46]. On the one hand, 4D BIM can simulate the construction sequences [29,30,31], such as the order of earthwork excavation, structure construction, and decoration. On the other hand, it can be used for progress tracking, comparing the planned schedule with the actual progress to identify potential delay risks and take corresponding adjustment measures [32].
Five-dimensional BIM further adds the cost dimension, integrating cost information with the 4D model for quantity surveying and cost management [47]. Specific functions include (1) quantity surveying: It extracts bills of quantities based on BIM [17,18,19,30,31,33,34]; (2) life cycle costing: It generates cost reports for different life cycle stages [35]; (3) financial decision making: It assesses the project’s feasibility by analyzing the life cycle cash flow [36,37]; and (4) cost monitoring and payment: Automated adjustment of payments in response to design alterations ensures precise cost control [19,32].
nD BIM introduces more dimensions based on 5D BIM. However, the industry has not yet agreed on which specific dimensions should be included [31,38]. Common extended dimensions are as follows: (1) Quality management: Associating quality standards with the BIM model to facilitate inspection and feedback during construction [38]. (2) Safety management: Using BIM to simulate construction safety hazards and proposing protective measures and emergency plans accordingly [38]. (3) Energy efficiency: Using BIM to simulate and analyze energy consumption and optimize energy performance [40,41]. (4) Carbon emission calculation: Calculating carbon emissions and selecting carbon reduction solutions [31,38].
Starting from the initial 3D, BIM has gradually expanded to 4D, 5D, and nD. Each expansion has brought new transformations and improvements to construction project management. In existing research, the extended dimensions of nD BIM, such as quality management, safety management, energy efficiency, and carbon emissions, have enriched the application value of the BIM model from different perspectives.
However, no research has considered environmental costs as part of the cost dimension of 5D BIM or as an extended dimension of nD BIM. Conventional 5D BIM mainly focuses on quantity surveying, emphasizing the accurate accounting of economic costs. In contrast, integrating environmental costs into it can combine economic and environmental costs, which is significant for a more comprehensive cost assessment in construction projects.

3. Method and Materials

Based on ISO 14040 [21] and ISO 14008 [48], this study proposes a method using 5D BIM to monetize the environmental impacts of the prefabricated substation into environmental costs during the construction process. The framework of this method consists of the following four steps: (1) Boundary definition: This includes defining the spatial boundary, temporal boundary, and environmental indicators. (2) Inventory acquisition: The resource inventory is automatically obtained using the coding system of 5D BIM. (3) Environmental impact assessment: The environmental impact results are obtained by multiplying the resource inventory by the environmental impact factors. (4) Environmental cost assessment: The environmental impacts are converted into environmental costs through the willingness-to-pay approach.

3.1. Boundary Definition

The boundary definition is divided into spatial and temporal scope boundaries, as shown in Figure 1.
The spatial scope encompasses all components that make up the prefabricated building, including the following: (1) Prefabricated wall (PW), (2) Prefabricated column (PC), (3) Prefabricated beam (PB), (4) Prefabricated slab (PS), (5) Prefabricated beam-slab (PBS), (6) Prefabricated foundation (PF) and so on.
The temporal boundary is defined as “cradle-to-site,” which includes five stages from material production to on-site assembly. This division is carried out by ISO 21931-1 [49], and the specific meanings of these stages are as follows: (1) Material production (MP): Extracting raw materials from nature and processing them into building materials; (2) Material transportation (MT): Transporting materials from their production site to a manufacturing factory; (3) Component prefabrication (CM): Producing prefabricated components in a prefabricated factory; (4) Component transportation (CT): Transporting components from a manufacturing factory to a construction site; (5) On-site assembly (OA): Pouring, assembling, and constructing components at a construction site.
In addition, the selection of environmental impact indicators is also crucial. Based on the recommendations of the China Life Cycle Database (CLCD) [50], these indicators include nine categories: climate change potential (CCP), primary energy demand (PED), abiotic depletion potential (ADP), water resource depletion (WRD), acidification potential (AP), eutrophication potential (EP), particulate matter formation (PMF), ozone depletion potential (ODP), photochemical ozone formation (POF).

3.2. Inventory Acquisition

The resource inventory is a detailed list that records all resources required for a construction project, covering the quantities of materials, energy, and machinery [43,44]. This study develops a 5D BIM method for automating resource inventory acquisition, achieving efficient data collection through a multi-software collaborative workflow. The specific technical route is as follows:
  • Structural model creation: The YJK structural design software (YJK-A) [51] was used to build an accurate structural BIM model. When setting material parameters, key attributes such as concrete strength grade (e.g., C30/C35) and steel bar type (e.g., HRB400) were included.
  • Architectural model supplementation: The YJK model was imported into Autodesk Revit 2018 [52] to supplement the architectural information of buildings.
  • Detailed design model development: BeePC V4.2 [53] was used to add details of prefabricated components and their connection nodes (such as grouting sleeves and embedded parts).
  • Resource inventory acquisition: BeePC software [53] can automatically collect and summarize resource data according to preset programs and rules, and then export the resource inventory for construction projects.
In the technical route, this study establishes a 5D BIM coding system for prefabricated building components (Figure 2). This coding system is used for data transmission in the above-mentioned technical route, which also facilitates the temporal and spatial analysis of environmental costs. The system uses a four-level mixed coding of English letters and Arabic numerals to achieve precise one-to-one coding for each component. Each level of coding is separated by a “.” (dot), while the sequence code is separated by a “-” (dash) within each level, such as UA.PB-01.OA-001.SE61-001.
  • System classification code: The first-level code inherits the building structure system from GB/T 51061-2014 [54], which enables the identification of power grid projects. In this standard, “U” represents the building part of the power grid system, and “UA” denotes the civil engineering part of substations.
  • Space dimension (3D) code: The second-level code inherits the IFC standard of buildingSmart [55]. This code represents the 3D information in the BIM model, namely the solid geometric information of components, which demonstrates the spatial dimension of the construction project, as shown in Table 3. Notably, Table 3 only shows the six types of prefabricated components involved in this study. Other entities, such as IfcChimney, IfcStairFlight, and IfcRoof, can be supplemented according to actual needs.
3.
Time dimension (4D) code: The third-level code is divided according to the construction stages. Based on the stage code, a serial number can be assigned sequentially to represent the construction sequence of components. As shown in Table 4, this code demonstrates the time dimension.
4.
Environmental cost (5D) code: The fourth-level code inherits the requirements of DL/T 5341-2021 [56]. As presented in Table 5, this four-digit code serves as a quota code initially employed for quantity surveying in power transformer projects. This quota code mainly emphasizes the resource consumption of prefabricated components. Specifically, it not only records the characteristics of resources but also provides the resource quantity of each unit component. By applying the corresponding quota, the resource inventory of components can be obtained, thus providing a basis for calculating environmental impacts and environmental costs.
Actually, this four-digit code is recommended for economic cost measurement in Chinese power projects [56]. In this study, it is applied to calculating environmental costs, enabling a more comprehensive assessment of environmental impacts.

3.3. Environmental Impact Assessment

After getting the resource inventory, the next step is to multiply resource quantities by corresponding environmental impact factors to obtain the environmental impact results (Equation (1)).
E I = E I F × Q
In Equation (1), Q represents the resource quantity of the resource inventory, which is derived from the BIM. E I F represents environmental impacts per unit of each resource. Table 6 shows its main data, which are sourced from the Chinese Life Cycle Database (CLCD) [50]. This database is a popular LCA database in China with regularly updated resources. It encompasses the majority of resources in the construction industry and takes into account their specific production processes within the Chinese context.

3.4. Environmental Cost Assessment

After accurately calculating the environmental impacts, a subsequent step is to convert them into intuitive environmental costs. This conversion is achieved through the willingness-to-pay (WTP) method, which represents the monetary value that the public is willing to pay to avoid or reduce specific environmental damages [48]. Its calculation formula is shown in Equation (2).
E C   =   W T P × E I
where EC stands for environmental costs, E I represents environmental impacts, and W T P denotes the monetary value by willingness-to-pay.
People in different regions may have different WTP due to variations in lifestyle, income level, environmental awareness, and other factors. When using the WTP method to monetize environmental impacts, these specific circumstances need to be fully taken into account. Therefore, this study adopts the WTP determined by Zhu et al. [57], Cao [58], and Li et al. [59] as the monetary values applicable to the actual situation in China. Although the studies were conducted some time ago, the relevant socioeconomic factors and people’s attitudes have not changed significantly, rendering these WTP values still applicable. Therefore, these parameters are more in line with China’s conditions, thus ensuring higher accuracy and reliability, as presented in Table 7.

3.5. Case Study

After proposing this method, this study employs a prefabricated substation as a case study to validate its effectiveness. In fact, according to Chen et al.’s review [60], most studies about the environmental impacts of prefabricated buildings have focused on residential and office buildings, while research on industrial buildings, especially substations, is extremely scarce. Therefore, this substation project is selected to fill the gap for the environmental aspects of industrial buildings.
The substation building is located in Xiamen City, with a floor area of 1080 square meters. It is a one-story building, and its total height is 12.55 m. This project is an unattended distribution device building. Its corresponding BIM is presented in Figure 3, with detailed background information provided in Table 8.
After calculating the environmental impacts and environmental costs of the case building, this study analyzes the results from two aspects, i.e., the space dimension and the time dimension. It examines the proportion attributed to each dimension and identifies factors that significantly influence the results.

4. Environmental Impact Results

Through the above calculations, the environmental impacts of the case study are as follows: CCP: 607,974.11 kgCO2eq, PED: 7,336,871.26 MJ, ADP: 3.57 kgSbeq, WRD: 2,002,933.13 kg, AP: 1874.12 kgSO2eq, EP: 215.32 kgPO43−eq, PMF: 745.79 kgPM2.5eq, ODP: 0.03 kgCFC-11eq, POF: 882.26 kgNMVOCeq. Their detailed calculation processes can be found in Table A1, Table A2, Table A3, Table A4, Table A5 and Table A6 in the Appendix.

4.1. Space Dimension Analysis of Environmental Impacts

The spatial dimension analysis for the environmental impacts of the case building is shown in Figure 4. For the vast majority of environmental indicators, the prefabricated wall is the biggest contributor to environmental impacts, followed by prefabricated beam-slabs, which may be positively correlated with their huge volume. In addition, structural components such as columns, beams, and foundations also contribute a lot to environmental impacts. Since these components bear the main structural loads, their cumulative environmental impacts are also relatively high.
However, an exception is particulate matter formation (PMF). The main contributors of PMF are prefabricated beam-slabs (26.5%) and prefabricated columns (26.4%), followed by prefabricated walls (22.8%). The main reason is that the main material of prefabricated walls, foamed ceramics, has a relatively low PMF value, only 0.19 kgPM2.5eq/m3. A similar environmental indicator is water resource depletion (WRD). Its spatial composition is prefabricated columns (26.8%) > prefabricated beam-slabs (25.6%) > prefabricated walls (23.0%).

4.2. Time Dimension Analysis of Environmental Impacts

Figure 5 shows the distribution of environmental impacts in the time dimension. Except for ozone depletion potential (ODP), material production serves as the core stage for all other indicators, accounting for a proportion that spans from 53.1% to 80.9%. This indicates that material selection is the key during prefabricated construction.
As an exception, the composition proportion of ODP is as follows: component transportation (56.4%) > material transportation (16.0%) > material production (12.6%). The main reason is the extensive use of diesel in the transportation process, with its environmental impact factor for ODP is particularly high, reaching 4.2 × 10−4 kgCFC-11eq/t. This is significantly higher than other building materials, such as 2.4 × 10−5 kgCFC-11eq/t for steel bars and 1.1 × 10−9 kgCFC-11eq/t for cement. Such a disparity suggests that reducing diesel use is key to lowering ODP in prefabricated building construction.

5. Environmental Cost Results

Using the above method, the environmental costs of this prefabricated building are 186,638.63 CNY (172.81 CNY/m2). Detailed calculation processes can be found in Table A7, Table A8, Table A9, Table A10, Table A11 and Table A12 in the Appendix. The corresponding environmental costs for CCP, PED, ADP, WRD, AP, EP, PMF, ODP, and POF are 170,232.75 CNY (91.2%), 2024.98 CNY (1.1%), 0.07 CNY (0.0%), 2784.08 CNY (1.5%), 3204.74 CNY (1.7%), 157.19 CNY (0.1%), 514.59 CNY (0.3%), 0.45 CNY (0.0%), and 7719.79 CNY (4.1%), respectively. It is obvious that the CCP constitutes the most significant environmental cost (91.2%), followed by POF (4.1%).

5.1. Space Dimension Analysis of Environmental Costs

From the spatial dimension analysis (Figure 6), the environmental costs of prefabricated walls, columns, beams, slabs, beam-slabs, and foundations in the case building are 79,361.65 CNY, 32,871.50 CNY, 13,348.31 CNY, 4703.26 CNY, 42,460.06 CNY, and 13,893.86 CNY, respectively.
Among these components, the walls make the greatest contribution to environmental costs, accounting for 42.5%, followed by beam-slabs (22.7%). This contribution might be positively correlated with their volume proportion. It is worth noting that, as shown in Table A10 and Table A11, the beam-slabs and slabs require concrete pouring during the on-site assembly stage to form an integrated structure. Therefore, their on-site assembly accounts for 32.08% and 32.74% of the environmental costs, respectively. This indicates that more attention should be paid to these two components compared to other components in this stage. This phenomenon also represents the emission-reduction bottleneck in the wet-work processes of current prefabricated buildings.
In addition, load-bearing components, such as columns, beams, and foundations, also contribute to a large share of environmental costs, accounting for 17.6%, 7.2%, and 7.4%, respectively. Since these components bear the main structural loads, their environmental costs during material production are relatively high. Notably, even though the case building is a single-story structure, the environmental costs of foundations remain considerable (7.4%). This finding underscores the importance of considering environmental costs associated with foundations, even in single-story buildings.

5.2. Time Dimension Analysis of Environmental Costs

Figure 7 shows significant differences in the environmental cost contributions of each stage. Material production emerges as the core stage, with an environmental cost of 146,738.31 CNY (accounting for 78.6%). This is understandable because climate change potential (CCP) is the most important environmental indicator, accounting for 91.2% of environmental costs, so its distribution is very similar between environmental impacts and environmental costs.
In contrast, the environmental costs of other stages seem less significant. The costs for material transportation, component manufacturing, component transportation, and on-site assembly are 2925.15 CNY (1.6%), 8322.44 CNY (4.5%), 10,296.93 CNY (5.5%), and 18,355.80 CNY (9.8%), respectively. Interestingly, the on-site assembly accounts for the second highest proportion (9.8%), due to the need to pour concrete for slabs and beam-slabs, as well as grouting materials for component connections.

6. Discussion

6.1. Sensitivity Analysis

To further explore the impact of monetary values that monetize environmental impacts into environmental costs, this study conducts a sensitivity analysis of these monetary values, as shown in Figure 8 and Table A13 and Table A14.
The results indicate that the monetary value of climate change potential (CCP) has the most significant influence on environmental costs, ranging from −18.24% to 18.24%. This is because CCP accounts for a substantial proportion (91.2%) of the total environmental costs. In contrast, the monetary values of other environmental impacts contribute no more than 1%, suggesting that their effects are negligible. Through this sensitivity analysis, more attention should be focused on the changes in CCP when managing environmental costs.

6.2. Benefit of Monetizing Environmental Impacts

This study monetizes environmental impacts during prefabricated construction, converting them into environmental costs. Historically, environmental impact results using LCA [21] were presented in different units, such as CO2 [12,15], Joule [16], and PM10 [13]. This proposed method overcomes this long-standing challenge of unit unification [61,62]. As a result, various environmental impacts can be measured by a single economic indicator, environmental costs, which facilitates their direct comparisons.
In practical applications, monetized environmental costs offer straightforward indicators for stakeholders in construction projects [63]. Previously, stakeholders often had a vague understanding of environmental impacts [8]. For instance, it is hard for them to comprehend the meaning of a CCP of 607,974.11 kgCO2eq, but it is easy for them to understand the corresponding environmental costs of 170,232.75 CNY in this case study. Therefore, the method enables engineers to convey the environmental impact results to clients and stakeholders more effectively.

6.3. Benefit of 5D BIM

Compared with conventional methods without BIM, 5D BIM technology offers superior efficiency and accuracy in environmental assessment. Conventional methods usually involve extensive manual data collection, which is highly susceptible to data errors and information delays [64]. In contrast, 5D BIM technology can automatically obtain the resource inventory through its coding system. This reduces the need for manual intervention, which enhances data reliability [33,34].
Additionally, this study extends the 5D BIM application from economic costs to environmental costs. Although traditional 5D BIM (space + time + cost) can provide information for the space and time analysis of economic costs [17,18,19], the extension of environmental costs offers stakeholders more comprehensive information that encompasses both economic and environmental aspects.
Furthermore, this innovation of the 5D BIM coding system enables project managers to efficiently retrieve relevant environmental cost data. For instance, users can target a specific code (such as SE60) to swiftly retrieve the environmental costs associated with this code.

6.4. Limitations and Future Research

This study proposes a methodology for monetizing environmental impacts, exemplified by a prefabricated substation case study. In the future, this methodology can be extended to other building types, such as residential and commercial buildings, and compare their environmental costs. Additionally, it is necessary to compare prefabricated buildings with conventional cast-in-place buildings to help the construction industry choose more eco-friendly and cost-effective construction methods.
Regrettably, this research only considers the construction process of prefabricated buildings because it is the most distinctive compared with traditional ones [14]. Future research can extend to other stages, such as operation and demolition, to form the life cycle environmental costs of construction projects.
Regarding data sources, the environmental impact factors and willingness-to-pay data used in this study are mainly based on the existing literature, which may have certain limitations. Future research can conduct more extensive field surveys and experimental studies to obtain more accurate and detailed data, thereby improving the accuracy of environmental cost assessments.
After completing the environmental cost analysis, it is reasonable to optimize prefabricated buildings to reduce their environmental costs. However, due to a lack of environmental impact factors for environmentally friendly materials [50], this optimization work could not be carried out in this study. Future research can further explore specific measures and solutions, such as three-dimensional printing [65], to reduce the environmental costs associated with prefabricated buildings.
Regarding research methods, future research can explore more intelligent methods for evaluating and analyzing environmental costs. For example, artificial intelligence models, such as machine learning [66], deep learning [67] and extreme gradient boosting [68], can be considered to predict environmental costs at the concept planning phase of construction projects.
Unlike building carbon emissions with a more perfected policy system [69], environmental costs face fewer legal constraints. Consequently, in practical applications, environmental costs are often overlooked in the bidding process [70]. Therefore, it is urgent to introduce corresponding laws in public procurement. In future building bidding and awarding, environmental costs should be incorporated into bid-evaluation decisions to encourage projects to reduce environmental impacts.
This study has converted environmental impacts into environmental costs to understand their economic effects. Future research can compare economic costs and environmental costs and then integrate them into a single model [71,72] to help with decision making for prefabricated buildings [73]. Moreover, future research also needs to add social costs to form life cycle sustainability costs in prefabricated buildings, thus achieving a balance among the economic, environmental, and social aspects.

7. Conclusions

This study proposes a 5D BIM-enabled analysis method to monetize environmental impacts into environmental costs during prefabricated building construction. The method steps are as follows: (1) Define the spatial boundaries, temporal boundaries, and environmental indicators. (2) Obtain the resource inventory using the 5D BIM coding system. (3) Multiply the quantities in the resource inventory by environmental impact factors to obtain environmental impact results. (4) Convert the environmental impacts into environmental costs through the willingness-to-pay approach.
Taking a prefabricated substation as an example, its environmental cost is 186,638.63 CNY (172.81 CNY/m2). Among them, climate change accounts for the largest proportion (91.2%), followed by photochemical ozone (4.1%). The sensitivity analysis further reveals that the monetary value of climate change is the most sensitive variable, while other environmental indicators can be ignored. From the spatial dimension, the prefabricated walls contribute the most to environmental costs (42.5%), followed by the prefabricated beam-slabs (22.7%). From the temporal dimension, material production is the core stage, accounting for 78.6% of the life cycle, which should be the focus for attention and optimization.
This study converts different environmental impacts into unified environmental costs in monetary form, providing a straightforward indicator for stakeholders to comprehend prefabricated buildings. In addition, this study extends the application of 5D BIM to environmental costs, enabling their spatial and temporal analysis.

Author Contributions

Conceptualization, K.L.; methodology, K.L.; software, X.C. and X.G.; validation, X.G. and X.D.; formal analysis, X.C.; investigation, X.G. and X.C.; resources, X.G. and X.C.; data curation, X.G. and X.C.; writing—original draft preparation, K.L.; writing—review and editing, X.G. and X.D.; visualization, X.C.; supervision, X.D.; project administration, X.D.; funding acquisition, X.G. and X.D. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the Research Project of State Grid Fujian Economic Research Institute (No. SGFJJY00BDJS2400085) and Science and Technology Project of State Grid Corporation of China (No. 5200-202456098A-1-1-ZN).

Data Availability Statement

Data will be made available on request.

Acknowledgments

The authors would like to acknowledge all authors whose works have been cited in this study.

Conflicts of Interest

The authors have no relevant financial or non-financial interests to disclose.

Abbreviations

The following abbreviations are used in this manuscript:
CCPClimate change potential
PEDPrimary energy demand
ADPAbiotic depletion potential
WRDWater resource depletion
APAcidification potential
EPEutrophication potential
PMFParticulate matter formation
ODPOzone depletion potential
POFPhotochemical ozone formation
ETEnvironment toxicity
HTHuman toxicity
LOLand occupation
IRIonizing radiation
BIMBuilding information modeling
LCALife cycle assessment
WTPWillingness-to-pay
CLCDChina life cycle database
EIFEnvironmental impact factor
PWPrefabricated wall
PCPrefabricated column
PBPrefabricated beam
PSPrefabricated slab
PBSPrefabricated beam-slab
PFPrefabricated foundation
MPMaterial production
MTMaterial transportation
CMComponent manufacturing
CTComponent transportation
OAOn-site assembly
CNYChinese Yuan

Appendix A

Appendix A.1. Environmental Impacts

Table A1. Environmental impacts of prefabricated walls.
Table A1. Environmental impacts of prefabricated walls.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C40m3226.60882,075.69574,649.050.05161,695.56214.1727.9080.490.001127.33
Foamed ceramicsm3216.192141,605.76309,262.660.76120,527.04246.2431.4640.270.00094.87
MTDiesel for transporting Concretet3.7242941.59175,006.260.0615,142.3914.272.152.250.00211.54
Diesel for transporting foamed ceramicst1.6711319.8878,524.390.036794.316.400.961.010.0015.18
CMElectricitykWh19,925.97814,725.30207,230.170.0155,394.2277.915.0422.910.0006.00
Binding wiret0.155358.485202.970.002508.581.470.140.900.0000.56
CTDiesel for component transportationt18.51914,630.31870,411.080.3175,312.1670.9910.6811.170.00857.41
OADry-mixed mortar DMM20m33.5421141.578131.760.002369.163.080.401.140.0001.78
Shimming iron partst0.9092145.3826,362.740.0010,508.737.450.746.950.0002.89
Grouting material for C40m37.2892639.9818,483.710.005200.976.890.902.590.0004.10
Diesel for construction machineryt1.039820.9748,842.270.024226.073.980.600.630.0003.22
Total 264,404.922,322,107.061.25459,679.18652.8780.97170.300.012314.88
Table A2. Environmental impacts of prefabricated columns.
Table A2. Environmental impacts of prefabricated columns.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C40m390.4132,745.52229,266.220.0264,511.2585.4511.1332.110.00050.80
Reinforcing steel barst23.1160,930.92903,458.540.67420,213.27252.3923.72151.010.00189.82
MTDiesel for transporting Concretet1.491173.6069,821.790.026041.325.690.860.900.0014.61
Diesel for transporting reinforcing steel barst0.13105.826295.910.00544.750.510.080.080.0000.42
CMElectricitykWh4520.453340.6147,012.680.0012,566.8517.671.145.200.0001.36
Binding wirest0.23112535.047765.630.013744.142.200.211.340.0000.84
CTDiesel for component transportationt5.864632.37275,596.500.1023,845.9422.483.383.540.00218.18
OADry-mixed mortar DMM20m30.72233.081660.310.00483.720.630.080.230.0000.36
Shimming iron partst0.19438.045382.680.002145.651.520.151.420.0000.59
Grouting material for C40m31.49539.023773.930.001061.911.410.180.530.0000.84
Diesel for construction machineryt0.33260.5515,501.170.011341.241.260.190.200.0001.02
Total 104,934.591,565,535.350.83536,500.05391.2241.13196.560.004168.83
Table A3. Environmental impacts of prefabricated beams.
Table A3. Environmental impacts of prefabricated beams.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C40m341.2614,945.68104,641.500.0129,444.1739.005.0814.660.00023.19
Reinforcing steel barst8.5222,458.81333,009.980.25154,888.3693.038.7455.660.00033.11
MTDiesel for transporting Concretet0.68535.6531,868.000.012757.372.600.390.410.0002.10
Diesel for transporting reinforcing steel barst0.0539.012320.640.00200.790.190.030.030.0000.15
CMElectricitykWh2475.861829.6625,748.990.006882.909.680.632.850.0000.75
Binding wirest0.09197.212862.380.001380.080.810.080.490.0000.31
CTDiesel for component transportationt2.632075.58123,483.620.0410,684.4010.071.521.590.0018.14
OAShimming iron partst0.05129.231587.980.00633.000.450.040.420.0000.17
Grouting material for C40m30.75270.621894.740.00533.150.710.090.270.0000.42
Diesel for construction machineryt0.22177.1810,540.790.00912.040.860.130.140.0000.70
Total 42,658.64637,958.630.32208,316.27157.3916.7376.500.00269.04
Table A4. Environmental impacts of prefabricated slabs.
Table A4. Environmental impacts of prefabricated slabs.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C40m311.64224216.7329,523.200.008307.2811.001.434.140.0006.54
Reinforcing steel barst1.844841.2371,783.810.0533,387.8220.051.8812.000.0007.14
MTDiesel for transporting Concretet0.19151.138991.130.00777.960.730.110.120.0000.59
Diesel for transporting reinforcing steel barst0.018.41500.240.0043.280.040.010.010.0000.03
CMElectricitykWh523.90387.165448.550.001456.442.050.130.600.0000.16
Binding wirest0.0242.50616.900.00297.430.170.020.110.0000.07
CTDiesel for component transportationt0.73574.7834,195.510.012958.762.790.420.440.0002.26
OAPost-cast Concrete C40m311.2934090.2228,637.510.008058.0610.671.394.010.0006.35
Shimming iron partst0.101237.392917.070.001162.800.820.080.770.0000.32
Grouting material for C40m30.2486.76607.470.00170.930.230.030.090.0000.13
Diesel for construction machineryt0.61480.9328,612.220.012475.672.330.350.370.0001.89
Total 15,117.24211,833.610.0959,096.4350.905.8622.640.00125.47
Table A5. Environmental impacts of prefabricated beam-slabs.
Table A5. Environmental impacts of prefabricated beam-slabs.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C40m3114.0241,295.56289,128.930.0381,355.50107.7614.0440.500.00064.06
Reinforcing steel barst14.7738,944.52577,453.250.43268,582.91161.3215.1696.520.00057.41
MTDiesel for transporting Concretet1.871480.0388,052.650.037618.747.181.081.130.0015.81
Diesel for transporting reinforcing steel barst0.0967.644024.090.00348.180.330.050.050.0000.27
CMElectricitykWh5130.693791.5853,359.160.0014,263.3120.061.305.900.0001.54
Binding wirest0.15341.974963.390.002393.061.400.140.860.0000.54
CTDiesel for component transportationt7.055567.66331,240.780.1228,660.5527.024.064.250.00321.85
OAPost-cast Concrete C40m3102.6137,166.01260,216.040.0273,219.9596.9812.6436.450.00057.66
Shimming iron partst0.992324.8228,567.670.0011,387.678.080.807.530.0003.13
Grouting material C40m32.35849.705949.150.001673.982.220.290.830.0001.32
Diesel for construction machineryt5.964709.87280,207.420.1024,244.9022.853.443.600.00318.48
Total 136,539.371,923,162.540.74513,748.76455.2052.99197.620.008232.07
Table A6. Environmental impacts of prefabricated foundations.
Table A6. Environmental impacts of prefabricated foundations.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
MPConcrete C30m343.812014,148.13100,616.190.0129,305.6938.105.0014.130.00021.98
Reinforcing steel barst9.4624,929.14369,638.950.27171,925.09103.269.7061.790.00036.75
MTDiesel for transporting Concretet0.71557.0233,139.280.012867.372.700.410.430.0002.19
Diesel for transporting reinforcing steel barst0.0543.302575.900.00222.880.210.030.030.0000.17
CMElectricitykWh2190.601618.8522,782.240.006089.878.570.552.520.0000.66
Binding wirest0.09218.913177.220.001531.870.900.090.550.0000.34
CTDiesel for component transportationt2.752169.77129,087.470.0511,169.2710.531.581.660.0018.51
OAShimming iron partst0.09212.272608.440.001039.780.740.070.690.0000.29
Grouting material C30m30.74237.781691.030.00492.530.640.080.240.0000.37
Diesel for construction machineryt0.23184.1810,957.390.00948.090.890.130.140.0000.72
Total 44,319.35676,274.080.35225,592.43166.5417.6682.170.00271.98

Appendix A.2. Environmental Costs

Table A7. Environmental costs of prefabricated walls.
Table A7. Environmental costs of prefabricated walls.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete—C40m3226.60822,981.19158.600.00224.76366.2320.3755.540.011114.13
Foamed ceramicsm3216.19239,649.6185.360.01167.53421.0722.9627.780.00830.07
MTDiesel for transporting Concretet3.724823.6548.300.0021.0524.411.571.550.03101.00
Diesel for transporting foamed ceramicst1.671369.5721.670.009.4410.950.700.700.0145.32
CMElectricitykWh19,925.9784123.0857.200.0077.00133.233.6815.810.0052.48
Binding wiret0.155100.371.440.003.492.520.100.620.004.92
CTDiesel for component transportationt18.5194096.49240.230.01104.68121.397.807.710.13502.34
OADry-mixed mortar DMM20m33.542319.642.240.003.295.270.290.790.0015.60
Shimming iron partst0.909600.717.280.0014.6112.750.544.790.0025.29
Concrete grouting material—C40m37.289739.205.100.007.2311.780.661.790.0035.84
Diesel for construction machineryt1.039229.8713.480.005.876.810.440.430.0128.19
Total 74,033.38640.900.02638.951116.4159.11117.510.192755.17
Table A8. Environmental costs of prefabricated columns.
Table A8. Environmental costs of prefabricated columns.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete C40m390.419168.7563.280.0089.67146.118.1322.160.01444.50
Reinforcing steel barst23.1117,060.66249.350.01584.10431.5917.31104.200.01785.93
MTDiesel for the transportation of Concretet1.49328.6119.270.008.409.740.630.620.0140.30
Diesel for the transportation of reinforcing steel barst0.1329.631.740.000.760.880.060.060.003.63
CMElectricitykWh4520.45935.3712.980.0017.4730.220.833.590.0011.91
Timber spacerst0.23112149.812.140.005.203.750.160.920.007.34
CTDiesel for component transportationt5.861297.0676.060.0033.1538.442.472.440.04159.05
OADry-mixed mortar DMM20m30.7265.260.460.000.671.080.060.160.003.18
Shimming iron partst0.19122.651.490.002.982.600.110.980.005.16
Grouting material—C40m31.49150.931.040.001.482.410.130.360.007.32
Diesel for construction machineryt0.3372.954.280.001.862.160.140.140.008.95
Total 29,381.68432.090.02745.74668.9830.02135.630.071477.28
Table A9. Environmental costs of prefabricated beams.
Table A9. Environmental costs of prefabricated beams.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete C40m341.264184.7928.880.0040.9366.693.7110.110.00202.88
Reinforcing steel barst8.526288.4791.910.00215.29159.086.3838.410.00289.69
MTDiesel for transporting Concretet0.68149.988.800.003.834.440.290.280.0018.39
Diesel for transporting reinforcing steel barst0.0510.920.640.000.280.320.020.020.001.34
CMElectricitykWh2475.86512.317.110.009.5716.550.461.960.006.52
Binding wirest0.0955.220.790.001.921.380.060.340.002.71
CTDiesel for component transportationt2.63581.1634.080.0014.8517.221.111.090.0271.27
OAShimming iron partst0.0536.180.440.000.880.770.030.290.001.52
Grouting material—C40m30.7575.770.520.000.741.210.070.180.003.67
Diesel for construction machineryt0.2249.612.910.001.271.470.090.090.006.08
Total 11,944.42176.080.01289.56269.1412.2152.790.03604.07
Table A10. Environmental costs of prefabricated slabs.
Table A10. Environmental costs of prefabricated slabs.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete C40m311.64221180.688.150.0011.5518.821.052.850.0057.24
Reinforcing steel barst1.841355.5519.810.0046.4134.291.388.280.0062.45
MTDiesel for transporting Concretet0.1942.322.480.001.081.250.080.080.005.19
Diesel for transporting reinforcing steel barst0.012.350.140.000.060.070.000.000.000.29
CMElectricitykWh523.90108.411.500.002.023.500.100.420.001.38
Binding wirest0.0211.900.170.000.410.300.010.070.000.58
CTDiesel for component transportationt0.73160.949.440.004.114.770.310.300.0019.74
OAPost-cast Concrete C40m311.2931145.267.900.0011.2018.251.022.770.0055.52
Shimming iron partst0.10166.470.810.001.621.410.060.530.002.80
Grouting material—C40m30.2424.290.170.000.240.390.020.060.001.18
Diesel for construction machineryt0.68134.667.900.003.443.990.260.250.0016.51
Total 4232.8358.470.0082.1487.044.2715.620.01222.87
Table A11. Environmental costs of prefabricated beam-slabs.
Table A11. Environmental costs of prefabricated beam-slabs.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete C40m3114.0211,562.7679.800.00113.08184.2610.2527.940.01560.56
Reinforcing steel barst14.7710,904.47159.380.01373.33275.8511.0766.600.01502.33
MTDiesel for transporting Concretet1.87414.4124.300.0010.5912.280.790.780.0150.82
Diesel for transporting reinforcing steel barst0.0918.941.110.000.480.560.040.040.002.32
CMElectricitykWh5130.691061.6414.730.0019.8334.300.954.070.0013.51
Binding wirest0.1595.751.370.003.332.400.100.590.004.69
CTDiesel for component transportationt7.051558.9591.420.0039.8446.202.972.930.05191.17
OAPost-cast Concrete C40m3102.6110,406.4871.820.00101.78165.849.2225.150.01504.51
Shimming iron partst0.99650.957.880.0015.8313.810.585.190.0027.41
Grouting material C40m32.35237.921.640.002.333.790.210.570.0011.53
Diesel for construction machineryt6.621318.7677.340.0033.7039.082.512.480.04161.72
Total 38,231.02530.790.01714.11778.3838.68136.360.122030.58
Table A12. Environmental costs of prefabricated foundations.
Table A12. Environmental costs of prefabricated foundations.
StageResourceUnitQuantityCCPPEDADPWRDAPEPPMFODPPOF
CNYCNYCNYCNYCNYCNYCNYCNYCNY
MPConcrete C30m343.81203961.4827.770.0040.7365.153.659.750.00192.32
Reinforcing steel barst9.466980.16102.020.01238.98176.587.0842.630.00321.55
MTDiesel for transporting Concretet0.71155.979.150.003.994.620.300.290.0019.13
Diesel for transporting reinforcing steel barst0.0512.120.710.000.310.360.020.020.001.49
CMElectricitykWh2190.60453.286.290.008.4614.650.401.740.005.77
Binding wirest0.0961.290.880.002.131.540.060.380.003.00
CTDiesel for component transportationt2.75607.5435.630.0015.5318.001.161.140.0274.50
OAShimming iron partst0.0959.440.720.001.451.260.050.470.002.50
Grouting material C30m30.7466.580.470.000.681.090.060.160.003.23
Diesel for construction machineryt0.2351.573.020.001.321.530.100.100.006.32
Total 12,409.42186.650.01313.57284.7812.8956.690.03629.82

Appendix A.3. Sensitivity Analysis

Table A13. Sensitivity analysis of monetary values on environmental costs: Absolute value.
Table A13. Sensitivity analysis of monetary values on environmental costs: Absolute value.
CNYCCPPEDADPWRDAPEPPMFODPPOF
−20%152,592.1186,233.6186,638.6186,081.8185,997.7186,607.2186,535.7186,638.5185,094.7
−15%161,103.7186,334.9186,638.6186,221.0186,157.9186,615.1186,561.4186,638.6185,480.7
−10%169,615.4186,436.1186,638.6186,360.2186,318.2186,622.9186,587.2186,638.6185,866.7
−5%178,127.0186,537.4186,638.6186,499.4186,478.4186,630.8186,612.9186,638.6186,252.6
0%186,638.6186,638.6186,638.6186,638.6186,638.6186,638.6186,638.6186,638.6186,638.6
5%195,150.3186,739.9186,638.6186,777.8186,798.9186,646.5186,664.4186,638.7187,024.6
10%203,661.9186,841.1186,638.6186,917.0186,959.1186,654.4186,690.1186,638.7187,410.6
15%212,173.5186,942.4186,638.6187,056.2187,119.3186,662.2186,715.8186,638.7187,796.6
20%220,685.2187,043.6186,638.6187,195.4187,279.6186,670.1186,741.5186,638.7188,182.6
Table A14. Sensitivity analysis of monetary values on environmental costs: Relative percentage.
Table A14. Sensitivity analysis of monetary values on environmental costs: Relative percentage.
%CCPPEDADPWRDAPEPPMFODPPOF
−20%−18.24%−0.22%0.00%−0.30%−0.34%−0.02%−0.06%0.00%−0.83%
−15%−13.68%−0.16%0.00%−0.22%−0.26%−0.01%−0.04%0.00%−0.62%
−10%−9.12%−0.11%0.00%−0.15%−0.17%−0.01%−0.03%0.00%−0.41%
−5%−4.56%−0.05%0.00%−0.07%−0.09%0.00%−0.01%0.00%−0.21%
0%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
5%4.56%0.05%0.00%0.07%0.09%0.00%0.01%0.00%0.21%
10%9.12%0.11%0.00%0.15%0.17%0.01%0.03%0.00%0.41%
15%13.68%0.16%0.00%0.22%0.26%0.01%0.04%0.00%0.62%
20%18.24%0.22%0.00%0.30%0.34%0.02%0.06%0.00%0.83%

References

  1. Cheng, B.; Lu, K.; Li, J.; Chen, H.; Luo, X.; Shafique, M. Comprehensive assessment of embodied environmental impacts of buildings using normalized environmental impact factors. J. Clean. Prod. 2022, 334, 130083. [Google Scholar] [CrossRef]
  2. Tavares, V.; Soares, N.; Raposo, N.; Marques, P.; Freire, F. Prefabricated versus conventional construction: Comparing life-cycle impacts of alternative structural materials. J. Build. Eng. 2021, 41, 102705. [Google Scholar] [CrossRef]
  3. Han, Q.; Chang, J.; Liu, G.; Zhang, H. The carbon emission assessment of a building with different prefabrication rates in the construction stage. Int. J. Environ. Res. Public Health 2022, 19, 2366. [Google Scholar] [CrossRef] [PubMed]
  4. Navaratnam, S.; Ngo, T.; Gunawardena, T.; Henderson, D. Performance review of prefabricated building systems and future research in Australia. Buildings 2019, 9, 38. [Google Scholar] [CrossRef]
  5. Andersen, S.C.; Sohn, J.; Oldfield, P.; Birkved, M. Evaluating the environmental impacts of conventional and modular buildings in absolute measures: A case study across different geographical contexts. Build. Environ. 2022, 223, 109509. [Google Scholar] [CrossRef]
  6. Guaygua, B.; Sánchez-Garrido, A.J.; Yepes, V. Life cycle assessment of seismic resistant prefabricated modular buildings. Heliyon 2024, 10, e39458. [Google Scholar] [CrossRef]
  7. Ansah, M.K.; Chen, X.; Yang, H.; Lu, L.; Lam, P.T.I. Developing an automated BIM-based life cycle assessment approach for modularly designed high-rise buildings. Environ. Impact Assess. Rev. 2021, 90, 106618. [Google Scholar] [CrossRef]
  8. Lu, K.; Deng, X. OpenBIM-based assessment for social cost of carbon through building life cycle. Sustain. Cities Soc. 2023, 99, 104871. [Google Scholar] [CrossRef]
  9. Lu, K.; Deng, X. Comprehensive carbon cost of building projects: Optimization and relationship. Build. Environ. 2025, 280, 113157. [Google Scholar] [CrossRef]
  10. Pons, O.; Wadel, G. Environmental impacts of prefabricated school buildings in Catalonia. Habitat Int. 2011, 35, 553–563. [Google Scholar] [CrossRef]
  11. Quale, J.; Eckelman, M.J.; Williams, K.W.; Sloditskie, G.; Zimmerman, J.B. Construction Matters: Comparing Environmental Impacts of Building Modular and Conventional Homes in the United States. J. Ind. Ecol. 2012, 16, 243–253. [Google Scholar] [CrossRef]
  12. Kamali, M.; Hewage, K.; Sadiq, R. Conventional versus modular construction methods: A comparative cradle-to-gate LCA for residential buildings. Energy Build. 2019, 204, 109479. [Google Scholar] [CrossRef]
  13. Jayawardana, J.; Sandanayake, M.; Jayasinghe, J.A.S.C.; Kulatunga, A.K.; Zhang, G. A comparative life cycle assessment of prefabricated and traditional construction—A case of a developing country. J. Build. Eng. 2023, 72, 106550. [Google Scholar] [CrossRef]
  14. Wang, S.; Sinha, R. Life cycle assessment of different prefabricated rates for building construction. Buildings 2021, 11, 552. [Google Scholar] [CrossRef]
  15. Tumminia, G.; Guarino, F.; Longo, S.; Ferraro, M.; Cellura, M.; Antonucci, V. Life cycle energy performances and environmental impacts of a prefabricated building module. Renew. Sustain. Energy Rev. 2018, 92, 272–283. [Google Scholar] [CrossRef]
  16. Balasbaneh, A.T.; Ramli, M.Z. A comparative life cycle assessment (LCA) of concrete and steel-prefabricated prefinished volumetric construction structures in Malaysia. Environ. Sci. Pollut. Res. 2020, 27, 43186–43201. [Google Scholar] [CrossRef]
  17. Baldrich Aragó, A.; Roig Hernando, J.; Llovera Saez, F.J.; Coll Bertran, J. Quantity surveying and BIM 5D. Its implementation and analysis based on a case study approach in Spain. J. Build. Eng. 2021, 44, 103234. [Google Scholar] [CrossRef]
  18. Banihashemi, S.; Khalili, S.; Sheikhkhoshkar, M.; Fazeli, A. Machine learning-integrated 5D BIM informatics: Building materials costs data classification and prototype development. Innov. Infrastruct. Solut. 2022, 7, 215. [Google Scholar] [CrossRef]
  19. Hosamo, H.H.; Rolfsen, C.N.; Zeka, F.; Sandbeck, S.; Said, S.; Sætre, M.A. Navigating the Adoption of 5D Building Information Modeling: Insights from Norway. Infrastructures 2024, 9, 75. [Google Scholar] [CrossRef]
  20. Antwi-Afari, P.; Ng, S.T.; Chen, J.; Zheng, X.M. Determining the impacts and recovery potentials of a modular designed residential building using the novel LCA-C2C–PBSCI method. J. Clean. Prod. 2022, 378, 134575. [Google Scholar] [CrossRef]
  21. ISO 14040; Environmental Management—Life Cycle Assessment—Principles and Framework. International Organization for Standardization: Geneva, Switzerland, 2006; pp. 1–20. Available online: https://www.iso.org/standard/37456.html (accessed on 1 June 2025).
  22. Faludi, J.; Lepech, M.D.; Loisos, G. Using life cycle assessment methods to guide architectural decision-making for sustainable prefabricated modular buildings. J. Green Build. 2012, 7, 151–170. [Google Scholar] [CrossRef]
  23. Bonamente, E.; Cotana, F. Carbon and energy footprints of prefabricated industrial buildings: A systematic life cycle assessment analysis. Energies 2015, 8, 12685–12701. [Google Scholar] [CrossRef]
  24. Jayawardana, J.; Sandanayake, M.; Kulatunga, A.K.; Jayasinghe, J.A.S.C.; Zhang, G.; Osadith, S.A.U. Evaluating the Circular Economy Potential of Modular Construction in Developing Economies—A Life Cycle Assessment. Sustainability 2023, 15, 16336. [Google Scholar] [CrossRef]
  25. Achenbach, H.; Wenker, J.L.; Rüter, S. Life cycle assessment of product- and construction stage of prefabricated timber houses: A sector representative approach for Germany according to EN 15804, EN 15978 and EN 16485. Eur. J. Wood Wood Prod. 2018, 76, 711–729. [Google Scholar] [CrossRef]
  26. Lu, K.; Deng, X.; Jiang, X.; Cheng, B.; Tam, V.W.Y. A review on life cycle cost analysis of buildings based on building information modeling. J. Civ. Eng. Manag. 2023, 29, 268–288. [Google Scholar] [CrossRef]
  27. Lu, K.; Jiang, X.; Yu, J.; Tam, V.W.Y.; Skitmore, M. Integration of life cycle assessment and life cycle cost using building information modeling: A critical review. J. Clean. Prod. 2021, 285, 125438. [Google Scholar] [CrossRef]
  28. Xu, Z.; Zhang, L.; Li, H.; Lin, Y.H.; Yin, S. Combining IFC and 3D tiles to create 3D visualization for building information modeling. Autom. Constr. 2020, 109, 102995. [Google Scholar] [CrossRef]
  29. Cheng, J.C.P.; Tan, Y.; Song, Y.; Liu, X.; Wang, X. A semi-automated approach to generate 4D/5D BIM models for evaluating different offshore oil and gas platform decommissioning options. Vis. Eng. 2017, 5, 12. [Google Scholar] [CrossRef]
  30. Alrashed, I.; Kantamaneni, K. A 5D building information model (BIM) for potential cost-benefit housing: A case of Kingdom of Saudi Arabia (KSA). Infrastructures 2018, 3, 13. [Google Scholar] [CrossRef]
  31. Zhang, A.; Zhou, X.; Wang, F.; Yang, J. A multiobjective optimisation and display framework for time-cost-carbon emissions in building materialisation phase based on nD BIM concept. J. Build. Eng. 2025, 103, 111993. [Google Scholar] [CrossRef]
  32. Pishdad, P.; Onungwa, I.O. Analysis of 5D BIM for cost estimation, cost control, and payments. J. Inf. Technol. Constr. 2024, 29, 525–548. [Google Scholar] [CrossRef]
  33. Stanley, R.; Thurnell, D. The benefits of, and barriers to, implementation of 5D BIM for quantity surveying in New Zealand. Australas. J. Constr. Econ. Build. 2014, 14, 105–117. [Google Scholar] [CrossRef]
  34. Mayouf, M.; Gerges, M.; Cox, S. 5D BIM: An investigation into the integration of quantity surveyors within the BIM process. J. Eng. Des. Technol. 2019, 17, 537–553. [Google Scholar] [CrossRef]
  35. Kehily, D.; Underwood, J. Embedding life cycle costing in 5D BIM. J. Inf. Technol. Constr. 2017, 22, 145–167. [Google Scholar]
  36. Lu, Q.; Won, J.; Cheng, J.C.P. A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM). Int. J. Proj. Manag. 2016, 34, 3–21. [Google Scholar] [CrossRef]
  37. Amin Ranjbar, A.; Ansari, R.; Taherkhani, R.; Hosseini, M.R. Developing a novel cash flow risk analysis framework for construction projects based on 5D BIM. J. Build. Eng. 2021, 44, 103341. [Google Scholar] [CrossRef]
  38. Ding, L.; Zhou, Y.; Akinci, B. Building Information Modeling (BIM) application framework: The process of expanding from 3D to computable nD. Autom. Constr. 2014, 46, 82–93. [Google Scholar] [CrossRef]
  39. Manzoor, B.; Charef, R.; Antwi-Afari, M.F.; Alotaibi, K.S.; Harirchian, E. Revolutionizing Construction Safety: Unveiling the Digital Potential of Building Information Modeling (BIM). Buildings 2025, 15, 828. [Google Scholar] [CrossRef]
  40. GhaffarianHoseini, A.; Zhang, T.; Nwadigo, O.; GhaffarianHoseini, A.; Naismith, N.; Tookey, J.; Raahemifar, K. Application of nD BIM Integrated Knowledge-based Building Management System (BIM-IKBMS) for inspecting post-construction energy efficiency. Renew. Sustain. Energy Rev. 2017, 72, 935–949. [Google Scholar] [CrossRef]
  41. GhaffarianHoseini, A.; Zhang, T.; Naismith, N.; GhaffarianHoseini, A.; Doan, D.T.; Rehman, A.U.; Nwadigo, O.; Tookey, J. ND BIM-integrated knowledge-based building management: Inspecting post-construction energy efficiency. Autom. Constr. 2019, 97, 13–28. [Google Scholar] [CrossRef]
  42. Manzoor, B.; Othman, I.; Gardezi, S.S.S.; Harirchian, E. Strategies for adopting building information modeling (BIM) in sustainable building projects—A case of Malaysia. Buildings 2021, 11, 249. [Google Scholar] [CrossRef]
  43. Lu, K.; Deng, X. OpenBIM driven marginal abatement cost of low-carbon measures in building design. Appl. Energy 2025, 377, 124477. [Google Scholar] [CrossRef]
  44. Deng, X.; Lu, K. Multi-level assessment for embodied carbon of buildings using multi-source industry foundation classes. J. Build. Eng. 2023, 72, 106705. [Google Scholar] [CrossRef]
  45. Lu, K.; Deng, X.; Zhai, X. OpenBIM-based simulation of building operational carbon under different information availability. Smart Sustain. Built Environ. 2024; ahead-of-print. [Google Scholar] [CrossRef]
  46. Whitlock, K.; Abanda, F.H.; Manjia, M.B.; Pettang, C.; Nkeng, G.E. 4D BIM for Construction Logistics Management. CivilEng 2021, 2, 325–348. [Google Scholar] [CrossRef]
  47. Umar, T. Challenges of BIM implementation in GCC construction industry. Eng. Constr. Archit. Manag. 2022, 29, 1139–1168. [Google Scholar] [CrossRef]
  48. ISO 14008:2019; Monetary Valuation of Environmental Impacts and Related Environmental Aspects. International Organization for Standardization: Geneva, Switzerland, 2019. Available online: https://www.iso.org/standard/43243.html (accessed on 1 June 2025).
  49. ISO 21931-1; Sustainability in Buildings and Civil Engineering Works—Framework for Methods of Assessment of the Environmental, Social and Economic Performance of Construction Works as a Basis for Sustainability Assessment—Part 1: Buildings. International Organization for Standardization: Geneva, Switzerland, 2022; pp. 1–57. Available online: https://www.iso.org/standard/71183.html (accessed on 1 June 2025).
  50. IKE Chinese Life Cycle Database (CLCD). Integrated Knowledge for Our Environment (IKE). 2025. Available online: https://www.weblca.net/database (accessed on 1 June 2025).
  51. YJK. YJK Building Structural Design Software (YJK-A); YJK Building Software: Beijing, China, 2024; Available online: https://www.yjk.cn/jgrj/ (accessed on 1 June 2025).
  52. Autodesk. Autodesk Revit 2018. 2024. Available online: https://www.autodesk.com.cn/products/revit/overview (accessed on 1 June 2025).
  53. BUZZ BeePC V4.2. BUZZ Technology. 2024. Available online: http://www.wengwengkeji.com/ (accessed on 1 June 2025).
  54. GB/T51061-2014; Code for Grid Identification System. Ministry of Housing and Urban-Rural Development of the People’s Republic of China: Beijing, China, 2014. Available online: https://ebook.chinabuilding.com.cn/zbooklib/bookpdf/probation?SiteID=1&bookID=59321 (accessed on 1 June 2025).
  55. BuildingSmart. Industry Foundation Classes (IFC). 2021. Available online: https://standards.buildingsmart.org/IFC/RELEASE/IFC4/FINAL/HTML/ (accessed on 15 March 2013).
  56. DL/T5341-2021; Standard Method of Measurement for Transformer Project. National Energy Administration of the People’s Republic of China: Beijing, China, 2021. Available online: https://ndls.org.cn/standard/detail/08312634449e1d215bd4ef2ff3342909 (accessed on 1 June 2025).
  57. Zhu, J.; Chen, X.; Wang, D.; Zuo, J. Quantitative analysis on the embodied environmental impact of buildings based on WTP. J. Civ. Archit. Environ. Eng. 2016, 38, 72–77. [Google Scholar] [CrossRef]
  58. Cao, X. Environmental Impact Assessment and Comparative Studies on Industrialized House and Traditional House Construction. Master’s Thesis, Tsinghua University, Beijing, China, 2012. Available online: https://newetds.lib.tsinghua.edu.cn/qh/paper/summary?dbCode=ETDQH&sysId=202306 (accessed on 1 June 2025).
  59. Li, X.D.; Wu, X.; Zhang, Z.H. Study on social WTP for environmental impacts based on the LCA theory. J. Harbin Inst. Technol. 2005, 37, 1507–1510. [Google Scholar]
  60. Chen, Y.; Zhou, Y.; Feng, W.; Fang, Y.; Feng, A. Factors that influence the quantification of the embodied carbon emission of prefabricated buildings: A systematic review, meta-analysis and the way forward. Buildings 2022, 12, 1265. [Google Scholar] [CrossRef]
  61. Demertzi, M.; Silvestre, J.; Garrido, M.; Correia, J.R.; Durão, V.; Proença, M. Life cycle assessment of alternative building floor rehabilitation systems. Structures 2020, 26, 237–246. [Google Scholar] [CrossRef]
  62. Trigaux, D.; Oosterbosch, B.; De Troyer, F.; Allacker, K. A design tool to assess the heating energy demand and the associated financial and environmental impact in neighbourhoods. Energy Build. 2017, 152, 516–523. [Google Scholar] [CrossRef]
  63. Nydahl, H.; Andersson, S.; Åstrand, A.P.; Olofsson, T. Extended building life cycle cost assessment with the inclusion of monetary evaluation of climate risk and opportunities. Sustain. Cities Soc. 2022, 76, 103451. [Google Scholar] [CrossRef]
  64. Lu, K.; Jiang, X.; Tam, V.W.Y.; Li, M.; Wang, H.; Xia, B.; Chen, Q. Development of a carbon emissions analysis framework using building information modeling and life cycle assessment for the construction of hospital projects. Sustainability 2019, 11, 6274. [Google Scholar] [CrossRef]
  65. Umar, T. Key factors influencing the implementation of three-dimensional printing in construction. Proc. Inst. Civ. Eng. Manag. Procure. Law 2020, 174, 104–114. [Google Scholar] [CrossRef]
  66. Elmousalami, H.H. Artificial intelligence and parametric construction cost estimate modeling: State-of-the-art review. J. Constr. Eng. Manag. 2020, 146, 03119008. [Google Scholar] [CrossRef]
  67. Zhang, P.-F.; Zhang, D.; Zhao, X.-L.; Zhao, X.; Iqbal, M.; Tuerxunmaimaiti, Y.; Zhao, Q. Natural language processing-based deep transfer learning model across diverse tabular datasets for bond strength prediction of composite bars in concrete. Comput. -Aided Civ. Infrastruct. Eng. 2025, 40, 917–939. [Google Scholar] [CrossRef]
  68. Zhang, P.F.; Zhao, X.L.; Zhang, D.; Iqbal, M.; Zhao, X.; Zhao, Q.; Tuerxunmaimaiti, Y.; Yu, C. Prediction of bond strength and failure mode of FRP bars embedded in UHPC or UHPSSC utilising extreme gradient boosting technique. Compos. Struct. 2024, 346, 118437. [Google Scholar] [CrossRef]
  69. Lu, K.; Deng, X.; Cheng, B.; Tam, V.W.Y. Commodity futures pricing of carbon policy costs in construction projects. Eng. Constr. Archit. Manag. 2025; ahead-of-print. [Google Scholar] [CrossRef]
  70. Nasab, T.J.; Monavari, S.M.; Jozi, S.A.; Majedi, H. Development of an environmental life cycle cost model for high-rise construction in Tehran. Int. J. Environ. Sci. Technol. 2022, 19, 9873–9882. [Google Scholar] [CrossRef]
  71. Ibn-Mohammed, T.; Greenough, R.; Taylor, S.; Ozawa-Meida, L.; Acquaye, A. Integrating economic considerations with operational and embodied emissions into a decision support system for the optimal ranking of building retrofit options. Build. Environ. 2014, 72, 82–101. [Google Scholar] [CrossRef]
  72. Schmidt, M.; Crawford, R.H.; Warren-Myers, G. Integrating life-cycle GHG emissions into a building’s economic evaluation. Build. Cities 2020, 1, 361–378. [Google Scholar] [CrossRef]
  73. Liu, H.; Zainul Abidin, N. A Review on Research of Prefabricated Building Costs: Exploring Collaborations, Intellectual Basis, and Research Trends. Sustainability 2024, 16, 9823. [Google Scholar] [CrossRef]
Figure 1. Boundary scope of environmental costs in prefabricated building construction.
Figure 1. Boundary scope of environmental costs in prefabricated building construction.
Civileng 06 00036 g001
Figure 2. Five-dimensional BIM coding system for prefabricated buildings.
Figure 2. Five-dimensional BIM coding system for prefabricated buildings.
Civileng 06 00036 g002
Figure 3. Building information modeling of the substation building in case study.
Figure 3. Building information modeling of the substation building in case study.
Civileng 06 00036 g003
Figure 4. Spatial analysis of environmental impacts in the case prefabricated building.
Figure 4. Spatial analysis of environmental impacts in the case prefabricated building.
Civileng 06 00036 g004
Figure 5. Temporal analysis of environmental impacts in the case prefabricated building.
Figure 5. Temporal analysis of environmental impacts in the case prefabricated building.
Civileng 06 00036 g005
Figure 6. Spatial analysis of environmental costs in the case prefabricated building.
Figure 6. Spatial analysis of environmental costs in the case prefabricated building.
Civileng 06 00036 g006
Figure 7. Temporal analysis of environmental costs in the case prefabricated building.
Figure 7. Temporal analysis of environmental costs in the case prefabricated building.
Civileng 06 00036 g007
Figure 8. Sensitivity analysis of monetary values.
Figure 8. Sensitivity analysis of monetary values.
Civileng 06 00036 g008
Table 2. Concepts and applications from 3D BIM to nD BIM.
Table 2. Concepts and applications from 3D BIM to nD BIM.
ConceptDimensionApplicationRef.
3DGeometryVisualization[28,29]
Clash detection[30]
4DTimeSchedule simulation[29,30,31]
Progress tracking[32]
5DCostQuantity surveying[17,18,19,30,31,33,34]
Life cycle costing[35]
Financial decision making[36,37]
Cost monitoring and payment[19,32]
nDQualityQuality management[38]
SafetySafety management[38,39]
EnergyEnergy efficiency[40,41,42]
Carbon emissionCarbon emission calculation[31,38]
Table 3. Three-dimensional BIM coding of components for spatial dimension.
Table 3. Three-dimensional BIM coding of components for spatial dimension.
CodingNameIFC Entity
PWPrefabricated walllfcWall
PCPrefabricated columnlfcColumn
PBPrefabricated beamlfcBeam
PSPrefabricated slablfcSlab
PBSPrefabricated beam-slabIfcBuildingElementProxy
PFPrefabricated foundation IfcFooting
Table 4. Four-dimensional BIM coding of components for temporal dimension.
Table 4. Four-dimensional BIM coding of components for temporal dimension.
CodingNameMeaning
MPMaterial productionExtracting raw materials from nature and processing them into building materials.
MTMaterial transportationTransporting materials from the production site to the manufacturing factory.
CMComponent manufacturingProcessing materials into prefabricated components in the manufacturing factory.
CTComponent transportationTransporting components from the manufacturing factory to the construction site.
OAOn-site assemblyAssembling and constructing components at the construction site.
Table 5. Five-dimensional BIM coding of components for environmental costs.
Table 5. Five-dimensional BIM coding of components for environmental costs.
CodingNameCharacteristicsUnit
Partial precast concrete components in the main structure are designed as cast-in-place.
SE46Rectangular column1. Concrete strength grade; 2. Concrete type; 3. Transportation distancem3
SE47Structural bracketm3
SE48Rectangular beamm3
SE49Lintel beam1. Concrete strength grade; 2. Concrete type; 3. Production or purchase; 4. Transportation distancem3
SE50Crane beamm3
SE51Thin-web beamm3
SE52Light-aggregate concrete wall panelm3
SE53Slab1. Concrete strength grade; 2. Concrete type; 3. Slab form; 4. Production or purchase; 5. Transportation distancem3
SE54Trench cover slab1. Concrete strength grade; 2. Concrete type; 3. Transportation distancem3
SE55Angle steel framed concrete cover slabm3
SE56Small-sized component1. Component name; 2. Concrete strength grade; 3. Concrete type; 4. Transportation distancem3
SE57Prestressed concrete slab1. Concrete strength grade; 2. Concrete type; 3. Slab form; 4. Transportation distancem3
SE58Prestressed concrete crane beam1. Concrete strength grade; 2. Concrete type; 3. Transportation distancem3
Precast concrete components in the main structure are designed as monolithic prefabricated units
SE59Precast concrete foundation1. Component name; 2. Concrete strength gradem3
SE60Precast concrete columnm3
SE61Precast concrete beamm3
SE62Precast concrete slabm3
SE63Precast concrete air conditioning slabm3
SE64Precast concrete wall panelm3
SE65Precast concrete parapet wallm3
SE66Precast concrete copingm3
SE67Precast concrete column capm3
SE68Precast concrete cable trenchm3
SE69Precast concrete water tankm3
SE70Precast concrete fence panelm3
SE71Precast firewallm3
SE72Steel truss composite floor slabm2
SE73Precast cover platem2
SE74Fiberglass grille1. Materialm2
SE75Aluminum-magnesium-manganese parapet copingm
Table 6. Environmental impact factors of main resources.
Table 6. Environmental impact factors of main resources.
NameUnitCCPPEDADPWRDAPEPPMFODPPOF
kgCO2eqMJkgSbeqkgkgSO2eqkgPO43−eqkgPM2.5eqkgCFC-11eqkgNMVOCeq
ElectricitykWh7.4 × 10−11.0 × 1014.7 × 10−72.83.9 × 10−32.5 × 10−41.2 × 10−33.4 × 10−93.0 × 10−4
Dieselt7.9 × 1024.7 × 1041.7 × 10−24.1 × 1033.85.8 × 10−16.0 × 10−14.2 × 10−43.1
Watert1.9 × 10−12.51.8 × 10−71.0 × 1031.0 × 10−31.0 × 10−43.1 × 10−44.2 × 10−107.6 × 10−5
Hot-rolled steel bart2.6 × 1033.9 × 1042.9 × 10−21.8 × 1041.1 × 1011.06.52.4 × 10−53.9
Ironwaret2.4 × 1032.9 × 1044.1 × 10−31.2 × 1048.28.1 × 10−17.62.0 × 10−53.2
Wire ropet2.3 × 1033.4 × 1042.8 × 10−21.6 × 1049.59.2 × 10−15.82.3 × 10−53.6
Embedded iron partt2.4 × 1032.9 × 1044.1 × 10−31.2 × 1048.28.1 × 10−17.72.0 × 10−53.2
Cementt5.7 × 10−27.9 × 10−12.5 × 10−61.22.1 × 10−41.2 × 10−46.8 × 10−51.1 × 10−95.5 × 10−5
Concrete C30m33.2 × 1022.3 × 1032.3 × 10−46.7 × 1028.7 × 10−11.1 × 10−13.2 × 10−13.8 × 10−65.0 × 10−1
Concrete C40m33.6 × 1022.5 × 1032.4 × 10−47.1 × 1029.5 × 10−11.2 × 10−13.6 × 10−13.8 × 10−65.6 × 10−1
Concrete C50m34.0 × 1022.8 × 1032.5 × 10−47.6 × 1021.01.3 × 10−13.9 × 10−13.8 × 10−66.2 × 10−1
Dry-mixed mortarm33.2 × 1022.3 × 1032.3 × 10−46.7 × 1028.7 × 10−11.1 × 10−13.2 × 10−13.8 × 10−65.0 × 10−1
Foamed ceramicm36.6 × 1021.4 × 1033.5 × 10−35.6 × 1021.11.5 × 10−11.9 × 10−14.2 × 10−74.4 × 10−1
Table 7. Monetary values of environmental costs based on willingness-to-pay (WTP).
Table 7. Monetary values of environmental costs based on willingness-to-pay (WTP).
Environmental IndicatorAbbreviationUnitMonetary ValueRef.
Climate change potentialCCPCNY/kgCO2eq0.28[57]
Primary energy demandPEDCNY/MJ0.00028[58]
Abiotic depletion potentialADPCNY/kgSbeq0.0191[59]
Water resource depletionWRDCNY/kg0.00139[57]
Acidification potentialAPCNY/kgSO2eq1.71[57]
Eutrophication potentialEPCNY/kgPO43−eq0.73[58]
Particulate matter formationPMFCNY/kgPM2.5eq0.69[57]
Ozone depletion potentialODPCNY/kgCFC-11eq16.24[57]
Photochemical ozone formationPOFCNY/kgNMVOCeq8.75[57]
Table 8. Background information and parameters of the substation building in case study.
Table 8. Background information and parameters of the substation building in case study.
ItemContent
Building type110 kV prefabricated substation
Building locationXiamen, China
Construction companyState Grid Fujian Electric Power Co., Ltd.
Building area1080 m2
Building floorOne floor
Building height12.55 m
Functional layout10 kV power distribution room, Main transformer room, Radiator room, 110 kV Gas Insulated Switchgear room, Secondary equipment room, Battery room, etc.
From concrete plant to prefabricated factory35 km
From steel plant to prefabricated factory30 km
From foam ceramic plant to prefabricated factory40 km
From prefabricated factory to construction site125 km
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Gao, X.; Chen, X.; Lu, K.; Deng, X. Monetizing Environmental Impacts into Environmental Costs During Prefabricated Building Construction: A 5D BIM-Enabled Analysis. CivilEng 2025, 6, 36. https://doi.org/10.3390/civileng6030036

AMA Style

Gao X, Chen X, Lu K, Deng X. Monetizing Environmental Impacts into Environmental Costs During Prefabricated Building Construction: A 5D BIM-Enabled Analysis. CivilEng. 2025; 6(3):36. https://doi.org/10.3390/civileng6030036

Chicago/Turabian Style

Gao, Xian, Xilong Chen, Kun Lu, and Xueyuan Deng. 2025. "Monetizing Environmental Impacts into Environmental Costs During Prefabricated Building Construction: A 5D BIM-Enabled Analysis" CivilEng 6, no. 3: 36. https://doi.org/10.3390/civileng6030036

APA Style

Gao, X., Chen, X., Lu, K., & Deng, X. (2025). Monetizing Environmental Impacts into Environmental Costs During Prefabricated Building Construction: A 5D BIM-Enabled Analysis. CivilEng, 6(3), 36. https://doi.org/10.3390/civileng6030036

Article Metrics

Back to TopTop