Stochastic Simulation of Construction Methods for Multi-purpose Utility Tunnels
Abstract
:1. Introduction
2. Materials and Methods
2.1. C&C Simulation Model
2.2. Microtunneling Simulation Model
3. Results
3.1. Numerical Example Description
3.2. Example Results
3.3. Four-Dimensional Modeling and Visualization
4. Discussion
5. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Alaghbandrad, A.; Hammad, A. Framework for multi-purpose utility tunnel lifecycle cost assessment and cost-sharing. Tunn. Undergr. Space Technol. 2020, 104, 103528. [Google Scholar] [CrossRef]
- Ormsby, C.M. A Framework for Estimating the Total Cost of Buried Municipal Infrastructure Renewal Projects; McGill University: Montreal, QC, Canada, 2009. [Google Scholar]
- Gagnon, M.; Gaudreault, V.; Overton, D. Age of Public Infrastructure: A Provincial Perspective; Statistics: Ottawa, ON, Canada, 2008. [Google Scholar]
- Oum, N. Modeling Socio-Economic Impacts of Infrastructure Works; Concordia University: Montreal, QC, Canada, 2017. [Google Scholar]
- Apak, M.Y.; Ozen, H.; Calis, M.; Golgeli, B.; Ataoglu, S. Applications of utility tunnels for natural gas pipelines. Tunn. Undergr. Space Technol. 2022, 122, 104243. [Google Scholar] [CrossRef]
- Cao, Y.; Gong, Z.; Li, N.; Wang, Q. How to Guarantee the Sustainable Operation and Maintenance of Urban Utility Tunnels? From the Perspective of Stakeholder and the Whole Life Cycle. Buildings 2023, 13, 1810. [Google Scholar] [CrossRef]
- Canto-Perello, J.; Curiel-Esparza, J. Assessing governance issues of urban utility tunnels. Tunn. Undergr. Space Technol. 2013, 33, 82–87. [Google Scholar] [CrossRef]
- Curiel-Esparza, J.; Canto-Perello, J.; Calvo, M.A. Establishing sustainable strategies in urban underground engineering. Sci. Eng. Ethics 2004, 10, 523–530. [Google Scholar] [CrossRef] [PubMed]
- Wu, C.; Wu, P.; Jiang, R.; Wang, J.; Wang, X.; Wan, M. Evaluating the economic and social benefits of multiutility tunnels with an agent-based simulation approach. Eng. Constr. Archit. Manag. 2022, 29, 1–25. [Google Scholar] [CrossRef]
- Sun, F.; Liu, C. An Exploratory Pledging Framework of Crowdfunding for Utilities Tunnel Engineering Project. Math. Probl. Eng. 2022, 2022, 4658454. [Google Scholar] [CrossRef]
- He, H. Incentive Mechanism of Utility Tunnel PPP Projects with User Involvement. Sustainability 2023, 15, 10771. [Google Scholar] [CrossRef]
- Genger, K.T.; Hammad, A.; Oum, N. Multi-objective optimization for selecting potential locations of multi-purpose utility tunnels considering agency and social lifecycle costs. Tunn. Undergr. Space Technol. 2023, 140, 105305. [Google Scholar] [CrossRef]
- Thomas, H.R.; Maloney, W.F.; Horner, R.M.W.; Smith, G.R.; Handa, V.K.; Sanders, S.R. Modeling construction labor productivity. J. Constr. Eng. Manag. 1990, 116, 705–726. [Google Scholar] [CrossRef]
- de Sol, C. Guide Pratique des Galeries Multiréseaux; Techni. Cités: Verrières le Buisson, France, 2005. [Google Scholar]
- Ramírez Chasco, F.D.A.; Meneses, A.S.; Cobo, E.P. Lezkairu Utilities Tunnel. Pract. Period. Struct. Des. Constr. 2011, 16, 73–81. [Google Scholar] [CrossRef]
- Byron, A.; Baker, J.; Condif, E.; Cotterell, J. MTC Utility Tunnel Design Final Report; Brigham Young University: Provo, UT, USA, 2015. [Google Scholar]
- Shannon, R.E. Simulation modeling and methodology. ACM SIGSIM Simul. Dig. 1977, 8, 33–38. [Google Scholar] [CrossRef]
- AbouRizk, S.M.; Halpin, D.W.; Lutz, J.D. State of the art in construction simulation. In Proceedings of the 24th Conference on Winter Simulation, Arlington, VA, USA, 13–16 December 1992; pp. 1271–1277. [Google Scholar] [CrossRef]
- Mawlana, M.; Vahdatikhaki, F.; Doriani, A.; Hammad, A. Integrating 4D modeling and discrete event simulation for phasing evaluation of elevated urban highway reconstruction projects. Autom. Constr. 2015, 60, 25–38. [Google Scholar] [CrossRef]
- Al-Bataineh, M.; AbouRizk, S.; Parkis, H. Using simulation to plan tunnel construction. J. Constr. Eng. Manag. 2013, 139, 564–571. [Google Scholar] [CrossRef]
- Liu, D.; Zhou, Y.; Jiao, K. TBM construction process simulation and performance optimization. Trans. Tianjin Univ. 2010, 16, 194–202. [Google Scholar] [CrossRef]
- Rahm, T.; Scheffer, M.; Thewes, M.; König, M.; Duhme, R. Evaluation of disturbances in mechanized tunneling using process simulation. Comput.-Aided Civ. Infrastruct. Eng. 2016, 31, 176–192. [Google Scholar] [CrossRef]
- Ruwanpura, J.Y.; AbouRizk, S.M.; Er, K.; Fernando, S. Special purpose simulation templates for tunnel construction operations. Can. J. Civ. Eng. 2001, 28, 222–237. [Google Scholar] [CrossRef]
- Touran, A.; Asai, T. Simulation of tunneling operations. J. Constr. Eng. Manag. 1987, 113, 554–568. [Google Scholar] [CrossRef]
- Abdallah, M.; Marzouk, M. Planning of tunneling projects using computer simulation and fuzzy decision making. J. Civ. Eng. Manag. 2013, 19, 591–607. [Google Scholar] [CrossRef]
- Dang, T.T.; Schoesser, B.; Thewes, M.; Koenig, M. Evaluation of productivities influenced by disturbances and different soil compositions in microtunnelling using process simulation. Tunn. Undergr. Space Technol. 2018, 76, 10–20. [Google Scholar] [CrossRef]
- Luo, R.Y.; Najafi, M. Productivity study of microtunneling pipe installation using simulation. J. Infrastruct. Syst. 2007, 13, 247–260. [Google Scholar] [CrossRef]
- Marzouk, M.; Abdallah, M.; El-Said, M. Modeling microtunneling projects using computer simulation. J. Constr. Eng. Manag. 2010, 136, 670–682. [Google Scholar] [CrossRef]
- Moharrami, S.; Taghaddos, M.; RazaviAlavi, S.; AbouRizk, S. A hybrid simulation approach for microtunneling construction planning. Constr. Innov. 2021, 21, 363–378. [Google Scholar] [CrossRef]
- Nido, A.A.; Knies, C.J.; Abraham, D.M. Role of operation simulation in the analysis and improvement of microtunnelling projects. Tunn. Undergr. Space Technol. 1999, 14, 1–19. [Google Scholar] [CrossRef]
- Jorjam, S.; Hammad, A. Discrete Event Simulation of Multi-purpose Utility Tunnels Construction Using Microtunneling. In Proceedings of the International Symposium on Automation and Robotics in Construction, Dubai, United Arab Emirates, 2–4 November 2021; IAARC Publications: Dubai, United Arab Emirates, 2021; pp. 303–310. [Google Scholar]
- Koo, B.; Fischer, M. Feasibility study of 4D CAD in commercial construction. J. Constr. Eng. Manag. 2000, 126, 251–260. [Google Scholar] [CrossRef]
- Hartmann, T.; Gao, J.; Fischer, M. Areas of application for 3D and 4D models on construction projects. J. Constr. Eng. Manag. 2008, 134, 776–785. [Google Scholar] [CrossRef]
- Genger, T.K.; Luo, Y.; Hammad, A. Multi-criteria spatial analysis for location selection of multi-purpose utility tunnels. Tunn. Undergr. Space Technol. 2021, 115, 104073. [Google Scholar] [CrossRef]
- Allen, T.T. Introduction to Discrete Event Simulation and Agent-Based Modeling: Voting Systems, Health Care, Military, and Manufacturing; Springer Science & Business Media: Berlin/Heidelberg, Germany, 2011. [Google Scholar] [CrossRef]
- Martinez, J.C. EZStrobe-general-purpose simulation system based on activity cycle diagrams. In Proceedings of the 2001 Winter Simulation Conference (Cat. No. 01CH37304), Arlington, VA, USA, 9–12 December 2001; IEEE: New York, NY, USA, 2001; pp. 1556–1564. [Google Scholar] [CrossRef]
- Gil-Martín, L.M.; Hernández-Montes, E.; Shin, M.; Aschheim, M. Developments in excavation bracing systems. Tunn. Undergr. Space Technol. 2012, 31, 107–116. [Google Scholar] [CrossRef]
- Marzouk, M.; Abdallah, M.; El-Said, M. Modeling Cut and Cover Tunnels Using Computer Simulation. In Proceedings of the 5th International Engineering and Construction Conference, Los Angeles, CA, USA, 27–29 August 2008; ASCE: Reston, VA, USA; p. 717. [Google Scholar]
- Najafi, M.; Gokhale, S.B. Trenchless Technology: Pipeline and Utility Design, Construction, and Renewal; McGraw-Hill Education: New York, NY, USA, 2005. [Google Scholar]
- Stein, D. Trenchless Technology for Installation of Cables and Pipelines; Stein & Partner: Bochum, Germany, 2005. [Google Scholar]
- Technology, F.S.F.T. Microtunneling and Horizontal Drilling: Recommendations; ISTE Ltd.: Newport Beach, CA, USA, 2006. [Google Scholar] [CrossRef]
- Valdenebro, J.-V.; Gimena, F.N.; López, J.J. Construction process for the implementation of urban utility tunnels in historic centres. Tunn. Undergr. Space Technol. 2019, 89, 38–49. [Google Scholar] [CrossRef]
- Dang, T.T. Analysis of Microtunnelling Using Process Simulation Module. In ISRM VietRock International Workshop; ISRM: Hanoi, Vietnam, 2015; p. ISRM–VIETROCK–2015-047. [Google Scholar]
- Doheny, M. Building Construction Costs with RSMeans Data; Gordian RSMeans Data: Rockland, MA, USA, 2021. [Google Scholar]
- Gagnon, M. Une première galerie multiréseaux en sol québécois. In Portail Constructo; Médias Transcontinental S.E.N.C.: Montreal, QC, Canada, 2020. [Google Scholar]
Symbol | Description |
---|---|
Queues hold resources that are idle. Each queue is associated with a particular resource type. | |
Combi activities represent tasks that start when certain conditions are met. | |
Normal activities represent tasks that start immediately when preceding tasks end. | |
Links connect network nodes and indicate the direction and type of resources that flow through them. |
Activity Name | Activity Description | Duration (min) | Cost (USD/min) | |||
---|---|---|---|---|---|---|
3 m Tunnel | 4 m Tunnel | 3 m Tunnel | 4 m Tunnel | |||
Surveying | Surveying | U [120, 180] | U [0.99, 1.83] | |||
Dem Urban Fur | Demolition of urban furniture | N [4320, 504] | U [7.73, 14.35] | |||
Exc Diver | Excavation for utility diversion | Fine sand | U [272, 506] | U [327, 607] | U [2.95, 5.45] | |
Sand and gravel | U [372, 690] | U [446, 828] | U [3.00, 5.58] | |||
Clay/Marl | U [463, 861] | U [557, 1034] | U [3.18, 5.91] | |||
Tr Unload RetA | Dump truck cycle | U [40, 80] | U [0.65, 1.21] | |||
Utility Diver | Diversion of the existing utilities | N [720, 120] | U [8.12, 15.08] | |||
Excavation | Trench excavation | Fine sand | U [636, 1182] | U [764, 1420] | U [2.95, 5.45] | |
Sand and gravel | U [867, 1611] | U [1042, 1934] | U [3.00, 5.58] | |||
Clay/Marl | U [1083, 2011] | U [1300, 2414] | U [3.18, 5.91] | |||
Trench Shoring | Assembly of the trench shoring system | U [90, 120] | U [2.55, 4.73] | |||
MUT Bed | Preparation of the MUT bed | U [39, 73] | U [47, 87] | U [15.74, 29.24] | ||
Sec to Site | Bringing the sections to the site | U [20, 40] | U [0.32, 0.59] | |||
FB Truck Return | Flatbed truck returning | U [20, 40] | U [0.32, 0.59] | |||
Atch lift Sec | Attaching the sections to the crane and lifting | T [1.6, 1.7, 2.3] | The cost of this activity is included in the cost of placing the MUT sections. | |||
Placing Sec | Placement of the MUT sections | T [2.4, 3.3, 4.5] | U [40.07,74.41] | U [53.42, 99.22] | ||
Sealing Joints | Sealing of the segment joints | U [22, 41] | U [29, 55] | U [1.25, 2.33] | ||
Uti Support | Installation of the utility supports | U [649.6, 1206] | U [6.98, 12.96] | |||
Uti Network | Installation of the utility networks | U [817, 1517] | U [37.72, 70.06] | |||
Disp Shoring | Displacement of the shoring system | U [90, 120] | U [2.55, 4.73] | |||
Backfilling | Backfilling | U [368, 683] | U [419, 779] | U [4.53, 8.41] | ||
MUT Network | Installation of the MUT networks | U [8269, 15,357] | U [28.93, 53.73] | |||
Found Pavement | Construction of the pavement foundation | U [48, 88] | U [57, 107] | U [85.44, 158.68] | ||
Final Pavement | Final pavement | U [97, 179] | U [116, 216] | U [236.07, 438.41] |
Activity Name | Activity | Duration (min) | Cost (USD/min) | |||
---|---|---|---|---|---|---|
6 m Shaft | 8 m Shaft | 6 m Shaft | 8 m Shaft | |||
Surveying | Surveying the location of shaft | U [120, 180] | U [0.99, 1.83] | |||
Exc Surf | Excavating the required depth for placing cutting edge | U [31, 57] | U [55, 103] | U [2.17, 4.03] | ||
Tr Unload RetA | Dump truck cycle | U [40, 80] | U [0.65, 1.21] | |||
Place_CutEdg | Placing cutting edge | T [14, 25, 47] | U [39.70, 73.74] | U [52.93, 98.31] | ||
Foundation Jack | Building the foundation for the jacking arms | U [58, 108] | U [76, 140] | U [28.76, 53.42] | ||
Jack_Placing | Placing the jacking arms on the foundation | U [480, 960] | U [4.26, 7.90] | |||
Sec to site | Bringing the sections to the site | U [20, 40] | U [0.32, 0.59] | |||
FB Truck Return | Truck return | U [20, 40] | U [0.32, 0.59] | |||
Atch lift crane | Attaching the sections to the crane and lifting | T [1.6, 1.7, 2.3] | The cost of this activity is included in the cost of placing the shaft sections. | |||
Placing_Section | Placing the sections | T [2.4, 3.3, 4.5] | U [39.70, 73.74] | U [52.93, 98.31] | ||
Pushing_Section | Pushing the shaft sections into the ground | Fine sand | T [88, 159, 278] | T [117, 213, 375] | U [1.94, 3.60] | |
Sand and gravel | T [255, 356, 376] | T [344, 477, 500] | ||||
Clay | T [476, 535, 667] | T [643, 711, 865] | ||||
Soil Removal | Soil removal | Fine sand | U [86, 160] | U [152, 282] | U [2.95, 5.45] | |
Sand and gravel | U [117, 217] | U [207, 385] | U [3.00, 5.58] | |||
Clay | U [146, 270] | U [258, 480] | U [3.18, 5.91] | |||
Remove-Jack | Removing the jacking arms | T [14, 25, 47] | U [4.1, 7.61] | |||
Dewater Shaft | Dewatering the shaft | N [600, 120] | U [2.28, 4.24] | |||
Shaft Found | Building the foundation of the shaft | U [161, 299] | U [286, 530] | U [28.76, 53.42] | ||
MTBM_Setup | MTBM installation in the shaft | N [1440, 480] | USD 134,000 | |||
Exc Ground | Pushing MTBM | Fine sand | T [72, 130, 227] | T [87, 157, 275] | U [21,813, 40,509] | U [29,084, 54,012] |
Sand and gravel | T [152, 217, 234] | T [197, 277, 296] | U [27,4630, 51,003] | U [36,618, 68,004] | ||
Clay | T [301, 355, 449] | T [386, 433, 548] | U [33,114, 61,498] | U [44,452, 81,997] | ||
Sec to Shaft | Bringing sections to the shaft | U [20, 40] | U [0.32, 0.59] | |||
FB_Truck_Return | Truck return | U [20, 40] | U [0.32, 0.59] | |||
Atch Sec Crane | Attaching sections to the crane and lifting | T [1.6, 1.7, 2.3] | The cost of these activities is included in the cost of pushing the tunnel sections. | |||
Lower Sec Shaf | Placing the sections | T [2.4, 3.3, 4.5] | ||||
Placing_Jack | Placing the jacking collar | T [4.4, 5.6, 6.7] | ||||
Connect Cables | Connecting the cables | T [28.9, 36.2, 48.1] | ||||
Jacking_Process | Pushing tunnel sections; cost is per section | Fine sand | T [72, 130, 227] | T [87, 157, 275] | U [21,813, 40,509] | U [29,084, 54,012] |
Sand and gravel | T [152, 217, 234] | T [197, 277, 296] | U [27,463, 51,003] | U [36,618, 68,004] | ||
Clay | T [301, 355, 449] | T [386, 433, 548] | U [33,114, 61,498] | U [44,452, 81,997] | ||
Replace_Jack | Replacing the jacking collar | T [5.18, 6.38, 7.33] | The cost of these activities is included in the cost of pushing the tunnel sections. | |||
Disconnect cabl | Disconnecting the cables | T [16.41, 18.53, 20.97] | ||||
Disassemb MTBM | Disassembling the MTBM in the receiving shaft | N [10,080, 1440] | USD 134,000 | |||
Cleaning | Cleaning the tunnel | N [3600, 720] | U [2.97, 5.51] | |||
Sealing_Joints | Sealing the joints of the tunnel sections | U [551, 1024] | U [736, 1367] | U [1.25, 2.33] | ||
Uti_Support | Installation of the utility supports | U [8117, 15,074] | U [6.98, 12.96] | |||
Uti Network | Installation of the utility networks | U [10,200, 18,942] | U [37.72, 70.06] | |||
MUT Network | Installation of the MUT’s own network | U [10,347, 19,216] | U [28.93, 53.73] | |||
Found Pavement | Construction of the foundation of the pavement | U [23, 42] | U [40, 57] | U [85.44, 158.68] | ||
Final Pavement | Final pavement of the street | U [125, 232] | U [222, 413] | U [236.07, 438.41] |
Attribute | Value |
---|---|
Tunnel length | 100 m |
Tunnel diameter | 3 m or 4 m |
Length of tunnel precast concrete sections | 4 m |
Depth of the tunnel | 10 m |
Working hours per day | 8 h |
Soil type | Fine sand, sand and gravel, or clay/marl |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Jorjam, S.; Mawlana, M.; Hammad, A. Stochastic Simulation of Construction Methods for Multi-purpose Utility Tunnels. Infrastructures 2024, 9, 1. https://doi.org/10.3390/infrastructures9010001
Jorjam S, Mawlana M, Hammad A. Stochastic Simulation of Construction Methods for Multi-purpose Utility Tunnels. Infrastructures. 2024; 9(1):1. https://doi.org/10.3390/infrastructures9010001
Chicago/Turabian StyleJorjam, Shayan, Mohammed Mawlana, and Amin Hammad. 2024. "Stochastic Simulation of Construction Methods for Multi-purpose Utility Tunnels" Infrastructures 9, no. 1: 1. https://doi.org/10.3390/infrastructures9010001
APA StyleJorjam, S., Mawlana, M., & Hammad, A. (2024). Stochastic Simulation of Construction Methods for Multi-purpose Utility Tunnels. Infrastructures, 9(1), 1. https://doi.org/10.3390/infrastructures9010001