1. Introduction
Preferably, dams are located in areas that are less occupied within a catchment and are characterized by natural landscapes. However, globally, the trend of land demand has continuously been increasing, resulting from population growth and development activities; according to Lanz et al., [
1], the world population has been steadily expanding, and it is estimated that, by 2100, the global population will be around 12.4 billion people. This phenomenon has been significantly impacting the natural landscape of catchments. Rapid urbanization is a popular term describing a scenario in which less developed areas are invaded and subjected to development activities [
2,
3]. According to Fiscal et al. [
4], this type of urbanization remains one of the crucial environmental challenges in developing countries. Therefore, with time, dams located within less-developed landscapes are finding themselves within a highly developed and crowded environment. When the natural landscape is developed into structures such as parking lots, tarmac roads, rooftops, as well as compacted grounds, the areas of impervious surfaces also increase [
5]. These impervious surfaces affect how the runoff is either absorbed or runs on the ground’s surface, where it becomes difficult for precipitation to infiltrate the ground, leading to more runoff [
6]. It becomes even more challenging when the impervious surfaces are combined with extreme events, such as extreme precipitation [
7]. With more runoff running on the ground’s surface, more water reaches nearby streams, exceeding the carrying capacity, and eventually causing flooding [
8,
9]. This also means that more water reaches nearby dams, which are located downstream, surpassing the flow rate employed during the design phase of the structure, putting it at risk of failure [
10,
11]. There are already many cases where dams have failed due to an increase in the runoff, including the Bilberry reservoir [
12], which failed in 1852 in Holme Valley, West Yorkshire, England; Hauser Dam in the United States, which failed in 1908 [
13]; Lower Otay Dam in the United States, which failed in 1916 [
14,
15]; as well as the Banqiao and Shimantan Dams in China failed in 1975 [
16]. In such cases, embankment dams are more prone to failure compared to concrete dams.
In certain cases, however, the failure does not occur immediately and is delayed by a change in the long-term design maximum water level [
17]. Furthermore, it is only a matter of fact that, during its lifetime, any embankment can be subjected to different operating water levels due to the changes in flow conditions in the particular catchment as influenced by factors such as land surface cover and climatic changes. Due to all of these challenges, the application of modeling for the risk analysis of dam failures has been a topic of interest in the recent past [
18]. Despite the fact that slope stability under rapid drawdown conditions has been a subject of interest in the recent past [
19,
20], unfortunately, to date, the design and analysis of embankment dams have completely ignored the risk posed by the combination of rapid drawdown and changing operating water levels. The looming danger becomes more significant when the aspect of the operating water level is combined with rapid drawdown loading conditions.
It should also be highlighted that, when the long-term maximum water level changes, the pattern of seepage within the embankment changes, resulting in a new pattern that was not addressed during the design process [
21]. Moreover, when the hydrological pattern in the catchment changes, the dam receives a new long-term water level that was not anticipated when the dam was designed. The dam may be subjected to progressive failure as a result of the new type of loading condition. The worst-case scenario is when the dam is rapidly drained while the long-term water level has changed [
22]. It is also important to note that, when an earth embankment has kept a reservoir with a relatively consistent water surface height for a long time, the seepage conditions within the embankment are likely to have stabilized. If the reservoir must be drained quickly, the pore-water pressures within the embankment may remain relatively high while the reservoir’s weight along the upstream side of the embankment acts as a stabilizing force. This is sometimes referred to as ‘rapid drawdown,’ and it might result in embankment instability on the upstream face [
23]. As a result, investigating all of these variables during the design phase of an embankment dam is crucial.
In addition, numerical modeling is useful in determining the slope stability of embankment dams under various loading situations. In geotechnical engineering, numerical modeling is a popular technique that employs computer simulation to tackle complex problems [
24]. This method has been utilized to analyze difficult embankment dam problems for many years [
25,
26,
27]. In general, the investigation of how changes in land surface cover might pose a serious threat to a dam in an urbanizing catchment will assist future dam designers in constructing highly sustainable dams. Unfortunately, past studies have not adequately captured the effects of land-use changes and extreme events on embankment dam slope stability, making it impossible to consider these elements during the design process effectively. Dams are often erected in less developed areas of a catchment, as previously indicated, but, as a result of causes such as population growth, these catchments are becoming increasingly urbanized, affecting the natural environment. All of these factors have an impact on a catchment’s hydrological pattern, posing a serious threat to dams. Furthermore, combining all of these aspects during the design phase of a dam, particularly an embankment dam, has always been a challenge.
This study investigates the potential influence of operating water levels and loading conditions on the slope stability of an embankment dam. Numerical modeling is used to investigate the problem in the case of the Chardara dam within the Syrdarya catchment in Kazakhstan. Four different cases were taken into consideration, as follows:
Modeling based on the current reservoir operating level;
Modeling with the long-term water level at half of the embankment height;
Modeling based on the embankment’s maximum height;
Modeling based on the overflowing reservoir level.
Analysis of variance and correlation matrices are among the methods used to evaluate the results.
2. Materials and Methods
2.1. Case Study Description
The Chardara dam is located in Kazakhstan’s South-Kazakh area, at the end of the middle stream of the Syrdariya river, to the north of the Turkestan mountains, and it covers the Golodniy steppe, the Arnasay depression, and the Syrdariya valley. The dam supplies agricultural water to the Kyzyl-Kum waterway. The dam’s reservoir has a maximum storage capacity of 5.7 billion m3 and a 900 km2 surface area. The dam was designed in 1955–1967 by the Central Asia department of “The Hydroproject” Institute in Tashkent. Construction works were completed in October 1967, and, in 1968, the full reservoir level was impounded. Chardara dam consists of a hydraulic fill embankment, channel-type power station combined in one building with two sluices at the left- and right-hand sides of the power station, and a Kyzylkum regulator on the left bank of the river. The dam was constructed by placing the hydraulic fill on two sides. The upstream slope of the embankment is strengthened by reinforced concrete slabs that were placed on a gravel–sandy bed. At the joints of the concrete facing, a double layer of the inverted filter was placed. The downstream slope is strengthened by local silty–gravel material. A pipe drain with a triple-layered inverted filter was constructed at the toe of the downstream slope. There are relief wells and a drainage water conduit at the downstream toe. There is a 6 m-wide asphalt road at the dam crest.
A silty–sandy layer 1.5 m to 2.5 m deep underpins a layer of fine sands 12 m to 17 m thick in the flood plain river portion, where the embankment axis is located. The intake construction is built on siltstones, marly clay, sand, and sandstone with conglomerate as bedrock. The base of the Chardara embankment is made up of a silty sand layer 8 to 10 m deep, which is overlain by a clay layer 2 to 5 m thick or a thick layer of fine silty sand. The groundwater table lies between 0.5 and 2 m below the surface in these places. The dam is situated in earthquake zone VI. However, the embankment and its buildings, on the other hand, were designed considering an earthquake intensity of VII [
28].
Table 1 lists the physical and mechanical characteristics of the construction materials used in the embankment foundations. The slope of the embankment is approximately 1:4 (V:H) or 4:1 (H:V).
2.2. Water Level Cases Investigated
Table 2 presents the different cases investigated in this study. In general, four (4) different cases were investigated based on the reservoir operating level. It has to be noted that one of the significant effects of the land use/land cover and climatic changes in the catchments is the changes in the reservoir’s operating levels. The streams receive more surface runoff than the underground flow when the catchment becomes more impervious. In such a phenomenon, there is a higher chance that the catchment will receive highly varied flows (high flows and low flows) while increasing the risk of the reservoir being subjected to long-term reduced operating water levels and long-term increased operating water levels.
Figure 1 further highlights some of the reservoir operating levels investigated in the study with a meshed embankment.
2.3. General Modeling Procedures and Embankment Material Properties
The embankment geometry (
Table 3 and
Figure 2) is divided into five zones, with zones 2a and 2b having similar material characteristics. Each zone of the embankment was assigned distinct material properties, with zone 1 primarily consisting of coarse material mixed with fine materials (silt and clay fraction), with saturated hydraulic conductivity (k
sat) and a liquid limit (w
L) of 45%. Cohesive material, fine-grained material, and clay characterize Zone 3. Zones 2a and 2b are distinguished by non-cohesive soil and filter material (sand and gravel), whereas Zone 4 is distinguished by coarse material with a low fine material concentration (
Table 3). More parameters of the material properties used in this study are summarized in
Table 3.
As previously highlighted, the dam embankment geometry is divided into four main zones (
Figure 2).
The finite element technique investigated the potential influence of the reservoir’s rapid drawdown on the embankment’s slope stability with different soil parameters. The steady-state, instantaneous drawdown, 5-day drawdown, 10-day drawdown, and 1 m per day drawdown rate to half of the maximum water level were investigated. Firstly, the embankment was subjected to long-term steady-state analysis, followed by the rapid drawdown rates (instantaneous, 5 days, 10 days, and 1 m per day) for each operating reservoir level. In the instantaneous drawdown case, it was assumed that the water in the dam or reservoir was drained instantly. In this case, the extreme situation or worst-case scenario was represented by the instantaneous drawdown case. The seepage analyses were conducted concurrently with the slope stability analyses.
In general, the study problems were investigated using the combination of GeoStudio sub-software SEEP/W [
29] and SLOPE/W [
30]. SEEP/W, which is based on FEM, was utilized for the seepage analysis in two-dimensional sections.
2.4. Seepage Analysis Procedures
As previously mentioned, the simulation of a slope’s drawdown behavior began with the establishment of a long-term steady state utilizing the steady-state analysis method in GeoStudio. The established long-term steady-state conditions were then employed as parents to the transient flow analyses, whereby the transient flow analyses utilized seepage-induced pore pressures generated from the long-term steady-state analysis. Throughout the transient seepage analyses, the variation in the water level during the drawdown process was modeled using a linear function that was given as a boundary condition on the upstream face of the embankment.
2.5. Slope Stability Analysis Procedures
To be more specific, the slope stability analysis was achieved using the Morgenstern–Price [
31] method under the general limit equilibrium (GLE) [
32] to define a distinct analysis for each of the slope stability analyses.
Figure 3 presents the summary of the volumetric water content and hydraulic conductivity functions from the first two zones of the study embankment generated based on the material characteristics assigned to the embankment.
2.6. Statistical Methods
One of the approaches used for assessing the research outcomes was the use of correlation matrices. These matrices were critical in assessing the strength of the relationship between the investigated parameters based on the factor of safety values. A high correlation in the matrices indicated a strong relationship between two or more variables, where the variables were not closely related if the correlation coefficient was low; the interpretation of the correlation coefficients was as follows:
0 to 0.29: weak correlation;
0.3 to 0.4: moderate correlation;
0.5 to 0.69: strong correlation;
0.7 to 1: very strong correlation.
Moreover, to determine whether the differences between the groups of data were statistically significant, a single-factor analysis of variance (ANOVA) was performed. This statistical analysis approach analyzes the levels of variance within the groups by taking samples from each of them.
4. Conclusions
The impact of land-use changes, extreme events, and loading conditions on the slope stability of an embankment dam was explored in this study. The problem was investigated using numerical modeling in the case of the Chardara dam in Kazakhstan’s Syrdarya basin. Numerical modeling was performed to explore the impact of flow conditions on embankment slope stability. The results revealed that the operating reservoir levels could substantially affect even the long-term steady-state conditions. For instance, the steady-state factor of safety from the reduced water level was approximately 8.9% less than that achieved from the normal operating water level. The transient flow analyses retrieved correlation coefficients ranging from 0.561 to 0.997 from drawdown days, the minimum factor of safety values, the maximum factor of safety values, and pore-water pressures. The highest correlation was found between the minimum factor of safety values and pore-water pressures, which was −0.997. Based on the p-values retrieved from ANOVA, it was observed that the differences in the factor of safety values from the normal, embankment height, and overflow operating water levels were statistically significant. The p-value for the reduced operating reservoir level, on the other hand, was higher than the alpha value, indicating that the differences in the factor of safety values were not statistically significant. In view of the results, it is reasonable to conclude that, despite the fact that both the reservoir rapid drawdown and reservoir operating water levels have a significant impact on the embankment slope stability, the operating reservoir level becomes an issue of significant concern when the drawdown rate is higher. From this study, we understand that it is of critical importance to investigate an embankment under different potential operating levels during the design phase toward achieving more sustainable embankment dams.