Next Article in Journal
Modelling and Characterizing a Concrete Gravity Dam for Fragility Analysis
Previous Article in Journal
Integrating Geographic Information Systems and Augmented Reality for Mapping Underground Utilities
Previous Article in Special Issue
Implementation of Advanced Demand Side Management for Microgrid Incorporating Demand Response and Home Energy Management System
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Performance Assessment and Economic Analysis of a Gas-Fueled Islanded Microgrid—A Malaysian Case Study

by
Moslem Uddin
,
Mohd Fakhizan Romlie
* and
Mohd Faris Abdullah
Electrical and Electronic Engineering Department, Universiti Teknologi PETRONAS, Seri Iskandar, Tronoh 32610, Perak, Malaysia
*
Author to whom correspondence should be addressed.
Infrastructures 2019, 4(4), 61; https://doi.org/10.3390/infrastructures4040061
Submission received: 8 July 2019 / Revised: 18 August 2019 / Accepted: 19 August 2019 / Published: 26 September 2019
(This article belongs to the Special Issue Smart Grid Infrastructure)

Abstract

:
In this study, the performance of an islanded gas turbine power generation system in Malaysia was investigated. Considering the low fuel efficiency of the plant during peak and part-load operations, an economic analysis was also carried out, over the period of one year (2017). The case study was conducted on the isolated electrical network of the Universiti Teknologi PETRONAS (UTP), which consists of two gas turbine units with a total capacity of 8.4 MW. Simple performance indicators were developed to assess the performance, which can also be applied to other power stations in Malaysia and elsewhere. Meanwhile, the economy of variable load operations was analyzed using the statistical data of generation, fuel consumption, and loads. The study reveals that the capacity factor of the microgrid in the period was between 52.77–63.32%, as compared to the industrial best practice of 80%. The average plant use factor for the period under review was 75.04%, with a minimum of 70.93% and a maximum of 78.61%. The load factor of the microgrid ranged from 56.68–65.47%, as compared to the international best practice of 80%, while the utilization factor was between 44.22–67.655%. This study further reveals that high fuel consumption rates, due to the peak and part-load operations, resulted in a revenue loss of approximately 17,379.793 USD per year. Based on the present performance of the microgrid, suggestions are made for the improvement of the overall performance and profitability of the system. This work can be valuable for microgrid utility research to identify the most economical operating conditions.

Graphical Abstract

1. Introduction

Gas turbines are used for wide range of services, most notably for producing power. Gas turbine-based power plants have gained a lot of attention, due to their simple design, sufficiently high economic efficiency, and low construction costs [1,2]. Further, they have been recognized for their good environmental performance, manifested as low environmental pollution [3]. Therefore, interest in gas turbines has been growing for the application of grid-independent small-scale generation systems, industrial generation systems, and isolated microgrid systems [4,5]. These small generation systems or microgrids are expected to achieve highly effective energy utilization. However, the performance of these plants are strongly affected by non-uniform electric-demand schedules, as they are not connected with a grid [6,7,8]. Load demand variations have been shown to greatly affect electricity production, fuel consumption, and plant incomes [9,10,11,12,13]. In addition, when gas turbines operate under varying duty conditions, the lifetimes of primary thermos-stressed components are considerably reduced and, consequently, repair costs increase [14]. Based on these facts, the assessment of gas-fired microgrid performance has become paramount.
In the literature, very few studies are available which have addressed this issue. In [15], a framework was developed to assess the performance and quantify the reliability of a fuel-based grid-connected microgrid, considering different power production scenarios in a regional system. However, no economic analysis was presented. To evaluate the performance of a gas-fueled islanded microgrid, an AC load flow technique was used in the MATLAB environment in [16]. Future directions were also outlined from the analyzed results, in order to improve the overall performance of the microgrid. However, the study made no attempt to deal with an economic analysis. Although an economic analysis of gas-fueled power plants was presented in [17,18], the costs (i.e., fuel costs) due to non-optimal production were not been analyzed. Additionally, these studies focused on large-scale generation systems. Thus, the scalability of these studies for microgrids in a real scenario remains ill-defined. Overall, the existing literature indicates that research on this issue is still in its infancy, and a multitude of issues are still un-addressed.
Therefore, this study was initiated to investigate the performance of an islanded microgrid, in order to ensure plant profitability with considerable cost savings (related to maintaining maximum fuel efficiency and availability). The importance and originality of this paper are summarized as follows:
  • Performance of a gas fuel-based islanded microgrid system (8.4 MW) is investigated (using the collected data of installed capacity, generation, and load) to find highly efficient operational conditions (Section 3).
  • Simple performance indicators are developed for assessing the performance of the gas-fueled islanded microgrid, which can also be applied to other power stations in Malaysia and elsewhere (Section 4).
  • The cost due to the non-optimal production (in terms of fuel cost) is analyzed (Section 5).
  • With the hope that microgrid owners will benefit from this study, some recommendations are proffered for improving power generation and reducing the generation costs of the microgrid (Section 6).

2. Gas-Fueled Electricity Generation in Malaysia

Power generation in Malaysia significantly depends on three major fossil fuel sources: Coal, natural gas, and fuel-oil [19]. In 2015, the ratio of gas-fired power generation was 46.3% of the total electricity production capacity, and coal was 41% [20]. Energy generation from different sources in Malaysia is depicted in Figure 1.
Since the commencement of natural gas exploration in 1983, gas has contributed significantly to the energy mix, replacing fuel oil as the main energy source [20]. Interest in natural gas-fired power generation has increased, due to the plentiful natural gas resources. In conjunction with the availability of natural gas resources, the high efficiency, low installation costs, and good reliability of gas turbine generators have made them popular in the power industry in Malaysia. In addition, the installation of gas turbine generators and connection of them to the national grid is faster, in comparison to other generators, such as steam turbine power plants [21]. As can be seen from the summary of the installed capacity (presented in Table 1), up until 2014 the installed capacity of natural gas-fired power plants was 15,248 MW.

3. System under Study

3.1. System Description

The system evaluated in this study is the electrical network of Universiti Teknologi PETRONAS (UTP), located in Perak, Malaysia. The electrical demand of UTP is supplied by an islanded microgrid consisting of two gas turbine generators located in the gas district cooling (GDC) plant in UTP. The rated capacity of each generator is 4.2 MW. Therefore, the total capacity of the microgrid is 8.4 MW. The UTP microgrid generates 11 kV and distributes along a 3–5 km distribution line before stepping down to 415 V. It supplies the offices, academic buildings, and residential villages (student accommodation) of UTP.

3.2. Electrical Generation and Consumption

The typical hourly load curves of the UTP microgrid are illustrated in Figure 2. These load curves graphically convey detailed information about the characteristics of energy consumption in the UTP microgrid.
From Figure 2, it can be observed that:
  • In working days (or study weeks), the UTP microgrid is characterized by a low load at night and early morning (12 a.m. to 6.30 a.m.), and an increased load between 6.30 a.m. and 10 a.m.; from the working day load profile, it can also be observed that there are two electrical demand peaks: Aa daytime peak between 11 a.m. and 1 p.m., and an evening peak, around 9 p.m., which may last about 2 h. During this evening peak, demand varies between 3.7–4.2 MW. To supply this 4.2 MW demand, the two generation units, with total capacity of 8.4 MW, are operated. This results in low efficiency and increased production costs.
  • Daily energy consumption during the weekend and semester break are nearly equal. However, the weekend load profile experiences more fluctuations.
  • It can also be remarked that the lowest energy demand on the UTP microgrid is during public holidays.
The installed capacity, generation capacity, and capacity utilization of the UTP microgrid for the year of 2017 are presented in Table 2. A close look of Table 2 shows that the electricity production of UTP microgrid is far below its installed capacity. The total generation capacity over the period of twelve months ranged from 3715 kW to 5836 kW, while the installed capacity was 8400 kW. There was a wide gap between generation and installed capacity. This reflects the extent of the inefficiency of the microgrid energy utilization.
Figure 3 and Figure 4 provide information of the running hours (by unit) and energy generation of the microgrid system from January 2017 to December 2017. There was a variability in running hours from January to December, ranging from 415–722 h for a single unit. The highest running hour total (overall) of the microgrid occurred in January (1242 h). The overall energy generation also varied from 3.347–3.829 GWh. The highest energy generation was obtained in April, which was 3.829 GWh.

3.3. Data Presentation

The required data for this study was collected from the UTP gas turbine power generation station. These are inventory records of daily energy generation between January 2017 and December 2017. A brief summary of the collected data is presented in Table 3. This table provides detailed information about the monthly energy production of microgrid, losses, average running hours, and capacity factor for the period under consideration (January–December 2017). By processing the data, the capacity factor, load factor, utilization factor, and other performance indices were evaluated.

4. Microgrid Performance Indices

The performance of a gas turbine generation system depends on several indices. Some of these are inextricable parts of a performance evaluation study. These important factors are discussed below in detail.

4.1. Load Factor

Load factor is a useful technique to measure the efficiency of energy utilization in a plant. It determines how efficiently electricity is being used, and is defined as the ratio of the average load to the peak load for a particular period of time. The load factor of the microgrid can be expressed by
L F = P a v e r a g e P p e a k ,
where P a v e r a g e is the average power demand and P p e a k is the peak load in given period of time [22]. Daily, monthly, and annual load factors can be calculated, depending upon the number of hours in a day, month, and year, accordingly. A low load factor means an electricity system is operated inefficiently, as well as uneconomically [23]. Therefore, a high load factor is a desirable quality for making a plant economically feasible. A high value of load factor ensures greater average load through the utilization of the total plant capacity for the maximum period of time [24]. Thus, the fixed cost (which is proportional to the peak load) is distributed over a greater number of generated units (kWh). As a result, the overall cost of the electric energy supply will be lesser [10]. Thus, improvement of the load factor is necessary to reduce the energy costs and make the plant more profitable. To improve the load factor, peak electrical load needs to be reduced.

4.2. Plant (Microgrid) Operating Factor

Plant operating factor is defined as the ratio of the duration during which the plant is in actual service to the total duration of the time period considered [25].

4.3. Plant Capacity ( C p l a n t )

Plant capacity ( C p l a n t ) refers to the total energy (kWh) and power (kW) that a plant is capable of producing, where the energy capacity of the plant is equal the plant power capacity multiplied by the expected running hours [25],
C e , p l a n t = C p , p l a n t × h e x p , r u n n i n g ,
where C e , p l a n t is the energy capacity of the plant, C p , p l a n t is the power capacity of the plant, and h e x p , r u n n i n g is the expected number of running hours.

4.4. Plant Capacity Factor ( F c , p l a n t )

This factor is important to measure the degree of utilization of the installed equipment in a generating plant. It is defined as the ratio of the actual energy (kWh) produced over a given period of time to the maximum possible energy produced from the plant during a particular time:
F c , p l a n t = E p l a n t C i , p l a n t × h t o t a l ,
where E p l a n t refers to the total generated energy (kWh) during the specified period of time, C i , p l a n t is the installed or rated capacity of the plant, and h t o t a l is the total number of hours in the specified period [25,26,27].

4.5. Utilization Factor ( F u t i l i z a t i o n )

The utilization factor can be defined as the ratio of the maximum (peak) demand to the installed (rated) capacity of the power plant. It measures the use of the total installed capacity of the plant [26]:
F u t i l i z a t i o n = P m a x C i , p l a n t ,
where P m a x is the maximum or peak (demand) load generated over a specified period of time.

4.6. Utility Factor ( F u t i l i t y )

The utility factor ( F u t i l i t y ) can be defined as the ratio of the total units of generated electricity per year to the capacity of the installed plant. It can also be defined as the ratio of the peak electrical demand of a plant to the installed capacity of that plant,
F u t i l i t y = P p e a k C i , p l a n t × L F ,
where P p e a k is the peak (maximum ) electrical load on the plant [25].

4.7. Plant Use Factor ( F u , p l a n t )

The plant use factor ( F u , p l a n t ) can be defined as the ratio of actual generated energy over a specified period of time to the product of installed plant capacity and the total number of operating hours of the plant during that specified period of time. The plant use factor is the modification of plant capacity factor, where only the actual operating hours are used. Therefore, the annual plant use factor can be defined as
F u , p l a n t = E g , t o t a l C i , p l a n t × h o , t o t a l ,
where E g , t o t a l refers to the overall energy production (kWh) over a specified period of time (one year) and h o , t o t a l is the total number of operating hours during the time of consideration (one year) [27].

5. Cost Analysis of Peak and Part Load Operations

The load is one of the primary considerations influencing the performance of a gas turbine-based power generation system. Optimum economic operation (lowest cost/kWh) of a gas turbine microgrid system is obtained when the turbines operate most efficiently. However, the performance of a gas turbine is greatly affected by the fluctuation of load, as is shown in Figure 5.
The lowest cost of energy generation is achieved when gas turbines operate at optimum load, depending on maximum efficiency and maximum power output, even though they are aerodynamically designed for base load operation. When the gas turbines do not operate at this load level, the flow triangles in the turbine expander stages and the compressor differs from the design assumptions, resulting in more energy being dissipated.
For the very long-term operations of a microgrid, the operating cost dominates. Thus, fuel consumption becomes the key cost factor, as the largest part of the operational and maintenance costs comes from fuel. Variation of load also influences the fuel consumption of a gas turbine. The variation of fuel consumption is shown in Figure 6.
Monthly fuel consumption of the UTP microgrid is shown in Table 4. By maintaining the optimum level of production fuel, the consumption of the plant can be improved. Further, a reduction in fuel consumption will result in a reduction of maintenance costs (as the largest maintenance costs come from fuel). The yearly fuel savings can be determined by
S f , y r = κ f , i m P p e a k C i , p l a n t × L F ,
where, S f , y r is the yearly fuel saving (in m 3 ), κ f , i m is the fuel efficiency improvement, E p , y r is the yearly energy production, and C f , y r is the yearly fuel consumption.
The yearly fuel cost savings can be calculated using
S c o s t ( f ) , y r = S f , y r × R f ,
where S c o s t ( f ) , y r is the yearly fuel cost saving and R f is the price of the fuel per m 3 .

6. Result and Discussion

6.1. Performance of the Test Microgrid

Under this study, the value of capacity factor ranged from 52.77% (in December) to 63.32% (in April). The variation of capacity factor is shown in Figure 7.
The average capacity factor of the UTP microgrid was 57.73%, as compared tothe industry best practice, which is between 50–80% [2,18,28]. For the economic operation of the microgrid, a high capacity factor is desirable, as the characteristic behavior of generating plant depends substantially on the utilization factor, as well as the capacity factor. In January, the low value of the capacity factor (52.77%) signifies that the average energy production of microgrid was low. In general, a low plant capacity factor implies that, for a major part of the year, the microgrid capacity remains un-utilized. As a result, the cost of energy generation becomes high. For the economic operation of the microgrid, the high value of the capacity factor is necessary. This high capacity factor will be attained if scheduled routine maintenance of the plant is significantly improved.
There was variability in the plant use factor over the year (as shown in Figure 8). For the period under review, the plant use factor varied between 70.93% (January) and 78.61%( October). The average value of plant use factor for this case study was 75.04%. The low value of plant use factor reveals a low ratio of actual energy generation to the expected energy generation. It is also an indication of immoderate plant failure, which led to the plant’s generation being below its rated capacity. On the other hand, a high value of plant use factor signifies a high ratio of actual energy generation from microgrid to the expected generation.
The variation of plant load factor is depicted in Figure 9. The load factor in the case study microgrid varied between 56.68–65.47%. The average value of load factor was 60.35%, which is low compared to the international best practice of 80% or above [17,28,29]. The load factor provides easily interpreted information regarding the utilization of the installed plant capacity. To reduce the per-unit generation cost of energy, a high load factor is desirable, as it can ensure the maximum utilization of the installed capacity. Effective energy management and optimum scheduling of generation can ensure the reliable, adequate, and cost-effective operation of the plant.
In the period of under review, the utilization factor was not consistent. There was variation in utilization factor over the year (as shown Figure 10). The minimum value of utilization factor was obtained in January (44.2226%). The maximum value of utilization obtained was 67.655%, in May. This value signifies that the utilization factor of the case study microgrid was always far from the best practice, which is 80% [2,17,28]. However, for a load above 80%, the gas turbine of the plant is limited by the turbine inlet temperature [28,30]. The low utilization factor implies that the generating facilities were poorly maintained. A significant reduction in the gap between actual operational capacity and installed capacity of the microgrid is required for a high utilization factor.

6.2. Cost of the Peak and Part Load Operations

The fuel consumption of a gas turbine generator largely depends on the load. In Figure 11, the fuel consumptions per kWh of the UTP microgrid under different loads are shown. The fuel consumption rate was minimum when the load was at nearly 80% of its rated capacity. However, the UTP microgrid infrequently operated at 80% load, mostly operating below 70% load. Therefore, the fuel consumption rate was high. This result indicates that a large amount of fuel can be saved by improving fuel efficiency. As fuel is the single largest operating expense, an improved fuel efficiency will result in lower energy production cost.
The total energy production of tge UTP microgrid in 2017 was 42,586,675 kWh, while the fuel consumption was 15,683,095.83 m 3 or 564,920.46 MMBTU. Considering the fuel price of RM 26.31 per MMBTU (as of January 2017), a mere 0.5 % improvement in fuel efficiency of the microgrid could have saved as much as RM 72,995.13/17,379.793 USD (1 USD∼RM 4.2) per year (calculated using Equations (7) and (8)). In practice, this fuel efficiency can be achieved by;
(i)
Operating the gas turbine generator at the optimum production level;
(ii)
scheduling the generators of microgrid most economically; and
(iii)
reducing the gap between average load and peak load.
An energy storage system could play a primary role in achieving these goals.

7. Conclusions

Performance evaluation and economic analysis of a gas-fueled microgrid (owned by the Universiti Teknologi PETRONAS, Malaysia) were presented in this research work. The results of this study indicate that the performance of the UTP microgrid was far below the optimal level, due to the huge gap between average load and peak load. This situation can be greatly enhanced by improving the average load. Further, the economic analysis results revealed that the operational cost of the microgrid was high, due to the high fuel consumption rate resulting from the peak and part-load operations. These results also indicate that a mere 0.5 % improvement in fuel efficiency could save as much as 17,379.793 USD per year.
The main limitation of the current study was that all factors affecting the performance of a gas turbine-based power generation system were been considered. The current study forms a basis from which future endeavors may analyze gas turbine microgrid systems in greater detail. More factors can be incorporated into future analyses to better understand the performance of gas-fueled islanded microgrid systems.

Author Contributions

Conceptualization, M.U. and M.F.R.; methodology, M.F.R. and M.U.; software, M.U.; validation, M.F.R. and M.F.A.; formal analysis, M.F.R.; investigation, M.U.; writing–original draft preparation, M.U.; writing–review and editing, M.F.R. and M.F.A.; supervision, M.F.R. and M.F.A.

Funding

This research was funded by the Petroleum Research Fund, Board of Trustees (Grant number 0153AA-H25) (PRF-BOT) and Yayasan Universiti Teknologi PETRONAS (YUTP).

Acknowledgments

The authors acknowledge Universiti Teknologi PETRONAS for their support to perform this research.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
TNBTenaga Nasional Berhad
IPPsIndependent Power Producers
SREPSmall Renewable Energy Power
FiTFeed-in-Tariff
SESBSabah Electricity Sdn Bhd
UTPUniversiti Teknologi PETRONAS
RMRinggit Malaysia (Malaysian Ringgit)
USDU.S. Dollar

References

  1. Walsh, P.P.; Fletcher, P. Gas Turbine Performance; John Wiley & Sons: Hoboken, NJ, USA, 2004. [Google Scholar]
  2. Boyce, M.P. Gas Turbine Engineering Handbook; Elsevier: Amsterdam, The Netherlands, 2011. [Google Scholar]
  3. Sasao, T.; Shimoki, T.; Akatsu, F.; Liu, K. Performance Evaluation of H-25 Gas Turbine. Hitachi Rev. 2003, 52, 97. [Google Scholar]
  4. Study on Gas-Fired Combined Cycle Power Plant Project in Malaysia; Technical Report; Tokyo Electric Power Services Co. Ltd.: Tokyo, Japan, 2016.
  5. El-Wakil, M.M. Powerplant Technology; Tata McGraw-Hill Education: New York, NY, USA, 1984. [Google Scholar]
  6. Gao, D.W. Energy Storage for Sustainable Microgrid; Academic Press: Cambridge, MA, USA, 2015. [Google Scholar]
  7. Oriti, G.; Julian, A.L.; Anglani, N.; Hernandez, G.D. Novel economic analysis to design the energy storage control system of a remote islanded microgrid. IEEE Trans. Ind. Appl. 2018, 54, 6332–6342. [Google Scholar] [CrossRef]
  8. Farrokhabadi, M.; Solanki, B.V.; Canizares, C.A.; Bhattacharya, K.; Koenig, S.; Sauter, P.S.; Leibfried, T.; Hohmann, S. Energy storage in microgrids: compensating for generation and demand fluctuations while providing ancillary services. IEEE Power Energy Mag. 2017, 15, 81–91. [Google Scholar] [CrossRef]
  9. Mehta, V.; Mehta, R. Principles of Power System; S. Chand: New Delhi, India, 2004. [Google Scholar]
  10. Uddin, M.; Romlie, M.F.; Abdullah, M.F.; Halim, S.A.; Kwang, T.C. A review on peak load shaving strategies. Renew. Sustain. Energy Rev. 2018, 82, 3323–3332. [Google Scholar] [CrossRef]
  11. Gu, W.; Wu, Z.; Bo, R.; Liu, W.; Zhou, G.; Chen, W.; Wu, Z. Modeling, planning and optimal energy management of combined cooling, heating and power microgrid: A review. Int. J. Electr. Power Energy Syst. 2014, 54, 26–37. [Google Scholar] [CrossRef]
  12. Zunnurain, I.; Maruf, M.; Rahman, M.; Shafiullah, G. Implementation of advanced demand side management for microgrid incorporating demand response and home energy management system. Infrastructures 2018, 3, 50. [Google Scholar] [CrossRef]
  13. Uddin, M.; Romlie, M.; Abdullah, M.; Hassan, K.; Tan, C.; Bakar, A. Modeling of campus microgrid for off-grid application. In Proceedings of the 5th IET International Conference on Clean Energy and Technology (CEAT2018), Kuala Lumpur, Malaysia, 5–6 September 2018. [Google Scholar]
  14. Aminov, R.; Kozhevnikov, A. Optimization of the operating conditions of gas-turbine power stations considering the effect of equipment deterioration. Therm. Eng. 2017, 64, 715–722. [Google Scholar] [CrossRef]
  15. Prete, C.L.; Hobbs, B.F.; Norman, C.S.; Cano-Andrade, S.; Fuentes, A.; von Spakovsky, M.R.; Mili, L. Sustainability and reliability assessment of microgrids in a regional electricity market. Energy 2012, 41, 192–202. [Google Scholar] [CrossRef]
  16. Uddin, M.; Romlie, M.F.; Abdullah, M.F. Performance Evaluation of Islanded Microgrid Using Load Flow Analysis Technique. In Proceedings of the 2018 International Conference on Intelligent and Advanced System (ICIAS), Kuala Lumpur, Malaysia, 13–14 August 2018; pp. 1–6. [Google Scholar]
  17. Oyedepo, S.O.; Fagbenle, R.; Adefila, S.; Adavbiele, S. Performance evaluation and economic analysis of a gas turbine power plant in Nigeria. Energy Convers. Manag. 2014, 79, 431–440. [Google Scholar] [CrossRef] [Green Version]
  18. Oyedepo, S.O.; Fagbenle, R.O.; Adefila, S.S. Assessment of performance indices of selected gas turbine power plants in Nigeria. Energy Sci. Eng. 2015, 3, 239–256. [Google Scholar] [CrossRef]
  19. Rahman, S.; Rahman, H.A. Use of Photovoltaics in Microgrid as Energy Source and Control Method using MATLAB/Simulink. Int. J. Electr. Comput. Eng. 2016, 6, 851–858. [Google Scholar] [CrossRef]
  20. Malaysia Energy Commission. Malaysia Energy Statistics Handbook 2015; Energy Commission: Kuala Lumpur, Malaysia, 2016. [Google Scholar]
  21. Tehrani, S.S.M.; Avval, M.S.; Alvandifar, N.; Rabiei, H. Technical and economic evaluation of gas turbine inlet air cooling in a combined cycle power plant. In Proceedings of the 3rd Conference on Thermal Power Plants, Tehran, Iran, 18–19 October 2011; pp. 1–6. [Google Scholar]
  22. Kothari, D.P.; Nagrath, I. Modern Power System Analysis; Tata McGraw-Hill Education: New York, NY, USA, 2011. [Google Scholar]
  23. Chua, K.H.; Lim, Y.S.; Morris, S. Energy storage system for peak shaving. Int. J. Energy Sect. Manag. 2016, 10, 3–18. [Google Scholar] [CrossRef]
  24. Grigsby, L.L. Electric Power Generation, Transmission, and Distribution; CRC Press: Boca Raton, FL, USA, 2018. [Google Scholar]
  25. Raja, A.; Srivastava, A.P. Power Plant Engineering; New Age International: Delhi, India, 2006. [Google Scholar]
  26. Husain, A. Electric Power System; CBS Publisher & Distributors: Delhi, India, 2014. [Google Scholar]
  27. Ray, S. Electrical Power Systems: Concept, Theory and Practice; PHI Learning Pvt. Ltd.: Delhi, India, 2014. [Google Scholar]
  28. Petek, J.; Hamilton, P. Performance monitoring for gas turbines. Orbit 2005, 25, 64–74. [Google Scholar]
  29. Melodi, A.; Famakin, S. Assessment of solar PV-grid parity in Akure, South-West Nigeria. J. Emerg. Trends Eng. Appl. Sci. 2011, 2, 531–536. [Google Scholar]
  30. Waniczek, P.; Therkorn, D.; Lilley, D. Optimal Gas Turbine Power Plant Operation Regarding Fuel and Maintenance Cost. In Proceedings of the ASME Turbo Expo 2017: Turbomachinery Technical Conference and Exposition, Charlotte, NC, USA; 2017; p. V003T08A009. [Google Scholar]
Figure 1. Electricity generation mix in GWh [20].
Figure 1. Electricity generation mix in GWh [20].
Infrastructures 04 00061 g001
Figure 2. Daily load profile of Universiti Teknologi PETRONAS (UTP) microgrid.
Figure 2. Daily load profile of Universiti Teknologi PETRONAS (UTP) microgrid.
Infrastructures 04 00061 g002
Figure 3. Monthly running hours (by unit).
Figure 3. Monthly running hours (by unit).
Infrastructures 04 00061 g003
Figure 4. Monthly energy generation in GWh.
Figure 4. Monthly energy generation in GWh.
Infrastructures 04 00061 g004
Figure 5. Efficiency of a turbine and compressor as function of load [2].
Figure 5. Efficiency of a turbine and compressor as function of load [2].
Infrastructures 04 00061 g005
Figure 6. Fuel consumption as a function of load [2].
Figure 6. Fuel consumption as a function of load [2].
Infrastructures 04 00061 g006
Figure 7. Variation of capacity factor by month.
Figure 7. Variation of capacity factor by month.
Infrastructures 04 00061 g007
Figure 8. Variation of plant use factor by month.
Figure 8. Variation of plant use factor by month.
Infrastructures 04 00061 g008
Figure 9. Variation of load factor by month.
Figure 9. Variation of load factor by month.
Infrastructures 04 00061 g009
Figure 10. Variation of utilization factor by month.
Figure 10. Variation of utilization factor by month.
Infrastructures 04 00061 g010
Figure 11. Hourly variation of load and fuel consumption rate (m 3 /kWh) for the month of January (2017).
Figure 11. Hourly variation of load and fuel consumption rate (m 3 /kWh) for the month of January (2017).
Infrastructures 04 00061 g011
Table 1. Summary of the installed capacity (MW) in Malaysia until 2014 [20].
Table 1. Summary of the installed capacity (MW) in Malaysia until 2014 [20].
HydroNatural GasCoalDieselBiomassSolarBiogasOthersTotal
TNB19114705------6616
IPPs2080697200-----15,289
PeninsularCo-Generation-514-879--51652
Self-Generation5--3382931--637
SREP/ FiT9---1916012-200
Subtotal194613,2887200346392161125123,396
SESB70112-181----363
IPPs-922-190----1112
SabahCo-Generation-42-8110---160
Self-Generation----115-3-543
SREP/ FiT7--425520--59
Subtotal77107608032770302236
SEB351595480158----1584
IPPs2400-------2400
SarwakCo-Generation-289--60---289
Self-Generation---960--170
Subtotal275188448016760--14343
Total477315,24876801315729161155229,973
Table 2. Summary of UTP microgrid (installed capacity, monthly generation, and capacity utilization).
Table 2. Summary of UTP microgrid (installed capacity, monthly generation, and capacity utilization).
MonthInstalled Capacity (kW)Generation (kW)Capacity Utilized (%)
Unit AUnit BOverallUnit AUnit BOverallUnit AUnit BOverall
January4200420084006423073371515.273.144.2
February42004200840022383358559653.279.966.6
March42004200840022933311560454.578.866.7
April42004200840024313405583657.881.069.4
May42004200840022723411568354.081.267.6
June42004200840035152301581683.654.769.2
July42004200840033122013532578.847.963.3
August42004200840025483119566660.660.667.4
September42004200840021733326546151.779.165.0
October4200420084007193258549917.177.565.4
November42004200840034682213568182.552.667.6
December42004200840035222148567083.851.167.5
Table 3. Monthly energy generation and running hours of the UTP microgrid (based on the year of 2017).
Table 3. Monthly energy generation and running hours of the UTP microgrid (based on the year of 2017).
MonthEnergy Generation (kWh)Average Running HoursCapacity Factor
Unit AUnit BOverall
January3,700,0445207226210.70
February3,347,1835435695560.71
March3,532,988532601566.50.74
April3,829,8046535315920.77
May3,733,9236485245860.75
June3,580,045665446555.50.76
July3,359,7906774155460.73
August3,716,390676469572.50.77
September3,388,5434946345640.71
October3,503,454590471530.50.78
November3,596,5306354895620.76
December3,297,978525492508.50.77
Average3,548,889596.5530.25563.380.75
Table 4. Monthly energy production and fuel consumption.
Table 4. Monthly energy production and fuel consumption.
MonthFuel ConsumptionEnergy GenerationFuel Consumption Rate
(m 3 )(kWh)(m 3 /kWh)
January1,414,9183,700,0440.38
February1,322,8763,347,1830.39
March1,348,7023,532,9880.38
April1,385,4443,829,8040.36
May1,342,2693,733,9230.35
June1,254,6553,580,0450.35
July1,249,6533,359,7900.37
August1,352,7063,716,3900.36
September1,218,6193,388,5430.35
October1,243,8693,503,4540.35
November1,350,2043,596,5300.37
December1,199,1803,297,9780.36
Total15,683,09542,586,675-

Share and Cite

MDPI and ACS Style

Uddin, M.; Romlie, M.F.; Abdullah, M.F. Performance Assessment and Economic Analysis of a Gas-Fueled Islanded Microgrid—A Malaysian Case Study. Infrastructures 2019, 4, 61. https://doi.org/10.3390/infrastructures4040061

AMA Style

Uddin M, Romlie MF, Abdullah MF. Performance Assessment and Economic Analysis of a Gas-Fueled Islanded Microgrid—A Malaysian Case Study. Infrastructures. 2019; 4(4):61. https://doi.org/10.3390/infrastructures4040061

Chicago/Turabian Style

Uddin, Moslem, Mohd Fakhizan Romlie, and Mohd Faris Abdullah. 2019. "Performance Assessment and Economic Analysis of a Gas-Fueled Islanded Microgrid—A Malaysian Case Study" Infrastructures 4, no. 4: 61. https://doi.org/10.3390/infrastructures4040061

Article Metrics

Back to TopTop