Next Article in Journal
Singularity, Observability and Statistical Independence in the Context of Chaotic Systems
Previous Article in Journal
On the General Sum Distance Spectra of Digraphs
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

The Optimization of Working Time for a Consecutively Connected Production Line

1
School of Economics & Management, Beijing Information Science & Technology University, Beijing 100192, China
2
Institute of Intelligent Manufacturing Technology, Shenzhen Polytechnic, Shenzhen 518055, China
3
Academy of Mathematics and Systems Science, Chinese Academy of Sciences, Beijing 100190, China
*
Authors to whom correspondence should be addressed.
Mathematics 2023, 11(2), 309; https://doi.org/10.3390/math11020309
Submission received: 29 November 2022 / Revised: 30 December 2022 / Accepted: 3 January 2023 / Published: 6 January 2023

Abstract

:
Most factory production processes are completed by machines and workers on production lines. The operation schedule is arranged to reduce the cost of the enterprises to obtain the maximum economic profit for sustainable running. Previous studies usually investigated the working time while only considering the workers’ conditions. This study proposed a method to optimize the operation schedule by jointly considering the workers’ fatigue states and the operation states of machines. This method was proposed based on a system structure called the multistate consecutively connected system (MCCS), which has been widely applied in many areas, such as electronic communications. This structure is also an analogy of the production line. The corresponding model is constructed based on the universal generating function (UGF) since it is a powerful tool in modeling a consecutively connected system. The proposed model can be used to evaluate the different productivities of different types of workers in different states and to realize the screening of the whole scheme through simulation. According to the proposed method, we obtained the optimal operation schedule, including the working time, rest time and allocation strategy for a production line system. Some examples are provided to illustrate the proposed method.

1. Introduction

In the transition from Industry 3.0 to Industry 4.0, companies have gradually replaced manual production by purchasing or leasing machines. However, most companies do not utilize full machine operation due to capital, operation or safety issues [1,2,3]. Thus, it is very important that machines and humans work perfectly together. MCCSs are widely applied in communication and industrial fields. An MCCS consists of several ordered positions. Workers or machines are assigned to work at each position. If any process in the linear production system is not qualified, the product will fail.
Researchers have done a lot of studies in reliability modeling and optimization of MCCS [4,5,6,7,8]. For example, Peng et al. [9] studied combined elements allocation and maintenance optimization. Levitin et al. [10] introduced the phased mission system, which had never been previously studied, and formulated a new optimal connected elements allocation problem. Gao et al. [11] proposed a model of LMCCS that considered signal loss. Through the joint optimization of a node building and connection elements allocation strategy, the optimal design problem of the system was solved. To date, there have been no studies related to MCCS on industrial production lines to reasonably alleviate worker fatigue.
In fact, none of the existing works considered worker fatigue when improving the production line to obtain the optimal work plan. Many researchers studied the impact of improved worker posture on product quality [12,13,14]. For example, Zhang et al. [15] studied the fatigue time threshold and labor time rate of standing, sitting, and alternating standing and sitting postures by analyzing the fatigue of operators in different working postures on a linear production system. Much work was also done to improve the efficiency of hardware in linear production systems without considering human fatigue [16,17,18,19,20,21]. For example, Lin et al. [22] studied JIT’s linear production system production efficiency improvement method. Taking a certain cable automatic production line as the research object, in order to solve the problems of an unbalanced production line, a large inventory of work-in-process, and production efficiency that cannot meet customers’ needs, research based on improvements to JIT was undertaken.
In this work, we introduced an MCCS to study the work fatigue of workers in the production line, which has never been previously studied. MCCS is used as a theoretical basis to study the product transfer between workers on a linear production system, which is of great significance in factory production. In this study, workers are rationally assigned to workstations according to their working hours and fatigue status, which reduced costs and losses for the purpose of increasing corporate profits. In order to increase the production accuracy of the production line, one possible way is to apply more machines, but this will increase the rental cost of machines and reduce the profit. Another method is to change each working time to improve the production accuracy of the worker. In this study, the optimal strategy was studied, which involved the assignment of work types to each workstation, to identify the optimal work schedule.
The remainder of the paper is organized as follows. In Section 2, we introduce the theoretical basis. In Section 3, we describe the problem and build the model. In Section 4, we provide data analysis. In Section 5, we conclude this paper.

2. Theoretical Basis

2.1. Learning Curve Theory

Yerkes–Dodson Law: The optimal level of motivation is not fixed, but varies with the nature of the task. In the completion of simple tasks, the intensity of motivation is high and the efficiency of work is higher [23,24]. In general, the stronger the motivation, the higher the enthusiasm for work; the better the potential, the higher the efficiency. Conversely, the lower the motivation, the lower the efficiency. Thus, work efficiency increases as motivation increases. However, research by the psychologist Yerkes confirmed that the relationship between motivation intensity and work efficiency is not linear, but rather an inverted U-shaped-curve relationship. This is reflected by the fact that work efficiency is the highest when the motivation intensity is appropriate. When the motivation intensity is too low, there is a lack of motivation to participate in activities and work efficiency cannot be improved. When the motivation intensity exceeds the peak, the work efficiency will continue to decrease as the motivation intensity increases. This is because excessive motivation puts the individual in a state of excessive anxiety and stress, interfering with the normal activity of mental processes, such as memory and thinking. According to the Yerkes–Dodson law, workers first experience a period of adaptation when they start working; then, their efficiency gradually increases and reaches a steady state within a certain period. Then, workers begin to fatigue and productivity gradually decreases. This relationship is shown in Figure 1.
Figure 1 provides the theoretical basis for this study. The new hands who are just starting their training have a much more difficult time on the job than skilled workers. For the skilled worker, the difficulty factor is lower because the work is already familiar to them [25]. Therefore, for the new hands who are just entering training, according to the Yerkes–Dodson law, workers begin their work by going through a period of adaptation, during which efficiency gradually increases until they reach a steady state. With the increase of time, the efficiency of workers gradually decreases as they fatigue, and hence, productivity decreases.

2.2. Human Factors Fatigue Curve Theory

Work curve: The curve of job performance over time under specific working conditions [26]. The indicators of work performance are as follows: output, productivity, correctness, success rate, etc. A typical work curve consists of four stages: work initiation stage, maximum work capacity stage, work capacity reduction stage, and work final sprint stage. The first three of these stages are inverted U-shaped curves, but the last stage is usually upturned.
In the era of transition from manual operations to mechanization, it is very common to combine machines with mechanized manufacturing. Due to the huge cost of machinery, the company as a for-profit company has limited capital to invest. If too much money is invested in purchasing new equipment, it will increase the risk of the company’s operation. Therefore, the purpose of this study was to find a balance between the number of producers and the number of machines to maximize profit. Based on the learning curve theory and human factor fatigue theory, we could calculate the statistics of worker fatigue and energy and then compare the costs of different types of workers.

3. Problem Description and Model Building

Considering the different numbers of workstations in actual factory production, eight workstations were selected as an example in this study. The continuous production system consisted of eight workstations represented by C i ( i = 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 ). Assumptions in this study: (1) The eight workstations had the same working time and the same delivery time. (2) The workstations in the linear production system were independent, which meant that the costs of different workstations were independent. (3) The types of workers investigated in this study were skilled workers and new hands. Since the time required for each process varied, the productivity varied by worker type. The production process is shown in Figure 2. From Section 2, the productivity of workers is different for 1, 2, and 3 h of work, and the productivities of workers in energetic and fatigued states are also different. This study did not provide a method of detection for their wakefulness or fatigue. The productivity of skilled workers and new hands in fatigued and energetic states are different, as shown in Table 1. Let G i C indicate the random variable representing the productivity of the i th workstation C i and assume there are K i C possible states for workstation C i . Let g i c ( k ) be the productivity at workstation C i when C i occupies state k and p i c ( k ) be the probability of C i being in work state k , where k = 1 , , K i C .
In this study, we assumed that the work state coefficients of skilled workers were 0.8 and 0.2 when they were energetic and fatigued, respectively; the work state probabilities of new hands were 0.6 and 0.4 when they were energetic and fatigued, respectively. This assumption was reasonable since new hands are less skilled and proficient than skilled workers. Skilled workers are more accustomed to the production method of the project and are better in terms of working time and accuracy. Therefore, we can avoid fatigue and increase the productivity of workers by increasing the frequency of their breaks. However, reducing the time that workers spend on their work too much will reduce productivity and profit. We studied this problem to give the optimal job plan for the production line system.
In this paper, we refer to the body–brain fatigue theory and data experiments to make assumptions about the rest duration of workers: (1) workers need a rest time of 10 min to return to an energetic state when they work for 1 h, (2) workers need a rest time of 15 min to return to an energetic state when they work for 2 h, and (3) workers need a rest time of 20 min to return to an energetic state when they work for 3 h. In addition, we assumed that the total time was 8 h, which included working time and rest time. In order to maximize productivity, we provide four kinds of working time plans combining working time and rest time, as shown in Table 2.

3.1. UGF of the Workstation

According to the different physical and psychological states of each worker every day, not all workers can completely relieve fatigue through a period of rest. The probability of this difference occurring is as follows:
  • A 10 min rest for every hour of work: skilled workers have an 80% probability of being well rested and new hands have a 60% probability of being well rested;
  • A 15 min rest for every 2 h of work: skilled workers have an 80% probability of being well rested and new hands have a 60% probability of being well rested;
  • A 20 min rest for every 3 h of work: skilled workers have an 80% probability of being well rested and new hands have a 60% probability of being well rested.
Although the machine can run continuously at full load in actual production, long time operation can make the system fail. Therefore, it is very important to control the risk of the system, and the machine operation should be stopped after a period of time to allow the machine to dissipate heat [27,28]. On the one hand, this can keep the productivity of the machine at a high level, and on the other hand, it can reduce the maintenance cost. Therefore, we assumed that the machine works for 1 h with 10 min of heat dissipation, the machine works for 2 h with 15 min of heat dissipation, and the machine works for 3 h with 20 min of heat dissipation. We assumed that E t denotes that there are three types of producers working at the workstation, namely, skilled workers, new hands, and machines. G t E indicates the random variable representing the productivity of producers E t . In addition, we assumed that there were K t E possible states for the work state of E t . g t e ( k ) denotes the productivity of producers E t when E t occupies work state k and p t e ( k ) indicates the probability of E t being at work state k , where k = 1 , , K t E .
In this study, we adopted the UGF method to analyze the reliability of the MCCS [29,30,31]. Let u ( z ) represent the UGF of the independent discrete random variable X as a polynomial:
u ( z ) = k = 1 K p k z X k
where K indicates the number of possible realizations of the variable X , p k is the probability that X takes the value x , and z is an indicator variable that has no practical significance. To evaluate the probability that a random variable X is not less than the realized w , the coefficients of the polynomial u ( z ) should be summed for each term with x k w :
Pr { X w } = x k w p k
This can be done using the following δ operator over u ( z ) as follows:
δ ( u ( z ) , w ) = δ ( k = 1 K p k z X k , w ) = k = 1 K [ 1 ( x k w ) p k ]
where 1 ( x k w ) = 1 if x k w is true and 1 ( x k w ) = 0 if x k w is false.
To obtain the UGF of the entire consecutively connected production system, it is necessary to define the UGF of each station in the production line. If h i is the type of work at workstation C i , we obtain G i C = G h i E . The productivity g i c ( k ) = { g i c ( k ) 1 , , g i c ( k ) N } is obtained from g h i e ( k ) = { g h i e ( k ) 1 , , g h i e ( k ) N } by taking the first N i items as g i c ( k ) = { g i c ( k ) 1 , , g i c ( k ) N } = { g h i e ( k ) 1 , , g h i e ( k ) N } , where k = 1 , , K i C and K i C = K h i E .
For workstation C i on the production line, let the productivity G i c represent a random variable X , where the productivity { g i c ( 1 ) , , g i c ( K i C ) } is the state probability of { x 1 , , x K i C } . p i c ( k ) denotes the probability of different states presented by workers. Therefore, we obtain the UGF of workstation C i as follows:
u i c ( z ) = k = 1 K i C p i c ( k ) z g i c ( k )
To conveniently express the information of the UGF, the probability of each state is associated with the performance in that state, and this approach can be used to represent all possible states. The UM of workstation C i is
U M i C = [ p i c ( 1 ) g i c ( 1 ) 1 g i c ( 1 ) N i + 1 p i c ( K i C ) g i c ( K i C ) 1 g i c ( K i C ) N i + 1 ]

3.2. UGF for Consecutively Connected Production System

The productivity of the consecutively connected production system is the product of the productivity of all eight workstations, and the entire linear system equation is as follows:
R S K i = g i c ( K i C )
Next, we describe the worker productivity of the entire system using UGF as follows:
u N s ( z ) = k = 1 K N S p N s ( k ) z g N s ( k )
When choosing a skilled worker, a new hand, or a machine, there will be corresponding reliability rates to ensure the effectiveness of the system. r is the minimum requirement for system reliability. Thus, we can estimate the reliability system according to (3) as follows:
R = δ ( u N s ( z ) , r ) = δ ( k = 1 K N S p N s ( k ) z g N s ( k ) , r ) = k = 1 K N S [ 1 ( g N s ( k ) 1 r ) p N s ( k ) ]

3.3. Production Cost

The total cost of the consecutively connected production system consists of labor costs and material costs.

3.3.1. Labor Cost

Labor costs vary depending on the type of workers selected for each permutation and are calculated as follows:
V E = i = 1 C T h i E V h i E
where V E denotes the total labor cost when completing the work task. V h i E is the wage of the producer of type h i , where the cost of the machine is the rental cost. T i C denotes the working time of the producer of type h i .

3.3.2. Material Cost

The input cost is equal to the daily input amount because no matter which working time arrangement plan is used, the workers work 7 h, and thus, the daily material input amount is equal; according to the 100 pieces of material input per hour, the daily input amount is 700 pieces. Thus, let V C denote the material cost. The material cost of the entire system is i = 1 N V C .
Therefore, we obtain the total cost T C of the system as follows:
T C = i = 1 N V C + V E = i = 1 N ( V C + T h i E V h i E )

3.4. Revenue from Product Sales

The product sales revenue T R can be obtained as follows:
T R = Q N S × P = R S K i ( T N S N T x ) T Q × P
where Q N S denotes the number of products in the specified working time. P is the selling price of each product. R S K i denotes the productivity of the production line system. T N S is the total time of production. N is the number of producers. T x is the time that work is suspended. T Q indicates the time required to complete a product.

3.5. Profitability

The total profit T P can be obtained as follows:
T P = T R T C

4. Reliability Analysis

Consider scheduling labor for each workstation. Productivity in a linear production system affects the next process. In order to avoid low reliability of the final product, machines or skilled workers should be arranged at the initial stage of production. New hands with lower wages should be scheduled in the subsequent stages to complete the production tasks.
In this study, the optimization was performed for an MCCS consisting of eight workstations. Table 3 provides the work time combinations under different work schedules and expresses the optimization results in terms of profit. Since each workforce had the same productivity and fatigue probability when working at the workstations in the MCCS, the specific allocation of the workforce is not shown in Table 3.
As shown in Table 3, the optimal solution for option 4 is the best, i.e., a combination of three one-hour and two two-hour working hours. This scenario yielded the highest profit and was applicable under all conditions. From the results, product production should be arranged with as many skilled workers as possible and a small number of new manual workers. This not only ensures a low input–output ratio but also generates higher profits. To better compare the impact of the number of skilled workers and machines on profits, we depict the comparison results in Figure 3.
As shown in Figure 3, the horizontal axis represents the number of skilled workers. Since the only objects of comparison were skilled workers and machines, and the sum of skilled workers and machines is 8, the number of machines decreased as the number of skilled workers increased. From the results, only the profit of plan 4 increased with the increase of skilled workers and the cost of the system gradually decreased. The profits of the other three plans decreased as the number of skilled workers increased.
Although the machine has the advantages of high productivity and a steady state, the cost required to run it is too high. For small- and medium-sized manufacturing companies, the high cost of machines prevents fully automated production on the production line. Therefore, plan 1, plan 2, and plan 3 can be selected to increase the number of machines appropriately to improve profits. Choosing plan 4 to produce products without considering the introduction of machines and the company obtained a better profit than the other three plans. To further illustrate the advantages of plan 4, we show Figure 4.
As shown in Figure 4, the reliability of the automatic filtering of the system was less than 0.0000384 due to the low systemic error caused by the mismatch between inputs and outputs. Figure 4 represents a comparison of the ratio of profit to cost between new hands and skilled workers. The results showed that the ratios of all four plans increased with the number of skilled workers. However, the increasing trend of the ratio of plan 4 was significantly better than the other three plans.
In conclusion, for MCCS in this case, plan 4 was chosen as the best, i.e., the combination of a 10 min rest for every one hour of work and a 15 min rest for two hours of consecutive work was selected. For the allocation of producers, as many skilled workers as possible were assigned. Although the cost of wages will be more than for the new hands, the profit for the company was higher than with the machines and new hands.

5. Conclusions

In this study, we proposed a method to optimize the operation schedule by jointly considering the workers’ fatigue states and the operation states of machines for the production line of MCCS. The corresponding model was constructed based on the universal generating function (UGF). The model can be used to evaluate the different productivity of different types of workers in different states. In this model, we mainly considered three kinds of producers: skilled workers, new hand workers, and machines. Each producer worked in two states: energetic and fatigued, and productivity changed with the change in state. The results of each operation schedule were reflected in the profit. According to the results of numerical examples, work priority was given to the types of work with high productivity, such as machines and skilled workers. Thus, the best strategy suggested that in the order of workstations, the machines and skilled workers were arranged at former positions, while the new hands are arranged at the last workstations. In this case, it was convenient for rearrangement when there were idle skilled workers or machines in the actual production process. The priority of arranging the number of producers in the production line was skilled workers > machines > new hands. According to the proposed method, we obtained the optimal operation schedule, including working time, rest time and allocation strategy for a production line system.
The work in this study can be extended in a few directions. One direction is the extension of the model to consider production lines where workers are unable to implement the same tasks as the machines. Another direction is to consider the optimal operation plan for multiple production lines.

Author Contributions

Conceptualization, B.L. and K.G.; methodology, Y.R., Z.W. and K.G.; software, B.L. and Y.R.; validation, B.L., Y.R. and Z.W.; formal analysis, Z.W.; investigation, Y.R. and Z.W.; resources, B.L. and X.G.; data curation, X.L.; writing—original draft preparation, B.L., Y.R., Z.W. and K.G.; writing—review and editing, X.G. and X.L.; visualization, Z.W. and Y.R; supervision, B.L. and K.G.; project administration, K.G; funding acquisition, B.L., K.G. and X.G. All authors have read and agreed to the published version of the manuscript.

Funding

This work was funded in part by the National Natural Science Foundation of China under grants 72001027, 72071005, and 72001078; Beijing Municipal Commission of Education under grant KM202111232007; and China Postdoctoral Science Foundation under grant 2021M693331.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
MCCSMultistate consecutively connected system
UGFUniversal generating function
UMUGF information matrix
C i Workstation at position i
G i C The random variable representing the productivity of the i th workstation C i
K i C Number   of   different   states   of   C i
g i c ( k ) The productivity   at   workstation   C i when C i occupies state k
p i c ( k ) The probability of C i being in work state k , where k = 1 , , K i C
E t The producer of type t ,   where   t = 1 , , T
G t E The   random   variable   representing   the   productivity   of   E t
K t E Number   of   different   states   of   E t
g t e ( k ) The   productivity   by   producers   E t   when   E t occupying work state k
P t e ( k ) The   probability   of   E t being in work state k ,   where   k = 1 , , K t E
h i The   type   of   producer   at   workstation   C i
u ( z ) UGF representing the performance distribution of a discrete random variable
r The minimum requirement for system reliability
R Reliability of the considered MCCS
VEThe total labor cost when completing the work task
V h i E The   wage   of   the   producer   of   type   h i , where the cost of the machine is the rental cost
T i C The   working   time   of   the   producer   of   type   h i
V C The material cost
T C Total cost of the MCCS
T R The product sales revenue
Q N S The number of products in the specified working time
P The selling price of each product
R S K i The productivity of the production line system
T N S The total time of production
N The number of producers
T x The time that work is suspended
T Q The time required to complete a product
T P The total profit

References

  1. Bakkari, M.; Khatory, A. Industry 4.0: Strategy for more sustainable industrial development in SMEs. In Proceedings of the IEOM 7th International Conference on Industrial Engineering and Operations Management, Rabat, Morocco, 11–13 April 2017. [Google Scholar]
  2. Liu, Z.; Xie, K.; Li, L.; Chen, Y. A paradigm of safety management in industry 4.0. Syst. Res. Behav. Sci. 2020, 37, 632–645. [Google Scholar] [CrossRef]
  3. Wadgaonkar, J.; Mane, N.; Bhole, K.; Shinde, D. Novel, low cost, efficient manual cum automation based alcohol & ethanol production plant. In Proceedings of the 2015 International Conference on Energy Systems and Applications, Pune, India, 30 October–1 November 2015. [Google Scholar]
  4. Levitin, G.; Yeh, W.C.; Dai, Y. Minimizing bypass transportation expenses in linear multistate consecutively-connected systems. IEEE Trans. Reliab. 2014, 63, 230–238. [Google Scholar] [CrossRef]
  5. Levitin, G.; Xing, L.; Dai, Y. Optimal arrangement of connecting elements in linear consecutively connected systems with heterogeneous warm standby groups. Reliab. Eng. Syst. Saf. 2017, 165, 395–401. [Google Scholar] [CrossRef]
  6. Xing, L.; Levitin, G. Connectivity modeling and optimization of linear consecutively connected systems with repairable connecting elements. Eur. J. Oper. Res. 2018, 264, 732–741. [Google Scholar] [CrossRef]
  7. Zhao, X.; Chai, X.; Sun, J.; Qiu, Q. Joint optimization of mission abort and protective device selection policies for multistate systems. Risk Anal 2022. [Google Scholar] [CrossRef] [PubMed]
  8. Peng, R.; Wu, D.; Gao, K. Reliability of a Dual Linear Consecutive System with Three Failure Modes. In Proceedings of the International Conference of Celebrating Professor Jinhua Cao’s 80th Birthday, Singapore, 16 October 2019. [Google Scholar]
  9. Peng, R.; Xie, M.; Ng, S.H.; Levitin, G. Element maintenance and allocation for linear consecutively connected systems. IIE Trans. 2012, 44, 964–973. [Google Scholar] [CrossRef]
  10. Levitin, G.; Xing, L.; Dai, Y. Optimal Allocation of Connecting Elements in Phase Mission Linear Consecutively-Connected Systems. IEEE Trans. Reliab. 2013, 62, 618–627. [Google Scholar] [CrossRef]
  11. Gao, K.; Yan, X.; Peng, R.; Xing, L. Economic design of a linear consecutively connected system considering cost and signal loss. IEEE Trans. Syst. Man Cybern. Syst. 2021, 51, 5116–5128. [Google Scholar] [CrossRef]
  12. Glock, C.H.; Grosse, E.H.; Kim, T.; Neumann, W.P.; Sobhani, A. An integrated cost and worker fatigue evaluation model of a packaging process. Int. J. Prod. Econ. 2019, 207, 107–124. [Google Scholar] [CrossRef]
  13. Zhang, Z.; Wang, K.; Zhu, L.; Cheng, W. Pareto Hybrid Ant Colony and Genetic Algorithm for Multi-Objective U-Shaped Disassembly Line Balancing Problem. J. Southwest Jiaotong Univ. 2018, 53, 628–637. [Google Scholar]
  14. Karuppiah, K.; Sankaranarayanan, B.; Ali, S.M.; Kabir, G. Role of Ergonomic Factors Affecting Production of Leather Garment-Based SMEs of India: Implications for Social Sustainability. Symmetry 2020, 12, 1414. [Google Scholar] [CrossRef]
  15. Zhang, J.; Kong, Q. Fatigue analysis of assembly line work posture. Mod. Manuf. Eng. 2009, 10, 58–61. [Google Scholar]
  16. Lai, C.; Yao, J. Design of Man–Machine Cooperative Assembly Line Based on Mathematical Model and Simulation. In Proceedings of the International Conference on Man-Machine-Environment System Engineering, Singapore, 22 September 2021. [Google Scholar]
  17. Shan, H.; Yuan, Y.; Zhang, Y.; Wang, C. Lean, simulation and optimization: The case of steering knuckle arm production line. In Proceedings of the 2018 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM), Bangkok, Thailand, 16–19 December 2018. [Google Scholar]
  18. Han, D.; Tang, Q.; Zhang, Z.; Li, Z. An Improved Migrating Birds Optimization Algorithm for a Hybrid Flow Shop Scheduling within Steel Plants. Mathematics 2020, 8, 1661. [Google Scholar] [CrossRef]
  19. Gao, K.; Peng, R.; Qu, L.; Wu, S. Jointly optimizing lot sizing and maintenance policy for a production system with two failure modes. Reliab. Eng. Syst. Saf. 2020, 202, 106996. [Google Scholar] [CrossRef]
  20. Qu, L.; Liao, J.; Gao, K.; Yang, L. Joint Optimization of Production Lot Sizing and Preventive Maintenance Threshold Based on Nonlinear Degradation. Appl. Sci. 2022, 12, 8638. [Google Scholar] [CrossRef]
  21. Llopis, J.; Lacasa, A.; Garcia, E.; Montés, N.; Hilario, L.; Vizcaíno, J. Manufacturing Maps, a Novel Tool for Smart Factory Management Based on Petri Nets and Big Data Mini-Terms. Mathematics 2022, 10, 2398. [Google Scholar] [CrossRef]
  22. Lin, Y.; Guo, J. Research on the method of improving the production efficiency of the assembly line based on JIT. Ind. Eng. Manag. 2012, 17, 124–128. [Google Scholar]
  23. Corbett, M. From law to folklore: Work stress and the Yerkes-Dodson Law. J. Manag. Psychol. 2015, 30, 741–752. [Google Scholar] [CrossRef]
  24. Gwyer, P.G. Applying the Yerkes-Dodson Law to Understanding Positive or Negative Emotions. Glob. J. Intell. Dev. Dis. 2017, 3, 37–39. [Google Scholar]
  25. Shin, W.S.; Son, C.B. A Plans for Attraction-Training-Maintenance of Domestic Construction Skilled Workers. J. Archit. Inst. Korea 2021, 37, 191–200. [Google Scholar]
  26. Martinez, I.; Revilla, J. Investigating the effect on the learning curve of performing similar work during the break between work stints. Procedia Manuf. 2015, 3, 3456–3462. [Google Scholar] [CrossRef]
  27. Yang, L.; Chen, Y.; Qiu, Q.; Wang, J. Risk Control of Mission-Critical Systems: Abort Decision-Makings Integrating Health and Age Conditions. IEEE Trans. Ind. Inform. 2022, 18, 6887–6894. [Google Scholar] [CrossRef]
  28. Qiu, Q.; Maillart, L.M.; Prokopyev, O.A.; Cui, L. Optimal Condition-Based Mission Abort Decisions. IEEE. Trans. Reliab. 2022, 5, 1–18. [Google Scholar] [CrossRef]
  29. Huang, S.; Lei, B.; Gao, K.; Wu, Z.; Wang, Z. Multi-State System Reliability Evaluation and Component Allocation Optimization Under Multi-Level Performance Sharing. IEEE Access 2021, 9, 88820–88834. [Google Scholar] [CrossRef]
  30. Gao, K.; Peng, R.; Qu, L.; Xing, L.; Wang, S.; Wu, D. Linear system design with application in wireless sensor networks. J. Ind. Inf. Integr. 2022, 27, 100279. [Google Scholar] [CrossRef]
  31. Gao, K.; Yan, X.; Xiao, H.; Peng, R. Reliability Modelling of Multi-Phased Linear Consecutively Connected Systems. In Stochastic Models in Reliability Engineering, 3rd ed.; Cui, L., Frenkel, L., Eds.; CRC Press: Boca Raton, FL, USA, 2020; pp. 41–48. [Google Scholar]
Figure 1. Productivity graph for different types of work at different times.
Figure 1. Productivity graph for different types of work at different times.
Mathematics 11 00309 g001
Figure 2. Workstation simulation diagram.
Figure 2. Workstation simulation diagram.
Mathematics 11 00309 g002
Figure 3. Cost and profit with respect to the number of skilled workers and machines.
Figure 3. Cost and profit with respect to the number of skilled workers and machines.
Mathematics 11 00309 g003
Figure 4. Cost of profit for skilled workers and new hands.
Figure 4. Cost of profit for skilled workers and new hands.
Mathematics 11 00309 g004
Table 1. Efficiencies of different types of work and different states with their associated parameters and descriptions.
Table 1. Efficiencies of different types of work and different states with their associated parameters and descriptions.
Skilled WorkerNew HandMachine
StatusEnergeticFatigueEnergeticFatigueStatus of Use
Average productivity during 1 h of work0.950.90.90.851
Average productivity during 2 h of work0.990.950.950.9
Average productivity during 3 h of work0.980.930.930.88
Table 2. Combination of working hours under different work plans.
Table 2. Combination of working hours under different work plans.
Plan 1Plan 2Plan 3Plan 4
1 h work7543
2 h work0102
3 h work0010
Table 3. Profit comparison of different work plans.
Table 3. Profit comparison of different work plans.
Number of Skilled WorkersNumber of New HandsNumber of MachinesTotal CostPlan 1 ProfitPlan 2 ProfitPlan 3 ProfitPlan 4 Profit
008432,000268,000268,000268,000268,000
017413,100202,900212,900211,900222,900
026394,200147,880165,980163,990184,080
035375,300101,730126,307123,360150,884
044356,40063,38793,05889,203122,729
053337,50031,91265,50460,80299,095
107413,300244,700254,700253,700264,700
116394,400184,640203,340201,290222,040
125375,500134,055159,718156,652185,381
134356,60091,809122,955118,923154,100
143337,70056,90092,27187,339127,643
206394,600223,920243,220241,110262,520
215375,700168,598195,383192,193222,168
224356,800122,182154,868150,652187,553
233337,90083,604120,844115,670158,085
242319,00051,92492,57986,523133,234
251300,10026,31369,42162,567112,529
305375,900205,509233,452230,136261,395
314357,000154,640188,933184,525223,225
323338,100112,143151,344145,917190,546
332319,20077,014119,903113,537162,793
341300,30048,36893,91686,698139,463
350281,40025,42872,76864,791120,108
404357,200189,324225,294220,687261,263
413338,300142,641183,900178,209225,159
422319,400103,828149,070142,378194,311
431300,50071,941120,062112,463168,182
440281,60046,14896,22187,811146,294
503338,500175,233218,650212,682262,067
512319,600132,485180,202173,169227,919
521300,70097,135147,970139,969198,805
530281,80068,295121,255112,389174,215
602319,800163,109213,431206,040263,753
611300,900124,060177,758169,336231,456
620282,00091,965147,975138,629203,985
701301,100152,834209,552200,686266,269
710282,200117,262176,494166,643235,726
800282,400144,298206,933196,551269,569
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Lei, B.; Ren, Y.; Wang, Z.; Ge, X.; Li, X.; Gao, K. The Optimization of Working Time for a Consecutively Connected Production Line. Mathematics 2023, 11, 309. https://doi.org/10.3390/math11020309

AMA Style

Lei B, Ren Y, Wang Z, Ge X, Li X, Gao K. The Optimization of Working Time for a Consecutively Connected Production Line. Mathematics. 2023; 11(2):309. https://doi.org/10.3390/math11020309

Chicago/Turabian Style

Lei, Bingyin, Yue Ren, Ziyang Wang, Xinquan Ge, Xiaolin Li, and Kaiye Gao. 2023. "The Optimization of Working Time for a Consecutively Connected Production Line" Mathematics 11, no. 2: 309. https://doi.org/10.3390/math11020309

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop