Next Article in Journal
Nanoparticle-Enhanced PVDF Flat-Sheet Membranes for Seawater Desalination in Direct Contact Membrane Distillation
Next Article in Special Issue
Treatment of Semiconductor Wastewater Containing Tetramethylammonium Hydroxide (TMAH) Using Nanofiltration, Reverse Osmosis, and Membrane Capacitive Deionization
Previous Article in Journal
Research Progress with Membrane Shielding Materials for Electromagnetic/Radiation Contamination
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimization and Evaluation for the Capacitive Deionization Process of Wastewater Reuse in Combined Cycle Power Plants

1
School of Civil and Environmental Engineering, Kookimin University, 77 Jeongneung-ro, Seongbuk-gu, Seoul 02707, Republic of Korea
2
Korea Institute of Civil Engineering and Building Technology, 283 Goyang-daero, Ilsanseo-gu, Goyang-si 10223, Republic of Korea
3
Desalination Technologies Research Institute (DTRI), Saline Water Conversion Corporation (SWCC), P.O. Box WQ36+XJP, Al Jubayl 35417, Saudi Arabia
*
Author to whom correspondence should be addressed.
Membranes 2023, 13(3), 316; https://doi.org/10.3390/membranes13030316
Submission received: 3 February 2023 / Revised: 26 February 2023 / Accepted: 3 March 2023 / Published: 9 March 2023
(This article belongs to the Special Issue Selected Papers from the MELPRO 2022)

Abstract

:
Combined cycle power plants (CCPPs) use large amounts of water withdrawn from nearby rivers and generate wastewater containing ions and pollutants. Despite the need for wastewater reclamation, few technologies can successfully convert the wastewater into make-up water for CCPPs. Therefore, this study aimed to apply capacitive deionization (CDI) for wastewater reclamation in CCPPs. Using a bench-scale experimental unit, which included ion exchange membranes and carbon electrodes, response surface methodology (RSM) was used to optimize the operating conditions of the CDI process to increase the total dissolved solids (TDS) removal and product water ratio. The optimal conditions were found to be a voltage of 1.5 V, a flow rate of 15 mL/min, and an adsorption/desorption ratio of 1:0.8. The changes in CDI performance with time were also studied, and the foulants on the membranes, spacers, and electrodes were examined to understand the fouling mechanism. The TDS removal decreased from 93.65% to 55.70% after 10 days of operation due to the deposition of scale and organic matter. After chemical cleaning, the TDS removal rate recovered to 93.02%, which is close to the initial condition.

1. Introduction

Combined cycle power plants (CCPPs) account for over 80% of the world’s electricity generation. Most of these plants use electric steam technology, which uses large amounts of water to produce steam that turns turbines to generate electricity. The blowdown from the steam cycle is typically quenched to 60 °C. To recycle this stream, a heat exchanger or chiller must be installed in the recycle path for reuse [1]. Combined heat and power plants combine two or more thermal cycles to increase the efficiency of energy use. A representative model is a mixture of a gas turbine cycle and a steam turbine cycle [2,3]. There are two major challenges with CCPPs. First, they use a large amount of pure water to operate the generator turbine and boiler. They also require cooling water to reduce the water temperature inside the plants [4,5]. Second, CCPPs generate wastewater that can harm the environment and human health if not properly treated. The high concentration of organic matter and hardness in the CCPP wastewater remaining in the operating system are the main causes of scale and fouling. This not only reduces the performance of the plant, but also degrades the quality of the treated water from the CCPPs and reduces the quantity of production. In addition, if it is used for irrigation, it can harm crops and make the soil less fertile [6,7,8]. As a result, discharge regulations for treated wastewater from CCPPs have become more stringent.
To address this issue, CCPPs must implement effective wastewater treatment and disposal strategies. A common approach is to treat the effluent using physical, chemical and biological processes to remove contaminants and produce clean water that can meet discharge regulations. These include sedimentation, coagulation and flocculation, activated sludge, or reverse osmosis. Another approach is to completely recycle and reuse wastewater after proper treatment, also known as zero liquid discharge (ZLD). Unlike the first approach, ZLD is free from environmental regulations because it allows for the complete elimination of pollutants. It also reduces water consumption, making it sustainable and environmentally friendly [9,10,11].
However, the application of ZLD to CCPPs is challenging due to the lack of appropriate and affordable technologies [8,12,13,14]. To reuse the wastewater, it is essential to remove ionic species to meet the process water quality. Conventional technologies include reverse osmosis (RO), electrodialysis (EDI), and mechanical vapor recompression (MVR) [15,16,17,18,19,20], which have drawbacks such as high energy consumption and high potential for scale and fouling [21,22]. Capacitive deionization (CDI) is an alternative to conventional deionization because it can effectively remove a wide range of ions, including dissolved salts, heavy metals, and other contaminants [23,24]. CDI requires relatively low energy consumption and maintenance, making it a cost-effective option [25,26,27]. Because of these advantages, CDI has been used to treat feed water that contains less than 2.0 g/L of total dissolved solids (TDS) [28].
Although CDI has the potential for ZLD in CCPPs, there are several issues to consider when applying CDI to the CCPP effluent [29]. Although the fouling potential in CDI is lower than in conventional pressure-driven membrane processes, the possibility of CDI fouling still exists due to contaminants in the effluent. CDI fouling can occur either in the flow path space or on the surfaces of ion exchange membranes and electrodes. In addition, the CDI deionization performance is sensitive to design and operating variables such as voltage, flow rate, sorption time, temperature, and electrode materials [30,31,32,33,34,35]. With so many variables involved, it is difficult to find the optimal conditions for CDI [36].
There are various approaches to optimize engineering systems and water treatment processes based on optimal algorithms, artificial intelligence, machine learning, the finite element method, and computational fluid dynamics [37,38,39,40,41,42,43]. The optimization could be implemented during the initial design assessment stage, leading to a reduction in cost and time [42,43]. Response surface methodology (RSM), which is one of such optimization methods, is efficient in deriving optimal conditions when various variable factors are present. RSM can predict and optimize results according to arbitrary varying levels in the desired range, reducing unnecessary experimental sets and conducting only the necessary experiments to derive optimal conditions [44]. Previous studies have used RSM to optimize treatment processes for municipal wastewater, industrial wastewater, landfill leachate, etc. [45].
The objective of this study was to apply CDI as an affordable technology for wastewater reclamation in CCPPs. The outline of this paper is as follows: First, the effect of operating variables on the TDS removal of CDI was investigated using the one-factor-at-a-time (OFAT) method. Second, further optimization of the operating variables for CDI was performed based on response surface methodology (RSM). Once the optimum conditions were obtained, long-term operation of the CDI was conducted to study performance degradation due to fouling. The foulants in the membranes, spacers, and electrodes were analyzed using FE-SEM, EDS, and XPS. Finally, the effectiveness of chemical cleaning was evaluated.

2. Materials and Methods

2.1. Materials

2.1.1. Principle of CDI

As one of the CDI types, membrane-coupled capacitive deionization (MCDI) was used in this work [46,47,48,49,50]. Ion removal by CDI is performed by repeating the ion adsorption and desorption phases [46,47,48,49,50,51,52]. Water is demineralized in an adsorption phase and the electrodes are regenerated in a desorption phase [8,50,53]. MCDI combines an ion exchange membrane on the electrode surface, reducing the influence of ions of the same charge and reducing the possibility of electrode fouling, resulting in better deionization performance [25,54,55]. CDI in this paper refers to MCDI. The principle of CDI is shown in Figure 1.

2.1.2. CDI Module

The lab-scale MCDI module consists of a few acrylic plates, a cathode, a cation exchange membrane, a spacer, an anion exchange membrane, and an anode (Figure 2). The cathode and an anode made of activated carbon with a size of W100 × L100 mm2 were purchased from Pureechem (Chungcheongbuk-do, South Korea). The adsorption capacity of the electrodes was 16 mg/g. The information about the pore volume and the surface area was not disclosed because the manufacturer considers it confidential information. The ion exchange membrane made of polyethylene with a size of W100 × L100 mm2, and the spacer made of polyethylene terephthalate with a size of W110 × L110 mm2 were provided by Pureechem (Chungcheongbuk-do, South Korea) (Table 1). The upper-left and center of the MCDI unit cell were punched at a size of 1 cm to allow the inflow and outflow water to flow, respectively. The top and bottom of the module had terminals (electrical contacts) that were connected to the electrodes to apply electricity. Since the CDI process was operated in constant voltage mode, the voltage was set to be constant while the current changed.

2.1.3. Experimental Setup

Figure 3 shows a schematic of an experimental apparatus for the CDI process. A pump was used to supply feed water to the CDI module, and a power supply was used to apply voltage to the CDI electrode. The conductivity sensor was connected to a computer for real-time measurement and data collection. An electrode and ion exchange membrane were used after being immersed in ultrapure water for 2 h or more to remove contaminants from surface pores to secure an adsorption site. In addition, adsorption and desorption operations were performed for at least one cycle to achieve concentration equilibrium by an electrical force.
In the adsorption phase, the electrodes were charged to a given voltage, and ions of the opposite charge were attracted to the electrodes. In the desorption phase, the electrodes were switched to a negative potential, which caused the ions to be released from the electrodes, and the ions were released to the feed water passing through the cell. Accordingly, the product water was obtained in the adsorption phase and the concentrate (brine) was generated in the desorption phase.
When the TDS removal decreased to less than 70%, the CDI unit was cleaned in clean-in-place (CIP) mode. When the cleaning began, the remaining feed water was drained and the tank containing cleaning chemicals was connected to the CDI unit. The cleaning was performed in the order of acid (1 mM HCl) and alkali (1 mM NaOH solution), and then all chemicals in the process were drained and sufficient flushing was performed using deionized water.

2.1.4. Feed Solution

Real wastewater effluent from a CCPP (referred to as CCPP ‘A’) in Korea was used as the feed water. Table 2 summarizes the wastewater quality and discharge standard. There are three types of wastewater from a CCPP: power generation wastewater, washing wastewater, and cooling wastewater, and the water quality (especially TDS) fluctuates with time depending on the mixing ratio of the wastewater streams. Therefore, two types of mixed wastewater samples were used in this work. To determine the optimum operating conditions, the high-TDS wastewater (referred to as F1) was used, which represents the worst-case scenario. To evaluate the long-term operating performance, the wastewater with low TDS (referred to F2) was used, which represents the normal operating conditions. The details of the water quality of the wastewater are summarized in Table 2. Since CDI was used to recycle the wastewater, the target water quality was set to the industrial water reuse standard rather than the discharge standard. Thus, the product water quality was compared to the reuse standard. The discharge standard and the industrial water reuse standard are also listed in Table 2.

2.2. Methods

2.2.1. Application of RSM

The central composite design method was used to derive the optimal operating conditions of the CDI [56,57,58]. Voltage ( X 1 ) , flow rate ( X 2 ) , and desorption ratio ( X 3 ) were used as input variables (factor), and the TDS removal rate   ( Y 1 ) and production quantity   ( Y 2 ) were designed as output variables (response) using a commercial software (Design-Expert 12.0). Table 3 summarizes the factors and responses used in the RSM.
The conversion formula for TDS is given by Equation (1) [59]:
TDS ( mg / L ) = k × E C
where k is a correction coefficient and EC (µS/cm) is an electrical conductivity.
The formula of rejection (%) is given by Equation (2):
R ( % ) = C 0 C C 0 × 100  
where C 0 is the initial concentration of the feed water, and C is the concentration of product water.
The production quantity (mL) of formula is given by Equation (3):
Q ( m L ) = V × t A D × T C  
where V is the flow rate (mL/min), t A D is the time of the adsorption time, and T C is the total cycle. The standard for 1 cycle was set as the sum of adsorption and desorption times, and the criterion of TC was 24 h.
The energy consumption (kWh/m3) of formula is given by Equation (4) [60]:
E = Δ t t A D I V d t η Σ Δ t t D E I V d t Δ t t A D Q d t
where I V is the current–voltage product (kW), η is the fraction of energy actually recovered and reused to power another charging phase, t A D is the time of the adsorption time (h), t D E is the time of the desorption time (h), and Q is the flow rate of the product water (m3/h).
Figure 3 shows a flow chart of the RSM for the optimization of the operating conditions for the CDI process. First, the objective of the optimization was clarified. The key variables, including factors (inputs) and responses (outputs), were then identified. The experimental design was then performed to determine the details of the experiments based on the central composite design (CCD) method. Using this experimental matrix, a series of experiments were conducted and the results were analyzed using the RSM regression method. In addition, ANOVA (analysis of variance) of the results was also performed to validate the regression models. When the ANOVA test failed, the experimental design was modified and the other steps were repeated. Otherwise, the regression model was considered valid. Using the regression model, optimal conditions were explored through both graphical and point optimization.
The R2 value for the regression models obtained from RSM trials was calculated using the Design-Expert software. The models were also validated using ANOVA. The larger the value of F and the smaller the value of p, the more significant the corresponding coefficient term [56]. The value of p was lower than 0.05, indicating that the model may be considered to be statistically significant [57].

2.2.2. Field Emission Scanning Electron Microscopy (FE-SEM) and Energy Dispersive X-ray Spectrometer (EDS) Analysis

The foulants on the membrane surfaces, spacers, and the electrode were examined to provide detailed information on the morphology and composition of the fouling materials [61,62]. A field emission scanning electron microscope (FE-SEM) and an X-ray spectrometer (EDS) (JSM-7160F from JEOL LTD) were applied to each sample. Prior to analysis, the samples were completely dried and coated with platinum for 30–45 s.

2.2.3. X-ray Photoelectron Spectrometer (XPS) Analysis

An X-ray photoelectron spectrometer Escalab250 (XPS) (Thermo Scientific) was used to analyze inorganic compounds, elements, etc. This technique has the advantage of being able to measure the elemental composition as well as the chemical and electronic state of the atoms within a material [63].

2.2.4. Sample Analysis

The pH and conductivity data were collected in real time using a WTW Multi 3620 IDS. An inductively coupled plasma optical emission spectrometer (ICP-OES) (Agilent) and an ion chromatograph 5000+ (Thermo Scientific) were used for cation and anion analysis, respectively. Turbidity was determined using a 2100Q and TOC was analyzed using a Shimadzu TOC analyzer.

3. Results and Discussion

3.1. Effects of Operating Variables

Initially, the effect of voltage, flow rate, and adsorption/desorption ratio on TDS removal in the CDI process was investigated using the one-factor-at-a-time (OFAT) method. The F1 feed water was used for different operating conditions.

3.1.1. Voltage

Figure 4 shows the effect of voltage on TDS removal. The voltage was applied in increments of 0.3 V and ranged from 1.2 V to 1.8 V. The TDS removal was highest at 86.3% at 1.5 V. In general, higher voltage can result in higher TDS removal. However, the TDS removal decreased at 1.8 V because the electrolysis of water occurs above 1.5 V, resulting in a decrease in ion adsorption efficiency.

3.1.2. Flow Rate

The TDS removal at different flow rates is shown in Figure 5. The flow rate conditions were set in increments of 5 mL/min, ranging from 10 mL/min to 20 mL/min. As the flow rate increased, the TDS removal decreased. For example, the highest TDS removal (94.3%) was achieved at the highest flow rate of 20 mL/min. This is due to a decrease in contact time as the flow rate increases.

3.1.3. Ratio of Sorption Time

The ratio of desorption time to adsorption time was adjusted from 1:0.8 to 1.2 in increments of 0.2, and the results are summarized in Figure 6. At the ratio of 1:1, the TDS removal was the highest (86.3%). When the desorption time was shorter than the adsorption time, the TDS removal decreased to 78.7%. This is because the ions adsorbed on the electrode are not sufficiently desorbed. When the desorption time was too long, the TDS removal was also low due to the occurrence of electrode aging, pore structure change, and by-product generation caused by the long desorption time.

3.2. Optimization of Capacitive Deionization in CCP under RSM

Although the OFAT approach is helpful for qualitatively understanding the influence of operating variables, it is inefficient for finding optimal conditions and is unable to reveal interactions among variables. Therefore, RSM was used to further optimize the operating variables for CDI. Table 4 shows the experimental design matrix and results from Design-Expert. Twenty-one experimental conditions were identified and a series of laboratory-scale experiments were conducted. The corresponding values for TDS removal (Response 1) and water production (Response 2) are also shown in Table 4.
The RSM results for the TDS removal and water production are shown in Table 5 and Table 6, respectively. The R2 values for several regression models, using linear, 2FI, quadratic, and cubic models, were compared. The sequential and lack-of-fit p-values were also calculated. The results indicated that the quadratic model was the most suitable for TDS removal   ( Y 1 ) , and the 2FI model was suitable for water production   ( Y 2 ).

3.2.1. TDS Removal

As shown in Table 4, the TDS removal varied from 47% to 91% by changing the voltage, flow rate, and adsorption/desorption ratio. Based on these results, a regression equation was derived as given by Equation (5):
Y 1 = + 84.47 + 12.26 X 1 5.83 X 2 5.93 X 3 + 0.5162 X 1 X 2 + 2.81 X 1 X 3 + 1.37 X 2 X 3 4.96 X 1 2 3.09 X 2 2 4.97 X 3 2
Y 1 : TDS Removal
X 1 : Voltage
X 2 : Flow rate
X 3 : Sorption ratio
According to the ANOVA (analysis of variance) results (Table 7), the model F-value was 28.94 (p-value < 0.0001), which means that the model is significant. In addition, the lack-of-fit F-value was 2.31, so it can be concluded that the lack of fit is not significant. In addition, the coefficient of determination (R2) was 0.9595, which is also sufficiently high. This indicates that the regression equation can be used to predict the TDS removed.
The response surface and contour plots for TDS removal are shown in Figure 7, which allows the visualization of the effect of the input variables. Increasing the voltage increased the TDS removal, while increasing the flow rate decreased the TDS removal. Increasing the sorption ratio also resulted in decreased TDS removal. However, the dependence of TDS removal on these variables is not linear, indicating that there were interactions among the variables.

3.2.2. Water Production

Equation (6) was obtained to predict water production using the data in Table 4:
Y 2 = + 10747.62 + 3843.90 X 2 925.00 X 3 725.00 X 2 X 3
Y 2 : Water Production
X 2 : Flow rate
X 3 : Sorption ratio
According to the results of ANOVA (analysis of variance) (Table 8), the F-value of the model was 248.67 (p-value < 0.0001), which means that the model is significant. The corresponding coefficient of determination R2 was 0.9907. Contrary to the case of TDS removal, the voltage was found to have no effect on water production.
Figure 8 shows the response surface and contour plots for water production. An increase in flow rate resulted in an increase in water production, while an increase in sorption ratio resulted in a slight decrease in water production. As mentioned earlier, the water production was constant regardless of the voltage. As can be seen in the figure, the water production is almost linearly proportional to the flow rate.

3.2.3. Graphical Optimization

There are two criteria to consider for CDI operation in this work. First, the TDS removal should be greater than 80%, which is required for wastewater reclamation. Second, the water production should be greater than 10,000 mL. To explore the conditions to satisfy both criteria at the same time, graphical optimization was carried out as shown in Figure 9. Here, the yellow areas correspond to the conditions for meeting the criteria. On the other hand, the gray areas correspond to conditions where the required criteria were not met. The desired ranges for voltage, flow rate and sorption ratio were then identified. A point optimization was also performed to determine the optimum point. The asterisks (star marks) indicate the proposed optimum conditions, which correspond to the voltage of 1.5 V, the flow rate of 15 mL/min and the sorption ratio of 1:0.8.
It should be noted that there are two major limitations to the RSM approach. The first is that RSM is a “black box” approach that lacks flexibility. If the model needs to be changed to describe something physically slightly different, a lot of work is required to develop a new model. The second limitation is that it is a local analysis. The response surface developed is invalid for regions other than the factor ranges studied. Accordingly, the RSM models developed here are limited to the conditions considered in this study.

3.2.4. Results of Product Water Quality Analysis

The summary of the product water quality from the experiment under the optimum conditions (the voltage of 1.5V, the flow rate of 15 mL/min, and the sorption ratio of 1:0.8) is shown in Table 9. The TDS removal was 86.31%, which is 7.14% higher than the target removal. The water quality standard for industrial water reuse was also met.

3.3. Long-Term Operation of CDI

Although the previous experiments allow the determination of the optimum conditions for TDS removal and water production, they were carried out within a few hours. Therefore, a long-term (up to 10 days) continuous operation of the CDI was performed to study the fouling behavior and to identify the main foulants using the F2.

3.3.1. Reduction in TDS Removal and Energy Consumption

The experiment was conducted on a laboratory scale for a total of 10 days on a 24-h basis. The average TDS removal decreased over time from 93.65% to 55.70% as shown in Figure 10. In addition to the average values, the maximum and minimum TDS removals are shown in Table 10.
Energy consumption was also calculated using equation (4) and the results are summarized in Table 10. Since the amount of water produced by the CDI process is constant (11.625 L/day), the denominator of equation (4) has a constant value regardless of time. On the other hand, the numerator of this equation is almost proportional to the amount of ions removed by the CDI, so it decreased over time due to a decrease in TDS removal. Accordingly, the calculated energy consumption, assuming no energy recovery, decreased from 3.51 kWh/m3 to 1.93 kWh/m3 during the 10-day operation. Assuming 100% energy recovery, it decreased from 0.62 kWh/m3 to 0.18 kWh/m3. This is undesirable because the quality of the product water deteriorated over time. To further investigate these phenomena, a series of analyses were performed on the membrane surface, spacers and electrodes.

3.3.2. Results of SEM–EDS Analysis

SEM–EDS analysis was performed for the electrodes before and after the CDI experiments. Figure 11a shows the SEM images of the electrode before the experiment. The intact electrode was composed of particulate materials with porous structures. After the experiment, the cathode was found to be covered with foulants. This can be seen in Figure 11b. On the other hand, the anode did not have any significant fouling as shown in Figure 11c. The EDS spectra are consistent with the results of the SEM analysis. Compared with the EDS spectrum for the intact electrode (Figure 11d), the EDS spectrum for the used cathode (Figure 11e) shows the peaks for Ca (9.67%), Si (2.92%) and Mg (1.03%). On the contrary, the EDS spectrum for the used anode (Figure 11f) does not show many foreign elements except for small amounts of S (0.06%) and Cl (0.05%). These results suggest that the fouling of the electrode preferentially occurs on the cathode side. Since the cathode adsorbs positively charged ions such as Ca2+ and Mg2+, it can be covered by the deposits formed by these ions and dissolved organic matter [64].
The ion exchange membranes were also examined using the SEM–EDS technique. Before the CDI experiment, the surfaces of the cation exchange membrane (CEM) and anion exchange membrane (AEM) were clean as shown in Figure 12a,b. After the experiment, the surfaces were covered with gel-like and thread-like deposits as shown in Figure 12c,d. The analysis of the deposits by EDS showed that the deposits on the CEM and AEM were different. The intact CEM contained a small amount of S and Na and the intact AEM had a small amount of N and Cl (Figure 12e,f) due to their functional groups [65]. After the experiment, Ca (2.69%), N (2.23%), Mg (0.53%), and Si (0.12%) were mainly found on the used CEM (Figure 12g), while O (21.61%) and S (1.88%) were observed on the used AEM (Figure 12h).
The spacers were also observed by SEM–EDS. As shown in Figure 13a,b, the spacers were blocked by the deposits after the CDI experiment. Based on the morphology, they were assumed to be inorganic scales. The EDS analysis in Figure 13c,d confirmed this. It was found that the deposits in the used spacer contained Ca (4.79%), Mg (10.25%) and silica (1.95%).

3.3.3. Results of XPS Analysis

In addition to EDS, XPS was used to further analyze the compositions of the deposits in the spacer. Figure 14 shows the XPS spectrum of the spacer after the CDI experiment. There were peaks corresponding to Mg 1s, O 1s, N 1s, Ca 2p, C 1s and Si 2p. Among them, the peaks for Mg, Ca, and O were higher than the others. These results are consistent with the previous results of the EDS analysis.

3.4. Cleaning

Previous results have shown that inorganic scale containing Ca and Mg is the main cause of CDI fouling. Since they degrade the treated water quality of CDI and reduce water production, it is necessary to remove them during or after CDI operation. Considering the compositions of the foulants, 1 mM HCl and 1 mM NaOH solutions were used as cleaning agents. The cleaning was performed by applying the acidic and alkaline solutions sequentially when the TDS removal decreased to less than 70%. Figure 15 shows the changes in TDS removal by CDI with time and the effectiveness of cleaning. The average TDS removal was 93.65% on day 1 and decreased to 68.82% on day 7.
The average TDS removal was 93.65% on day 1 and decreased to 68.82% on day 7. One of the reasons for this degradation is the electro-oxidation in electrodes. Due to the operation of the cell at a high voltage of 1.5 V, the anode can be electro-oxidized, leading to a reduction in capacity via a loss of pore structure and changes in surface chemistry. The elemental analysis indicated an increase in oxygen content, which may be associated with the electro-oxidation. Nevertheless, it should be noted that the TDS removal was restored to the initial level of 93.02% after the chemical cleaning. If electro-oxidation occurs, then the changes in the electrode should be irreversible and cannot be reverted by the chemical cleaning. Accordingly, further works will be required to clearly investigate the effect of electro-oxidation on the CDI performance degradation. Moreover, it is also necessary to optimize the cleaning methods for the long-term operation of CDI in future studies.

4. Conclusions

In this study, the CDI process has been proposed for the treatment of wastewater from CCPPs. The effect of operating conditions such as voltage, flow rate, and adsorption/desorption time ratio on the TDS removal in CDI was analyzed using both OFAT and RSM approaches. At the optimum conditions (the voltage of 1.5 V, the flow rate of 15mL/min, and the sorption ratio of 1:0.8), the TDS removal was 86.31%, which meets the requirement for industrial water reuse. However, a long-term CDI test showed a significant decrease in TDS removal from 93.65% to 55.70% over 10 days. To identify the foulants, the anodes, cathodes, CEMs, AEMs, and spacers were analyzed using SEM–EDS and XPS. It was found that fouling did not occur on the anode but on the cathode. Foulants were also observed in the CEMs, AEMs and spacers and they mainly contained Ca, Mg and Si. Accordingly, inorganic foulants, which may be associated with the organic matter, seemed to be responsible for the deterioration of the CDI performance. After the CDI test, chemical cleaning was performed using the acid and alkali solutions, which could recover the TDS removal from 68.82% to 92.03%. This indicates that CDI fouling can be controlled by chemical cleaning.
The significance of this paper lies in the application of the CDI process to the reclamation of CCPP wastewater, which is currently discharged despite its potential for reuse. Accordingly, this paper can contribute to the reduction of water withdrawal in CCPPs by accelerating the adoption of wastewater reclamation by the CDI process. One of the findings in this paper is the occurrence of fouling during the long-term operation of the CDI process, which is attributed to inorganic scale and organic matter. Although a chemical cleaning procedure has been proposed in this study, it has not yet been fully optimized. Therefore, further work will be required to explore the optimal methods and conditions for mitigating CDI fouling. It will also be necessary to develop pre-treatment techniques for this CDI process.

Author Contributions

Conceptualization, Y.K. and S.L.; methodology, Y.K. and J.K.; software, Y.K. and H.C.; validation, Y.K., H.C. and Y.C.; formal analysis, Y.K., H.C. and Y.C.; investigation, Y.K. and J.K.; resources, Y.K. and J.K.; data curation, Y.K., H.C. and Y.C.; writing—original draft preparation, Y.K.; writing—review and editing, S.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the Clean Production-Based Industrial Symbiotic Technology Development Project (R&D) (20017177, Clean Factory Technology Development Project of the Ministry of Trade, Industry and Energy).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Pakzadeh, B. Wastewater Reuse in Combined Cycle Power Plants. February 2018. Available online: https://midwestawma.org/wp-content/uploads/2018/02/2018Conference/2018Day2/WastewaterReuseCCPlants.pdf (accessed on 30 April 2020).
  2. Polyzakis, A.; Koroneos, C.; Xydis, G. Optimum gas turbine cycle for combined cycle power plant. Energy Convers. Manag. 2008, 49, 551–563. [Google Scholar] [CrossRef]
  3. Poullikkas, A. An overview of current and future sustainable gas turbine technologies. Renew. Sustain. Energy Rev. 2005, 9, 409–443. [Google Scholar] [CrossRef]
  4. Wang, J.; Qu, D.; Tie, M.; Ren, H.; Peng, X.; Luan, Z. Effect of Coagulation Pretreatment on Membrane Distillation Process for Desalination of Recirculating Cooling Water. Sep. Purif. Technol. 2008, 64, 108–115. [Google Scholar] [CrossRef]
  5. Koeman-Stein, N.E.; Creusen, R.; Zijlstra, M.; Groot, C.; Broek, W.B. Membrane distillation of industrial cooling tower blowdown water. Water Resour. Ind. 2016, 14, 11–17. [Google Scholar] [CrossRef] [Green Version]
  6. Altman, S.J.; Jensen, R.; Cappelle, M.; Sanchez, A.; Everett, R.; Anderson, H.L.; McGrath, L. Membrane treatment of side-stream cooling tower water for reduction of water usage. Desalination 2012, 285, 177–183. [Google Scholar] [CrossRef]
  7. Han, X.; Zhang, D.; Yan, J.; Zhao, S.; Liu, J. Process development of flue gas desulphurization wastewater treatment in coal-fired power plants towards zero liquid discharge: Energetic, economic and environmental analyses. J. Clean. Prod. 2020, 261, 121144. [Google Scholar] [CrossRef]
  8. Clark, K. Wastewater Treatment Issues for Combined Cycly Plants. Power Engineering. 14 April 2014. Available online: https://www.power-eng.com/emissions/policy-regulations/wastewater-treatment-issues-for-combined-cycle-plants/#gref (accessed on 30 April 2020).
  9. Tong, T.; Elimelech, M. The global rise of zero liquid discharge for wastewater management: Drivers, technologies, and future directions. Environ. Sci. Technol. 2016, 50, 6846–6855. [Google Scholar] [CrossRef]
  10. Panagopoulos, A.; Haralambous, K.-J. Minimal Liquid Discharge (MLD) and Zero Liquid Discharge (ZLD) strategies for wastewater management and resource recovery—Analysis, challenges and prospects. J. Environ. Chem. Eng. 2020, 8, 104418. [Google Scholar] [CrossRef]
  11. Yaqub, M.; Lee, W. Zero-liquid discharge (ZLD) technology for resource recovery from wastewater: A review. Sci. Total Environ. 2019, 681, 551–563. [Google Scholar] [CrossRef]
  12. Choi, Y.-I.; Jung, J.-H.; Jung, B.-G. Application Study of BIRM-UF-RO System for Industrial Water Reuse in Wastewater Treatment Plant. J. Korean Soc. Environ. Technol. 2020, 21, 196–204. [Google Scholar] [CrossRef]
  13. Park, Y.-M.; Park, C.-H. Evaluation of Pressured UF Membrane in UF/RO Process for Wastewater Reuse. J. Korean Soc. Urban Environ. 2019, 19, 65–75. [Google Scholar] [CrossRef]
  14. Bae, J.-H.; Park, H.-S.; Kyung, D. A Study on the Method and Verification of Wastewater Treatment and Reuse Water Production in a Power Plant. J. Korea Acad. Ind. Coop. Soc. 2022, 23, 325–333. [Google Scholar]
  15. Oren, Y. Capacitive deionization (CDI) for desalination and water treatment—Past, present and future. A review. Desalination 2008, 228, 10–29. [Google Scholar] [CrossRef]
  16. Tsai, J.-H.; Macedonio, F.; Drioli, E.; Girono, L.; Chou, C.Y.; Hu, F.C.; Tung, K.L. Membrane-based zero liquid discharge: Myth or reality? J. Taiwan Inst. Chem. Eng. 2017, 80, 192–202. [Google Scholar] [CrossRef]
  17. Oren, Y.; Korngold, E.; Daltrophe, N.; Messalem, R.; Volkman, Y.; Aronov, L. Pilot studies on high recovery BWRO-EDR for near zero liquid discharge approach. Desalination 2010, 261, 321–330. [Google Scholar] [CrossRef]
  18. Xu, Y.; Sun, Y.; Ma, Z.; Wang, R.; Wang, J.; Wang, L.; Gao, X.; Gao, J. Response surface modeling and optimization of electrodialysis for reclamation of RO concentrates in coal-fired power plants. Sep. Sci. Technol. 2020, 55, 2593–2603. [Google Scholar] [CrossRef]
  19. Loganathan, K.; Chelme-Ayala, P.; El-Din, M. Treatment of basal water using a hybrid electrodialysis reversal—Reverse osmosis system combined with a low-temperature crystallizer for near-zero liquid discharge. Desalination 2015, 363, 92–98. [Google Scholar] [CrossRef]
  20. Bond, R.; Batchelor, B.; Davis, T.; Klayman, B. Zero liquid discharge desalination of brackish water with an innovative form of electrodialysis: Electrodialysis metathesis. Fla. Water Resour. J. 2011, 7, 63. [Google Scholar]
  21. Anderson, M.A.; Cudero, A.; Palma, J. Capacitive deionization as an electrochemical means of saving energy and delivering clean water. Comparison to present desalination practices: Will it compete? Electrochim. Acta 2010, 55, 3845–3856. [Google Scholar] [CrossRef]
  22. Liu, E.; Lee, L.Y.; Ong, S.; Ng, H.Y. Treatment of industrial brine using Capacitive Deionization (CDI) towards zero liquid discharge—Challenges and optimization. Water Res. 2020, 183, 116059. [Google Scholar] [CrossRef]
  23. Gamaethiralalage, J.; Singh, K.; Sahin, S.; Yoon, J.; Elimelech, M.; Suss, M.E.; De Smet, L.C.P.M. Recent advances in ion selectivity with capacitive deionization. Energy Environ. Sci. 2021, 14, 1095–1120. [Google Scholar] [CrossRef]
  24. Guyes, E.N.; Shocron, A.N.; Chen, Y.; Diesendruck, C.E.; Suss, M.E. Long-lasting, monovalent-selective capacitive deionization electrodes. Npj Clean Water 2021, 4, 22. [Google Scholar] [CrossRef]
  25. Luong, V.T.; Kurtz, E.E.C.; Hellriegel, U.; Dinh, D.N.; Tran, H.; Figoli, A.; Bartolo, G.; Tran, L.; Hoinkis, J. Modular desalination concept with low-pressure reverse osmosis and capacitive deionization: Performance study of a pilot plant in Vietnam in comparison to seawater reverse osmosis. J. Environ. Manag. 2022, 329, 117078. [Google Scholar] [CrossRef]
  26. Pan, S.Y.; Haddad, A.Z.; Kumar, A.; Wang, S.-W. Brackish water desalination using reverse osmosis and capacitive deionization at the water-energy nexus. Water Res. 2020, 183, 116064. [Google Scholar] [CrossRef]
  27. Lee, L.Y.; Yoke, L.; Ng, H.Y.; Ong, S.L.; Tao, G.; Kekre, K.; Viswanath, B.; Lay, W.; Seah, H. Integrated pretreatment with capacitive deionization for reverse osmosis reject recovery from water reclamation plant. Water Res. 2009, 43, 4769–4777. [Google Scholar] [CrossRef]
  28. Choi, J.; Dorji, P.; Shon, H.K.; Hong, S. Applications of capacitive deionization: Desalination, softening, selective removal, and energy efficiency. Desalination 2019, 449, 118–130. [Google Scholar] [CrossRef]
  29. Rusydi, A.F. Correlation between Conductivity and Total Dissolved Solid in Various Type of Water: A Review. In IOP Conference Series: Earth and Environmental Science; IOP Publishing: Bristol, UK, 2018. [Google Scholar]
  30. Huyskens, C.; Helsen, J.; De Haan, A. Capacitive deionization for water treatment: Screening of key performance parameters and comparison of performance for different ions. Desalination 2013, 328, 8–16. [Google Scholar] [CrossRef]
  31. Luciano, M.A.; Ribeiro, H.; Bruch, G.E.; Silva, G.G. Efficiency of capacitive deionization using carbon materials based electrodes for water desalination. J. Electroanal. Chem. 2020, 859, 113840. [Google Scholar] [CrossRef]
  32. Tang, W.; Kovalsky, P.; Cao, B.; Waite, T.D. Investigation of fluoride removal from low-salinity groundwater by single-pass constant-voltage capacitive deionization. Water Res. 2016, 99, 112–121. [Google Scholar] [CrossRef]
  33. Zhao, X.; Wei, H.; Zhao, H.; Wang, Y.; Tang, N. Electrode materials for capacitive deionization: A review. J. Electroanal. Chem. 2020, 873, 114416. [Google Scholar] [CrossRef]
  34. Uwayid, R.; Seraphim, N.M.; Guyes, E.N.; Eisenberg, D.; Suss, M.E. Characterizing and mitigating the degradation of oxidized cathodes during capacitive deionization cycling. Carbon 2021, 173, 1105–1114. [Google Scholar] [CrossRef]
  35. Algurainy, Y.; Call, D.F. Improving long-term anode stability in capacitive deionization using asymmetric electrode mass ratios. ACS EST Eng. 2021, 2, 129–139. [Google Scholar] [CrossRef]
  36. Chai, S.; Xi, J.; Chen, L.; He, W.; Shen, J.; Gong, H. Selective Ion Removal by Capacitive Deionization (CDI)-Based Technologies. Processes 2022, 10, 1075. [Google Scholar] [CrossRef]
  37. Nguyen, T.V.T.; Huynh, N.T.; Vu, N.C.; Kieu, V.N.; Huang, S.C. Optimizing compliant gripper mechanism design by employing an effective bi-algorithm: Fuzzy logic and ANFIS. Microsyst. Technol. 2021, 27, 3389–3412. [Google Scholar] [CrossRef]
  38. Wang, R.; Yu, Y.; Chen, Y.; Pan, Z.; Li, X.; Tan, Z.; Zhang, J. Model construction and application for effluent prediction in wastewater treatment plant: Data processing method optimization and process parameters integration. J. Environ. Manag. 2022, 302, 114020. [Google Scholar] [CrossRef]
  39. Niu, G.; Li, X.; He, X.; Zhao, Y.; Yi, X.; Chen, C.; Xujun, L.; Ying, G.; Huang, M. Dynamic optimization of wastewater treatment process based on novel multi-objective ant lion optimization and deep learning algorithm. J. Clean. Prod. 2022, 345, 131140. [Google Scholar] [CrossRef]
  40. Hakanen, J.; Miettinen, K.; Sahlstedt, K. Wastewater treatment: New insight provided by interactive multiobjective optimization. Decis. Support Syst. 2011, 51, 328–337. [Google Scholar] [CrossRef]
  41. Yao, J.; Mei, Y.; Jiang, J.; Xia, G.; Chen, J. Process optimization of electrochemical treatment of COD and total nitrogen containing wastewater. Int. J. Environ. Res. Public Health 2022, 19, 850. [Google Scholar] [CrossRef]
  42. Wang, C.-N.; Yang, F.-C.; Nguyen, V.T.T.; Nguyen, Q.M.; Huynh, N.T.; Huynh, T.T. Optimal Design for Compliant Mechanism Flexure Hinges: Bridge-Type. Micromachines 2021, 12, 1304. [Google Scholar] [CrossRef]
  43. Wang, C.-N.; Yang, F.-C.; Nguyen, V.T.T.; Vo, N.T.M. CFD Analysis and Optimum Design for a Centrifugal Pump Using an Effectively Artificial Intelligent Algorithm. Micromachines 2022, 13, 1208. [Google Scholar] [CrossRef]
  44. Khuri, A.I.; Mukhopadhyay, S. Response surface methodology. Wiley Interdiscip. Rev. Comput. Stat. 2010, 2, 128–149. [Google Scholar] [CrossRef]
  45. Bashir, M.J.; Amr, S.A.; Aziz, S.Q.; Ng, C.A. Wastewater treatment processes optimization using response surface methodology (RSM) compared with conventional methods: Review and comparative study. Middle-East J. Sci. Res. 2015, 23, 244–252. [Google Scholar]
  46. Ahmed, M.; Giwa, A.; Hasan, S. Chapter 26—Challenges and Opportunities of Graphene-Based Materials in Current Desalination and Water Purification Technologies. In Nanoscale Materials in Water Purification; Thomas, S., Ed.; Elsevier: Geneva, Switzerland, 2019; pp. 735–758. [Google Scholar]
  47. Gupta, S.S.; Islam, M.; Pradeep, T. Chapter 7—Capacitive Deionization (CDI): An Alternative Cost-Efficient Desalination Technique. In Advances in Water Purification Techniques; Ahuja, S., Ed.; Elsevier: Geneva, Switzerland, 2019; pp. 165–202. [Google Scholar]
  48. Khan, Q.; Maraqa, M.; Mohamed, A.-M. Chapter 17—Inland desalination: Techniques, brine management, and environmental concerns. In Pollution Assessment for Sustainable Practices in Applied Sciences and Engineering; Mohamed, A.-M.O., Paleologos, E.K., Howari, F.M., Eds.; Butterworth-Heinemann: Oxford, UK, 2021; pp. 871–918. [Google Scholar]
  49. Rabiee, H.; Khalilpour, K.R.; Betts, J.M.; Tapper, N. Chapter 13—Energy-Water Nexus: Renewable-Integrated Hybridized Desalination Systems. In Polygeneration with Polystorage for Chemical and Energy Hubs; Khalilpour, K.R., Ed.; Academic Press: Cambridge, MA, USA, 2019; pp. 409–458. [Google Scholar]
  50. Sillanpää, M.; Shestakova, M. Chapter 3—Emerging and Combined Electrochemical Methods. In Electrochemical Water Treatment Methods; Sillanpää, M., Shestakova, M., Eds.; Butterworth-Heinemann: Oxford, UK, 2017; pp. 131–225. [Google Scholar]
  51. Porada, S.; Zhao, R.; Wal, A.; Presser, V.; Biesheuvel, P.M. Review on the science and technology of water desalination by capacitive deionization. Prog. Mater. Sci. 2013, 58, 1388–1442. [Google Scholar] [CrossRef] [Green Version]
  52. Woo, Y.C.; Kim, S.H.; Shon, H.K.; Tijing, L.D. Introduction: Membrane Desalination Today, Past, and Future. In Current Trends and Future Developments on (Bio-) Membranes; Basile, A., Inamuddin Curcio, E., Eds.; Elsevier: Geneva, Switzerland, 2019; pp. xxv–xlvi. [Google Scholar]
  53. Zhao, R.; Biesheuvel, P.M.; Miedema, H.; Bruning, H.; Wal, A. Charge efficiency: A functional tool to probe the double-layer structure inside of porous electrodes and application in the modeling of capacitive deionization. J. Phys. Chem. Lett. 2010, 1, 205–210. [Google Scholar] [CrossRef]
  54. Biesheuvel, P.; Van der Wal, A. Membrane capacitive deionization. J. Membr. Sci. 2010, 346, 256–262. [Google Scholar] [CrossRef]
  55. Lee, J.-B.; Park, K.-K.; Eum, H.-M.; Lee, C.-W. Desalination of a thermal power plant wastewater by membrane capacitive deionization. Desalination 2006, 196, 125–134. [Google Scholar] [CrossRef]
  56. Ahmadi, M.; Vahabzadeh, F.; Bonakdarpour, B.; Mofarrah, E.; Mehranian, M. Application of the central composite design and response surface methodology to the advanced treatment of olive oil processing wastewater using Fenton’s peroxidation. J. Hazard. Mater. 2005, 123, 187–195. [Google Scholar] [CrossRef]
  57. Asadi, N.; Zilouei, H. Optimization of organosolv pretreatment of rice straw for enhanced biohydrogen production using Enterobacter aerogenes. Bioresour. Technol. 2017, 227, 335–344. [Google Scholar] [CrossRef]
  58. Wikipedia, Central Composite Design. Available online: https://en.wikipedia.org/wiki/Central_composite_design (accessed on 30 April 2020).
  59. Hassanvand, A.; Chen, G.Q.; Webley, P.A.; Kentish, S.E. An investigation of the impact of fouling agents in capacitive and membrane capacitive deionisation. Desalination 2019, 457, 96–102. [Google Scholar] [CrossRef]
  60. Hawks, S.A.; Ramachandra, A.; Porada, S.; Campbell, P.G.; Suss, M.E.; Biesheuvel, P.M.; Santiago, J.G.; Stadermann, M. Performance metrics for the objective assessment of capacitive deionization systems. Water Res. 2019, 152, 126–137. [Google Scholar] [CrossRef]
  61. Falsafi, S.R.; Rostamabadi, H.; Assadpour, E.; Jafari, S.D. Morphology and microstructural analysis of bioactive-loaded micro/nanocarriers via microscopy techniques; CLSM/SEM/TEM/AFM. Adv. Colloid Interface Sci. 2020, 280, 102166. [Google Scholar] [CrossRef]
  62. Kleiner, F.; Robler, C.; Vogt, F.; Osburg, A.; Ludwig, H.M. Reconstruction of calcium silicate hydrates using multiple 2D and 3D imaging techniques: Light microscopy, mu-CT, SEM, FIB-nT combined with EDX. J. Microsc. 2022, 286, 102–107. [Google Scholar] [CrossRef]
  63. Liu, J.; Liu, M.; Chen, S.; Wang, B.; Chen, J.; Yang, D.P.; Zhang, S.; Du, W. Conversion of Au (III)-polluted waste eggshell into functional CaO/Au nanocatalyst for biodiesel production. Green Energy Environ. 2022, 7, 352–359. [Google Scholar] [CrossRef]
  64. Xu, P.; Drewes, J.; Heil, D.; Wang, G. Treatment of brackish produced water using carbon aerogel-based capacitive deionization technology. Water Res. 2008, 42, 2605–2617. [Google Scholar] [CrossRef]
  65. Xu, T. Ion exchange membranes: State of their development and perspective. J. Membr. Sci. 2005, 263, 1–29. [Google Scholar] [CrossRef]
Figure 1. Principle of (a) capacitive deionization (CDI); (b) membrane capacitive deionization (MCDI).
Figure 1. Principle of (a) capacitive deionization (CDI); (b) membrane capacitive deionization (MCDI).
Membranes 13 00316 g001
Figure 2. (a) Configuration of the lab-scale MCDI module unit cell; (b) schematic diagram of the lab-scale experimental setup for CDI process.
Figure 2. (a) Configuration of the lab-scale MCDI module unit cell; (b) schematic diagram of the lab-scale experimental setup for CDI process.
Membranes 13 00316 g002
Figure 3. Flow chart for the RSM-based optimization.
Figure 3. Flow chart for the RSM-based optimization.
Membranes 13 00316 g003
Figure 4. The results of the applied voltage of the CDI: (a) Voltage was set in 0.3 V increments from 1.2 V to 1.8 V; (b) The TDS removal rate was the highest at 86.3% at 1.5 V.
Figure 4. The results of the applied voltage of the CDI: (a) Voltage was set in 0.3 V increments from 1.2 V to 1.8 V; (b) The TDS removal rate was the highest at 86.3% at 1.5 V.
Membranes 13 00316 g004
Figure 5. The results of the flow rate of the CDI: (a) Flow rate was set in 5 mL/min increments from 10 mL/min to 20 mL/min; (b) The TDS removal rate was the highest at 94.3% at 10 mL/min.
Figure 5. The results of the flow rate of the CDI: (a) Flow rate was set in 5 mL/min increments from 10 mL/min to 20 mL/min; (b) The TDS removal rate was the highest at 94.3% at 10 mL/min.
Membranes 13 00316 g005
Figure 6. The results of the sorption ratio (adsorption/desorption) of the CDI: (a) Sorption ratio was set at 1:0.8, 1:1 and 1:1.2; (b) The TDS removal rate was the highest at 86.3% at 1:1.
Figure 6. The results of the sorption ratio (adsorption/desorption) of the CDI: (a) Sorption ratio was set at 1:0.8, 1:1 and 1:1.2; (b) The TDS removal rate was the highest at 86.3% at 1:1.
Membranes 13 00316 g006
Figure 7. 3D response surface plots showing the effects of the three main factors on TDS removal using the CDI: (a) voltage and flow rate; (b) flow rate and sorption ratio; (c) voltage and sorption ratio.
Figure 7. 3D response surface plots showing the effects of the three main factors on TDS removal using the CDI: (a) voltage and flow rate; (b) flow rate and sorption ratio; (c) voltage and sorption ratio.
Membranes 13 00316 g007
Figure 8. 3D response surface plots showing the effects of the three main factors on water production using the CDI: (a) voltage and flow rate; (b) flow rate and sorption ratio; (c) voltage and sorption ratio.
Figure 8. 3D response surface plots showing the effects of the three main factors on water production using the CDI: (a) voltage and flow rate; (b) flow rate and sorption ratio; (c) voltage and sorption ratio.
Membranes 13 00316 g008
Figure 9. Contour overlay plots showing the graphical optimization of the CDI (yellow area: conditions for meeting the water reuse criteria, grey area: conditions failing to meet the criteria, star marks (asterisks): proposed optimum conditions). (a) TDS removal vs. voltage and flow rate; (b) TDS removal vs. voltage and sorption ratio; (c) TDS removal vs. flow rate and sorption ratio.
Figure 9. Contour overlay plots showing the graphical optimization of the CDI (yellow area: conditions for meeting the water reuse criteria, grey area: conditions failing to meet the criteria, star marks (asterisks): proposed optimum conditions). (a) TDS removal vs. voltage and flow rate; (b) TDS removal vs. voltage and sorption ratio; (c) TDS removal vs. flow rate and sorption ratio.
Membranes 13 00316 g009
Figure 10. The variation of TDS removal rate over 10 days of 24 h per day operation. The average TDS removal rate was 93.65% on Day 1 and gradually fell to 55.70% on Day 10.
Figure 10. The variation of TDS removal rate over 10 days of 24 h per day operation. The average TDS removal rate was 93.65% on Day 1 and gradually fell to 55.70% on Day 10.
Membranes 13 00316 g010
Figure 11. FE-SEM images and EDS spectrum of electrodes surface before and after use: (a) virgin electrodes for different times; (b) cathode fouled by Ca, Si, and Mg; (c) anode fouled by S and Cl at 2000 times, respectively; (df) show the EDS spectra of (ac), respectively.
Figure 11. FE-SEM images and EDS spectrum of electrodes surface before and after use: (a) virgin electrodes for different times; (b) cathode fouled by Ca, Si, and Mg; (c) anode fouled by S and Cl at 2000 times, respectively; (df) show the EDS spectra of (ac), respectively.
Membranes 13 00316 g011
Figure 12. FE-SEM images and EDS spectrum of the ion exchange membrane surface before and after use: (a) and (b) virgin cation and anion exchange membrane; (c) CEM fouled by Ca, N, Mg, Si and S; (d) AEM fouled by S at 500 times, respectively; (eh) show the EDS spectra of (ad), respectively.
Figure 12. FE-SEM images and EDS spectrum of the ion exchange membrane surface before and after use: (a) and (b) virgin cation and anion exchange membrane; (c) CEM fouled by Ca, N, Mg, Si and S; (d) AEM fouled by S at 500 times, respectively; (eh) show the EDS spectra of (ad), respectively.
Membranes 13 00316 g012
Figure 13. FE-SEM images and EDS spectrum of the spacer surface before and after use: (a) virgin spacer; (b) spacer fouled by Ca, Mg and Si at 40 times, respectively; (c,d) show the EDS spectra of (a,b), respectively.
Figure 13. FE-SEM images and EDS spectrum of the spacer surface before and after use: (a) virgin spacer; (b) spacer fouled by Ca, Mg and Si at 40 times, respectively; (c,d) show the EDS spectra of (a,b), respectively.
Membranes 13 00316 g013
Figure 14. The XPS spectra of the deposits in the spacer.
Figure 14. The XPS spectra of the deposits in the spacer.
Membranes 13 00316 g014
Figure 15. The variation of TDS removal rate over 7 days of 24 h per day operation and after cleaning at 8 days; The average TDS removal rate was 93.65% on day 1 and gradually fell to 68.82% on day 7. After cleaning processes, the TDS removal rate recovered to the initial level of 93.02%.
Figure 15. The variation of TDS removal rate over 7 days of 24 h per day operation and after cleaning at 8 days; The average TDS removal rate was 93.65% on day 1 and gradually fell to 68.82% on day 7. After cleaning processes, the TDS removal rate recovered to the initial level of 93.02%.
Membranes 13 00316 g015
Table 1. Summary of MCDI module specification.
Table 1. Summary of MCDI module specification.
MaterialStandardCapacity
ElectrodeActivated Carbon, GraphiteW100 × L100 × T0.6 mm316 mg/g or more
CEMPolyethyleneW100 × L100 × T0.015 mm31.6 meq/g or more
(Sheet resistance:
0.5 Ω cm2 or under)
AEMPolyethyleneW100 × L100 × T0.015 mm31.7 meq/g or more
(Sheet resistance:
0.3 Ω cm2 or under)
SpacerPolyethylene
terephthalate
W110 × L110 × T0.01 mm3-
Table 2. The water quality of the wastewater and standards of industrial discharge limits.
Table 2. The water quality of the wastewater and standards of industrial discharge limits.
ItemsUnitFeed ConditionsStandard to
Discharge
Target to
Removal Rate (%)
F1F2F1F2
pH-8.297.36~8--
ConductivityμS/cm24021055<500:reuse79.1752.61
TOCmg/L3.28.7<25--
Clmg/L145123< 795.1794.31
Alkalinity (as CaCO3)mg/L10577<1090.4887.01
Hardness (as CaCO3)mg/L267285<1096.2596.49
Turbidity NTU0.120.94<2--
Femg/L0.0170.601<0.05-91.68
NH4+mg/L0.030.1 < 0.03 -70.00
SO42−mg/L8574 < 8 90.5989.19
Table 3. Factors and responses used in RSM.
Table 3. Factors and responses used in RSM.
NameUnitsTypeValues
VoltageVFactor1.2, 1.5, 1.8
Flow ratemL/minFactor10, 15, 20
Sorption ratio (ad:de)-Factor1.0:0.8, 1.0:1.0, 1.0:1.2
TDS Removal rate%Response
Water ProductionmLResponse
Table 4. Arrangement of response surface design.
Table 4. Arrangement of response surface design.
StdRunFactor 1Factor 2Factor 3Response 1Response 2
X1: Voltage
(V)
X2: Flow Rate
(mL/min)
X3: Sorption
Ratio
Y1: TDS
Removal
(%)
Y2: Water
Production
(mL)
311.2200.857.4716,000
1221.515188.9110,800
1131.515185.2410,800
941.515184.7810,800
1051.515186.3110,800
561.2101.256.176550
671.8101.289.416550
1381.515185.4410,800
891.8201.279.0413,100
7101.2201.249.8713,100
4111.8200.881.5316,000
2121.8100.891.236550
1131.2100.875.376550
19141.2151.447.609000
17151.523164.8316,560
20161.515180.1910,800
21171.515180.4410,800
1418115149.9910,800
18191.5150.679.4713,500
1520215188.3210,800
16211.57184.955040
Table 5. Summary of quadratic model on the response   ( Y 1 ) : TDS removal.
Table 5. Summary of quadratic model on the response   ( Y 1 ) : TDS removal.
SourceSequential
p-Value
Lack of Fit
p-Value
Adjusted
R2
Predicted
R2
Linear<0.00010.00420.66060.5631
2FI0.80760.00240.61470.4262
Quadratic<0.00010.16860.92630.7414Suggested
Cubic0.19820.19030.9461−0.1471
Table 6. Summary of 2FI model on the response   ( Y 2 ) : water production.
Table 6. Summary of 2FI model on the response   ( Y 2 ) : water production.
SourceSequential
p-value
Lack of Fit
p-value
Adjusted
R2
Predicted
R2
Linear<0.0001 0.96590.9465
2FI0.0009 0.98670.9604Suggested
Quadratic0.4543 0.98650.9397
Cubic0.0406 0.99410.5363
Table 7. ANOVA for the response surface quadratic model.
Table 7. ANOVA for the response surface quadratic model.
SourceSum of SquaresdfMean SquareF-Valuep-Value
Model4107.279456.3628.94<0.0001Significant
X 1 : Voltage2038.0512038.05129.26<0.0001
X 2 : Flow rate445.611445.6128.260.0002
X 3 : Sorption ratio562.281562.2835.66<0.0001
X 1 X 2 2.1312.130.13520.7201
X 1 X 3 63.23163.234.010.0705
X 2 X 3 14.93114.930.94710.3514
X 1 2 356.011356.0122.580.0006
X 2 2 121.931121.937.730.0179
X 3 2 669.141669.1442.44<0.0001
Residual173.441115.77
Lack of fit114.15522.832.310.1686Not significant
Pure Error59.2969.88
Cor Total4280.7120
Table 8. ANOVA for the response surface 2FI model.
Table 8. ANOVA for the response surface 2FI model.
SourceSum of SquaresdfMean SquareF-Valuep-Value
Model2.118 × 10863.529 × 107248.67<0.0001Significant
X 1 : Voltage0.000010.00000.00001.0000
X 2 : Flow rate1.939 × 10811.939 × 1081365.94<0.0001
X 3 : Sorption ratio1.369 × 10711.369 × 10796.46<0.0001
X 1 X 2 0.000010.00000.00001.0000
X 1 X 3 0.000010.00000.00001.0000
X 2 X 3 4.205 × 10614.205 × 10629.63<0.0001
Residual1.987 × 106141.419 × 105
Lack of fit1.987 × 10682.484 × 105
Pure Error0.000060.0000
Cor Total2.137 × 10820
Table 9. Summary of the product water quality and standards of industrial discharge limits using feed solution F1.
Table 9. Summary of the product water quality and standards of industrial discharge limits using feed solution F1.
ItemsUnitFeed ConditionsStandard to
Discharge
Product Water Quality of CDI
F1
pH-8.296~87.1
ConductivityμS/cm2402<500:reuse329
TOCmg/L3.2<251.5
Clmg/L145<713.8 (±1)
Alkalinity (as CaCO3)mg/L105<107 (±1)
Hardness (as CaCO3)mg/L267<1037 (±1)
Turbidity NTU 0.12<20.23 (±1)
Femg/L0.017<0.050.019 (±0.005)
NH4+mg/L0.03<0.030.01 (±0.005)
SO42−mg/L85<87.7 (±1)
Table 10. Variations of TDS removal and energy consumption with time.
Table 10. Variations of TDS removal and energy consumption with time.
Time (day)Removal (%)Energy Consumption (kWh/m3)
AverageMaximumMinimumNo Energy Recovery (η = 0)100% Energy Recovery (η = 1)
193.6597.2788.643.510.62
292.7295.7388.273.380.46
386.7791.4582.153.130.37
481.2783.7378.912.880.31
576.4480.8272.642.680.27
672.2075.8268.362.550.27
768.8273.3665.362.410.25
864.4168.7361.182.280.23
959.6668.1857.002.090.20
1055.7059.4553.181.930.18
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Kim, Y.; Cho, H.; Choi, Y.; Koo, J.; Lee, S. Optimization and Evaluation for the Capacitive Deionization Process of Wastewater Reuse in Combined Cycle Power Plants. Membranes 2023, 13, 316. https://doi.org/10.3390/membranes13030316

AMA Style

Kim Y, Cho H, Choi Y, Koo J, Lee S. Optimization and Evaluation for the Capacitive Deionization Process of Wastewater Reuse in Combined Cycle Power Plants. Membranes. 2023; 13(3):316. https://doi.org/10.3390/membranes13030316

Chicago/Turabian Style

Kim, Yesol, Hyeongrak Cho, Yongjun Choi, Jaewuk Koo, and Sangho Lee. 2023. "Optimization and Evaluation for the Capacitive Deionization Process of Wastewater Reuse in Combined Cycle Power Plants" Membranes 13, no. 3: 316. https://doi.org/10.3390/membranes13030316

APA Style

Kim, Y., Cho, H., Choi, Y., Koo, J., & Lee, S. (2023). Optimization and Evaluation for the Capacitive Deionization Process of Wastewater Reuse in Combined Cycle Power Plants. Membranes, 13(3), 316. https://doi.org/10.3390/membranes13030316

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop