You are currently viewing a new version of our website. To view the old version click .
Applied Sciences
  • Article
  • Open Access

11 April 2022

Maximum Safe Parameters of Outbound Loaded Vessels for Wind Turbine Installation

,
,
and
Faculty of Navigation, Maritime University of Szczecin, 70-500 Szczecin, Poland
*
Author to whom correspondence should be addressed.
This article belongs to the Special Issue Maritime Transportation System and Traffic Engineering

Abstract

A paper presents problems related to the safe operation of wind turbine installation vessels in port waterways. It presents a developed method for determining maximum safe lengths of blades of wind turbines loaded transversely on a jack-up vessel leaving a given port. In this method, the safety criterion for navigation is the acceptable risk of accidents, whose scenarios are determined by the identification of hazards in the studied waterway. Based on this safety criterion, the confidence level of the width of the safe maneuvering area of the loaded jack-up vessel and the maximum safe lengths of the transversely loaded wind turbine blades, respectively, are determined.

1. Introduction

The observed increase in the capacity of offshore wind turbines (OWT) designed and installed worldwide determines the construction of vessels for their installation. The following types of vessels are used for the construction of wind turbines:
  • Foundation transport and installation vessels (FTIV);
  • Wind turbine transport vessels (WTTV) to transport offshore wind turbine components;
  • Wind turbine installation vessels (WTIV).
This paper will present problems related to the safe operation of WTIV jack-up vessels in port waterways. Taking into account the criterion of the jack-up vessel navigation safety, the attachment and transport of the cargo transverse to the ship axis should be taken into account, where one of the most important parameters determining the length of the wind turbine wing panel (half of the rotor diameter minus half of the hub diameter) is the surface width of the available navigation area. If a vessel passes through a waterway with a deck load extending beyond the outline of the vessel’s sides, there is a possibility of the vessel (deck load) striking a hydrotechnical structure or moored vessel. The length of the transversely loaded wind turbine blades on jack-up vessels determines the safety of the departure of these vessels from the ports.
Designing terminals to handle WTIV vessels with wind turbine blades loaded across them involves the need to ensure safe passage of these vessels through the waterway system leading to these terminals.
The paper will present an elaborated method for determining maximum safe lengths of wing blades of wind turbines loaded transversely on a jack-up vessel leaving a given port. In this method, the safety criterion for navigation is the risk of acceptable accidents, whose scenarios are determined by the identification of hazards in the studied waterway. Based on this safety criterion, the confidence level of the width of the safe maneuvering area of the loaded jack-up vessel and the maximum safe lengths of the transversely loaded wind turbine blades, respectively, are determined.

4. A Method for Determining Maximum Safe Blade Lengths of Wind Turbines Loaded across a Jack-Up Vessel in Port Waterways

Contingency scenarios (accident types) are specified for maneuvers performed by ships of a given type and size based on hazard analysis and accident statistics in specific bodies of water. The emergency scenarios do not take into account navigational mistakes made by humans, which are classified as gross errors. Instead, they take into account accidental and systematic errors of all types of navigational measurements and assessments and maneuvering inaccuracies committed by a navigator with specific qualifications while maneuvering the vessel [].
Assuming that wind turbine blades can be loaded across a jack-up vessel symmetrically or asymmetrically to either starboard or port side depending on the turbine installations being performed, contingency scenarios need to be determined depending on the infrastructure and operating conditions of the waterway section.
Contingency scenarios resulting from a loaded jack-up vessel crossing an available shipping area include the following accidents:
  • Striking a moored vessel or hydro-engineering structure with the blade tip;
  • Striking a moored vessel or hydro-engineering structure with the side of a jack-up vessel;
  • Grounding of the jack-up vessel.
To determine the acceptable length of wind turbine blades, an original method based on the value of acceptable risk was developed. This risk depends on the possible consequences of an accident involving a jack-up vessel, and its value can be assumed on the basis of typical values available in the literature. Using the assumed acceptable risk, the permissible probability of the safe maneuvering area crossing the available shipping area is determined. The value of this probability is calculated using the author’s original relation taking into account the value of acceptable risk and traffic intensity. In the next step, assuming that the calculated probability is equal to the required level of significance, the width of the safe maneuvering area is determined. For the calculations, the CIRM method, which has been previously developed and well-tested in practice, is used. The calculated width of the maneuvering area together with the width of available maneuvering area and ship parameters enable to determine the acceptable length of the wind turbine blades. The novelty of the developed method results from the original dependencies that allow calculating the acceptable probability of exceeding the available navigable area by the safe maneuvering area and the acceptable length of the wind turbine blades.
The above-water width of the navigable water body of the section D i n a d should be taken as the minimum distance between:
  • The sides of “maximum” ships standing at quays or hydrotechnical constructions on both sides of the fairway;
  • The side of the “maximum” vessel or hydrotechnical structure on one side of the waterway and a safe isobath on the other side.
The navigational risk of accidents resulting from a loaded jack-up vessel crossing the waterway width of the available shipping area is determined by the following relationship:
R = p i n a d   ×   I i /   G r   [ year 1 ]
where:
p i n a d -The probability of the safe maneuvering area of the loaded jack-up vessel d i n a d crossing the above-water available navigation area D i n a d on the i-th section of the waterway.
Assuming that navigational risk equals acceptable risk:
R = Rakc
the permissible probability of the above-water safe maneuvering area of a jack-up vessel loaded transversely with wind turbine blades was obtained:
p i n a d = R akc   ×   G r / I r  
The above-water width of the safe maneuvering area of a jack-up vessel loaded transversely with wind turbine blades determined at the confidence level (1−α) is:
d i   ( 1 α ) n a d = d i ( 1 - α )   + L blades   B
where:
di(1−α)-Width of the safe maneuvering area of a jack-up vessel passing through the i-th waterway section determined at the confidence level (1−α);
Lblades-Length of loaded across ship wind turbine blades;
B-Width of jack-up vessel
The width of the safe maneuvering area of the jack-up vessel determined by the CIRM method at the confidence level (1−α) for the i-th track section is []:
d ( 1 α ) = d m + 2 d n ( 1 α ) + d r p + d r l  
where:
dm-Maneuvering component of the lane width;
d n ( 1 α ) -Navigation component of the lane width determined at the confidence level (1−α);
d r p , d r l -Provision for the bank and channel effect of the right and left sides of the waterway, respectively.
Assuming that the significance level is equal to the permissible probability of crossing the above-water navigation area ( D i n a d ) by the above-water safe manoeuvring area ( d i n a d ):
α = p i n a d
determining the acceptable safe length of wind turbine blades loaded across the jack-up vessel at the level of accepted acceptable navigational risk,
L i a k c = D i n a d + B d m 2 d n ( 1 α ) d r p d r l α = p i n a d }
where:
p i n a d = R akc   ×   G r / I r
The developed method is recommended to be used with the average annual number of jack-up loaded vessel exits in the range:
Ir = 7–100 [year−1]
Within these limits, the significance level (α) corresponding to the acceptable probability of a ship’s above-water safe maneuvering area exceeding the above-water accessible navigable area determined for an acceptable risk of Rakc = 1 × 10−3 is, respectively:
α = 0.05 ÷ 0.003
that is, it ranges from the standard confidence level assumed in navigation, (1−α) = 0.95, to the confidence level (1−α) = 0.997, corresponding to three standard deviations.
If the average number of maneuvers per year is less than seven, the navigational risk criterion for a specific accident per year should not be applied, but the navigational risk criterion for a specific accident per (single) maneuver should be used assuming, respectively:
  • Acceptable risk of accident: Rakc = 5 × 10−2;
  • Acceptable risk of a fatal accident:
    For a crew member: Rs akc = 1 × 10−3;
    For passenger: Rs akc = 1 × 10−4.

5. Application of the Developed Method to Determine the Acceptable Length of Wind Turbine Blades in the Port of Świnoujście

A terminal for offshore wind farms is planned to be built in the port of Świnoujście on the Świna river. The terminal will be used for the construction of offshore wind turbines on the Baltic Sea in the Polish economic zone [].
The terminal will consist of service and installation berths. WTTV vessels will be handled at the service berths and WTIV jack-up vessels at the installation berths.
Jack-up vessels at installation berths load themselves by standing on the legs of the jack-up system. The deck cargo of these vessels includes, among other things, wind turbine blades loaded symmetrically or asymmetrically across the vessel.
The method was applied to determine the permissible blade lengths of wind turbines loaded across the jack-up vessel to allow safe passage on the Świnoujście–Szczecin fairway between the Mielińska Obrotnica and the pair of buoys “15”–“16”. The exit of the loaded jack-up vessel (with the permissible blade length) should be safe for the “maximum vessels” moored at the Ferry Terminal facilities in Świnoujście (Figure 4) and Chemików Quay (Figure 5).
Figure 4. Available navigation area, stand no. 2 of the ferry terminal in Świnoujście.
Figure 5. Available navigation area, Chemików Quay.
It was assumed that the “maximum ship” of the jack-up type operated in Świnoujście port will be the “Voltaire” currently under construction with the following parameters:
  • LOA = 170 m;
  • B = 60 m;
  • T = 7.5 m.
On the Świnoujście–Szczecin fairway from the Mielińska Obrotnica to the pair of buoys “15”–“16”, there are two sections with the smallest above-water widths limiting the navigational risk and thus the maximum (allowable) length of transversely loaded blades on an outbound jack-up vessel.
These are:
  • Passage along the designed ferry stand no. 2 during moored ferry LOA = 230 m (4.3 km of track), D = 210 m, Dnad = 231 m (Figure 3);
  • Passage along the Chemików Quay during berthing of a bulk carrier with width B = 50 m (1.3 km of track), D = 198 m, Dnad = 266 m (Figure 4).
The accident contingency scenarios for the two track sections generating the greatest navigational risk can be characterized as follows:
Scenario 1: Impact of the outgoing jack-up vessel with turbine blades loaded asymmetrically on the starboard side on the moored ferry LOA = 230 m at the modernized ferry stand no. 2. The kinetic energy of impact of this vessel on the ferry is relatively high (V = 4 ÷ 6 knots), which may cause damage to gangways and ramps. The result of such an accident may be the death of a group of passengers.
The acceptable risk of such an accident should be taken as equal:
  • Rakc1 = 1 × 10−6 (1/year).
Scenario 2: Impact of an outbound jack-up vessel with its blades asymmetrically loaded on the starboard side on a moored bulk carrier with a width of B = 50 m at the Chemików Quay. The kinetic energy of the impact of this ship against the bulk carrier (at a speed of 4 ÷ 6 knots) may cause damage to the wind turbine blades, the jack-up vessel, and the bulk carrier.
The acceptable risk of such an accident should be taken as equal:
  • Rakc2 = 1 × 10−3 (year−1)
Assuming the predicted average annual number of jack-up vessel maneuvers from Świnoujście port as equal to Ir = 20, the calculation significance levels for both scenarios were determined:
  • α1 = 1.852 × 10−5,
  • α1 = 1.852 × 10−2,
and the corresponding navigational components—the widths of the safe maneuvering area []:
  • dn(1−α1) ≈ 10 m,
  • dn(1−α2) ≈ m.
The permissible safe lengths of wind turbine blades loaded across the jack-up vessel leaving the port of Świnoujście are, respectively:
L 1 a k c ≈ 170 m (at Rakc = 1 × 10−6);
L 2 a k c ≈ 140 m (at Rakc = 1 × 10−3).
When calculating the safe blade lengths, the basic maneuvering component dm = 1.3B (very good ship steering) and dr = 0.1B (ship speed 4 ÷ 6 knots) were assumed. Detailed results for determining the acceptable safe lengths of wind turbine blades loaded across the jack-up vessel leaving the port of Świnoujście are presented in Table 1.
Table 1. Detailed results for determining the acceptable safe lengths of wind turbine blades loaded across the jack-up vessel leaving the port of Świnoujście.

6. Discussion and Conclusions

Based on the above results of calculations, it should be assumed that jack-up vessels loaded crosswise with wind turbine blades of maximum length L = 140 m will be able to safely exit from the designed offshore wind farm terminal in Świnoujście.
This paper presents a method for determining the maximum safe blade lengths of wind turbines loaded across jack-up vessels maneuvering in port waterways. In this method, after identifying the hazards in the waterway under study, the acceptable risk of each accident scenario was determined.
The navigational safety criterion used is the impassibility of acceptable risk. Based on this criterion, a confidence level was determined, based on which the above-water width of the safe maneuvering area of jack-up vessels with wind turbine blades loaded crosswise was determined. Considering the above-water available width of the study shipping area, the maximum safe length of the wind turbine blades for a specific accident scenario was also determined.
It has been established that the developed method is recommended to be used within the range of 7 ÷ 100 departure maneuvers of a loaded jack-up vessel from the port per year.
The developed method was applied to determine the allowable length of wind turbine blades loaded across jack-up vessels exiting the proposed offshore wind farm terminal in Świnoujście. This length is Lakc = 140 m.

Author Contributions

Conceptualization, S.G. and W.Ś.; methodology, S.G.; software, R.G. and M.P.; validation, S.G. and W.Ś.; formal analysis, S.G., R.G., M.P. and W.Ś.; investigation, S.G., R.G., M.P. and W.Ś.; resources, R.G. and M.P.; data curation, R.G. and M.P.; writing—original draft preparation, S.G.; writing—review and editing, R.G. and M.P.; visualization, R.G.; supervision, W.Ś.; project administration, S.G.; funding acquisition, W.Ś. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Durakovic, A. World’s Largest, Most Powerful Wind Turbine Stands Complete. Offshorewind. 2021. Available online: https://www.offshorewind.biz/2021/11/12/worlds-largest-most-powerful-wind-turbine-stands-complete (accessed on 24 February 2022).
  2. Siemens Gamesa. Sofia’s Giant Leap: Siemens Gamesa Selected to Deliver 100 Flagship 14 MW Turbines. 2021. Available online: https://www.siemensgamesa.com/newsroom/2021/03/210330-siemens-gamesa-press-release-sofia-uk (accessed on 24 February 2022).
  3. General Electric. GE Renewable Energy Launches the Uprated Haliade-X 13 MW Wind Turbine for the UK’s Dogger Bank Wind Farm. 2020. Available online: https://www.ge.com/news/press-releases/ge-renewable-energy-launches-uprated-haliade-x-13-mw-wind-turbine-uk-dogger-bank (accessed on 24 February 2022).
  4. Sonal, P. POWER Offshore Wind Notebook: GE Boosts Haliade-X to 14 MW. 2020. Available online: https://www.powermag.com/power-offshore-wind-notebook-ge-boosts-haliade-x-to-14-gw-dominion-kicks-off-2-6-gw-virginia-project-vestas-absorbs-mhi-vestas/ (accessed on 24 February 2022).
  5. Nehls, G. Vestas to Install V236-15.0 MW Prototype Turbine at Østerild in Denmark. CompositesWorld. 2021. Available online: https://www.compositesworld.com/news/vestas-to-install-v236-150-mw-prototype-turbine-at-osterild-in-denmark (accessed on 24 February 2022).
  6. Eneti Inc. Offshore Wind Update Call. 2021. Available online: https://www.eneti-inc.com/wp-content/uploads/ENETI_Company_Presentation_vf-1.pdf (accessed on 24 February 2022).
  7. Snieckus, D. The French Re-Connection: Technip Returns to Floating Wind Power with New Energy. Energy Transition. 2021. Available online: https://www.rechargenews.com/energy-transition/the-french-re-connection-technip-returns-to-floating-wind-power-with-new-energy/2-1-1089292 (accessed on 24 February 2022).
  8. Bartlett, P. Floating Offshore Wind—Its Time Has Come. Seatrade Maritime News. 2021. Available online: https://www.seatrade-maritime.com/offshore/floating-offshore-wind-its-time-has-come (accessed on 24 February 2022).
  9. Office of Energy Efficiency & Renewable Energy. Offshore Wind Market Report: 2021 Edition; DOE/GO-102021-5614; U.S. Department of Energy: Washington, DC, USA, 2021. [Google Scholar]
  10. Tufts University. Wind Turbine Installation Vessels: Global Supply Chain Impacts on the U.S. Offshore Wind Market; Report No. OSPRE-2021-02; Tufts University: Medford, MA, USA, 2021. [Google Scholar]
  11. Durakovic, A. Super-Sized Turbines and Offshore Wind Farms Bring ‘Game-Changing’ Cost Cuts—NREL. Offshorewind. 2021. Available online: https://www.offshorewind.biz/2021/11/08/super-sized-turbines-and-offshore-wind-farms-bring-game-changing-cost-cuts-nrel (accessed on 24 February 2022).
  12. Zhu, W.J.; Shen, W.Z.; Kim, T. Towards Innovation in Next Generation of Wind Turbine Rotor Design. Front. Energy Res. 2021, 9, 783039. [Google Scholar] [CrossRef]
  13. Polish Wind Energy Association. The Future of Offshore Wind Energy in Poland; PWEA Report; Polish Wind Energy Association: Szczecin, Poland, 2019. [Google Scholar]
  14. Hartkopf-Mikkelsen, J. Havmølleproducent: Vi Mangler Installationsskibe Nu [Offshore Wind Turbine Manufacturer: We Are Missing Installation Vessels Now]. Søfart. Last Modified 26 August 2020. Available online: https://www.soefart.dk/article/view/736115/havmolleproducent_vi_mangler_installationsskibe_n (accessed on 24 February 2022).
  15. Rystad Energy. The World May Not Have Enough Heavy Lift Vessels to Service the Offshore Wind Industry Post 2025. 2020. Available online: https://www.rystadenergy.com/newsevents/news/press-releases/the-world-may-not-have-enough-heavy-lift-vessels-to-service-the-offshore-wind-industry-post-2025/ (accessed on 24 February 2022).
  16. NEEC. Fresh Breezes for Offshore Installation Vessels. 2021. Available online: https://neec.no/the-offshore-installation-vessels-market-meets-its-opportunities/ (accessed on 24 February 2022).
  17. Durakovic, A. First Steel Cut for Mega Jack-Up Voltaire. Offshorewind. 2020. Available online: https://www.offshorewind.biz/2020/05/26/first-steel-cut-for-mega-jack-up-voltaire/ (accessed on 24 February 2022).
  18. Allen, S. Triumph Subsea Services Orders Two New Installation Vessels. 4C Offshore. 2020. Available online: https://www.4coffshore.com/news/triumph-subsea-servicesorders-two-new-installation-vessels-nid17947.html (accessed on 24 February 2022).
  19. The Maritime Executive. New Versatile Wind Turbine Installation Vessel: The Atlas C-Class. 2021. Available online: https://www.maritime-executive.com/corporate/new-versatile-wind-turbine-installation-vessel-the-atlas-c-class (accessed on 24 February 2022).
  20. Gucma, S. Marine Traffic Engineering; Wydawnictwo Okrętownictwo i Żegluga Publishing House: Gdańsk, Poland, 2001. [Google Scholar]
  21. Gucma, S.; Artyszuk, J.; Bąk, A.; Gucma, L.; Gucma, M.; Jankowski, S.; Kasyk, L.; Mazurkiewicz, B.; Przywarty, M.; Ślączka, W.; et al. Marine Waterways—Design and Operation in Terms of Traffic Engineering; Foundation for the Promotion of the Shipbuilding Industry and Maritime Economy: Gdansk, Poland, 2015. [Google Scholar]
  22. Gucma, L. Guidelines for Maritime Risk Management; Wydawnictwo Naukowe Akademii Morskiej w Szczecinie: Szczecin, Poland, 2009. [Google Scholar]
  23. Bak, A.; Gucma, S.; Przywarty, M. Safety of Navigation in Restricted Waters; Wydawnictwo Naukowe Akademii Morskiej w Szczecinie: Szczecin, Poland, 2021. [Google Scholar]
  24. Gucma, S.; Artyszuk, J.; Bilewski, M.; Gralak, R.; Gucma, L.; Gucma, M.; Marcjan, K.; Ślączka, W.; Zalewski, P. Marine Traffic Engineering. Guidelines for the Design of Marine Waterways and Ports and Conditions for Their Safe Operation; Foundation for the Promotion of the Shipbuilding Industry and Maritime Economy: Gdansk, Poland, 2017. [Google Scholar]
  25. Gucma, S.; Gralak, R. The Designed Port for Offshore Wind Farms in Świnoujście—Navigation Risk Analysis; Inżynieria Morska i Geotechnika Nr 2/2021, EN ISSN 0867-4299; IMOGEOR Sp. z o.o.: Gdańsk, Poland, 2021. [Google Scholar]
  26. Maritime Academy in Szczecin. Report of the Scientific and Research Work. Maximum Safe Parameters of Loaded Vessels for Offshore Wind Turbine Installation (Jack-Up) Exiting the Designed Offshore Wind Farm Terminal in Świnoujście—Navigational Analysis; Maritime University in Szczecin: Szczecin, Poland, 2021. [Google Scholar]
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.