Next Article in Journal
Advanced Hybrid Modeling of Cementitious Composites Using Machine Learning and Finite Element Analysis Based on the CDP Model
Previous Article in Journal
AAR-Reactive Fillers in Concrete: Current Understanding and Knowledge Gaps
Previous Article in Special Issue
Bolt Loosening and Preload Loss Detection Technology Based on Machine Vision
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Bayesian Network-Driven Risk Assessment and Reinforcement Strategy for Shield Tunnel Construction Adjacent to Wall–Pile–Anchor-Supported Foundation Pit

School of Transportation and Logistics Engineering, Wuhan University of Technology, Wuhan 430063, China
*
Authors to whom correspondence should be addressed.
Buildings 2025, 15(17), 3027; https://doi.org/10.3390/buildings15173027
Submission received: 30 June 2025 / Revised: 18 August 2025 / Accepted: 19 August 2025 / Published: 25 August 2025

Abstract

With the increasing demand for urban rail transit capacity, shield tunneling has become the predominant method for constructing underground metro systems in densely populated cities. However, the spatial interaction between shield tunnels and adjacent retaining structures poses significant engineering challenges, potentially leading to excessive ground settlement, structural deformation, and even stability failure. This study systematically investigates the deformation behavior and associated risks of retaining systems during adjacent shield tunnel construction. An orthogonal multi-factor analysis was conducted to evaluate the effects of grouting pressure, grout stiffness, and overlying soil properties on maximum surface settlement. Results show that soil cohesion and grouting pressure are the most influential parameters, jointly accounting for over 72% of the variance in settlement response. Based on the numerical findings, a Bayesian network model was developed to assess construction risk, integrating expert judgment and field monitoring data to quantify the conditional probability of deformation-induced failure. The model identifies key risk sources such as geological variability, groundwater instability, shield steering correction, segmental lining quality, and site construction management. Furthermore, the effectiveness and cost-efficiency of various grouting reinforcement strategies were evaluated. The results show that top grouting increases the reinforcement efficiency to 34.7%, offering the best performance in terms of both settlement control and economic benefit. Sidewall grouting yields an efficiency of approximately 30.2%, while invert grouting shows limited effectiveness, with an efficiency of only 11.6%, making it the least favorable option in terms of both technical and economic considerations. This research provides both practical guidance and theoretical insight for risk-informed shield tunneling design and management in complex urban environments.

1. Introduction

The rapid development of urban underground transportation infrastructure has become an effective solution to urban surface traffic congestion. Among various tunneling techniques, shield tunneling has become the mainstream method for metro construction due to its advantages of safety, efficiency, and environmental friendliness [1,2,3]. However, with increasingly complex geological and construction conditions, the excavation of shield tunnels near existing foundation pits has introduced significant risks [4,5,6]. These include disturbance of the in situ stress equilibrium in the surrounding soil, leading to deformation of adjacent strata and retaining structures, and, in extreme cases, ground collapse and support instability [7,8,9,10]. Therefore, strict settlement control of both the foundation pit and the surrounding soil during shield tunneling is essential.
When a shield tunnel passes adjacent to a diaphragm wall–pile–anchor-supported pit, it is critical to ensure that settlements of the retaining system remain within serviceability limits [11,12]. Current practice often relies on settlement control theory to formulate construction control schemes, with grouting-based ground improvement used as a primary countermeasure [13,14,15,16]. Common grouting methods include high-pressure jet grouting, sleeve-valve pipe grouting, and MJS (multi-directional jet grouting) [17,18,19]. Studies have shown that combining radial grouting inside the tunnel with sleeve-valve surface grouting can reduce wall settlement by up to 44% [20,21,22]. Moreover, numerical analyses have demonstrated that increasing vertical grouting depth is more effective in reducing surface settlement than expanding the circumferential injection angle.
Due to the multiplicity of risk sources in shield construction, various management science techniques have been adopted for risk assessment. These include the Analytic Hierarchy Process (AHP), fuzzy logic theory, and fault tree analysis [21,23]. However, these methods often fail to capture the stochastic and uncertain nature of multiple interacting risk factors, limiting their effectiveness in dynamic risk warning [24,25,26,27]. With the advancement of intelligent technologies, Bayesian networks have emerged as powerful tools for risk assessment due to their ability to incorporate prior knowledge and update probabilities in real time [28,29,30].
Recent studies have applied dynamic Bayesian networks to assess shield tunneling risks beneath existing structures, incorporating monitoring data into predictive frameworks [31,32]. For example, Chen [33] used Bayesian models to predict pre-construction risks; Wang [34] combined Bayesian networks with fuzzy evaluation to assess underground construction risks; Xiang [35] integrated fault tree analysis with Bayesian inference to evaluate pipeline damage risks from nearby excavation. Despite their advantages, these studies primarily focus on special geotechnical conditions or tunneling near existing tunnels and utilities, with limited application to shield tunneling adjacent to retaining pits. Moreover, there is a lack of research integrating risk identification with practical mitigation strategies.
To address these gaps, this study adopts an orthogonal experimental design to analyze the influence and significance levels of shield tunneling parameters on settlement control. A Bayesian network model is then used to assess the probabilistic risk of settlement-related failures when a shield tunnel is constructed near a diaphragm wall–pile–anchor-supported pit. The key influencing factors are identified, and numerical simulations are employed to evaluate the effectiveness of grouting reinforcement around the tunnel. A practical and economically viable control strategy is proposed to reduce the risk of settlement-induced failures, thereby offering technical guidance for safer shield tunneling adjacent to foundation pits.

2. Methodology

2.1. Finite Element Numerical Model

Finite element modeling was conducted using MIDAS GTS/NX 2024R1 to simulate the ground and structural response during adjacent shield tunnel construction [36,37]. The primary purpose of this numerical analysis was twofold: (1) to quantitatively evaluate the influence of different construction parameters (e.g., grouting pressure, soil properties) on surface settlement and support system performance and (2) to generate representative physical data that supports the conditional probability structure within the Bayesian network model developed in this study [38,39]. The overall model dimensions are 120 m in length, 120 m in width, and 50 m in height. The soil mass and segmental lining were modeled using 3D hexahedral solid elements. The shield shell and diaphragm wall were modeled using 2D shell elements. The struts and piles were represented by 1D beam elements, while the anchors were simulated using 1D embedded truss elements. In the meshing process, a balance between simulation accuracy and computational efficiency was considered, and a uniform mesh size of 1.0 m was selected for model analysis.
In the FEM model, the soil was assumed to be a homogeneous elastoplastic material, with all soil layers uniformly distributed across the construction site. The diaphragm wall, piles, capping beams, anchor bolts, and tunnel segments were modeled as linear elastic elements. To account for the mechanical behavior of segmental joints, the structural strength of the tunnel segments was reduced by 15%. The initial stress field considered only self-weight-induced stress, and the interface friction between the shield machine and the surrounding soil was neglected. The groundwater table was modeled as a stable confined aquifer located 10.8 m below the ground surface.
In the numerical model, the long side of the excavation pit is aligned parallel to the X-axis, the short side is parallel to the Y-axis, and the Z-axis is oriented vertically. Boundary conditions are applied as follows: the bottom surface is fully constrained in the X, Y, and Z directions; all vertical side surfaces are constrained in the direction normal to each respective face; and the top surface remains free without any constraints. For the one-dimensional (1D) structural elements in the model, rotational degrees of freedom are restrained to prevent torsional effects. During the tunnel excavation process, grouting is simulated by modifying the material properties of the soil elements within the grouting zone using the “attribute modification” function, thereby reflecting the improvement effect of grouting on the mechanical behavior of the surrounding soil.
To improve computational efficiency, a 2D finite element model was employed to perform an orthogonal experimental analysis of shield tunneling adjacent to a diaphragm wall–pile–anchor-supported excavation. Figure 1 presents the 2D finite element model, while Figure 2 illustrates the 3D counterpart. The comparison of results between the 2D and 3D models is shown in Table 1. The difference in computed values was within 6%, indicating that the deviation was minor. It should be noted that the maximum surface settlement outside the excavation zone was selected as the primary index for comparing the 2D and 3D models, mainly due to its critical role in engineering practice. This parameter is highly sensitive and commonly used as a key control criterion in risk evaluation and surface deformation monitoring during shield tunnel construction [40,41,42]. It should also be noted that the maximum surface settlement outside the excavation zone was selected as the primary index for comparing the 2D and 3D models, mainly due to its critical role in engineering practice. This parameter is highly sensitive and commonly used as a key control criterion in risk evaluation and surface deformation monitoring during shield tunnel construction.

2.2. Model Parameter Design

2.2.1. Soil Parameters

In the modified Mohr–Coulomb [43] constitutive model, the required soil parameters include unit weight, internal friction angle, cohesion, Poisson’s ratio, secant stiffness from triaxial tests ( E 50 r e f ), tangent stiffness from oedometer tests ( E o e d r e f ), and unloading–reloading stiffness ( E u r r e f ). In the model parameterization process, the geotechnical properties of the soil, such as unit weight, cohesion, internal friction angle, compression modulus, and Poisson’s ratio, were primarily derived from the geotechnical investigation report of the project site. Based on this, a series of laboratory soil tests were conducted to obtain the parameters of each soil layer, as summarized in Table 2. The physical and mechanical properties of the soil are listed in Table 2, and the thicknesses of the soil layers are provided in Table 3.

2.2.2. Structural Material Parameters

The diaphragm wall, piles, and struts are composed of C35 concrete, while the tunnel segments are made of C50 concrete. To account for the effect of segmental joint staggering, a stiffness reduction factor of 0.85 is applied to the tunnel segments. The mechanical properties of all structural materials used in the model were obtained through laboratory testing, and the test results are presented in Table 4.

2.2.3. Simulation of Ground Loss

In this study, ground loss is simulated using equivalent layers and controlled grouting parameters. The configuration of the equivalent layer is illustrated in Figure 3. It is modeled as a three-dimensional solid element with a thickness calculated using Equation (1) [44,45], and a value of 10 cm is adopted.
δ = η Δ
where Δ is the tail void (half of the difference between the shield outer diameter and the segment outer diameter, taken as 0.15 m in this study), and η is the reduction factor, ranging from 0.7 to 1.5, with 0.7 used herein.
The equivalent layer is filled with grout. To simulate the curing process, different material parameters are assigned according to the number of rings behind the shield tail [46,47]. Specifically, the 1st ring uses 0-day grout, the 2nd ring uses 1-day grout, the 3rd to 4th rings use 2-day grout, the 5th to 10th rings use 7-day grout, and rings beyond the 10th use 28-day grout. In addition, considering the performance requirements of grouting materials during actual shield tunneling operations, a series of laboratory-prepared grouting samples were tested to determine their physical and mechanical properties at different curing ages. The corresponding results are shown in Table 5.

3. Orthogonal Experimental Design

Key experimental factors selected for this study include grouting pressure, elastic modulus of the grouting layer after 28 days of hardening (400 MPa), and the cohesion and internal friction angle of the soil above the tunnel. The levels of each factor were determined based on engineering experience. The orthogonal experimental factors and their corresponding levels are presented in Table 6.
An orthogonal experimental matrix was constructed according to standard orthogonal array design principles, and numerical simulations were performed [48]. The maximum surface settlement outside the excavation zone was chosen as the evaluation index, as it directly reflects the intensity of the shield tunnel excavation effect. The results of each test scenario are summarized in Table 7.
The experimental results reveal clear trends. Lower grouting pressure and zero soil cohesion (e.g., Test 1) resulted in the highest observed settlement of 10.2 mm, while the smallest deformation (2.6 mm) was achieved under high pressure (525 kPa) and moderate soil strength (Test 14). As grouting pressure and soil cohesion increased, settlement generally decreased, reflecting enhanced soil confinement and load redistribution. Notably, although Ea and φ exhibited marginal influence compared to P and C, tests with elevated Ea (e.g., 1.75 E in Test 4 and 12) consistently showed improved performance in settlement reduction. These results indicate that soil cohesion and grouting pressure are dominant control parameters. This lays the foundation for subsequent variance analysis and multi-objective optimization of reinforcement strategies, as discussed in the following sections.

4. Results and Discussion

4.1. Analysis of Influencing Factors of Ground Settlement During Shield Tunneling

4.1.1. Analysis of Range

Table 8 presents the range analysis of the maximum surface settlement. It indicates that grouting pressure and soil cohesion exhibit the largest range of values, suggesting a stronger influence on surface settlement. In contrast, the elastic modulus of the grouting layer and the internal friction angle have smaller range values, indicating a weaker effect. As shown in Figure 4, the steeper the slope of the response curve, the greater the factor’s influence on surface settlement. Based on the test data, the factors influencing are ranked in descending order of significance as follows: cohesion (c), grouting pressure (P), elastic modulus of the grouting layer (Ea), and internal friction angle (φ).

4.1.2. Analysis of Variance

To further evaluate the significance of each factor, an analysis of variance (ANOVA) was conducted using the maximum surface settlement as the response variable. A confidence level of 95% was adopted. The ANOVA results are shown in Table 9. The result presents the ANOVA for surface settlement. The F-values of grouting pressure and soil cohesion are 1382.33 and 3491.33, respectively, which are significantly higher than those of the other factors. This demonstrates that these two parameters have the most prominent effect on surface settlement. Therefore, under a 95% confidence level, soil cohesion and grouting pressure are identified as the primary influencing factors.

4.2. Bayesian Network Evaluation of Construction Risks for Shield Tunneling near Wall–Pile–Anchor-Supported Excavations

To control deformation-related failures during shield tunneling adjacent to pile–anchor-supported foundation pits, it is essential to conduct a thorough risk assessment prior to construction [49,50]. In this study, a Bayesian network Model is employed to quantitatively analyze the probability of deformation-induced failures in such scenarios [22,35,51].

4.2.1. Identification and Analysis of Risk Factors

It is acknowledged that the input parameters used in the Bayesian network model, particularly the conditional probabilities, are primarily derived from expert elicitation due to the lack of comprehensive field monitoring data. While this approach facilitates the construction of a functional and interpretable causal model, it inevitably introduces a degree of subjectivity. Therefore, the present model is intended primarily for qualitative trend analysis and identification of dominant risk factors. In projects involving shield tunneling near existing pile–anchor-supported pits, the structural safety of the tunnel and pit is influenced by multiple factors, including the construction environment, construction plan, construction technique, and construction management. Based on field investigations, expert consultations, literature review [27,31,35], and simulated construction processes, the main risk sources were identified and classified into basic events, as listed in Table 10.
The top event of the Bayesian network model is defined as the occurrence of a “shield tunneling failure,” denoted as node T. The full Bayesian network structure is shown in Figure 5. Once the basic events are determined, prior probabilities for each node are calculated using an expert weight-based evaluation method. Specifically, before construction, experts assess the likelihood of each basic event by assigning it a risk level, as specified in Table 10. These assessments are based on relevant documentation or personal experience. The final prior probability for each event is calculated as the weighted average of expert opinions, with results presented in Table 11.
A total of six experts in geotechnical and tunneling engineering contributed to the assessment of prior probabilities for the basic events in the Bayesian network. The weighting assigned to each expert is listed in Table 12, while the index and prior probability of each basic event are provided in Table 13.
Conditional probabilities are defined as the probability that a child event occurs, given that the parent event has failed. For example, if the conditional probability of X1 is 0.55, it indicates that, given an unfavorable construction environment, the probability of failure in the shield tunneling adjacent to the pile–anchor-supported pit is 55%. These probabilities are calculated by weighted averaging of expert evaluations, as shown in Table 14. Taking the “construction environment” node X1 as an example, its conditional probabilities are defined as shown in Table 15. In this context, X11 = S denotes favorable weather conditions, X11 = D denotes adverse weather, X12 = S represents favorable geological conditions, X12 = D represents poor geological conditions, X13 = S indicates stable groundwater, and X13 = D indicates unstable groundwater. The parent node X1 = S indicates a generally safe construction environment, whereas X1 = D implies a hazardous condition. When all three influencing factors are favorable, i.e., X11 = S, X12 = S, and X13 = S, the conditional probability of X1 = S is assigned a value of 1.0 (or 100%). This assignment is based on an idealized modeling assumption, indicating that under the optimal combination of weather, geology, and groundwater conditions, the construction environment can be considered highly reliable. It should be noted that this value does not imply absolute certainty in real-world conditions, but rather, it represents the maximum confidence output of the system under this specific input configuration.

4.2.2. Risk Factor Evaluation

Using the Bayesian network software NETICA V5.18, the construction risk associated with shield tunneling adjacent to pile–anchor-supported foundation pits was quantitatively assessed. The calculation results, shown in Figure 6, indicate that the probability of engineering failure is 13.1% when no effective construction control measures are implemented. In the model, “S” denotes the safe state and “D” denotes the dangerous state; all probabilities are expressed in percentage terms.
Subsequently, the backward inference function of the Bayesian network was applied. Assuming that the engineering failure has already occurred (i.e., the top node T is set to state D with a probability of 100%), the posterior probabilities of all basic events were calculated, as illustrated in Figure 7. The results of the maximum causal chain analysis reveal that the geological condition (X12) is the primary contributing factor to failure during shield tunneling adjacent to the pile–anchor-supported pit. In addition, groundwater stability (X13), along with construction-related technical factors, including shield deviation correction (X31), pile–anchor support reinforcement (X32), segmental lining assembly (X33), tail void grouting (X34), and construction team management practices (X42), also significantly influence construction safety.
The posterior probabilities of each basic event under the condition of engineering failure are presented in Table 16. Based on the results of the Bayesian inference, key risk factors in the construction of shield tunnels adjacent to pile–anchor-supported foundation pits were identified. These include unfavorable geological conditions, unstable groundwater, insufficient control of construction techniques, and inadequate management systems. Corresponding mitigation measures should be implemented for each critical factor identified in the assessment, with the aim of minimizing the probability of failure and ensuring the safety and reliability of the tunneling operation.

4.3. Analysis of Soil Reinforcement Control for Shield Tunneling near Wall–Pile–Anchor Support

4.3.1. Grouting Reinforcement Scheme for the Surrounding Soil of the Tunnel

During the construction of a shield tunnel passing through a foundation pit supported by wall–pile–anchor systems, grouting reinforcement around the tunnel is often required to improve local ground conditions and control ground settlement outside the pit. Prior to grouting, it is necessary to determine the appropriate size and location of the reinforcement zone. To define the optimal reinforcement extent, a series of single-factor parametric analyses were conducted based on the numerical model presented [52]. A schematic diagram of the grouting reinforcement area surrounding the tunnel is shown in Figure 8, and the mechanical parameters of the grouted soil are listed in Table 17.
To assess the effectiveness of different reinforcement positions and ranges, the maximum surface settlement outside the excavation before and after reinforcement was used as the primary control index [53]. In comparing various reinforcement strategies, two indicators were introduced to evaluate the settlement reduction effect and economic feasibility, including grouting improvement ratio W and grouting efficiency Z [50,54]. The grouting improvement ratio W is calculated using Equation (2). A higher value of W indicates a more effective reinforcement outcome. In this study, the reinforcement ratio W is defined as a dimensionless index that quantifies the relative effectiveness of grouting in reducing the maximum surface settlement. It is calculated as the percentage reduction in maximum settlement after reinforcement compared to the unreinforced condition. This index quantifies the proportional effectiveness of the reinforcement measure in controlling settlement, allowing for a direct and comparable evaluation across different reinforcement schemes. By expressing performance improvements in percentage terms, it also facilitates the integration of technical effectiveness with cost–benefit analysis for decision-making. The grouting efficiency Z, defined by Equation (3), reflects the settlement control effect per unit reinforcement width; the larger the value of Z, the greater the economic benefit of the grouting reinforcement schemes.
W = S S S × 100
where W is the grouting reinforcement ratio, S is the maximum surface settlement caused by shield tunneling without reinforcement, and S′ is the maximum surface settlement caused by shield tunneling after reinforcement.
Z = W B × 100
where B is the width of the reinforced soil, in meters (m); Z is the grouting reinforcement efficiency, expressed in inverse meters (m−1).

4.3.2. Analysis of the Effect of Grouting Reinforcement on the Surrounding Tunnel Soil

(1) Soil reinforcement on both sides of the tunnel spring line
To simulate the effect of grouting reinforcement, the mechanical properties of the soil within the reinforcement zones were modified. The lateral reinforcement widths on each side of the tunnel were set to 1 m, 1.5 m, 2 m, and 2.5 m, resulting in total widths B of 2 m, 3 m, 4 m, and 5 m, respectively. The corresponding surface settlement curves after tunneling are shown in Figure 9. The maximum surface settlements for reinforcement widths of 2 m, 3 m, 4 m, and 5 m were 8.48 mm, 7.81 mm, 7.25 mm, and 6.98 mm, respectively. Increasing the reinforcement width effectively reduces surface settlement. The location of maximum settlement remains directly above the tunnel centerline and does not shift with reinforcement width. The reinforcement ratio and efficiency for lateral grouting are shown in Figure 10. The result illustrates that as the lateral reinforcement width increases from 2 m to 5 m, the reinforcement ratio increases from 15.1% to 30.2%, while the reinforcement efficiency decreases from 7.6% to 6.0%. This indicates that although expanding the reinforcement zone improves settlement control, it yields diminishing economic returns.
(2) Soil reinforcement below the tunnel invert
Subsequently, the bottom reinforcement depth was set to 1 m, 1.5 m, 2 m, and 2.5 m. Figure 11 presents the corresponding settlement curves. The maximum surface settlements were 9.38 mm, 9.21 mm, 9.02 mm, and 8.90 mm, respectively. Although deeper bottom reinforcement reduces settlement, the control effect remains limited. By replacing the reinforcement width B in Equation (3) with the bottom reinforcement depth, the corresponding reinforcement ratio and efficiency were calculated (Figure 12). As depth increases from 1 m to 2.5 m, the reinforcement ratio increases from 6.2% to 11.6%, while the efficiency decreases from 6.2% to 4.2%. This demonstrates that bottom reinforcement contributes little to settlement control and exhibits lower cost-effectiveness.
(3) Soil reinforcement above the tunnel crown
The top reinforcement height varied as 1 m, 1.5 m, 2 m, and 2.5 m. The post-construction settlement curves are shown in Figure 13. The maximum surface settlements were 8.34 mm, 7.63 mm, 7.03 mm, and 6.53 mm, respectively. These results confirm that top reinforcement significantly reduces surface settlement.
By substituting the top reinforcement height into Equation (3), the reinforcement ratio and efficiency were computed (Figure 14). As the height increases from 1 m to 2.5 m, the ratio increases from 16.6% to 34.7%, while the efficiency decreases from 16.6% to 13.9%. This indicates that grouting above the tunnel is highly effective in controlling surface settlement with strong economic performance. In conclusion, considering both settlement control and cost efficiency, grouting above the tunnel should be prioritized, followed by lateral grouting. Bottom reinforcement proves less effective and can be excluded. The extent of reinforcement should be selected based on allowable settlement thresholds and simulation outcomes, as indiscriminately expanding the zone may lead to unnecessary economic loss.

5. Conclusions

This study integrates numerical simulation, experimental design, and Bayesian probabilistic inference to systematically investigate the deformation behavior and risk control strategies associated with deep excavations supported by wall–pile–anchor systems adjacent to shield tunnels. The research identifies key parameters influencing ground surface settlement and proposes a technical framework for deformation risk control under such complex urban tunneling scenarios. The following conclusions are drawn:
  • Range and variance analyses based on maximum surface settlement outside the excavation indicate significant differences in the impact of influencing parameters. Soil cohesion and grouting pressure are identified as the most critical variables, jointly accounting for over 72% of the variance in settlement response, followed by the elastic modulus of the grouted layer and the internal friction angle of the soil.
  • A Bayesian network model was established to represent and infer causal relationships among various risk sources by integrating expert knowledge and field data. The results indicate that unfavorable geological conditions, unstable groundwater, insufficient shield steering correction, inadequate support reinforcement, and weak construction management are the primary causes of failure. Posterior inference further confirms the leading role of geology and construction control in ensuring project safety, providing a scientific basis for pre-construction risk mitigation.
  • The effectiveness and cost-efficiency of different grouting reinforcement strategies around the tunnel were evaluated through parametric simulation. The results show that top grouting increases the soil reinforcement ratio to 34.7% and achieves the highest reinforcement efficiency (13.9%), offering the best performance in settlement control and economic return. Sidewall grouting provides a reinforcement efficiency of approximately 6.0%, serving as a supplementary measure. In contrast, invert grouting yields a low efficiency of only 4.2%, indicating limited effectiveness and cost performance.
  • This study provides a systematic modeling framework and quantitative analysis method for addressing deformation response and risk control associated with adjacent shield tunneling in complex urban environments. However, the research is constrained by idealized boundary conditions and the static nature of the model. Future work may focus on integrating real-time monitoring data and machine learning techniques to enable dynamic model updating and enhance the broader applicability of the proposed approach.

Author Contributions

Y.L.: Data Curation, Formal Analysis, Methodology, Writing—Original Draft Preparation, and Writing—Review and Editing. B.Z.: Data Curation, Formal Analysis, Writing—Original Draft Preparation, and Writing—Review and Editing. H.Q.: Conceptualization, Data Curation, Visualization, and Writing—Review and Editing. All authors have read and agreed to the published version of the manuscript.

Funding

The study was sponsored by the National Natural Science Foundation of China (Grant No. 11672215) and financially supported by self-determined and innovative research funds of WUT (Grant No. 104972025RSCbs0054).

Data Availability Statement

The data can be provided as needed.

Conflicts of Interest

The authors declare that they have no known competing financial interests or personal relationships that could have appeared to influence the work reported in this paper.

References

  1. Ba, Z.; Sun, Y.; Li, D.; Han, S.; Lu, Y.; Sun, D. Full-process seismic simulation method for urban underground rail transit networks considering source-path-structure effects. Tunn. Undergr. Space Technol. 2025, 164, 106780. [Google Scholar] [CrossRef]
  2. Lai, Y.; Wang, Y.; Cheng, J.; Chen, X.; Liu, Q. Review of constraints and critical success factors of developing urban underground space. Undergr. Space 2023, 12, 137–155. [Google Scholar] [CrossRef]
  3. Yu, T.; Zhang, Y.; Yan, Z.; Zhu, H.; Cao, K. Methods for determining multiple hazards and response analysis of metro shield tunnels considering existing structural damage. Tunn. Undergr. Space Technol. 2025, 162, 106662. [Google Scholar] [CrossRef]
  4. Ou, X.; Liao, W.; Zheng, X.; Yang, G.; Osman, A.S. Large deformation problems arising from deep excavation in silt strata: A case study in Shenzhen, China. J. Rock Mech. Geotech. Eng. 2025, 17, 2576–2589. [Google Scholar] [CrossRef]
  5. Schwartzkopff, A.K.; Sainoki, A.; Bruning, T.; Karakus, M. A conceptual three-dimensional frictional model to predict the effect of the intermediate principal stress based on the Mohr-Coulomb and Hoek-Brown failure criteria. Int. J. Rock Mech. Min. Sci. 2023, 172, 105605. [Google Scholar] [CrossRef]
  6. Wang, D.; Peng, M.; Liu, L.; Xie, X.; Shi, Z.; Liang, Y.; Shen, J.; Wu, Q. Automatic GPR detection of grouting defects behind the tunnel shield segments based on wavelet coherence analysis combined with modified Res-RCNN. Case Stud. Constr. Mater. 2025, 22, e04245. [Google Scholar] [CrossRef]
  7. Ma, S.; Li, Z.; Fu, R. Experimental investigation on the mechanical properties and failure mechanism of key joints in a new-type prefabricated pile-wall composite structure for the open-cut tunnel. Eng. Fail. Anal. 2024, 165, 108771. [Google Scholar] [CrossRef]
  8. Wang, L.; Huang, Y.; Wang, Y.; Gu, B.; Li, B.; Fang, D. Comprehensive lifecycle safety risk assessment for construction robotics using T-S fault tree analysis and Bayesian network. Autom. Constr. 2025, 172, 106041. [Google Scholar] [CrossRef]
  9. Wang, L.; Zheng, G. Numerical analysis of underground displacements stirred by compaction grouting during tunnel construction. Tunn. Undergr. Space Technol. 2024, 152, 105931. [Google Scholar] [CrossRef]
  10. Zhou, X.-H.; Shen, S.-L.; Zhou, A. A novel data-driven approach for proactive risk assessment in shield tunnel construction. Transp. Geotech. 2025, 50, 101466. [Google Scholar] [CrossRef]
  11. Bao, X.; Wu, X.; Zhang, X.; Shen, J.; Chen, X.; Dang, P.; Cui, H. Mechanical behaviours of concrete segmented tunnel considering the effects of grouting voids—A 3D numerical simulation. Case Stud. Constr. Mater. 2025, 22, e04370. [Google Scholar] [CrossRef]
  12. Fall, M.; Gao, Z.; Ndiaye, B.C. Three-dimensional response of double anchored sheet pile walls subjected to excavation and construction sequence. Heliyon 2019, 5, e01348. [Google Scholar] [CrossRef] [PubMed]
  13. Li, T.; Gong, W.; Yang, X. Stability analysis of a non-circular tunnel face in soils characterized by modified Mohr-Coulomb yield criterion. Tunn. Undergr. Space Technol. 2021, 109, 103785. [Google Scholar] [CrossRef]
  14. Liu, C.; Zhu, D.; Cui, J.; Jing, L.; Huang, X. Investigation on synchronous grouting process during shield tunneling in coarse grained ground using CFD-DEM approach. Comput. Geotech. 2024, 170, 106308. [Google Scholar] [CrossRef]
  15. Nie, X.; Long, L.; Fu, Q.; Xiao, Q.; Xu, Q.; Chen, G.; Zhou, H. Experimental study on the effect of supplementary grouting on the mechanical properties of grout-deficient sleeve connections. Structures 2025, 77, 108986. [Google Scholar] [CrossRef]
  16. Zhu, H.; Xu, H.; Wei, G.; Yu, X.; Ma, D.; Tang, Y.; Ma, H. Evaluation of grouting effectiveness for Semi-Rigid pavement base layer cracks based on Time-Frequency domain signal characteristics of 3D GPR. Measurement 2024, 237, 115228. [Google Scholar] [CrossRef]
  17. Jiang, X.; Zhu, H.; Yan, Z.; Zhang, F.; Ye, F.; Li, P.; Zhang, X.; Dai, Z.; Bai, Y.; Huang, B. A state-of-art review on development and progress of backfill grouting materials for shield tunneling. Dev. Built Environ. 2023, 16, 100250. [Google Scholar] [CrossRef]
  18. Jin, H.; Wang, E.; Liu, X.; Xu, Z.; Wang, M.; Yuan, D. Micro-mechanism of shield-soil interaction during shield tunneling based on DEM-MBD coupling simulation. Comput. Geotech. 2025, 186, 107439. [Google Scholar] [CrossRef]
  19. Liu, S.; Peng, B.; Liu, J.; Yang, Y.N.; Xiong, M.R.; Wang, Z.B. Research on sealing technology of karst pipeline by dynamic water grouting. Constr. Build. Mater. 2025, 483, 141839. [Google Scholar] [CrossRef]
  20. Chen, H.; Lei, Y.; Xia, L.; Deveci, M.; Chen, Z.-S.; Liu, Y. Dynamic evaluation of the safety risk during shield construction near existing tunnels via a pair-copula Bayesian network. Appl. Soft Comput. 2025, 169, 112583. [Google Scholar] [CrossRef]
  21. Chen, H.; Shen, G.Q.; Feng, Z.; Yang, S. Safety risk assessment of shield tunneling under existing tunnels: A hybrid trapezoidal cloud model and Bayesian network approach. Tunn. Undergr. Space Technol. 2024, 152, 105936. [Google Scholar] [CrossRef]
  22. Wu, C.; Xiao, X.; Ma, S.; Yang, C. Mechanical performance and failure mode judgment criteria of grouted sleeve connectors considering large deformation and grouting compactness. Case Stud. Constr. Mater. 2024, 21, e03997. [Google Scholar] [CrossRef]
  23. Ma, M.; Yang, X.; Zhou, J.; Li, L.; Tian, J. Model tests and numerical simulations of deformation repair effect for operating shield tunnels under horizontal lateral grouting. Transp. Geotech. 2024, 47, 101277. [Google Scholar] [CrossRef]
  24. Dong, X.; Li, Z.; Cui, Z.; Zhou, C. Stability analysis of the pile-prestressed anchor composite structure based on failure mode. Eng. Fail. Anal. 2022, 137, 106223. [Google Scholar] [CrossRef]
  25. Kong, H.-Q.; Zhang, N. Risk assessment of water inrush accident during tunnel construction based on FAHP-I-TOPSIS. J. Clean. Prod. 2024, 449, 141744. [Google Scholar] [CrossRef]
  26. Koohathongsumrit, N.; Meethom, W. Risk analysis in underground tunnel construction with tunnel boring machines using the Best-Worst method and data envelopment analysis. Heliyon 2024, 10, e23486. [Google Scholar] [CrossRef]
  27. Zheng, X.; Yao, W.; Xu, Y.; Wang, N. Algorithms for Bayesian network modeling and reliability inference of complex multistate systems with common cause failure. Reliab. Eng. Syst. Saf. 2024, 241, 109663. [Google Scholar] [CrossRef]
  28. Fathallah, W.; Amor, N.B.; Leray, P. Approximate inference on optimized quantum Bayesian networks. Int. J. Approx. Reason. 2024, 175, 109307. [Google Scholar] [CrossRef]
  29. Guo, D.; Meng, F.; Wu, H.; Yang, X.; Chen, R. Risk assessment of shield construction adjacent to the existing shield tunnel based on improved nonlinear FAHP. Tunn. Undergr. Space Technol. 2025, 155, 106154. [Google Scholar] [CrossRef]
  30. Wang, M.; Li, S.; Zhou, H.; Peng, K.; Yuan, C. Visualization investigation of the large deformation and instability failure of shield tunnel using transparent soil models. Eng. Fail. Anal. 2024, 166, 108861. [Google Scholar] [CrossRef]
  31. Liu, W.; Shao, Y.; Li, C.; Li, C.; Jiang, Z. Development of a non-Gaussian copula Bayesian network for safety assessment of metro tunnel maintenance. Reliab. Eng. Syst. Saf. 2023, 238, 109423. [Google Scholar] [CrossRef]
  32. Medjadba, Y.; Drid, H.; Rahouti, M. Intrusion detection in Software-Defined Networking using hybrid Bayesian model averaging for reliable uncertainty quantification. Comput. Netw. 2025, 269, 111436. [Google Scholar] [CrossRef]
  33. Chen, H.; Shen, Q.; Li, T.; Liu, Y. Modeling the dynamic safety management of buildings adjacent to karst shield construction: An improved cloud Bayesian network. Adv. Eng. Inform. 2023, 58, 102192. [Google Scholar] [CrossRef]
  34. Wang, Z.Z.; Chen, C. Fuzzy comprehensive Bayesian network-based safety risk assessment for metro construction projects. Tunn. Undergr. Space Technol. 2017, 70, 330–342. [Google Scholar] [CrossRef]
  35. Xiang, W.; Zhou, W. Bayesian network model for predicting probability of third-party damage to underground pipelines and learning model parameters from incomplete datasets. Reliab. Eng. Syst. Saf. 2021, 205, 107262. [Google Scholar] [CrossRef]
  36. Fan, S.-Y.; Song, Z.-P.; Zhang, Y.-W.; Liu, N.-F. Case Study of the Effect of Rainfall Infiltration on a Tunnel Underlying the Roadbed Slope with Weak Inter-Layer. KSCE J. Civ. Eng. 2020, 24, 1607–1619. [Google Scholar] [CrossRef]
  37. Islam, M.S.; Iskander, M. Ground settlement caused by perpendicularly crossing twin tunnels, a parametric study. Tunn. Undergr. Space Technol. 2024, 146, 105657. [Google Scholar] [CrossRef]
  38. Alzabeebee, S.; Chapman, D.N.; Faramarzi, A. A comparative study of the response of buried pipes under static and moving loads. Transp. Geotech. 2018, 15, 39–46. [Google Scholar] [CrossRef]
  39. Shabani, M.J.; Shamsi, M.; Zakerinejad, M. Slope topographic impacts on the nonlinear seismic analysis of soil-foundation-structure interaction for similar MRF buildings. Soil Dyn. Earthq. Eng. 2022, 160, 107365. [Google Scholar] [CrossRef]
  40. Çetindemir, O. Nonlinear Constitutive Soil Models for the Soil–Structure Interaction Modeling Issues with Emphasis on Shallow Tunnels: A Review. Arab. J. Sci. Eng. 2023, 48, 12657–12691. [Google Scholar] [CrossRef]
  41. Embaby, K.; El Naggar, M.H.; El Sharnouby, M. Performance of large-span arched soil–steel structures under soil loading. Thin-Walled Struct. 2022, 172, 108884. [Google Scholar] [CrossRef]
  42. Islam, M.S.; Iskander, M. Three-dimensional numerical investigation of ground settlement caused by piggyback twin tunnels. Tunn. Undergr. Space Technol. 2023, 134, 104970. [Google Scholar] [CrossRef]
  43. Jong, S.C.; Ong, D.E.L. A novel Bayesian network approach for predicting soil-structure interactions induced by deep excavations. Tunn. Undergr. Space Technol. 2024, 152, 105865. [Google Scholar] [CrossRef]
  44. Shan, Y.; Wang, G.; Lin, W.; Zhou, S.; Rackwitz, F. Analytical solution of the evolution of railway subgrade settlement induced by shield tunnelling beneath considering soil stress release. Tunn. Undergr. Space Technol. 2025, 162, 106607. [Google Scholar] [CrossRef]
  45. Wang, R.; Yang, H.; Ni, P.; Zhao, C.; Guo, C.; Ma, H.; Dong, P.; Liang, H.; Tang, M. Model test and numerical simulation of a new prefabricated double-row piles retaining system in silty clay ground. Undergr. Space 2023, 13, 262–280. [Google Scholar] [CrossRef]
  46. Shi, X.; Zheng, L.; Rong, C.; Cheng, H.; Cai, H.; Li, T. Study on the Rules of Ground Settlement and Pipeline Deformation Considering the Combined Effects of Pipeline Damage Leakage and Shield Tunneling Construction. Transp. Geotech. 2024, 49, 101367. [Google Scholar] [CrossRef]
  47. Ye, Z.K.; Ai, Z.Y. A matrix-form complex variable method for multiple non-circular tunnels in layered media. Appl. Math. Model. 2024, 131, 570–595. [Google Scholar] [CrossRef]
  48. Donovan, D.; Burrage, K.; Burrage, P.; McCourt, T.A.; Thompson, B.; Yazici, E.Ş. Estimates of the coverage of parameter space by Latin Hypercube and Orthogonal Array-based sampling. Appl. Math. Model. 2018, 57, 553–564. [Google Scholar] [CrossRef]
  49. Su, J.; Wang, Y.; Niu, X.; Sha, S.; Yu, J. Prediction of ground surface settlement by shield tunneling using XGBoost and Bayesian Optimization. Eng. Appl. Artif. Intell. 2022, 114, 105020. [Google Scholar] [CrossRef]
  50. Yang, W.; Zhou, Q.; Shi, Z.; Tang, X.; Zhu, J.; Min, Q.; Yang, J. Modeling layered composite rock with excavated tunnels subjected to ground loads. Appl. Math. Model. 2024, 125, 29–47. [Google Scholar] [CrossRef]
  51. Xu, Z.; Zhou, S.; Zhang, C.; Yang, M.; Jiang, M. A Bayesian network model for suitability evaluation of underground space development in urban areas: The case of Changsha, China. J. Clean. Prod. 2023, 418, 138135. [Google Scholar] [CrossRef]
  52. Wu, Y.; Liu, J.; Deng, Y.; Liu, F.; Zhao, C.; Zhang, J.; Wei, X. Vertical bearing mechanisms of tip post-grouting piles under different grouting conditions: Experiment and theoretical model. Ocean. Eng. 2025, 337, 121926. [Google Scholar] [CrossRef]
  53. Xie, X.-C.; Ceccato, F.; Zhang, D.-M.; Zhou, M.-L.; Zhai, W.-Z.; Huang, Z.-K.; Zhang, X.-L. MPM-FEM based numerical analysis on responses of stratum and twin tunnels to water-soil gushing. Transp. Geotech. 2025, 50, 101471. [Google Scholar] [CrossRef]
  54. Xu, Y.; Zhang, Z.; Zhang, C.; Han, X.; Liu, T.; Zhang, X. Analysis of longitudinal deformation of existing rectangular pipe jacking tunnel caused by shield tunnel undercrossing. Tunn. Undergr. Space Technol. 2025, 161, 106532. [Google Scholar] [CrossRef]
Figure 1. The 2D finite element model for orthogonal experiment.
Figure 1. The 2D finite element model for orthogonal experiment.
Buildings 15 03027 g001
Figure 2. The 3D finite element model.
Figure 2. The 3D finite element model.
Buildings 15 03027 g002
Figure 3. Schematic of equivalent gap layer behind shield tail.
Figure 3. Schematic of equivalent gap layer behind shield tail.
Buildings 15 03027 g003
Figure 4. Effect curves of key factors on maximum ground settlement outside the pit.
Figure 4. Effect curves of key factors on maximum ground settlement outside the pit.
Buildings 15 03027 g004
Figure 5. Bayesian network model diagram.
Figure 5. Bayesian network model diagram.
Buildings 15 03027 g005
Figure 6. Bayesian network structure and node probability diagram (%).
Figure 6. Bayesian network structure and node probability diagram (%).
Buildings 15 03027 g006
Figure 7. Bayesian network structure and posterior node probability diagram (%).
Figure 7. Bayesian network structure and posterior node probability diagram (%).
Buildings 15 03027 g007
Figure 8. Schematic of grouting reinforcement zones around the tunnel.
Figure 8. Schematic of grouting reinforcement zones around the tunnel.
Buildings 15 03027 g008
Figure 9. Post-construction ground settlement curves with sidewall grouting.
Figure 9. Post-construction ground settlement curves with sidewall grouting.
Buildings 15 03027 g009
Figure 10. Reinforcement ratio and efficiency for tunnel sidewall grouting.
Figure 10. Reinforcement ratio and efficiency for tunnel sidewall grouting.
Buildings 15 03027 g010
Figure 11. Post-construction ground settlement curves with invert grouting.
Figure 11. Post-construction ground settlement curves with invert grouting.
Buildings 15 03027 g011
Figure 12. Reinforcement ratio and efficiency for tunnel invert grouting.
Figure 12. Reinforcement ratio and efficiency for tunnel invert grouting.
Buildings 15 03027 g012
Figure 13. Transverse ground settlement curves with crown grouting.
Figure 13. Transverse ground settlement curves with crown grouting.
Buildings 15 03027 g013
Figure 14. Reinforcement ratio and efficiency for tunnel crown grouting.
Figure 14. Reinforcement ratio and efficiency for tunnel crown grouting.
Buildings 15 03027 g014
Table 1. Comparison between 2D and 3D finite element model results.
Table 1. Comparison between 2D and 3D finite element model results.
Model/Deformation2D Simulation Result3D Simulation ResultError
Maximum ground surface settlement outside the excavation (mm)10.610.06%
Table 2. Geotechnical properties of soil layers.
Table 2. Geotechnical properties of soil layers.
Layer Number and Soil TypeUnit Weight γ
(kN/m)
Cohesion c (kPa)Internal Friction Angle
ϕk (°)
Compression Modulus E(1–2) (MPa)Poisson’s Ratio v
Layer 1 (Miscellaneous Fill)19.115153.00.37
Layer 2 (Silty Clay)2032187.50.32
Layer 3 (Silty Clay)19.530207.20.33
Layer 4 (Silt)20.6282410.50.31
Layer 5 (Silty Sand)21.6135120.29
Layer 6 (Silty Clay)20.3302780.32
Table 3. Assigned soil layer thicknesses in the numerical model.
Table 3. Assigned soil layer thicknesses in the numerical model.
Formation NameThickness of Soil Layer in the Model (m)
Layer 1 (Miscellaneous Fill)2
Layer 2 (Silty Clay)3
Layer 3 (Silty Clay)3
Layer 4 (Silt)5
Layer 5 (Silty Sand)10
Layer 6 (Silty Clay)17
Table 4. Material properties for structural elements.
Table 4. Material properties for structural elements.
Structural ElementsElastic Modulus E (MPa)Density ρ (kg/m3)Poisson’s Ratio μ
Shield shell2.1 × 1058 × 1030.30
Wall, pile, and tie beam3.15 × 1042.35 × 1030.25
Ground anchor2.0 × 1057.7 × 1030.2
Tunnel segment2.93 × 1042.35 × 1030.25
Table 5. Physical and mechanical parameters of grouting material in equivalent gap layers at different curing ages.
Table 5. Physical and mechanical parameters of grouting material in equivalent gap layers at different curing ages.
Grout Curing Age (d)Density (kg/m3)Poisson’s RatioElastic Modulus (MPa)Thickness (cm)
016000.45510
116600.42510
217000.355010
718000.2530010
2821000.240010
Table 6. Orthogonal test factors and levels.
Table 6. Orthogonal test factors and levels.
FactorsLevels
1234
Grouting pressure, P (kPa)300375450525
Elastic modulus of the grouting layer, Ea (MPa)E1.25 E1.5 E1.75 E
Cohesion of the soil above the tunnel, c (kPa)051015
Internal friction angle of the soil above the tunnel, φ (°)10152025
Table 7. Orthogonal test design and results.
Table 7. Orthogonal test design and results.
FactorsP (kPa)Ea (MPa)C (MPa)φ (°)Maximum Ground Settlement Outside the Excavation (mm)
Test 1300E01010.2
Test 23001.25 E5155.9
Test 33001.5 E10205.6
Test 43001.75 E15255.0
Test 5375E5205.0
Test 63751.25 E0258.5
Test 73751.5 E15104
Test 83751.75 E10153.7
Test 9450E10253.5
Test 104501.25 E15203.3
Test 114501.5 E0157.1
Test 124501.75 E5103
Test 13525E15152.9
Test 145251.25 E10102.6
Test 155251.5 E5252.7
Test 165251.75 E0206.6
Table 8. Range analysis of maximum ground settlement outside the pit (mm).
Table 8. Range analysis of maximum ground settlement outside the pit (mm).
LevelsPEacφ
Mean 16.6755.4008.1004.950
Mean 25.3005.0754.1504.900
Mean 34.2254.8503.8505.125
Mean 43.7004.5753.8004.925
Range (R)2.9750.8254.3000.225
Rank2314
Table 9. ANOVA of maximum ground settlement outside the pit (mm).
Table 9. ANOVA of maximum ground settlement outside the pit (mm).
FactorsDegrees of FreedomSum of Squares of Deviations from the MeanMean SquareF-Valuep-Value
P320.7356.91171382.330.000
Ea31.4650.488397.670.002
c352.37017.45673491.330.000
φ30.2500.04178.330.058
Error30.0150.005
Table 10. Risk sources and basic events of shield tunneling adjacent to diaphragm wall–pile–anchor-supported pit.
Table 10. Risk sources and basic events of shield tunneling adjacent to diaphragm wall–pile–anchor-supported pit.
Serial NumbersRisk SourceBasic Events
1Construction environmentClimatic conditions, stratigraphic conditions, and groundwater stability
2Construction schemeGeological investigation, shield tunneling design, and monitoring plan
3Construction technologyShield steering correction, reinforcement of wall–pile–anchor support, segment installation, and tail grouting
4Construction managementContractor experience, construction team management system, and emergency response plan
Table 11. Classification criteria for likelihood of risk occurrence.
Table 11. Classification criteria for likelihood of risk occurrence.
Risk LevelsLikelihoodProbability
IFrequent[0.1, 1]
IIProbable[0.01, 0.1)
IIIOccasional[0.001, 0.01)
IVRare[0.0001, 0.001)
VImpossible[0, 0.0001)
Table 12. Weight assignment for expert judgment.
Table 12. Weight assignment for expert judgment.
ClassificationDescriptionWeightNumber of Experts
IExperts (Category I)12
IIExperts (Category II)0.84
Table 13. Prior probabilities of basic events related to shield tunnel accidents.
Table 13. Prior probabilities of basic events related to shield tunnel accidents.
No.Basic EventsExperts (Category I)Experts (Category II)Prior Probability
123456
X11Climatic conditions0.0530.0460.040.080.050.070.056
X12Stratigraphic conditions0.1850.20.170.120.150.130.163
X13Groundwater stability0.10.130.140.120.110.140.123
X21Geological investigation0.030.040.050.0480.040.050.042
X22Shield tunneling design0.010.0120.0060.010.0060.0070.009
X23Monitoring plan0.0020.0030.0010.0030.0020.0030.002
X31Shield steering correction0.0550.0640.10.0750.080.0850.075
X32Reinforcement of wall–pile–anchor support0.090.10.10.120.130.10.106
X33Segment installation0.070.0680.0350.050.050.0450.055
X34Tail grouting0.0070.0050.0050.0080.0060.0070.006
X41Contractor experience0.0370.0430.0250.030.0350.030.034
X42Construction team management0.0450.0550.090.060.0850.060.065
X43Emergency response plan0.0020.0050.0030.0020.0010.0030.003
Table 14. Conditional probabilities of shield tunnel accident events.
Table 14. Conditional probabilities of shield tunnel accident events.
No.Basic EventsExperts (Category I)Experts (Category II)Conditional Probability
123456
X1Climatic conditions0.520.580.60.480.550.570.55
X2Stratigraphic conditions0.360.40.410.370.350.450.39
X3Groundwater stability0.360.40.30.450.350.30.36
X4Geological investigation0.440.50.450.330.350.430.42
X11Shield tunneling design0.180.160.20.110.150.160.16
X12Monitoring plan0.60.50.60.430.50.550.53
X13Shield steering correction0.520.50.450.540.60.450.51
X21Reinforcement of wall–pile–anchor support0.240.30.320.370.30.350.31
X22Segment installation0.330.350.350.450.370.330.36
X23Tail grouting0.150.190.20.270.250.220.21
X31Contractor experience0.200.220.150.220.30.230.22
X32Construction team management0.180.240.250.150.20.10.19
X33Emergency response plan0.550.50.540.480.550.60.54
X34Climatic conditions0.520.50.50.350.40.470.46
X41Stratigraphic conditions0.160.20.20.270.250.220.21
X42Groundwater stability0.450.40.440.390.50.320.42
X43Geological investigation0.210.20.250.230.30.20.23
Table 15. Conditional probability table of construction environment X1 (%).
Table 15. Conditional probability table of construction environment X1 (%).
X11X12X13X1 = SX1 = D
SSS1000
SSD4951
SDS4753
SDD2377
DSS8416
DSD4159
DDS3961
DDD1981
Table 16. Posterior probabilities of basic events.
Table 16. Posterior probabilities of basic events.
Event Risk LevelsBasic Events
IX12, X13, X31, X32, X33, X34, X42
IIX11, X21, X22, X41
IIIX23, X43
IV
V
Table 17. Mechanical parameters of grouted soil.
Table 17. Mechanical parameters of grouted soil.
Cement Contentγ (kN/m3) ϕ k ( ° ) E 50 r e f ( M P a ) E o e d r e f ( M P a ) E u r r e f ( M P a ) C (kN/m2)
15%17.851.2250.1175.1750.3447.6
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Lu, Y.; Zhu, B.; Qiu, H. Bayesian Network-Driven Risk Assessment and Reinforcement Strategy for Shield Tunnel Construction Adjacent to Wall–Pile–Anchor-Supported Foundation Pit. Buildings 2025, 15, 3027. https://doi.org/10.3390/buildings15173027

AMA Style

Lu Y, Zhu B, Qiu H. Bayesian Network-Driven Risk Assessment and Reinforcement Strategy for Shield Tunnel Construction Adjacent to Wall–Pile–Anchor-Supported Foundation Pit. Buildings. 2025; 15(17):3027. https://doi.org/10.3390/buildings15173027

Chicago/Turabian Style

Lu, Yuran, Bin Zhu, and Hongsheng Qiu. 2025. "Bayesian Network-Driven Risk Assessment and Reinforcement Strategy for Shield Tunnel Construction Adjacent to Wall–Pile–Anchor-Supported Foundation Pit" Buildings 15, no. 17: 3027. https://doi.org/10.3390/buildings15173027

APA Style

Lu, Y., Zhu, B., & Qiu, H. (2025). Bayesian Network-Driven Risk Assessment and Reinforcement Strategy for Shield Tunnel Construction Adjacent to Wall–Pile–Anchor-Supported Foundation Pit. Buildings, 15(17), 3027. https://doi.org/10.3390/buildings15173027

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop