A Fuzzy Unit Commitment Model for Enhancing Stability and Sustainability in Renewable Energy-Integrated Power Systems
Abstract
1. Introduction and Literature Review
2. Mathematical Model Formulation
2.1. Deterministic Unit Commitment Model (DUCM)
2.1.1. Notations
2.1.2. Decision Variables
2.1.3. Extension of Unit Commitment to Include Renewable Energy
- Power balance constraint:The total of power generation and transmission power must exceed the load demand in each zone and each time period.
- Generator limit constraint:This constraint shows the boundary of the operation for each conventional generator when it operates.
- Spinning reserve constraint:The spinning reserve constraint ensures that the power system maintains sufficient reserve capacity to respond to unexpected fluctuations in load or sudden generation outages during each scheduling period. This constraint establishes a direct relationship between the total scheduled generation and the required minimum reserve margin. Among the various approaches used to define reserve requirements, a widely accepted method is to base the reserve level on the capacity of the single largest generator in the system.In this study, the reserve requirement parameter, denoted as , is defined as the sum of the maximum capacities of the largest conventional generator and the largest renewable energy generator, specifically a solar photovoltaic (PV) system. This formulation provides a conservative estimate, ensuring that the system can withstand the simultaneous loss of significant generating units while maintaining operational reliability.
- Transportation limit constraint:The first transmission constraint is the limitation of the transmission line. The second constraint shows that the total transmission power into each zone must be less than or equal to the total production in that zone.
- Unit status constraint:The unit status constraint defines the relationship between startup, shutdown, and operational status across consecutive time periods. A startup occurs when a unit transitions from offline in the current period to online in the next period, resulting in a startup status value of one. If the unit remains in the same state or shuts down, the startup status is zero, as the objective function minimizes unnecessary startups. The shutdown status reflects the opposite transition, from online to offline, and is calculated based on the difference between the unit status and startup status over adjacent periods.
- Initial condition constraint:The initial condition constraint connects the unit’s final status from the previous day to its status, startup, and shutdown decisions in the first period of the current day. If the unit was online at the end of the previous day, the startup status for the first period is zero. Conversely, if the unit was offline, the shutdown status for the first period is zero.
- Ramp rate constraint:The ramp rate constraint is a limitation on increases and decreases in production in each generator calculated based on the difference between the current period and the next period.
- Minimum uptime/downtime constraint:The minimum time constraint is a limitation on the number of consecutive operations and shutdown time of each unit, which must be less than or equal to the minimum uptime and minimum downtime, respectively. The cumulative operation and shutdown time of the previous day are also considered by these constraints.
2.2. Mixed-Integer Linear Programming Formulation for Fuzzy Unit Commitment Model (FUCM)
- Model 1: Lower-Bound Model (case )
- Model 2: Upper-Bound Model (case )
- Model 3: Fuzzy Model
3. Case Study Analysis and Results
3.1. Validation on a Small-Scale Power System
Performance of Deterministic and Fuzzy Unit Commitment Solutions
3.2. Application to National Large-Scale Power System
3.2.1. Performance Evaluation for National Large-Scale Power System
3.2.2. Generation Scheduling and System Feasibility Assessment
4. Conclusions and Discussion
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Sundarajumpaka, P. Thailand Solar PV Policy Paper 1/2018. Technical Report, Deutsche Gesellschaft für Internationale Zusammenarbeit. 2018. Available online: http://www.thai-german-cooperation.info (accessed on 1 July 2021).
- Afzali, P.; Hosseini, S.A.; Peyghami, S. A Comprehensive Review on Uncertainty and Risk Modeling Techniques and Their Applications in Power Systems. Appl. Sci. 2024, 14, 12042. [Google Scholar] [CrossRef]
- Alqunun, K.; Guesmi, T.; Albaker, A.F.; Alturki, M.T. Stochastic Unit Commitment Problem, Incorporating Wind Power and an Energy Storage System. Sustainability 2020, 12, 10100. [Google Scholar] [CrossRef]
- Liu, J.; Wang, Z.; Chen, Y.; Zhu, J. Solving the Unit Commitment Problem with Improving Binary Particle Swarm Optimization. In Advances in Swarm Intelligence; Tan, Y., Shi, Y., Niu, B., Eds.; Lecture Notes in Computer Science; Springer: Cham, Switzerland, 2022; Volume 13344, pp. 185–193. [Google Scholar] [CrossRef]
- Muralikrishnan, N.; Jebaraj, L.; Rajan, C.C.A. A comprehensive review on evolutionary optimization techniques applied for unit commitment problem. IEEE Access 2020, 8, 132980–133014. [Google Scholar] [CrossRef]
- Takriti, S.; Birge, J.R.; Long, E. A stochastic model for the unit commitment problem. IEEE Trans. Power Syst. 1996, 11, 1497–1508. [Google Scholar] [CrossRef]
- Jokar, H.; Bahmani-Firouzi, B.; Alhelou, H.H.; Siano, P. Energy management considering large-scale energy storage and SCUC. IEEE Access 2022, 10, 123723–123735. [Google Scholar] [CrossRef]
- Hong, Y.Y.; Apolinario, G.F.; Lu, T.K.; Chu, C.C. Chance-constrained unit commitment with energy storage systems. Energy Rep. 2022, 8, 1067–1090. [Google Scholar] [CrossRef]
- Ruiz, P.; Philbrick, C.; Sauer, P. Wind power day-ahead uncertainty management through stochastic unit commitment policies. In Proceedings of the 2009 IEEE/PES Power Systems Conference and Exposition, Seattle, WA, USA, 15–18 March 2009; pp. 1–9. [Google Scholar] [CrossRef]
- Siahkali, H.; Vakilian, M. Stochastic unit commitment of wind farms integrated in power system. Electr. Power Syst. Res. 2010, 80, 1006–1017. [Google Scholar] [CrossRef]
- Wang, Q.; Wang, J.; Guan, Y. Stochastic unit commitment with uncertain demand response. IEEE Trans. Power Syst. 2012, 28, 562–563. [Google Scholar] [CrossRef]
- Kaewpasuk, S.; Intiyot, B.; Jeenanunta, C. Stochastic unit commitment model for power system with renewable energy. In Proceedings of the 2017 International Electrical Engineering Congress (iEECON), Pattaya, Thailand, 8–10 March 2017; pp. 1–4. [Google Scholar] [CrossRef]
- Doubleday, K.; Lara, J.D.; Hodge, B.-M. Stochastic unit commitment for high shares of solar PV: Enabling grid flexibility. Appl. Energy 2022, 321, 119337. [Google Scholar] [CrossRef]
- Zhu, X.; Yu, Z.; Liu, X. Security constrained unit commitment with extreme wind scenarios. J. Mod. Power Syst. Clean Energy 2020, 8, 464–472. [Google Scholar] [CrossRef]
- Mena, R.; Godoy, M.; Catalán, C.; Viveros, P.; Zio, E. Multi-objective stochastic unit commitment model considering wind power uncertainty. Int. J. Electr. Power Energy Syst. 2023, 152, 109214. [Google Scholar] [CrossRef]
- Zhang, Z.; Chen, Y.; Liu, X.; Wang, W. Two-stage robust security-constrained unit commitment model considering time autocorrelation of wind/load prediction error and outage contingency probability of units. IEEE Access 2019, 7, 25398–25408. [Google Scholar] [CrossRef]
- Pawar, R.; Dalsania, K.P.; Sircar, A.; Yadav, K.; Bist, N. Renewable Energy Hybridization: A Comprehensive Review of Integration Strategies for Efficient and Sustainable Power Generation. Clean Technol. Environ. Policy 2024, 26, 4041–4058. [Google Scholar] [CrossRef]
- Brown, D.B.; Smith, J.E. Unit Commitment Without Commitment: A Dynamic Programming Approach for Managing an Integrated Energy System Under Uncertainty. Oper. Res. 2025, 73, 1744–1766. [Google Scholar] [CrossRef]
- Medvedev, A.; Gruson, M.; Jans, R. A Two-Stage Stochastic Integrated Unit Commitment and Distribution Problem; Technical Report CIRRELT-2025-06, CIRRELT; 2025; Available online: https://www.cirrelt.ca/documentstravail/cirrelt-2025-06.pdf (accessed on 25 July 2025).
- Cheng, Y.; Zhang, J.; Al Shurafa, M.; Liu, D.; Zhao, Y.; Ding, C.; Niu, J. An Improved Multiple Adaptive Neuro Fuzzy Inference System Based on Genetic Algorithm for Energy Management System of Island Microgrid. Sci. Rep. 2025, 15, 17988. [Google Scholar] [CrossRef]
- Pan, J.; Liu, T. Optimal Scheduling for Unit Commitment with Electric Vehicles and Uncertainty of Renewable Energy Sources. Energy Rep. 2022, 8, 13023–13036. [Google Scholar] [CrossRef]
- Zimmermann, H.J. Applications of fuzzy set theory to mathematical programming. Inf. Sci. 1985, 36, 29–58. [Google Scholar] [CrossRef]
- Truong, H.; Jeenanunta, C. Fuzzy MILP for monthly unit commitment under price-based uncertainty. Electr. Power Syst. Res. 2022, 209, 107963. [Google Scholar] [CrossRef]
- Venkatesh, B.; Bathaee, R.; Chang, L. Fuzzy MILP unit commitment incorporating wind generators. IEEE Trans. Power Syst. 2008, 23, 1738–1746. [Google Scholar] [CrossRef]
- Siahkali, H. Operation planning of wind farms with pumped storage plants based on interval type-2 fuzzy modeling of uncertainties. J. Oper. Autom. Power Eng. 2020, 8, 182–194. [Google Scholar] [CrossRef]
- Amid, A.; Ghodsypour, S.; O’Brien, C. Fuzzy multiobjective linear model for supplier selection in a supply chain. Int. J. Prod. Econ. 2006, 104, 394–407. [Google Scholar] [CrossRef]
- Taghipourian, F.; Mahdavi, I.; Mahdavi-Amiri, N.; Makui, A. A fuzzy programming approach for dynamic virtual hub location problem. Appl. Math. Model. 2012, 36, 3257–3270. [Google Scholar] [CrossRef]
- Nasab, M.; Zand, M.; Padmanaban, S.; Bhaskar, M.S.; Guerrero, J.M. A robust optimization framework for day-ahead unit commitment problem considering RES and PSH. Comput. Electr. Eng. 2022, 100, 107846. [Google Scholar] [CrossRef]
- Naval, N.; Yusta, J.M.; Sánchez, R.; Sebastián, F. Optimal Scheduling and Management of Pumped Hydro Storage Integrated with Grid-Connected Renewable Power Plants. J. Energy Storage 2023, 73, 108993. [Google Scholar] [CrossRef]
- Wu, T.; Zhang, Y.-J.A.; Wang, S. Security-constrained unit commitment with uncertain wind power and battery energy storage systems using deep learning. IEEE Trans. Sustain. Energy 2022, 13, 231–240. [Google Scholar] [CrossRef]
- Li, J.; Wang, S.; Ye, L.; Fang, J. Coordinated dispatch of pumped-storage and battery-storage with renewable integration. Prot. Control Mod. Power Syst. 2018, 3, 2. [Google Scholar] [CrossRef]
- Ny, D.; Jeenanunta, C. Optimizing Power System Reliability and Carbon Emissions With a Fuzzy Unit Commitment Model Incorporating Renewable Energy, Load Forecast Errors, EV Charging, and Energy Storage System. IEEE Access 2024, 12, 164412–164426. [Google Scholar] [CrossRef]
- Ny, D.; Jeenanunta, C.; Takada, J.I.; Chanyachatchawan, S.; Kaewpasuk, S.; Intiyot, B.; Dumrongsiri, A. Fuzzy Mixed Integer Linear Programming for Daily Unit Commitment with Pumped Storage Hydropower, EV Charging Demand, and Solar PV Supply. In Proceedings of the 2023 IEEE PES 15th Asia-Pacific Power and Energy Engineering Conference (APPEEC), Chiang Mai, Thailand, 6–9 December 2023; pp. 1–6. [Google Scholar] [CrossRef]
- Trojani, A.G.; Baigi, J.M.; Moghaddam, M.S. Stochastic Security-constrained Unit Commitment Considering Electric Vehicles, Energy Storage Systems, and Flexible Loads with Renewable Energy Resources. J. Mod. Power Syst. Clean Energy 2023, 11, 1405–1414. [Google Scholar] [CrossRef]
- Hashem, A.; ALLayith, A.A.; Hussein, L.A.; Zaidan, D.T. Quantifying Uncertainty in Predicting Renewable Energy Time Series: Machine Learning Applications. In Proceedings of the 2024 International Conference on IoT, Communication and Automation Technology (ICICAT), Gorakhpur, India, 23–24 November 2024. [Google Scholar] [CrossRef]
- Kaewpasuk, S. Stochastic and Fuzzy Unit Commitment Models to Accommodate Solar Energy and Electric Vehicle Charging Penetration. Ph.D. Thesis, Chulalongkorn University, Bangkok, Thailand, 2024. [Google Scholar] [CrossRef]
Name | Type | Initial Product (MW) | Initial Uptime (Periods) | Initial Down Time (Periods) | Minimum Uptime (Periods) | Minimum Down Time (Periods) | Minimum Generation (MW) | Maximum Generation (MW) | Ramp Rate Uptime (MW/minute) | Ramp Rate Downtime (MW/minute) | Start Cost (THB) | Fuel Cost (THB) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
BLCP-T1 | Thermal | 650 | 24 | 0 | 12 | 12 | 161 | 673.25 | 450 | 450 | 1,484,255 | 137.9183 |
BLCP-T2 | Thermal | 650 | 24 | 0 | 12 | 12 | 161 | 673.25 | 450 | 450 | 1,484,255 | 137.9183 |
BPK-T1 | Thermal | 300 | 24 | 0 | 12 | 12 | 300 | 526.5 | 150 | 150 | 627,676 | 406.6576 |
BPK-T2 | Thermal | 300 | 24 | 0 | 12 | 12 | 300 | 526.5 | 150 | 150 | 627,676 | 406.6576 |
BPK-T3 | Thermal | 300 | 24 | 0 | 12 | 12 | 300 | 576 | 150 | 150 | 627,676 | 406.6576 |
BPK-T4 | Thermal | 0 | 0 | 24 | 12 | 12 | 300 | 576 | 150 | 150 | 627,676 | 406.6576 |
RB-T1 | Thermal | 300 | 24 | 0 | 12 | 12 | 300 | 685 | 1110 | 1110 | 627,676 | 424.3366 |
RB-T2 | Thermal | 0 | 0 | 24 | 12 | 12 | 300 | 685 | 1110 | 1110 | 627,676 | 424.3366 |
KA-T1 | Thermal | 0 | 0 | 24 | 12 | 12 | 145 | 315 | 204 | 204 | 627,676 | 440.6814 |
KN-T1 | Thermal | 70 | 24 | 0 | 12 | 12 | 50 | 75 | 40.5 | 25.5 | 627,676 | 186.6475 |
KN-T2 | Thermal | 0 | 0 | 24 | 12 | 12 | 60 | 75 | 40.5 | 24.3 | 627,676 | 186.6475 |
MM-T4 | Thermal | 140 | 24 | 0 | 6 | 6 | 90 | 150 | 60 | 60 | 627,676 | 51.16874 |
MM-T5 | Thermal | 140 | 24 | 0 | 6 | 6 | 90 | 150 | 60 | 60 | 627,676 | 51.16874 |
MM-T6 | Thermal | 140 | 24 | 0 | 6 | 6 | 90 | 150 | 60 | 60 | 627,676 | 51.16874 |
MM-T7 | Thermal | 140 | 24 | 0 | 6 | 6 | 90 | 150 | 60 | 60 | 627,676 | 51.16874 |
MM-T8 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
MM-T9 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
MM-T10 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
MM-T11 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
MM-T12 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
MM-T13 | Thermal | 285 | 24 | 0 | 6 | 6 | 150 | 300 | 75 | 75 | 627,676 | 51.16874 |
SB-T1 | GasTur | 0 | 0 | 24 | 12 | 12 | 110 | 186 | 90 | 90 | 627,676 | 409.4488 |
SB-T2 | GasTur | 0 | 0 | 24 | 12 | 12 | 110 | 186 | 90 | 90 | 627,676 | 409.4488 |
SB-T3 | GasTur | 0 | 0 | 24 | 12 | 12 | 170 | 265 | 300 | 300 | 627,676 | 409.4488 |
SB-T4 | GasTur | 0 | 0 | 24 | 12 | 12 | 170 | 265 | 300 | 300 | 627,676 | 409.4488 |
SB-T5 | GasTur | 0 | 0 | 24 | 12 | 12 | 170 | 294 | 300 | 300 | 627,676 | 409.4488 |
NPO-C11 | GasCom | 80 | 24 | 0 | 6 | 6 | 70 | 124.96 | 240 | 240 | 3785 | 272.2742 |
NPO-C12 | GasCom | 80 | 24 | 0 | 6 | 6 | 70 | 123.71 | 240 | 240 | 3785 | 272.2742 |
NPO-C21 | GasCom | 80 | 24 | 0 | 6 | 6 | 70 | 120.73 | 240 | 240 | 3785 | 272.2742 |
NPO-C22 | GasCom | 80 | 24 | 0 | 6 | 6 | 25 | 123.98 | 240 | 240 | 3785 | 272.2742 |
Time Period Starting Time | Solar Min () | Solar Max () | Time Period Starting Time | Solar Min ( | Solar Max () | Time Period Starting Time | Solar Min () | Solar Max () |
---|---|---|---|---|---|---|---|---|
12:00 AM | 0 | 0 | 8:00 AM | 30.84 | 246.69 | 4:00 PM | 25.46 | 203.65 |
12:30 AM | 0 | 0 | 8:30 AM | 40.23 | 321.86 | 4:30 PM | 16.11 | 128.88 |
1:00 AM | 0 | 0 | 9:00 AM | 48.55 | 388.38 | 5:00 PM | 7.96 | 63.70 |
1:30 AM | 0 | 0 | 9:30 AM | 55.45 | 443.63 | 5:30 PM | 2.63 | 21.04 |
2:00 AM | 0 | 0 | 10:00 AM | 61.34 | 490.74 | 6:00 PM | 0.40 | 3.20 |
2:30 AM | 0 | 0 | 10:30 AM | 65.13 | 521.03 | 6:30 PM | 0.01 | 0.04 |
3:00 AM | 0 | 0 | 11:00 AM | 67.41 | 539.24 | 7:00 PM | 0 | 0 |
3:30 AM | 0 | 0 | 11:30 AM | 68.41 | 547.24 | 7:30 PM | 0 | 0 |
4:00 AM | 0 | 0 | 12:00 PM | 68.24 | 545.95 | 8:00 PM | 0 | 0 |
4:30 AM | 0 | 0 | 12:30 PM | 66.96 | 535.70 | 8:30 PM | 0 | 0 |
5:00 AM | 0 | 0 | 1:00 PM | 64.84 | 518.75 | 9:00 PM | 0 | 0 |
5:30 AM | 0.02 | 0.18 | 1:30 PM | 61.31 | 490.48 | 9:30 PM | 0 | 0 |
6:00 AM | 0.73 | 5.85 | 2:00 PM | 56.13 | 449.01 | 10:00 PM | 0 | 0 |
6:30 AM | 4.48 | 35.82 | 2:30 PM | 50.00 | 400.01 | 10:30 PM | 0 | 0 |
7:00 AM | 11.79 | 94.29 | 3:00 PM | 42.79 | 342.29 | 11:00 PM | 0 | 0 |
7:30 AM | 21.14 | 169.14 | 3:30 PM | 34.33 | 274.64 | 11:30 PM | 0 | 0 |
Load Demand Groups | DUCM (Upper-Bound Model) | DUCM (Lower-Bound Model) | DUCM with the Mean of Solar Output | FUCM |
---|---|---|---|---|
Winter weekday | 366,788,709.45 | 354,004,140.76 | 359,659,033.45 | 359,659,033.45 |
Winter weekend | 223,423,738.00 | 213,470,077.13 | 219,100,769.50 | 217,198,191.26 |
Summer weekday | 331,819,030.25 | 319,124,664.08 | 325,389,411.83 | 325,464,420.50 |
Summer weekend | 284,347,963.06 | 272,899,916.30 | 278,078,298.70 | 278,285,308.57 |
Rainy weekday | 281,868,755.61 | 270,306,696.95 | 275,931,547.87 | 275,849,996.13 |
Rainy weekend | 273,071,257.34 | 261,078,788.62 | 266,367,439.64 | 266,706,435.12 |
Long Holidays | 75,496,148.51 | 71,910,515.25 | 73,815,916.13 | 73,572,939.98 |
Load Demand Groups | The Number of Lacking Scenarios | Total Number of Missing Periods | Average Lack Percentage | Maximum Lack Percentage | ||||
---|---|---|---|---|---|---|---|---|
DUCM | FUCM | DUCM | FUCM | DUCM | FUCM | DUCM | FUCM | |
Winter weekday s | 17 | 17 | 17 | 17 | 0.45% | 0.45% | 1.1% | 1.1% |
Winter weekend f | 0 | 21 | 0 | 21 | 0% | 0.51% | 0.5% | 1.38% |
Summer weekday d | 82 | 44 | 147 | 48 | 0.6% | 0.45% | 2.43% | 1.17% |
Summer weekend d | 13 | 7 | 13 | 7 | 0.36% | 0.24% | 1.38% | 0.62% |
Rainy weekday f | 6 | 4 | 6 | 4 | 0.59% | 1.27% | 2.33% | 1.80% |
Rainy weekend d | 2 | 9 | 2 | 9 | 1.64% | 0.77% | 2.42% | 2.80% |
Long holidays f | 93 | 92 | 248 | 247 | 1.09% | 0.8% | 4.26% | 4.04% |
Demand Groups | DUCM Upper Bound | DUCM Lower Bound | DUCM with Mean Solar Power Output | FUCM |
---|---|---|---|---|
Winter weekday | 988,393,514.73 | 972,570,613.41 | 977,310,614.65 | 979,219,219.00 |
Winter weekend | 827,045,401.66 | 810,586,800.33 | 816,585,997.99 | 821,092,464.06 |
Summer weekday | 1,058,328,162.88 | 1,039,452,661.02 | 1,045,271,246.00 | 1,047,922,497.98 |
Summer weekend | 899,683,085.82 | 884,986,068.41 | 889,207,314.70 | 892,447,492.76 |
Rainy weekday | 877,186,680.84 | 862,265,287.64 | 867,423,700.54 | 868,118,138.84 |
Rainy weekend | 1,006,050,776.65 | 985,791,282.47 | 992,639,130.93 | 1,048,041,623.59 |
Long Holidays | 508,277,718.52 | 507,931,149.07 | 507,942,510.09 | 507,517,650.60 |
Load Demand Groups | DUCM Upper Bound | DUCM Lower Bound | DUCM with Mean Solar Power Output | FUCM | ||||
---|---|---|---|---|---|---|---|---|
Avg | SD | Avg | SD | Avg | SD | Avg | SD | |
Winter weekday | 182 | 15 | 165 | 20 | 175 | 23 | 2668 | 73 |
Winter weekend | 111 | 21 | 98 | 18 | 104 | 17 | 3009 | 50 |
Summer weekday | 92 | 12 | 87 | 15 | 91 | 21 | 842 | 47 |
Summer weekend | 98 | 18 | 102 | 10 | 104 | 25 | 1844 | 71 |
Rainy weekday | 57 | 16 | 64 | 22 | 53 | 19 | 2990 | 57 |
Rainy weekend | 62 | 20 | 70 | 13 | 65 | 18 | 1810 | 72 |
Long holidays | 55 | 14 | 52 | 11 | 49 | 14 | 603 | 69 |
Load Demand Groups | Number of Lacking Scenarios | Number of Missing Periods | ||||
DUCM * | FUCM | Percent Improvement | DUCM * | FUCM | Percent Improvement | |
Winter weekday | 39 | 59 | −51.28% | 42 | 87 | −107.14% |
Winter weekend | 34 | 13 | 61.76% | 36 | 15 | 58.33% |
Summer weekday | 44 | 29 | 34.09% | 50 | 34 | 32.00% |
Summer weekend | 64 | 36 | 43.75% | 92 | 46 | 50.00% |
Rainy weekday | 46 | 41 | 10.87% | 62 | 51 | 17.74% |
Rainy weekend | 67 | 42 | 37.31% | 100 | 52 | 48.00% |
Long holidays | 0 | 0 | 0.00% | 0 | 0 | 0.00% |
Load Demand Groups | Average Lack Percentage | Maximum Lack Percentage | ||||
DUCM * | FUCM | Percent Improvement | DUCM * | FUCM | Percent Improvement | |
Winter weekday | 0.87% | 0.93% | −6.90% | 2.52% | 3.54% | −40.48% |
Winter weekend | 0.94% | 1.02% | −8.51% | 3.03% | 2.90% | 4.29% |
Summer weekday | 0.66% | 0.48% | 27.27% | 1.69% | 1.91% | −13.02% |
Summer weekend | 0.98% | 0.90% | 8.16% | 3.51% | 3.09% | 11.97% |
Rainy weekday | 1.19% | 0.89% | 25.21% | 4.01% | 2.99% | 25.44% |
Rainy weekend | 0.91% | 0.86% | 5.49% | 3.32% | 2.71% | 18.37% |
Long holidays | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Kaewpasuk, S.; Intiyot, B.; Jeenanunta, C. A Fuzzy Unit Commitment Model for Enhancing Stability and Sustainability in Renewable Energy-Integrated Power Systems. Sustainability 2025, 17, 6800. https://doi.org/10.3390/su17156800
Kaewpasuk S, Intiyot B, Jeenanunta C. A Fuzzy Unit Commitment Model for Enhancing Stability and Sustainability in Renewable Energy-Integrated Power Systems. Sustainability. 2025; 17(15):6800. https://doi.org/10.3390/su17156800
Chicago/Turabian StyleKaewpasuk, Sukita, Boonyarit Intiyot, and Chawalit Jeenanunta. 2025. "A Fuzzy Unit Commitment Model for Enhancing Stability and Sustainability in Renewable Energy-Integrated Power Systems" Sustainability 17, no. 15: 6800. https://doi.org/10.3390/su17156800
APA StyleKaewpasuk, S., Intiyot, B., & Jeenanunta, C. (2025). A Fuzzy Unit Commitment Model for Enhancing Stability and Sustainability in Renewable Energy-Integrated Power Systems. Sustainability, 17(15), 6800. https://doi.org/10.3390/su17156800