Next Article in Journal
Historical Ecology: A Robust Bridge between Archaeology and Ecology
Next Article in Special Issue
Intelligent Identification of the Line-Transformer Relationship in Distribution Networks Based on GAN Processing Unbalanced Data
Previous Article in Journal
Assessing the Static and Dynamic Efficiency of Scientific Research of HEIs China: Three Stage DEA–Malmquist Index Approach
Previous Article in Special Issue
Improved Adaptive Hamiltonian Control Law for Constant Power Load Stability Issue in DC Microgrid: Case Study for Multiphase Interleaved Fuel Cell Boost Converter
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

D-distance Risk Factor for Transmission Line Maintenance Management and Cost Analysis

by
Waraporn Luejai
1,
Thanapong Suwanasri
1,* and
Cattareeya Suwanasri
2
1
Electrical Power and Energy Engineering (EPE), The Sirindhorn International Thai-German Graduate School of Engineering (TGGS), King Mongkut’s University of Technology North Bangkok (KMUTNB), Bangkok 10800, Thailand
2
Department of Electrical and Computer Engineering, Faculty of Engineering, King Mongkut’s University of Technology North Bangkok (KMUTNB), Bangkok 10800, Thailand
*
Author to whom correspondence should be addressed.
Sustainability 2021, 13(15), 8208; https://doi.org/10.3390/su13158208
Submission received: 26 June 2021 / Revised: 16 July 2021 / Accepted: 19 July 2021 / Published: 22 July 2021
(This article belongs to the Special Issue Advances in Sustainable Electrical Engineering)

Abstract

:
In this paper, a D-distance risk factor was proposed to prioritize high-voltage transmission lines from high to low risk in transmission line maintenance and renovation management. Various conditions and importance assessment criteria together with the weighting and scoring method were proposed to calculate both the renovation and importance indices of transmission lines. The scores of different test methods and visual inspection were differentiated from zero to five as end-of-life to very good condition to evaluate the condition of the line and its components. Additionally, the scores of different importance criteria were modified to assess the line importance from low to high importance. Moreover, the analytic hierarchy process was applied to determine the important weight of all test methods and importance criteria, which were evaluated by utility experts. The renovation and importance indices were combined in a risk matrix to finally determine the risk of the line by using the D-distance technique. Later, the risk of every transmission line was plotted in a risk matrix to prioritize and manage maintenance tasks. Finally, a maintenance cost was analyzed by applying the D-distance risk factor and compared with the replacement cost of a new transmission line for maintenance planning and cost minimization. Twenty out of 115, 230 and 500 kV transmission lines fleet in Thailand were practically analyzed with actual data. The results were realistic to feasibly implement in a transmission system for sustainable management.

1. Introduction

Nowadays, thirty-five percent of high-voltage transmission lines (HVTLs) in Thailand and several worldwide are aged and mostly more than 30 years old. Ageing and deterioration as well as harsh environmental conditions and electrical stress on HVTL components cause unexpected failures and supply interruption leading to system reliability problems [1,2,3,4]. Consequently, there is a concrete requirement to effectively assess HVTL conditions to manage the reparation, replacement, or renovation tasks of transmission lines as well as to manage operational risks to improve the system operating performance and reliability [5,6,7]. To reach this goal, different approaches were proposed to cope with the risk assessment of HVTLs and manage maintenance tasks [7,8,9,10,11,12]. In addition, some risk factors were also intensively investigated for condition assessment and risk management [13,14,15]. Based on the acquired condition and risk, different maintenance strategies were proposed for effective HVTL maintenance management [16,17,18,19]. Moreover, economic crisis has forced the power supply industry to maintain acceptable power quality and reliability under the minimum cost of operation and maintenance [20,21]. Therefore, an asset management strategy of HVTLs in Thailand is proposed in this paper to effectively cope with maintenance management and investment planning problems in the country.
According to the critical components in HVTLs discussed in [22,23,24], the major components of 115, 230 and 500 kV transmission lines in Thailand were practically divided into eight major groups consisting of conductor, conductor accessory, insulator, steel structure, foundation, lighting protection, tower accessory and right of way, as shown in Table 1. Sub-components of each major group were also clarified according to transmission utility maintenance tasks and inspection strategies during on-site testing and visual inspection. The major components with their renovation indices, as a percentage of conductor (%CRI), conductor accessory (%CARI), insulator (%IRI), steel structure (%SSRI), foundation (%FRI), lighting protection (%LPRI), tower accessory (%TARI) and right of way (%RWRI), are illustrated in Figure 1. The risk of HVTLs was assessed by considering two aspects. The first is the overhead line condition evaluated in the actual system based on their historical test data and presented in forms of renovation index. The second aspect is to access the importance of the overhead line to the electrical network, named as the importance index. For renovation index calculation, various testing methods [23,24,25,26,27] together with practical testing experience and visual inspection of a Thailand’s transmission utility [28] were determined as methods for condition assessment with a comprehensive, detailed clarification of aging and degradation characteristics and the scoring of degradation levels as basic input for the renovation index calculation. For importance index determination, the significant impact factors encountered during transmission system operation were considered, such as the percentage of line loading (MVA), system usage, operating voltage level (kV), contingency of HVTL, statistical failure, age of HVTL, as well as pollution, public image, and human impact in various locations along the HVTL were thoroughly considered. Some significant criteria were mentioned in [29,30,31]. The weighting and scoring method (WSM) was applied in this research to calculate both renovation indices of sub-components, components and the overall transmission line as well as for the importance index as it is a simple, clear and transparent method in any calculating steps. The analytical hierarchy process (AHP) method [32,33,34] was applied to identify the utility-consensus weight of any sub-components, components, testing methods and importance criteria for HVTL assessment.
The risk assessment procedure with the D-distance risk factor was proposed and is illustrated in Figure 2. The steps for the condition and importance evaluating method and equations are also expressed. After the evaluation, both the line renovation index (%LRI) and importance index (%IMI) were coordinated and plotted in a risk matrix in Figure 2, which was classified into nine groups. The D-distance risk factor was determined by using a proposed D-distance method to measure the risk. Finally, transmission utility could make an appropriate decision on an HVTL maintenance strategy, renovation, or new investment for replacement planning.

2. D-distance Risk Factor

In Figure 3, the risk was calculated from %LRI and %IMI by coordinating them in the risk matrix. Points x1 and x2 as well as y1 and y2 identified a boundary of low, moderate, and high levels in the renovation and importance indices.
The ranges for x1, x2, y1 and y2 could be adjusted by the utility depending on the experiences and historical data. The risk of HVTL was identified by using distance “d”, named “D-distance risk factor”, measured from the point coordinated by %LRI and %IMI perpendicular to a 45° line, as illustrated in Figure 3. The angles θ1 and θ2 of 45° mean that the condition or renovation requirement and importance of HVTLs play equal significance for this utility. The “d” distance was calculated by using (1) and (2).
Figure 3. Risk matrix with D-distance risk factor “d”.
Figure 3. Risk matrix with D-distance risk factor “d”.
Sustainability 13 08208 g003
d = ( d 1 ) + ( d 2 ) d m a x
d = ( % L R I × s i n θ 1 ) + ( % I M I × s i n θ 2 ) d m a x × 100
where d is the perpendicular distance from %LRI to 45° line, d1 is the perpendicular distance from %LRI to 45° line, d2 is the perpendicular distance from %IMI to 45° line, dmax is the maximum D-distance in the risk matrix, x is the value of %LRI as a percentage line renovation index, y is the value of %IMI as a percentage line importance index, θ1 is the angle between the y-axis and 45° line and θ2 is the angle between the x-axis and 45° line.
In Figure 3, there are nine clusters of risk in the risk matrix from the lowest risk in cluster 1 represented by the green color to the highest risk in cluster 9 represented by the red color. The renovation index, importance index, overall risk and required maintenance task for each cluster are detailed as follows.
In cluster 1, equipment has a good condition with low importance. The corrective maintenance strategy should be applied with this minimum risk cluster. The damage could be corrected when equipment was broken. The visual inspection and corrective maintenance (CM) by routine inspection was introduced.
In cluster 2, equipment has a good condition with moderate importance. Time-based maintenance (TBM) based on a planning schedule should be applied.
In cluster 3, equipment has a good condition with high importance. The TBM with condition-based maintenance (CBM) should be applied. Condition monitoring should probably be considered based on cost analysis.
In cluster 4, equipment has a moderate condition with low importance. The normal maintenance or CM could be applied.
In cluster 5, equipment has a moderate condition with moderate importance. Then, preventive maintenance (PM) was suggested. However, if the system is working properly, regular maintenance or TBM could be applied.
In cluster 6, equipment has a moderate condition with high importance. The CBM is strongly recommended to trace the change in condition or renovation requirement, and the proper remedy could be executed in time.
In cluster 7, equipment has a poor condition with low importance; then, repairing or renovation when fault without blackout was requested.
In cluster 8, equipment has a poor condition with moderate importance; then, intensive maintenance, repair or refurbishment or renovation should be carried out based on the economic suitability or available budget or repair, renovation, or refurbishment according to economic consideration.
In cluster 9, equipment encounters the worst condition with the highest importance leading to the highest risk. Then, the utility must immediately consider a short-term repair, renovation, or refurbishment.

3. Condition Assessment

In Figure 4, various testing methods and visual inspection techniques for renovation index assessment of HVTL components are proposed.
The application of WSM was used to calculate the renovation index. The WSM method considered a score representing the actual condition and weight indicating importance of considered components and criteria, i.e., score of the testing method, was categorized into six levels, namely, “0” for very good, “1” for good, “2” for satisfy, “3” for moderate, “4” for degradation and “5” for reaching the end-of-life condition. The weight of testing method was assigned by the AHP method. The percentage renovation index of sub-component (%SRI) was determined by using (3).
% S R I i = i = 1 M ( S i × W i ) i = 1 M ( S m a x , i × W i ) × 100
where i is the index of the sub-component, M is the total number of testing methods of the sub-component, Si is the score of each testing method, Smax,i is the maximum score of each testing method and Wi is the weight of each testing method.
Next, the renovation index of the component (%RI) was determined by using (4). For example, to determine %CARI, the percentage renovation index of five sub-components in the conductor accessory group, namely, spacer, damper, joint, dead end and PGC, should be previously calculated in advance. Thereafter, %CRI, %IRI, %CARI, %FRI, %SSRI, %LPRI and %RWRI were finally calculated in this step.
% R I j = j = 1 N ( % S R I j × W j ) j = 1 N ( % S R I m a x , j × W j ) × 100
where j is the index of the component, N is the total number of sub-components in each component, %SRIj is the percentage renovation index of each sub-component, %SRImax,j is the maximum percentage renovation index of each sub-component and Wj is the weight of each sub-component.
Figure 4. Structure for condition assessment of HVTL procedure.
Figure 4. Structure for condition assessment of HVTL procedure.
Sustainability 13 08208 g004
Then, the tower renovation index (%TRI) was determined by using (5).
% T R I k = k = 1 P ( % R I k × W k ) k = 1 P ( % R I m a x , k × W k ) × 100
where k is the index of the tower, P is the total number of components in each tower, %RIk is the percentage renovation index of each component, %RImax,k is the maximum percentage renovation index of each component and Wk is the weight of each component.
Finally, the transmission line renovation index (%LRI) was determined by using (6). The average renovation index of all components was applied in this step.
% L R I l = l = 1 P ( % R I a v g , l × W l ) l = 1 P ( % R I m a x , l × W l ) × 100
where l is the index of the line, P is the total number of components of each tower, %RIavg is the average percentage renovation index of each component, %RImax is the maximum percentage renovation index of each component and Wl is the weight of each component.

4. Importance Assessment

The importance criteria are presented and shown in Table 2, consisting of the percentage of line loading (MVA), system usage, voltage level (kV), contingency analysis, statically failure record, age, public image, pollution, and human impact. The determination of assigned scores and weights of all criteria are presented in Table 2. Line loading considered the maximum percentage of the highest power flow compared to the MVA rating of the line. The higher the line loading percentage, the greater the expected impact on customers in the case of line outage. System usage was also important regarding the type of usage, i.e., connection to power plant, tie transmission line, rapid load shedding scheme and radial or loop line, which could cause a severe impact on the electrical system. The voltage level was considered as it implied the power transfer capability of such transmission line in an electrical transmission system, i.e., at the 500 kV level, the HVTL would have more power transfer capability and a greater impact on the system than the 115 kV line when fault occurred. Contingency related to the redundancy of the HVTL affected the system availability and reliability of the electrical supply system. Moreover, the age of the transmission line could reflect the invisible deterioration, which could subsequently cause a higher probability of power outage. Age could imply an old design and obsolete technical specifications or lower performance for current operating conditions. The importance index (%IMI) was calculated by using (7). Similarly, the WSM was applied in the calculation.
% I M I m = m = 1 Q ( S m × % W m ) S m a x , m × m = 1 Q ( % W m ) × 100
where m is the index of importance, Q is the total number of importance criteria, Sm is the score of each importance criterion, Smax,m is the maximum score of each importance criterion and Wm is the weight of each importance criterion.
AHP [32,33] is a multi-criteria decision-making method. It was applied to determine importance the weight of each testing method, assessment criterion, component, and sub-component to avoid conflict among people as experts working with the transmission system in the utility. These experts have intensive experience and deep knowledge in transmission system construction, operation, and maintenance engineering. They were invited to share diverse opinions in weight determination based on their valuable experience and responsibility in the utility. An inquiry form based on the AHP method was developed in MS Excel file and distributed to experts to share their opinions in weight determination to obtain the utility-consensus value. Finally, the final weights were calculated by using the geometric mean technique. Eventually, this WSM and the overall process were well accepted by all departments without any disagreement.
Table 2. Importance criteria of transmission system.
Table 2. Importance criteria of transmission system.
CriteriaScore Sm from 0 to 4%Wm
Very Low (0)Low (1)Moderate (2)High (3)Very High (4)
percentage line loading (MVA)0–2021–3031–4041–50>5014
system usage no tie line radial linetie line/rapid load shedding/generator connected11
voltage level (kV) ≤115 230500/300 DC5
contingency analysisnon N-2 N-110
statistically failure (event/year)0 1–56–10>106
age (years)10–020–1125–2130–26>3032
public imagenormal province industrial estate/big province/tourist/business area7
pollution
(>20% of total length)
rice field/
agricultural area
plant burn/firingbird droppingscoastal area/
industrial estate
5
human impact normal line compact line10

5. Cost Analysis

Maintenance costs of the transmission line, including the replacement cost, adjusted maintenance cost, loss of selling cost and loss of penalty fee cost, were determined and subsequently used to multiply with the D-distance risk factor, as shown in (8) to (11), which revealed the actual maintenance cost based on actual risk. Finally, the total maintenance cost could be expressed as shown in (12). With this calculated total maintenance cost, the utility could properly plan the annual budget for the maintenance, renovation, or replacement of the HVTL.
R P C = d × E Q C
A M C = d × M C
L S C = d × D S × E R × D T
L R C = d × D S × L P F
T C = R P C + A M C + L S C + L F C
where RPC is the replacement cost, EQC is the equipment cost, MC is the maintenance cost, AMC is the adjusted maintenance cost, LSC is the loss of selling cost, DS is the MW sold, ER is the electricity selling rate, DT is the down time for repair, LRC is the loss of reputation cost, LPF is the utility penalty fee in the case of power interruption and TC is the total cost.

6. Results and Discussion

After a clear procedure for the HVTL was established, risk assessment was set up, and the asset management program for the HVTL at the 115, 230 and 500 kV levels was developed. It is currently used by Thailand’s transmission system utility for recording technical and financial data, testing and inspection results and condition and importance evaluation results. All mentioned data with maintenance costs were recorded in a central database. At present, the actual technical and testing data of the HVTL can be quickly retrieved from the database, and further analysis can be performed regarding the results shown in this section.

6.1. Risk Analysis

The renovation and importance indices calculations are clearly demonstrated in this section. All actual testing and visual inspection results were used in this analysis. A pilot 115 kV TL#1 was selected as an example. In Table 3, the calculation of the conductor renovation index or %CRI is expressed as 75%. In the group of conductors, it only consists of a conductor by itself. By using (3), there were four test methods for the conductor; the weight percentage of each method was equally assigned as 25%. By using (4), %CRI could be obtained as 75%, while the %RI of other components was similarly calculated and is presented in Table 4. Next, the %TRI of tower No.1 (Tower#1) was determined by using (5) and was equal to 63.45%, as shown in Table 4. Then, the %RIavg of all components in 103 towers of HVTL No.1 (TL#1) was further used to calculate the %LRI of TL#1 by applying (6). The %LRI of TL#1 was equal to 66.21%, as shown in Table 5. Simultaneously, the %IMI of the 115 kV TL#1 was similarly calculated by applying (7) with the actual importance data, as presented in Table 6, which was equal to 67.75%. After obtaining both indices, the %D-distance of the 115 kV TL#1 risk could be determined by (2) as 80.60%. Finally, the %LRI and %IMI of twenty transmission lines in Thailand were successfully determined. The percentage D-distance risk factor relevant to the %LRI and %IMI of individual line was further investigated, as shown in Table 7, and plotted in the risk matrix, as shown in Figure 5. The obtained D-distance from the risk matrix was used to manage the risk by classifying the obtained risk into four levels from very high to low risk. Therefore, different actions could be performed according to these risks, as shown in Table 8.

6.2. Cost Analysis

The cost analysis of HVTLs was further analyzed after obtaining the D-distance value. The maintenance budget could be effectively planned according to the actual condition or renovation requirement and risk of HVTLs. To demonstrate the implementation of the proposed method, a double circuit 230 kV HVTL with a 1 × 1272 MCM ACSR conductor was chosen as an example due to its complete information of the actual maintenance cost. The cost included the replacement cost, adjusted maintenance cost, loss of selling cost and loss of supply penalty fee cost per kilometer. As shown in Table 9, the investment cost of this 230 kV HVTL was 4285.06 THB/m. The maintenance cost of the line was also obtained, which was further used to compare with the investment of the new line in order to analyze the breakeven point to install the new line instead of continuing to conduct maintenance tasks for the lines. The inflation rate, MW loss of sale, down time of outage, electricity rate and loss of reputation rate were also given. Consequently, the total cost consisted of the summation of the replacement cost of equipment (3,762,500 THB/km), maintenance cost (517,000 THB/km), loss of opportunity to sale electricity during outage (2.513 THB/kWh) and reputation cost (0.7 THB/kWh). In addition, all maintenance costs were equal for all of 115, 230 and 500 kV lines. The loss of sale and reputation cost were assumed by using the line loss of 100 MW in 3 h. The cost of loss was increasing due to the 3% inflation rate.
As presented in Table 10, the result showed that TL#1 encountered the highest risk with a D-distance of 80.60%, represented in red color, as it was located near seashore with poor pollution resulting from salt spray due to strong winds. This led to poor conditions of the insulator, conductor, foundation, etc. By using (8) and (9), the replacement cost and maintenance cost of TL#1 at the age of 51 years, which were determined by multiplying the D-distance with its relevant cost, were equal to 2396.68 and 368.99 kTHB/km, respectively. Similarly, by using (10) and (11), the loss of sale and reputation cost were equal to 719.85 and 40.30 kTHB/km, respectively. Therefore, the total cost of this line is 3525.83 kTHB/km, which is nearly equal to the investment cost of a new overhead line—3508.28 kTHB/km. Now, the decision can be easily made to replace this TL#1 with the new one due to the highest risk and maintenance cost. With the D-distance technique, the D-distances and overall costs of 20 HVTLs were successfully calculated. The result showed that five, twelve and three HVTLs were at low, medium, and high risk as represented in Table 10 in green, yellow and orange colors, respectively. From the obtained results, TL#1 has the highest risk at 80.60% D-distance and a high total cost of maintenance at 3525.83 kTHB/km, which is comparable to the investment cost of a new overhead line. Then, the decision should be the immediate replacement of TL#1 by a new line. TL#12 was ranked as having the second highest risk of 69.45% D-distance with 43 years in service. Its total maintenance cost is 3348 kTHB/km, which is slightly lower than the new investment cost of 4279.54 kTHB/km. Short-term planning to replace TL#12 should be performed. From this proposed method of D-distance risk factor and cost analysis, the comprehensive information to support the decision regarding HVTL maintenance or replacement by a new line can be effectively compared based on the actual condition of the HVTL, its importance to the electrical network, its usage risk and total cost comparison. This method was further developed as a systematic evaluation tool for all HVTLs in a utility’s network to facilitate the maintenance and renovation tasks.

7. Conclusions

Risk-based maintenance using renovation and importance indices for HVTLs was proposed. The actual testing and visual inspection results obtained from the utility practice during annual on-site HVTL maintenance as well as data for the importance assessment were considered together to determine the risk of HVTL usage. The renovation index referred to the maintenance/renovation/replacement requirement, while the importance index considered the overall impact of HVTLs on electrical systems. The weighting and scoring method was applied to calculate both renovation and importance indices. The score and its ranges were assigned based on the utility practice and international standard, while all importance weights were assigned by the brainstorming of experts from various departments responsible for HVTLs in a utility with the aid of the AHP method. The maintenance tasks according to the calculated renovation and importance indices were suggested and differentiated into nine clusters in the risk matrix. The input data, including visual inspection, on-site tests and special tests, of 20 HVTLs in 115, 230 and 500 kV transmission networks were applied in this assessment process. With the application of the D-distance risk factor, all HVTLs could be prioritized for maintenance planning and ranked from required urgent action to long-term planning. The results showed that five lines were in a low-risk zone, twelve lines in a medium risk zone, two lines in high-risk zone and one line in a very high-risk zone, respectively. Moreover, in this risk-based analysis, the maintenance costs together with the outage cost of these existing lines was compared with the investment cost of a new line to support the decision-making process in whether to maintain/renovate or construct a new HVTL. From the results, TL#1 has the highest risk of 80.60% D-distance with the total cost of maintenance at 3525.83 kTHB/km. Since the cost of a new overhead line is 3508.28 kTHB/km, the decision can be made easily to replace this TL#1. Presently, the transmission line maintenance department and asset management division can apply the developed procedure and its obtained results for successful maintenance planning in the repair, renovation, or replacement of aged HVTLs according to their actual condition and renovation requirements as well as the available budget.

Author Contributions

Conceptualization, T.S. and C.S.; methodology, T.S., C.S. and W.L.; Software, W.L.; formal analysis, T.S. and W.L.; Validation, T.S., C.S. and W.L.; investigation, T.S. and C.S.; resources, T.S. and W.L.; data curation; writing original draft preparation, W.L.; writing review and editing, T.S. and C.S.; supervision, T.S.; project administration, T.S.; All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable

Data Availability Statement

Not applicable

Acknowledgments

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Guo, Y.; Chen, R.; Shi, J.; Wan, J.; Yi, H.; Zhong, J. Determination of the power transmission line ageing failure probability due to the impact of forest fire. IET Gener. Transm. Distrib. 2018, 12, 3812–3819. [Google Scholar] [CrossRef]
  2. Teh, J. Uncertainty analysis of transmission line end-of-life failure model for bulk electric system reliability studies. IEEE Trans. Reliab. 2018, 67, 1261–1268. [Google Scholar] [CrossRef]
  3. Teh, J.; Lai, C.M.; Cheng, Y.H. Impact of the real-time thermal loading on the bulk electric system reliability. IEEE Trans. Reliab. 2017, 66, 1110–1119. [Google Scholar] [CrossRef]
  4. Montanari, G.C.; Seri, P.; Dissado, L.A. Aging mechanisms of polymeric materials under DC electrical stress: A new approach and similarities to mechanical aging. IEEE Trans. Dielectr. Electr. Insul. 2019, 26, 634–641. [Google Scholar] [CrossRef]
  5. Cigre: WG C1.16. Transmission Asset Risk Management. Cigre Technical Brochures. Reference: 422; Paris, France, 2010.
  6. Khuntia, S.R.; Rueda, J.L.; Bouwman, S.; Van der Meijden, M.A.M.M. A literature survey on asset management in electrical power [transmission and distribution] system. Int. Trans. Electr. Energy Syst. 2016, 26, 2123–2133. [Google Scholar] [CrossRef] [Green Version]
  7. Heo, J.H.; Kim, M.K.; Kim, D.; Lyu, J.K.; Kang, Y.C.; Park, J.K. Priority index of overhead transmission lines for reliability centered approach. J. Electr. Eng. Technol. 2014, 9, 1248–1257. [Google Scholar] [CrossRef] [Green Version]
  8. Liu, Y.; Xv, J.; Yuan, H.; Lv, J.; Ma, Z. Health assessment and prediction of overhead line based on health index. IEEE Trans. Ind. Electron. 2019, 66, 5546–5557. [Google Scholar] [CrossRef]
  9. Khoddam, M.; Sadeh, J.; Pourmohamadiyan, P. Performance evaluation of circuit breaker electrical contact based on dynamic resistance signature and using health index. IEEE Trans. Compon. Pack. Manuf. Technol. 2016, 6, 1505–1512. [Google Scholar] [CrossRef]
  10. Hashim, R.; Usman, F.; Baharuddin, I.N.Z. Determining health index of transmission line asset using condition-based method. Resources 2019, 8, 80. [Google Scholar] [CrossRef] [Green Version]
  11. Chojnacki, A.L. Assessment of the risk of damage to 110 kV overhead lines due to wind. Energies 2021, 14, 556. [Google Scholar] [CrossRef]
  12. Chen, W.; Zhou, W.; Zhou, E.; Xiang, Z.; Zhou, W.; Lu, J. Wildfire Risk Assessment of Transmission-Line Corridors Based on Naïve Bayes Network and Remote Sensing Data. Sensors 2021, 21, 634. [Google Scholar] [CrossRef]
  13. Teh, J.; Lai, C.-M. Risk-based management of transmission lines enhanced with the dynamic thermal rating system. IEEE Access 2019, 7, 76562–76572. [Google Scholar] [CrossRef]
  14. Lijuan, C.; Li, L.; Yan, P.; Wenjin, C.; Hongyang, H.; Tiantian, W.; Xiaohui, X. Distribution network operational risk assessment and early warning considering multi-risk factors. IET Gener. Transm. Distrib. 2020, 14, 3139–3149. [Google Scholar]
  15. Lei, G.; Qiwei, Q.; Jian, L.; Yu, Z.; Linglei, J. Power transmission risk assessment considering component condition. J. Mod. Power Syst. Clean Energy 2014, 2, 50–58. [Google Scholar]
  16. Zhang, D.; Li, W.; Xiong, X. Overhead line preventive maintenance strategy based on condition monitoring and system reliability assessment. IEEE Trans. Power Syst. 2014, 29, 1839–1846. [Google Scholar] [CrossRef]
  17. Piana, E.A.; Bignucolo, F.; Donini, A.; Spezie, R. Maintenance of a high-voltage overhead transmission line: Sustainability and noise impact assessment. Sustainability 2018, 10, 491. [Google Scholar] [CrossRef] [Green Version]
  18. Zhong, J.; Li, W.; Wang, C.; Yu, J.; Xu, R. Determining optimal inspection intervals in maintenance considering equipment aging failures. IEEE Trans. Power Syst. 2017, 32, 1474–1482. [Google Scholar] [CrossRef]
  19. Adami, J.; Silveira, P.; Martinez, M.; Perez, R.; Dallbello, A.C. New approach to improve high-voltage transmission line reliability. IEEE Trans. Power Deliv. 2009, 24, 1515–1520. [Google Scholar] [CrossRef]
  20. Heydt, G.T. A probabilistic cost/benefit analysis of transmission and distribution asset expansion projects. IEEE Trans. Power Syst. 2017, 32, 4151–4152. [Google Scholar] [CrossRef]
  21. Lima, R.M.; Osis, R.; Queiroz, A.R.D.; Santos, A.H.M. Least-cost path analysis and multi-criteria assessment for routing electricity transmission lines. IET Gener. Transm. Distrib. 2016, 10, 4222–4230. [Google Scholar] [CrossRef]
  22. Gharakheili, M.A.; Fotuhi-Firuzabad, M.; Dehghanian, P. A new multiattribute decision making support tool for identifying critical components in power transmission systems. IEEE Syst. J. 2018, 12, 316–327. [Google Scholar] [CrossRef]
  23. Eskom Power Series. The Planning, Design and Construction of Overhead Power Lines; Eskom: Johannesburg, South Africa, 2005; Volume 1. [Google Scholar]
  24. Eskom Power Series. The Fundamentals and Practice of Overhead Line Maintenance; Eskom: Johannesburg, South Africa, 2005; Volume 2. [Google Scholar]
  25. Cigre: WG B2.03. Guide for the assessment of old cap & pin and long-rod transmission line insulators made of porcelain or glass: What to check and when to replace? Cigre Technical Brochure. Reference: 306; Paris, France, 2006.
  26. Chen, C.; Jia, Z.; Ye, W.; Guan, Z.; Li, Y. Condition assessment strategies of composite insulator based on statistic methods. IEEE Trans. Dielectr. Electr. Insul. 2016, 23, 3231–3241. [Google Scholar] [CrossRef]
  27. Tzimas, A.; Silva, E.D.; Rowland, S.M.; Boumecid, B.; Queen, M.; Michel, M. Asset management frameworks for outdoor composite insulators. IEEE Trans. Dielectr. Electr. Insul. 2012, 19, 2044–2054. [Google Scholar] [CrossRef]
  28. Suwanasri, T. Program development for condition and importance evaluation of transmission line. Final Research Report, 2018.
  29. Montanari, G.C.; Hebner, R.; Morshuis, P.; Seri, P. An approach to insulation condition monitoring and life assessment in emerging electrical environments. IEEE Trans. Power Deliv. 2019, 34, 1357–1364. [Google Scholar] [CrossRef]
  30. Moradkhani, A.; Haghifam, M.R.; Mohammadzadeh, M. Failure rate modelling of electric distribution overhead lines considering preventive maintenance. IET Gener. Transm. Distrib. 2014, 8, 1028–1038. [Google Scholar] [CrossRef]
  31. Narayanan, V.J.; Sivakumar, M.; Karpagavani, K.; Chandrasekar, S. Prediction of flashover and pollution severity of high voltage transmission line insulators using wavelet transform and fuzzy C-means approach. J. Electr. Eng. Technol. 2014, 9, 1677–1685. [Google Scholar] [CrossRef]
  32. Saaty, T.L.; Vargas, L.G. Models, Methods, Concept and Applications of the Analytic Hierarchy Process, 2nd ed.; Springer: New York, NY, USA, 2012. [Google Scholar]
  33. Tanaka, H.; Tsukao, S.; Yamashita, D.; Niimura, T.; Yokoyama, R. Multiple criteria assessment of substation conditions by pair-wise comparison of analytic hierarchy process. IEEE Trans. Power Deliv. 2010, 25, 3017–3023. [Google Scholar] [CrossRef]
  34. Leccesea, F.; Salvadoria, G.; Roccaa, M.; Burattib, C.; Bellonib, E. A method to assess lighting quality in educational rooms using analytic hierarchy process. Build. Environ. 2020, 168, 106501. [Google Scholar] [CrossRef]
Figure 1. High-voltage transmission line components for condition assessment.
Figure 1. High-voltage transmission line components for condition assessment.
Sustainability 13 08208 g001
Figure 2. Risk assessment for maintenance strategy flowchart.
Figure 2. Risk assessment for maintenance strategy flowchart.
Sustainability 13 08208 g002
Figure 5. Risk assessment matrix and D-distance.
Figure 5. Risk assessment matrix and D-distance.
Sustainability 13 08208 g005
Table 1. HVTL components and sub-components.
Table 1. HVTL components and sub-components.
GroupComponent%LRISub-Component
1conductor%CRIconductor
2conductor accessory%CARIjoint, compression dead end, damper, spacer, parallel glove clamp (PGC)
3insulator%IRIinsulator
4steel structure%SSRIsteel structure, anchor and guy
5foundation%FRIconcrete foundation, grillage foundation, stub
6lightning protection%LPRIoverhead/optical ground wire and fittings, marker ball, grounding system
7tower accessory%TARIdanger sign, tower number sign, phase plate
8right-of-way%RWRIright-of-way
Table 3. %CRI of conductor of 115 kV TL#1, tower# 1.
Table 3. %CRI of conductor of 115 kV TL#1, tower# 1.
Testing Method%Wi%Si%Wi × %Si%CRI
visual inspection25512575%
loss of zinc25375
loss of tensile strength254100
torsional ductility25375
Table 4. %TRI of 115 kV TL#1, tower# 1.
Table 4. %TRI of 115 kV TL#1, tower# 1.
TowerComponent%RIj%Wj%TRI#1
Tower#1conductor%CRI = 75%25.3163.45%
conductor accessory%CARI = 40%2.91
insulator%IRI = 24.62%10.48
steel structure%SSRI = 80%15.48
foundation%FRI = 90%19.06
lightning protection%LPRI = 18.82%16.89
tower accessory%TARI = 40%3.10
right-of-way%RWRI = 100%6.77
Table 5. %LRI of 115 kV TL#1.
Table 5. %LRI of 115 kV TL#1.
LineComponent%RIavg,lWl%LRI
115 kV TL#1conductor%CRIavg = 62.89%25.3163.45%
conductor accessory%CARIavg = 40%2.91
insulator%IRIavg = 24.62%10.48
steel structure%SSRIavg = 77.86%15.48
foundation%FRIavg = 96.99%19.06
lightning protection%LPRIavg = 39.59%16.89
tower accessory%TARIavg = 31.073.10
right-of-way%RWRIavg = 94.176.77
Table 6. %IMI of HVTL 115 kV TL# 1.
Table 6. %IMI of HVTL 115 kV TL# 1.
Importance CriteriaDataSm%WmSm × Wm%IMI
loading percentage
system usage
58.62142867.75%
tie line41144
voltage level115 kV155
contingency analysisnon0100
failure record6 event/year3618
age31 years432128
social aspectsbig province4728
pollutionplant burn/firing2510
human impactnormal line11010
Table 7. Assessment results of 20 HVTLs.
Table 7. Assessment results of 20 HVTLs.
HVTL’s NameAge (y)%LRI%IMI%D-distance
115 kV TL#15166.2167.7580.60
115 kV TL#22820.0639.5035.84
115 kV TL#33017.9251.5041.77
115 kV TL#43215.7870.2551.76
115 kV TL#55041.5251.5055.97
115 kV TL#63021.4458.5048.10
115 kV TL#73925.6471.5058.45
230 kV TL#85537.1766.7562.53
230 kV TL#9215.4626.2519.08
230 kV TL#103525.0157.5049.65
230 kV TL#113021.0667.0052.98
230 kV TL#124367.1848.2569.45
230 kV TL#1325.467.757.95
230 kV TL#142622.9461.0050.51
500 kV TL#15207.5133.7524.83
500 kV TL#162858.5919.1046.74
500 kV TL#171919.1070.5053.91
500 kV TL#183618.1238.7534.22
500 kV TL#19135.4929.7521.20
500 kV TL#202617.2530.0028.43
Table 8. Range of risk management from D-distance.
Table 8. Range of risk management from D-distance.
%D-distanceRiskRequirementsSuggested Action
>80.1very high1st priorityurgent action
60.1–80high2nd priorityshort-term planning
30.1–60medium3rd prioritymedium-term planning
0–30low4th prioritylong-term planning
Table 9. Maintenance cost of 115, 230 and 500 kV HVTL (kTHB/km).
Table 9. Maintenance cost of 115, 230 and 500 kV HVTL (kTHB/km).
Group115 kV230 kV500 kV
EQCMCEQCMCEQCMC
conductor50843900501500100
conductor accessory65.53567.54012070
insulator50.1813072150100200
steel structure1600100180011426002300
foundation600957501001000200
lightning protection1303515040300100
tower accessory4.84.8551010
right-of-way151518182525
sum2973.48457.83762.551756553005
total maintenance cost (EQC + MC)3431.284279.58660
HVTL Information115 kV230 kV500 kV
investment of new line (THB/km)
ACSR conductor, double circuit
3508.28
2 × 795 MCM
4285.06
2 × 1272 MCM
10,949.71
4 × 1272 MCM
inflation rate: IR (%)333
demand of sale: DS (MW)100100100
down time: DT (hrs)345
electricity rate: ER (THB/kWh)2.9772.5132.479
loss of penalty fee: LPF (THB/kW)0.50.70.9
Table 10. Cost analysis according to D-distance (kTHB/km).
Table 10. Cost analysis according to D-distance (kTHB/km).
%DAgeLinekVRPCAMCLSCLRCTC
7.952#13230299.0541.0979.905.56425.61
19.0821#9230717.8698.64191.7913.361021.65
21.2013#195001199.05637.16262.8219.082118.11
24.8320#155001403.88746.01307.7122.342479.95
28.4326#205001607.70854.31352.3925.592839.98
34.2236#185001935.021028.25424.1330.803418.19
35.8428#21151065.59164.06320.0617.921567.62
41.7730#31151241.99191.22373.0420.881827.13
46.7428#165002643.431404.69579.40442.074669.59
48.1030#61151430.21220.20432.8924.052107.34
49.6535#102301867.90256.67499.0334.752658.34
50.5126#142301900.27261.11507.6835.352704.42
51.7632#41151539.16236.97462.3025.882264.31
52.9830#112301993.54273.93532.6037.092837.16
53.9119#175003048.671620.03668.2348.525385.44
55.9750#51151664.22256.23499.8627.982448.29
58.4539#71151737.93267.57522.0029.222556.73
62.5355#82302352.58323.27628.5243.773348.14
69.4543#122302613.15359.07698.1448.623718.98
80.6051#11152396.68368.99719.8540.303525.83
Note: the traffic light color in the above table represents the risk level as green for low risk, yellow for moderate risk and red for high risk.
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Luejai, W.; Suwanasri, T.; Suwanasri, C. D-distance Risk Factor for Transmission Line Maintenance Management and Cost Analysis. Sustainability 2021, 13, 8208. https://doi.org/10.3390/su13158208

AMA Style

Luejai W, Suwanasri T, Suwanasri C. D-distance Risk Factor for Transmission Line Maintenance Management and Cost Analysis. Sustainability. 2021; 13(15):8208. https://doi.org/10.3390/su13158208

Chicago/Turabian Style

Luejai, Waraporn, Thanapong Suwanasri, and Cattareeya Suwanasri. 2021. "D-distance Risk Factor for Transmission Line Maintenance Management and Cost Analysis" Sustainability 13, no. 15: 8208. https://doi.org/10.3390/su13158208

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop