Techno-Economic Comparison of Microgrids and Traditional Grid Expansion: A Case Study of Myanmar
Abstract
1. Introduction
2. Literature Review
3. Materials and Methods
3.1. Study Design and Workflow
- Chin State—mountainous terrain with dispersed rural settlements and low accessibility.
- Nay Pyi Taw (NPT)—flat terrain with high accessibility and better existing infrastructure.
- Medium-Voltage (MV) Line-Cost Modelling (Excel-based): Estimates capital needs for 11 kV distribution line extensions to unelectrified villages, adjusted for terrain conditions.
- Centralized Generation Expansion Modelling (PLEXOS): Simulates hydro-based generation to meet additional demand from MV extension. Outputs include NPC, LCOE, CAPEX, OPEX, ENS, and reliability indices.
- Microgrid Simulation (HOMER Pro): Optimizes hybrid PV–diesel–battery systems under the same demand profiles. Indicators include NPC, LCOE, CAPEX, OPEX, and REF. Reliability targets are aligned with grid extension scenarios.
3.2. Case Study Descriptions
3.2.1. Electrification Status of Study Regions
Chin State (Terrain Region)
Nay Pyi Taw (Flat Region)
3.2.2. Case Study Area
Short-Distance Connection (Within 5 km to 10 km of Existing Grid)
- Lailui (82 households, 1.3 miles from the grid).
- Zatour (70 households, 1.6 miles from the grid).
- Dimlo (84 households, 2.9 miles from the grid).
- Te Myint (445 households, 1.48 miles from the grid).
- Se To (237 households, 2.54 miles from the grid).
- Chin Su (332 households, 1.23 miles from the grid).
Long-Distance Connection (Approximately 15 km to 20 km from Existing Grid)
3.2.3. Average Load Consumption per Household
- Lailui: 82 × 0.9125 MWh = 74.825 MWh/year.
- Zatour: 70 × 0.9125 MWh = 63.875 MWh/year.
- Dimlo: 84 × 0.9125 MWh = 76.65 MWh/year.
3.3. Medium-Voltage (MV) Line-Cost Modelling
3.3.1. Scope and Assumptions
3.3.2. Cost Components
3.3.3. Financials
3.3.4. Levelized Cost (MV Only)
3.3.5. Terrain Adjustment
3.3.6. Worked Example
3.3.7. Chin State (Terrain Region)
Nay Pyi Taw (Flat Region)
- Base cost: Derived from NEP procurement data for flat terrain.
- Table 4 shows MV (11 kV) line-cost breakdown per km in flat and mountainous terrain. A detailed breakdown of MV line-cost components is provided in Appendix A (Table A1).
3.4. Reliability Assessment and Adjustments
3.4.1. Data Sources and Assumptions
3.4.2. Reliability of Grid Extension
- Chin State (proxy 2023): SAIDI ≈ 2948 min/year (≈590 h/year); ASAI ≈ 93%
- Nay Pyi Taw (2023): SAIDI ≈ 48.8 min/year (9.76 h/year); ASAI ≈ 99.9%.
3.5. Centralized Generation Modelling with PLEXOS
3.5.1. Input Data and Modelling Assumptions
3.5.2. Reliability Constraints and Mapping (LOLP/ASAI)
3.5.3. Capacity Expansion and Chronological Dispatch Setup
3.5.4. Key Performance Indicators (KPIs) (PLEXOS)
- NPC—discounted system cost.
- LCOE—USD/kWh delivered.
- CAPEX and OPEX—annualized investment and operating expenditures.
- ENS—residual unmet demand.
- ENS and generation-related NPC, CAPEX, OPEX, and LCOE were obtained directly from the software outputs. For the distribution (MV line extension), CAPEX, OPEX, NPC, and LCOE were calculated externally in Excel, incorporating reliability adjustments.
3.6. Microgrid Modelling in HOMER Pro
3.6.1. Solar Radiation, Load Profile, and Input Data for Microgrid Modelling
3.6.2. Incorporating Reliability into HOMER Pro
3.6.3. Simulation Assumptions, Sensitivity Parameters, and Scenarios (HOMER Pro)
- Diesel price: 0.70 USD/L, based on recent local retail prices [52].
- Battery cost, 300 USD/kWh, and PV capital cost, 2500 USD/kW, sourced from HOMER Pro’s technology cost library relevant to Southeast Asia [53].
- Discount rate: 10%, reflecting Myanmar’s sovereign risk and consistent with grid extension assumptions and IEA/OECD guidance for developing economies [48].
- Project lifetime: 20 years, matching the grid extension timeframe [53].
- Maximum annual capacity shortage: 7%, corresponding to 93% system availability, aligned with Chin State reliability.
- Diesel price: 0.70–1.30 USD/L.
- Battery cost: 150–300 USD/kWh.
- PV capital cost: 1250–2500 USD/kW.
- Discount rate: 8–12%.
- Base Case: Current assumptions, as above.
- Lowest Cost Case: Favorable market trends (diesel 0.70 USD/L, battery 150 USD/kWh, PV 1250 USD/kW, discount rate 8%).
- Highest Cost Case: Pessimistic assumptions (diesel 1.30 USD/L, battery 300 USD/kWh, PV 2500 USD/kW, discount rate 12%).
- Mid Cost Case: Moderate trends (diesel 1.00 USD/L, battery 225 USD/kWh, PV 1875 USD/kW, discount rate 10%).
3.6.4. Key Performance Indicators (KPIs) (HOMER Pro)
- NPC, LCOE, CAPEX, OPEX: HOMER Pro outputs.
- ENS: Directly provided by HOMER Pro.
- REF: Provided by HOMER Pro, reflecting the share of energy delivered by renewables.
3.7. Indicator Acquisition Approach
4. Results and Discussion
4.1. MV Line Extension Results
4.2. PLEXOS Simulation Results
- Interpretation of results:
- The model confirmed that a single 0.3 MW hydro unit suffices to meet demand in both Chin State and Nay Pyi Taw.
- The planning horizon starts in January 2024, with hydro commissioning scheduled for mid-2025. ENS is observed in 2024–mid-2026, reflecting the gap between initial demand and available supply during construction.
- ENS is fully eliminated once the hydro unit becomes operational, emphasizing the importance of timely infrastructure deployment in rural unelectrified areas
- After commissioning, the system meets projected demand through 2038 under the assumed 2% annual growth, confirming that a single hydro unit meets reliability targets in both regions.
- Differences in LOLP (7% for Chin vs. 0.1% for Nay Pyi Taw) do not affect generation outcomes, indicating that early ENS is driven by construction lead time rather than generation inadequacy.
- In Chin State, high MV line extension costs remain the dominant factor affecting overall grid extension feasibility, rather than generation costs.
4.3. Total Grid Extension Cost (MV Line + Generation): Chin State vs. Nay Pyi Taw
4.4. Microgrid Results (HOMER Simulations)
- Reliability: No significant cost difference was observed between 93% and 100% reliability, as the system met full demand under all scenarios.
- Renewable Fraction (REF): Electricity supply varies across microgrid scenarios. In the base case, REF is 29.6%, reflecting the PV–battery–diesel combination. The lowest-cost scenario achieves the highest REF (63.4%) due to reduced battery and PV costs, enabling greater renewable integration. Mid- and highest-cost scenarios yield REF of 41.2% and 30.4%, respectively, illustrating the trade-off between system cost and renewable penetration. These results demonstrate the flexibility of microgrids to increase renewable share depending on economic and technical design choices.
- Cost Scenarios: The lowest-cost scenario yields the lowest NPC (USD 409,543) and LCOE (USD 0.368/kWh) with the highest renewable fraction (63.4%). The highest-cost scenario shows substantially higher NPC and LCOE.
- Sensitivity: Diesel price has the largest impact on NPC and LCOE, with higher diesel costs reducing economic viability. Battery and PV cost reductions moderately improved outcomes. Discount rate variations showed minor impact.
- Renewable Fraction (REF): Results varied notably across microgrid scenarios. The base case shows 0% renewable penetration due to system design and PV constraints. The lowest-cost scenario achieves the highest renewable fraction at 64.2%, enabled by lower PV and battery costs. Mid- and highest-cost scenarios have renewable fractions of 37.3% and 35.4%, respectively. These findings indicate that renewable integration in microgrids is highly sensitive to technology costs and system design choices, enabling flexibility to increase renewable share while maintaining reliability.
- Cost Outcomes: The lowest-cost scenario achieves LCOE of USD 0.337/kWh, and the highest-cost scenario shows LCOE at USD 0.572/kWh, reflecting sensitivity to diesel price and capital costs.
- Capital–OPEX Trade-off: Capital-intensive scenarios with higher PV and battery investments reduce long-term OPEX and LCOE despite higher upfront CAPEX.
4.5. Cost Comparison and Scenario Analysis
4.6. Ranking of Influential Factors Affecting LCOE
- Diesel Price: In both regions, diesel price is the most influential factor, with Chin State experiencing a higher LCOE increase (+0.178 USD/kWh) compared to Nay Pyi Taw (+0.112 USD/kWh). This underscores the vulnerability of microgrid economics to fuel price fluctuations.
- Battery Cost: While reducing battery costs from USD 300 to USD 150/kWh led to a modest decrease in LCOE in Chin State (–0.014 USD/kWh), it had no impact in Nay Pyi Taw. This suggests that battery economics become more significant when there is substantial renewable energy integration.
- Discount Rate: Changes in the discount rate (8–12%) had a moderate effect on LCOE in both regions, with Chin State showing a wider range of ±0.018 USD/kWh compared to Nay Pyi Taw’s ±0.011 USD/kWh.
- PV Capital Cost: Lowering PV costs from USD 2500 to USD 1250/kW reduced LCOE more significantly in Nay Pyi Taw (–0.076 USD/kWh) than in Chin State (–0.007 USD/kWh), highlighting the greater impact of PV cost reductions in regions with higher renewable energy penetration.
4.7. Cross-Case Synthesis
4.8. Discussion and Implications
4.9. Policy Recommendations
- Dual Electrification Strategy: Formalize integrated planning of grid extension and microgrids, guided by geospatial and demographic factors.
- Renewable Incentives: Promote solar-dominant microgrids through import duty exemptions and concessional financing.
- Fast-Track Microgrid Deployment: Streamline regulations and standardize technical designs to accelerate rural electrification in remote areas.
- Affordable Financing: Expand access to low-interest loans and guarantees for public and private microgrid projects.
- Aligned Reliability Standards: Implement comparable service quality benchmarks for grid and microgrids to ensure equitable electrification.
- Enhanced Planning Tools: Increase use of integrated simulation platforms (HOMER, PLEXOS) for evidence-based multi-scenario rural electrification planning.
5. Conclusions
5.1. Summary of Findings
5.2. Limitations
5.3. Future Research Directions
- National-Scale Optimization: Extending the analysis to all Myanmar states and regions for a comprehensive lowest-cost electrification roadmap integrating both grid and microgrid options.
- Environmental and Social Indicators: Incorporating carbon emissions, job creation, and community acceptance metrics to support holistic decision making.
- Hybrid and Transitional Systems: Investigating modular microgrids capable of evolving into grid-connected mini-grids to inform dynamic long-term planning.
- Resilience and Climate Risks: Modeling climate-related hazards (flooding, landslides, extreme weather) to enhance infrastructure robustness.
- Business Models and Ownership: Examining community-based and public–private microgrid ownership models to facilitate scalable and inclusive rural electrification.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Abbreviations
ASAI | Average Service Availability Index |
CAPEX | Capital Expenditure |
GHI | Global Horizontal Irradiance |
HOMER | Hybrid Optimization of Multiple Energy Resources |
kWh | Kilowatt-hour |
LCOE | Levelized Cost of Electricity |
MG | Microgrid |
MV | Medium Voltage |
NEP | National Electrification Plan |
NPC | Net Present Cost |
O&M | Operation and Maintenance |
OPEX | Operational Expenditure |
ENS | Unserved Energy |
REF | Renewable Fraction |
KPIs | Key Performance Indicators |
PV | Photovoltaic |
SAIDI | System Average Interruption Duration Index |
SAIFI | System Average Interruption Frequency Index |
IEA | International Energy Agency |
OECD | Organisation for Economic Co-operation and Development |
NEA | Nuclear Energy Agency |
Appendix A
Description | Chin State Short Distance (<10 km) | Chin State Long Distance (15–20 km) | Nay Pyi Taw Short Distance (<10 km) | Nay Pyi Taw Long Distance (15–20 km) | Unit | Source/Notes |
---|---|---|---|---|---|---|
Total line length for 3 villages | 5.8 | 10 | 5.8 | 10 | miles | NEP Contract Agreements/Adjusted lengths |
Number of transformers (11/0.4 kV) | 3 | 3 | 3 | 3 | units | NEP Contract Agreements |
11 kV line material cost per mile | 23.04 | 23.04 | 18.11 | 18.11 | million MMK | [46] |
Transformer cost per unit (50 kVA) | 2.14 | 2.14 | 2.14 | 2.14 | million MMK | [47] |
Installation cost for 11 kV line | 36.13 | 62.30 | 9.18 | 15.83 | million MMK | Estimated based on NEP Phase 2 (Chin)/ Phase 1 (Nay Pyi Taw) |
Transformer installation cost | 4.30 | 4.30 | 1.50 | 1.50 | million MMK | NEP Contract Agreements |
Transportation cost | 7.98 | 13.75 | 2.37 | 4.09 | million MMK | NEP Contract Agreements |
Total CAPEX (before adjustment) | 209,747 | 351,353 | 110,737 | 185,119 | USD | Converted at exchange rate 1360 MMK/USD (reference rate at the time of contract) |
Adjusted CAPEX (+30% terrain factor) | — | 456,759 | — | — | USD | 30% increase for Chin’s difficult terrain |
Annual O&M cost (Transformer + Line) | 4405 | 9592 | 2215 | 3702 | USD/year | Assumed 2% of CAPEX/year |
Adjusted OPEX (+30% terrain factor) | 12,470 | 30% increase for Chin’s difficult terrain | ||||
Transmission cost (3% of 1 MWh) | 125.85 | 274.06 | 66.44 | 111.07 | USD/MWh | Existing 66 kV (Chin) and 33 kV (Nay Pyi Taw) transmission assumption |
Loss cost (2% losses per 1 MWh) | 83.90 | 182.70 | 44.29 | 74.05 | USD/MWh | Included in electricity delivered cost |
Delivered energy | 215.35 | 215.35 | 215.35 | 215.35 | MWh/year | Based on village load assumptions |
Discount rate (r) | 10% | 10% | 10% | 10% | — | Standard financial assumption |
Capital Recovery Factor (CRF) | 0.1175 | 0.1175 | 0.1175 | 0.1175 | — | For 20 years lifetime, 10% discount |
LCOE (CAPEX + OPEX) | 0.1349 | 0.3071 | 0.0712 | 0.1191 | USD/kWh | Levelized cost of electricity (MV line only) |
NPC | 247,234 | 562,882 | 130,529 | 218,205 | USD | Net Present Cost (MV line only) |
References
- World Bank. Myanmar National Electrification Project; Report No. PAD1410; World Bank: Washington, DC, USA, 2015; Available online: https://documents1.worldbank.org/curated/en/149061468191334165/pdf/PAD1410-CORRIGENDUM-IDA-R2015-0237-2-Box393200B-OUO-9.pdf (accessed on 7 August 2025).
- Sustainable Energy for All (SEforALL). Myanmar National Electrification Program (NEP) Roadmap and Investment Prospectus; SEforALL: Washington, DC, USA, 2014; Available online: https://www.seforall.org/sites/default/files/Myanmar_IP_EN_Released.pdf (accessed on 7 August 2025).
- International Energy Agency (IEA). World Energy Investment 2021; IEA: Paris, France, 2021; Available online: https://iea.blob.core.windows.net/assets/5e6b3821-bb8f-4df4-a88b-e891cd8251e3/WorldEnergyInvestment2021.pdf (accessed on 7 August 2025).
- World Bank. Power Sector Challenges in Myanmar (In the Dark: Power Sector Challenges in Myanmar). Available online: https://thedocs.worldbank.org/en/doc/6bd0c527c8469333b119d88cc0b8b410-0070062023/original/In-The-Dark-Power-Sector-Challenges-in-Myanmar-August2023.pdf (accessed on 6 September 2025).
- Bloomberg.NEF. Global Climate Scope. Myanmar Country Profile—Climate Scope 2024. Available online: https://global-climatescope.org/markets/myanmar (accessed on 6 September 2025).
- World Bank. World Development Indicators: Access to Electricity (% of Population). Available online: https://data.worldbank.org/indicator/EG.ELC.ACCS.ZS?locations=MM (accessed on 6 September 2025).
- Trading Economics. Myanmar—Access to Electricity (% of Population). Available online: https://tradingeconomics.com/myanmar/access-to-electricity-percent-of-population-wb-data.html (accessed on 6 September 2025).
- Our World in Data. Share of the Population with Access to Electricity—Myanmar. Available online: https://ourworldindata.org/grapher/share-of-the-population-with-access-to-electricity (accessed on 6 September 2025).
- International Renewable Energy Agency (IRENA). Smart Grids and Renewables: A Cost-Benefit Analysis Guide for Developing Countries. Available online: https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2015/IRENA_PST_Smart_Grids_CBA_Guide_2015.pdf (accessed on 7 August 2025).
- Korkovelos, A.; Zerriffi, H.; Howells, M.; Bazilian, M.; Rogner, H.-H.; Fuso Nerini, F. A Retrospective Analysis of Energy Access with a Focus on the Role of Mini-Grids. Sustainability 2020, 12, 1793. [Google Scholar] [CrossRef]
- Bekele, A.; Khan, B.; Zdiri, M.A.; Guerrero, J.M.; Chaudhary, S.; Vasquez, J.C.; Agundis Tinajero, G.D. Optimal Planning and Sizing of Microgrid Cluster for Performance Enhancement. Sci. Rep. 2024, 14, 26653. [Google Scholar] [CrossRef] [PubMed]
- London School of Economics (LSE). How Microgrids Can Electrify Rural Africa. 2023. Available online: https://blogs.lse.ac.uk/africaatlse/2023/12/14/how-microgrids-can-electrify-rural-africa/ (accessed on 7 August 2025).
- Karanki, S.B.; Ranjan, R.; Giri, S.; Kotsampopoulos, P.; Hatziargyriou, N. Development of Microgrids for Rural Electrification in India: The Case of Keonjhar. ELECTRA, December 2024. Available online: https://reempowered-h2020.com/wp-content/uploads/2025/01/Electra-Paper_postprint.pdf (accessed on 7 August 2025).
- Mentis, D.; Howells, M.; Rogner, H.; Korkovelos, A.; Arderne, C.; Zepeda, E.; Siyal, S.; Taliotis, C.; Bazilian, M.; De Roo, A.; et al. Lighting the World: The First Application of an Open Source, Spatial Electrification Tool (OnSSET) on Sub-Saharan Africa. Environ. Res. Lett. 2017, 12, 085003. [Google Scholar] [CrossRef]
- Kemausuor, F.; Adkins, E.; Adu-Poku, I.; Brew-Hammond, A.; Modi, V. Electrification Planning Using Network Planner Tool: The Case of Ghana. Energy Sustain. Dev. 2014, 19, 92–101. [Google Scholar] [CrossRef]
- Sotiropoulou, K.F.; Vavatsikos, A.P.; Botsaris, P.N. A Hybrid AHP-PROMETHEE II Onshore Wind Farms Multicriteria Suitability Analysis Using kNN and SVM Regression Models in Northeastern Greece. Renew. Energy 2024, 221, 119795. [Google Scholar] [CrossRef]
- Duan, F.; Eslami, M.; Okati, M.; Jasim, D.J.; Mahmood, A.K. Hybrid Stochastic and Robust Optimization of a Hybrid System with Fuel Cell for Building Electrification Using an Improved Arithmetic Optimization Algorithm. Sci. Rep. 2025, 15, 1779. [Google Scholar] [CrossRef] [PubMed]
- Pabla, A. Electric Power Distribution. Available online: https://highered.mheducation.com/sites/0070144559 (accessed on 16 July 2025).
- Ya, A.Z. Feasibility Study on a Stand-Alone Photovoltaic Hybrid Mini-Grid Power Generation System to Promote the Rural Elec-Trification-Rate in Mandalay Region of Myanmar. Trans. GIGAKU 2014, 2, S01009/1–S01009/7. [Google Scholar]
- Bhattacharyya, S.C.; Palit, D. Mini-Grid Based off-Grid Electrification to Enhance Electricity Access in Developing Countries: What Policies May Be Required? Energy Policy 2016, 94, 166–178. [Google Scholar] [CrossRef]
- Kipng’etich, K. Kenya The Rise of Green Mini-Grids—How Community-Based Solar Projects Are Electrifying Kenya’s Last Mile. 2025. Available online: https://africa-energy-portal.org/blogs/kenya-rise-green-mini-grids-how-community-based-solar-projects-are-electrifying-kenyas-last-mile (accessed on 19 July 2025).
- Trotter, P.A.; McManus, M.C.; Maconachie, R. Electricity Planning and Implementation in Sub-Saharan Africa: A Systematic Review. Renew. Sustain. Energy Rev. 2017, 74, 1189–1209. [Google Scholar] [CrossRef]
- Malla, K.; Pandey, S.; Bodger, P.; Wood, A. An Economic Comparison between Grid Based and Isolated Rural Electrification in Nepal. In Proceedings of the 2011 Asia-Pacific Power and Energy Engineering Conference, Wuhan, China, 25–28 March 2011; IEEE: Wuhan, China, 2011; pp. 1–5. [Google Scholar] [CrossRef]
- Robert, F.C.; Gopalan, S. Low Cost, Highly Reliable Rural Electrification through a Combination of Grid Extension and Local Renewable Energy Generation. Sustain. Cities Soc. 2018, 42, 344–354. [Google Scholar] [CrossRef]
- Carvallo, J.P.; Nag, S.; Broad, O.; Kammen, D.M. The Costs and Benefits of Electrifying Rural Communities: A Comprehensive Review; Copenhagen Consensus Center: Tewksbury, MA, USA, 2016. [Google Scholar]
- Liu, Q.; Michael Kamoto, K.; Liu, X. Microgrids-As-A-Service for Rural Electrification in Sub-Saharan Africa. Comput. Mater. Contin. 2020, 63, 1249–1261. [Google Scholar] [CrossRef]
- Kumar, P.H.; Alluraiah, N.C.; Gopi, P.; Bajaj, M.; P, S.K.; Kalyan, C.N.S.; Blazek, V. Techno-Economic Optimization and Sensitivity Analysis of off-Grid Hybrid Renewable Energy Systems: A Case Study for Sustainable Energy Solutions in Rural India. Results Eng. 2025, 25, 103674. [Google Scholar] [CrossRef]
- Boddapati, V.; Daniel, S.A. Optimal Design and Techno-Economic Analysis of a Microgrid for Community Load Applications. In Advances in Clean Energy Technologies; Baredar, P.V., Tangellapalli, S., Solanki, C.S., Eds.; Springer: Singapore, 2021; pp. 361–374. [Google Scholar]
- Lazard Lazard’s Levelized Cost of Energy Analysis, Version 20.0; Lazard: New York, NY, USA, 2015.
- Brown, D.; Dahlan, N.; Richardson-Barlow, C. Evaluating Microgrid Business Models for Rural Electrification: A Novel Framework and Three Cases in Southeast Asia. Energy Sustain. Dev. 2024, 80, 101443. [Google Scholar] [CrossRef]
- Motjoadi, V.; Bokoro, P.N.; Onibonoje, M.O. A Review of Microgrid-Based Approach to Rural Electrification in South Africa: Architecture and Policy Framework. Energies 2020, 13, 2193. [Google Scholar] [CrossRef]
- World Bank; ESMAP. Mini-Grids for Half a Billion People: Market Outlook and Handbook for Decision Makers; World Bank/ESMAP: Washington, DC, USA, 2019; Updates 2022; Available online: https://openknowledge.worldbank.org/handle/10986/31926 (accessed on 7 September 2025).
- International Energy Agency (IEA). Africa Energy Outlook 2019. Available online: https://www.iea.org/reports/africa-energy-outlook-2019 (accessed on 7 July 2025).
- United Nations Development Programme (UNDP). The State of Local Governance: Trends in Chin. Available online: https://www.undp.org/myanmar/publications/state-local-governance-trends-chin (accessed on 7 August 2025).
- Department of Population, Ministry of Immigration and Population. The 2014 Myanmar Population and Housing Census: Chin State Report; Ministry of Immigration and Population: Naypyidaw, Myanmar, 2015.
- Han Zaw, U.; Ministry of Electric Power. Fulfilling the Power in Chin State; Presentation Slide. Available online: https://www.bing.com/ck/a?!&&p=e3651d2bde97ed79c791c688848955a3c7d470e685352106525b137fd6e057fcJmltdHM9MTc1ODE1MzYwMA&ptn=3&ver=2&hsh=4&fclid=3b064e43-0299-655f-2216-5bd003ee6424&psq=U+Han+Zaw%2c+Ministry+of+Electric+Power+Fulfilling+the+Power+in+Chin+State&u=a1aHR0cHM6Ly93d3cuZGljYS5nb3YubW0vc2l0ZXMvZGljYS5nb3YubW0vZmlsZXMvbmV3cy1maWxlcy8wNV9jaGluX3N0YXRlZGVwcDE2LTMtMTkucGRm (accessed on 17 April 2025).
- Ministry of Electric Power (MOEP). National Electrification Project Updates. Available online: https://moep.gov.mm/en/ignite/page/80 (accessed on 7 August 2025).
- World Bank. Myanmar National Electrification Project (NEP): Project Overview. Energydata.Info, 2021. Available online: https://energydata.info/ (accessed on 7 August 2025).
- Department of Population. The 2014 Myanmar Population and Housing Census: Nay Pyi Taw Report; Ministry of Immigration and Population: Nay Pyi Taw, Myanmar, 2015. Available online: https://www.dop.gov.mm/ (accessed on 7 August 2025).
- World Bank. Myanmar National Electrification Project (NEP); World Bank: Washington, DC, USA, 2019; Available online: https://projects.worldbank.org/en/projects-operations/project-detail/P153115 (accessed on 7 August 2025).
- MOEP. Ministry of Electric Power Electricity Statistics 2019–2020; MOEP: Nay Pyi Taw, Myanmar, 2020.
- Energydat.info Village Electricity Access Database. Available online: https://energydat.info/ (accessed on 15 June 2025).
- Numata, M.; Sugiyama, M.; Mogi, G.; Swe, W.; Anbumozhi, V. Technoeconomic Assessment of Microgrids in Myanmar. In ERIA Discussion Paper Series 2018, ERIA-DP-2018-05. Available online: https://www.eria.org/uploads/media/ERIA_DP_2018_05.pdf (accessed on 7 August 2025).
- Power Africa. Mini-Grid Development Guide: A Practical Handbook for Developers in Africa. Available online: https://www.usaid.gov/powerafrica/resources/mini-grid-development-guide (accessed on 7 August 2025).
- Mandelli, S.; Barbieri, J.; Mereu, R.; Colombo, E. Off-Grid Systems for Rural Electrification in Developing Countries: Definitions, Classification and a Comprehensive Literature Review. Renew. Sustain. Energy Rev. 2016, 58, 1621–1646. [Google Scholar] [CrossRef]
- Ministry of Electric Power, Electric Supply Enterprise (ESE). Standard Design and Cost Estimation Manual for 11 kV Lines; Internal Report, Ministry of Electric Power, Electric Supply Enterprise (ESE): Naypyidaw, Myanmar, 2011. [Google Scholar]
- Ministry of Electric Power. Rate and Fee of Meter and Transformer Application. Available online: https://moep.gov.mm/en/ignite/page/594 (accessed on 15 June 2025).
- IEA; OECD-NEA. Projected Costs of Generating Electricity 2020 Edition; International Energy Agency: Paris, France, 2020. [Google Scholar]
- HOMER Energy. HOMER Pro—Hybrid Renewable and Distributed Generation System Design Software. Available online: https://www.homerenergy.com/products/pro/index.html (accessed on 7 August 2025).
- World Bank Group. Solar Resource and Photovoltaic Potential of Myanmar; World Bank Group: Washington, DC, USA, 2018. [Google Scholar]
- Global Solar Atlas. Global PV Potential Study: Factsheet—Myanmar. Available online: https://globalsolaratlas.info/ (accessed on 7 August 2025).
- Max Energy, Myanmar. Retail Fuel Price Updates. 2024. Available online: https://www.maxenergy.com.mm/ (accessed on 7 August 2025).
- HOMER Energy. HOMER Pro Software Documentation and Cost Library. 2024. Available online: https://www.homerenergy.com/ (accessed on 7 August 2025).
Indicator | Value/Notes | Year(s) | Source |
---|---|---|---|
Total installed capacity (grid) | ≈7122 MW | December 2022 | [4] |
Capacity by fuel | Natural gas 3567 MW Hydropower 3225 MW; Solar 192 MW; Coal 138 MW | December 2022 | [4] |
Electricity generation share | Hydro ≈ 57.8%; Natural gas ≈ 29.5%; Others ≈ 12.7% | 2023 | [5] |
Household electrification rate | 39.1% (2017) → 57.9% (2020) → 61.6% (2021) | 2017–2021 | [4] |
Population with access (WDI) | 70.4% (2020); 72.5% (2021); 73.6% (2022); 76.8% (2023) | 2020–2023 | [6,8] |
Urban/rural access | Urban ≈ 94.6%; Rural ≈ 68.8% | 2023 | [7] |
Access Tier | Daily Energy Use | Monthly Use | Typical Usage |
---|---|---|---|
Tier 2— Basic Needs | 0.3–0.5 kWh | 9–15 kWh | Lighting, phone charging, radio |
Tier 3— Moderate Use | 0.6–1.2 kWh | 18–36 kWh | +Fan, TV, small appliances |
Tier 4— Productive Use | 1.5–3.0 kWh | 45–90 kWh | +Refrigerator, water pump, small business equipment |
Region | Village | Real Households | Assumed Households | Real Grid Distance (Miles) | Assumed Grid Distance (Miles) | Real Annual Consumption (MWh) | Assumed Annual Consumption (MWh) |
---|---|---|---|---|---|---|---|
Chin State (Short) | Lailui | 82 | 82 | 1.3 | 1.3 | 74.83 | 74.83 |
Zatour | 70 | 70 | 1.6 | 1.6 | 63.88 | 63.88 | |
Dimlo | 84 | 84 | 2.9 | 2.9 | 76.65 | 76.65 | |
Nay Pyi Taw (Short Distance) | Te Myint | 445 | 82 | 1.48 | 1.3 * | 406.56 | 74.83 |
Se To | 237 | 70 | 2.54 | 1.6 * | 216.26 | 63.88 | |
Chin Su | 332 | 84 | 1.23 | 2.9 * | 302.89 | 76.65 | |
Chin State (Long Distance) | Selbung | 82 | 82 | ~20 | 10 | 74.83 | 74.83 |
Tuimi | 105 | 70 | 95.81 | 63.88 | |||
Vaivet | 60 | 84 | 54.75 | 76.65 | |||
Nay Pyi Taw (Long Distance) | Letha | 131 | 82 | ~19 | 10 | 119.54 | 74.83 |
Zaletgyi | 194 | 70 | 177.03 | 63.88 | |||
Lepan | 108 | 84 | 98.55 | 76.65 |
Cost Component | Flat Terrain [USD/km] | Mountainous Terrain [USD/km] |
---|---|---|
Poles & crossarms | 5200 | 6760 |
Conductors | 3800 | 4940 |
Transformers | 2500 | 3250 |
Labor & civil works | 4000 | 5200 |
Total | 15,500 | 20,150 |
Parameter | Value | Notes/Source |
---|---|---|
Technology | Hydropower | Centralized resource |
Installed Capacity (max) | 0.3 MW (scaled) | Expansion candidate |
Capital Cost | 3250 USD/kW | [48] |
Fixed O&M Cost | 35 USD/kW/year | [48] |
Variable O&M Cost | 0 USD/MWh | No fuel cost |
Fuel Cost | 0 | Hydro (non-fuel-based) |
Capacity Factor (Max) | 60% | Assumed from IEA [48] |
Discount Rate | 10% | Applied in cost calculations |
Simulation Time Horizon | 15 years | Capacity expansion & dispatch optimization |
Project Lifetime | 20 years | For LCOE & NPC calculations |
Component | Parameter | Value | Notes/Source |
---|---|---|---|
Solar PV | Capital Cost | 2500 USD/kW | HOMER default |
O&M Cost | 10 USD/kW/year | HOMER default | |
Diesel Generator | Capital Cost | 500 USD/kW | HOMER database |
Fuel Cost | 0.7 USD/L | Regional diesel price | |
Battery (Lead Acid) | Capital Cost | 300 USD/kWh | HOMER database |
Project Lifetime | 20 years | Same as PLEXOS | |
Discount Rate | 10% | Same as PLEXOS |
Scenario | CAPEX (USD) | OPEX (USD/Year) | LCOE (USD/kWh) | NPC (USD) |
---|---|---|---|---|
Chin State Short (<10 km) | 209,747 | 4405 | 0.1349 | 247,234 |
Chin State Long (15–20 km) | 456,759 | 12,470 | 0.3071 | 562,882 |
Nay Pyi Taw Short (<10 km) | 110,737 | 2215 | 0.0712 | 130,529 |
Nay Pyi Taw Long (15–20 km) | 185,119 | 3702 | 0.1191 | 218,205 |
Region | CAPEX (USD) | OPEX (USD/Year) | LCOE (USD/kWh) | NPC (USD) |
---|---|---|---|---|
Chin State | 97,500 | 3150 | 0.0121 | 98,841 |
Nay Pyi Taw | 97,500 | 3150 | 0.0121 | 98,841 |
Region | Distance | CAPEX (USD) | OPEX (USD/Year) | LCOE (USD/kWh) | NPC (USD) | Notes on Cost Drivers |
---|---|---|---|---|---|---|
Chin State | 5–10 | 307,247 | 7555 | 0.1470 | 346,075 | |
15–20 | 554,259 | 15,620 | 0.3192 | 661,723 | Terrain cost adjustment (+30%) | |
Nay Pyi Taw | 5–10 | 208,237 | 5475 | 0.0833 | 229,370 | |
15–20 | 282,619 | 7038 | 0.1311 | 317,046 |
Scenario | Max Annual Capacity Shortage | NPC (USD) | CAPEX (USD) | OPEX (USD/Year) | LCOE (USD/kWh) | Renewable Fraction (%) |
---|---|---|---|---|---|---|
Microgrid—Base Case | 7% (93% reliability) | 429,057 | 119,176 | 31,195 | 0.4500 | 29.6 |
Microgrid—Base Case | 0% (100% reliability) | 429,057 | 119,176 | 31,195 | 0.4500 | 29.6 |
Microgrid—Lowest Cost | 7% | 409,543 | 139,466 | 23,322 | 0.3680 | 63.4 |
Microgrid—Mid Cost | 7% | 472,637 | 144,618 | 33,020 | 0.4980 | 41.2 |
Microgrid—Highest Cost | 7% | 520,121 | 133,395 | 44,818 | 0.6280 | 30.4 |
Scenario | Max Annual Capacity Shortage | NPC (USD) | CAPEX (USD) | OPEX (USD/Year) | LCOE (USD/kWh) | Renewable Fraction (%) |
---|---|---|---|---|---|---|
Microgrid—Base Case | 0.1% (99.9% reliability) | 462,515 | 15,500 | 44,999 | 0.4400 | 0 |
Microgrid—Base Case | 0% (100% reliability) | 462,515 | 15,500 | 44,999 | 0.4400 | 0 |
Microgrid—Lowest Cost | 0.1% | 412,576 | 134,163 | 24,042 | 0.3370 | 64.2 |
Microgrid—Mid Cost | 0.1% | 476,428 | 113,776 | 36,507 | 0.4530 | 37.3 |
Microgrid—Highest Cost | 0.1% | 522,161 | 136,754 | 44,665 | 0.5720 | 35.4 |
Region | Distance | System Type | LCOE (USD/kWh) | CAPEX (USD) | OPEX (USD/Year) | NPC (USD) | Renewable Fraction (%) |
---|---|---|---|---|---|---|---|
Chin (Terrain) | Short (<10 km) | Grid Extension | 0.1470 | 307,247 | 7555 | 346,075 | 100 (Hydro) |
Chin (Terrain) | Long (15–20 km) | Grid Extension | 0.3192 | 554,259 | 15,620 | 661,723 | 100 (Hydro) |
Chin (Terrain) | — | Microgrid (Base) | 0.4500 | 119,176 | 31,195 | 429,057 | 29.6 (Solar + PV + Diesel) |
Nay Pyi Taw | Short (<10 km) | Grid Extension | 0.0833 | 208,237 | 5475 | 229,370 | 100 (Hydro) |
Nay Pyi Taw | Long (15–20 km) | Grid Extension | 0.1311 | 282,619 | 7038 | 317,046 | 100 (Hydro) |
Nay Pyi Taw | — | Microgrid (Base) | 0.4400 | 15,500 | 44,999 | 462,515 | 0 (Solar + PV + Diesel) |
Region | Influential Factor | LCOE Deviation (USD/kWh) | Direction of Impact |
---|---|---|---|
Chin State | Diesel Price (USD 0.7–1.3/L) | +0.178 | Increase |
Battery Cost (USD 300–150/kWh) | –0.014 | Decrease | |
Discount Rate (8–12%) | ±0.018 | Both directions | |
PV Capital Cost (USD 2500–1250/kW) | ±0.007 | Both directions | |
Nay Pyi Taw | Diesel Price (USD 0.7–1.3/L) | +0.112 | Increase |
PV Capital Cost (USD 2500–1250/kW) | –0.076 | Decrease | |
Discount Rate (8–12%) | ±0.011 | Both directions | |
Battery Cost (USD 300–150/kWh) | 0.000 | None |
Rank | Chin State (Terrain) | Nay Pyi Taw (Flat) |
---|---|---|
1 | Diesel Price | Diesel Price |
2 | Discount Rate | PV Cost |
3 | Battery Cost | Discount Rate |
4 | PV Cost | Battery Cost |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Oo, T.T.; Cho, K.-w.; Park, S.-j. Techno-Economic Comparison of Microgrids and Traditional Grid Expansion: A Case Study of Myanmar. Energies 2025, 18, 4988. https://doi.org/10.3390/en18184988
Oo TT, Cho K-w, Park S-j. Techno-Economic Comparison of Microgrids and Traditional Grid Expansion: A Case Study of Myanmar. Energies. 2025; 18(18):4988. https://doi.org/10.3390/en18184988
Chicago/Turabian StyleOo, Thet Thet, Kang-wook Cho, and Soo-jin Park. 2025. "Techno-Economic Comparison of Microgrids and Traditional Grid Expansion: A Case Study of Myanmar" Energies 18, no. 18: 4988. https://doi.org/10.3390/en18184988
APA StyleOo, T. T., Cho, K.-w., & Park, S.-j. (2025). Techno-Economic Comparison of Microgrids and Traditional Grid Expansion: A Case Study of Myanmar. Energies, 18(18), 4988. https://doi.org/10.3390/en18184988