1. Introduction
Extruded High Voltage Direct Current (HVDC) cables have been extensively used in power transmission in the recent few decades, pushed by the need to achieve a higher transmission capacity, and hence, a higher temperature and voltage ratings [
1,
2]. Extruded HVDC cables must pass qualification tests established by CIGRÉ Technical Brochure (TB) 852:2021 to ensure that they meet the required performance and reliability when used in service [
3]. In turn, qualification tests consist of prequalification tests (PQTs) and type tests (TTs).
Focusing on the PQT, the core of this test is the “long duration voltage test” [
3], consisting of 360 daily load cycles at a constant DC voltage. This long-lasting test has been applied for many years (starting from CIGRÉ TB 219:2003 [
4] and continuing with CIGRÉ TB 496:2012 [
5]) to evaluate the long-term performance of HVDC extruded cables. For this reason, it is a milestone test in the qualification of HVDC extruded cable systems.
However, in 2021, CIGRÉ TB 852 introduced a new extension of qualification test (EQT) as a reflection of the industry’s progression towards higher voltage levels. Such an EQT, consisting of only 82 daily cycles at a higher DC voltage than the PQT, aims at verifying in a much shorter time the long-term performance of modified HVDC cable systems that were already qualified. In this way, there is no need to repeat the full PQT, thus dramatically cutting the test time of the cable system from ≈1 year to less than 3 months.
The structure of EQT load cycles established by CIGRE TB 852:2021 [
3] is analogous to the structure of load cycles of the PQT: as hinted at above, the difference is in the applied voltage and in the number of daily load cycles, as illustrated in
Table 1 for Voltage Source Converter (VSC) cables [
3].
Table 1 shows that the EQT and PQT involve a series of load cycles lasting 1 day each, with a steady DC voltage applied all over the load cycles. The load cycles are grouped into three periods, each with different heating currents:
the “load cycle” (LC) period, where every day, the cable is first heated with the switching conductor current on, and then naturally cooled, with the switching conductor current off (for more details, see [
3]);
the “high load” (HL) period, with such a current as to keep the design temperature of the cable conductor at Tcond,max, and the design temperature drop across cable insulation at ΔTmax throughout the period;
the “zero load” (ZL) period, where no heating current is applied to the cable.
Figure 1 shows the temperature profile within the insulation of a 500-kV DC-XLPE cable during a 24 h load cycle of the LC, HL, and ZL periods, when one sets the conductor temperature
Tcond =
Tcond,max = 70 °C and temperature drop across cable insulation Δ
T = Δ
Tmax.
Table 1 shows that the sequence of load cycles and the polarity of the applied voltage of the EQT is similar to that of the PQT, while the number of cycles and the test voltage levels are different: 82 cycles for EQT, much less than the 360 cycles for PQT;
UEQ1 = 1.68
U0 for the EQT, which is greater than
UTP1 = 1.45
U0 for the PQT.
According to [
3], the EQT can replace the PQT only in certain circumstances (reported in detail in Cigré TB 852 Section 10.4 [
3]), such as when the modifications of the previously qualified cable do not affect the insulation material, the fundamental manufacturing technique, and the electric field level. However, the question arises whether the greater voltage level and the different structure of the EQT compared to the PQT can compensate for the much shorter duration, as well as whether the greater voltage (being farther from the rated voltage
U0) is also representative of the PQT voltage (closer to
U0) of the working conditions of cables in service, with the relevant stresses. In summary, it is important to assess if the EQT is as challenging as the PQT, as well as if it is well representative of the long-term behavior of the cable system down to service stresses. The answers to these questions are very important, especially for cable stakeholders, which have to be well-aware of the differences and consequences of the EQT compared to the PQT. Unfortunately, direct experimental tests on full-size cable systems for answering these questions are practically unfeasible, as illustrated later in this paper.
On the other hand, researchers have developed a procedure for the life and reliability estimation of HVDC cables subjected to qualification load cycles in a series of previous publications [
6,
7,
8,
9,
10]. The temperature profile and thermal properties of the cable insulation were extensively investigated in [
6]. The first development of the reliability model of HVDC cables under load cycles was introduced in [
7], while the transient electric field calculations that replaced the approximated analytical electric field calculations were introduced in [
9] for PQT load cycles. Different sets of periodic 24 h and 48 h load cycles, i.e., type test load cycles, were applied to the cable in [
10].
While in previous works, the authors of this paper studied the life and reliability of various types of HVDC cables under both prequalification and type test conditions [
6,
7,
8,
9,
10], this paper comes to investigate—for the first time in the literature, as to our best knowledge—the electrothermal life of extruded 500 kV DC-XLPE-insulated cables under EQT load cycles, and to compare the results obtained under EQT conditions with those previously obtained under PQT conditions. Therefore, the results obtained in this paper can help in providing a preliminary answer to the above questions. This goal has been achieved in the present investigation by properly modifying the previously developed procedure for the life and reliability estimation of HVDC cables [
6,
7,
8,
9,
10]—implemented in the Matlab
TM (R2024b Update 5 (24.2.0.2863752), 64-bit (win64)) environment—to make it applicable to EQT load cycles in addition to PQT and type test load cycles, which are already considered in the former version of the procedure.
This paper is structured as follows. In
Section 2, the theoretical background of the procedure for the life and reliability estimation of HVDC cables subjected to qualification load cycles is given, emphasizing the modifications to the previous version of the procedure—and to the relevant Matlab
TM code—implemented in this investigation to make the procedure applicable to EQT load cycles. In
Section 3, the case study for the application of the procedure to EQT load cycles and the comparison with PQT load cycles are described.
Section 4 illustrates the results obtained, while
Section 5 discusses some aspects of the loss-of-life fraction estimation and the validation of the life evaluation algorithm in more detail. In
Section 6, a proposal for a modified extension of qualification test (MEQT) is put forward, which is based on the obtained results.
Section 7 draws some final conclusions.
2. Theoretical Background
The procedure developed by the authors for the evaluation of the life and reliability of HVDC cables under qualification (i.e., prequalification test and type test [
3]) load cycles is illustrated in [
7,
9,
10]. It begins with collecting the data of the cable electrical and thermal properties, the load cycles, and the thermal data of the cable environment. First, the transient temperature during qualification load cycles is calculated inside the insulation thickness. Then, two methods of electric field calculation are chosen for the sake of completeness, i.e., the rigorous numerical computation of the electric field via the solution of Maxwell’s equations and the analytical approximate Eoll’s formula. By knowing the distributions of the transient temperature and electric field within the insulation during qualification load cycles, the fraction of life lost over all qualification load cycles can be estimated at each location within the insulation. Then, the life of the cable under qualification load cycling conditions is estimated, followed by the reliability estimation as a function of time and a final thermal stability check [
6]. In [
9], the rigorous numerical calculation of the electric field was introduced in the life estimation procedure for 320 kV-HVDC cables subjected to the prequalification test (PQT). Later, in [
10], the authors broadened the investigation to include the type test (TT). Subsequently, this procedure has been used to analyze MIND cables as well [
11].
The procedure consists of the following stages—or, better, numerical algorithms run in the following sequence:
1st stage: algorithm for the computation of the transient temperature in the cable insulation during qualification load cycles;
2nd stage: algorithm for the computation of the electric field in the cable insulation during qualification load cycles;
3rd stage: algorithm for the evaluation of the electrothermal life of the cable under qualification load cycles;
4th stage: algorithm for the evaluation of the reliability of the cable as a function of cycling time;
5th stage: algorithm for the final thermal stability check.
As anticipated in the Introduction, in this paper, the above procedure has been improved and broadened to also treat extension of qualification (EQT) load cycles—which are fairly different from TT and PQT load cycles, as shown in
Table 1—and the relevant electric field profiles—which, consequently, are fairly different from those obtained during TT and PQT load cycles. The first three algorithms, employed in the case study in
Section 3 and
Section 4, are explained in detail hereafter, together with the modifications required to adapt them to the EQT, while stages 4 and 5 are skipped here for the sake of brevity (more details on them can be found, e.g., in [
6,
10]).
By using the improved procedure—and the relevant MatlabTM code—PQT, TT, and EQT load cycles can be now treated in an exhaustive way with the estimation of transient temperature profiles, transient field profiles, insulation loss-of-life fractions, cable life, and reliability—with the final check on thermal runaway.
2.1. Transient Temperature
The algorithm for the calculation of the transient temperature within the insulation of the cable throughout qualification load cycles (1st step of the procedure) is based on IEC Standard 60853-2 [
12]. This algorithm comes from another one previously developed for HVAC cables, which was validated in [
13] by comparing the algorithm results with experimental data from [
14]. Later on, the algorithm was re-adapted in [
7,
9,
10,
11] to HVDC cables. This was quite straightforward, as the transient temperature calculation is simpler for HVDC than for HVAC cables, since the former cables are without skin and proximity effects in the conductor, induce losses in outer metallic layers, and have typically negligible dielectric losses [
15]—unless thermal runaway occurs [
6].
The temperature profiles in
Figure 1 have been calculated using this algorithm.
2.2. Electric Field Distribution
The algorithm for the calculation of the transient electric field within the insulation of the cable throughout qualification load cycles (2nd step of the procedure) performs the computation of the transient electric field profile within the cable insulation by means of the numerical iterative solution of Maxwell’s Equations (1)–(4) [
9,
10,
16]:
where
E = electric field vector,
J = current density vector, σ = density of free charges,
= electrical conductivity of the insulation,
σ0 = value of
at
T0 = 0 °C and
E0 ≈ 0 kV/mm,
= temperature coefficient of
,
= stress coefficient of
[
6],
ε0 = permittivity of free space, and
εr = relative permittivity of the dielectric.
In Equations (1)–(4), and coefficients represent the charge conduction characteristics in the cable insulation in the macroscopic conduction model. The coefficient rules the exponential dependence of conductivity on temperature variation, while the coefficient governs the exponential dependence of conductivity on the electric field.
The transient electric field calculation algorithm was validated in [
9], comparing the algorithm results for a “standard” 450 kV HVDC cable with previous calculations from [
17].
The application to the EQT of the procedure for the life and reliability estimation of HVDC cables under qualification load cycles has required adapting the algorithm for transient electric field calculation to EQT load cycles, which feature a different voltage level compared to PQT and TT load cycles, and resetting the step duration in the time domain, the mesh size in the space domain, and the underrelaxation factors in the iterative numerical solution of Maxwell’s equations to ad hoc values. In this way, convergence in the iterative numerical calculation of the electric field has been achieved during the EQT cycles as well.
2.3. Life Evaluation
The algorithm for the calculation of the life of the cable insulation subjected to qualification load cycles (3nd step of the procedure) employs an ad hoc electrothermal life model, called the IPM (Inverse Power Model)-Arrhenius model [
2], to assess the lifespan of the HVDC cable under qualification load cycling conditions. Specifically, it estimates the accumulated fraction of life lost by the cable insulation during qualification load cycles (see
Table 1 for PQT and EQT), as well as the life of the location of greatest electrothermal stress in the insulation, which determines the cable’s overall life. These estimates rely on Miner’s law of cumulated aging [
18], using the equations listed below [
7,
9,
10,
11]:
where
is life at DC electric field
E and temperature
T,
T/
TD − 1/
T (
ED,
TD and
LD being design electric field, temperature, and life of cable insulation, respectively),
nD is the value of life exponent at
TD,
B = ∆
W⁄
KB, ∆
W is the activation energy of the main thermal degradation reaction,
KB = 1.38 × 10
−23 J/
K is the Boltzmann constant,
bET is the factor of synergism between the thermal and the electrical stress,
LFcycle(
r) is the loss-of-life fraction over all the cycles at a certain radius
r within the cable insulation, and
Kcycle(
r) is the number of cycles to failure at a certain radius
r within the cable insulation, with
r ranging from the inner insulation radius
ri to the outer insulation radius
ro.
For more details on the algorithm for the evaluation of the life and reliability of HVDC cables under time-varying load cycles—skipped here for brevity—the readers should address [
7,
9,
10,
11].
The validation of the algorithm for the calculation of the life of the cable insulation subjected to qualification load cycles (3rd step of the procedure for life and reliability evaluation of HVDC cables under time-varying load cycles) is much more cumbersome than that of the previous two algorithms. It is unfeasible in practice for full-size cables—as illustrated in
Section 5—and it is also quite hard for small size test objects as flat specimens or mini cables, because it would require the application of a huge number of transient loads to cover all possible—or at least typical—load cycles encountered on site. To our best knowledge, only constant stress electrothermal life models have been—quite rarely, indeed—validated by comparison with the electrothermal Accelerated Life Test (ALT) [
19] results, performed at selected combinations of a constant voltage and temperature. An electrothermal model which was validated in this way is the IPM-Arrhenius model, shown in Equation (5), whose parameters
nD (relevant to the IPM electrical life model), B (relevant to the Arrhenius life model), and
bET (relevant to the synergism between electrical and thermal stress) were estimated for XLPE and EPR-insulated mini cables tested under various combinations of a constant temperature and constant (in the rms sense) AC voltage at power frequency, as reported, e.g., in [
20]. This is the first reason why the IPM-Arrhenius model in Equation (5) was selected for use in this procedure.
The second reason—even sounder in the case of HVDC extruded cables—is that in fact, the IPM-Arrhenius model is the combination of two models, both of which are used in reference International Standards for HVDC extruded cables:
- (a)
the IPM electrical life model with
L0 =
LD = 40 years,
n0 =
nD = 10 is the model taken in CIGRÈ TB 852 [
3] (the reference Standard for HVDC extruded cables, see above), precisely to establish the voltage level and the duration of TT, PQT, and EQT load cycles (see Appendix A, Clause A.1, of [
3]);
- (b)
the Arrhenius thermal life model is the reference life model taken in IEC 60216 [
21], to provide guidelines for the thermal endurance evaluation of electrical insulating materials—among which extruded insulation for HVDC cables is included.
Therefore, when applied to DC-XLPE cable insulation, the IPM-Arrhenius model is used in the procedure with the following values of parameters:
LD = 40 years,
nD = 10,
B = 12,430 K (derived from XLPE mini cable ALT data after [
20]), and
bET = 0 (which can be shown to correspond to the worst case of electrothermal synergism for cable life) [
2,
8].
For all these reasons, although the validation of the algorithm for the life and reliability evaluation of HVDC cables under time-varying load cycles was not performed in a direct way because it is extremely difficult—or practically unfeasible—the IPM-Arrhenius model used in the procedure can be deemed as a sound, reliable, and accurate tool for electrothermal life estimation.
The application to the EQT of the procedure for the life and reliability estimation of HVDC cables under qualification load cycles has required adapting the algorithm for the evaluation of the electrothermal life of the cable to EQT load cycles, by recasting the calculation of the loss-of-life fractions within load cycling periods to the different durations of the various load cycling periods of the EQT compared to PQT (see
Table 1) and TT. This has implied proper modifications, in particular, to relationships (6) and (7), in order to perform the following:
- (1)
properly compute the loss-of-life fractions LFcycle(r) at each cable insulation radius r within the grouped load cycles of the LC, HL, and ZL periods, which have a different duration in the EQT compared to the PQT;
- (2)
properly compute the number of cycles to failure Kcycle(r) at each cable insulation radius r.
3. Case Study
The studied cable is a DC extruded cable for use with VSC. It has a rated power of 960 MW in a monopolar scheme under a rated voltage of 500 kV and rated current of 1920 A. The single core conductor is made of copper with a cross-section of 2000 mm
2. The design temperature of the cable conductor is set to
Tcond,max = 70 °C. The conductor is insulated by a 28.1 mm thick DC-XLPE (Cross Linked Polyethylene for DC applications) insulation between two layers of a semiconductive material (usually Polyethylene-based with added carbon black). The design temperature drop across the cable insulation is set to Δ
Tmax = 15.7 °C. The thickness of the inner semiconductive layer is 2 mm, while the thickness of the outer semiconductive layer is 1 mm. The latter layers are shielded by a 1 mm thick metallic screen. Then, a thermoplastic sheath covers the aforementioned layers with a thickness of 4.5 mm. The design life is considered
LD = 40 years, with a life exponent of
nD = 10. As for the values of life exponent
nD = 10 and design life
LD = 40 y, used in relationship (5), as pointed out at
Section 2.3, these values are derived from Appendix A, Clause A.1, of TB 852, where voltages and durations of qualification tests are established, starting from the Inverse Power Model (IPM) with these life exponent and design life values. Since in this study, the EQT according to TB 852 is analyzed, it is important to set these values in the life model (5). In TB 852:2021, the value of life exponent
n = 10 is considered as a conservative estimate, although extruded insulations for HVDC cables with values of
n greater than 10 have been developed over the years (see e.g., [
22,
23,
24,
25,
26]).
The cable undergoes PQT load cycles, i.e., 160 “24-h” LC, 80 HL, and 120 ZL load cycles; then (in another simulation run), it undergoes EQT load cycles, i.e., 40 “24-h” LC, 36 HL, and 6 ZL load cycles according to TB 852 (see
Table 1) [
3]. The calculations are carried out for three different sets of values of
coefficients (see
Table 2), in order to scan the various conductivity behaviors of different insulation compounds. Further attention will be given to the medium values that represent DC-XLPE insulation in the literature [
27,
28].
5. Discussion
These results deserve more analysis and discussion, especially those relevant to loss-of-life fraction and life estimation.
In particular, to confirm the thermal effect of the fractions of life lost in the HL period with respect to those in the LC period in both the PQT and EQT (the fraction of life lost during ZL cycles is practically irrelevant, as hinted at above), the fractions of life lost in the HL and in the LC period have also been estimated with a simplified version of the IPM-Arrhenius electrothermal life model (5). In such a simplified version of the IPM-Arrhenius model, the IPM electrical life model and the electrothermal synergism factor are replaced with the life model used in [
3], Appendix A, clause A.1, to determine the test voltage
UT from the system voltage
U0, design life
LD, and test duration
LT (in clause A.1 of [
3],
UT =
Vdc,
U0 =
V0,
LD =
t0 = 40 years,
LT =
t1), namely:
where, consistently with [
3], Appendix A, clause A.1,
nD = 10, as in Equation (5). Of course, this model yields
LPQT = 360 days when
UT =
UTP1 = 1.45
U0 and
LEQT = 82 days when
UT =
UEQ1 = 1.68
U0.
By inserting (9) in (5) in place of the IPM and of the electrothermal synergism factor, only the Arrhenius thermal life model is left active, thereby excluding the electric field effect on the loss of life, as follows.
where
T(
r,
t) is the transient temperature at radius
r within cable insulation and at time
t during the load cycles, as in
Figure 1. B = 12,430 (K) for DC-XLPE comes from the results after [
20] for XLPE-insulated mini cables.
Introducing this simplified version of Equation (5) in the algorithm for life evaluation (3rd step of the procedure described in
Section 2, see
Section 2.3), the values of the ratio
have been calculated at the inner insulation surface, 50% of insulation thickness (=middle insulation), and outer insulation surface for the PQT and EQT.
Figure 6 shows the bar plot of the ratio
LFHL/
LFLC for the PQT (left part of
Figure 6) and the EQT (right part of
Figure 6). These same values are listed in
Table 7 for a more accurate comparison with the values of the ratio
LFHL/
LFLC obtained when using the rigorous IPM-Arrhenius electrothermal model in Equation (5) of the procedure with the three sets of
a,
b coefficients for the PQT and the EQT; note that these latter values—referred as “E-T” rigorous values in
Table 7—can be deduced from
Figure 3a–c and
Figure 4a–c, respectively, for the PQT and EQT with a
L, b
L, a
M, b
M, and a
H, b
H.
The values of the ratio
LFHL/
LFLC reported in
Figure 6 and
Table 7 are all greater than 1: this clearly emphasizes that the loss of life during the whole HL period is greater than that during the whole LC period (overall ≈2 times and ≈4.5 times greater in PQT and EQT, respectively). It also emphasizes that the loss-of-life ratio is greater in the EQT compared to the PQT, due to the longer duration of the HL period in the EQT compared to the duration of the HL period in the PQT, as hinted at above. Hence, the approximate results obtained with the Arrhenius model agree overall with the findings and the discussion of the algorithm used in this paper by applying the electrothermal life model.
In addition, let us note that the results in
Table 7 can be explained more in detail as follows.
When the Arrhenius simplified approach is used, only temperature is active in degrading the cable insulation; since the inner insulation always has the highest temperature—and this happens steadily during the whole HL—inner insulation has the greatest loss of life and the ratio LFHL/LFLC is the greatest at the inner insulation. On the contrary, moving from the inner to outer insulation, the situation is the opposite. Indeed, the outer insulation has the lowest temperature—and this happens steadily during the whole HL—hence, it has the lowest loss of life, and the ratio LFHL/LFLC is the lowest at outer inner insulation.
When the rigorous electrothermal approach is used, the inner insulation during the HL period has a lower field than at room temperature due to the higher temperature (remember that the field at inner insulation drops as temperature increases, see
Figure 2a), and this reduces the field-induced loss of life during the HL period (although the ratio remains >1); conversely, the outer insulation during the HL period has a higher field than at room temperature due to the higher temperature (remember that the field at the outer insulation rises as temperature increases, see
Figure 2a), and this raises the field at the outer insulation and increases the field-induced loss of life during the LC. Hence, the ratio
LFHL/
LFLC is the lowest at the inner insulation, increases at the middle insulation, and is the highest at the outer insulation when the rigorous electrothermal approach is used.
Let us emphasize that—as hinted at in
Section 2—the transient thermal calculations (1st step of the procedure) and the transient electric field calculations (2nd step of the procedure) have been validated with an independent validation (namely, comparison with experimental case for the 1st step, see
Section 2.1, and a software developed by other authors for the 2nd step, see
Section 2.2), so no more doubts should arise about the precision of the code’s outputs for field and temperature. On the contrary, the direct experimental validation of the life estimation algorithm (3rd step of the procedure), although relying on a sound and validated constant stress electrothermal life model—the IPM-Arrhenius model—and on the good old Miner’s law of cumulated aging, is practically unfeasible for full-size cable systems (see
Section 2.2). Let us explain here in more detail why; this is essentially for two reasons.
- (1)
The detailed results of the PQT and EQT—with the description of possible failures and failure times—are kept confidential by the involved parties, namely manufacturers and utilities.
- (2)
The validation of (life lost and) life estimates for full-size cable systems would require finding a manufacturer available to arrange, in a huge and dedicated lab, a suitable number of cable loops for the PQT, as well as for the EQT (say, three as a minimum, from five to ten for a better statistical processing required for accuracy estimation), apply PQT load cycles, as well as EQT load cycles, and wait for a time long enough to cause the breakdown of all loops for the sake of good statistical processing; eventually, results would have to be processed and estimates of the kind provided by our procedure would have to be derived. Our computations (see
Table 5) show that for the PQT, the average failure time might range from two to five times the duration of the test, i.e., from 2 to 5 years, but also long-lasting outliers have to be accounted for: the last breakdown might take even more than two to three times the average, i.e., more than 10–15 years for the PQT! The same procedure should be repeated for the EQT: this would take something less than one-quarter of the time spent for the PQT (see
Table 6), but this is still a few years! Of course, this experimental procedure is unfeasible—and even if it were feasible, no manufacturer would disclose these results.
This is precisely the reason why this simulation procedure and the relevant algorithms have been developed, first for the TT and PQT, and here for the EQT. And since the third algorithm is the hardest to verify, it can be deemed as very satisfactory if the life estimates obtained are in line with the experimental evidence of qualification tests—as their results are more or less fuzzily disclosed by manufacturers and utilities in a generic way—namely, well-designed, manufactured, and installed cables do pass qualification tests without problems—and going down to service stresses, CIGRE TB 815:2015 [
31] confirms this satisfactory long-term behavior obtained in the PQT with the extremely rare failures reported for HVDC cables in service until 2015, all qualified according to TB 219:2003 [
4] and TB 496:2012 [
5], thus in the absence of the EQT option. This outcome is perfectly in line with the results in
Table 3 and
Table 5 for the PQT, as well as with those in
Table 4 and
Table 6 for the EQT. In particular,
Table 5 and
Table 6 show that the time to failure forecasts obtained with the procedure illustrated here are always longer than the duration of the PQT and EQT, respectively. This is indirect evidence that the procedure is satisfactory—although its accuracy for a life estimate cannot be evaluated. The alternative would be simply doing nothing, i.e., refraining from estimating life and reliability simply because the accuracy of the procedure cannot be directly evaluated. As engineers, the authors aim at providing cable stakeholders with tools that help solve problems: this is the reason why in the authors’ opinion, it is preferable to provide an uncertain estimate—in line, or not against, the experimental evidence—than doing nothing. In the end, utilities companies always ask power cable engineers the following: “how long will this cable last in certain conditions?”
For this reason, in our opinion, the best comparison to be made for validating these results is the comparison with the PQT and EQT test durations (see
Table 5 and
Table 6), as this provides an estimation about whether the cable will withstand the test or not.
Table 5 and
Table 6 reveal that the most stressed point always has a life greater than the duration of the PQT and the EQT, respectively, for all the conductivity coefficient sets. This indicates that the case study cable will pass both the EQT and the PQT load cycles. Hence, the results of the analysis carried out in this paper are in fair agreement with the common general evidence that well-designed, manufactured, and installed HVDC extruded cable loops do pass the PQT and EQT with broad margin. This is certainly an indirect, but important experimental validation of the results obtained. However, the p.u. values of life in
Table 5 (namely those for the PQT) are greater than the homologous values in
Table 6 (namely those for the EQT). This indicates that EQT conditions are overall more stressful than PQT conditions—at least for this case study cable, but similar results are obtained for other cable types, omitted for brevity here.
6. Proposal for a Modified Extension of Qualification Test Procedure
It should be noted that EQT load cycles are performed at a voltage which is much greater than the rated voltage of the cable system U0 compared to the PQT, and conversely, the duration of the EQT load cycles is much shorter than the design life of the cable system, LD. Hence, if it is true that the EQT shortens the testing times and emphasizes the role of high load conditions, its capability to really assess the long-term behavior of the cable system in testing conditions representative of service conditions is poorer than that of the PQT.
Therefore, as a response to the findings and results revealed in this paper, the authors propose two novel modified test procedures for the extension of qualification test, namely, modified extension of qualification test 1 (MEQT1) and modified extension of qualification test 2 (MEQT2). The main aim of this technical proposal is to make a compromise between the beneficial need to speed up the long-term tests (in certain conditions), as in the EQT, while keeping the results predictive of real-world performance, as in the long-term load cycles of the PQT.
The details of the two proposals, MEQT1 and MEQT2, in terms of applied constant DC voltage, overall duration, and duration of the load cycling periods, are reported and compared with the PQT and EQT in
Table 8. As
Table 8 shows, the two proposals MEQT1 and MEQT2 are based on extending the total EQT duration to 180 days instead of 82 days and reducing the test voltage from
UEQT1 = 1.68
U0 to
UMEQT = 1.55
U0: this latter value has been determined following the same approach as for
UTP1 and
UEQT1 in Appendix A, Clause A.1 of TB 852 [
3], namely, using the IPM of Equation (9). The difference between MEQT1 and MEQT2 is the value of the ratio between the duration of the three cycling periods LC, HL, and ZL, and the overall duration of the test, as follows:
- (A)
the 1st proposal, i.e., MEQT1, keeps the same ratio between the duration of LC, HL, and ZL periods and the overall test duration as in the PQT;
- (B)
the 2nd proposal, i.e., MEQT2, practically keeps the same ratio between the duration of LC, HL, and ZL periods and the overall test duration as in the EQT.
Since the difference is the ratio between the duration of the three cycling periods LC, HL, and ZL and the overall duration of the test, selecting MEQT1 means following the structure of the PQT and giving all three periods a fairly similar weight compared to the overall duration of the test, while selecting MEQT2 means following the structure of the EQT and giving much more emphasis to the high load period and its enhanced thermal stress, as one might have easily guessed qualitatively, but this investigation has highlighted more accurately in a quantitative way.
Of course, these are just preliminary proposals that should be broadly discussed in the scientific community, also based on the experience gathered in the PQT and EQT.
7. Conclusions
In this paper, the authors investigated the electrothermal life of DC-XLPE-insulated cables that underwent the prequalification test (PQT) and extension of qualification test (EQT) conditions according CIGRÉ Technical Brochure 852. First, the transient temperature across the insulation was computed throughout the PQT and EQT load cycles. Then, the transient electric field profile was computed, considering three sets—i.e., low, medium, and high—of coefficients of electrical conductivity. The calculations are closed with the evaluation of the fractions of life lost throughout the cycles and of the life of DC-XLPE insulation.
The results show similar patterns of fractions of life lost and life across the insulation in both the PQT and EQT, where the insulation experiences the greatest stress at its inner surface for low and medium set of conductivity coefficients, and at its outer surface for high set conductivity coefficients. According to the electrothermal life model, the studied cable is expected to pass both the PQT and EQT and to withstand the electrothermal stresses applied during both tests. Hence, the results of the analysis carried out in this paper—in agreement with other studies relevant to similar cables, omitted here for the sake of brevity—are in fair agreement with the common general evidence that well-designed, manufactured, and installed HVDC extruded cable loops do pass the PQT and EQT with broad margin. This is certainly an indirect but important experimental validation of the results obtained.
The results show that the electrothermal loss of life during the EQT is double that during the PQT compared to the duration of each test (i.e., 360 days and 82 days, respectively). The dominance of high load cycles in the EQT compared to only a few zero load cycles might be the justification (the HL percentage of the total test duration is 44% in EQT compared to only 22% in PQT).
However, it should be noted that EQT load cycles are performed at a voltage which is much greater than the rated voltage of the cable system U0 compared to the PQT, and conversely, the duration of the EQT load cycles is much shorter than the design life of the cable system, LD. Hence, if it is true that the EQT shortens the testing times, its capability to really assess the long-term behavior of the cable system in testing conditions representative of service conditions is poorer than that of the PQT. For this reason—notwithstanding the fact that the EQT seems quite challenging in terms of loss-of-life fraction and estimated life—the PQT is recommended as an optimal compromise between the contrasting needs of, on the one hand, reducing testing time and, on the other hand, reproducing cable system stresses in service as closely as possible.
As an alternative, as well as a response to the findings of this paper, the authors propose two novel modified test procedures for the extension of qualification test, namely, modified extension of qualification test 1 (MEQT1) and modified extension of qualification test 2 (MEQT2), their difference being the value of the ratio between the duration of the three cycling periods LC, HL, and ZL and the overall duration of the test; selecting MEQT1 means following the structure of the PQT and giving all three periods a fairly similar weight compared to the overall duration of the test, while selecting MEQT2 means following the structure of the EQT and giving much more emphasis to the high load period and its enhanced thermal stress, as this investigation has highlighted in a quantitative way. The main aim of this technical proposal is to make a compromise between the beneficial need to speed up the long-term tests (in certain conditions) as in the EQT, while keeping the results predictive of real-world performance as in the long-term load cycles of the PQT. Of course, these preliminary proposals should be broadly discussed in the scientific community, also based on the experience gathered in the PQT and EQT.