Next Article in Journal
Numerical Study of the Condenser of a Small CO2 Refrigeration Unit Operating Under Supercritical Conditions
Previous Article in Journal
The Environmental Dimension of Sustainable Development in Relation to the Transition from Brown to Green Energy—A Case Study of Poland from 2005 to 2023
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Analysis of Renewable Energy Absorption Potential via Security-Constrained Power System Production Simulation

1
Economic and Technological Research Institute, State Grid Gansu Electric Power Company, Lanzhou 730050, China
2
College of Electrical Engineering, Sichuan University, Chengdu 610065, China
*
Author to whom correspondence should be addressed.
Energies 2025, 18(11), 2994; https://doi.org/10.3390/en18112994
Submission received: 15 April 2025 / Revised: 25 May 2025 / Accepted: 3 June 2025 / Published: 5 June 2025

Abstract

The increasing penetration of renewable energy sources presents significant challenges for power system stability and operation. Accurately assessing renewable energy absorption capacity is essential to ensuring grid reliability while maximizing renewable integration. This paper proposes a security-constrained sequential production simulation (SPS) framework, which incorporates grid voltage and frequency support constraints to provide a more realistic evaluation of renewable energy absorption capability. Additionally, hierarchical clustering (HC) based on dynamic time warping (DTW) and min-max linkage is employed for temporal aggregation (TA), significantly reducing computational complexity while preserving key system characteristics. A case study on the IEEE 39-bus system, integrating wind and photovoltaic generation alongside high-voltage direct current (HVDC) transmission, demonstrates the effectiveness of the proposed approach. The results show that the security-constrained SPS successfully prevents overvoltage and frequency deviations by bringing additional conventional units online. The study also highlights that increasing grid demand, both locally and through HVDC export, enhances renewable energy absorption, though adequate grid support remains crucial.

1. Introduction

Driven by the global shift towards decarbonization to meet climate goals, global renewable capacity additions in 2023 reached 473 GW, accounting for 86% of all electricity capacity additions, according to IRENA [1]. The share of renewable energy in global electricity capacity rose to 43%, up from 28.2% in 2014. However, the intermittent and unpredictable nature of renewable sources makes their integration into power systems more complex. This leads to the share of renewable energy in electricity production lagging behind, standing at only 29.1%, compared to 22.2% in 2014. While progress has been made in increasing renewable capacity, the integration of intermittent sources into power systems remains a significant challenge. As such, understanding renewable energy absorption capacity is crucial for achieving the energy goals set forth at COP28.
International experience with the curtailment of wind and solar energy in bulk power systems has been reviewed in [2], highlighting that renewable energy absorption is influenced by various factors, including grid infrastructure, power system stability, market structure, and technological advancements. In [3], artificial intelligence algorithms were employed to capture the complex impact of these factors on absorption capacity. The study developed the quantum harmony search optimized modified discounted mean squared forecast error combined forecast model to predict renewable energy absorption potential under different scenarios. In [4,5], EnergyPLAN was used to simulate the energy system, incorporating technologies across the electricity, heat, and transport sectors. Three scenarios with different shares of renewable energy in electricity demand were set up to assess renewable energy absorption capacity.
The intermittent and unpredictable nature of renewable energy poses significant challenges to real-time supply–demand balancing, ultimately leading to the inability to fully absorb renewable generation. To reflect this key factor affecting renewable energy absorption, a logic-based method was proposed in [6], based on the idea that each controllable resource, such as thermal power, pumped storage, and grid interconnection, adjusts to maintain supply–demand balance. The total non-controllable imbalance was allocated to each controllable resource while ensuring compliance with their operating limits. A minute-based economic dispatch model was employed in [7] to capture the effects of solar PV intermittency. The study defines the PV hosting capacity of a transmission network as the maximum solar PV capacity that can be connected to the system without requiring significant upgrades to its circuits to ensure stable operation. However, real-time grid balancing is constrained not only by the operating limits of controllable resources but also by transmission capacity. To address this, a power flow analysis method that considers transmission congestion was proposed in [8] to determine renewable power curtailment, offering a measure of the grid’s renewable energy absorption capacity.
The integration of renewable energy, replacing conventional synchronous units, leads to a decline in system inertia and worsens frequency response under external disturbances. To address these issues, the commitment strategy of conventional synchronous units (e.g., thermal and hydro) has become crucial. Frequency-related constraints—such as the rate of change of frequency (RoCoF), frequency deviation at quasi-steady-state, and maximum transient frequency deviation—are introduced into traditional unit commitment models. These constraints are typically derived from a uniform frequency response model, which is a reduced representation of the full-order frequency response model [9,10,11,12,13]. By applying the uniform frequency response model, study [14] introduces a new transient frequency security index and establishes quantitative relationships between this index and renewable energy absorption capacity. Similarly, study [15] translates the frequency constraint into a kinetic energy constraint by analyzing active energy changes during disturbances, and derives an analytical expression for the maximum renewable energy penetration, which is used to measure renewable energy absorption capacity. The integration of renewable energy also introduces voltage stability challenges in the power grid due to its lack of reactive power support capability. Study [16] established a quantitative transient stability assessment framework for power systems with high renewable energy penetration. By adjusting the penetration level, the study evaluates the renewable energy absorption capacity that ensures voltage stability. Study [17] evaluates renewable energy absorption capacity by adjusting the dispatch power of committed synchronous generators under multiple load scenarios, considering both frequency nadir constraints and dynamic voltage security constraints. Study [18] constructs an optimization model for renewable energy absorption capacity in an AC-DC hybrid grid, aiming to maximize renewable energy penetration and minimize network losses, while considering both static and transient stability constraints. For simplification, only the typical operational scenario of the power grid was considered.
Assessment in a single scenario fails to capture the temporal characteristics of renewable generation and the regulation capability of the system, leading to inaccurate results. To address these challenges, study [19] proposes a multi-scenario renewable energy absorption capacity assessment method based on an attention-enhanced time convolutional network. Study [20] uses a multi-time-horizon optimization of unit commitment and economic dispatch to examine the hosting capacity of renewables. Specifically, one sampled typical week from each month in the horizon is modeled, and the results are then applied to the other weeks. Study [21] presents a renewable energy accommodation capability model based on standard time-series production simulation. Moreover, a week-by-week optimization strategy, combined with the hybrid particle swarm optimization algorithm, was used to achieve the rapid solution of the model. Similarly to capacity expansion planning (CEP), the assessment of renewable energy absorption capacity typically spans time periods of one year or more. Such extended time horizons substantially increase the computational complexity of the problem. To reduce the temporal resolution, time-series aggregation methods are widely employed to identify representative periods that preserve key temporal and operational characteristics. Typically, the original time series is partitioned into K operationally independent periods, and multiple similar periods are aggregated and represented by a single typical period. In recent years, clustering-based techniques—such as k-means clustering, k-medoids clustering, and hierarchical clustering—have gained popularity for this purpose [22,23,24,25,26].
While prior studies often address frequency or voltage constraints independently, this paper presents a unified security-constrained sequential production simulation (SPS) framework that simultaneously considers both types of security constraints. To enhance computational efficiency, the framework incorporates a hierarchical clustering (HC) method based on dynamic time warping (DTW) and min-max linkage for time-series aggregation, effectively reducing the problem scale while preserving essential temporal and operational characteristics. The main contributions of this work are as follows:
(1)
The voltage and frequency support requirements for renewable energy absorption are translated into a set of constraints on the operational status of synchronous generators.
(2)
A security-constrained SPS framework is developed to assess the renewable energy absorption capacity while considering both frequency and voltage security constraints.
(3)
An HC based on DTW and min-max linkage is employed for TA, effectively reducing the computational complexity of the security-constrained SPS while preserving key system characteristics.

2. Grid Support Requirements for Renewable Energy Absorption

Renewable energy sources (RESs) offer significant environmental and economic benefits. However, their integration into the power grid poses challenges due to their variability, intermittency, and lack of inherent stability support. Ensuring effective renewable energy absorption requires sufficient grid support, particularly in voltage and frequency regulation, to maintain system reliability and efficiency.

2.1. Voltage Support Requirements

Voltage support requirements refer to the essential grid capabilities needed to maintain stable voltage levels in a power system with a high share of renewable energy. To evaluate those grid capabilities, several key indicators are considered, among which the short-circuit ratio (SCR) is one of the most critical [27]. Accordingly, the voltage support requirement for renewable energy absorption can be expressed as the following constraint on the SCR [27]:
S cr , j = S sc , j P N , j = V N , j I f , j S base P N , j S cr , j min
where S cr , j is the short-circuit ratio at bus j; S cr , j min is the required short-circuit ratio at bus j; S sc , j represents the short-circuit capacity at bus j; P N , j is the rated capacity at bus j, which corresponds to the rated power of the renewable energy unit if bus j is a renewable energy integration bus, or the rated power of the DC system if bus j is a DC converter bus; V N , j denotes the per-unit rated voltage at bus j; I f , j is the per-unit three-phase short-circuit current at bus j; and S base represents the base value of capacity in per-unit terms.
For a given bus j, the parameters V N , j , P N , j , and S base are given. According to Equation (1), the SRC S sc , j is exclusively determined by the short-circuit current I f , j . To calculate I f , j , synchronous generators in operation are modeled using their sub-transient impedance and sub-transient electromotive force (EMF), while loads are represented as constant impedance. The corresponding equivalent circuit diagram is shown in Figure 1.
Applying the principle of superposition, the three-phase short-circuit current at bus j can be expressed as:
I f , j = i = 1 N G y i I f , i j
where N G represents the total number of synchronous generators; y i denotes the operating status of synchronous generator i, where y i = 1 indicates the generator is online and y i = 0 indicates it is offline; and I f , i j represents the short-circuit current supplied by synchronous generator i to bus j.
The short-circuit current supplied by synchronous generator i in service to bus j can be determined by short-circuiting the sub-transient EMFs of all other operating synchronous generators in the equivalent circuit depicted above. While the sub-transient EMFs of those generators are short-circuited, their sub-transient impedances remain connected, significantly influencing the equivalent impedance between synchronous generator i and bus j.
It is evident that I f , i j is closely related to the operating status of synchronous generators in the power grid, exhibiting an implicit relationship. To facilitate computation, we define I f , i j , the short-circuit current contribution factor, as the short-circuit current supplied by synchronous generator i to bus j when it is the only generator in operation. This can be calculated by disconnecting all other operating synchronous generators in the equivalent circuit illustrated in Figure 1. Additionally, we introduce α i , a correction factor, which accounts for the impact of other in-service synchronous generators on the equivalent impedance between synchronous generator i and bus j. The correction factor is closely related to the number of online synchronous generators and, for a fixed unit count, is further influenced by the specific combination of operating units. As shown in Figure 2, for the IEEE 39-bus system with two generators online (including Generator 1), the correction factor for the short-circuit current contribution from Generator 1 to Bus 2 remains relatively consistent across different unit combinations. Therefore, it is reasonable to approximate the correction factor as a piecewise constant with respect to the number of online synchronous generators.
Thus, Equation (2) can be approximated as:
I f , j i = 1 N G y i α i I f , i j
By substituting Equation (3) into Equation (1), the voltage support requirement for renewable energy absorption can be formulated as a constraint on the operational status of synchronous generators:
i = 1 N G y i α i I f , i j S cr , j min P N , j V N , j S base

2.2. Frequency Support Requirements

RESs such as wind and solar rely on inverter-based interfaces and inherently lack physical rotational inertia. With the increasing integration of RESs into modern power systems, this lack of inertia makes the system more vulnerable to rapid frequency deviations following sudden power imbalances. Therefore, ensuring resilient frequency support is crucial for the stable and reliable operation of systems with high shares of renewable energy. The requirements for frequency support are commonly evaluated using key indicators extracted from the system’s dynamic frequency response following a power disturbance. Those indicators include the rate of change of frequency (RoCoF), frequency deviation at quasi-steady-state, and maximum transient frequency deviation. Figure 3 illustrates the typical frequency response of a high-RES system following a fault in an export transmission corridor, which results in surplus generation and consequently causes system over-frequency. As shown in Figure 3, the RoCoF reflects how rapidly the system frequency changes during the initial seconds after a major power disturbance, the maximum transient frequency deviation corresponds to the greatest deviation from the nominal frequency during the transient period, and the frequency deviation at quasi-steady-state represents the frequency level at which the system stabilizes after the transient phase.
Consider a large-scale power system where most conventional generating units are reheating steam turbines. Assuming a uniform network frequency, the system’s frequency response can be aggregated and modeled as an equivalent single-machine system with a centralized load [28,29], as illustrated in Figure 4.
From Figure 4, the transfer function between the frequency deviation Δ f and the disturbance power Δ P L can be derived as:
Δ f s Δ P L s = 1 + T R s 2 H T R s 2 + 2 H + D T R s + D + 1 R
where
H = i = 1 N G y i S i H i
D = j = 1 N L D j P j L
1 R = i = 1 N G y i S i R i
In the equations: TR is the reheating time constant; D denotes the system load damping factor; H is the system equivalent inertia constant; and R represents the system governor regulation coefficient. N G denotes the total number of synchronous generators in the system, where yi, Si, Hi, and Ri correspond to the operational status, capacity, inertia, and governor regulation coefficient of the ith synchronous generator, respectively. N L represents the set of system loads, where Dj and P j L denote the damping coefficient and active power of the jth load, respectively.
Sudden power disturbances can be approximated as a step input. By applying the Laplace transform, the time-domain expression of the frequency deviation can be obtained. Subsequently, RoCoF, frequency deviation at quasi-steady-state, and maximum transient frequency deviation can be formulated as (6) and (7). The detailed derivations can be found in references [28,29].
R CoF = d Δ f t d t t = 0 = Δ P L 2 H R CoF max
Δ f s = Δ P L D + 1 / R Δ f s max
Δ f peak = Δ P L D + 1 / R 1 + 1 ζ 2 β e ζ ω n t peak Δ f peak max
where
β = 1 2 T R ζ ω n + T R 2 ω n 2 1 ζ 2
ω n = D R + 1 2 H T R R
ζ = 1 2 ω n 1 T R + D 2 H
In the equations: t peak is the time corresponding to the peak transient frequency deviation.
The expression of the maximum transient frequency deviation is inherently nonlinear. Several studies [9,10,11,12,13] have proposed approximate linear methods to address this complexity. In this work, we adopt the approach presented in [11], which assumes linear governor power regulation and derives an approximate analytical expression for the maximum transient frequency deviation constraint, as given in Equations (9) and (10). The detailed derivation and theoretical proof can be found in [11].
H / R k peak
where k peak is the unique solution derived from the following equation:
Δ f peak max = Δ P L D + 2 k peak T R D 2 log 2 k peak 2 k peak T R D Δ P L
By substituting Equation (5a) into Equation (6), Equation (5b,c) into Equation (7), and Equation (5a,c) into Equation (8), the frequency support requirement for renewable energy accommodation can be formulated as a set of constraints on the operational status of synchronous generators:
i = 1 N G y i S i H i Δ P L 2 R CoF max
i = 1 N G y i S i R i Δ P L Δ f s max D L j = 1 N L P j L
i = 1 N G y i S i H i i = 1 N G y i S i R i k peak

3. Security-Constrained Sequential Production Simulation for Assessing Renewable Energy Absorption Capacity

Standard SPS primarily focuses on power and energy balance constraints, ensuring that generation meets demand while optimizing economic and operational efficiency over a given time horizon. However, with the large-scale development and integration of renewable energy, it fails to explicitly account for the critical role of synchronous generators in maintaining grid security, particularly in terms of voltage and frequency support. To more accurately evaluate the renewable energy absorption capacity, this paper proposes a production simulation model incorporating voltage and frequency support constraints. Figure 5 illustrates the structure of the proposed security-constrained sequential production simulation model. The objective function minimizes both renewable energy curtailment cost and conventional generation cost. The basic constraints include conventional unit, renewable curtailment, and system operation constraints, as commonly formulated in the literature (see [21] for details). The proposed constraints, derived in Section 2.1 and Section 2.2, are newly introduced in this study.

3.1. Objective Function

For assessing renewable energy absorption capacity, the objective of the security-constrained SPS aims to maximize the utilization of renewable energy while ensuring system reliability and economic efficiency. This is achieved by minimizing the cost of renewable energy curtailment, along with reducing conventional generator production costs over the operational period. Specifically, the optimization objective is:
min t = 1 T simu i = 1 N G a i P i , t G 2 + b i P i , t G + c i + C i , t SU + C i , t SD + i = 1 N R η P i , t R , CUR
where T simu represents the operational period for production simulation, which is typically set to one year (8760 h). a i , b i , and c i are the operation cost coefficients of conventional generator i; P i , t G is the power output of conventional generator i at time t; and C i , t SU and C i , t SD are auxiliary variables for the startup/shutdown costs of conventional generator i at time t. N R represents the total number of renewable energy power stations, η is the penalty cost per unit curtailed power, and P i , t R , CUR is the curtailed power of renewable energy power station i at time t.

3.2. Startup and Shutdown Cost Constraints

In the objective function, both startup and shutdown costs are included to capture the operational economics of conventional generators. However, these two cost terms are mutually exclusive at any given time step, as a generator cannot be started up and shut down simultaneously. To ensure that this exclusivity is properly enforced, the following constraints are introduced:
C i , t SU c i SU y i , t y i , t 1 C i , t SU 0
C i , t SD c i SD y i , t 1 y i , t C i , t SD 0
where c i SU and c i SD represent the startup cost and shutdown cost of conventional generator i, respectively; and y i , t 1 and y i , t denote the operating status of synchronous generator i at time t − 1 and time t, with 1 signifying the generator is online and 0 indicating it is offline.

3.3. Conventional Generator Unit Constraints

(1)
Power Output Limits
Each generating unit has a limit on the power it can generate:
y i , t P i G , min P i , t G y i , t P i G , max
where P i G , min and P i G , max are the minimum and maximum power limits of generator i, respectively.
(2)
Ramp Rate Limits
Generally, a power turbine cannot adjust its output instantaneously. Generating units have limits on how quickly they can increase or decrease output:
P i , t + 1 G P i , t G P i G , UP Δ t P i , t G P i , t + 1 G P i G , DN Δ t
where P i , t G and P i , t + 1 G are the power output of generator i at time t and t + 1; P i G , UP and P i G , DN are the ramp-up rate and ramp-down rate of generator i; and Δ t is the time step duration.
(3)
Minimum Up/Down Time Limits
Before shutting down, a generating unit has to stay online for a minimum duration T i G , ON . Similarly, once shut down, it must stay offline for at least T i G , OFF consecutive time periods:
k = t t + T i G , ON 1 1 y i , k T i G , ON y i , t 1 y i , t
k = t t + T i G , OFF 1 y i , k T i G , OFF y i , t y i , t 1

3.4. Renewable Energy Curtailment Constraints

To ensure that curtailment does not exceed available generation:
0 P i , t R , CUR P i , t R , FORE
where P i , t R , FORE is the available generation power of renewable energy power station i at time t.

3.5. System Constraints

(1)
Spinning Reserve Constraint
To ensure system reliability, a certain amount of additional generation capacity must be maintained:
i = 1 N G y i , t P i G , max P i , t G ρ i = 1 N L P i , t L
where ρ is the spinning reserve factor.
(2)
Power Balance Constraints
At each bus i, the net injected power must equal the sum of power flows on all lines connected to the bus. Using DC power flow:
P i , t B , G P i , t B , L = j Ω B B i j θ i , t θ j , t
where P i , t B , G and P i , t B , L represent generated power and load demand at bus i at time t. B i j is the susceptance of the transmission line between buses i and j, Ω B denotes the set of buses connected to bus i, and θ i and θ j are the voltage phase angles at buses i and j at time t.
(3)
Transmission Line Flow Limits
The absolute value of the power flow on each transmission line must not exceed its thermal capacity:
P i j max B i j θ i , t θ j , t P i j max
where P i j max is the maximum permissible power flow on the line between buses i and j.
(4)
Voltage Support Constraints
The voltage support constraints can be formulated by Equation (4), which has already been discussed in Section 2.1.
(5)
Frequency Support Constraints
As discussed in Section 2.2, the frequency support constraints can be described by Equations (11)–(13).

4. Temporal Aggregation-Based Solution for Security-Constrained Sequential Production Simulation

Although the security-constrained SPS accurately captures time-series characteristics of real-world power system operation, its long time horizon significantly expands the optimization model size, leading to high computational complexity. A natural solution to this challenge is to reduce the dimensionality in the time domain, such as through TA.

4.1. Hierarchical Clustering-Based TA

TA compresses long time-series data into a few typical periods. It reduces computation time significantly while preserving the model’s core time-varying characteristics. To achieve a more structured and efficient representation of time-series data, clustering is often employed. Compared to traditional feature-based classification methods, clustering does not rely on subjective experience. Instead, it uses mathematical techniques to identify similarities or differences in data. This enables natural grouping.
Among various clustering algorithms, k-means clustering and HC are two of the most widely used methods for TA. Unlike k-means, HC requires neither initial cluster centers nor a pre-specified number of clusters. Instead, it determines cluster merging or splitting based on distance metrics between data points or clusters, forming a clear hierarchical structure. This structure enables multi-scale analysis. It allows patterns to be examined at different levels of granularity, making it particularly useful for capturing complex temporal dynamics.
Similarity measurement is the foundation of HC, as well as all other clustering algorithms. For time-series data, Euclidean distance measurement may result in poor similarity assessments due to temporal misalignment. To address this issue, we consider DTW in this paper. DTW measures the similarity by computing the minimum cumulative distance between elements of two time series [25]. Given two time series X = x 1 , x 2 , , x m and Z = z 1 , z 2 , , z n , let Δ x i , z j represent the distance between element x i in X and element z j in Z. The cumulative distance matrix D ist is constructed based on Δ x i , z j as follows:
D ist i , j = Δ x i , z j + min D ist i 1 , j , D ist i , j 1 , D ist i 1 , j 1
The second term of Equation (25) accounts for the “warping” of the time axis, ensuring that similar patterns are aligned even if they occur at different time steps. The final DTW distance is the value at D ist m , n .
Besides that, another essential requirement of HC is determining how to measure the distance between clusters, known as the linkage criterion. In this paper, we employ the min-max linkage criterion, which identifies a point referred to as the cluster prototype [30]. Having a cluster prototype is beneficial as it aligns with the purpose of temporal aggregation—that is, selecting representative periods to replace the full time series.
Let r Ω i denote the radius of the cluster Ωi, defined as:
r Ω i = min X Ω i max Δ X , Z Z Ω i Z X
where Δ X , Z represents the distance between point X and point Z within cluster Ωi. The point X that minimizes (26) is designated as the prototype of cluster Ωi. Consequently, the min-max linkage can be expressed as follows:
L inkage Ω i , Ω j = r Ω i Ω j
Since HC does not require a predefined number of clusters, the optimal number of clusters can be determined by cutting the dendrogram using methods such as the Elbow Method. Once the final set of clusters is obtained, each cluster is represented by its cluster prototype, which serves as a representative day. The weight assigned to each representative day is equal to the number of points within the corresponding cluster.

4.2. Solution Framework

Based on HC with DTW and min-max linkage discussed above, the solution process for security-constrained SPS using TA is illustrated in Figure 6. The key steps are as follows:
(1)
Set wind and solar installed capacity.
(2)
Generate 8760 h time-series power output based on annual wind and solar generation characteristics.
(3)
Organize full-year data by structuring wind, solar, and load demand in a daily format.
(4)
Select representative days using HC with DTW and min-max linkage.
(5)
Perform security-constrained SPS for each representative day. If no renewable energy curtailment occurs, increase the renewable energy installation ratio and return to Step 2. Otherwise, statistically analyze renewable energy absorption.
(6)
Estimate annual renewable energy absorption by aggregating the weighted results of representative days.

5. Case Study

5.1. Case1: The IEEE 39-Bus System

The IEEE 39-bus system is a widely used benchmark model proposed by the IEEE Task Force on Benchmark Systems for Stability Controls [31]. This system was modified to test the proposed security-constrained SPS for assessing renewable energy absorption capability. Wind farms were integrated at Buses 3, 8, and 18, while photovoltaic (PV) stations were connected at Buses 4 and 16. Bus 2 was modified to include an HVDC transmission system for power export to external grids. The annual 8760 h time-series load data, coupled with the time-series output data for wind and photovoltaic generation, were sourced from [32] and are illustrated in Figure 7, Figure 8 and Figure 9. The dynamic simulation parameters used in this paper—such as generator and governor models—are derived from the official MATLAB (since R2024b) example [33], which is based on the IEEE Task Force specification.
(1)
Representative Day Selection
The proposed HC with DTW and min-max linkage was applied for temporal aggregation. Using the Elbow Method, the optimal number of clusters is determined as 18. Figure 10 shows the prototypes of each cluster and their assigned days. Different colors represent different clusters. Solid dots indicate the clustered days, and black-edged hollow dots represent the prototypes.
The core of temporal aggregation is to preserve the time-dependent features of the original time series. For renewable energy, this involves maintaining the distribution of generation levels and their corresponding frequencies of occurrence. This is typically represented by the duration curve of renewable energy output [26]. Figure 11 illustrates the wind duration curve for both original and clustered data. As seen in the figure, the proposed method (HC with DTW and min-max linkage) produces a wind duration curve that closely aligns with the original wind power output duration curve, especially in the lower output range. This is crucial for the accuracy of renewable energy absorption assessments, as it directly impacts the demand for grid reserve capacity.
To further evaluate the performance of each clustering method, the root mean square deviation (RMSE) between the clustered duration curves and the original duration curve was calculated, as shown in Table 1. The proposed method outperforms HC using Euclidean distance and ward linkage, as well as k-means, indicating that the proposed TA provides a better approximation.
(2)
Renewable Energy Absorption Assessment
After selecting the representative days, security-constrained sequential production simulations were performed for each typical day to determine renewable energy absorption. Then, the annual renewable energy absorption was calculated by weighting each typical day, as illustrated in Figure 12.
Table 2 presents a detailed comparison of renewable energy absorption results obtained from the security-constrained SPS with TA and without TA, covering both monthly and annual data. The relative errors between the two methods are also analyzed. For the case without TA, the security-constrained SPS over the full 8760 h horizon requires 7050.52 s of computation time and yields an annual renewable energy absorption of 79,740.40 p.u. In contrast, the TA-based approach completes in only 13.19 s, achieving a comparable annual absorption of 81,012.84 p.u. Calculations were performed using GUROBI 10.0.1 on a PC with Intel Core i5-13400 2.5 GHz CPU and 16 GB RAM. The relative error between the two methods is merely 1.60%, indicating that the TA-based method significantly enhances computational efficiency while preserving a high level of accuracy in the assessment results.
The security-constrained SPS entails additional conventional units online to fulfill the system’s voltage and frequency support requirements. This reduces the space available for renewable energy absorption, leading to curtailment. On the other hand, the standard SPS that only considers power and energy balance may fail to ensure the grid’s voltage and frequency safety, potentially resulting in an inaccurate reflection of renewable energy absorption.
Taking day 239 as an example, the load, available wind power, and photovoltaic output for that day are shown in Figure 13. The 24 h operating and output schedules for the conventional units, as determined by the standard SPS and the security-constrained SPS, are shown in Figure 14 and Figure 15, respectively. In Figure 14, solid dots indicate generator startups, while hollow dots represent shutdowns. A detailed numerical comparison of the conventional unit outputs under the standard and security-constrained SPS methods is provided in Table 3.
The standard SPS only considers power and energy balance constraints. Its goal is to minimize operational costs by activating the fewest units. However, this may lead to insufficient voltage and frequency support for the system. In contrast, the security-constrained SPS ensures that additional units are brought online to meet the system’s voltage and frequency support needs. For instance, at hour 14, when solar output was high and the load was relatively low, renewable energy accounted for 44.5% of the electricity demand. Under the standard SPS, the number of online units is reduced, and the operating units are kept at their economic load levels. On the other hand, the security-constrained SPS brings Unit 3 and Unit 6 online to provide adequate voltage and frequency support for the system.
For the system operating condition at hour 14, a dynamic simulation of the grid response to an HVDC lockout fault was conducted. Figure 16 and Figure 17 illustrate the system’s frequency response curve and DC bus voltage response curve, respectively. Under the unit startup schedule determined by the standard SPS, the maximum frequency deviation reaches approximately 0.67 Hz. According to the National Standards of the People’s Republic of China (GB standards) [34,35], if the frequency deviation exceeds 0.5 Hz, the dispatching agency may issue high-frequency disconnection commands to renewable energy units. Such disconnections can potentially lead to a large-scale blackout in the grid. Consequently, the actual renewable energy absorption is reduced.
Additionally, the maximum DC bus voltage reaches approximately 1.21 p.u., which poses a potential risk of overvoltage. According to the GB standards, if the voltage exceeds 1.3 p.u., renewable energy sources may be disconnected from the grid. Such overvoltage-related disconnections near the DC bus could further reduce the actual renewable energy absorption.
In contrast, the unit startup schedule determined by the security-constrained sequential production simulation maintains grid voltage and frequency safety under the same fault condition, thereby better representing renewable energy absorption under practical system conditions.
The same holds true for moments when the share of renewable energy output is relatively small. At hour 17, the photovoltaic output sharply decreases as the sun sets, while the load begins to increase with the approaching evening peak. The standard SPS brings Unit 3 online to balance the reduction in renewable energy output and the increase in load. Figure 18 and Figure 19 show the system’s frequency response curve and DC bus voltage response curve under the same HVDC lockout fault for the system operating condition at hour 17. Under the unit startup schedule determined by the standard SPS, the steady-state frequency deviation exceeds the allowable threshold of 0.2 Hz (GB standards [36]). The standard SPS fails to maintain the system’s frequency safety, whereas the security-constrained simulation ensures the system remains within acceptable frequency limits.
From the above analysis, it is evident that the renewable energy absorption evaluated by the proposed security-constrained sequential production simulation provides a representation that is more consistent with the grid’s actual operating conditions, offering a more realistic assessment.
(3)
Factors Improving Renewable Energy Absorption
Reducing the output or shutting down conventional units does not necessarily improve renewable energy absorption, as fewer units cannot ensure system safety. The key to enhancing absorption is increased demand, whether from local load or export demand. Based on the proposed security-constrained SPS, the impact of load scale and HVDC transmission capacity on renewable energy absorption was analyzed by varying either the load scale or the HVDC transmission capacity.
Using day 267 as an example, Figure 20, Figure 21 and Figure 22 show the relationship between load scale, HVDC transmission capacity, and renewable energy absorption. In these figures, the vertical axis represents the renewable energy utilization, while the horizontal axes represent total system load and HVDC transmission capacity, respectively. It can be seen that increasing both the load scale and HVDC transmission capacity can improve renewable energy absorption—one for local absorption and the other for export absorption. However, both require sufficient regulation support from the power grid. Figure 18 shows how renewable energy absorption changes as the share of renewable energy capacity is increased. If the grid’s regulation support capacity remains unchanged, increasing renewable energy capacity will eventually exceed the grid’s ability to absorb it, leading to a decline in absorption.

5.2. Case2: The IEEE 68-Bus System

The IEEE 68-bus system, one of the six benchmark systems recommended by the IEEE Task Force on Benchmark Systems for Stability Controls, includes 68 buses, 16 generators, and 86 transmission lines. The system topology can be found in [37], and the corresponding dynamic simulation parameters are also derived from the same source. Wind farms were integrated at Buses 39, 51, and 56, while photovoltaic plants were connected at Buses 44 and 60. Bus 17 was further modified to act as the sending terminal of an HVDC transmission system. The 8760 h annual time-series data for load, wind, and PV generation were also obtained from [32].
TA was performed using the proposed HC with DTW and min–max linkage. A total of 25 clusters are obtained. The number of days in each cluster and their corresponding representative days are shown in Table 4. The cluster representatives and their assigned days are visualized in Figure 23. Dots in different colors represent different clusters. The solid dots of the same color indicate the days assigned to each cluster, while the black-edged hollow dots represent the prototype of each cluster.
Following the selection of representative days, security-constrained SPSs were performed for each day to evaluate renewable energy absorption. The annual absorption was then calculated by aggregating these results according to the occurrence frequency of each representative day. Figure 24 illustrates the renewable energy absorption outcomes from security-constrained SPSs both with and without TA, while Table 5 provides detailed numerical data. The relative errors between the two approaches are also analyzed.
Without TA, conducting the security-constrained SPS over the full 8760 h requires 24,682.95 s and results in an annual renewable energy absorption of 94,893.77 p.u. In contrast, the TA-based approach reduces the computation time to 621.79 s, while yielding a comparable annual absorption of 94,658.44 p.u. All simulations were carried out using GUROBI 10.0.1 on a PC equipped with an Intel Core i5-13400 2.5 GHz CPU and 16 GB of RAM. The resulting relative error is only 0.23%, demonstrating that the TA-based method offers a substantial reduction in computational burden while maintaining high accuracy in the renewable energy absorption estimates.
The case study on the IEEE 68-bus system demonstrates that the proposed method can be effectively applied to more complex power systems, confirming its scalability and robustness for practical renewable energy absorption assessment in large-scale networks.

6. Conclusions

This paper presents an assessment of renewable energy absorption capacity using a security-constrained SPS, incorporating grid voltage and frequency support constraints. Through a case study of the IEEE 39-bus system, which integrated wind and photovoltaic generation alongside HVDC transmission for power export, the proposed approach was demonstrated to provide a more realistic evaluation of renewable energy absorption capacity. This was particularly evident when evaluating the system’s performance under varying load and renewable energy conditions. For instance, during periods of high renewable output or low load, the security-constrained SPS successfully brought additional conventional units online, helping maintain grid stability. It prevented overvoltage and frequency deviations that could otherwise lead to renewable energy curtailment.
Furthermore, this case study analyzed the factors that improve renewable energy absorption. It revealed that increasing grid demand—both locally and through export via HVDC transmission—is a key driver of enhanced renewable energy absorption. However, this requires the grid to provide sufficient support. To address this challenge, advanced grid technologies such as energy storage and demand response have been developed. Future research should focus on how to effectively coordinate these measures to better accommodate the growing share of renewable energy in power systems.
It is worth noting that while the proposed TA method improves computational efficiency with acceptable accuracy under typical conditions, it does not explicitly account for rare but high-impact extreme weather events. Incorporating such scenarios in future studies will help enhance the method’s robustness. Also, future work will explore integrating AI-based techniques to improve the representation of security and stability constraints. AI models trained on operational data may help approximate complex dynamics, enabling faster and more accurate assessments.

Author Contributions

Conceptualization, Z.F.; methodology, Y.Z. and L.X.; formal analysis, J.L. and T.W.; writing—original draft preparation, L.X. and P.C.; writing—review and editing, L.X.; visualization, P.C.; supervision, Z.F. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the scientific and technological project funding from State Grid Corporation of China (SGCC), grant number 522730240008.

Data Availability Statement

The data presented in this study are openly available in IEEE DataPort at DOI: 10.21227/ggy4-7497.

Conflicts of Interest

Authors Zhihui Feng, Yaozhong Zhang, Jiaqi Liu, Tao Wang and Ping Cai were employed by the Economic and Technological Research Institute, State Grid Gansu Electric Power Company. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. IRENA. Renewable Energy Statistics 2024; International Renewable Energy Agency: Abu Dhabi, United Arab Emirates, 2024. [Google Scholar]
  2. Bird, L.; Lew, D.; Milligan, M.; Carlini, E.M.; Estanqueiro, A.; Flynn, D.; Gomez-Lazaro, E.; Holttinen, H.; Menemenlis, N.; Orths, A. Wind and solar energy curtailment: A review of international experience. Renew. Sustain. Energy Rev. 2016, 65, 577–586. [Google Scholar] [CrossRef]
  3. Li, P.; Sun, W.; Zhang, Z.; He, Y.; Wang, Y. Forecast of renewable energy penetration potential in the goal of carbon peaking and carbon neutrality in China. Sustain. Prod. Consum. 2022, 34, 541–551. [Google Scholar] [CrossRef]
  4. You, W.; Geng, Y.; Dong, H.; Wilson, J.; Pan, H.; Wu, R.; Sun, L.; Zhang, X.; Liu, Z. Technical and economic assessment of RES penetration by modelling China’s existing energy system. Energy 2018, 165, 900–910. [Google Scholar] [CrossRef]
  5. Zhang, D.; Mu, S.; Chan, C.C.; Zhou, G.Y. Optimization of renewable energy penetration in regional energy system. Energy Procedia 2018, 152, 922–927. [Google Scholar] [CrossRef]
  6. Bunodiere, A.; Lee, H.S. Renewable energy curtailment: Prediction using a logic-based forecasting method and mitigation measures in Kyushu, Japan. Energies 2020, 13, 4703. [Google Scholar] [CrossRef]
  7. Akeyo, O.M.; Patrick, A.; Ionel, D.M. Study of renewable energy penetration on a benchmark generation and transmission system. Energies 2020, 14, 169. [Google Scholar] [CrossRef]
  8. Memmel, E.; Schlüters, S.; Völker, R.; Schuldt, F.; Von Maydell, K.; Agert, C. Forecast of renewable curtailment in distribution grids considering uncertainties. IEEE Access 2021, 9, 60828–60840. [Google Scholar] [CrossRef]
  9. Egido, I.; Fernandez-Bernal, F.; Centeno, P.; Rouco, L. Maximum frequency deviation calculation in small isolated power systems. IEEE Trans. Power Syst. 2009, 24, 1731–1738. [Google Scholar] [CrossRef]
  10. Ahmadi, H.; Ghasemi, H. Security-constrained unit commitment with linearized system frequency limit constraints. IEEE Trans. Power Syst. 2014, 29, 1536–1545. [Google Scholar] [CrossRef]
  11. Teng, F.; Trovato, V.; Strbac, G. Stochastic scheduling with inertia-dependent fast frequency response requirements. IEEE Trans. Power Syst. 2015, 31, 1557–1566. [Google Scholar] [CrossRef]
  12. Paturet, M.; Markovic, U.; Delikaraoglou, S.; Vrettos, E.; Aristidou, P.; Hug, G. Stochastic unit commitment in low-inertia grids. IEEE Trans. Power Syst. 2020, 35, 3448–3458. [Google Scholar] [CrossRef]
  13. Zhang, Z.; Du, E.; Teng, F.; Zhang, N.; Kang, C. Modeling frequency dynamics in unit commitment with a high share of renew able energy. IEEE Trans. Power Syst. 2020, 35, 4383–4395. [Google Scholar] [CrossRef]
  14. Dai, J.; Tang, Y.; Wang, Q. Fast method to estimate maximum penetration level of wind power considering frequency cumulative effect. IET Gener. Transm. Distrib. 2019, 13, 1726–1733. [Google Scholar] [CrossRef]
  15. Wang, B.; Sun, H.; Zhao, B.; Wu, P.; Li, W.; Xu, S.; Chen, J. Calculation method of renewable maximum penetration considering frequency response of renewable energy. Electr. Power Syst. Res. 2024, 237, 110984. [Google Scholar] [CrossRef]
  16. Niu, S.; Zhang, Z.; Ke, X.; Zhang, G.; Huo, C.; Qin, B. Impact of renewable energy penetration rate on power system transient voltage stability. Energy Rep. 2022, 8, 487–492. [Google Scholar] [CrossRef]
  17. Lekshmi, J.D.; Rather, Z.H.; Pal, B.C. A new tool to assess maximum permissible solar PV penetration in a power system. Energies 2021, 14, 8529. [Google Scholar] [CrossRef]
  18. Li, C.; Zhang, D.; Liu, Z.; Xiong, Y.; Yu, T.; Gao, Z.; Miao, S. An Evaluation Method of Renewable Energy Resources’ Penetration Capacity of an AC-DC Hybrid Grid. Energies 2022, 15, 2550. [Google Scholar] [CrossRef]
  19. Wu, Y.; Zhou, H.; Zhang, C.; Liu, S.; Chen, Z. Multi-scenario renewable energy absorption capacity assessment method based on the attention-enhanced time convolutional network. Front. Energy Res. 2024, 12, 1347553. [Google Scholar] [CrossRef]
  20. Dalala, Z.; Al-Omari, M.; Al-Addous, M.; Bdour, M.; Al-Khasawneh, Y.; Alkasrawi, M. Increased renewable energy penetration in national electrical grids constraints and solutions. Energy 2022, 246, 123361. [Google Scholar] [CrossRef]
  21. Zhou, D.; Zhang, Q.; Dan, Y.; Guo, F.; Qi, J.; Teng, C.; Zhu, H. Research on renewable-energy accommodation-capability evaluation based on time-series production simulations. Energies 2022, 15, 6987. [Google Scholar] [CrossRef]
  22. Kotzur, L.; Markewitz, P.; Robinius, M.; Stolten, D. Impact of different time series aggregation methods on optimal energy system design. Renew. Energy 2018, 117, 474–487. [Google Scholar] [CrossRef]
  23. Hoffmann, M.; Kotzur, L.; Stolten, D.; Robinius, M. A Review on Time Series Aggregation Methods for Energy System Models. Energies 2020, 13, 641. [Google Scholar] [CrossRef]
  24. Gke, L.; Kendziorski, M. Adequacy of time-series reduction for renewable energy systems. Energy 2022, 238, 121701. [Google Scholar] [CrossRef]
  25. Teichgraeber, H.; Brandt, A.R. Time-series aggregation for the optimization of energy systems: Goals, challenges, approaches, and opportunities. Renew. Sustain. Energy Rev. 2022, 157, 111984. [Google Scholar] [CrossRef]
  26. Poncelet, K.; Höschle, H.; Delarue, E.; Virag, A.; D’haeseleer, W. Selecting representative days for capturing the implications of integrating intermittent renewables in generation expansion planning problems. IEEE Trans. Power Syst. 2016, 32, 1936–1948. [Google Scholar] [CrossRef]
  27. Shair, J.; Li, H.; Hu, J.; Xie, X. Power system stability issues, classifications and research prospects in the context of high-penetration of renewables and power electronics. Renew. Sustain. Energy Rev. 2021, 145, 111111. [Google Scholar] [CrossRef]
  28. Anderson, P.M.; Mirheydar, M. A low-order system frequency response model. IEEE Trans. Power Syst. 1990, 5, 720–729. [Google Scholar] [CrossRef]
  29. Bevrani, H. Robust Power System Frequency Control; Springer: Berlin/Heidelberg, Germany, 2009. [Google Scholar]
  30. Bien, J.; Tibshirani, R. Hierarchical clustering with prototypes via minimax linkage. J. Am. Stat. Assoc. 2011, 106, 1075–1084. [Google Scholar] [CrossRef]
  31. Canizares, C.; Fernandes, T.; Geraldi, E.; Gerin-Lajoie, L.; Gibbard, M.; Hiskens, I.; Kersulis, J.; Kuiava, R.; Lima, L.; DeMarco, F.; et al. Benchmark Models for the Analysis and Control of Small-Signal Oscillatory Dynamics in Power Systems. IEEE Trans. Power Syst. 2017, 32, 715–722. [Google Scholar] [CrossRef]
  32. Zhuo, Z.; Zhang, N.; Yang, J.; Kang, C.; Smith, C.; O’Malley, M.J.; Kroposki, B. Transmission expansion planning test system for AC/DC hybrid grid with high variable renewable energy penetration. IEEE Trans. Power Syst. 2019, 35, 2597–2608. [Google Scholar] [CrossRef]
  33. Available online: https://ww2.mathworks.cn/help/sps/ug/ieee-39-bus-system.html (accessed on 24 May 2025).
  34. GB/T 19963.1-2021; Technical Specification for Connecting Wind Farm to Power System-Part 1: On Shore Wind Power. National Standardization Administration of China: Beijing, China, 2021. (In Chinese)
  35. GB/T 19964-2024; Technical Requirements for Connecting Photovoltaic Station to Power System. National Standardization Administration of China: Beijing, China, 2024. (In Chinese)
  36. GB/T 15945-2008; Power Quality—Frequency Deviation for Power System. National Standardization Administration of China: Beijing, China, 2008. (In Chinese)
  37. Abhinav Kumar, S.; Pal, B.C. IEEE PES Task Force on Benchmark Systems for Stability Controls: Report on the 68-Bus, 16-Machine, 5-Area System. 2013. Available online: https://www.researchgate.net/publication/311680574_IEEE_PES_Task_Force_on_Benchmark_Systems_for_Stability_Controls_Report_on_the_68-Bus_16-Machine_5-Area_System (accessed on 24 May 2025).
Figure 1. Equivalent circuit diagram for short-circuit current calculation.
Figure 1. Equivalent circuit diagram for short-circuit current calculation.
Energies 18 02994 g001
Figure 2. The correction factor under different unit combinations.
Figure 2. The correction factor under different unit combinations.
Energies 18 02994 g002
Figure 3. The typical frequency response.
Figure 3. The typical frequency response.
Energies 18 02994 g003
Figure 4. Block diagram of frequency model.
Figure 4. Block diagram of frequency model.
Energies 18 02994 g004
Figure 5. Overview of the security-constrained production simulation model.
Figure 5. Overview of the security-constrained production simulation model.
Energies 18 02994 g005
Figure 6. Solution process for security-constrained SPS using TA.
Figure 6. Solution process for security-constrained SPS using TA.
Energies 18 02994 g006
Figure 7. Annual load curve.
Figure 7. Annual load curve.
Energies 18 02994 g007
Figure 8. Annual available wind power curve.
Figure 8. Annual available wind power curve.
Energies 18 02994 g008
Figure 9. Annual available photovoltaic output curve.
Figure 9. Annual available photovoltaic output curve.
Energies 18 02994 g009
Figure 10. Clustering results.
Figure 10. Clustering results.
Energies 18 02994 g010
Figure 11. The wind duration cure for both original and clustered data.
Figure 11. The wind duration cure for both original and clustered data.
Energies 18 02994 g011
Figure 12. The annual renewable energy absorption of the IEEE 39-bus system.
Figure 12. The annual renewable energy absorption of the IEEE 39-bus system.
Energies 18 02994 g012
Figure 13. Load demand, wind power, and solar output of day 239.
Figure 13. Load demand, wind power, and solar output of day 239.
Energies 18 02994 g013
Figure 14. The 24 h operating schedule.
Figure 14. The 24 h operating schedule.
Energies 18 02994 g014
Figure 15. The 24 h output schedule.
Figure 15. The 24 h output schedule.
Energies 18 02994 g015
Figure 16. The system’s frequency response at hour 14.
Figure 16. The system’s frequency response at hour 14.
Energies 18 02994 g016
Figure 17. The DC bus voltage response at hour 14.
Figure 17. The DC bus voltage response at hour 14.
Energies 18 02994 g017
Figure 18. The system’s frequency response at hour 17.
Figure 18. The system’s frequency response at hour 17.
Energies 18 02994 g018
Figure 19. The DC bus voltage response at hour 17.
Figure 19. The DC bus voltage response at hour 17.
Energies 18 02994 g019
Figure 20. The renewable energy utilization vs. load scale.
Figure 20. The renewable energy utilization vs. load scale.
Energies 18 02994 g020
Figure 21. The renewable energy utilization vs. HVDC transmission capacity.
Figure 21. The renewable energy utilization vs. HVDC transmission capacity.
Energies 18 02994 g021
Figure 22. The renewable energy utilization vs. the share of renewable energy capacity.
Figure 22. The renewable energy utilization vs. the share of renewable energy capacity.
Energies 18 02994 g022
Figure 23. Cluster prototypes and the days associated with each cluster.
Figure 23. Cluster prototypes and the days associated with each cluster.
Energies 18 02994 g023
Figure 24. The annual renewable energy absorption of the IEEE 68-bus system.
Figure 24. The annual renewable energy absorption of the IEEE 68-bus system.
Energies 18 02994 g024
Table 1. RMSE for each clustering method.
Table 1. RMSE for each clustering method.
MethodsRMSE
HC with DTW and min-max linkage0.0238
HC with ED and ward linkage0.0486
k-means0.0317
Table 2. RE absorption (p.u.) under different methods in the IEEE 39-bus system.
Table 2. RE absorption (p.u.) under different methods in the IEEE 39-bus system.
MonthThe Available Generation Power of RESRenewable Energy Absorption Using Standard SPSRenewable Energy Absorption
Security-Constrained SPS Without TASecurity-Constrained SPS with TARelated Error
January4955.224955.224939.044954.660.32%
February5182.585182.585167.065174.170.14%
March8094.108094.107835.938024.942.41%
April7526.107526.107225.507441.942.99%
May8143.928143.927976.648084.041.35%
June8420.048420.048188.838329.421.72%
July9297.899297.898874.799068.782.19%
August7874.097874.097701.227860.442.07%
September7557.157557.157262.777472.092.88%
October4479.674479.674455.424479.670.55%
November5083.135083.135077.675080.600.06%
December5042.095042.095035.535042.090.13%
Annual81,655.9981,655.9979,740.4081,012.841.60%
Table 3. The 24 h unit output (p.u.) under standard SPS and security-constrained SPS.
Table 3. The 24 h unit output (p.u.) under standard SPS and security-constrained SPS.
tStandard SPSSecurity-Constrained SPS
Unit 1Unit 3Unit 6Unit 7Unit 9Unit 10Unit 1Unit 3Unit 6Unit 7Unit 9Unit 10
15.087.25off6.388.6511.005.087.253.263.128.6511.00
25.087.25off4.778.6511.005.086.163.213.128.1911.00
35.087.25off3.468.6511.005.085.123.183.127.9511.00
45.087.25off3.618.6511.005.085.862.743.127.7911.00
55.087.25off5.828.6511.005.086.533.483.128.5911.00
65.087.25off3.338.6511.003.242.187.013.228.6511.00
75.084.71off3.788.6511.001.522.187.014.688.6511.00
85.08offoff7.308.6511.001.522.187.013.858.6511.00
95.08offoff7.788.6511.001.522.187.014.528.6511.00
105.08offoff5.528.6511.001.522.187.013.168.6511.00
115.08offoff7.108.6511.002.922.183.963.128.6511.00
125.08offoff7.998.6511.005.082.322.553.128.6511.00
135.08offoff3.128.2811.003.402.182.553.125.2411.00
145.08offoff3.128.3811.002.582.182.553.126.1511.00
155.08offoff6.138.6511.004.342.182.553.127.6811.00
165.084.71off4.068.6511.005.083.102.553.128.6511.00
175.087.25off3.188.6511.004.072.675.653.128.6511.00
185.087.255.533.968.6511.005.087.026.593.128.6511.00
195.087.258.505.818.6511.005.087.258.505.818.6511.00
205.087.257.014.238.6511.005.086.227.334.948.6511.00
215.087.257.154.948.6511.005.087.257.154.948.6511.00
225.087.255.534.558.6511.005.087.037.013.288.6511.00
235.087.25off7.488.6511.005.085.675.943.128.6511.00
245.087.25off4.688.6511.005.082.995.823.128.6511.00
Table 4. Representative days and corresponding cluster assignments.
Table 4. Representative days and corresponding cluster assignments.
No.Representative DayDays Included
114863
233025
3552
416813
51463
61679
729021
81869
91772
101549
113164
121795
132121
142996
153525
163817
173577
182948
192689
203358
2128673
2211124
2323524
24789
252079
Table 5. RE absorption (p.u.) under different methods in the IEEE 68-bus system.
Table 5. RE absorption (p.u.) under different methods in the IEEE 68-bus system.
MonthThe Available Generation Power of RESRenewable Energy Absorption
Security-Constrained SPS Without TASecurity-Constrained SPS with TARelated Error
January4731.354588.714594.220.12%
February7077.316590.426533.330.81%
March9006.418269.128342.460.81%
April10,210.219308.109362.000.53%
May9334.788664.078669.020.05%
June11,696.2210,775.1610,765.990.08%
July9747.339204.939148.440.58%
August9127.138430.928505.850.82%
September9137.348413.788399.010.16%
October8388.057876.977764.961.34%
November6034.205792.505704.111.46%
December7112.836979.106869.061.55%
Annual101,603.1894,893.7794,658.440.23%
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Feng, Z.; Zhang, Y.; Liu, J.; Wang, T.; Cai, P.; Xu, L. Analysis of Renewable Energy Absorption Potential via Security-Constrained Power System Production Simulation. Energies 2025, 18, 2994. https://doi.org/10.3390/en18112994

AMA Style

Feng Z, Zhang Y, Liu J, Wang T, Cai P, Xu L. Analysis of Renewable Energy Absorption Potential via Security-Constrained Power System Production Simulation. Energies. 2025; 18(11):2994. https://doi.org/10.3390/en18112994

Chicago/Turabian Style

Feng, Zhihui, Yaozhong Zhang, Jiaqi Liu, Tao Wang, Ping Cai, and Lixiong Xu. 2025. "Analysis of Renewable Energy Absorption Potential via Security-Constrained Power System Production Simulation" Energies 18, no. 11: 2994. https://doi.org/10.3390/en18112994

APA Style

Feng, Z., Zhang, Y., Liu, J., Wang, T., Cai, P., & Xu, L. (2025). Analysis of Renewable Energy Absorption Potential via Security-Constrained Power System Production Simulation. Energies, 18(11), 2994. https://doi.org/10.3390/en18112994

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop