Financial, Economic, and Environmental Analyses of Upgrading Reverse Osmosis Plant Fed with Treated Wastewater
Abstract
:1. Introduction
2. Case Study
3. Methodology
3.1. Technical Specifications of Existing and Upgraded RO Systems
- To use the latest technology membrane and to improve the quality of the pumps to boost the system’s efficiency from 43.2% to 75%;
- To reduce the electricity requirement of the system;
- To reduce the amount of local and global emissions that are produced by utilizing the energy that is required by the system;
- To replace the current backwash system, which is a manual method, with a clean-in-process system (CIP), which operates relatively quickly and efficiently, thereby reducing the quantity of power and water required for backwash and thus producing less brine discharge;
- To reduce the chemical amount required per one cubic meter produced;
- The overall objective is to reduce the financial, economic, and environmental costs of producing a cubic meter of clean water.
3.2. Estimation of the Costs and Benefits of Upgrading the RO Technology
4. Results and Discussion
4.1. Financial Analysis
4.1.1. Case I: Both Plants Produce the Same Amount of Water as Currently Produced by the Existing Plant (75% Utilization Rate)
4.1.2. Case II: New Technology Producing the Same Amount of Water as the Existing Plant When Operating at 100% Capacity
4.1.3. Case III: Both Plants Operate at 100% of Their Capacity
4.2. Economic Analysis
4.3. Emission Costs
4.3.1. Steps for the Estimation of Emission Costs
- Calculate the annual electricity consumption of the RO plant;
- Estimate the total MMBtu (million British thermal units) of the fuel required to generate this electricity. This is a standard measure of the amount of heat energy produced on the combustion of 1 kg of fuel;
- Estimate the quantities of pollutants emitted per MMBtu through generating this quantity of electricity when using the types of plants that are employed in North Cyprus. These air pollutant emission factors, by generator type, are obtained from the United States Environmental Protection Agency [23] (Table 9, col. 1);
- The cost of the damage inflicted on North and South Cyprus arises from an increased health impact (morbidity and mortality) and property damage. Estimates are provided by the EU for North and South Cyprus and are combined for each pollutant that is produced by North Cyprus’ electricity generation [24] (Table 9, col. 2). These values have been adjusted to 2022 prices;
- The kgs of emissions, by type, are then multiplied by their social costs per kg to estimate the monetary values of the damage inflicted each year. In addition, the PVs of these emission costs are calculated over the plant’s lifetime.
4.3.2. Case I: Both Plants Produce the Same Amount of Water as Is Currently Being Produced by the Existing Plant (75% Utilization Rate)
4.3.3. Case II: New Technology Producing the Same Amount of Water as the Existing Plant when Operating at 100% Capacity
5. Quantified Stakeholder Impacts on Water Risk Mitigation
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Acknowledgments
Conflicts of Interest
Appendix A
Data | New Technology | Current Plant |
---|---|---|
Construction duration (years) | 1 | 1 |
Operations duration (years) | 20 | 20 |
Liquidation year (years) | 21 | 21 |
Replacement of carbon filters | Every 3 years | Every 3 years |
Replacement of membranes | Every 3 years * | Every 3 years * |
Pump replacement | Every 10 years | Every 10 years |
Cartridge filter replacement | Every 2 months | Every 6 months |
Lifetime of a water storage tank | 40 years | 40 years |
Lifetime of building | 50 years | 50 years |
Wastewater intake pump installations | ||
Number of wastewater intake pumps in operation | 1 | 1 |
Number of working hours per day | 23.97 h | 20 h |
Cost per wastewater intake pump (USD) | 6500 | 6500 |
Concrete storage to membrane pump installations | ||
Number of concrete storages to membrane pumps | 1 | 1 |
Number of working hours per day | 1–23.97 h | 1–20 h |
Cost per pump for concrete storage to membrane (USD) | 3117 | 3117 |
High-pressure pump installations | ||
Number of high-pressure pumps in operation | 1 | 2 |
Number of working hours per day | 1–23.97 h | 1–20 h |
Cost per high-pressure pump (USD) | 8989 | 12,000 |
Membrane backwash pump installations | ||
Number of membrane backwash pumps | 1 | 1 |
Number of working hours per day | 0.03 h | 4 h |
Cost of membrane backwash pumps (USD) | 512 | 512 |
Product transfer pump installations | ||
Number of product transfer pumps in operation | 1 | 1 |
Number of working hours per day | 1–23.97 h | 1–20 h |
Cost per transfer pump (USD) | 3080 | 3080 |
RO membrane installations | ||
Number of RO membranes | 60 | 60 |
Cost per RO membrane (USD) | 1200 | 1000 |
Cost of installation of RO (USD) | 72,000 | 60,000 |
Filters | ||
Cartridge filter installations | ||
Number of filters | 22 | 3 |
Cost per filter (USD) | 25 | 200 |
Sand filter installations | ||
Number of filters | 2 | 2 |
Cost per filter (USD) | 11,425 | 11,425 |
Carbon filter installations | ||
Number of filters | 2 | 2 |
Cost per filter | 13,360 | 13,360 |
Storage tank | ||
Number of storage tanks (250 m3) | 2 | 2 |
Cost per tank (USD) | 18,000 | 18,000 |
CIP installation | 7593 | 0 |
References
- Anis, S.F.; Hashaikeh, R.; Hilal, N. Reverse osmosis pretreatment technologies and future trends: A comprehensive review. Desalination 2019, 452, 159–195. [Google Scholar] [CrossRef] [Green Version]
- Wang, Y.; He, W.; Müller, J.D. Sensitivity analysis and gradient-based optimisation of feed spacer shape in reverse osmosis membrane processes using discrete adjoint approach. Desalination 2019, 449, 26–40. [Google Scholar] [CrossRef]
- Haidari, A.H.; Heijman, S.G.J.; van der Meer, W.G.J. Optimal design of spacers in reverse osmosis. Sep. Purif. Technol. 2018, 192, 441–456. [Google Scholar] [CrossRef]
- Kim, J.; Park, K.; Yang, D.R.; Hong, S. A comprehensive review of energy consumption of seawater reverse osmosis desalination plants. Appl. Energy 2019, 254, 113652. [Google Scholar] [CrossRef]
- Tawalbeh, M.; Qalyoubi, L.; Al-Othman, A.; Qasim, M.; Shirazi, M. Insights on the development of enhanced antifouling reverse osmosis membranes: Industrial applications and challenges. Desalination 2023, 553, 116460. [Google Scholar] [CrossRef]
- Zhao, D.L.; Japip, S.; Zhang, Y.; Weber, M.; Maletzko, C.; Chung, T.S. Emerging thin-film nanocomposite (TFN) membranes for reverse osmosis: A review. Water Res. 2020, 173, 115557. [Google Scholar] [CrossRef] [PubMed]
- Goh, L.M.; Thong, Z.; Li, W.P.; Ooi, S.T.; Esa, F.; Ng, K.S.; Dhalla, A.; Gudipati, C. Development and Industrial-Scale Fabrication of Next-Generation Low-Energy Membranes for Desalination. Membranes 2022, 12, 540. [Google Scholar] [CrossRef] [PubMed]
- Villena-Martínez, E.M.; Alvizuri-Tintaya, P.A.; Lora-Garcia, J.; Torregrosa-López, J.I.; Lo-Iacono-Ferreira, V.G. A Comparative Analysis of Statistical Models and Mathematics in Reverse Osmosis Evaluation Processes as a Search Path to Achieve Better Efficiency. Water 2022, 14, 2485. [Google Scholar] [CrossRef]
- Sim, A.; Mauter, M.S. Cost and energy intensity of U.S. potable water reuse systems. Environ. Sci. Water Res. Technol. 2021, 7, 748–761. [Google Scholar] [CrossRef]
- National Research Council. Desalination: A National Perspective; The National Academies Press: Washington, DC, USA, 2008; Available online: https://nap.nationalacademies.org/catalog/12184/desalination-a-national-perspective (accessed on 31 January 2023).
- Chamaki, F.N.; Jenkins, H.; Hashemipour, M.; Jenkins, G.P. Wastewater Reuse to Mitigate the Risk of Water Shortages: An Integrated Investment Appraisal. Water 2022, 14, 3859. [Google Scholar] [CrossRef]
- Gingerich, D.; Mauter, M.S. Air Emission Reduction Benefits of Biogas Electricity Generation at Municipal Wastewater Treatment Plants. Environ. Sci. Technol. 2018, 52, 1633–1643. [Google Scholar] [CrossRef] [PubMed]
- Jenkins, G.; Kuo, C.Y.; Harberger, A.C. Cost-Benefit Analysis for Investment Decisions, 1st ed.; Independently Published, 22 January 2019; Available online: https://www.amazon.com/Cost-Benefit-Analysis-Investment-Decisions-Jenkins-ebook/dp/B07N148F2R/ref=sr_1_1?keywords=cost+benefit+analysis+book+Glenn+Jenkins&qid=1680695764&sr=8-1 (accessed on 31 January 2023).
- Bryant, R.E.; Mason, M. Water Technology and Sustainability in North Cyprus: Climate Change and the Turkey-North Cyprus Water Pipeline; PRIO Cyprus Centre Report, 1; PRIO Cyprus Centre: Nicosia, Cyprus, 2017. [Google Scholar]
- Elkiran, G.; Dahiru, A.; Gokcekus, H. Water resources management and trend of water use in North Cyprus. Desalination Water Treat. 2020, 177, 264–274. [Google Scholar] [CrossRef]
- Ağıralioğlu, N.; Danandeh Mehr, A.; Akdeğirmen, Ö.; Taş, E. Cyprus Water Supply Project: Features and Outcomes [Review of Cyprus Water Supply Project: Features and Outcomes]. In Proceedings of the 13th International Congress on Advances in Civil Engineering, Izmir, Turkey, 12–14 September 2018; Available online: https://www.researchgate.net/publication/328042100 (accessed on 31 January 2023).
- Marin, P.; Charalambous, B.; Davy, T. Securing Potable Water Supply under Extreme Scarcity: Lessons and Perspectives from the Republic of Cyprus. 2018. Available online: http://hdl.handle.net/10986/30593 (accessed on 31 January 2023).
- New Nicosia Wastewater Treatment Plant, United Nations Development Program. (n.d.); UNDP. Available online: https://www.undp.org/cyprus/projects/new-nicosia-wastewater-treatment-plant (accessed on 19 January 2023).
- Blair, S.; Rossmiller, B.; Abu-Awwad, A.; Meserlian, M. Bi-communal reuse of treated effluent in Cyprus. J. Water Reuse Desalination 2012, 2, 218–226. [Google Scholar] [CrossRef] [Green Version]
- Simonič, M. Reverse Osmosis Treatment of Wastewater for Reuse as Process Water—A Case Study. Membranes 2021, 11, 976. [Google Scholar] [CrossRef] [PubMed]
- Wang, Z.; Zhang, Y.; Wang, T.; Zhang, B.; Ma, H. Design and Energy Consumption Analysis of Small Reverse Osmosis Seawater Desalination Equipment. Energies 2021, 14, 2275. [Google Scholar] [CrossRef]
- Kamal, A.; Al-Ghamdi, S.; Koç, M. Assessing the Impact of Water Efficiency Policies on Qatar’s Electricity and Water Sectors. Energies 2021, 14, 4348. [Google Scholar] [CrossRef]
- United States Environmental Protection Agency. AP 42, Fifth Edition, Volume I, Chapter 3: Stationary Internal Combustion Sources, 3.4 Large Stationary Diesel and All Stationary Dual-Fuel Engines 3.4.1 General; US Environmental Protection Agency: Washington, DC, USA, 2022; pp. 3.4–5, Table 3.4-1. Available online: https://www.epa.gov/air-emissions-factors-and-quantification/ap-42-fifth-edition-volume-i-chapter-3-stationary-0 (accessed on 31 January 2023).
- Schroten, A.; de Bruyn, S. Handbook on the External Costs of Transport—Version 2019; CE Delft: Delft, The Netherlands, 2019; Available online: https://cedelft.eu/publications/handbook-on-the-external-costs-of-transport-version-2019/ (accessed on 31 January 2023).
- Jenkins, G.P. Evaluation of stakeholder impacts in cost-benefit analysis. Impact Assess. Proj. Apprais. 1999, 17, 87–96. [Google Scholar] [CrossRef]
New Plant | Current Plant | |
---|---|---|
Input capacity (actual flow rate due to friction) | 60 m3/h | 88 m3/h |
Output of potable water per hour operating 20 h/day | 45 m3/h | 38 m3/h |
Operating RO (maximum) | 23.97 h/day | 20 h/day |
Backwash RO | 0.03 h/day | 4 h/day |
Efficiency | 75% | 43.20% |
Electricity input per cubic meter | 1.92 kWh | 3.63 kWh |
Parameter | Definition |
---|---|
PV, as of year 0 (2022), of the quantity of water produced by plant i over 20 years | |
Financial real discount rate | |
Financial cost of plant i in year t | |
Financial value of the payment to the municipality for raw water from operations of plant i | |
Total financial electricity cost of pumping from operations of plant i | |
Total financial chemical cost from operations of plant i | |
Total financial fixed O&M expenditures from the operations of plant i | |
Total financial initial capital costs of plant i | |
Total financial recurrent capital costs from operations of plant i | |
Total financial levelized cost of water of plant i | |
Economic cost in year t (without pollution) of plant i | |
North Cyprus’ economic cost in year t from operations of plant i | |
Cyprus’ economic cost in year t from operations of plant i | |
Global economic cost in year t from operations of plant i | |
Economic value of the payment to the municipality for raw water for operations of plant i | |
Total economic electricity cost of pumping from operations of plant i | |
Total economic chemical cost from operations of plant i | |
Total economic fixed O&M expenditures from operations of plant i | |
Total economic initial capital costs of plant i | |
Total economic recurrent capital costs from operations of plant i | |
Economic cost of local emissions in North Cyprus from operations of plant i | |
Economic cost of local emissions in all of Cyprus from operations of plant i | |
Economic cost of GHGs from operations of plant i | |
Economic levelized cost of water (without pollution), in terms of 2022 prices, of plant i | |
Total economic levelized cost of water (North Cyprus) of plant i | |
Total economic levelized cost of water (all Cyprus) of plant i | |
Total economic levelized cost of water (global) of plant i | |
PV of economic cost in year t (without pollution) from operations of plant i | |
PV of North Cyprus’ economic cost in year t from operations of plant i | |
PV of Cyprus’ economic cost in year t from operations of plant i | |
PV of global economic cost in year t from operations of plant i | |
NPV of financial cost in year t from operations of plant i | |
NPV of economic cost in year t (without pollution) from operations of plant i | |
NPV of North Cyprus’ economic cost in year t from operations of plant i | |
NPV of Cyprus’ economic cost in year t from operations of plant i | |
NPV of global economic cost in year t from operations of plant i |
Row No. | New Plant | Current Plant | Change in Cost | |
---|---|---|---|---|
Capacity utilization (%) | 52.85 | 75 | ||
1 | Quantity of water produced (’000) m3 | 2042.67 | 2042.67 | |
2 | Total payment for wastewater (’000) USD | 272.36 | 473.04 | 200.68 |
3 | Total electricity cost (’000) USD | 678.24 | 1281.37 | 603.13 |
4 | Total chemical cost (’000) USD | 6.23 | 11.92 | 5.69 |
5 | Total variable cost (’000) USD | 856.83 | 1766.32 | 909.49 |
6 | Total fixed O&M costs (’000) USD | 205.16 | 199.18 | −5.98 |
7 | Total initial capital costs (’000) USD | 294.69 | 177.93 * | −116.76 |
8 | Total recurrent capital costs (’000) USD | 202.15 | 239.63 | 37.48 |
9 | Total Fixed Cost (’000) USD | 701.99 | 616.74 | −85.25 |
10 | Total lifetime financial costs (’000) USD | 1658.82 | 2383.07 | 724.25 |
Row No. | New Plant | Current Plant | |
---|---|---|---|
Capacity utilization (%) | 52.85 | 75 | |
1 | Payment to municipality | 0.133 | 0.232 |
2 | Electricity cost | 0.332 | 0.627 |
3 | Chemical cost | 0.003 | 0.006 |
4 | Total variable cost | 0.468 | 0.865 |
5 | Fixed O&M cost | 0.1 | 0.098 |
5 | Initial capital cost | 0.144 | 0.087 |
7 | Recurrent capital cost | 0.099 | 0.117 |
8 | Total fixed cost | 0.344 | 0.302 |
9 | Levelized cost of water | 0.812 | 1.167 |
Row No. | New Plant | Current Plant | Change in Cost | |
---|---|---|---|---|
Capacity utilization (%) | 70.47 | 100 | ||
1 | Quantity of water produced (’000) m3 | 2723.55 | 2723.55 | |
2 | Total payment for wastewater (’000) USD | 363.14 | 630.72 | 267.58 |
3 | Total electricity cost (’000) USD | 902.05 | 1699.41 | 797.36 |
4 | Total chemical cost (’000) USD | 8.31 | 15.89 | 7.58 |
5 | Total variable cost (’000) USD | 1273.50 | 2346.02 | 1072.52 |
6 | Total fixed O&M expenditures (’000) USD | 203.83 | 196.7 | −7.13 |
7 | Total initial capital costs (’000) USD | 294.69 | 177.93 * | −116.76 |
8 | Total recurrent capital costs (’000) USD | 236.9 | 278.97 | 42.07 |
9 | Total fixed cost (’000) USD | 735.42 | 653.60 | −81.82 |
10 | Total lifetime financial costs (’000) USD | 2008.92 | 2999.62 | 990.7 |
Row No. | New Plant | Current Plant | |
---|---|---|---|
Capacity utilization (%) | 70.47 | 100 | |
1 | Payment to municipality | 0.133 | 0.232 |
2 | Electricity cost | 0.331 | 0.624 |
3 | Chemical cost | 0.003 | 0.006 |
4 | Total variable cost | 0.468 | 0.861 |
5 | Fixed O&M cost | 0.075 | 0.072 |
6 | Initial capital cost | 0.108 | 0.065 |
7 | Recurrent capital cost | 0.087 | 0.103 |
8 | Total fixed cost | 0.27 | 0.24 |
9 | Levelized cost of water | 0.738 | 1.101 |
Row No. | New Plant | Current Plant | |
---|---|---|---|
Capacity utilization (%) | 100 | 100 | |
1 | Quantity of water produced (’000) m3 | 3864.94 | 2723.55 |
2 | Total payment for wastewater (’000) USD | 515.33 | 630.72 |
3 | Total electricity cost (’000) USD | 1277.22 | 1699.41 |
4 | Total chemical cost (’000) USD | 11.79 | 15.89 |
5 | Total variable cost (’000) USD | 1804.34 | 2346.02 |
6 | Total fixed O&M expenditures (’000) USD | 201.61 | 196.7 |
7 | Total initial capital costs (’000) USD | 294.69 | 177.93 * |
8 | Total recurrent capital costs (’000) USD | 309.44 | 278.97 |
9 | Total fixed cost (’000) USD | 805.73 | 653.6 |
10 | Total lifetime financial costs (’000) USD | 2610.07 | 2999.62 |
Row No. | New Plant | Current Plant | |
---|---|---|---|
1 | Capacity utilization (%) | 100 | 100 |
2 | Payment to municipality | 0.133 | 0.232 |
3 | Electricity cost | 0.33 | 0.624 |
4 | Chemical cost | 0.003 | 0.006 |
5 | Total variable cost | 0.467 | 0.861 |
6 | Fixed O&M cost | 0.052 | 0.072 |
7 | Initial capital cost | 0.076 | 0.065 |
8 | Recurrent capital cost | 0.08 | 0.103 |
9 | Total fixed cost | 0.208 | 0.24 |
10 | Levelized cost of water | 0.675 | 1.101 |
Row No. | Pollutants from Electricity Generation by Heavy Fuel Oil | kg/MMBtu | USD/kg Emission Costs (2022 Prices) | |
---|---|---|---|---|
1 | Volatile organic compounds | NMVOC | 0.04 | −0.51 1 |
2 | Nitrogen oxides | NOx | 0.86 | 8.8 2 |
3 | Particulate matter | PM10 | 0.03 | 10.45 |
4 | Ultra-fine particulate matter | PM2.5 | 0.02 | 67.61 3 |
5 | Sulfur dioxide | SO2 | 0.46 | 9.94 |
6 | Carbon dioxide | CO2 | 74.84 | 0.07 |
7 | Carbon monoxide | CO | 0.39 | 0.05 |
8 | Methane | CH4 | 0.004 | 0.86 |
Row No. | PV of the Quantity of Water over 20 Years 2042.672 (’000) m3 | New Plant | Current Plant |
---|---|---|---|
Capacity utilization (%) | 52.85 | 75 | |
Local emission | |||
1 | Economic cost of NMVOC emissions | 60.9 | 127.69 |
2 | Economic cost of nitrogen oxide emissions | 101.41 | 212.64 |
3 | Economic cost of particulate matter (10μm) emissions | 3.63 | 7.62 |
4 | Economic cost of particulate matter (2.5μm) emissions | 16.38 | 34.34 |
5 | Economic cost of sulfur dioxide emissions | −0.25 | −0.53 |
6 | Subtotal of local economic cost | 182.06 | 381.75 |
Global emission | |||
7 | Economic cost of carbon dioxide emissions | 72.7 | 152.44 |
8 | Economic cost of carbon monoxide emissions | 0.25 | 0.53 |
9 | Economic cost of methane emissions | 0.04 | 0.09 |
10 | Subtotal of global economic cost | 72.99 | 153.06 |
11 | Economic cost of emissions in North Cyprus | 91.03 | 190.87 |
12 | Economic cost of emissions in all of Cyprus | 182.06 | 381.75 |
13 | Economic cost of GHGs | 72.99 | 153.06 |
14 | Total economic cost of emissions for electricity production | 255.06 | 534.8 |
Row No. | PV of the Quantity of Water over 20 Years 2042.672 (’000) m3 | New Plant | Current Plant |
---|---|---|---|
Capacity utilization (%) | 52.85 | 75 | |
1 | Total economic opportunity cost of wastewater | 20.43 | 20.427 |
2 | Total economic cost of electricity | 678.24 | 1281.368 |
3 | Total economic cost of chemicals | 6.23 | 11.918 |
4 | Total variable cost | 704.9 | 1313.71 |
5 | Total economic cost of initial capital | 294.69 | 177.93 * |
6 | Total economic cost of recurrent capital | 202.15 | 239.63 |
7 | Total economic cost of fixed O&M | 205.16 | 199.18 |
8 | Total fixed cost | 701.99 | 616.74 |
9 | Total cost North Cyprus’ emissions | 91.03 | 190.87 |
10 | Total cost all of Cyprus’ emissions | 182.06 | 381.75 |
11 | Total cost of GHG emissions | 72.99 | 153.06 |
12 | Total economic cost of water (without pollution) | 1406.89 | 1930.46 |
13 | Total economic cost of water (North Cyprus’ emissions) | 1497.92 | 2121.33 |
14 | Total economic cost of water (all of Cyprus’ emissions) | 1588.96 | 2312.20 |
15 | Total economic cost of water (local and global emissions) | 1661.95 | 2465.26 |
Row No. | PV of the Quantity of Water over 20 Years 2042.672 (’000) m3 | New Plant | Current Plant |
---|---|---|---|
Capacity utilization (%) | 52.85 | 75 | |
1 | Levelized economic opportunity cost of wastewater | 0.01 | 0.01 |
2 | Levelized economic electricity cost | 0.332 | 0.627 |
3 | Levelized economic chemical cost | 0.003 | 0.006 |
4 | Total levelized variable cost | 0.345 | 0.643 |
5 | Levelized economic initial capital cost | 0.144 | 0.087 |
6 | Levelized economic recurrent capital cost | 0.099 | 0.117 |
7 | Levelized economic fixed O&M cost | 0.1 | 0.098 |
8 | Total levelized fixed cost | 0.344 | 0.302 |
9 | Levelized cost of North Cyprus’ emissions | 0.045 | 0.093 |
10 | Levelized cost of all of Cyprus’ emissions | 0.089 | 0.187 |
11 | Levelized cost of GHG emissions | 0.036 | 0.075 |
12 | Levelized economic cost of water (without pollution) | 0.689 | 0.945 |
13 | Levelized economic cost of water (North Cyprus’ emissions) | 0.733 | 1.039 |
14 | Levelized economic cost of water (all of Cyprus’ emissions) | 0.778 | 1.132 |
15 | Levelized economic cost of water (global emissions) | 0.814 | 1.207 |
Row No. | PV of the Quantity of Water over 20 Years 2723.55 (’000) m3 | New Plant | Current Plant |
---|---|---|---|
Capacity utilization (%) | 70.47 | 100 | |
1 | Total economic opportunity cost of wastewater | 27.24 | 27.24 |
2 | Total economic cost of electricity | 902.05 | 1699.41 |
3 | Total economic cost of chemicals | 8.31 | 15.89 |
4 | Total variable cost | 937.6 | 1742.53 |
5 | Total economic cost of initial capital | 294.69 | 177.93 * |
6 | Total economic cost of recurrent capital cost | 236.9 | 278.97 |
7 | Total economic cost of fixed O&M | 203.83 | 196.7 |
8 | Total fixed cost | 735.42 | 653.6 |
9 | Total cost of North Cyprus’ emissions | 121.07 | 253.28 |
10 | Total cost of all of Cyprus’ emissions | 242.14 | 506.56 |
11 | Total cost of GHG emissions | 97.08 | 203.09 |
12 | Total economic cost of water (without pollution) | 1673.01 | 2396.13 |
13 | Total economic cost of water (North Cyprus’ emissions) | 1794.08 | 2661.58 |
14 | Total economic cost of water (all of Cyprus’ emissions) | 1915.15 | 2902.69 |
15 | Total economic cost of water (local and global emissions) | 2012.23 | 3105.79 |
Row No. | PV of the Quantity of Water over 20 Years 2723.55 (’000) m3 | New Plant | Current Plant |
---|---|---|---|
Capacity utilization (%) | 70.47 | 100 | |
1 | Levelized economic opportunity cost of wastewater | 0.01 | 0.01 |
2 | Levelized economic electricity cost | 0.331 | 0.624 |
3 | Levelized economic chemical cost | 0.003 | 0.006 |
4 | Total levelized variable cost | 0.344 | 0.64 |
5 | Levelized economic initial capital cost | 0.108 | 0.065 |
6 | Levelized economic recurrent capital cost | 0.087 | 0.102 |
7 | Levelized economic fixed O&M cost | 0.075 | 0.072 |
8 | Total levelized fixed cost | 0.27 | 0.24 |
9 | Levelized cost of North Cyprus’ emissions | 0.044 | 0.093 |
10 | Levelized cost of all of Cyprus’ emissions | 0.089 | 0.186 |
11 | Levelized cost of GHG emissions | 0.036 | 0.075 |
12 | Levelized economic cost of water (without pollution) | 0.614 | 0.88 |
13 | Levelized economic cost of water (North Cyprus’ emissions) | 0.659 | 0.973 |
14 | Levelized economic cost of water (all of Cyprus’ emissions) | 0.703 | 1.066 |
15 | Levelized economic cost of water (global emissions) | 0.739 | 1.14 |
Row No. | PV of the Quantity of Water Produced over 20 Years (’000) m3 | 2042.67 | 2723.55 |
1 | NPV of financial savings | 724.24 | 990.7 |
2 | NPV of the economic cost of water (without pollution) | 523.57 | 723.12 |
3 | NPV of the economic cost of water (North Cyprus’ emissions) | 623.41 | 867.5 |
4 | NPV of the economic cost of water (all of Cyprus’ emissions) | 723.24 | 987.54 |
5 | NPV of the economic cost of water (greenhouse gases) | 80.07 | 106.01 |
6 | NPV of the economic cost of water (local and global emissions) | 803.31 | 1093.56 |
Row No. | PV of the Quantity of Water Produced over 20 Years (’000) m3 | 2042.67 | 2723.55 |
1 | NPV of economic costs | 803.31 | 1093.56 |
2 | NPV of financial costs | 724.25 | 990.7 |
3 | PV of the sum of net stakeholder impacts (rows 1–2) | 79.06 | 102.85 |
Stakeholders | |||
4 | PV economic benefit of fewer emissions for the residents of North Cyprus | 99.84 | 132.21 |
5 | PV economic benefit of fewer emissions for the residents of South Cyprus | 99.84 | 132.21 |
6 | PV economic benefit of fewer GHGs | 80.07 | 106.01 |
7 | PV of savings on payments to the municipality for wastewater | 200.68 | 267.58 |
8 | PV of net stakeholder impacts (rows 4 + 5 + 6 − 7) | 79.06 | 102.85 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Nazari Chamaki, F.; Jenkins, G.P.; Hashemipour, M. Financial, Economic, and Environmental Analyses of Upgrading Reverse Osmosis Plant Fed with Treated Wastewater. Energies 2023, 16, 3292. https://doi.org/10.3390/en16073292
Nazari Chamaki F, Jenkins GP, Hashemipour M. Financial, Economic, and Environmental Analyses of Upgrading Reverse Osmosis Plant Fed with Treated Wastewater. Energies. 2023; 16(7):3292. https://doi.org/10.3390/en16073292
Chicago/Turabian StyleNazari Chamaki, Foroogh, Glenn P. Jenkins, and Majid Hashemipour. 2023. "Financial, Economic, and Environmental Analyses of Upgrading Reverse Osmosis Plant Fed with Treated Wastewater" Energies 16, no. 7: 3292. https://doi.org/10.3390/en16073292
APA StyleNazari Chamaki, F., Jenkins, G. P., & Hashemipour, M. (2023). Financial, Economic, and Environmental Analyses of Upgrading Reverse Osmosis Plant Fed with Treated Wastewater. Energies, 16(7), 3292. https://doi.org/10.3390/en16073292