1. Introduction
A power system operation with a large scale of renewable and intermittent sources may face new obstacles due to the dynamic performance of these sources during the day [
1]. Some of these challenges, such as wind power curtailment (WPC), can be overcome by energy storage systems. In this regard, the pricing of hydro-thermal-wind-photovoltaic (HTWP) power systems and the introduction of a battery energy storage system (BESS) in the Daily Operation Scheduling (DOS) should be adopted and analyzed.
As seen in [
2,
3], for instance, a large scale of wind power generation is being integrated into the electricity grid in Brazil, and some problems may appear. One of them is the WPC, which cut off part of the available wind power generation. This problem occurs when there is congestion in the transmission grid or when the wind power exceeds the difference between the load demand and the minimum generation needed to maintain the stability of the system.
Other situations can cause the reduction of wind power generation in power systems with a significant number of wind farms. In addition to that, this paper explores the effect of Distributed Generation (DG) on the load demand curve and the ramp rate of the thermal power generation.
To reduce such a problem and improve power grid operation, the works of [
4,
5,
6,
7] apply BESS as an option. In this paper, the main application of BESS is to provide an energy time-shift in DOS.
With several sources in a complex power system, the DOS aims to establish a daily generation of each source to attend the load demand optimally and safely for each hour of the day, always for the next day. Furthermore, for the Brazilian national independent system operator, the DOS is a short-term problem with a horizon of up to 2 weeks, with hourly discretization. In this case, more details about the power system are provided, such as, for example, the constraints related to the generating machines and the electric grid, allowing greater reproducibility of the operation by the agents. Plus, the DOS problem can be represented by the DC optimal power flow (DCOPF) problem to explore properties of the real problem, as seen in [
8].
This work is justified as a result of progressive energy market deregulation in some countries with a significant number of wind power plants (WPPs) in HTWP systems and continental-size, like Brazil. In this scenario, it is expected that the energy pricing policy is the main target, as seen in [
9,
10,
11,
12]. Then, an economic signal that should be applied to the day-ahead electricity market is the Locational Marginal Pricing (LMP). This signal is determined by the iteration between the source and the load demand, to get the supply of the cheapest energy source, considering losses and congestion of the transmission grid.
However, for HTWP systems, wind and photovoltaic electricity generation are rarely assessed for economic reasons or as a decision variable for the DCOPF problem, as seen in [
13,
14,
15,
16,
17,
18]. Therefore, this work considers the pricing in the DOS of HTWP systems with the wind and photovoltaic power generation as being variables of the problem and they are modeled with zero-cost. In addition to that, an analysis of the BESS effect to reduce the total operation cost and the WPC is proposed. Plus, the modeling of the DOS problem allows a partial supply of WPP (with power curtailment) due to the safe operation requirements [
19,
20,
21].
The DCOPF, which represents the DOS problem, is solved using the predictor–corrector primal-dual Interior Point Method (IPM). To consider the loss of the system, a modified method, based on [
22,
23,
24,
25], is used to calculate the LMP. The test system is a modified version of the IEEE 24-bus that may represent Brazil.
In Brazil, the Energy Research Company forecasts that the average load demand will grow 3.2% per year until 2030, as seen in [
26]. In this country, several generation ventures are being built to assist load demand, mainly wind farms. According to [
27], the installed wind power generation capacity has increased from 25 MW in 2005 to 15.762 GW in 2020.
In this scenario, the northeast subsystem stands out with more than 85% of the wind power generation capacity, with the states of Bahia and Rio Grande do Norte contributing the most to this type of generation. Furthermore, since 2018 there has been a record of the entire subsystem being served by wind power energy and still being able to export a certain amount of energy [
27].
Moreover, there is a positive fact that the wind power seasonality in the northeast subsystem is complementary to the water profile. In
Figure 1, it is possible to observe this complementarity through the curves of the average affluent natural energy and the average wind power generation in 2019 [
27]. Although photovoltaic generation is not complementary to either of the two sources mentioned above, its growth has been gaining prominence in recent years. Solar irradiation in the northeastern region of Brazil does not have a characteristic variation over the year as the wind power generation, as can be seen in [
28].
This complementarity is a reason that brings security to the energy supply. In addition, wind power generation is spread across the northeast subsystem, which causes a difference in wind behavior during the day.
Figure 2 shows the average hourly capacity factor curves of WPPs in the states of Bahia (inland) and Rio Grande do Norte (coast) in 2019, as well as the daily profile of average load demand curve for the northeast subsystem, in the same year [
27].
The WPC has been strongly discussed in the literature on thermal-based systems. Yet, for hydro-based systems predominantly, as in Brazilian ones, the power depends on river inflows and reservoir storage levels. In the driest period, this may cause a risk of energy deficit, as can be seen in [
8,
29]. Therefore, in this case, the priority is to use the available wind or photovoltaic power. Furthermore, the continental dimensions of Brazil and the fact that the power system is regionally connected make the country even more dependent on hydrological and wind regimes. This point causes an interdependence among the subsystems and is necessary to avoid WPC for energy security, economic and strategic reasons [
18].
More specifically, the main contribution of this paper is to present an analysis in which the wind power generation, modeled as a variable and with the help of BESS, performs an efficient WPC in the DOS of HTWP systems. Thus, a new contribution is provided, since the analysis shown here may be an economical solution.
Following, in
Section 2 is described the DOS formulation used in HTWP systems with BESS and the WPC, and it is shown how the losses were included in the DCOPF problem to calculate the LMP values by an iterative method. The studied cases and results are shown in
Section 3. Finally, in
Section 4 are presented discussions and the conclusion of the study, respectively.
2. Materials and Methods
The DOS problem aims to minimize the operation costs, and the decision variables are time-linking. In other words, the modeling used here is assembled so that the solution of the problem is found considering the variable for the first hour of the day and the last one. The mathematical formulation of the DOS problem considered here is described below.
Following, the t index represents each hour of the day, and the maximum length is . In addition to that, the i index represents each bus of the system, and the is the set of buses.
2.1. Hydroelectric Power Plants
The operational limits of Hydroelectric Power Plants (HPPs) depend on the turbine flow limits and the levels of downstream and upstream, according to [
30]. However, to simplify the problem, hydraulic variables are omitted in this model. This way, the operational limits of the HPPs are represented by constraints:
where
is the HPP dispatch at the bus
i in period
t;
and
are the minimum and maximum operating limits of the HPP at the bus
i, respectively.
2.2. Thermoelectric Power Plants Constraints
The operational limits of Thermoelectric Power Plants (TPPs) are represented by constraints:
where
is the TPP dispatch at the bus
i in period
t;
and
are the minimum and maximum operating limits of the TPP at the bus
i, respectively.
In addition to that, according to [
30], maximum ramp rate constraints for the increase and decrease of TPP generation are enforced as operative features that couple two consecutive periods. Thus, in some cases, it is not possible to admit an abrupt variation in the power generated in short intervals of time. Mathematically, ramp rate constraints are modeled by:
where
is the maximum ramp rate of the TPP at the bus
i. In this formulation, we consider the ramp down and ramp up constraints to be the same value.
2.3. Wind Power Plants Constraints
Wind power generation has a dynamic behavior according to the location where the wind farms are installed. This variability promotes several studies to represent this generation as a variable of the model in the DOS problem. For this, it is considered the hourly wind power forecast is the maximum limit that this variable can achieve [
18,
31,
32,
33].
In addition, the operational limits, represented by the predicted wind power for each hour of the day, allow a partial or total WPC. This modeling may be considered in a regional context, as seen in [
34,
35,
36]. Thus, the geographic diversification of WPP can smooth out the fluctuations in wind power generation, making it more predictable. Finally, the wind power variables and your limits can be represented by:
where
and
are the wind power generation and the expected production at the bus
i in period
t, respectively.
2.4. Photovoltaic Power Plants Constraints
The power generation of a photovoltaic power plant (PPP) also has a dynamic behavior according to the location where the solar farms are installed. Therefore, here, it is considered the hourly solar power forecast as the maximum limit that this variable can achieve [
37]. The photovoltaic power variables and the limits can be represented by:
where
and
are the photovoltaic power generation and the expected production at the bus
i in period
t, respectively.
2.5. Battery Energy Storage Systems Constraints
As it was previously mentioned, the use of BESS can be an alternative to reduce the WPC. Therefore, when there is surplus wind power energy, the amount of energy that would be cut, now it can be stored. For this, the BESS acts as load demand, when there is an excess of wind power generation, and provide power injection, alternatively.
The stored energy helps to reduce peaks and valleys of the load demand curve. Thus, the BESS discharge energy quickly in some situations: when the hourly price is higher than when the energy had been stored; when the system requires additional power to meet the load demand; and when it is necessary to relieve the transmission system.
The characteristics of BESS were modeled here, such as proposed in [
33,
38,
39,
40]. The energy capacity of BESS is generally defined according to the type of technology used to conserve the energy, and the constraints are represented by:
where
is the energy stored at the bus
i in period
t;
and
are the minimum and maximum storage capacities at the bus
i, respectively. The energy stored available is:
where
is the BESS self-discharge rate at the bus
i;
is the BESS efficiency at the bus
i;
and
are the BESS discharging and charging at the bus
i in period
t, respectively.
Furthermore, the term State of Charge (SOC) defines, in percentage, the level of energy stored in BESS. The constraints of these variables are defined by:
where
is the SOC at the bus
i in period
t, and its limits, that increase the useful life of BESS, are defined by:
where
and
are the minimum and maximum SOC of BESS at the bus
i, respectively. This way, relating (
8) and (
9), it is possible to obtain new limits for stored energy through:
Finally, as can be seen in [
40], the charging and discharging power variables can be related to the variable
, described by:
This is allowed since
and
are solutions of DCOPF problem, and:
Therefore, it is possible to represent charging and discharging limits separately in two variables, respectively, by:
and
where
and
are the BESS charging and discharging limits at the bus
i, respectively.
2.6. Energy Balance Constraint
The energy balance constraint is responsible for supplying the load demand and guaranteeing the use of all energy generated. This constraint is defined by:
and
where
and
are the net and expected load demands at the bus
i in period
t, respectively;
is the DG in period
t.
The DG is modeled here as a reduction in expected system load demand in a certain period. Thus, it is a generation that cannot be controlled by the power system, but we can use it with an expected daily curve.
2.7. Transmission Limits Constraints
The transmission system has constraints related to the system security that influence the operating decisions. In this work, the DC power flow is modeled using the Power Transfer Distribution Factors (PTDF) matrix [
41], and it is represented by:
where
is the element of the PTDF matrix;
is the power flow variation at the
k transmission line due the injected or extracted power
at the bus
i;
is the set of transmission lines.
In addition to that, the PTDF matrix contains the participation of power injection factors in the composition of the flows in the system transmission lines. This matrix can be defined by:
where
is the primitive admittance matrix and
is the reduced system incidence matrix. Therefore, the inequality constraints that define the capacity of the transmission system are:
where
is the capacity of the transmission line
k.
2.8. Objective Function
The objective of the DOS problem is to minimize the total operating cost related to the fuel cost from scheduled TPP. However, it is necessary to define a priority order when the system is faced with the possibility to choose the energy provided from other sources. For HPP and BESS, the energy is considered with a null unitary cost. Therefore, a priority factor that the IPM will choose the WPP or the PPP as a priority source is proposed here. This technique was created to avoid the WPC and based on the environmental value of the water.
The priority factor
is a value that does not interfere in the IPM to find the best solution. Then, the objective function of the problem may be represented by:
where
is the cost of fossil-fuel generator
i, and it is adopted
= −10
R
$/MWh.
2.9. DCOPF with Losses and the LMP
In this subsection, the calculations of the system losses and the LMP for DCOPF are described. It can be done with an iterative method, but, different from what is described in [
22,
23,
24,
25], this work considers the dimension of the problem to achieve the solution.
To simplify the development of the method, the ramp rate and energy storage constraints are disregarded. In addition to that, the active power injection at the bus
i in period
t is represented by the new variable
defined by:
Thus, (
15) and (
19) can be rewritten, respectively, as:
and
Lastly, the active power injection limits are defined by the constraints:
2.9.1. System Losses Evaluation
Most DCOPF studies ignore electrical losses. In these cases, the energy price and the congestion price follow a linear model with a null loss price. However, system losses need to be considered in LMP.
To represent the system losses, the components Marginal Loss Factor (MLF) and Marginal Delivery Factor (MDF) are used, which are defined, respectively, by:
and
where
is the total system losses that can be represented by:
where
is the resistance of transmission line
k.
Thus, we can represent the power flow through the PTDF matrix and obtain a new equation for the MLF:
In this case, the MLF can be positive or negative. When positive, it means that the increase of the power injection at bus can increase the system losses. When negative, the increased injection on the bus can reduce system losses.
It has been observed in [
22] that the MDF may double losses. Furthermore, in the same work it is proved that, in this model, an offset should be the estimated total system losses. Therefore, (
22) can be rewritten by:
where
is the offset or total system losses.
As shown in (
28), the MLF values depend on the power flow in the transmission lines. To overcome this obstacle, the DCOPF problem is solved firstly without considering the MLF (
= 0,
= 1 and
= 0). Therefore, with the solution found, the MLF values can be estimated and the DCOPF problem is solved again. This iterative process is repeated until the convergence stop criteria is reached. This entire process can be seen in the flowchart shown in
Figure 3.
This method converges when:
or
where
m is the iteration of the method and
n is the the number of power system buses.
2.9.2. LMP Evaluation
After obtaining the DCOPF solution, the LMP can be calculated for any system bus from the Lagrange function
:
and
where
is the Lagrange multiplier related to the energy balance restriction;
is the Lagrange multiplier related to the lower limit constraint;
is the Lagrange multiplier related to the upper limit constraint.
Therefore, the LMP is calculated by:
2.9.3. Fictitious Nodal Demand for System Losses
In (
23), the power flow assumes a network without electrical losses, and the energy balance constraint, in (
29), requires that the total generation be greater than the total load demand due to system losses. This leads to a mismatch effect, in a way that all losses appear in bus reference, as proven in [
22]. Thus, it is necessary to represent the losses in the transmission lines.
To solve this problem, we implemented the Fictitious Nodal Demand (FND) concept to represent the electrical losses of the transmission lines connected to a bus. Hence, the FND is responsible for distributing system losses for each line of the network, aside from mitigating the mismatch effect. In this case, the losses of the transmission line are divided into two halves at respective buses. Thus, each half represents an increase in load demand at that bus. Finally, FND can be represented by:
where
is the set of transmission lines connected to bus
i.
Now, the power flow will also be limited by the FND:
Additionally, some steps in the iterative process, shown in
Figure 3, are modified to integrate the FND: the second step, that initializes the marginal loss variables, should now consider
, and the step of updating these variables should now evaluate
.
Considering the DOS problem presented here, the next step is to verify solutions of operation and pricing.
4. Conclusions
This paper considered the DOS in an HTWP power system with a high intake of wind power energy, which can be wasted due to the existing constraints in the optimization problem. WPP was modeled as a priority over other sources since its operating cost is equal to zero and promotes less environmental impact. In addition, WPPs may also control the power dispatch.
To reduce the WPC, it was proposed to use BESS on the same bus that the problem arises. In addition to being able to store the wasted energy, the storage system also promotes the benefit of relieving overloaded transmission lines. For this, it was observed that BESS fulfilled the role of shifting energy over time, as expected. Thus, the energy was stored during the period when there was less demand to be dispatched in moments of great load requests from the system.
The results for the modified IEEE 24-bus system showed that WPC can impact the operating costs. This is explained as other sources with a considerable cost must operate as a replacement for WPPs to supply the energy demand. It was observed that the use of BESS could promote a 2.65% reduction in operating costs in the analyzed case. As the analyzed system is a genuine reduction of the Brazilian power electric system, larger systems can generate even greater reductions.
In addition to reducing WPC and operating cost, the BESS used also impacted the average LMP, which signal prices were reduced to higher value times. This caused the appearance of a negative signal part in part of the system due to an overload in one of the transmission lines, indicating how susceptible the system can be.
We conclude that the modeling of WPP as a variable of the problem in cases in which there is a great intake of wind can promote better analysis of the WPC. This makes it possible to use storage energy systems to assist the elimination of WPC and other problems, such as the reduction of operating costs and daily signal prices.
We suggest for future work a further investigation of other energy storage technologies, the use of stochastic models for forecasting variables, and a study about the sensitivity of the signal prices with the presence of BESS in the power system. These additional analyses can promote an improvement in the results found here and open new study paths.