Abstract
Public private partnerships (PPPs) are a well-known instrument used worldwide by public administration (PA) to build public infrastructure using private knowhow and financial resources, and sharing risks. In recent years, PPPs have been widely adopted to develop energy efficiency projects between public and private sectors. In this context, a successful project requires a contractual arrangement based on energy performance contracting (EPC) that balances the interests of the two parties. This paper aims to answer two questions: how to share the benefits between the contractual parties and reach an optimal long-term contractual agreement; and which type of contract ensures a consistent risk transfer to the private partner, allowing the PA an “off balance” accounting treatment. The research questions are answered through the development of a mathematical equation able to calculate the optimal percentage of benefits sharing between partners in a long-term contractual agreement. The results are tested with a simulation based on a case study about the energy efficiency project of an Italian hospital. The paper is innovative because it provides suggestions to improve the EPC-PPP contractual structure and realize a balanced agreement between the public and private partners. Moreover, it analyzes the different allocation of risks in EPC contracts to identify the implication for the PA in terms of on-off balance accounting treatment in energy efficiency investment. We show how a successful long-term EPC-PPP can benefit from a mixed contractual structure in which profit-sharing percentage changes during the contract’s life to ensure the same net present value (NPV) to both public and private partners. This paper supports public decision making in order to choose contracts that are able to transfer energy and management risks. Moreover, it helps to understand the balance between public and private interests in a long-term EPC-PPP contract.
1. Introduction
Energy performance contracts (EPC) were first developed in the 1970s and gradually become one of the most used approaches to energy savings and emission reduction. Many European and non-European countries use EPC contracts to reach the goal of sustainable development in line with European Commission directives that require matching the objectives fixed in the European energy policy plan 2030 [1]. The target is a share of at least 32% for renewable energy and at least 32.5% in energy efficiency improvement by the end of 2030.
As reported in the “Energy Efficiency Report 2019” [2], the total of investments in energy efficiency in 2018 in Italy were equal to approximately euro 7.1 billion. The trend of the last 5 years has been very positive, recording a CAGR (compound annual growth rate) of 12%. The Home and Building segment leads the investment ranking (with 65% of the total), followed by the industrial sector (overall around euro 2.3 billion, just under 33%) and finally the Public Administration, with 2% of the total investments.
The public administration, although it accounts for only 2% of the total, has the largest increase compared to 2017 (+12%) and, in recent years, many deals have been launched by the PA under PPP schemes.
In general, these deals are arranged by a private entity, usually an energy service company (ESCO), that provides energy audit, energy savings, technological development and performance-based projects to the public administration (PA) [3,4,5,6,7].
These contracts can be classified as public private partnerships (PPPs); nevertheless, the notion of PPPs is not commonly shared [8,9]. Some countries, including Italy, consider any partnership between public and private as PPP. Other countries, in line with Eurostat guidance, consider PPP as the agreements in which the main payer of the services is the PA [10,11]. The EU defines PPPs as “long-term contractual arrangements between a government body and a non-government partner, usually for public service building projects. The partner is responsible for building, operating and maintaining an asset, and in exchange the government body pays regular fees to the partner” [1].
According to the Eurostat decision and international public sector accounting standards (IPSAS), it is possible to consider the investment “off” public accounts (so called “off-balance accounting treatment”) only if the main risks of the project are transferred to the private partner. PA has a strong interest in off-balance treatment due to public budget constraints [12,13,14,15,16,17].
In recent years, the promotion of the energy efficiency of public buildings and environmental and social sustainability became a central issue for public administrations (PA). For this reason, many administrations are signing energy performance contracts (EPC), mainly with energy service companies (ESCO), to perform activities related to the provision of energy services. These services involve investments such as the co-generation of plants, heating systems, air-conditioning plants, the thermal insulation of buildings and the installation of solar panels or led lights [18,19,20,21].
The implementation of these energy efficiency systems is normally accompanied by the introduction of technologically advanced systems of performance monitoring [22], which are becoming an important part of the deal.
These systems are based on intelligent buildings and internet of things (IoT), that allow real-time energy monitoring and control in order to improve energy-saving and efficiency [23,24].
These monitoring systems are even more important in the context of PPP because they enable a better allocation of performance risks between partners, allowing PA to develop control activities and performance-based mechanisms.
This type of contract (here called EPC-PPP contracts) presents typical features (mainly fixed price and risks transfer) that perfectly match public–private partnership (PPP) schemes. Nevertheless, the possibility of accounting these contracts’ off-balance is not always shared in practice and in the literature.
In 2017 Eurostat clarified how to account EPC contracts in national accounts, specifying that “For an EPC to be recorded off government balance sheet, the EPC contractor must be considered as the economic owner of the assets installed, which means that it will have to be the entity incurring most of the risks and benefitting from most of the rewards related to the EPC contract.”. In the past, researchers, operators and the legislator focused on issues such as: (i) the contract life, (ii) the existence of contracts, whether government provides financing or other guarantees to the EPC provider, (iii) on the clauses able to distort the distribution of the risks and rewards in a the EPC contracts.
In addition, it is important to check if the EPC contractor is classified outside the general government sector.
Moreover, the EU commission affirms that “The possibility of off balance sheet recording can make the use of EPCs more attractive, allowing governments to invest in energy savings while complying with the debt and deficit thresholds established in the Maastricht Treaty”.
The issue of risk transfer from public-to-private will be consequently examined, showing that there are two main operational risks to allocate: energy performance risks (EPR) and operation performance risks (OPR). For both, advanced monitoring systems have a positive impact on risk allocation and, consequently, on the off-balance treatment.
The paper answers a major problem encountered on the market regarding how to set PPP-EPC deals, which equally share benefits between the public and private partners and can be counted as off-balance by the PA because of an allocation of the projects’ risks, consistent with the legal framework.
The goal of the first part of the paper is to identify and discuss the main risks that discourage or limit the adoption of EPC contracts, including on–off balance, accounting for the treatment of the energy investments.
The second part of the paper is focused on the PA decision-making process, in line with some authors [25,26,27]. We will try to identify a sustainable model for building energy efficiency and, in particular, a model able to minimize the difference between the net profit (NPV) gained by the contractual parties, ensuring a balanced condition [28].
The use of NPV in the evaluation of PPPs is also suggested in the PPP guidelines 2018 by the Italian contract authority (ANAT) that require, in a private proposal, an NPV near zero to avoid extra profit from the investments.
Building upon the model proposed by Carbonara and Pellegrino [28] for “assessing and benchmarking the net benefit of different EPC structures”, this paper aimed to identify a new contract structure able to minimize the difference in net present value (NPV) gained by the contractual parties in a long-term agreement.
The paper answers the following research questions.
- Which kind of “PPP-EPC contracts are able to provide an optimal allocation of the risks ensuring an off balance accounting treatment of the investment?
- Which contractual structure is able to minimize the difference of the net present value (NPV) gained by the contractual parties’ in a long term agreement?
The paper is organized as follows: Section 2 examines risk allocation in PPP-EPC contracts and discusses how to share the benefits of EPC contracts. Section 3 presents the methodology and a numeric simulation on a case study. Section 4 discusses the results obtained. Section 5 presents the conclusions, policy implications and limitations of the paper, identifying future research activities.
3. Methodology
To test this assumption, an equation is developed and tested.
We use the Carbonara and Pellegrino [28] model as an interpretative lens to understand the net benefits gained by public and private partners through an EPC contract, and demonstrate that a new contractual agreement (which we call “mixed contract”) is able to ensure the balance of economic benefits for the parties in a fixed-period, long-term concession.
Let us assume the optimal equilibrium condition as the NPV’s ESCO and government (G) difference is equal to zero:
NPV(ESCO) − NPV(G) = 0
Equation (1) is used to calculate the NPV (ESCO) over two different periods. The period “1–n” necessary for investment amortization, the period “(n+1)–z”, where z is the end of the concession contract:
−I0 = Investment
CF ESCO = cash flow ESCO
x% = percentage of profit sharing ESCO
1−x% = percentage of profit sharing government
n = year of complete amortization of the investment (break even)
z = year of end of the contract
i = discount rate %
Equation (2) is used to calculate the NPV(G) under the same conditions, but assuming the government obtains a value of investment from the partners to repay with energy savings cash flows (CF Gov):
where:
+I0 = Investment achieved
−CF Gov = cash flow paid by government
CF ESCO = cash flow ESCO
x% = percentage of profit sharing ESCO
1−x% = percentage of profit sharing government
n = year of complete amortization of the investment (break even)
z = year of end of the contract
i = discount rate %
Equation (1) quantifies the NPV of the ESCO. It is the sum of the net cash flows earned by the energy company until the amortization of the investment (year n), and the net cash flows earned until the last year of concession (year z), because of the activation of the profit sharing option.
Equation (2) quantifies the NPV of the government by the sum of the net cash flows paid (until year n), and the net cash flows earned until the end of the contract (year z) because of the activation of the profit-sharing option.
Equation (3) quantifies the optimal profit-sharing % in year n + 1, based on the assumption that NPV (ESCO) – NPV (G) equal to 0.
In particular, NPV (ESCO) is given by the investment paid (−I0) in time zero, as repaid by the 100% of savings (until year n), and by a recognition of a percentage of total savings in the period n + 1 to z (after investment amortization).
The NPV (G) is given by the value of investment achieved (+I0), with less savings paid (or renounced) in favor of the ESCO, plus the % of savings earned after the amortization of the investment. This theoretical NPV is affected by real and figurative outflow (including savings renounced by the PA).
By using the proposed Equation (3), it will be possible to determine the optimal percentage of profit-sharing over a long-term contract or to re-determine this percentage for contract re-balancing when savings are changed during the concession period.
Numeric Simulation on A Case Study
A numerical simulation is used to demonstrate our assumption. Data and general information for the simulation have been collected from internal documents and talks with public officer in charge of the project of energy efficiency of an Italian Hospital. Because the project is still in the tender phase, the name of the hospital is kept confidential and we call it “AL Hospital”.
The PPP-EPC-contract of “AL Hospital” has two central elements:
- Energy efficiency, rationalization and compliance, through investments, partly "guided" by hospital requirements, and partly by the "free" or "free proposal" part of the competing Economic Operator during the tender;
- The transfer of management and maintenance risks, both in relation to the existing hospital assets.
The project is going to be realized with a PPP-EPC contract, which aims to achieve environmental comfort performance indicators (temperature, relative humidity, air changes, lighting, etc.), with a “control room” for the constant measurement and verification of the compliance with contractually defined objectives.
The contract structure aims to ensure an agreed level of performance through proper management and maintenance of the assets, mainly focusing on energy services (heating and continuous thermal services, cooling/air conditioning, trigeneration of heating, cooling and electrical energy). Because both OPR and EPR are going to be transferred to the private partner, the investment (in the management opinion) will be counted as off-balance.
Nevertheless, as the contract has not been signed yet, a simulation on the NPV achievable by the project under different contractual agreements (shared savings, first out, first out + option of shared savings) is carried out to demonstrate the convenience of a “mixed contract” in a long-term concession contract of 16 years (1 year construction and 15 years management).
As has been seen, the project refers to an EPC-PPP contract for building energy efficiency in the health sector. In particular, the AL (Alessandria) Hospital launched a public procurement to identify a private operator able to realize euro 10 million investments and manage the related energy services for a value of about euro 9.9 million per year.
ESCO retains 100% savings to amortize the investments. Savings amount euro 1.3 million per year on a total expense of euro 9.97 million. The concession is assumed to be 16 years. The discount rate is assumed to be 5%, in line with the European Commission recommendations. The EU suggests using a 5% financial discount rate as a benchmark for financial investment projects who use EU funds. However, values that deviate from the 5% may be accepted due to: (i) specific macroeconomic conditions in the member state, (ii) investor nature (iii) the sector of activity (e.g., hospitals, environment, energy, etc.). Nevertheless, in the literature, Carbonara and Pellegrino [28] demonstrated that the “discount rate” does not strongly influence the choice of the appropriate contract.
The period of analysis and calculation is assumed to be 1 year for construction and 15 years for cash flows.
Actual and “to be” energy and management costs are reported in Table 2.
Table 2.
Current and expected expenses for energy services in AL Hospital.
Current expenses are the expenses incurred by the administration before the energy efficiency intervention. Expected expenses are the expenses incurred by the administration after the energy efficiency intervention. Their difference measures the annual savings obtained through Energy efficiency investments.
On the basis of these assumptions, it is possible to calculate the NPV (ESCO) and NPV (G) under the following contractual structures: “shared savings contract”, “first out contract” and “mixed contract”.
4. Main Findings and Discussion
In the “first out contract” (first column), the NPV (ESCO) is euro 3.4 million due to earnings of euro 1.30 million per year for 15 years, without any sharing mechanism of savings with the government. Because the whole amount of cost savings is paid to the ESCO, we have a fast investment amortization and debt repayment, with the ESCO gaining extra profit equal to the savings from the end of the amortizations of the investments until the end of the concession. The ESCO gets an IRR (internal rate of return) of 10%.
Vice versa, the PA waives a cash flow of 1.3 for 15 years in exchange for an investment of 10 million euro. The NPV of the government is then euro −3.4 million, because the contract period is higher than necessary and extra profits are generated (from year 11) only to the benefit of the ESCO without any re-distribution to the government. Only by setting the end of the contract to be in 10 years can the NPV of the partners be balanced.
In the “sared saving contract” (second column), the NPV (ESCO) is 0.8 million. We assumed the ESCO is gaining 80% of savings (euro 1.05 million) per year for 15 years to amortize an investment of euro 10 million. The government gets 20% of savings (euro 0.26 million), which reduces the amount spent (or virtually spent) every year for the services provision. This means that the PA waives a cash flow of 0.79 million (euro 1.05–euro 0.26) for 15 years in exchange for an investment of euro 10 million. The difference between NPV (ESCO) and NPV (G) is negative because the PA gets an NPV higher than the NPV (ESCO). The NPV (G) is theoretical because it does not involve a real financial outflow towards the PA, but only measures the value for money that the PA forgoes during the concession.
Therefore, this model is more convenient for the PA (compared to the first out contract); nevertheless, it is still sustainable for the ESCO, which is able to amortize the investment in 14 years with an IRR of 6%.
In the “mixed” model (third column), the NPV (ESCO) is euro 1.1 million. The ESCO earns euro 1.30 million for the first 10 years over 15 of management, than the percentage of profit sharing is calculated according to Equation (3). Then, from year 11 until the end of the concession, the ESCO earns only euro 0.43 million. From year 11, energy savings are shared according to Equation (3) in about 32.5% to ESCO and 67.5% to the PA. The equation used to calculate the profit-sharing percentage allows partners to achieve the same NPV at the end of the contract. Moreover, because partners share the savings only after the amortization of the investments, the ESCO is able to: (i) to maximize its internal rate of return and (ii) reduce the amortization period improving the projects’ bankability (Table 3).
Table 3.
Net present value comparison in EPC contracts.
Nevertheless, while previous authors identified the “first out contract” as the model that minimizes the difference in the economic benefits of the partners, our findings show that a “mixed contract” (combining “first out” and “shared savings” contracts) avoids the distortion of excessive benefits gained by the ESCO in a longer concession period and ensures benefits to both partners, achieving the goal of an equal NPV (see Appendix A, Table A1, Table A2 and Table A3).
Equation (4) can determine the % of savings available to share between the party at year n + 1 to rebalance the contract to an NPV (ESCO) – NPV (G) = 0.
I0 = investment = 10 million euro
CF Gov = cash flow government = 1.30 million euro
CF ESCO = cash flow ESCO = 1.30 million euro
n = year of complete amortization of the investment (break even) = 10
z = year of end of the contract = 16
i = discount rate = 5%
x% = percentage of profit sharing ESCO = ?
1−x% = percentage of profit sharing government = ?
Unfolding the equation, we arrive at the following results:
x = 32.5%
1−x = 67.5%
All three types of contract achieve satisfactory profitability ratios for the ESCO (IRR higher than the discount rate that ranges between 10% and 6%). At the same time, all three contracts are theoretically sustainable for the PA, which finances the new investment, with energy savings without additional expenses. Nevertheless, the analysis shows that the mixed model is best able to balance the benefits between partners pursuing the principle of “equally sharing benefits”.
In particular, the proposed new contractual model called “mixed contract” ensures that ESCO and PA have the same NPV, allowing the PA to demonstrate the value for money of its choices. Moreover, the ESCO optimizes the amortization period of its investment and is able to rapidly reimburse its debts, reducing financial costs and increasing project bankability (when banking resources have been provided).
5. Conclusions and Policy Implications
The paper can be framed in the public choice theory and, in particular, in a neo-classical approach to economic behavior. These models assume that private operators are motivated primarily by individualism. Institutions and policy makers have to guide the partners toward agreements that equally share the benefits and create value for money for the PA.
Several public guidelines in different countries have been produced which require PA: (i) measuring the value for money achieved in PPPs as a justification for the privatization of public services and (ii) avoiding extra profits, generated during the contract’s life, for private operators. In particular, the Italian evolution guideline suggests that extra profit is generated when the IRR of the project is higher than the weighted average cost of capital (WACC) for the investor (ESCO).
The value of this paper is identifying an alternative contractual model for sharing energy savings and proposing a simple but useful equation to calculated profit sharing % after the investment amortization. The model is based on the assumption of “equal NPVs”. Although, in coherence with previous studies [28], the “equal NPV” is considered a good measure of equally shared benefits, our results differ from previously published papers because we consider “first out” contracts to be sub-optimal in long-term agreements or when the amortization period of the investments can be defined ex ante with certainty (e.g., energy savings can vary during the contracts).
In addition, the paper answers the first question “which kind of PPP-EPC contracts are able to provide an optimal allocation of the risks ensuring an off balance accounting treatment of the investment?” by identifying theoretical advances in risk-transfer conditions for the off-balance accounting of PPP-EPC contracts. It shows that the “shared savings” contract does not allow “off balance” recording, while “guaranteed savings” and “first out” contracts are more attractive for the PA, allowing (when transferring availability risks) an “off balance accounting” of the investments.
Moreover, the paper suggests solutions to mitigate some of the barriers (identified in the literature) to EPC use [34]. In particular, the transfer of financial and operating risks to a private partner mitigates the public budget constraints while, at the same time, the use of advanced monitoring and control systems mitigates the operational risks, ensuring an efficient management and an easier application of the contract’s penalties.
The paper also answers a second question “which contractual structure is able to minimize the difference of the net present value (NPV) gained by the contractual parties in a long term agreement?” In particular, it provides a new model of calculation of shared savings (called mixed contract) with an extended possibility of application in EPC-PPP schemes.
This paper is innovative because it provides additional insight and knowledge, useful to support public decision-making in the use of a new contractual structure (called mixed model), which is able to combine the better elements of the “first out” contract with those of the “shared savings” contract, balancing the public and private benefits of EPC-PPP contracts in long-term concession contracts. In particular, although all three models can be used within the contractual freedom left to the parties, the “mixed contract”, is preferable to other models because it ensure a satisfactory IRR to the ESCO and, at the same time, the maximum value for money for the PA.
The results of this paper are also useful to the academic community and practitioners interested in finding solid and fair agreements with the PA.
The interpretation of the results finds is limited in the use of a single case study, which makes it necessary to plan further research activity aimed at testing results under the different conditions of energy savings and a discount rate. Future research avenues should also focus on more standardized contractual solutions for an optimal allocation of risks between partners or aimed at setting up monitoring and control indicators which are useful to apply contractual penalties ensuring: (i) an ongoing monitoring of the project revenues and costs necessary to identify the real amortization period of investments and (ii) a transfer of OPR to count such contracts as off-balance.
Author Contributions
The authors contributed equally to the development of this research, and are listed in alphabetical order. Conceptualization, L.M., D.M., F.P. and R.T.; Data curation, L.M., D.M., F.P. and R.T.; Formal analysis, L.M., D.M., F.P. and R.T.; Investigation, L.M., D.M., F.P. and R.T.; Methodology, L.M., D.M., F.P. and R.T.; Project administration, L.M., D.M., F.P. and R.T.; Resources, L.M., D.M., F.P. and R.T.; Software, L.M., D.M., F.P. and R.T.; Supervision, L.M., D.M., F.P. and R.T.; Validation, L.M., D.M., F.P. and R.T.; Visualization, L.M., D.M., F.P. and R.T.; Writing—original draft, L.M., D.M., F.P. and R.T.; Writing—review & editing, L.M., D.M., F.P. and R.T. All authors have read and agreed to the published version of the manuscript.
Funding
This research received no external funding.
Conflicts of Interest
The authors declare no conflict of interest.
Appendix A
Table A1.
First out contract—cash flows.
Table A2.
Shared savings contract—cash flows.
Table A3.
Mixed contract—cash flows.
References
- Studies on Climate Change Related Aspects. Available online: https://ec.europa.eu/clima/policies/strategies/2020_en#tab-0-2 (accessed on 4 June 2020).
- Edison. The Energy Efficiency Report 2019. Available online: https://www.efficienzaenergetica.edison.it/primo-piano/energy-efficiency-report-2019/ (accessed on 4 June 2020).
- Zhijian, L.; Shuai, S. Impact of government subsidies on pricing and performance level choice in Energy Performance Contracting: A two step optimal decision model. Appl. Energy 2016, 184, 1176–1183. [Google Scholar]
- AlFaris, F.; Juaidi, A.; Manzano-Agugliaro, F. Improvement of efficiency through an energy management program as a sustainable practice in schools. J. Clean. Prod. 2016, 135, 794–805. [Google Scholar] [CrossRef] [Scilit]
- Bertoldi, P.; Rezessy, S.; Vine, E. Energy service companies in European countries: Current status and a strategy to foster their development. Energy Policy 2006, 34, 1818–1832. [Google Scholar] [CrossRef] [Scilit]
- Lee, M.K.; Park, H.; Noh, J.; Painuly, J.P. Promoting energy efficiency financing and ESCO in developing countries: Experience from Korean ESCO business. J. Clean. Prod. 2003, 11, 651–657. [Google Scholar] [CrossRef] [Scilit]
- Berrutto, V.; Renzio, M.; Adnot, J.; Vine, E. How are EU ESCOs behaving and how to create a real ESCO market? In Proceedings of the 2003 ECEEE summer study conference, Paris, France, 2–7 June 2003; pp. 909–916. [Google Scholar]
- Burger, P.; Hawkesworth, I. How to attain value for money: Comparing PPP and traditional infrastructure public procurement. OECD J. Budg. 2011, 11, 1–56. [Google Scholar]
- Dastig, M. How can EU-Funds be used to finance Public-Private Partnerships? Eur. Public Private Partn. Law Rev. 2009, 4, 158. [Google Scholar] [CrossRef] [Scilit]
- HM Treasury. Value for Money Assessment Guidance. Available online: http://www.hmtreasury.gov.uk/d/vfm_assessmentguidance061006opt.pdf (accessed on 2 June 2020).
- Shaol, J.; Stafford, A.; Stapleton, P. The cost of using private finance to build finance and operate hospitals. Public Money Manag. 2008, 28, 101–108. [Google Scholar] [CrossRef] [Scilit]
- Martiniello, L.; Moro Visconti, R.; Morea, D.; Gebennini, E. Can public private partnership foster sustainability in smart hospitals? Sustainability 2019, 11, 1704. [Google Scholar] [CrossRef] [Scilit]
- Stafford, A.; Shaoul, J.; Stapleton, P. NHS capital investment and PFI: From central government responsibility to local affordability. Financ. Account. Manag. 2011, 27, 1–17. [Google Scholar]
- De Clerck, D.; Demeulemeester, E.; Herroelen, W. Public private partnerships: Look before you leap into marriage. Rev. Bus. Econ. Lit. 2012, 57, 249–262. [Google Scholar]
- Coulson, A. Value for money in PFI proposals: A commentary on the UK treasury guidelines for public sector comparators. Public Adm. 2008, 86, 483–498. [Google Scholar] [CrossRef] [Scilit]
- Iossa, E.; Antellini Russo, F. Potenzialità e criticità del Partenariato Pubblico Privato in Italia. Riv. di Polit. Econ. 2008, 98, 125–158. [Google Scholar]
- Lapsely, I.; Mussari, R.; Paulsson, G. On the adopting of accrual accounting in the public sector: A self-evident and problematic reform. Eur. Account. Rev. 2009, 18, 719–723. [Google Scholar] [CrossRef] [Scilit]
- Goldman, C.A.; Hopper, N.C.; Osborn, J.G. Review of U.S. Esco industry market trends. An empirical analysis of project data. Energy Policies 2005, 33, 387–405. [Google Scholar] [CrossRef] [Scilit]
- Sarkar, A.; Singh, J. Financing energy efficiency in developing countries e lessons learned and remaining challenges. Energy Policy 2010, 38, 5560–5571. [Google Scholar] [CrossRef] [Scilit]
- Blanco, C.; Choi, S.; Soronow, D. Energy Price Processes used for Derivatives Pricing & Risk Management. Commodities Now 2001, 1, 74–80. [Google Scholar]
- Singer, T. IEA DSM Task x-Performance Contracting Country Report: United States; International Energy Agency: Paris, France, 2002. [Google Scholar]
- Kahveci, R.; Meads, C. Analysis of strengths, weaknesses, opportunities, and threats in the development of a health technology assessment program in Turkey. Int. J. Techn. Assess. in Health Care 2008, 24, 235–240. [Google Scholar] [CrossRef] [Scilit]
- Ippolito, A.; Viggiani, V. Positioning matrix of economic efficiency and complexity: A case study in a university hospital. Int. J. Healthc. Plan. Manag. 2014, 29, 362–372. [Google Scholar] [CrossRef] [Scilit]
- Chuyuan, W.; Yongzhen, L. Design of energy consumption monitoring and energy-saving management system of intelligent building based on the Internet of Things. In Proceedings of the International Conference on Electronics, Communications and Control (ICECC), Ningbo, China, 9–11 September 2011. [Google Scholar]
- Vine, E.; Hamrin, J.; Crossley, D.; Maloney, M.; Watt, G. Public policy analysis of energy efficiency and load management in changing electricity businesses. Energy Policy 2003, 31, 405–430. [Google Scholar] [CrossRef] [Scilit]
- Xu, P.P.; Chan, E.H.W. ANP model for sustainable Building Energy Efficiency Retrofit (BEER) using Energy Performance Contracting (EPC) for hotel buildings in China. Habitat 2013, 37, 104–112. [Google Scholar] [CrossRef] [Scilit]
- Yuan, X.; Ma, R.; Zuo, J.; Mu, R. Towards a sustainable society: The status and future of energy performance contracting in China. J. Clean. Prod. 2016, 112, 1608–1618. [Google Scholar] [CrossRef] [Scilit]
- Carbonara, N.; Pellegrino, R. Public Private Partnership for energy efficiency projects: A win - win model to choose the energy performance contracting structure. J. Clean. Prod. 2018, 170, 1064–1075. [Google Scholar] [CrossRef] [Scilit]
- Zhenfeng, W.; Guangyin, X.; Ruojue, L.; Heng, W.; Jingzheng, R. Energy performance contracting, risk factors, and policy implications: Identification and analysis of risks based on the best-worst network method. Energy 2019, 170, 1–13. [Google Scholar]
- Sorrell, S. The economics of energy service contracts. Energy Policy 2007, 35, 507–521. [Google Scholar] [CrossRef] [Scilit]
- Taylor, R.P.; Govindarajalu, C.; Levin, J.; Meyer, A.S.; Ward, W.A. Financing Energy Efficiency: Lessons from Brazil, China, India and Beyond; The World Bank: Washington, DC, USA, 2007. [Google Scholar]
- Sussex, J. The Economics of the Private Finance Initiative in the NHS; Office of Health Economics: London, UK, 2001. [Google Scholar]
- Fiaschi, D.; Bandinelli, R.; Conti, S. A case study for energy issue of public building and utilities in small municipalities: Investigation of possible improvements and integration with renewables. Appl. Energy 2012, 97, 101–114. [Google Scholar] [CrossRef] [Scilit]
- Roshchanka, V.; Evans, M. Scaling up the energy service company business: Market status and company feedback in Russian federation. J. Clean. Prod. 2016, 112, 3905–3914. [Google Scholar] [CrossRef] [Scilit]
- Chan, A.P.C.; Yeung, J.F.Y.; Yu, C.C.P.; Shou, Q.W.; Ke, Y. Empirical study of risk assessment and allocation of public-private partnership projects in China. J. Manag. Eng. 2011, 27, 136–148. [Google Scholar] [CrossRef] [Scilit]
- Grimsey, D.; Lewis, M.K. Evaluating the risks of public private partnerships for infrastructure projects. Int. J. Proj. Manag. 2002, 20, 107–118. [Google Scholar] [CrossRef] [Scilit]
- Acerete, B.; Stafford, A.; Stapleton, P. New development: New global health care PPP developments—A critique of the success story. Public Money Manag. 2012, 32, 311–314. [Google Scholar] [CrossRef] [Scilit]
- Chirkunova, E.K.; Kornilova, D.A.; Pschenichnikova, J.S. Research of instruments for financing of innovation and investment construction projects. Procedia Eng. 2016, 153, 112–117. [Google Scholar] [CrossRef] [Scilit]
- Barlow, K.G. Delivering innovation in hospital construction: Contracts and collaboration in the UK’s private finance initiative hospitals program. Calif. Manag. Rev. 2008, 51, 126–143. [Google Scholar] [CrossRef] [Scilit]
- Eurostat. Manual on Government Deficit and Debt. Available online: https://ec.europa.eu/eurostat/documents/3859598/7203647/KS-GQ-16-001-EN-N.pdf/5cfae6dd-29d8-4487-80ac-37f76cd1f012 (accessed on 2 June 2020).
- Eurostat Guidance Note. The Recording of Energy Performance Contract in Government Accounts; European Commission: Brussels, Belgium, 19 September 2017. [Google Scholar]
- The Chamber of Tax Consultant. Epc Contracts-Compendium On Taxation and Regulatory Issues; Wolters Kluer: Maharashtra, India, 2017. [Google Scholar]
- Costantino, N.; Mummolo, G.; Pascarelli, C.; Pellegrino, R.; Ranieri, L. A real options-based approach in guaranteed energy savings contracting. Int. J. Ing. Manag. Econ. 2012, 3, 305–325. [Google Scholar] [CrossRef] [Scilit]
- De Marco, A.; Mangano, G.; Cagliano, A.C.; Grimaldi, S. Public financing into build operate-transfer hospital projects in Italy. J. Constr. Eng. Manag. 2012, 138, 1294–1302. [Google Scholar] [CrossRef] [Scilit]
- Demartini, C.; Mella, P. Beyond feedback control: The interactive use of performance management systems. Implications for process innovation in Italian healthcare organizations. Int. J. Health 2013, 29, 1–30. [Google Scholar] [CrossRef] [Scilit] [PubMed]
© 2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).