Real-Time Drilling Control for Hanging-Wall Stability: SCADA-Based Mitigation of Overbreak and Dilution in Long-Hole Stoping
Abstract
1. Introduction
2. Relevant Background Literature
2.1. Forms and Impacts of Dilution in Underground Mining
2.2. Dilution Causes: Geotechnical and Operational Factors
2.3. Monitoring and Control of Dilution
3. Methodology
- Primary data collection (manual monitoring assessment)—The drilling accuracy and dilution results under the current manual monitoring regime were first observed and quantified. This involved direct observation of drilling in the study stopes, measurements of drill hole deviations using manual tools, and communication with mine personnel to identify typical issues and delay points in the process.
- Design of the SCADA monitoring system—Based on the identified needs (parameters to monitor, required accuracy, environmental conditions underground), appropriate sensors and hardware were selected. The sensors were then integrated with a PLC, and the SCADA software interface (HMI) was developed with alarm logic for real-time deviation detection. The system was initially tested on surface (in a controlled setting or mock-up) to ensure it functioned as intended.
- Installation and commissioning—The SCADA system components were installed in the chosen stopes (on the drilling rig used for those stopes). Communication networks were established (wired or wireless) to transmit data from the underground PLC to a central SCADA computer on surface or at a central control room on site. A 30-day trial license of AVEVA™ InTouch (a SCADA software platform) was used for the development of the monitoring dashboards and data logging.
- System testing (field trial)—The SCADA monitoring was run in parallel with normal drilling operations in the study stopes over multiple rings of drilling. During this phase, any interventions triggered by the system (e.g., automatic drill stoppages or operator alerts) were documented, and the drilling parameters were also continuously recorded. The field trial was conducted in collaboration with geologists, mining engineers and other expects in order to ensure thorough understanding and monitoring of the geological conditions of the stopes.
- Performance measurement—The outcomes in terms of drilling deviations (actual vs. planned angles, lengths, and positions) were measured with the SCADA system active, and we compared these to the baseline deviations recorded previously under manual monitoring. Any hanging wall collapse incidents and dilution percentages in the stopes during the trial were also tracked, comparing them to historical data.
- Secondary data collection—Historical records from the mine’s production and survey databases for the past year were gathered to contextualise the baseline dilution and to verify if the trial period outcomes represented a significant improvement beyond normal variance. Any economic data (cost of dilution, previous support costs, etc.) was also reviewed to feed into the economic analysis.
- Economic analysis—A cost–benefit analysis comparing the estimated annual loss due to dilution (if no improvements are made) against the cost of implementing and running the SCADA system was finally performed. This was to evaluate the financial viability of the solution.
3.1. Design of the SCADA-Based Monitoring System
- Sensors—industrial-grade sensors to measure each parameter (Table 2) were selected. For drill hole angle, an inertial measurement unit (IMU) sensor (with an integrated accelerometer/gyroscope) was mounted on the drill feed assembly. This provided continuous inclination data with ±0.1° accuracy. For penetration depth, a rotary encoder was attached to the drill feed mechanism—as the drill carriage advances, the encoder tracks rotation corresponding to linear advancement, measuring depth to within a few centimetres. To monitor the drill position (ensuring correct collar location and spacing), the study deployed a LiDAR distance sensor or laser rangefinder that measured the horizontal distance between the drill feed and a fixed reference point or adjacent hole marks. The LiDAR was particularly useful for confirming that the drill had been set up at roughly the correct spacing from the previous hole (target of about 1 m). Simple limit switches were also placed to detect contact (e.g., whether the drill guide was firmly pressed against the collar point).
- Angle threshold—±0.8° from planned angle. If the IMU reading deviated more than 0.8° from the target angle (e.g., if target is 65°, reading goes below 64.2° or above 65.8°), it triggered an alert. If deviation exceeded ±1.0°, it would initiate an automatic pause in drilling. The rationale was that 1° deviation can be significant over long holes, as discussed.
- Depth threshold—0.1 m short of planned depth. The PLC continuously compared the encoder count to the target depth (e.g., 20.0 m). If the drill hit target depth, it would automatically stop the feed motor (to avoid over-drilling). If the drill was withdrawn prematurely (e.g., hitting void or broken through), or if the depth was short by more than 0.1 m while supposed to be at full length, it flagged an incomplete hole.
- Positional (spacing) threshold—±0.1 m from planned spacing (1.0 m). The LiDAR sensor was used at setup—before drilling each hole, the crew would position the rig and then press a ‘confirm position’ button on the HMI. The PLC would record the LiDAR distance to a reflector placed at the previous hole collar. If this measured spacing was outside 0.9–1.1 m, a warning would display indicating misposition. This was a soft alert; the study did not automate any machine action for position, as repositioning requires manual adjustment.
3.2. Geological Consistency Across Trial Stopes
4. Results
4.1. Baseline Manual Monitoring Results
4.2. SCADA System Performance and Drilling Accuracy Results
4.3. Reduction in Ore Dilution and Improved Production Metrics
4.4. Additional Observations
5. Discussion
5.1. Interpretation of Results and Mechanisms of Improvement
5.1.1. Economic Implications
5.1.2. Broader Implications for Industry and Future Work
- Initial setup and calibration—The study was successful in a relatively controlled case. Other mines can have more challenging conditions (e.g., extreme temperatures, presence of water, more electromagnetic interference) that could affect sensors. Robustness of equipment must be ensured for each context. In our case study, minimal protective adjustments (like housing LiDAR against dust) were made. In more difficult environments, additional engineering may be needed (e.g., explosion-proof casings in coal mines, etc.).
- Reliance on technology—Over-reliance on sensors could be an issue if not managed. If the system fails, operators need to know how to revert to manual without losing performance. The mine plans to implement standard operating procedures for fallback (in the trial, no major failures occurred, but one should always be prepared). Also, sensor malfunctions could potentially give false security (e.g., if a sensor drifts out of calibration without notice). Regular maintenance and calibration are thus crucial, which is budgeted for.
- Training and change management—The human factor cannot be ignored. It was fortunate that after demonstration, operator buy-in was achieved in this study. In some cases, the workforce may resist new tech or misuse it. Ongoing training (as included in our study) and engaging operators in the improvement process help. In this study, operators eventually felt empowered by the tool rather than threatened, which is the ideal outcome.
- Data utilisation—The wealth of data from SCADA opens possibilities for continuous improvement. Analysis of drilling performance, for example, can lead to better blast designs or identify if certain patterns correlate with slight remaining dilution—enabling a feedback loop into mine planning. This data can be used to refine drilling patterns (customising burden where minor differences in geology require it).
- Integration with other systems—The system could integrate with a mine’s broader IoT or digital platform. Giving as an example, linking drilling data with geological models—if a sensor notices a void or change in drilling resistance (via vibration or penetration rate), it could tag geologists that maybe they hit a weaker zone, etc. Also, integration with explosive charging units (future idea: ensure the charging is adjusted if a hole deviates—but since now deviations are tiny, that is less of an issue).
- Scalability—The study was only implemented on a few stopes; scaling to all stopes means more equipment and centralised monitoring of multiple sections. The mine can consider a central control room where one technician can watch all stope monitors. This centralisation is part of what modern SCADA enables—fewer eyes underground, more oversight at a control centre, improving safety. Networks must, however, be robust (latency must remain low as scale grows).
- Other mining methods—While the study was applied to sublevel stoping, the concept can be adapted to other methods—e.g., in longwall coal mining, shearer positions. The case study adds to the evidence that underground mines can indeed adopt high-precision monitoring despite more challenging conditions.
5.1.3. Further Research
5.1.4. Safety and Other Benefits
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Tatman, C.R. Mining dilution in moderate- to narrow-width deposits. In Underground Mining Methods: Engineering Fundamentals and International Case Studies; Society of Mining, Metallurgy and Exploration: Littleton, CO, USA, 2001; pp. 615–626. [Google Scholar]
- Sotoudeh, F.; Nehring, M.; Kizil, M.; Knights, P. Integrated underground mining and pre-concentration systems; a critical review of technical concepts and developments. Int. J. Min. Reclam. Environ. 2021, 35, 153–182. [Google Scholar]
- Sotoudeh, F.; Nehring, M.; Kizil, M.; Knights, P.; Mousavi, A. A new mathematical programming formulation for production scheduling optimisation of sublevel stoping operations in the presence of pre-concentration systems. Min. Metall. Explor. 2023, 40, 2255–2267. [Google Scholar] [CrossRef]
- Dunwen, L. Sublevel Stoping Mining Method. In The ECPH Encyclopedia of Mining and Metallurgy; Springer Nature: Singapore, 2024; pp. 2079–2081. [Google Scholar]
- Upadhyay, R.K. Mining, Mineral Beneficiation, and Environment. In Geology and Mineral Resources; Springer Nature: Singapore, 2025; pp. 799–858. [Google Scholar]
- Ranganai, R.T. Euler deconvolution and spectral analysis of regional aeromagnetic data from the south-central Zimbabwe Craton: Tectonic implications. Afr. J. Sci. Technol. 2012, 12, 34–50. [Google Scholar]
- Atlas Copco. Mining Methods in Underground Mining; Atlas Copco: Nacka, Sweden, 2007. [Google Scholar]
- Scoble, M.J.; Moss, A. Dilution in underground bulk mining: Implications for production management. Geol. Soc. Lond. Spec. Publ. 1994, 79, 95–108. [Google Scholar]
- Suglo, R.S.; Opoku, S. An assessment of dilution in sublevel caving at Kazansi Mine. Int. J. Min. Miner. Eng. 2012, 4, 1–16. [Google Scholar] [CrossRef]
- Delentas, A.; Benardos, A.; Nomikos, P. Analyzing stability conditions and ore dilution in open stope mining. Minerals 2021, 11, 1404. [Google Scholar] [CrossRef]
- Appianing, E.J.A.; Ben-Awuah, E.; Pourrahimian, Y. Life-of-mine optimization for integrated open stope development and production scheduling using a mixed-integer linear programming framework. Min. Technol. 2023, 132, 106–120. [Google Scholar]
- Chimunhu, P.; Faradonbeh, R.S.; Topal, E.; Asad, M.W.A.; Ajak, A.D. Development of novel hybrid intelligent predictive models for dilution prediction in underground sub-level mining. Min. Metall. Explor. 2024, 41, 2079–2098. [Google Scholar] [CrossRef]
- Anderson, B.; Grebenc, B. Controlling dilution at the Golden Giant mine. In Proceedings of the 12th CIM Mine Operators Conference, Timmins, ON, Canada, 12–16 February 1995. [Google Scholar]
- Henning, J.G. Evaluation of Long-Hole Mine Design Influences on Unplanned Ore Dilution. Doctoral Thesis, McGill University, Montreal, QC, Canada, 2007. [Google Scholar]
- Hughes, R.; Mitri, H.S.; Lecomte, E. Examining the influence of stope strike length on unplanned ore dilution in narrow vein longitudinal mining. In Proceedings of the ARMA US Rock Mechanics/Geomechanics Symposium, Salt Lake City, UT, USA, 27–30 June 2010; ARMA: Eaton, CO, USA, 2010; p. ARMA-10-392. [Google Scholar]
- Chen, T.; Mitri, H.S. October. Unplanned ore dilution control in longhole mining using sill pillars–A case study. In Proceedings of the ISRM Congress, Salzburg, Austria, 9–14 October 2023; ISRM: Lisbon, Portugal, 2023; pp. 409–414. [Google Scholar]
- Elbrond, J. Economic effects of ore losses and rock dilution. CIM Bull. 1994, 87, 131–134. [Google Scholar]
- Diederichs, M.S.; Kaiser, P.K. Rock instability and risk analyses in open stope mine design. Can. Geotech. J. 1996, 33, 431–439. [Google Scholar] [CrossRef]
- Amedjoe, C.G.; Agyeman, J. Assessment of effective factors in performance of an open stope using cavity monitoring system data: A case study. J. Geol. Min. Res. 2015, 7, 19–30. [Google Scholar] [CrossRef]
- Le Roux, P.J.; Stacey, T.R. Value creation in a mine operating with open stoping mining methods. J. S. Afr. Inst. Min. Metall. 2017, 117, 133–142. [Google Scholar]
- Jang, H.; Topal, E. Underground stope dilution optimization applying machine learning. In Applications of Artificial Intelligence in Mining and Geotechnical Engineering; Elsevier: Amsterdam, The Netherlands, 2024; pp. 315–323. [Google Scholar]
- Mussin, A.; Imashev, A.; Matayev, A.; Abeuov, Y.; Shaike, N.; Kuttybayev, A. Reduction of ore dilution when mining low-thickness ore bodies by means of artificial maintenance of the mined-out area. Min. Miner. Depos. 2023, 17, 35–42. [Google Scholar]
- Serdaliyev, Y.; Iskakov, Y.; Amanzholov, D. Selection of the optimal composition and analysis of the detonating characteristics of low-density mixed explosives applied to break thin ore bodies. Min. Miner. Depos. 2023, 17, 53–60. [Google Scholar] [CrossRef]
- Imashev, A.; Mussin, A.; Adoko, A.C. Investigating an Enhanced Contour Blasting Technique Considering Rock Mass Structural Properties. Appl. Sci. 2024, 14, 11461. [Google Scholar] [CrossRef]
- Casale, M.; Dino, G.A.; Oggeri, C. Blasting of Unstable Rock Elements on Steep Slopes. Appl. Sci. 2025, 15, 712. [Google Scholar] [CrossRef]
- Vera-Encarnación, J.K.; Cotrina-Teatino, M.A.; Arango-Retamozo, S.M. An Intelligent Approach to Predicting Dilution, Over-break and Costs in Underground Mining Using Kolmogorov-Arnold Networks. Math. Model. Eng. Probl. 2025, 12, 815–828. [Google Scholar]
- Brady, B.H.; Brown, E.T. Rock Mechanics: For Underground Mining; Springer Science & Business Media: Berlin/Heidelberg, Germany, 2006. [Google Scholar]
- Diakité, O. Ore Dilution in Sublevel Stoping. Master’s Thesis, McGill University, Montreal, QC, Canada, 1998. [Google Scholar]
- Hamrin, H.; Hustrulid, W.; Bullock, R. Underground mining methods and applications. In Underground Mining Methods: Engineering Fundamentals and International Case Studies; Society for Mining, Metallurgy, and Exploration, Inc.: Englewood, CO, USA, 2001; pp. 3–14. [Google Scholar]
- Bamber, A.S. An Integrated Underground Mining and Processing System for Massive Sulphide Ores. Master’s Thesis, University of British Columbia, Vancouver, BC, Canada, 2004. [Google Scholar]
- Bagde, M.N. Ore and backfill dilution in underground hard rock mining. J. Min. Sci. 2021, 57, 995–1005. [Google Scholar] [CrossRef]
- De la Vergne, J. Hard Rock Miner’s Handbook, 1st ed.; McIntosh Redpath Engineering: North Bay, ON, Canada, 2000; 430p, ISBN 0-9687006-0-8. [Google Scholar]
- Whillans, P.T. Mining Dilution and Mineral Losses, An Underground Operator’s Perspective. In Proceedings of the Mining Tech, Santiago, Chile, 29 July 2018. [Google Scholar]
- Konyukh, V. Strategy of automation for underground mining. In Proceedings of the 2007 International Forum on Strategic Technology, Ulaanbaatar, Mongolia, 3–6 October 2007; IEEE: New York, NY, USA, 2007; pp. 615–618. [Google Scholar]
- Wodecki, J.; Stefaniak, P.; Polak, M.; Zimroz, R. Unsupervised anomaly detection for conveyor temperature SCADA data. In Proceedings of the International Conference on Condition Monitoring of Machinery in Non-Stationary Operation, Gliwice, Poland, 12–16 September 2016; Springer International Publishing: Cham, Switzerland, 2016; pp. 361–369. [Google Scholar]
- Wojaczek, A.; Wojaczek, A. Monitoring the environment and machines in underground mine. Zesz. Nauk. Inst. Gospod. Surowcami Miner. Pol. Akad. Nauk. 2017, 99, 57–70. [Google Scholar]
- İlten, E.; Ünsal, M.E. PLC based SCADA system design for instant monitoring and early warning mechanism of toxic gases in underground mines. Mühendislik Bilim. Tasarım Derg. 2024, 12, 64–74. [Google Scholar] [CrossRef]
- Li, J.G.; Zhan, K. Intelligent mining technology for an underground metal mine based on unmanned equipment. Engineering 2018, 4, 381–391. [Google Scholar] [CrossRef]
- Zeng, Q.; Zhu, S.; Li, Z.; Wu, A.; Wang, M.; Su, Y.; Wang, S.; Qu, X.; Feng, M. Research on real-time monitoring and warning technology for multi-parameter underground debris flow. Sustainability 2023, 15, 15006. [Google Scholar] [CrossRef]
- Jiang, Y.; Chen, W.; Zhang, X.; Zhang, X.; Yang, G. Real-time monitoring of underground miners’ status based on mine IoT system. Sensors 2024, 24, 739. [Google Scholar] [CrossRef]
- Anvari, K.; Benndorf, J. Real Time Mining—A Review of Developments Within the Last Decade. Mining 2025, 5, 38. [Google Scholar] [CrossRef]
- Pramanik, J.; Jayanthu, S.; Samal, D.A.K. Applications of IoT framework for underground mine safety: Limitations and solutions. J. Min. Environ. 2024, 15, 923–942. [Google Scholar]
- Onifade, M.; Zvarivadza, T.; Adebisi, J.A. Towards application of positioning systems in the mining industry. Int. J. Min. Miner. Eng. 2024, 15, 15–48. [Google Scholar] [CrossRef]
- Bamber, A.S. Integrated Mining, Pre-Concentration and Waste Disposal Systems for the Increased Sustainability of Hard Rock Metal Mining. Doctoral Thesis, University of British Columbia, Vancouver, BC, Canada, 2008. [Google Scholar]
- Xingwana, L. Monitoring ore loss and dilution for mine-to-mill integration in deep gold mines: A survey-based investigation. J. S. Afr. Inst. Min. Metall. 2016, 116, 149–160. [Google Scholar] [CrossRef]
- Hartman, H.L.; Mutmansky, J.M. Introductory Mining Engineering; John Wiley & Sons: Hoboken, NJ, USA, 2002. [Google Scholar]
- Napier-Munn, T.; Wills, B.A. Wills’ Mineral Processing Technology; Butterworth-Heinemann Elsevier Ltd.: Oxford, UK, 2005; pp. 246–266. [Google Scholar]
- Hoek, E.; Brown, E.T. The Hoek–Brown failure criterion and GSI–2018 edition. J. Rock Mech. Geotech. Eng. 2019, 11, 445–463. [Google Scholar] [CrossRef]
- Wang, J. Influence of Stress, Undercutting, Blasting and Time on Open Stope Stability and Dilution. Doctoral Thesis, University of Saskatchewan, Saskatoon, SK, Canada, 2004. [Google Scholar]
- Shekhawat, A. Digitization and Environmental Stewardship in Blasting Operations; Continuous Improvement and Asset Optimization; Centre of Excellence in Mining: Quetta, Pakistan, 2025; p. 91. [Google Scholar]
- Clark, L.M. Minimizing Dilution in Open Stope Mining with a Focus on Stope Design and Narrow Vein Longhole Blasting. Doctoral Thesis, University of British Columbia, Vancouver, BC, Canada, 1998. [Google Scholar]
- Zhang, Z.X. Rock mechanics related to mining engineering. In Proceedings of the ISRM Nordic Rock Mechanics Symposium-NRMS, Helsinki, Finland, 11–12 October 2017; ISRM: Lisbon, Portugal, 2017; pp. 39–64. [Google Scholar]
- Louwerse, D. Waste Rock Dilution in Stoping of Steeply Dipping Narrow-Vein Deposits. Master’s Thesis, Aalto University, Espoo, Finland, 2018. [Google Scholar]
- Bazaluk, O.; Petlovanyi, M.; Zubko, S.; Lozynskyi, V.; Sai, K. Instability assessment of hanging wall rocks during underground mining of iron ores. Minerals 2021, 11, 858. [Google Scholar] [CrossRef]
- Ngoma, K.; Mutambo, V. Factors Influencing Ore Recovery and Unplanned Dilution in Sublevel Open Stopes. Case Study of Shaft No.4 at Konkola Mine, Zambia. Curr. World Environ. 2020, 15, 31–46. [Google Scholar]
- Pickering, R.G.B. The optimization of mining method and equipment. In Proceedings of the Third Southern African Conference on Base Metals, Platinum Adding Value Conference, Sun City, South Africa, 3–7 October 2004; pp. 4–6. [Google Scholar]
- Wenquan, D. Underground Mining Design, Principles of. In The ECPH Encyclopedia of Mining and Metallurgy; Springer Nature: Singapore, 2024; pp. 2237–2238. [Google Scholar]
- Lv, Z.; Hu, N.; Li, G. Analysis of factors affecting the human behavior safety in metal underground mines. In Proceedings of the 2011 International Conference on Management and Service Science, Wuhan, China, 12–14 August 2011; IEEE: New York, NY, USA, 2011; pp. 1–3. [Google Scholar]
- Rogers, W.P.; Kahraman, M.M.; Drews, F.A.; Powell, K.; Haight, J.M.; Wang, Y.; Baxla, K.; Sobalkar, M. Automation in the mining industry: Review of technology, systems, human factors, and political risk. Min. Metall. Explor. 2019, 36, 607–631. [Google Scholar] [CrossRef]
- Skrzypkowski, K.; Gómez, R.; Zagórski, K.; Zagórska, A.; Gómez-Espina, R. Review of underground mining methods in world-class base metal deposits: Experiences from Poland and Chile. Energies 2022, 16, 148. [Google Scholar] [CrossRef]
- Mah, S.G.L. Quantification and Prediction of Wall Slough in Open Stope Mining. Master’s Thesis, University of British Columbia, Vancouver, BC, Canada, 1997. [Google Scholar]
- Liu, X.L.; Li, X.B.; Li, F.B.; Zhao, G.Y.; Qin, Y.H. 3D cavity detection technique and its application based on cavity auto scanning laser system. J. Cent. South Univ. Technol. 2008, 15, 285–288. [Google Scholar]
- Henning, J.G.; Mitri, H.S. Assessment and control of ore dilution in long hole mining: Case studies. Geotech. Geol. Eng. 2008, 26, 349–366. [Google Scholar] [CrossRef]
- Jarosz, A.P.; Shepherd, L. Open stope cavity monitoring for the control of dilution and ore loss. In Mine Planning and Equipment Selection 2000; Routledge: London, UK, 2018; pp. 63–66. [Google Scholar]
- Mitchell, J.; Marshall, J.A. Towards a novel auto-rotating lidar platform for cavity surveying. Tunn. Undergr. Space Technol. 2020, 97, 103260. [Google Scholar] [CrossRef]
- Wu, J. Research on sublevel open stoping recovery processes of inclined medium-thick orebody on the basis of physical simulation experiments. PLoS ONE 2020, 15, e0232640. [Google Scholar] [CrossRef]
- Nowak, S.; Sherizadeh, T.; Esmaeelpour, M.; Brooks, P.; Guner, D.; Karadeniz, K. Numerical back analysis of an underground bulk mining operation using distributed optical fiber sensors for model calibration. Bull. Eng. Geol. Environ. 2024, 83, 71. [Google Scholar] [CrossRef]
- Rinne, M.; Janiszewski, M.; Pontow, S.; Uotinen, L.; Kiuru, R.; Kangas, L.; Laine, I.; Leveinen, J. Improvements in Rock Mass Description for Stope Design by Geophysical and Geochemical Methods. Appl. Sci. 2024, 14, 957. [Google Scholar] [CrossRef]
- Jang, H.; Topal, E.; Kawamura, Y. Unplanned dilution and ore loss prediction in longhole stoping mines via multiple regression and artificial neural network analyses. J. S. Afr. Inst. Min. Metall. 2015, 115, 449–456. [Google Scholar] [CrossRef]
- Hudyma, M.R.; Frenette, P.; Leslie, I. Monitoring open stope caving at Goldex Mine. Min. Technol. 2010, 119, 142–150. [Google Scholar] [CrossRef]
- Bamford, T.; Medinac, F.; Esmaeili, K. Continuous monitoring and improvement of the blasting process in open pit mines using unmanned aerial vehicle techniques. Remote Sens. 2020, 12, 2801. [Google Scholar] [CrossRef]
- Debashish, C.; Srikant, A. November. Development of systems for monitoring stability of large excavations. In Recent Advances in Rock Engineering (RARE 2016); Atlantis Press: Dordrecht, The Netherlands, 2016; pp. 429–439. [Google Scholar]
- Rysbekov, K.; Bitimbayev, M.; Akhmetkanov, D.; Yelemessov, K.; Barmenshinova, M.; Toktarov, A.; Baskanbayeva, D. Substantiation of mining systems for steeply dipping low-thickness ore bodies with controlled continuous stope extraction. Min. Miner. Depos. 2022, 16, 64–72. [Google Scholar] [CrossRef]
- Guohua, X.; Jianhua, H. Open Stope Mining Method. In The ECPH Encyclopedia of Mining and Metallurgy; Springer Nature: Singapore, 2024; p. 1483. [Google Scholar]
- Chilunjika, A. Application of fourth industrial technologies: A case of Zimbabwe’s mines. Insights Into Reg. Dev. 2024, 6, 124–140. [Google Scholar] [CrossRef]
- Mazimba, C. Development of Underground Mine Monitoring and Communication System Based on Wireless Sensor Networks. Master’s Thesis, The University of Zambia, Lusaka, Zambia, 2023. [Google Scholar]
- Nowak, S.V. Novel Uses of Distributed Optical Fiber Sensing for Geomechanical Monitoring. Doctoral Thesis, Missouri University of Science and Technology, Rolla, MO, USA, 2023. [Google Scholar]
- Cacciuttolo, C.; Atencio, E.; Komarizadehasl, S.; Lozano-Galant, J.A. Internet of Things long-range-wide-area-network-based wireless sensors network for underground mine monitoring: Planning an efficient, safe, and sustainable labor environment. Sensors 2024, 24, 6971. [Google Scholar] [CrossRef] [PubMed]
- Zvarivadza, T.; Onifade, M.; Dayo-Olupona, O.; Said, K.O.; Githiria, J.M.; Genc, B.; Celik, T. On the impact of Industrial Internet of Things (IIoT)-mining sector perspectives. Int. J. Min. Reclam. Environ. 2024, 38, 771–809. [Google Scholar] [CrossRef]
- Long, M.; Schafrik, S.; Kolapo, P.; Agioutantis, Z.; Sottile, J. Equipment and operations automation in mining: A review. Machines 2024, 12, 713. [Google Scholar] [CrossRef]
- Kolapo, P.; Ogunsola, N.O.; Komolafe, K.; Omole, D.D. Envisioning human–machine relationship towards mining of the future: An overview. Mining 2025, 5, 5. [Google Scholar] [CrossRef]
- Osei, R.; Frimpong, S.; Venkat, A. Human-machine collaboration in mining: A critical review of emerging frontiers of intelligence systems in the mining industry. Extr. Ind. Soc. 2025, 24, 101746. [Google Scholar] [CrossRef]
- Azeem, E.F. Automation in Mining: Improving Efficiency and Safety in Deep Mines. Am. J. Min. Eng. 2020, 1, 8–15. [Google Scholar]
- Bisschoff, R.A.D.P.; Grobbelaar, S. Evaluation of data-driven decision-making implementation in the mining industry. S. Afr. J. Ind. Eng. 2022, 33, 218–232. [Google Scholar] [CrossRef]
- Chowdu, A.; Nesbitt, P.; Brickey, A.; Newman, A.M. Operations research in underground mine planning: A review. Inf. J. Appl. Anal. 2022, 52, 109–132. [Google Scholar]
- Obosu, M.; Frimpong, S. Advances in automation and robotics: The state of the emerging future mining industry. J. Saf. Sustain. 2025, 2, 181–194. [Google Scholar] [CrossRef]
- Waghmare, G.H.; Thelkar, A.R.; Babu, S.B.T.; Katre, R.; Kumar, A.; Mahender, K. Robotics in Underground Mining for Improved Worker Safety and Efficiency. Int. J. Environ. Sci. 2025, 11, 279–286. [Google Scholar]
- Nandan Technicals. SCADA Types, Functions, SCADA System Architecture, Benefits and Applications. 2022. Available online: https://www.nandantechnicals.com/2022/07/scada-types-functions-scada-system.html (accessed on 10 June 2025).
- Nguyen, H.N.; Koo, J. Enhancing SCADA Security Using Generative Adversarial Network. J. Cybersecur. Priv. 2025, 5, 73. [Google Scholar] [CrossRef]














| Hole (Ring 15L) | Planned Angle (°) | Actual Angle (°) | Angle Deviation (°) | Planned Length (m) | Actual Length (m) | Length Deviation (m) | Positional Deviation (m) |
|---|---|---|---|---|---|---|---|
| Ring 1 Hole 1 | 66 | 68 | 2 | 20.0 | 19.5 | 0.5 | 0.4 |
| Ring 1 Hole 2 | 67 | 65 | 2 | 18.5 | 18.0 | 0.5 | 0.3 |
| Ring 1 Hole 3 | 65 | 66 | 1 | 24.0 | 22.0 | 2.0 | 0.5 |
| Ring 1 Hole 4 | 67 | 68 | 1 | 20.0 | 18.5 | 1.5 | 0.3 |
| Ring 1 Hole 5 | 76 | 76.6 | 0.6 | 22.0 | 21.3 | 0.7 | 0.4 |
| Ring 1 Hole 6 | 75 | 75.8 | 0.8 | 25.0 | 24.6 | 0.4 | 0.3 |
| Input Parameter | Sensor Type | Purpose |
|---|---|---|
| Drill hole angle | IMU (Inertial Measurement Unit) inclinometer | Measures the feed beam inclination to ensure the drilling angle is as per design (e.g., 65°). Provides live angle feedback during drilling. |
| Drilling depth | Feed Encoder (rotary encoder) | Tracks the linear advance of the drill. Used to monitor actual drilled depth in real time and stop at planned depth. |
| Hole collar position | LiDAR distance sensor | Measures horizontal distance from a fixed point (or between holes). Ensures each hole is started at the correct spacing; detects mispositioning of the rig. |
| Drill vibration (bit condition) | Vibration sensor (accelerometer) | Monitors drill bit performance—abnormal vibrations might indicate bit wear or hard inclusions. (Used for research/diagnostics; not directly for deviation, but can correlate to drilling issues.) |
| Metric | Average Value (Stope 12L, Manual) |
|---|---|
| Planned hole angle (°) | 66° (varied 62–70° by design) |
| Average actual drilled angle (°) | 67° |
| Average angle deviation | +0.8° (hole steeper than planned) |
| Planned hole length (m) | 20.2 m (varied 15–22 m by design) |
| Average actual drilled length (m) | 19.1 m |
| Average length deviation | 1.1 m short |
| Average positional deviation | 0.32 m (holes off-mark laterally) |
| Metric | Average Value (Stope 14L, Manual) |
|---|---|
| Planned hole angle (°) | 67° (varied 56–72° by design) |
| Average actual drilled angle (°) | 68.5° |
| Average angle deviation | +1.6° (steeper than planned) |
| Planned hole length (m) | 21.7 m (varied 15–35 m by design) |
| Average actual drilled length (m) | 20.9 m |
| Average length deviation | 0.8 m short |
| Average positional deviation | 0.25 m |
| Level (Stope) | Angular Deviation (°) | Length Deviation (m) | Positional Deviation (m) |
|---|---|---|---|
| 15L (post-SCADA) | 0.3° | 0.07 m | 0.05 m |
| 14L (post-SCADA) | 0.2° | 0.05 m | 0.04 m |
| 12L (post-SCADA) | 0.3° | 0.08 m | 0.06 m |
| (Additional stopes) 8L (post-SCADA) | 0.5° | 0.07 m | 0.05 m |
| 10L (post-SCADA) | 0.2° | 0.06 m | 0.08 m |
| 13L (post-SCADA) | 0.4° | 0.05 m | 0.06 m |
| Week | Ore Hoisted (t) | Waste Hoisted (t) | Total Tonnage (t) | Dilution (%) |
|---|---|---|---|---|
| Pre-SCADA Week 1 | 4100 | 1052 | 5152 | 20.4% |
| Pre-SCADA Week 2 | 3510 | 990 | 4500 | 22.0% |
| Pre-SCADA Week 3 | 3002 | 798 | 3800 | 21.0% |
| Pre-SCADA Week 4 | 4860 | 1140 | 6000 | 19.0% |
| Post-SCADA Week 1 | 5000 | 1000 | 6000 | 16.7% |
| Post-SCADA Week 2 | 4800 | 960 | 5760 | 16.7% |
| Post-SCADA Week 3 | 5050 | 950 | 6000 | 15.8% |
| Post-SCADA Week 4 | 5200 | 1040 | 6240 | 16.7% |
| Component | Quantity | Unit Cost ($) | Total Cost ($) | Rationale |
|---|---|---|---|---|
| Hardware | ||||
| IMU inclinometer sensors | 30 | $5000 | $150,000 | 5 sensors per stope (multiple rigs/spares) |
| LiDAR rangefinders | 24 | $3000 | $72,000 | 4 per stope (for multiple reference setups) |
| Rotary encoders | 36 | $700 | $25,200 | 6 per stope (one per drill rig per stope, plus spares) |
| PLC units | 6 | $15,000 | $90,000 | 1 PLC + modules per stope area |
| Network infrastructure (fiber, switches, wireless nodes) | 1 lot | $150,000 | $150,000 | Fibre optic cables and wireless access points for 6 stopes coverage |
| Servers and data storage | 2 | $15,000 | $30,000 | Central and backup server for SCADA data |
| Power backup systems (UPS/solar) | 6 | $10,000 | $60,000 | One per stope area for PLC and comms |
| Software and installation | ||||
| SCADA software license (AVEVA) | 1 | (site license) | $200,000 | Unlimited tags license + development kit (approx.) |
| Installation labour (contractors) | – | – | $15,000 | Configuration and installation man-hours |
| Staff training sessions | 30 (people) | – | $7500 | Training 30 staff (engineers, operators) on system use |
| Annual operating costs | (per year, estimated) | |||
| Sensor recalibration and maintenance | – | – | $14,400 | E.g. recalibrate sensors, replace one or two yearly |
| Energy (power to run system) | – | – | $30,000 | Added power usage for network and servers |
| Software licensing support (annual) | – | – | $24,000 | Support contract, updates for SCADA software |
| Data and IT support labour | – | – | $60,000 | 1–2 IT/engineers for system maintenance |
| TOTAL COST (initial + first year) | – | – | $928,100 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Gurumani, E.; Zvarivadza, T.; Ndhlovu, L.; Moyo, R.; Masethe, R.; Mpanza, M.; Onifade, M. Real-Time Drilling Control for Hanging-Wall Stability: SCADA-Based Mitigation of Overbreak and Dilution in Long-Hole Stoping. Mining 2025, 5, 68. https://doi.org/10.3390/mining5040068
Gurumani E, Zvarivadza T, Ndhlovu L, Moyo R, Masethe R, Mpanza M, Onifade M. Real-Time Drilling Control for Hanging-Wall Stability: SCADA-Based Mitigation of Overbreak and Dilution in Long-Hole Stoping. Mining. 2025; 5(4):68. https://doi.org/10.3390/mining5040068
Chicago/Turabian StyleGurumani, Eustina, Tawanda Zvarivadza, Lawrence Ndhlovu, Rejoice Moyo, Richard Masethe, Mbalenhle Mpanza, and Moshood Onifade. 2025. "Real-Time Drilling Control for Hanging-Wall Stability: SCADA-Based Mitigation of Overbreak and Dilution in Long-Hole Stoping" Mining 5, no. 4: 68. https://doi.org/10.3390/mining5040068
APA StyleGurumani, E., Zvarivadza, T., Ndhlovu, L., Moyo, R., Masethe, R., Mpanza, M., & Onifade, M. (2025). Real-Time Drilling Control for Hanging-Wall Stability: SCADA-Based Mitigation of Overbreak and Dilution in Long-Hole Stoping. Mining, 5(4), 68. https://doi.org/10.3390/mining5040068

