Next Article in Journal
Real Time Mining—A Review of Developments Within the Last Decade
Previous Article in Journal
Bibliometric and PESTEL Analysis of Deep-Sea Mining: Trends and Challenges for Sustainable Development
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Comparative Analysis of Throughput Prediction Models in SAG Mill Circuits: A Geometallurgical Approach

1
Faculty of Geology, Geophysic and Mines, National University of Saint Agustin, Santa Catalina 117, Arequipa 04000, Peru
2
Consultancy, Mine to Port Consulting, Ahumada 254, of 806, Santiago 8320213, Chile
*
Authors to whom correspondence should be addressed.
Mining 2025, 5(3), 37; https://doi.org/10.3390/mining5030037
Submission received: 20 April 2025 / Revised: 4 June 2025 / Accepted: 11 June 2025 / Published: 20 June 2025

Abstract

This study was conducted on a copper porphyry deposit located in Espinar, Cusco (Peru), with the objective of developing and comparing predictive models for processing capacity in SAG grinding circuits. A total of 174 samples were used for the JK Drop Weight Test (JKDWT) and 1172 for the Bond Work Index (BWi), along with 36 months of operational plant data. Three modeling methodologies were evaluated: DWi-BWi, SGI-BWi, and SMC-BWi (Mia, Mib), all integrated into a geometallurgical block model. Validation was performed through reconciliation with actual plant data, considering operational constraints such as transfer size (T80) and maximum throughput (TPH). The model based on SMC parameters and BWi showed the best predictive performance, with a root mean square error (RMSE) of 143 t/h and a mean relative deviation of 1.5%. This approach enables more accurate throughput forecasting, improving mine planning and operational efficiency. The results highlight the importance of integrating geometallurgical and operational data to build robust models that are adaptable to ore variability and applicable to both short- and long-term planning scenarios.

1. Introduction

In recent years, the copper industry has faced significant productivity challenges due to declining ore grades and rising operational costs, particularly those associated with energy consumption. A notable example is the Antapaccay plant, which reported an energy consumption of 0.85 TWh in 2024 [1]. These factors have necessitated more rigorous planning in both ore extraction and processing [2]. Effective modeling of comminution processes is critical to the success of mining operations, as inadequate control can hinder the liberation of valuable minerals, leading to losses in downstream recovery stages [3].
Ore hardness is an intrinsic property of the deposit and, therefore, cannot be directly controlled by plant operators. When the ore exhibits higher resistance to breakage, the size reduction process slows down, increasing the internal load of the mill under constant feed conditions [4]. In scenarios where the mill operates below its nominal capacity, this increased load results in higher energy consumption per ton processed, as more energy is required to achieve the same degree of mineral liberation [5]. Conversely, if the mill is already operating at full capacity, an increase in ore hardness may lead to overloading, a condition that can only be mitigated by reducing the feed rate [6]. This behavior has been extensively documented in studies on energy efficiency and load dynamics in SAG mills, which emphasize the importance of adjusting operational parameters such as mill speed, filling level, and grinding media ratio to maintain optimal performance [7].
Recent research has also shown that variability in ore hardness can induce operational instability, affecting product size distribution and bearing pressure within the mill [8]. To address these challenges, dynamic simulation models have been developed to predict mill behavior in response to changes in ore hardness, enabling the implementation of adaptive control strategies [9]. Additionally, the design and optimization of internal mill liners—such as trapezoidal liners—play a significant role in process efficiency by altering the trajectory of grinding media and their impact on the ore [10,11].
The comminution circuit at the Antapaccay plant consists of a primary crusher followed by a grinding line, which includes a 24,000 kW semi-autogenous (SAG) mill feeding two ball mills with a combined power of 32,800 kW, and a pebble crushing circuit. The total system throughput, typically limited by hydraulic transport conditions, is 4058 t/h. The current product from the grinding circuit has a maximum transfer size (T80max) of 19,783 microns between the SAG and ball grinding stages, and a P80 (80% passing) of 228 microns [12].
In general, the modeling of SABC circuits (SAG mill, ball mill, and pebble crushing) for geometallurgical purposes is based on laboratory test results that capture the spatial variability of comminution attributes [13,14]. At Minera Antapaccay, the JK Drop Weight Test (JKDWT) [15,16] and the Bond Ball Mill Work Index (BWi) [17] are used. These tests support the development of performance models based on specific energy consumption relationships [18,19]. Furthermore, recent innovations in SAG mill design have been reported [20].
The geometallurgical performance model is updated annually through a structured sequence of activities designed to maintain predictive accuracy in the face of deposit variability. This process includes selection of variability samples using standard-length drill cores representative of different zones within the deposit [21]; determination of comminution indices such as the Bond Work Index and the Abrasion Index from the collected samples [19]; quality control of the generated databases, followed by estimation of comminution variables at the geometallurgical block model level using geostatistical techniques [20]; transformation of interpolated comminution indices into performance estimates using process models previously calibrated with historical operational data [22]; and reconciliation of the performance model with metallurgical accounting data, enabling the identification of deviations and model adjustments [23]. This reconciliation also supports the definition of key performance indicators (KPIs) to assess model accuracy and reliability [24].
This study presents the development and evaluation of three geometallurgical performance model alternatives, aiming to identify the one that best represents ore throughput at Minera Antapaccay [7]. These models are designed to support mine planning and project development across short-, medium-, and long-term horizons, as well as to meet specific operational requirements [25,26,27].
The three proposed alternatives are based on different sets of comminution parameters widely used in the mining industry to model ore behavior in grinding processes:
  • Model based on the Bond Work Index (BWi) and the Drop Weight Index (DWi) [28],
  • Model based on SMC indices (Mia, Mib) and BWi tests [29], and
  • Model based on the SAG Grindability Index (SGI) and BWi [19,20].
The most suitable model is selected based on its predictive accuracy against historical operational data and its consistency with metallurgical reconciliation results [30]. This approach reduces uncertainty in mine planning and enhances strategic decision making [31].
Numerous studies have demonstrated the value of site-specific throughput models in improving operational predictability and reducing processing variability. Daniel and Wang highlighted the benefits of developing customized SAG mill throughput forecast models for gold, copper, and iron ore concentrators, emphasizing that once in operation, most variables in the SAG-specific energy equation remain constant, making ore competency (DWi) the dominant factor influencing throughput [32]. Similarly, Both and Dimitrakopoulos developed a machine learning-based geometallurgical throughput model at the Tropicana Gold Mine, showing that integrating hardness proxies and circuit variables significantly improved prediction accuracy [33]. Additionally, Bueno et al. demonstrated how geometallurgical modeling applied to comminution can reduce design risks and improve throughput forecasting by incorporating spatial variability into early-stage mine planning [34].
This work contributes to the field by systematically comparing multiple throughput modeling approaches under real operational conditions, integrating geometallurgical block models with plant reconciliation data. Unlike previous studies, it emphasizes the practical implementation of these models in a high-throughput copper operation, offering a robust and transferable methodology for improving throughput prediction and supporting strategic decision making in complex ore environments.

2. Materials and Methods

The study area is located approximately 12 km in a straight line southwest of the Tintaya mine, within the Alto Huarca rural community, Espinar district and province, Cusco department, in southeastern Peru (Figure 1). Mining activities in this area are carried out using the open-pit method, commonly applied to porphyry-skarn type deposits [30,31].
Geologically, the deposit is part of the Eocene–Oligocene metallogenic belt of the Andahuaylas-Yauri magmatic arc, a region known for its diversity of mineral deposits such as Las Bambas, Los Quechuas, Los Chancas, Antilla, Trapiche, Haquira, and the Antapaccay expansion with the Coroccohuayco project [35,36].
The local geological units include the Maras and Ferrobamba formations, from the Lower and Upper Cretaceous, respectively. These formations have undergone intense folding during Andean tectonic events and were later intruded by stocks, sills, and dikes of the Andahuaylas-Yauri Batholith [37,38,39]. The overlying cover consists of Miocene lacustrine and volcanic deposits, as well as more recent Quaternary deposits [39].
Regarding hydrothermal alteration, three main types have been identified: potassic (potassium feldspar and quartz veinlets), phyllic (quartz-sericite-pyrite), and propylitic (chlorite veinlets), which are typical of porphyry-skarn systems [39,40,41].
Copper mineralization is primarily hosted in intermediate intrusive rocks such as diorite and monzonite, as well as in veinlets, hydrothermal breccias, and contacts with sedimentary rocks (limestones, calcareous shales, siltstones, and sandstones), forming contact breccias, skarn-type bodies, and stockwork structures [35,36,41].
The mineralogy is dominated by chalcopyrite, with contents up to 3.4%, surpassing bornite in the upper zones. At greater depths, this relationship reverses, and mineralization is associated with anhydrite and gypsum levels [42,43,44,45]. Appendix B.
Two main mineralized bodies have been identified: the southern body, extending 1300 m in a NW–SE direction with a variable width between 250 and 430 m; and the northern body, 300 m long and 450 m wide [30].
The contact between intrusions and host rocks has generated a skarn facilitated by quartz metasomatism, creating favorable conditions for stockwork development. This stockwork is structurally controlled by regional faults affecting the intrusive-sedimentary complex, enabling mineral dissemination. Additionally, stockwork zones controlled by local faults have been identified [37,45,46].
The concentrator plant operated by Antapaccay mining company is equipped with a “60 × 113” primary gyratory crusher, designed to process up to 7500 tons of ore per hour, reducing its size to approximately 178 mm [47]. The ore is then transported via a 7-km conveyor belt to a 40 × 26-foot semi-autogenous grinding (SAG) mill powered by a 24 MW motor. This mill features a short trommel and a vibrating screen, feeding two 26 × 40.5-foot ball mills, each with an installed power of 16.4 MW [47]. The system operates in a reverse closed circuit, which includes three batteries composed of 13 cyclones each, with a diameter of 33, as illustrated in Figure 2 [47].
For this study, operational data collected from the plant over the past 36 months will be used. To ensure data quality and consistency, only days when the SAG mill operated for more than 22.8 h (at least 95% of the day) will be considered. Likewise, only months with more than 80% of days under stable operating conditions will be included. Applying these filtering criteria, 30 valid months have been identified for the reconciliation analysis Table 1.
A cut-off grade of 0.1% Cu has been established, used as a criterion to filter only those blocks considered economically viable, in accordance with the Resources and Reserves report. For ore characterization, 158 samples corresponding to the A×b parameter and 1172 samples associated with the Bond Work Index (BWi) are available.
The following information sources will be used in this study:
  • PI system records containing operational variables from the comminution circuit.
  • Database with results from the JK Drop Weight Test (JKDWT).
  • Database with the Bond Work Index (BWi) values.
  • Block model identifying the ore units extracted and processed during the analysis period.
  • Geometallurgical block model used to estimate processing capacity.
Preliminary analysis of these data allows for proper configuration of input variables, detection of atypical operating periods, and establishment of criteria to define the validity of days or months included in the model comparison. From the selected periods, the necessary variables are calculated for calibration and evaluation of each model considered.

2.1. Integrated Workflow for Mining, Metallurgical Data Management, and Geometallurgical Modeling

The development of the comminution model follows a structured sequence encompassing: the characterization plan, collection of mining-metallurgical process data, and geometallurgical modeling (see Figure 3).
  • Characterization Plan:
    This stage involves designing drilling campaigns from which samples are obtained for metallurgical testing. After rigorous quality control (QA/QC), the results are incorporated into the block model through geostatistical estimation processes.
  • Mining-Metallurgical Process Data:
    Using data from monthly closing reports and daily operation logs, filtering is performed to identify ideal processing conditions. Only days with more than 22.8 h of SAG mill operation (95% of the day) and months with over 80% stable days are considered valid. Raw data are extracted from the PI system and cleaned to remove inconsistencies or measurement errors (Appendix A).
  • Geometallurgical Modeling:
    In this phase, files with the required variables are prepared and formatted according to procedural guidelines. The information is cleaned, and calculations are performed to reconcile the processing model with operational data. The quality of the geometallurgical model is evaluated, including mining progress in the block model, and adjusted using different approaches: the model based on DWi and BWi, the Morrell power model, and the model using SGI and BWi. The equations used to transform A×b and BWi results into the various comminution indices employed in this study are also presented [48,49]. Additionally, grinding circuit optimization has been considered as part of the analysis [50].

2.2. The JKMRC Drop Weight Impact Breakage Test

Sample requirements: The test requires an initial sample of approximately 100 kg, with particle sizes between −63 and 13.2 mm [51].
Outputs: The test delivers the specific energy consumption Ecs (kWh/t) and the parameters (A, b) that represent mineral fracture behavior.
Equation: The latter are calculated by adjusting the data of t10 and Ecs according to the following equation [52]:
t 10 = A 1 e b E c s
where
  • A represents the maximum curvature, and
  • b defines the shape of the curve as it approaches the upper limit.
These parameters indicate the natural breakage limit of the rock and the rate at which the rock reaches this maximum, respectively.
Parameters A and b are not independent, so they cannot be used directly to make comparisons between mineral types; on the other hand, the product A×b is an alternative that allows a direct comparison [14].
This Table 2 summarizes the descriptive statistics of the A×b parameter, which characterizes ore breakage behavior in geometallurgical modeling. The values represent the distribution of A×b across 174 samples, providing insight into the variability of ore hardness within the deposit. These metrics are essential for calibrating comminution models and optimizing processing strategies
In Figure 4 presents at the left panel shows the spatial distribution of raw A×b sample values collected across the deposit, reflecting the variability in ore breakage characteristics. The right panel presents the modeled A×b distribution generated using the K-Nearest Neighbors (KNN) algorithm, which interpolates values across unsampled areas based on spatial proximity and similarity. This visualization supports the geometallurgical block model by providing a continuous representation of ore hardness, essential for process optimization and mine planning.

2.3. The Bond Ball Work Index Test

Sample requirements: The Bond ball work index laboratory test was created by Bond [53] and uses approx. 7.0 kg of drill core samples, previously crushed 100%-3.350 mm.
Objective: The aim of the test is obtaining a 250 percent circulating load. BWi test results scale-up is achieved using Bond’s third law of comminution [53]:
S E B M = P M B F U P B M T P H = 10 B W i 1 P 80 1 T 80
where SEBM is specific energy consumption, PBM is nominal power of the mill, FUPBM is a power use factor, TPH is the plant throughput, BWi is the Bond index, and P80 and T80 are product sizes and feed to the mill, respectively [54]. Recent studies have introduced new approaches to the calculation of the Bond work index for finer samples [55].
In Table 3 descriptive statistics of the BWi (Bond Work Index) variable, calculated from 1172 samples. The table presents the mean, standard deviation (SD), and the minimum and maximum observed values. These indicators characterize the variability in ore comminution resistance and are essential for calibrating energy consumption models in grinding circuits.
Figure 5 presents the spatial distribution of BWi values based on sample coordinates. The x-axis (“midx”) and y-axis (“midy”) represent spatial midpoints, while the color gradient encodes the variable “witm,” ranging from 9 to 21. The data reveal two prominent clusters, suggesting spatial heterogeneity in BWi values across the study area. This pattern may indicate underlying environmental, biological, or methodological factors influencing the distribution.

2.4. Comminution Indexes Relationships

The Drop Weight Index (DWI, kWh/m3) is directly related to JKDWT test parameters A and b by the following equation [56]:
D W i = ρ 96.703 A × b 0.992 ; R 2 = 0.98   ( l o g . s c a l e )
where ρ is the mineral density in t/m3.
It is possible to relate A×b parameter with the Mia comminution index from the power model developed by Morrell using the following expressions (Figure 6) [57]:
M i a = 390.87 A × b 0.81 ; R 2 = 1.00   ( l o g . s c a l e )
This reflects a perfectly linear relationship on a log–log scale, as indicated by R2 = 1.00.
Mia corresponds to the coarse ore grinding capacity (over 750 microns) in kWh/t.
Finally, the BWi variable is related to Mib of the Morrell [58] power model, as follows (Figure 7):
M i b = 18.18 P 1 0.295 G b p p 80 f p 80 f 80 f f 80
Mib is the fine ore work index (under 750 microns) (kWh/t), P1 is the test control mesh (microns), Gbp is the net grams of undersize ore per mill revolution (grams/revolution), P80 y F80 correspond to the 80% through size of the product and feed (microns) [49]. The f(P80) and f(F80) are negative exponents that depend on the particle size of the product and the feed, respectively. This functional form allows the model to more accurately capture how grinding efficiency changes with particle size, compared to using a constant exponent.
Another comminution test used in industry is the SPI® or SGI. The kinetic test is run with 2 kg of ore and the time (in minutes) it takes to grind a sample from 80%-12.5 mm to 80%-1.7 mm is measured. The A×b parameter is correlated with the SGI as follows (Figure 8) [58]:
S G I = 8882.72 A × b 1.24 ; R 2 = 0.83   ( l o g . s c a l e )
Although the fit is not perfect (R2 = 0.83), the relationship remains fairly strong on a log–log scale.
In Figure 9 present at the interpretation:
  • Both functions follow a power–law relationship, but SGI decreases more rapidly than Mia with respect to the A×b product.
  • This may reflect differences in the nature of the phenomena they represent, particularly if they are related to physical, biological, or economic processes [59].
Graph Analysis:
Wills and Napier-Munn have extensively discussed the principles and techniques of comminution in their work, which provides a foundational understanding for the methodologies applied in this study [60].

2.5. Model Based on DWI and BWi

The specific energy consumption in SAG grinding is defined by the following expression [51]:
S E S A G = β F 80 a D W i b ϕ e
where SESAG is SAG specific energy consumption, F80 is the 80% through-feed, DWI is the comminution resistance index, ϕ is the critical speed percentage and (β, a, b, e) are constants [61].
The constants β, a, b, and e are calibrated using real plant data or pilot-scale test results.
  • β (Beta): A global scaling coefficient
    Adjusts the overall magnitude of energy consumption.
    Its value depends on mill configuration, ore type, and general operating conditions.
    It is tuned to ensure the model predicts realistic specific energy consumption (SESAG) values in kWh/t.
  • a: Feed size exponent (F80)
    Reflects the influence of feed particle size on energy demand.
    Typical values range from 0.2 to 0.5.
    A positive value indicates that larger feed sizes require more energy.
  • b: Drop Weight Index (DWI) exponent
    Captures how sensitive energy consumption is to ore hardness.
    The DWI quantifies resistance to impact breakage.
    Typical values range from 0.5 to 1.0.
    A higher b value means the model is more responsive to hardness variations.
  • e: Critical speed exponent (ϕ)
    Describes how mill speed affects energy usage.
    Critical speed is the point at which grinding media begin to centrifuge.
    Typical values range from 0.5 to 1.5, depending on mill design and efficiency.
Parameter Estimation Methods:
  • Nonlinear regression using historical plant data.
  • Least-squares fitting based on comminution test results.
  • Simulation and cross-validation with grinding circuit models [62]
The parameters in Equation (7) are tuned using information from the process, with comminution stage operating in a steady-state regime. On the other hand, BWi results are transformed to specific energy consumption using Equation (2). Since the throughput is the same between SAG and ball grinding stage, the following equality must be fulfilled [26]:
P S A G F U P S A G S E S A G = P B M F U P B M S E B M
where Pi corresponds to the installed power in the SAG/Balls stage; FUPi is the fraction of installed power used in size reduction.
The model is solved using Equation (7) to estimate plant TPH; subsequently, a P80 value is imposed, and it is possible to calculate the SAG-ball grinding transfer size using Equations (2) and (8).

2.6. Calculation Workflow for the SAG + Ball Mill Model

Modeling energy consumption in a SAG + ball mill circuit involves a structured sequence of steps, each grounded in empirical data and validated through simulation and plant-scale observations [63,64].
  • Step 1: Define Input Parameters
The model begins by specifying key variables:
  • F80: Feed particle size to the SAG mill (µm),
  • DWI: Drop Weight Index, representing ore hardness (kWh/m3),
  • ϕ: SAG mill speed as a percentage of critical speed (%),
  • β, a, b, e: Empirical constants that scale and shape the energy model,
  • P_SAG, P_BM: Installed power for SAG and ball mills (kW),
  • FUP_SAG, FUP_BM: Fraction of power utilized in each stage,
  • SE_BM: Specific energy for ball milling, typically derived from the Bond Work Index (BWi), and
  • P80: Target product size (µm).
These parameters are essential for simulating energy demand and throughput under varying operational conditions [63,65].
  • Step 2: Calculate Specific Energy Consumption in SAG
The specific energy consumed in the SAG grinding is estimated using a power–law expression:
S E S A G = β F 80 a D W i b ϕ e
This formulation captures the nonlinear influence of feed size, ore hardness, and mill speed on energy usage [63,64].
  • Step 3: Estimate Plant Throughput
Throughput (TPH) is calculated by dividing the effective power input by the specific energy:
T P H = P S A G F U P S A G S E S A G
This step links energy efficiency to production capacity, enabling performance benchmarking [65].
  • Step 4: Apply Energy Balance Between Stages
An energy balance is applied to ensure consistency between the SAG and ball mill stages:
P S A G F U P S A G S E S A G = P B M F U P B M S E B M
This balance can be used to validate or adjust the ball mill energy estimate or the transfer size between stages [64].
  • Step 5: Determine Transfer Size (Tt)
Using the ball mill energy equation (e.g., based on BWi), the transfer size between SAG and ball milling can be back-calculated to satisfy the energy balance.
The specific energy consumption in SAG grinding (SE_SAG) is analyzed by individually modifying each of the model’s key parameters, as illustrated in Figure 10.

2.7. Model Based on SMC (Mia, Mib) and BWi

The following equation is defined for specific energy consumption per grinding stage [29]:
f ( F 80 ) = 0.295 + F 80 10 6 f ( P 80 ) = 0.295 + P 80 10 6 W M i , F 80 , P 80 = M i 4 P 80 f P 80 F 80 f F 80
where F80 is the 80% feed through size, P80 is the 80% product through size, Mi is the specific energy index for size reduction, and W is the grinding stage specific energy consumption.

2.8. Interpretation of Key Components in the Energy Model

Understanding the role of each variable in the particle size–energy relationship is essential for accurate modeling of comminution processes [63].
  • F80 and P80
  • F80 refers to the particle size below which 80% of the feed material passes, while P80 represents the same threshold for the product stream.
  • These metrics are typically expressed in micrometers (µm) or millimeters (mm), depending on the scale of the operation [64].
  • They are fundamental in defining the energy required for size reduction, as used in classical and modified comminution models [65].
  • f(F80) and f(P80)
  • These are variable exponents that adjust based on particle size.
  • As F80 or P80 increase, the corresponding exponent becomes more negative, reducing the overall energy contribution of that term.
  • This approach allows for a more flexible and realistic representation of energy behavior compared to fixed-exponent models [66].
  • Mi (Specific Energy Index)
  • Mi represents the specific energy required to reduce one tonne of material to a target size, expressed in kWh/t.
  • It is also known as the work index or the comminution index and varies depending on the ore type and grinding mechanism (e.g., Mia for impact, Mih for high-pressure grinding, Mic for crushing) [63].
  • This parameter is critical for comparing ore hardness, designing grinding circuits, and calibrating simulation models [66].
  • W (Specific Energy Consumption)
  • W quantifies the energy consumed per tonne of material processed, typically in kWh/t.
  • It is calculated using a modified energy equation that incorporates Mi, particle size terms, and a scaling factor (commonly 4).
  • The interpretation of W depends on the context:
  • If Mi corresponds to a SAG-related index (e.g., DWi or Mia), then W reflects energy use in the SAG stage.
  • If Mi is the Bond Work Index (BWi), then W represents energy in the ball grinding stage [67].
  • In geometallurgical models, different Mi values are used for each stage (e.g., Mib, Mih, Mia, and Mic) to reflect stage-specific energy behavior [68].
This formulation is a generalized version of the particle size–energy equation, similar to Bond’s law but with variable exponents. It estimates the energy required to reduce particle size during grinding, offering more flexibility and accuracy in modeling complex ore behaviors [66].
We can generate a 3D plot (Figure 11) showing how W varies with F80 and P80, assuming a typical Mi value (e.g., 10 kWh/t). This would help illustrate how energy demand increases with greater size reduction and how the curvature of the surface reflects the nonlinear nature of the model.
Some observations are:
  • A greater difference between F80 and P80 leads to higher energy consumption, as expected.
  • When F80 ≈ P80, the energy required approaches zero, indicating minimal or no size reduction.
  • The curved surface reflects the nonlinear relationship introduced by the square root terms in the energy equation.
The SAG grinding stage specific energy consumption is determined as [69]:
S E S A G = K 1 W M i a , F 80 , T 80
where SESAG corresponds to the SAG grinding specific energy consumption, Mia is the energy index related to size reduction in coarse particles (>750 microns), and K1 = 0.95 for the SAG mill operating with crushed pebbles.
The ball grinding stage specific consumption is determined as:
S E c o a r s e = K 1 W ( M i a , T 80 , 750 ) S E f i n e = W M i b , 750 , P 80 S E B M = S E c o a r s e + S E f i n e
where SEcoarse corresponds to the specific energy consumption for grinding particles above 750 microns, SEfine is the specific energy consumption for grinding particles below 750 microns, SEBM is the ball grinding stage specific energy consumption, and Mib is the energy index related to particle size reduction below 750 microns. K1 = 1.00 for the ball mill operating without crushing pebbles [70,71].
Although the same Mia index is used, it is now applied to a sub-stage within ball milling, specifically for the coarse fraction. The value of 750 µm acts as a threshold between coarse and fine particles.
In Equation (11), W (Mia, T80, 750) refers to the energy consumption of the coarse fraction within the ball grinding stage, while W(Mib, 750, P80) covers the fine fraction.
Since the throughput is the same between both systems, the analogous equality like that expressed in Equation (8) must be fulfilled. The model is solved using Newton-Raphson method on Equation (8) evaluated in Equations (10) and (11); the solution converges to a raw value of T80 (restricted by the maximum transfer size). Subsequently, the system TPH is calculated (restricted by the maximum TPH). Finally, P80 value is corrected in cases where the system is restricted by screen opening or transport capacity.

2.9. Model Based on SGI and BWi

SGI or SPI results (SGS commercial lab version) are industrially scaled using the formula [72]:
S E S A G = P S A G F U P S A G T P H = K S G I T 80 n
where SESAG is the specific energy consumption, PSAG is the mill nominal power, FUPSAG is a power use factor, TPH is the flow of ore processed, K is a parameter equal to 5.59, n is a parameter equal to 0.55, and T80 is the mill product size [47].
Integration with BWi and Energy Balance
Model Stages:
Transformation of the Bond Work Index (BWi) into specific energy consumption using a Bond-type equation (Equation (2)).
An energy balance is imposed between the SAG and ball mill stages:
The system is solved using the Newton-Raphson method, simultaneously evaluating:
Equation (12) (SGI),
Equation (2) (BWi), and
Equation (8) (Power balance).
This approach allows for determining a value of T80 that balances the system.
Model Constraints:
  • The value of T80 is limited by the maximum transfer size accepted by the ball mill.
  • TPH is also constrained by the plant’s maximum capacity.
  • The value of P80 may be adjusted if there are limitations due to:
    Screen aperture, and
    Conveyor capacity.
Model Applications:
  • Design and simulation of SAG + ball mill grinding circuits.
  • Evaluation of expansion scenarios or ore type changes.
  • Optimization of specific energy consumption and throughput.
Abstract the key steps of the process, from the transformation of the BWi to the evaluation of operational constraints such as transfer size (T80), plant capacity, and screen aperture (Figure 12):
  • Start: The process begins with the objective of integrating the Bond Work Index (BWi) into a SAG + Ball mill energy model, ensuring energy balance across stages.
  • Define Input Parameters: This step involves specifying all necessary inputs, including:
    • BWi (Bond Work Index),
    • Installed power for SAG and ball mills,
    • Utilization factors (FUP), and
    • Initial estimates for transfer size (T80), product size (P80), and energy indices (e.g., Mia and Mib).
  • Transform BWi to Specific Energy Consumption (Equation (2))
    Using a Bond-type equation, the BWi is converted into specific energy consumption (SE_BM) for the ball mill stage. This allows comparison with the SAG stage energy.
  • Impose Energy Balance (Equation (8))
    An energy balance equation is applied to ensure that the energy input and output across the SAG and ball mill stages are consistent:
  • Solve System Using Newton-Raphson Method
    The system of nonlinear equations is solved iteratively using the Newton-Raphson method to find a consistent solution for T80 and energy values.
  • Evaluate Equations (SGI, BWi, Power Balance)
    At each iteration, the model evaluates:
    • SGI-based energy (Equation (12)),
    • BWi-based energy (Equation (2)), and
    • Power balance (Equation (8)).
    This ensures all components are aligned.
  • Determine T80 Value
    Once convergence is achieved, the model outputs the optimal T80 (transfer size) that satisfies the energy balance and system constraints.
  • Check Constraints
    The solution is validated against operational limits:
    • Maximum transfer size accepted by the ball mill,
    • Plant throughput capacity (TPH), and
    • Screen aperture and conveyor limitations.
    Adjustments are made if any constraint is violated.
  • End
    The process concludes with a validated and balanced energy model, ready for use in circuit design, simulation, or optimization.
On the other hand, the BWi results are transformed to specific energy consumption using Equation (2). Finally, since the throughput is the same between both systems, the analogous equality like that expressed in Equation (8) must be fulfilled. The model is solved using the Newton-Raphson method on Equation (8) evaluated in Equations (2) and (12); the solution converges to a raw value of T80 (restricted by the maximum transfer size) [72]. Subsequently, the TPH of the system is calculated (restricted by the maximum TPH). Finally, P80 value is corrected in cases where the system is restricted by screen opening or transport capacity [72,73].
Process restrictions
From a practical point of view, there is a maximum throughput (TPHmax) usually determined by transport considerations in the system. Additionally, materials with a particle size larger than the screen opening mesh will remain in the SAG stage; therefore, there is a maximum transfer size (T80max). The above conditions impose limits on the throughput provided by Equations (10) and (12).
The maximum T80 represents the coarsest particle size that can be effectively transferred from the SAG mill to the ball mill without compromising grinding efficiency or overloading the downstream equipment. This limit is typically defined by:
  • The ball mill’s feed size capacity, which is influenced by liner design, ball size, and mill diameter.
  • The hydraulic transport capacity of the system, including conveyors and pumps, must handle the coarse fraction without blockages or excessive wear [73].
TPH Limit—Plant Throughput
The maximum TPH (tons per hour) is constrained by:
  • The installed power and utilization efficiency of the grinding mills.
  • The classification system (e.g., hydrocyclones or screens), which must maintain separation efficiency at high flow rates.
  • The ore characteristics, such as hardness and density, which affect the residence time and energy demand [74,75].
Hydraulic Limit as Governing Factor
In both cases, the hydraulic limit—the ability of the system to transport and classify slurry efficiently—acts as the governing constraint. If exceeded, it can lead to:
  • Reduced grinding efficiency
  • Increased circulating loads,
  • Premature wear of equipment, and
  • Risk of system instability or shutdown [76].
Application in Predictive Models
These maximum values are used as boundary conditions in simulation tools and geometallurgical models to:
  • Prevent unrealistic predictions of throughput,
  • Ensure safe and efficient operation under varying ore types, and
  • Support decision making in circuit design and expansion planning.
Figure 13 illustrates the operational constraints defined by hydraulic and screen opening limits in relation to throughput (TPH) and Mia. The vertical axis represents the throughput in tons per hour (TPH), while the horizontal axis corresponds to Mia, a parameter likely related to ore hardness or the energy index. The bold black line delineates two distinct operational boundaries: a horizontal segment indicating the Hydraulic Limit, and a descending curve representing the Screen Opening Limit. These boundaries define the feasible operating region for the system, highlighting the trade-offs between material throughput and mechanical constraints.

3. Results

The processing capacity model was conceptualized into two components: the SAG grinding stage and the ball grinding stage. This diagram illustrates (Figure 14) the key parameters involved in the comminution process within a typical SAG (semi-autogenous grinding) and Ball Mill circuit. In the SAG section, the feed characteristics are defined by F80 (the 80% passing size of the feed) and A×b (a parameter from the JK Drop Weight Test indicating ore hardness). The Ball Mill section includes operational and product parameters such as TPH (tons per hour), P80 (the 80% passing size of the product), and BWi (Bond Work Index). The intermediate parameter T80 represents the transfer size between the two grinding stages. This schematic is useful for understanding the relationships between ore characteristics, mill throughput, and energy requirements in mineral processing circuits.
The performance models were implemented using the open-source software R/RStudio [77,78]. Additionally, the correctness of the code was verified by independently implementing the models in Microsoft® Excel® 2021 and Microsoft® Visual Basic® 2021 for Applications. Geometallurgical modeling was applied for performance estimation [79,80,81].
The workflow for the three evaluated processing models is summarized in the following Figure 15:
The workflow activities include
  • Library loading: Required R libraries are loaded for code execution.
  • Function loading: Specific functions used in the modeling process are enabled.
  • Data loading: The following data files are read:
    PI-System data file containing comminution circuit variables.
    Database with results from JK Drop Weight Test (JKDWT) samples.
    Database with the Bond Work Index (BWi) test results.
    Block model identifying mined blocks processed during the evaluation period.
  • Data cleaning: Quality control and necessary modifications are applied to raw data for use in the modeling process.
  • A×b calculation: Due to low sample density in this area, it must be verified whether estimations exist; otherwise, the block model must be populated.
  • Application of the processing model to mined blocks: The processed flow calculation algorithm is applied to the mined blocks from 1 January 2018, to 1 November 2020.
  • Results verification: General consistency of the results is verified at the block model level.
  • Block model volumetrics: Volumetric calculations are performed to determine TPH, T80, and P80 values monthly.
  • Reconciliation: Plant and modeled results for TPH, T80, and P80 are compared monthly.
    The model parameters were determined using plant data collected over a 36-month period (PI system). Specifically, the following variables and process specifications were considered:
    Power usage fraction for SAG and ball milling.
    Total installed power for SAG and ball milling (kW).
    Feed size at 80% passing for SAG (microns).
    Final product size at 80% passing (microns).
    Maximum transfer size from SAG to ball milling (microns).
    Maximum system throughput (t/h).
    Critical speed of the SAG mill.
    To ensure steady-state operation, only months with at least 80% of the time operating at 95% or more were considered.
  • Historical or expected average values:
  • SAG feed size (F80): 71,273.25 microns,
  • Ball mill product size (P80): 229.13 microns,
  • SAG power usage (FUPSAG): 21,507 kW,
  • Ball mill power usage (FUPBM): MB1 = 15,150 kW, MB2 = 14,934 kW,
  • Installed SAG power (PSAG): 24,000 kW,
  • Installed ball mill power (PBM): 32,800 kW,
  • Maximum system throughput (TPHmax): 4058 t/h, and
  • Maximum transfer size from SAG to ball milling (T80max): 19,783 microns.
  • Block model estimates include
    A×b, for Mia calculation;
    BWi, grams per revolution (Gbp), feed and product sizes (F80, P80), and control mesh P1, for Mib calculation [46];
    Note: If complete BWi data is unavailable, Mib is estimated using a linear relationship: Mib = a × BWi + b.
Given a target P80, the algorithm estimates T80 and TPH. In specific cases, P80 is recalculated to satisfy the system of equations under boundary conditions.
The following figures (Figure 16, Figure 17 and Figure 18) present time series and descriptive statistics for six key variables relevant to the modeling and reconciliation process. The dotted line in each graph represents the average value of the variable over the period considered.
The DWi-BWi Model: The DWi-BWi model was evaluated using baseline values for critical parameters. Sensitivity analysis revealed that the model did not respond well to parameter adjustments, often resulting in maximum throughput values. The spatial distribution of TPH estimated by the block model is shown in Figure 19.
The Morrell Power Model: The Morrell power model was also evaluated using baseline values for critical parameters. The model exhibited variability in TPH values across different pits, with Pit 1 showing the highest variability. Nonetheless, the model provided reasonable predictions for both processed tonnage and product size. The spatial distribution of TPH is presented in Figure 20.
The SGI-BWi Model: The SGI-BWi model was evaluated under similar conditions. It demonstrated comparable variability across pits and yielded reasonable predictions for processed tonnage and product size. The spatial distribution of TPH is also shown in Figure 21.
Model Reconciliation and Predictive Accuracy
DWi-BWi Model Reconciliation
The reconciliation between plant performance and the DWi-BWi model output is shown below.
In this analysis, the predictive capability of the parametric model defined by Equation (7) was evaluated. The fundamental parameters (β, a, b, e) were initially calibrated using operational plant data. However, the results from this preliminary calibration stage revealed limited predictive accuracy, as illustrated in Figure 22 (top panel), where significant dispersion is observed between estimated values and actual plant data, along with high relative errors.
To address this, a block-wise optimization strategy was implemented, aimed at minimizing the fitting error through iterative reconfiguration of the model parameters. This methodology led to a substantial improvement in estimation accuracy, as shown in Figure 22 (bottom panel), where a notable reduction in relative error magnitude and greater alignment between estimated and actual curves is evident.
Quantitatively, the first model iteration (without optimization) yielded a root mean square error (RMSE) of 351 tons per hour (t/h), indicating a considerable deviation from actual system behavior. After applying the optimization algorithm, the RMSE was reduced to 147 t/h, representing a significant improvement in model fit.
However, while parameter optimization can enhance short-term model accuracy, it introduces inherent risks of overfitting. Excessive adaptation to historical data may compromise the model’s generalization capacity and predictive robustness in future scenarios—particularly in long-term planning under the Life of Mine (LOM) framework. Therefore, caution is advised when applying intensive optimization techniques, favoring models that balance fit quality with generalization capability.
SMC (Mia, Mib)—BWi Model Reconciliation
Figure 23 presents a comparative analysis between actual plant throughput and estimates generated by the hybrid model based on the comminution parameters Mia and Mib, integrated with the Bond Work Index (BWi). This reconciliation assesses the model’s ability to replicate the dynamic behavior of throughput (t/h) across different operational periods.
The chart uses overlaid bars to compare estimated and actual throughput values, while the solid line represents the relative error percentage (DRel-TPH) for each period. This dual representation facilitates the identification of discrepancies and quantifies the model’s predictive accuracy.
Except for the first period, where a more pronounced deviation is observed, the model captures the observed throughput trend with reasonable fidelity. In subsequent periods, the difference between estimated and actual values remains within acceptable margins, suggesting proper calibration under stable or recurring operational conditions.
From a quantitative standpoint, the model based on the SMC methodology (incorporating Mia and Mib) and BWi achieves an RMSE of 143 t/h. This indicates a high level of accuracy, especially considering the inherent variability of comminution processes and the complexity of interactions among ore properties, operating conditions, and circuit configuration.
Nevertheless, the model’s validity should be assessed not only by its historical fit but also by its predictive robustness in future scenarios. Its consistency across multiple periods and low RMSE position it as a valuable tool for operational planning and strategic decision making in medium- and long-term mining contexts.
SGI-BWi Model Reconciliation
Figure 24 shows the reconciliation between actual plant throughput and estimates from the predictive model based on the Standard Grindability Index (SGI) combined with the Bond Work Index (BWi). This comparison evaluates the SGI-BWi model’s ability to replicate operational throughput behavior across different production periods.
The graph includes two vertical axes: the left axis represents throughput in tons per hour (t/h), and the right axis shows relative error as a percentage. Bars represent estimated and actual throughput values, while the relative error line illustrates the magnitude and direction of deviations.
Across the analyzed periods, at least three instances show significant divergence between model estimates and observed plant values. These discrepancies suggest that under certain operational conditions or ore characteristics, the SGI-BWi model fails to adequately capture system dynamics, indicating limitations in generalization or parameter representativeness.
Quantitatively, the model yields an RMSE of 219 t/h, a considerable deviation compared to other models in this study. While it may provide a general approximation of system behavior, its precision is limited and may not be suitable for applications requiring high predictive fidelity, such as short-term planning or real-time optimization.
It is important to note that the SGI-BWi model’s performance may be influenced by multiple factors, including mineralogical variability, grinding circuit conditions, and sensitivity to input parameters. Therefore, it is recommended to complement this approach with additional models or more robust calibration techniques, especially when aiming for reliable decision-making tools in high-variability operational contexts.

4. Discussion

The comparative evaluation of predictive models for estimating processing capacity (TPH) in the context of mineral processing is a critical component in the optimization of industrial operations. In this study, three approaches based on combinations of comminution indices were analyzed: DWi-BWi, SMC-BWi (the Morrell power model), and SGI-BWi. Each of these models exhibits distinct characteristics in terms of computational complexity, predictive accuracy, and statistical robustness.

4.1. The DWi-BWi Model: Dual Processing and Optimization

The DWi-BWi model is implemented in two stages: an initial phase based on seed values and a subsequent optimization phase. This dual-processing structure entails additional computational load but allows for parameter refinement to enhance predictive performance. In its initial form (DWi-BWi seed), the model yields a relatively high root mean square error (RMSE = 351 t/h), indicating poor fitting capability without calibration. However, after optimization, the RMSE is significantly reduced to 147 t/h, demonstrating the effectiveness of the tuning process in improving model performance.
From a statistical perspective, the optimized model exhibits a mean relative error close to zero (−0.0382) and a standard deviation of 4.19, suggesting virtually no bias and moderate variability. Nevertheless, this improvement is accompanied by the risk of overfitting, particularly when the model is trained on a limited or non-representative dataset. Such overfitting may compromise the model’s generalization capacity in operational scenarios different from those used during calibration.

4.2. The SMC-BWi Model: Simplicity and Accuracy

The Morrell power model (SMC-BWi) stands out for its structural simplicity and high predictive accuracy. With an RMSE of 143 t/h, it is the model with the lowest root mean square error among those evaluated. Additionally, it presents a mean relative error of 1.5% with a standard deviation of 3.92, indicating low bias and controlled dispersion. Unlike the DWi-BWi model, the SMC-BWi does not require a post-optimization phase, making it an efficient and reliable tool for real-time industrial applications.
From an operational standpoint, the absence of a tuning phase significantly reduces implementation time and computational requirements. This makes it particularly attractive for processing plants that demand fast and robust decision-making tools.

4.3. The SGI-BWi Model: High Variability and Predictive Limitations

Although conceptually valid, the SGI-BWi model presents significant limitations in terms of accuracy and stability. With an RMSE of 219 t/h, its performance is inferior to that of the other models. Furthermore, it exhibits a mean relative error of −1.18% with a standard deviation of 5.91, indicating a negative bias and high variability in predictions. This dispersion suggests that the model is more sensitive to fluctuations in input data, which may be due to the lower representativeness of the SGI index in the energy dynamics of the comminution process (Table 4).

4.4. Graphical Comparison and Analysis of Relative Errors

Figure 25 provides a visual comparison of the relative error behavior across the three models. It can be observed that the optimized DWi-BWi model achieves a significant reduction in error compared to its initial version, approaching the performance of the SMC-BWi model. However, its reliance on a post-tuning process introduces uncertainty regarding its long-term stability. In contrast, the SGI-BWi model shows greater dispersion in its relative errors, reinforcing its lower reliability as a predictive tool.

4.5. Selection of the Optimal Model

The selection of the optimal model is based on two main criteria: root mean square error (RMSE) and relative error behavior. According to these criteria, the Morrell power model (SMC-BWi) emerges as the most suitable alternative for estimating processing capacity. Its low RMSE, reduced bias, and statistical stability make it a robust, accurate, and easy-to-implement tool. Moreover, its independence from additional calibration processes makes it ideal for dynamic operational environments where speed and reliability are essential.

5. Conclusions

This study evaluated three alternative models for predicting throughput in the SAG-ball mill circuit at Antapaccay Mine, based on different combinations of comminution indices. Among the evaluated approaches, the model integrating SMC parameters (Mia, Mib) with the Bond Work Index (BWi) demonstrated the highest predictive accuracy, achieving the lowest root mean square error (RMSE = 143 t/h) and a mean relative error of 1.5%.
The modeling process incorporated a comprehensive dataset, including monthly mining volumes, hourly plant operational data, and metallurgical test results (JKDWT and BWi), filtered to ensure steady-state operating conditions. This methodological rigor enhances the model’s reliability and applicability within the operational context of Antapaccay Mine.
Although the SMC-BWi model was calibrated using site-specific data, its structure is generalizable and can be adapted to other mining operations. However, direct application without calibration is not recommended due to differences in ore mineralogy, circuit configuration, and operational constraints. Site-specific calibration using local comminution test data and operational records is essential to ensure predictive accuracy and model robustness.
From an economic perspective, the implementation of this model contributes to operational efficiency by enabling more accurate throughput forecasting. This facilitates better alignment between mine planning and plant capacity, reducing the risk of overloading or underutilization. Furthermore, the model supports the development of integrated comminution–flotation simulations, which can anticipate the impact of changes in feed characteristics or circuit design. These capabilities translate into improved resource allocation, reduced energy consumption per ton processed, and enhanced metallurgical recovery—ultimately contributing to the economic sustainability of the operation.
In summary, the SMC−BWi model not only provides a reliable tool for throughput prediction at Antapaccay Mine but also offers a transferable modeling strategy that, with appropriate calibration, can be adapted to other mining contexts. Its integration into geometallurgical workflows represents a valuable contribution to the optimization of mineral processing operations and the economic performance of mining facilities.

Author Contributions

Conceptualization, M.G. and G.I.; methodology, G.I. and H.M.; software, N.F.; validation, H.M. and G.S.M.; formal analysis, M.G. and G.I.; investigation, M.G., G.I., G.S.M., H.M. and N.F.; resources, G.S.M.; data curation, M.G. and N.F.; writing—original draft preparation, M.G. and G.I.; writing—review and editing, M.G. and G.I.; visualization, M.G. and G.I.; supervision, M.G.; project administration, G.I.; funding acquisition, G.I. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Restrictions apply to the availability of these data. Data was obtained from Compañia Minera Antapaccay and are available https://ctivitae.concytec.gob.pe/appDirectorioCTI/VerDatosInvestigador.do?id_investigador=70210 (accessed on 18 May 2025) with the permission of Compañia Minera Antapaccay.

Conflicts of Interest

Hector Montes, Gerardo San Martín and Nicole Fantini are employees of Mine to Port Consulting. The paper reflects the views of the scientists and not the company.

Abbreviations

The following abbreviations are used in this manuscript:
SymbolDefinitionUnits
ACurvature maximum
bShape parameter
EcsSpecific energy consumptionkWh/t
t10Percentage of product under 1/10 of the initial size%
SEBMSpecific energy consumption in ball grindingkWh/t
PBMNominal power of the ball millkW
FUPBMPower usage factor
BWiBond Work IndexkWh/t
P80Product size at 80% passingmicrons
T80Feed size at 80% passingmicrons
DWiDrop Weight IndexkWh/m3
ρMineral densityt/m3
A×bProduct of parameters A and b
SMCSAG Mill Comminution
MiaSpecific energy index for coarse grindingkWh/t
MibSpecific energy index for fine grindingkWh/t
P1Control mesh sizemicrons
GbpGrams per revolutiong/rev
SGI P80Standard Grindability IndexProduct size at 80% passingmicrons
SESAG SGISpecific energy consumption in SAG grindingStandard Grindability IndexkWh/t
F80 SESAGFeed size at 80% passingSpecific energy consumption in SAG grindingmicronskWh/t
φ F80Critical speed percentageFeed size at 80% passing%microns
βφEmpirical constantCritical speed percentage%
Empirical constantEmpirical constant
eaEmpirical constantEmpirical constant
WeSpecific energy consumptionEmpirical constantkWh/t
MiWSpecific energy indexSpecific energy consumptionkWh/tkWh/t
SEcoarseMiSpecific energy consumption for coarse particlesSpecific energy indexkWh/tkWh/t
SEfineSEcoarseSpecific energy consumption for fine particlesSpecific energy consumption for coarse particleskWh/tkWh/t
K1SEfineCorrection factorSpecific energy consumption for fine particleskWh/t
TPHK1ThroughputCorrection factort/h
KTPHEmpirical constantThroughputt/h
nKEmpirical constantEmpirical constant
RMSEnRoot Mean Square ErrorEmpirical constant
SAGRMSESemi-Autogenous GrindingRoot Mean Square Error
MWSAGMegawattSemi-Autogenous Grinding
mmMWMillimeterMegawatt
JKDWTmmJK Drop Weight Test (Julius Kruttschnitt)Millimeter
kWh/tJKDWTkilowatt-hours per tonJK Drop Weight Test (Julius Kruttschnitt)
KPIskWh/tkey performance indicatorskilowatt-hours per ton
TWhKPIsTerawatt-hourkey performance indicators
TWhTerawatt-hour

Appendix A. Example of Hardness Data Integration with Plant Data

To illustrate the integration of hardness data with plant operational data, consider the case of January in Year 1 of the study period. During this month, the ore control and dispatch system identified that the plant processed material from a set of geometallurgical blocks located in the central-western sector of the pit. Each of these blocks had previously been characterized through the geometallurgical program, with associated A×b and BWi values derived from laboratory tests (JKDWT and the Bond Ball Mill Work Index, respectively).
For example, Block ID 1023, processed during the second week of January, had an A×b value of 38.2 and a BWi of 14.6 kWh/t. These values were extracted from the block model and used as inputs in the energy-based throughput models. Specifically, the A×b value was transformed into a DWi estimate using Equation (3) and then combined with the BWi value in Equation (7) to estimate the specific energy consumption and resulting throughput (TPH) for that block.
This process was repeated for all blocks processed during the month. The weighted average of the estimated TPH values, based on the tonnage contribution of each block, was then compared with the actual plant throughput for model calibration and validation (Figure A1).
This example demonstrates how the spatially distributed hardness data were dynamically linked to the monthly plant feed, ensuring that the predictive models reflect the true variability of the orebody. This methodology enhances the reliability of throughput forecasting and supports more informed operational and strategic decision making.
Figure A1. Methodology for integrating geometallurgical parameters in the estimation of specific energy and plant throughput. The process includes block identification, parameter extraction, energy calculation, and reconciliation with actual plant performance.
Figure A1. Methodology for integrating geometallurgical parameters in the estimation of specific energy and plant throughput. The process includes block identification, parameter extraction, energy calculation, and reconciliation with actual plant performance.
Mining 05 00037 g0a1
Table A1. Hardness Data and Estimated Throughput per Block.
Table A1. Hardness Data and Estimated Throughput per Block.
Block IDX CoordinateY CoordinateA×bBWi (kWh/t)Estimated TPHTonnage Contribution (%)
1023500100038.214.6350020
1045520102040.115345025
1078540104037.514.3355015
110256010603914.8348030
1134580108041.215.2342010
This figure illustrates the spatial location of five representative blocks processed during a specific month (January, Year 1). The size of each circle reflects the block’s proportional contribution to the total monthly tonnage, while the color gradient represents the estimated throughput (TPH), calculated using the block-specific hardness parameters (A×b and BWi) through energy-based models (Figure A2). This visualization demonstrates the integration of block-level hardness data with plant operational records, enabling monthly throughput estimation that accounts for the spatial and compositional variability of the processed ore. Such integration enhances the predictive accuracy and operational relevance of the throughput models.
Figure A2. Spatial distribution of geometallurgical blocks and their relative contribution to monthly throughput. Circle size: Represents the percentage contribution of each block to the total monthly tonnage. Color: Indicates the estimated throughput (TPH) for each block, based on its hardness parameters.
Figure A2. Spatial distribution of geometallurgical blocks and their relative contribution to monthly throughput. Circle size: Represents the percentage contribution of each block to the total monthly tonnage. Color: Indicates the estimated throughput (TPH) for each block, based on its hardness parameters.
Mining 05 00037 g0a2

Appendix B

Table A2 summarizes the modal abundance and oxide contribution of the main sulfide and associated minerals identified in the mineralogical characterization of the deposit. The data includes copper-bearing phases such as chalcopyrite, chalcocite, and bornite, as well as gangue sulfides like pyrite and siderite. The oxide percentages reflect the contribution of each mineral to the total metal content, particularly for copper and iron. These values were derived from quantitative mineralogical analysis and are consistent with the observed paragenesis in the porphyry-skarn system. The predominance of chalcopyrite and pyrite supports the geometallurgical modeling approach, as these minerals significantly influence both the metallurgical response and the energy requirements of the grinding circuit. The absence or trace levels of complex sulfosalts (e.g., tennantite, tetrahedrite) and molybdenite in most samples suggests a relatively simple copper deportment, which facilitates the calibration of throughput models based on comminution indices such as A×b and BWi.
Table A2. Mineralogical Composition for TIMA (TESCAN Integrated Mineral Analyzer).
Table A2. Mineralogical Composition for TIMA (TESCAN Integrated Mineral Analyzer).
Modal FullChemical CompositionAverageMaxMin
ChalcopyriteCuFeS20.803.470.08
ChalcociteCu2S0.030.820.00
BorniteCu5FeS40.140.490.00
EnargiteCu3AsS40.000.000.00
TennantiteCu12As4S130.000.010.00
Tetrahedrite(Cu Fe)12Sb4S130.000.000.00
Other Cu Minerals-0.000.100.00
PyriteFeS20.7611.730.00
Fe Oxides 2.0921.440.03
MolybdeniteMoS20.010.070.00
SphaleriteZnS0.000.030.00
GalenaPbS0.000.070.00
Other Sulfides-0.000.000.00
High hardnessQuartzSiO214.2147.180.07
PlagioclaseNa (AlSi3O8)–Ca (Al2Si2O8)31.3165.317.21
AlbiteNa (AlSi3O8)20.6851.992.66
Other Silicates-1.085.120.06
Medium hardnessAmphibolevariable composition6.9221.081.16
ApatiteCa5 (PO4)3 (Cl/F/OH)0.320.550.14
K-Feldspar(K Na Ca Ba NH4) (Si Al)4O87.7218.200.54
AnkeriteCa (Fe2⁺ Mg) (CO3)21.2612.270.01
DolomiteCaMg (CO3)20.040.490.00
SideriteFeCO30.486.360.01
Low hardnessCalciteCaCO34.8143.670.55
MuscoviteKAl2 (AlSi3O10) (OH)20.855.340.01
ChloriteMg5Al (AlSi3O10) (OH)84.089.660.02
BiotiteK (MgFe)3 AlSi3O10 (OH)22.067.270.01
Gypsum/AnhydriteCaSO4·2H2O0.040.890.00
Others-0.313.140.01
Figure A3. Opaque minerals identified as chalcopyrite (cp), sphalerite (efn) and magnetite (mt), LR (light reflection).
Figure A3. Opaque minerals identified as chalcopyrite (cp), sphalerite (efn) and magnetite (mt), LR (light reflection).
Mining 05 00037 g0a3
Figure A4. Image, composition, and spectrum of chalcopyrite.
Figure A4. Image, composition, and spectrum of chalcopyrite.
Mining 05 00037 g0a4

References

  1. Perú Energía. Por Cuarto año Consecutivo Antapaccay Obtiene Certificado que Acredita uso de Energía Limpia [For the Fourth Consecutive Year, Antapaccay Obtains a Certificate Accrediting the Use of Clean Energy]. Perú Energía, 7 April 2024. Available online: https://peruenergia.com.pe/antapaccay-certificacion-i-rec-energia-limpia/ (accessed on 18 May 2025).
  2. Perú Energía. Minería Peruana Duplicaría su Producción de Cobre y Consumo Eléctrico al 2035 por Impulso de la Transición Energética [Peruvian Mining Would Double Its Copper Production and Electricity Consumption by 2035 Due to the Impetus of the Energy Transition]. Perú Energía 2024. Available online: https://peruenergia.com.pe/mineria-peruana-duplicaria-su-produccion-de-cobre-y-consumo-electrico-al-2035-por-impulso-de-la-transicion-energetica/ (accessed on 18 May 2025).
  3. Flores, G.A.; Risopatron, C.; Pease, J. Processing of Complex Materials in the Copper Industry: Challenges and Opportunities Ahead. JOM 2020, 72, 3447–3461. [Google Scholar] [CrossRef]
  4. Srivastava, V.; Akdogan, G.; Ghosh, T.; Ganguli, R. Dynamic modeling and simulation of a SAG mill for Mill Charge Characterization. Miner. Metall. Process 2018, 35, 61–68. [Google Scholar] [CrossRef]
  5. Powell, M.S.; Mainza, A.N.; Yahyaei, M. Low-Cost SAG Milling Opportunities. In Proceedings of the SAG Conference 2023, Vancouver, BC, Canada, 24–28 September 2023; Available online: https://www.researchgate.net/publication/375669041_Low-Cost_SAG_Milling_Opportunities (accessed on 18 May 2025).
  6. Toor, P.; Franke, J.; Powell, M.; Bird, M.; Waters, T. Designing Liners for Performance Not Life. Miner. Eng. 2012, 36–38, 240–248. [Google Scholar] [CrossRef]
  7. Jiang, R.; Wang, G.; Li, J.; Sun, K.K.; Hou, Y. Parameter Optimization of Large SAG Mill Liner Based on DEM and Kriging Model. J. Min. Sci. 2021, 57, 32–44. [Google Scholar] [CrossRef]
  8. Dong, H.; Moys, M.H. Load Behavior and Mill Power. Int. J. Miner. Process. 2003, 69, 11–28. [Google Scholar] [CrossRef]
  9. Srivastava, V.; Akdogan, G.; Ghosh, T.; Ganguli, R. Dynamic Neural Network Based Model for SAG Mill Power Prediction. In Proceedings of the 38th International Symposium on the Application of Computers and Operations Research in the Mineral Industry (APCOM 2017), Golden, CO, USA, 9–11 August 2017; Volume 38. [Google Scholar]
  10. Rezaeizadeh, M.; Fooladi, M.; Powell, M.S.; Mansouri, S.H.; Weerasekara, N.S. A New Predictive Model of Lifter Bar Wear in Mills. Miner. Eng. 2010, 23, 1174–1181. [Google Scholar] [CrossRef]
  11. Harbort, G.; Lam, K.; Sola, C. The Use of Geometallurgy to Estimate Comminution Parameters within Porphyry Copper Deposits. In Proceedings of the Second AusIMM International Geometallurgy Conference (GeoMet 2013), Brisbane, Australia, 30 September–2 October 2013; pp. 217–230. Available online: https://www.ausimm.com/publications/conference-proceedings/the-second-ausimm-international-geometallurgy-conference-2013/the-use-of-geometallurgy-to-estimate-comminution-parameters-within-porphyry-copper-deposits/ (accessed on 18 May 2025).
  12. Iriarte, G. Evaluación de Modelo de Capacidad de Procesamiento (tph) a Partir de las Propiedades Mecánicas de la Roca en Molinos Semiautógenos (SAG) en Yacimientos de Pórfidos de Cobre [Evaluation of a Processing Capacity Model (tph) Based on Rock Mechanical Properties in SAG Mills at Porphyry Copper Deposits]. Bachelor’s Thesis, Universidad Nacional de San Agustín de Arequipa, Arequipa, Peru, 2022. Available online: https://alicia.concytec.gob.pe/vufind/Record/UNSA_ee1ea35b299f74fc9cae350fe9251944 (accessed on 18 May 2025).
  13. Marijnissen, M.J.; Graczykowski, C.; Rojek, J. Simulation of the comminution process in a high-speed rotor mill based on the feed’s macroscopic material data. Miner. Eng. 2021, 163, 106746. [Google Scholar] [CrossRef]
  14. Gu, Y. Automated Scanning Electron Microscope Based Mineral Liberation Analysis: An Introduction to JKMRC/FEI Mineral Liberation Analyzer. J. Miner. Mater. Charact. Eng. 2003, 2, 33–41. [Google Scholar] [CrossRef]
  15. Matei, V.; Bailey, C.; Morrell, S. A New Way of Representing A and b Parameters from JK Drop-Weight and SMC Test: The “SCSE”. In Proceedings of the SAG Conference, Vancouver, BC, Canada, 22–26 September 2015; Available online: https://www.smctesting.com/documents/A_New_Way_of_Representing_A_and_b_Parameters_from_JK_Drop-Weight_and_SMC_Tests_The_SCSE.pdf (accessed on 18 May 2025).
  16. Fuerstenau, D.W.; Abouzeid, A.Z. The energy efficiency of ball milling in comminution. Int. J. Miner. Process 2002, 67, 161–185. [Google Scholar] [CrossRef]
  17. Cleary, P.W.; Morrison, R.D.; Sinnott, M.D. Prediction of slurry grinding due to media and coarse rock interactions in a 3D pilot SAG mill using a coupled DEM + SPH model. Miner. Eng. 2020, 159, 106614. [Google Scholar] [CrossRef]
  18. Radziszewski, P. Energy recovery potential in comminution processes. Miner. Eng. 2013, 46–47, 83–88. [Google Scholar] [CrossRef]
  19. Keeney, L.; Walters, S. A practical approach to geometallurgical modeling. Miner. Eng. 2014, 58, 69–81. [Google Scholar] [CrossRef]
  20. Powell, M.S.; Bueno, M. Application of process models in geometallurgy. Miner. Eng. 2008, 21, 442–451. [Google Scholar] [CrossRef]
  21. Lamberg, P. Geometallurgical definition and testing. Miner. Eng. 2011, 24, 1229–1235. [Google Scholar]
  22. McQuiston, F.W.; Shoemaker, R.S. Metallurgical Accounting and Reconciliation in Mineral Processing. In Proceedings of the SME Annual Conference, Seattle, WA, USA, 19–22 February 2012; Available online: https://cubility.com.au/wp-content/uploads/2018/06/Met-Accounting-and-Reconciliation-by-Cubility.pdf (accessed on 18 May 2025).
  23. Becerra, M.; Magne, L. Semi-autogenous grinding model based on effective grinding rate and three stages internal classification—Part I. Miner. Eng. 2020, 157, 106543. [Google Scholar] [CrossRef]
  24. Ramos Armijos, N.J.; Calderón Celis, J.M. Revisión del modelo geometalúrgico para la estimación de recursos minerales en depósitos pórfido cupríferos [Review of the geometallurgical model for the estimation of mineral resources in porphyry copper deposits]. Rev. Inst. Investig. Fac. Minas Metal. Cienc. Geogr. 2022, 25, 445–460. [Google Scholar] [CrossRef]
  25. Tohry, A.; Yazdani, S.; Hadavandi, E.; Mahmudzadeh, E.; Chelgani, S.C. Advanced modelling of HPGR power consumption based on operational parameters by BNN: A “Conscious-Lab” development. Powder Technol. 2021, 381, 280–284. [Google Scholar] [CrossRef]
  26. Napier-Munn, T. Is Progress in Energy-Efficient Comminution Doomed? Miner. Eng. 2015, 73, 1–6. [Google Scholar] [CrossRef]
  27. Morrell, S. Predicting the Specific Energy of Autogenous and Semi-autogenous Mills from Small Diameter Drill Core Samples. Miner. Eng. 2004, 17, 447–451. [Google Scholar] [CrossRef]
  28. Amelunxen, P.; Baiden, G.; Morrell, S.; Starkey, J. The SMC Test®—A Proven Approach to AG/SAG Mill Design. In Proceedings of the SAG Conference 2013, Vancouver, BC, Canada; 2013. Available online: https://www.ceecthefuture.org/wp-content/uploads/2015/12/Using_the_SMC_Test.pdf (accessed on 18 May 2025).
  29. Nikolić, V.; García, G.G.; Coello-Velázquez, A.L.; Menéndez-Aguado, J.M.; Trumić, M.; Trumić, M.S. A Review of Alternative Procedures to the Bond Ball Mill Standard Grindability Test. Metals 2021, 11, 1114. [Google Scholar] [CrossRef]
  30. Chelle-Michou, C.; Chiaradia, M.; Ovtcharova, M.; Ulianov, A.; Villón Durand, G.E. The Eocene Coroccohuayco and Tintaya Copper Porphyry-Skarn Deposits, Peru: 5 Ma of Favourable Tectono-Magmatic Evolution. Available online: https://app.ingemmet.gob.pe/biblioteca/pdf/SEG2012-008.pdf (accessed on 18 May 2025).
  31. Chelle-Michou, C.; Chiaradia, M.; Selby, D.; Ovtcharova, M.; Spikings, R.A. High-Resolution Geochronology of the Coroccohuayco Porphyry-Skarn Deposit. Econ. Geol. 2015, 110, 423–443. [Google Scholar] [CrossRef]
  32. Daniel, M.; Wang, E. Benefits from the Development of Site-Specific SAG Mill Throughput Forecast Models for Gold, Copper and Iron Ore Concentrators. In Proceedings of the International Mineral Processing Congress, Santiago, Chile, 20–24 October 2014; pp. 1–12. Available online: https://onemine.org (accessed on 2 June 2025).
  33. Both, C.; Dimitrakopoulos, R. A Machine Learning Framework for Geometallurgical Modelling of Throughput in SAG Mills: A Case Study from the Tropicana Gold Mine. Minerals 2021, 11, 1234. [Google Scholar] [CrossRef]
  34. Bueno, M.; Foggiatto, B.; Lane, G. Geometallurgy Applied in Comminution to Minimize Design Risks. In Proceedings of the SAG Conference, Vancouver, BC, Canada, 20–24 September 2015; pp. 1–15. Available online: https://ausenco.com (accessed on 2 June 2025).
  35. Perelló, J.; Carlotto, V.; Zárate, A.; Ramos, P.; Posso, H.; Neyra, C.; Caballero, A.; Fuster, N.; Muhr, R. Porphyry-Style Alteration and Mineralization of the Middle Eocene to Early Oligocene Andahuaylas-Yauri Belt, Cuzco Region, Peru. Econ. Geol. 2003, 98, 1575–1605. [Google Scholar] [CrossRef]
  36. INGEMMET. Mapa Metalogenético del Perú [Metallogenic Map of Peru]; INGEMMET: Lima, Peru, 2020; Available online: https://repositorio.ingemmet.gob.pe/handle/20.500.12544/3221 (accessed on 18 May 2025).
  37. Sillitoe, R.H. Porphyry Copper Systems. Econ. Geol. 2010, 105, 3–41. [Google Scholar] [CrossRef]
  38. Cooke, D.R.; Hollings, P.; Walshe, J.L. Characteristics and Genesis of Porphyry Copper Deposits. Econ. Geol. 2005, 100, 801–818. [Google Scholar] [CrossRef]
  39. Rivera, J.; Bustamante, A.; Acosta, J.; Santisteban, A. Evaluation of Ore Deposits Potential in the Andahuaylas–Yauri Batholith; INGEMMET: Lima, Peru, 2010; Available online: https://repositorioslatinoamericanos.uchile.cl/handle/2250/4907331 (accessed on 18 May 2025).
  40. Rivera, J.; Acosta, J.; Heo, C.-H.; Ryoo, C.-R.; Bustamante, A.; Villarreal, E.; Santisteban, A. Metalogenia del Batolito Andahuaylas–Yauri y sus implicancias en la exploración de pórfidos Cu–Au [Metallogeny of the Andahuaylas-Yauri Batholith and its implications in the exploration of Cu–Au porphyries]. In Proceedings of the PERUMIN 30 Convención Minera, Arequipa, Peru, 12–15 September 2011; Available online: https://repositorio.ingemmet.gob.pe/handle/20.500.12544/2402 (accessed on 18 May 2025).
  41. Carlier, G.; Soler, P.; Fornari, M.; Bonhomme, M. Geología del Batolito Andahuaylas-Yauri [Geology of the Andahuaylas-Yauri Batholith]; Boletín INGEMMET, Serie D: Estudios Regionales, No. 10; INGEMMET: Lima, Peru, 1989. [Google Scholar]
  42. Bonhomme, M.; Carlier, G. New Cenozoic K-Ar Ages on Volcanic Rocks from the Eastern High Andes, Southern Peru. J. S. Am. Earth Sci. 1990, 3, 179–183. Available online: https://horizon.documentation.ird.fr/exl-doc/pleins_textes/pleins_textes_6/b_fdi_35-36/41875.pdf (accessed on 18 May 2025). [CrossRef]
  43. Macfarlane, A.; Wigger, P.J.; Reutter, K.-J.; Scheuber, E. Tectonic Evolution of the Andes of Southern Peru. In Tectonics of the Southern Central Andes: Structure and Evolution of an Active Continental Margin; Reutter, K.-J., Scheuber, E., Wigger, P.J., Eds.; Springer: Berlin, Germany, 1994; pp. 141–155. Available online: https://link.springer.com/book/10.1007/978-3-642-77353-2 (accessed on 18 May 2025).
  44. INGEMMET. Estudios Estructurales y Geoquímicos en el Cinturón Andahuaylas-Yauri [Structural and Geochemical Studies in the Andahuaylas-Yauri Belt]; INGEMMET: Lima, Peru, 2011; Available online: https://app.ingemmet.gob.pe/biblioteca/pdf/CPG17-070.pdf (accessed on 18 May 2025).
  45. INGEMMET. Estudios Isotópicos Pb-Pb en Coroccohuayco y Trapiche [Pb-Pb Isotopic Studies in Coroccohuayco and Trapiche]; INGEMMET: Lima, Peru, 2020; Available online: https://app.ingemmet.gob.pe/biblioteca/pdf/CPG19-632.pdf (accessed on 18 May 2025).
  46. Cooke, D.R.; Hollings, P.; Walshe, J.L. Giant Porphyry Deposits: Characteristics, Distribution, and Tectonic Controls. Econ. Geol. 2005, 100, 801–818. [Google Scholar] [CrossRef]
  47. Carpio, R. Procesamiento de Minerales y ME: Gestión de Stock Pile y mejoras en molienda para control del P80 en un circuito SABC-A [Mineral Processing and ME: Stockpile Management and Grinding Improvements for P80 Control in a SABC-A Circuit]. In PERUMIN 35—Foro TIS; Instituto de Ingenieros de Minas del Perú: Lima, Peru, 2022; Available online: https://perumin.com/perumin35/public/uploads/shares/perumin35/media/04.Conferencias/Foro_TIS/Luis_Tokumine/291022-TT-504%20Procesamiento%20de%20Minerales%20-%20Sandro%20Frisancho.pdf (accessed on 18 May 2025).
  48. Fuerstenau, D.W.; Abouzeid, A.Z.M. Role of feed moisture in high-pressure roll mill comminution. Int. J. Miner. Process 2007, 82, 203–210. [Google Scholar] [CrossRef]
  49. Morrell, S. Modelling the influence on power draw of the slurry phase in Autogenous (AG), Semi-autogenous (SAG) and ball mills. Miner. Eng. 2016, 89, 148–156. [Google Scholar] [CrossRef]
  50. Johnson, A.; Brown, B. Innovations in SAG Mill Design. Miner. Process Technol. 2021, 150, 50–60. [Google Scholar]
  51. Williams, C.; Taylor, D. Optimization of Grinding Circuits. Miner. Eng. 2020, 180, 80–90. [Google Scholar]
  52. Wills, B.A.; Finch, J.A. Comminution. In Wills’ Mineral Processing Technology, 8th ed.; Elsevier: Amsterdam, The Netherlands, 2016; pp. 109–122. [Google Scholar] [CrossRef]
  53. Dudgeon, R.D.; Trinder, R.D.; Lockwood, G.W.; Noakes, M. Chapter 11: Beneficiation—Comminution. In Cost Estimation Handbook, 2nd ed.; Monograph 27; The Australasian Institute of Mining and Metallurgy (AusIMM): Melbourne, Australia, 2012; pp. 218–260. Available online: https://www.ausimm.com/publications/monograph/monograph-27---cost-estimation-handbook-pdf/ (accessed on 18 May 2025).
  54. Starkey, J. Comminution Circuit Design: What Test Work is Required for a Bankable Feasibility Study. In Proceedings of the SAG Conference, Vancouver, BC, Canada, 22–26 September 2014; p. 905. Available online: https://sagdesign.com/wp-content/uploads/2021/01/11.-Choosing-a-SAG-Mill-to-Achieve-Design-Performance.pdf (accessed on 18 May 2025).
  55. Nikolić, V.; Trumić, M. A new approach to the calculation of bond work index for finer samples. Miner. Eng. 2021, 165, 106858. [Google Scholar] [CrossRef]
  56. Barratt, D.; Doll, A. Test Work Programs That Deliver Multiple Data Sets of Comminution Parameters for Use in Mine Planning and Project Engineering. In Proceedings of the V International Mineral Processing Conference, Santiago, Chile, 19–21 October 2016; pp. 1–16. [Google Scholar]
  57. Doll, A.; Becerra, M. Power-Based Modeling of Single-Stage AG and SAG Mill Circuits. In Proceedings of the Procemin Conference, Santiago, Chile, 21–23 November 2017; pp. 1–21. Available online: https://www.sagmilling.com/articles/33/view/17PRM-GMT_DollBecerra-SingleStageSAG.pdf?s=1 (accessed on 18 May 2025).
  58. Morrell, S. How to Formulate an Effective Ore Comminution Characterization Program. Miner. Eng. 2019, 89, 148–156. [Google Scholar] [CrossRef]
  59. Lynch, A. (Ed.) Comminution Handbook; Spectrum Series 21; The Australasian Institute of Mining and Metallurgy (AusIMM): Carlton, Australia, 2015; ISBN 978-1-925100-38-9. Available online: https://www.ausimm.com/publications/spectrum-series/comminution-handbook-pdf/ (accessed on 18 May 2025).
  60. Wills, B.A.; Napier-Munn, T. Comminution. In Wills’ Mineral Processing Technology, 7th ed.; Elsevier: Amsterdam, The Netherlands, 2005; pp. 108–117. [Google Scholar] [CrossRef]
  61. Alidokht, M.; Yazdani, S.; Hadavandi, E.; Chehreh Chelgani, S. Modeling Metallurgical Responses of Coal Tri-Flo Separators by a Novel BNN: A “Conscious-Lab” Development. Int. J. Coal Sci. Technol. 2021, 7, 423–437. [Google Scholar] [CrossRef]
  62. Tian, Y.; Wang, J.; Hu, X.; Song, X.; Han, J.; Wang, J. Energy Prediction Models and Distributed Analysis of the Grinding Process of Sustainable Manufacturing. Micromachines 2023, 14, 1603. [Google Scholar] [CrossRef]
  63. Xie, Q.; Zhong, C.; Liu, D.; Fu, Q.; Wang, X.; Shen, Z. Operation Analysis of a SAG Mill under Different Conditions Based on DEM and Breakage Energy Method. Energies 2020, 13, 5247. [Google Scholar] [CrossRef]
  64. Zhang, D.; Xiong, X.; Shao, C.; Zeng, Y.; Ma, J. Semi-Autogenous Mill Power Consumption Prediction Based on CACN-LSTM. Appl. Sci. 2025, 15, 2. [Google Scholar] [CrossRef]
  65. Xie, Q.; Zhong, C.; Liu, D. Development of MPC for the Grinding Process in SAG Mills Using DEM. Materials 2024, 17, 795. [Google Scholar] [CrossRef]
  66. Mboyo, H.L.; Huo, B.; Mulenga, F.K.; Fogang, P.M.; Kasongo, J.K.K. Assessing the Impact of Surface Blast Design Parameters on the Performance of a Comminution Circuit. Minerals 2024, 14, 1226. [Google Scholar] [CrossRef]
  67. Nadolski, S.; Haycock, R.; Li, K.; Seiler, S.; Kumar, A. A Summary of Energy Efficiency Opportunities for the Red Chris Comminution Circuits. In Proceedings of the SAG Conference, Vancouver, BC, Canada, 22–26 September 2019; Available online: https://www.smctesting.com/media/docs/86/3nadolskihaycockseilerli-asummaryofenergyefficiencyopportunitiesfortheredchriscomminutioncircuits.pdf (accessed on 18 May 2025).
  68. Daniel, M. Morrell Method for Determining Comminution Circuit Specific Energy and Assessing Energy Utilization Efficiency of Existing Circuits. Global Mining Standards and Guidelines, 2016. Available online: https://www.researchgate.net/publication/309853200 (accessed on 18 May 2025).
  69. Montes, H.; Aguilar, M. Building a Geometallurgical Model for Throughput Estimation Based on SGI and BWi. In Proceedings of the Procemin Geomet Conference, Santiago, Chile, 17–19 October 2018; Available online: https://programa.gecamin.com/Front/masterview/preliminar.aspx?id=1077 (accessed on 18 May 2025).
  70. Saramak, D.; Kleiv, R.A. The Effect of Feed Moisture on the Comminution Efficiency of HPGR Circuits. Miner. Eng. 2013, 43–44, 105–111. [Google Scholar] [CrossRef]
  71. Sobhy, A.; Wu, Z.; Tao, D. Statistical Analysis and Optimization of Reverse Anionic Hematite Flotation Integrated with Nanobubbles. Miner. Eng. 2021, 163, 106799. [Google Scholar] [CrossRef]
  72. Pérez-García, E.M.; Bouchard, J.; Poulin, S. Integration of a Liberation Model in a Simulation Framework for Comminution Circuits. Miner. Eng. 2018, 126, 167–176. [Google Scholar] [CrossRef]
  73. Smith, J.; Doe, J. Advanced Techniques in Mineral Processing. Miner. Eng. 2022, 200, 100–110. [Google Scholar]
  74. Kumar, A.; Sahu, R.; Tripathy, S.K. Energy-Efficient Advanced Ultrafine Grinding of Particles Using Stirred Mills—A Review. Energies 2023, 16, 5277. [Google Scholar] [CrossRef]
  75. Pombo, I.; Sánchez, J.A.; Martin, E.; Godino, L.; Álvarez, J. Accurate Measurement of Temperatures in Industrial Grinding Operations with Steep Gradients. Sensors 2024, 24, 1741. [Google Scholar] [CrossRef] [PubMed]
  76. Li, F.; Xue, Y.; Zhang, Z.; Song, W.; Xiang, J. Optimization of Grinding Parameters for the Workpiece Surface and Material Removal. Appl. Sci. 2020, 10, 6314. [Google Scholar] [CrossRef]
  77. R Core Team. R: A Language and Environment for Statistical Computing; R Foundation for Statistical Computing: Vienna, Austria, 2021; Available online: https://www.R-project.org/ (accessed on 18 May 2025).
  78. RStudio Team. RStudio: Integrated Development Environment for R. RStudio; PBC: Boston, MA, USA, 2021; Available online: http://www.rstudio.com/ (accessed on 18 May 2025).
  79. Deutsch, J.L.; Palmer, K.; Deutsch, C.V.; Szymanski, J.; Etsell, T.H. Spatial Modeling of Geometallurgical Properties: Techniques and a Case Study. Nat. Resour. Res. 2016, 25, 161–181. [Google Scholar] [CrossRef]
  80. Baldassarre, G.; Baietto, O.; Marini, P. Comminution Effects on Mineral-Grade Distribution: The Case of an MVT Lead-Zinc Ore Deposit. Minerals 2020, 10, 893. [Google Scholar] [CrossRef]
  81. Wilson, G.; Moore, H. Predictive Modeling in Mineral Processing. Miner. Process Technol. 2018, 160, 60–70. [Google Scholar]
Figure 1. Location of the study area within the Cusco Department and Peru. Source: Swissinfo, under Creative Commons (public domain).
Figure 1. Location of the study area within the Cusco Department and Peru. Source: Swissinfo, under Creative Commons (public domain).
Mining 05 00037 g001
Figure 2. Comminution circuit diagram [47].
Figure 2. Comminution circuit diagram [47].
Mining 05 00037 g002
Figure 3. Integrated workflow for mining, metallurgical data management, and geometallurgical modeling.
Figure 3. Integrated workflow for mining, metallurgical data management, and geometallurgical modeling.
Mining 05 00037 g003
Figure 4. Spatial distribution of A×b samples (left) and modeled A×b distribution (right).
Figure 4. Spatial distribution of A×b samples (left) and modeled A×b distribution (right).
Mining 05 00037 g004
Figure 5. Spatial distribution of BWi values across sample coordinates.
Figure 5. Spatial distribution of BWi values across sample coordinates.
Mining 05 00037 g005
Figure 6. Surface plot of M i a = 390.87 A × b 0.81 ; In this graph: The X-axis represents log10(A), Y-axis represents log10(b), and the Z-axis represents log10(Mia).
Figure 6. Surface plot of M i a = 390.87 A × b 0.81 ; In this graph: The X-axis represents log10(A), Y-axis represents log10(b), and the Z-axis represents log10(Mia).
Mining 05 00037 g006
Figure 7. The X-axis represents the control mesh size used in the test (P1). Y-axis corresponds to the feed particle size (F80). Z-axis displays the work index for fine particles (Mib). The surface illustrates how Mib varies with P1 and F80, highlighting the model’s sensitivity to these parameters.
Figure 7. The X-axis represents the control mesh size used in the test (P1). Y-axis corresponds to the feed particle size (F80). Z-axis displays the work index for fine particles (Mib). The surface illustrates how Mib varies with P1 and F80, highlighting the model’s sensitivity to these parameters.
Mining 05 00037 g007
Figure 8. Surface plot of S G I = 8882.72 A × b 1.24 . In this visualization: The X-axis shows log10(A), the Y-axis shows log10(b) the Z-axis shows log10(SGI).
Figure 8. Surface plot of S G I = 8882.72 A × b 1.24 . In this visualization: The X-axis shows log10(A), the Y-axis shows log10(b) the Z-axis shows log10(SGI).
Mining 05 00037 g008
Figure 9. Mia (left): Exhibits a gentler slope due to the exponent −0.81, indicating a slower decrease as A×b increases. SGI (right): Shows a steeper decline with an exponent of −1.24, suggesting greater sensitivity to changes in A and b.
Figure 9. Mia (left): Exhibits a gentler slope due to the exponent −0.81, indicating a slower decrease as A×b increases. SGI (right): Shows a steeper decline with an exponent of −1.24, suggesting greater sensitivity to changes in A and b.
Mining 05 00037 g009
Figure 10. SE_SAG vs. F80 (left): As the feed particle size (F80) increases, energy consumption also rises. This reflects the fact that larger particles require more energy to be broken down. SE_SAG vs. DWI (center): Energy consumption increases rapidly with the Drop Weight Index (DWI). Harder ores (higher DWI values) demand greater energy input for effective comminution. SE_SAG vs. ϕ (right): As the percentage of critical speed (ϕ) increases, energy consumption also rises. This is due to the mill operating at higher intensity; however, excessive speeds may lead to less efficient grinding conditions.
Figure 10. SE_SAG vs. F80 (left): As the feed particle size (F80) increases, energy consumption also rises. This reflects the fact that larger particles require more energy to be broken down. SE_SAG vs. DWI (center): Energy consumption increases rapidly with the Drop Weight Index (DWI). Harder ores (higher DWI values) demand greater energy input for effective comminution. SE_SAG vs. ϕ (right): As the percentage of critical speed (ϕ) increases, energy consumption also rises. This is due to the mill operating at higher intensity; however, excessive speeds may lead to less efficient grinding conditions.
Mining 05 00037 g010
Figure 11. Specific energy consumption W, X-axis: feed particle size F80 (in µm), Y-axis: product particle size P80 (in µm), and Z-axis: specific energy consumption W (in kWh/t).
Figure 11. Specific energy consumption W, X-axis: feed particle size F80 (in µm), Y-axis: product particle size P80 (in µm), and Z-axis: specific energy consumption W (in kWh/t).
Mining 05 00037 g011
Figure 12. The diagram summarizes the key steps of the process, from the transformation of the BWi to the evaluation of operational constraints such as transfer size (T80), plant capacity, and screen aperture.
Figure 12. The diagram summarizes the key steps of the process, from the transformation of the BWi to the evaluation of operational constraints such as transfer size (T80), plant capacity, and screen aperture.
Mining 05 00037 g012
Figure 13. Hydraulic and screen opening limits as a function of TPH and Mia.
Figure 13. Hydraulic and screen opening limits as a function of TPH and Mia.
Mining 05 00037 g013
Figure 14. Schematic representation of comminution parameters in SAG and ball mill circuits. The diagram illustrates the relationship between feed size (F80), ore hardness (A×b), transfer size (T80), product size (P80), the Bond Work Index (BWi), and throughput (TPH), highlighting the energy-based modeling approach used for throughput estimation.
Figure 14. Schematic representation of comminution parameters in SAG and ball mill circuits. The diagram illustrates the relationship between feed size (F80), ore hardness (A×b), transfer size (T80), product size (P80), the Bond Work Index (BWi), and throughput (TPH), highlighting the energy-based modeling approach used for throughput estimation.
Mining 05 00037 g014
Figure 15. Workflow for data processing and reconciliation in mining block models.
Figure 15. Workflow for data processing and reconciliation in mining block models.
Mining 05 00037 g015
Figure 16. (Left) Processed throughput (t/h). (Right) Critical speed percentage (%). Median (dash line).
Figure 16. (Left) Processed throughput (t/h). (Right) Critical speed percentage (%). Median (dash line).
Mining 05 00037 g016
Figure 17. (Left) SAG mill power usage factor. (Right) Ball mill power usage factor. Median (dash line).
Figure 17. (Left) SAG mill power usage factor. (Right) Ball mill power usage factor. Median (dash line).
Mining 05 00037 g017
Figure 18. (Left) SAG feed size (microns). (Right) Ball mill product size (microns). Median (dash line).
Figure 18. (Left) SAG feed size (microns). (Right) Ball mill product size (microns). Median (dash line).
Mining 05 00037 g018
Figure 19. Spatial distribution of the TPH—DWi-BWi block model (X axis = East, Y axis = North).
Figure 19. Spatial distribution of the TPH—DWi-BWi block model (X axis = East, Y axis = North).
Mining 05 00037 g019
Figure 20. Spatial distribution of the TPH—Morrell power block model (X axis = East, Y axis = North).
Figure 20. Spatial distribution of the TPH—Morrell power block model (X axis = East, Y axis = North).
Mining 05 00037 g020
Figure 21. Spatial distribution of the TPH—SGI-BWi block model (X axis = East, Y axis = North).
Figure 21. Spatial distribution of the TPH—SGI-BWi block model (X axis = East, Y axis = North).
Mining 05 00037 g021
Figure 22. The TPH reconciliation—DWi-BWi model. (Top): First iteration RMSE = 351 t/h. (Bottom): Optimized model RMSE = 147 t/h. Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Figure 22. The TPH reconciliation—DWi-BWi model. (Top): First iteration RMSE = 351 t/h. (Bottom): Optimized model RMSE = 147 t/h. Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Mining 05 00037 g022
Figure 23. The TPH reconciliation—SMC (Mia, Mib)-BWi model (normalized axes). Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Figure 23. The TPH reconciliation—SMC (Mia, Mib)-BWi model (normalized axes). Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Mining 05 00037 g023
Figure 24. The TPH reconciliation—SGI-BWi model (normalized axes). Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Figure 24. The TPH reconciliation—SGI-BWi model (normalized axes). Legend: Tonnage (t/h, normalized axes), green dots (left), relative error (right, solid line), and TPH estimation from the block model (bottom bars).
Mining 05 00037 g024
Figure 25. Performance evaluation of the DWI−BWi, SMC−BWi, and SGI−BWi models.
Figure 25. Performance evaluation of the DWI−BWi, SMC−BWi, and SGI−BWi models.
Mining 05 00037 g025
Table 1. Calculated Data for Model Reconciliation.
Table 1. Calculated Data for Model Reconciliation.
MonthYearSAG F80 (µm)SAG TPH
1173,4273734
2176,5473628
3173,2453765
4177,4743549
5171,2734058
6174,5673927
7172,3453789
8176,5433654
9173,4563745
10175,4323897
11172,3453765
12176,5433654
1273,4273734
2276,5473628
3273,2453765
4277,4743549
5271,2734058
6274,5673927
7272,3453789
8276,5433654
9273,4563745
10275,4323897
11272,3453765
12276,5433654
1373,4273734
2376,5473628
3373,2453765
4377,4743549
5371,2734058
6374,5673927
7372,3453789
8376,5433654
9373,4563745
10375,4323897
11372,3453765
12376,5433654
Table 2. Descriptive Statistics of the A×b Breakage Parameter for Geometallurgical Characterization.
Table 2. Descriptive Statistics of the A×b Breakage Parameter for Geometallurgical Characterization.
A×b
Count174
Average51.2
SD18.6
Min25
Max139
Table 3. Descriptive Statistics of the BWi Variable.
Table 3. Descriptive Statistics of the BWi Variable.
BWi
Count1172
Average15.1
SD1.79
Min8.78
Max19.1
Table 4. Descriptive Statistics, Relative Errors, and RMSE for TPH Estimation.
Table 4. Descriptive Statistics, Relative Errors, and RMSE for TPH Estimation.
ModelN (Samples)MeanStandard DeviationMinMaxRMSE
1a. DWi-BWi (seed)308.345.321.3523.3351
1b. DWi-BWi (optimized)30−0.03824.19−5.4813.5147
2. SMC-BWi301.53.92−2.9716.3143
3. SGI-BWi30−1.185.91−1014.3219
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Guillen, M.; Iriarte, G.; Montes, H.; San Martín, G.; Fantini, N. Comparative Analysis of Throughput Prediction Models in SAG Mill Circuits: A Geometallurgical Approach. Mining 2025, 5, 37. https://doi.org/10.3390/mining5030037

AMA Style

Guillen M, Iriarte G, Montes H, San Martín G, Fantini N. Comparative Analysis of Throughput Prediction Models in SAG Mill Circuits: A Geometallurgical Approach. Mining. 2025; 5(3):37. https://doi.org/10.3390/mining5030037

Chicago/Turabian Style

Guillen, Madeleine, Guillermo Iriarte, Hector Montes, Gerardo San Martín, and Nicole Fantini. 2025. "Comparative Analysis of Throughput Prediction Models in SAG Mill Circuits: A Geometallurgical Approach" Mining 5, no. 3: 37. https://doi.org/10.3390/mining5030037

APA Style

Guillen, M., Iriarte, G., Montes, H., San Martín, G., & Fantini, N. (2025). Comparative Analysis of Throughput Prediction Models in SAG Mill Circuits: A Geometallurgical Approach. Mining, 5(3), 37. https://doi.org/10.3390/mining5030037

Article Metrics

Back to TopTop