1. Introduction
In recent years, with the increasingly serious environmental pollution and aggravation of the global energy crisis, developing renewable energy vigorously has become an inevitable choice of mankind. Wind energy and solar energy, as reliable and promising forms of renewable energy, have been developing swiftly worldwide. It is noteworthy that, in 2016, China’s total installed capacity of wind power and solar power both ranked first in the world. However, at the same time, the phenomenon of power curtailment is becoming increasingly prominent since wind and solar energy are characterized by volatility and intermittency [
1]. This kind of phenomenon has brought humans huge economic loss and restricted the development of renewable energy. One of the main causes of this phenomenon is that the current peak shaving capacity of the power system is seriously poor. The current power source structure in China is unreasonable, and the thermal power as the main structure of the power source accounts for 71.1%. However, the load response of thermal power is slow, resulting in the shortage of its peak capacity.
Energy storage systems are one of the possible solutions for mitigating the effects of intermittent renewable resources [
2]. Among all energy storage technologies, pumped hydro energy storage (PHES) technology is the most widely used. The share of various storage technologies in the global electricity storage system is shown in
Figure 1. Although a lot of forms of energy storage technology have been developed, the PHES technology accounted for the energy storage of absolute dominance. PHES is now one of the most mature and cost-effective technologies since water lifting devices have been invented, used, and improved by humans, for thousands of years [
1]. This technique uses electricity produced by other power stations to pump water up to the upper reservoir when the energy demand is low, and release the water back down to the lower reservoir to generate electricity when the energy demand is high [
3]. Thanks to the fast response ability of PHESPs, a huge push to build them will ensure that electricity production matches demands at all times.
In June 2017, the installed capacity of PHESPs in China reached 27.73 million kW, surpassed Japan, and became the biggest capacity of PHESP in the world. But despite all that, the proportion of pumped storage in electric power systems in China is less than 2%. Thus, lately, the “13th Five-Year Plan for Electric Power Development” released by the National Energy Administration (NEA) made it clear that the installed capacity of the new pumped hydro energy storage plant must arrive at 60 million kWh by 2020. There is no doubt that the PHES industry is in an important period of strategic opportunities for accelerated development.
In recent years, the existing literature on various aspects of PHESP has become much more enriched. Rogeau et al. [
1] proposed a generic method able to evaluate the potential of small-PHESP over a large geographical zone. Gimeno-Gutierrez and Lacal-Arantegui [
4] assessed a PHESP potential based on two existing reservoirs in Europe by developing and applying a GIS-based software model. Petrakopoulou et al. [
5] conducted a simulation and analysis of a stand-alone solar-wind and PHESP in the Aegean Sea. Pérez-Díaz et al. [
6] aimed at assessing the contribution of pumped-hydro energy storage to reduce the scheduling costs of hydrothermal power systems with high wind penetration, which may yield unrealistic results. Pérez-Díaz and Chazarra [
7] reviewed the current trends in the PHESP operation, and presented the main challenges faced by PHESP operators. Yang and Jackson [
8] analyzed the opportunities and barriers to PHESP in the United States. By contrast, there has been relatively little research on the site selection of PHESP. For example, Lu and Wang [
9] provided promising locations of the PHESPs through Geographic Information Science (GIS) analyses. Kucukali [
10] found the most suitable existing hydropower reservoirs for the development of PHS by using the multi-criteria scoring technique. Also, Connolly et al. [
11] developed a computer program to locate potential sites for pumped hydroelectric energy storage. However, in the entire life cycle of the renewable energy plant, the site selection is important and determines the sustainable development ability and socio-economic values of the power plant [
12]. At the meantime, identifying suitable sites for PHESP is a complex task since many potential site alternatives are feasible. Thus, by all appearances, the site selection of PHESP is a valuable research issue.
A number of conflicting criteria need to be taken into account simultaneously in the process of PHESP site selection. So, the site selection of PHESP can be defined as a MCDM problem. MCDM is a well-known branch of decision-making, which aims to find the most suitable solutions from a set of alternatives under multiple criteria conditions [
13]. Nevertheless, existing methods for solving MCDM problems that are not applicable for the site selection of PHESP, which are mainly reflected in the loss of information. In detail, the complexity of PHESP site selection is much higher than other MCDM problems since it is very strict with topography and geomorphology. Also, many data are impossible to obtain, and they are also inaccurate. So, in such a complex decision-making environment, the best way to give a reasonable representation of the criteria value and preserve the integrity of the original decision information is very difficult to establish.
Therefore, this paper tries to select the optimal PHESP site and handle the problem of information loss in this process. Firstly, an evaluation criteria system of PHESP site selection is established. Then, according to the properties of the identified criteria, we divide them into three categories: quantitative criteria that can be measured accurately, quantitative criteria that cannot be measured accurately, and qualitative criteria. The values of the three categories are represented by CNVs, TIFNs, and 2DULVs, respectively. In this way, the criteria values with different natures can be better described. Furthermore, based on Hamming distance, the VIKOR method is proposed to rank the PHESP sites. This method is particularly useful for those problems for which the values of the alternatives are not represented by the same units, since there is no need to translate different forms of decision information. The innovations of this paper are as follows: (1) a comprehensive evaluation criteria system is established; (2) an extended VIKOR-based MCDM approach with heterogeneous criteria values comprising CNVs, TIFNs, and 2DULVs is proposed.
2. Literature Review
The values of the criteria involved in site selection not only contain objective quantitative statistical data, but include some subjective judgment data given by DMs with their knowledge and experience. Thus, using a single form of decision information makes it difficult to meet the requirement of site selection decision-making. Most scholars have recognized this problem, and utilized different forms of decision information to represent criteria of different characteristics. Among various information forms, numerical numbers, interval numbers, linguistic variables, and fuzzy numbers are the most commonly used forms. Wu and Chen [
14] used CNVs and linguistic variables (LVs) to describe the values of criteria involved in waste-to-energy plant site selection. Wu and Geng [
15] applied CNVs and LVs to model the values of criteria involved in solar thermal power plant site selection. Later, both the two studies converted the CNVs into the LVs for convenience of calculation. Sánchez-Lozano et al. [
16] utilized CNVs, LVs, and triangular fuzzy numbers (TFNs) to represent the values of criteria involved in onshore wind farm site selection, and then, the CNVs and LVs were both converted into the TIFNs. Wu and Zhang [
17] utilized CNVs and LVs to represent the values of criteria involved in offshore wind power station site selection, and transformed both the CNVs and the LVs into intuitionistic fuzzy numbers (IFNs). Also, Wu et al. [
18] used CNVs and IFNs in the process of wind farm project plan selection, and then, the CNVs were transformed into the IFNs. In addition, some extended forms of LVs have been also applied, such as 2-tuple linguistic variables. CNVs and 2-tuple linguistic variables are used in the process of low-speed wind farm site selection; after that, both of them are transformed into 2-tuple linguistic variables [
19].
The contribution of the above literatures in the field of site selection is understandable. However, there are some problems that have not been well solved. Firstly, for qualitative criteria, their values are generally assessed by DMs with their knowledge and experience. Due to the complexity of PHESP site selection, some DMs may not be very confident about their assessment. In other words, the assessments given by DMs are not very reliable in some cases. However, the current forms of decision information, such as the 2-tuple linguistic variables, have not taken this into account. Secondly, the different forms of decision information in the above studies have been unified into one kind of decision information. Nevertheless, information loss will inevitably occur in such a unification process.
As for the first question, it is necessary to introduce the 2DUIVs. The 2-dimension linguistic variables (2DLVs) were proposed by Zhu et al. [
20] in 2009 and include two common linguistic labels to precisely assess alternatives with linguistic information. One dimension is used for describing the evaluation result of alternatives provided by the DM, and the other is used for describing the self-assessment of the DM on the reliability of the given evaluation result. However, due to time pressure, and lack of knowledge and information processing capabilities, the evaluation information provided by DMs may not match any of the original linguistic phrase, and it may be between two linguistic phrases [
21]. For this reason, Liu and Zhang [
22] extended 2DIVs to 2DULVs, and developed a method to deal with the MCDM problem in which the criteria values take the form of 2-dimension uncertain linguistic information. Naturally, the 2DUIVs spread in the MCDM field [
23,
24,
25]. Thus, introducing the 2DULVs to represent the values of qualitative criteria involved in PHESP site selection is a meaningful work, which reflects more accurately the assessment of DM on alternatives and decreases the information loss.
To solve the second problem, some distance-based techniques play an important role. Among them, the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) approach and the VIKOR approach are the most commonly used techniques. They are particularly useful for those problems for which the values of the criteria are not represented by the same forms. The core idea of them is to calculate the relative gaps between each alternative and the optimal alternative by means of distance formula associated with hybrid criteria. In view of this, Wu and Xu [
26] studied the site selection problem of the tidal power plant with the criteria value as numerical numbers, interval numbers, and random numbers; then, a rank method based on TOPSIS was proposed. Matsui et al. [
27] presented a modified VIKOR method based on numerical numbers, fuzzy numbers, interval numbers, and linguistic variables. Sun and Liu [
28] handled with numerical numbers, fuzzy numbers, interval numbers, and linguistic variables simultaneously to evaluate the candidate power system restoration alternatives based on an extended VIKOR method. However, it have been proved that the TOPSIS approach cannot reflect the closeness of the alternatives to positive and negative ideal solutions [
29]. In contrast, the VIKOR method can overcome the shortcomings of the TOPSIS approach; in addition, it considers a maximum group utility and a minimum of individual regret simultaneously and takes into account the subjective preference of DMs [
30,
31]. In recent years, the research on the extension and application of VIKOR methods has attracted the attention of some scholars. For example, Mousavi and Jolai [
32] used a stochastic VIKOR to evaluate and rank probability distributions for each alternative. Liu and You [
33] used a fuzzy VIKOR for failure mode and effects analysis; triangular fuzzy numbers are preferred to express linguistic evaluations. Mokhtarian and Sadi-Nezhad [
34] used fuzzy VIKOR on interval-valued fuzzy numbers for facility site selection problems. You and You [
35] used the linguistic VIKOR method for supplier selection; the attributes are expressed with 2-tuple linguistic variables. As can be seen from the above, the VIKOR method has been successfully applied in various fields. Therefore, this work tries to adopt the VIKOR method to rank candidate PHESP alternatives.
5. An Extended, VIKOR-Based MCDM Approach with Heterogeneous Information
Consider a MCDM problem with three types of values: CNVs, TIFNs, and 2DULVs. The alternatives set is , and the criteria set is . Among it, the criteria set with CNVs is , TIFNs is , and 2DULVs is . A CNV is expressed as , a TIFN is expressed as , and a 2DULV is expressed as . The pre-defined linguistic assessment sets are and .
Step 1: Normalize decision matrix.
This step performs the normalization process of the decision matrix. The data in the decision matrix are normalized to unify different measurement scales. The normalized matrix
, composed by a mixture of CNVs, TIFNs, and 2DULVs, can be expressed as follows:
The normalized values for benefit- and cost-related criteria are calculated using the following equations:
Step 2: Determine PIS and NIS, respectively:
where
is PIS and
is NIS;
denote the set of CNVs, TIFNs and 2DULVs, respectively.
Step 3: Calculate the separation measures
The calculation of the separation of each alternative with respect to the PIS and NIS, respectively, based on the Hamming distance. The distance between two CNVs is an absolute value of difference, and the distance between two TIFNs and 2DULVs is calculated according to Formulas (1) and (2).
Step 4: Calculate criteria weight
Reasonable weights for decision criteria may be obtained by many techniques, one of which is the AHP [
41]. It utilizes pair-wise comparisons for a set of criteria to judge the relative importance between one attribute and another. In this context, the fundamental “1–9 scale” defined by Saaty is employed for DMs to evaluate the priority score. The judgment matrix is constructed as follows:
where the element
indicates representation of relative importance between criteria
and
.
Step 5: Calculate the values of
,
, and
by the relations:
where
is the group utility of alternative;
is the individual regret of the worst index of
;
is the weight of majority criteria; and
is the weight of individual regret.
Step 6: Rank the alternatives and obtain the evaluation results.
Rank the alternatives by in an increasing order. The new order is expressed as . If satisfies the conditions and , is considered as the optimal alternative with the minimum .