Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction
Abstract
1. Introduction
2. Methods
2.1. Description of Cable Cranes’ Operation Characteristics
2.2. Cable Crane Trajectory Planning Model with Smooth Hoisting
2.2.1. Model Framework and Strategy
2.2.2. Path Planning
- Environment map building
- 2.
- Optimized obstacle-avoidance path based on improved A* algorithm
- Node Deletion Criterion: If the current node was colinear with its adjacent nodes, or if the interior angle formed with them satisfied and the direct line between adjacent nodes was free of obstacles, the node was deemed redundant and removed. After each modification, the updated path was re-traversed to refresh the node list.
- Node Addition Criterion: If the angle between the current node and its adjacent segments exceeded a threshold angle (), a new node was inserted by shifting the midpoint of the segment by grid cells () along the normal line. Based on the direction of the path, the side with fewer obstacles was automatically selected.
2.2.3. Velocity Planning
- Improved S-curve function
- 2.
- Construction of velocity curve function based on multi-segment polynomials
2.2.4. Trajectory Optimization Based on Orthogonal Experiments
3. Model Validation
3.1. Offline Global Baseline Trajectory Planning
3.1.1. Results of Offline Global Baseline Trajectory Planning
3.1.2. Comparison with Trapezoidal Velocity Planning
3.1.3. Analysis of the Influence of the Traction Hoisting Mechanism’s Maximum Velocity on the Cable Cranes’ Hoisting Process
3.2. Real-Time Trajectory Planning for Obstacle Avoidance
4. Discussion
5. Conclusions
- (1)
- To address the challenge of balancing efficiency and real-time responsiveness in conventional planning, a hierarchical strategy of offline global baseline planning and online real-time local adjustment is proposed. In the offline stage, a static environmental map is constructed from a BIM model to generate the global baseline trajectory. In the online stage, real-time monitoring data are used to rapidly adjust the local trajectory. The total computation time for optimal trajectory generation is only 0.08 s (offline) and 0.01 s (online), satisfying real-time obstacle avoidance requirements in complex environments and overcoming the limitation of static paths in adapting to dynamic obstacles.
- (2)
- The proposed path–velocity decoupling model substantially enhances trajectory performance. In geometric path planning, an improved A* algorithm is adopted to reduce redundant nodes and lower the frequency of changes in direction. In velocity planning, a simplified S-curve is designed for long-distance composite motions. At the same time, polynomial interpolation is employed for short-range scenarios, effectively suppressing bucket oscillations and ensuring smooth velocity.
- (3)
- Engineering trials confirm that the model is well-adapted to cable crane dynamics and produces geometrically smooth trajectories. Compared with conventional trapezoidal velocity planning, the maximum bucket swing amplitude during composite motion is reduced by 40.78%, with only a minor increase in composite motion duration, resulting in negligible impact on single-cycle tasks. In real-time obstacle avoidance scenarios, the maximum bucket swing amplitude is reduced by 30.48% relative to an emergency stop strategy, demonstrating the method’s effectiveness in safeguarding operational safety and efficiency.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Zhang, X.; Xiao, J.; Lin, Y.; Zhao, D. Valley Deformation Analysis for a High Arch Dam in Jinsha River, China. Arab. J. Geosci. 2021, 14, 1374. [Google Scholar] [CrossRef]
- Jin, L.; Shen, J.; Chen, S.; Chen, Y.; Shao, B.; Liang-hai, J.I.N.; Jia-li, S.; Shu, C.; Yun, C.; Bo, S. Optimal Scheduling Method of Multi-Cable Crane Operation for Dam Jump Pouring. China Rural. Water Hydropower 2023, 3, 186–190. [Google Scholar]
- Wang, H.; Yang, Q.; Liu, Q.; Zhao, C.; Zhou, W. Automatic Planning for Cable Crane Operations in Concrete Dam Construction. J. Constr. Eng. Manag. 2024, 150, 04024177. [Google Scholar] [CrossRef]
- Wang, R. Key Technologies in the Design and Construction of 300m Ultra-High Arch Dams. Engineering 2016, 2, 350–359. [Google Scholar] [CrossRef]
- Liang, Z.; Peng, J.; Zhao, C.; Zhou, H.; Li, D.; Zhou, Y.; Liu, Q.; Li, X.; Zhang, C.; Wang, F. Modelling and Simulation of the Block Pouring Construction System Considering Spatial–Temporal Conflict of Construction Machinery in Arch Dams. Sci. Rep. 2025, 15, 28236. [Google Scholar] [CrossRef]
- Shu, C.; Yue, Y.; Ya, T.; Jiali, Z. Simulation of Spatial Conflict during Cross Operation in Dam Construction. China Saf. Sci. J. 2020, 29, 63. [Google Scholar]
- Chen, S.; Tian, Y.; Jin, L.; Xiang, L. Estimating the Frequency of Exposure to Uncertain Hazards: Impact of Wind Conditions on Concrete Dam Construction. J. Constr. Eng. Manag. 2020, 147, 04020167. [Google Scholar] [CrossRef]
- Dashti, M.S.; RezaZadeh, M.; Khanzadi, M.; Taghaddos, H. Integrated BIM-Based Simulation for Automated Time-Space Conflict Management in Construction Projects. Autom. Constr. 2021, 132, 103957. [Google Scholar] [CrossRef]
- Wang, F.; Zhong, G.; Fan, Q.; Xu, J.; Gao, S.; Yang, N. High Arch Dam Cable Transport Efficiency and Safety Analysis Based on Real-Time Monitoring Technology. IOP Conf. Ser. Earth Environ. Sci. 2019, 218, 012078. [Google Scholar] [CrossRef]
- Rebmeister, M.; Schenk, A.; Weisgerber, J.; Westerhaus, M.; Hinz, S.; Andrian, F.; Vonié, M. Ground-Based InSAR and GNSS Integration for Enhanced Dam Monitoring. Appl. Geomat. 2025, 17, 393–400. [Google Scholar] [CrossRef]
- Casserly, C.M.; Turner, J.N.; O’ Sullivan, J.J.; Bruen, M.; Magee, D.; Coiléir, S.O.; Kelly-Quinn, M. Coarse Sediment Dynamics and Low-Head Dams: Monitoring Instantaneous Bedload Transport Using a Stationary RFID Antenna. J. Environ. Manag. 2021, 300, 113671. [Google Scholar] [CrossRef]
- Shao, C.; Zheng, S.; Xu, Y.; Gu, H.; Qin, X.; Hu, Y. A Visualization System for Dam Safety Monitoring with Application of Digital Twin Platform. Expert Syst. Appl. 2025, 271, 126740. [Google Scholar] [CrossRef]
- Wu, H.; Tao, J.; Li, X.; Chi, X.; Li, H.; Hua, X.; Yang, R.; Wang, S.; Chen, N. A Location Based Service Approach for Collision Warning Systems in Concrete Dam Construction. Saf. Sci. 2013, 51, 338–346. [Google Scholar] [CrossRef]
- Wang, D.; Wang, X.; Ren, B.; Wang, J.; Zeng, T.; Kang, D.; Wang, G. Vision-Based Productivity Analysis of Cable Crane Transportation Using Augmented Reality–Based Synthetic Image. J. Comput. Civ. Eng. 2021, 36, 04021030. [Google Scholar] [CrossRef]
- Wang, H.; Yang, Q.; Liu, Q.; Zhao, C.; Zhang, H. Productivity Analysis of Cable Crane Transportation Based on Visual Tracking and Pattern Recognition. J. Tsinghua Univ. Sci. Technol. 2024, 64, 1646–1657. [Google Scholar]
- Wu, H.; Yin, Y.; Shi, W.; Clarke, K.C.; Miao, Z. Optimizing GPS-Guidance Transit Route for Cable Crane Collision Avoidance Using Artificial Immune Algorithm. GPS Solut. 2016, 21, 823–834. [Google Scholar] [CrossRef]
- Huang, Z.; Wu, H. Overview of Trajectory Planning Methods for Robot Systems. In Proceedings of the 2021 IEEE International Conference on Power, Intelligent Computing and Systems (ICPICS), Shenyang, China, 29–31 July 2021; pp. 375–381. [Google Scholar]
- Zhao, Y.; Lin, H.-C.; Tomizuka, M. Efficient Trajectory Optimization for Robot Motion Planning. In Proceedings of the 2018 15th International Conference on Control, Automation, Robotics and Vision (ICARCV), Singapore, 18–21 November 2018; pp. 260–265. [Google Scholar]
- Bouzar Essaidi, A.; Haddad, M.; Lehtihet, H.E. Minimum-Time Trajectory Planning under Dynamic Constraints for a Wheeled Mobile Robot with a Trailer. Mech. Mach. Theory 2022, 169, 104605. [Google Scholar] [CrossRef]
- Ma, J.; Gao, S.; Yan, H.; Lv, Q.; Hu, G. A New Approach to Time-Optimal Trajectory Planning with Torque and Jerk Limits for Robot. Robot. Auton. Syst. 2021, 140, 103744. [Google Scholar] [CrossRef]
- Hu, Y.; Sang, M.; Duan, H. A Novel Trajectory Planning Approach with Torque and Jerk Constraints Based on Polynomial Interpolation Profile and Adaptive Iteration. CIRP J. Manuf. Sci. Technol. 2025, 60, 277–295. [Google Scholar] [CrossRef]
- Yang, J.; Wang, J.; Li, J.; Meng, X.; Jiang, X.; Lu, C. Sobol Sequence RRT* and Numerical Optimal Joint Algorithm-Based Automatic Parking Trajectory Planning of Four-Wheel Steering Vehicles. Robot. Auton. Syst. 2025, 186, 104909. [Google Scholar] [CrossRef]
- Zhang, X.; Zang, Z.; Chen, X.; Lu, Y.; Qi, J.; Gong, J. Optimization-Based Trajectory Planning for Autonomous Vehicles in Scenarios with Multiple Reference Lines. Control Eng. Pract. 2025, 163, 106407. [Google Scholar] [CrossRef]
- Zhang, D.; Jiao, X.; Zhang, T. Lane-Changing and Overtaking Trajectory Planning for Autonomous Vehicles with Multi-Performance Optimization Considering Static and Dynamic Obstacles. Robot. Auton. Syst. 2024, 182, 104797. [Google Scholar] [CrossRef]
- Fan, J.; Chen, X.; Liang, X. UAV Trajectory Planning Based on Bi-Directional APF-RRT* Algorithm with Goal-Biased. Expert Syst. Appl. 2023, 213, 119137. [Google Scholar] [CrossRef]
- Luo, Y.; Ding, W.; Zhang, B.; Huang, W.; Liu, C. Optimization of Bits Allocation and Path Planning with Trajectory Constraint in UAV-Enabled Mobile Edge Computing System. Chin. J. Aeronaut. 2020, 33, 2716–2727. [Google Scholar] [CrossRef]
- Zhang, P.; Mei, Y.; Wang, H.; Wang, W.; Liu, J. Collision-Free Trajectory Planning for UAVs Based on Sequential Convex Programming. Aerosp. Sci. Technol. 2024, 152, 109404. [Google Scholar] [CrossRef]
- Rahman, M.H.; Gulzar, M.M.; Haque, T.S.; Habib, S.; Shakoor, A.; Murtaza, A.F. Trajectory Planning and Tracking Control in Autonomous Driving System: Leveraging Machine Learning and Advanced Control Algorithms. Eng. Sci. Technol. Int. J. 2025, 64, 101950. [Google Scholar] [CrossRef]
- Li, J.; Lei, S.; Wang, S.; Zhao, S.; Han, G.; Huo, Z.; Chen, H.; Sun, Y. Dynamic Modeling and Robust Control of a Multi-Cable Payload Transfer System for Offshore Cranes Subjected to Random Waves and Wind Loads. Ocean Eng. 2024, 313, 119516. [Google Scholar] [CrossRef]
- Krishna, A.; Bisht, R.S.; Panigrahi, S.K. Dynamic Modelling and Payload Response Analysis of a 3-D Overhead Gantry Crane. In Advances in Systems Engineering; Saran, V.H., Misra, R.K., Eds.; Lecture Notes in Mechanical Engineering; Springer: Singapore, 2021; pp. 189–198. ISBN 978-981-15-8024-6. [Google Scholar]
- Tang, Y.; Huang, B.; Wang, S.; Zhou, J.; Xiang, Z.; Sheng, C.; He, C.; Wang, H.; Ruan, L. Computer Vision-Based Real-Time Continuous Monitoring of the Pose for Large-Span Bridge Cable Lifting Structures. Autom. Constr. 2024, 162, 105383. [Google Scholar] [CrossRef]
- Zhu, B.; Li, C.; Song, L.; Song, Y.; Li, Y. A* Algorithm of Global Path Planning Based on the Grid Map and V-Graph Environmental Model for the Mobile Robot. In Proceedings of the 2017 Chinese Automation Congress (CAC), Jinan, China, 20–22 October 2017; pp. 4973–4977. [Google Scholar]
- Hart, P.E.; Nilsson, N.J.; Raphael, B. Correction to “A Formal Basis for the Heuristic Determination of Minimu. m Cost Paths”. ACM SIGART Bull. 1972, 37, 28–29. [Google Scholar] [CrossRef]
- Zhu, Q.; Xiang, Q.; Cai, L. An Improved A* Algorithm for AUV Path Planning. In Proceedings of the 2024 2nd International Conference on Algorithm, Image Processing and Machine Vision (AIPMV), Zhenjiang, China, 12 July 2024; IEEE: New York, NY, USA, 2018; pp. 53–57. [Google Scholar]
- Yan, B.; Chen, T.; Zhu, X.; Yue, Y.; Xu, B.; Shi, K. A Comprehensive Survey and Analysis on Path Planning Algorithms and Heuristic Functions. In Proceedings of the Intelligent Computing, Virtual, 16–17 July 2020; Arai, K., Kapoor, S., Bhatia, R., Eds.; Springer International Publishing: Cham, Switzerland, 2020; pp. 581–598. [Google Scholar]
- Yan, Z.; Gu, S. Cable Crane; China Electric Power Press: Beijing, China, 2010; pp. 13–16. [Google Scholar]
Planning Type | Global Planning | Local Planning | |||
---|---|---|---|---|---|
Number of Directions | Path Length (m) | Number of Corners | Path Length (m) | Number of Corners | |
4 | 437.18 | 1 | 137.47 | 1 | |
8 | 349.24 | 10 | 118.45 | 7 | |
16 | 324.32 | 6 | 113.35 | 5 | |
24 | 324.32 | 6 | 112.12 | 5 |
Power Mechanisms | First Gear | Second Gear | Third Gear | Fourth Gear | Fifth Gear |
---|---|---|---|---|---|
Traction mechanism | 0.60 | 1.50 | 3.00 | 5.00 | 7.50 |
Hoisting mechanism | 0.20 | 0.60 | 1.50 | 2.50 | 3.50 |
Motion Phase | Method | Maximum Absolute Value of the Swing Angle (rad) | Corresponding Pendulum Length (m) | Corresponding Swing Amplitude (m) |
---|---|---|---|---|
Compound motion | Traditional Method | 0.1425 | 57.21 | 8.12 |
Proposed Method | 0.1154 | 54.40 | 6.26 | |
Stabilization | Traditional Method | 0.1084 | 197.00 | 21.31 |
Proposed Method | 0.0641 | 197.00 | 12.62 |
Scheme Number | Maximum Horizontal Hoisting Velocity (m/s) | Maximum Vertical Hoisting Velocity (m/s) |
---|---|---|
1 | 3.0 | 1.5 |
2 | 5.0 | 3.0 |
3 | 7.5 | 3.5 |
Hoisting Stage | Operating Conditions | Average Horizontal Hoisting Velocity (m/s) | Average Vertical Hoisting Velocity (m/s) | Hoisting Duration (s) |
---|---|---|---|---|
Outbound | Scheme 1 | 2.13 | 1.09 | 134.00 |
Scheme 2 | 3.14 | 1.58 | 91.00 | |
Scheme 3 | 3.86 | 1.89 | 74.00 | |
Return | Scheme 1 | 1.98 | 1.17 | 143.00 |
Scheme 2 | 2.80 | 1.57 | 102.00 | |
Scheme 3 | 3.25 | 1.66 | 88.00 |
Hoisting Stage | Operating Conditions | Maximum Swing Angle During Positioning/Empty Bucket Descending (rad) | Corresponding Pendulum Length (m) | Corresponding Swing Amplitudes (m) |
---|---|---|---|---|
Outbound | Scheme 1 | 0.0248 | 197.00 | 4.89 |
Scheme 2 | 0.0398 | 197.00 | 7.84 | |
Scheme 3 | 0.0641 | 197.00 | 12.62 | |
Return | Scheme 1 | 0.1242 | 45.00 | 5.57 |
Scheme 2 | 0.1821 | 45.00 | 8.15 | |
Scheme 3 | 0.3069 | 45.00 | 13.59 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Wang, F.; Xu, H.; Zhao, C.; Zhou, Y.; Zhou, H.; Liang, Z.; Lei, L. Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction. Appl. Sci. 2025, 15, 8894. https://doi.org/10.3390/app15168894
Wang F, Xu H, Zhao C, Zhou Y, Zhou H, Liang Z, Lei L. Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction. Applied Sciences. 2025; 15(16):8894. https://doi.org/10.3390/app15168894
Chicago/Turabian StyleWang, Fang, Haobin Xu, Chunju Zhao, Yihong Zhou, Huawei Zhou, Zhipeng Liang, and Lei Lei. 2025. "Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction" Applied Sciences 15, no. 16: 8894. https://doi.org/10.3390/app15168894
APA StyleWang, F., Xu, H., Zhao, C., Zhou, Y., Zhou, H., Liang, Z., & Lei, L. (2025). Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction. Applied Sciences, 15(16), 8894. https://doi.org/10.3390/app15168894