Research Progress and Typical Case of Open-Pit to Underground Mining in China
Abstract
1. Introduction
2. Analysis of Key Technologies for the Transition from Open-Pit to Underground Mining
2.1. Analysis of Mine Development Systems in the Transition from Open-Pit to Underground Mining
2.1.1. Independent Development System
2.1.2. Partially Integrated Development System
2.1.3. Fully Integrated Development System
2.2. Selection of Mining Methods and Technical Adaptability Analysis
2.2.1. Stope Mining Method
2.2.2. Caving Mining Method
2.2.3. Backfilling Mining Method
2.3. Current Status of Slope Stability Research in Open-Pit Underground Mining
2.4. Research and Technical Risk Analysis of Crown Pillar Thickness in the Transition from Open-Pit to Underground Mining
2.4.1. Design and Safety Balance of Crown Pillar Thickness
2.4.2. Application of Numerical Simulation and Computational Methods in Determining Crown Pillar Thickness
2.4.3. Technical Analysis and Challenge Evaluation
3. Typical Case: Integrated Demonstration of Xinqiao Iron Mine
3.1. Overview of Xinqiao Mine
3.2. Measures for the Transition from Open-Pit to Underground Mining at Xinqiao Mine
- Post-closure treatment: Following the closure of the open pit, the pit floor is promptly treated to prevent seepage. Following the open-pit waste rock management plan, the pit is then backfilled to the −106 m level. This procedure ensures the stability of the mining area while meeting environmental protection standards.
- Safety isolation layer: The ore body above the 180 m level, with a thickness of 24 m, serves as a safety isolation layer between surface and underground mining. This layer acts as a buffer, preventing potential safety risks between the surface and underground operations. The underground mining site is illustrated in Figure 7b.
- Open-pit slope monitoring system: An open-pit slope monitoring system is established to closely monitor the impact of underground mining activities on the stability of the open-pit slopes. This system provides real-time data to assess and manage risks during the transition period.
- Comprehensive drainage system planning: During the transition period, water from the open-pit excavation is discharged through the existing open-pit drainage facilities. Once the open pit is closed and backfilled to the 106 m level, a collection pit (10 m × 6 m × 6 m) is constructed at the lowest point. Water is then directed through the existing drainage infrastructure to a permanent pumping station located at the 48 m level.
3.3. Selection of Mining Methods for the Transition from Open-Pit to Underground Mining at Xinqiao Mine
3.4. Determining the Crown Pillar Thickness at Xinqiao Mine
3.5. Implementation of Mining Methods
- Block Layout and Structural Params:
- 2.
- Mining Development Layout:
- 3.
- Mining Process:
- 4.
- Ore Removal:
- 5.
- Backfilling Process:
- 6.
- Key Technical and Economic Indicators:
3.6. Tailings Resource Utilization and Open-Pit Ecological Restoration Practices
4. Conclusions
- The transition from open-pit to underground mining necessitates a mine-specific, phased implementation approach. It is essential to choose an appropriate development system—whether independent, partially integrated, or fully integrated—based on geological conditions, resource depth, and production scale. The joint development system at Xinqiao Mine, which integrates a main and auxiliary shaft with a ramp, has successfully increased mining efficiency by 25% and reduced surface disturbance by 40%, confirming the model’s effectiveness and environmental advantages under specific conditions.
- The selection of mining methods directly impacts the success of the transition and the efficiency of resource recovery. Compared to stope mining and caving mining methods, backfilling mining offers distinct advantages in stabilizing surrounding rock structures, controlling surface subsidence, and enhancing resource recovery rates. As backfilling materials and techniques continue to evolve, their application in green mining construction becomes increasingly significant. Xinqiao Mine has adopted the upward horizontal layered backfilling method, achieving a recovery rate of 84.66% and a low dilution rate of 3.41%, while significantly reducing environmental disturbances. This demonstrates the comprehensive advantages of the method.
- Slope stability control is essential for ensuring the safe operation of a mine throughout its lifecycle. During the transition from open-pit to underground mining, the original slope stability system faces rebalancing challenges due to stress redistribution and disturbances from mining activities. Existing research has developed several theories and models, including limit equilibrium analysis, numerical simulations, and physical modeling, providing a scientific basis for predicting slope behavior and disaster risks. However, the mechanisms of slope instability under multi-factor coupling conditions remain highly uncertain, necessitating further studies in multi-field coupling, time evolution, and system dynamics.
- National-level green mining policies, especially the “Zero Waste Mine” initiative, have driven significant technological innovations in the mining sector, particularly in tailings backfilling and solid waste resource utilization. Tailings backfilling not only reduces tailings discharge but also facilitates the ecological restoration of closed pit land. Additionally, it enhances resource utilization efficiency and lowers energy consumption per unit of production. For example, Xinqiao Mine has successfully integrated solid waste resource utilization with environmental protection by utilizing tailings from the Dongguashan Copper Mine for open-pit backfilling. This approach demonstrates both the feasibility and the exemplary role of green mining transformation.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Chen, J.H.; Gu, D.S.; Li, J.X. Optimization principle of combined surface and underground mining and its applications. J. Cent. South Univ. Technol. 2003, 10, 222–225. [Google Scholar] [CrossRef]
- Duan, B.; Xia, H.; Yang, X. Impacts of bench blasting vibration on the stability of the surrounding rock masses of roadways. Tunn. Undergr. Space Technol. 2018, 71, 605–622. [Google Scholar] [CrossRef]
- Espinoza, D.; Goycoolea, M.; Moreno, E.; Newman, A. MineLib: A library of open pit mining problems. Ann. Oper. Res. 2013, 206, 93–114. [Google Scholar] [CrossRef]
- Molotilov, S.G.; Norri, V.K.; Cheskidov, V.I.; Mattis, A.R. Nature-oriented open coal mining technologies using mined-out space in an open pit. part I: Analysis of the current mineral mining methods. J. Min. Sci. 2006, 42, 622–627. [Google Scholar] [CrossRef]
- Tawadrous, A.S.; Katsabanis, P.D. Prediction of surface crown pillar stability using artificial neural networks. Int. J. Numer. Anal. Methods Geomech. 2007, 31, 917–931. [Google Scholar] [CrossRef]
- Cui, Z.; Zhang, J.; Wu, D.; Cai, X.; Wang, H.; Zhang, W.; Chen, J. Hybrid many-objective particle swarm optimization algorithm for green coal production problem. Inf. Sci. 2020, 518, 256–271. [Google Scholar] [CrossRef]
- Hao, X.; Wen, S.; Li, K.; Wu, J.; Wu, H.; Hao, Y. Environmental governance, executive incentive, and enterprise performance: Evidence from Chinese mineral enterprises. Resour. Policy 2023, 85, 103858. [Google Scholar] [CrossRef]
- Bakhtavar, E.; Shahriar, K.; Oraee, K. Mining method selection and optimization of transition from open pit to underground in combined mining. Arch. Min. Sci. 2009, 54, 481–493. [Google Scholar]
- Dintwe, T.K.M.; Sasaoka, T.; Shimada, H.; Hamanaka, A.; Moses, D. Evaluating the Influence of Underground Mining Sequence under an Open Pit Mine. J. Min. Sci. 2022, 58, 35–43. [Google Scholar] [CrossRef]
- Chung, J.; Asad, M.W.A.; Topal, E. Timing of transition from open-pit to underground mining: A simultaneous optimisation model for open-pit and underground mine production schedules. Resour. Policy 2022, 77, 102632. [Google Scholar] [CrossRef]
- Rybnikova, L.S.; Rybnikov, P.A.; Smirnov, A.Y. Flooding of Open Pit and Underground Mines in the Chelyabinsk Coal Field: Consequences, Problems and Solutions. J. Min. Sci. 2023, 59, 497–504. [Google Scholar] [CrossRef]
- Bakhtavar, E.; Shahriar, K.; Mirhassani, A. Optimization of the transition from open-pit to underground operation in combined mining using (0-1) integer programming. J. South. Afr. Inst. Min. Metall. 2012, 112, 1059–1064. [Google Scholar]
- Gutiérrez-Viñuales, A. Chuquicamata: Patrimonio industrial de la minería del cobre en Chile. Apunt. Rev. Estud. Sobre Patrim. Cult.-J. Cult. Herit. Stud. 2008, 21, 74–91. [Google Scholar]
- Sanislav, I.V.; Brayshaw, M.; Kolling, S.L.; Dirks, P.H.G.M.; Cook, Y.A.; Blenkinsop, T.G. The structural history and mineralization controls of the world-class Geita Hill gold deposit, Geita Greenstone Belt, Tanzania. Miner. Depos. 2017, 52, 257–279. [Google Scholar] [CrossRef]
- Crawford, A.J.; Doyle, M.G. Granulite-Hosted Gold: Tectonic Setting and Lithogeochemistry of the Tropicana Deposit, Western Australia. Econ. Geol. 2016, 111, 395–420. [Google Scholar] [CrossRef]
- Ngidi, S.; Boshoff, P. Cave management and secondary breaking practices at Palabora Mining Company. J. South. Afr. Inst. Min. Metall. 2007, 107, 783–789. [Google Scholar]
- Gurney, J.J.; Hildebrand, P.R.; Carlson, J.A.; Fedortchouk, Y.; Dyck, D.R. The morphological characteristics of diamonds from the Ekati property, Northwest Territories, Canada. Lithos 2004, 77, 21–38. [Google Scholar] [CrossRef]
- Wafforn, S.; Seman, S.; Kyle, J.R.; Stockli, D.; Leys, C.; Sonbait, D.; Cloos, M. Andradite garnet u-pb geochronology of the big gossan skarn, ertsberg-grasberg mining district, indonesia. Econ. Geol. 2018, 113, 769–778. [Google Scholar] [CrossRef]
- Chowdu, A.; Nesbitt, P.; Brickey, A.; Newman, A.M. Operations Research in Underground Mine Planning: A Review. Inf. J. Appl. Anal. 2022, 52, 109–132. [Google Scholar] [CrossRef]
- Hou, D.; Xu, M.; Li, X.; Wang, J.; Wang, M.; Li, S. Optimization of mining methods for deep orebody of large phosphate mines. Front. Built Environ. 2023, 9, 1282684. [Google Scholar] [CrossRef]
- Bakhtavar, E.; Abdollahisharif, J.; Aminzadeh, A. A stochastic mathematical model for determination of transition time in the non-simultaneous case of surface and underground mining. J. South. Afr. Inst. Min. Metall. 2017, 117, 1145–1153. [Google Scholar] [CrossRef]
- Li, S.; Zou, P.; Yu, H.; Hu, B.; Wang, X. Advantages of Backfill Mining Method for Small and Medium-Sized Mines in China: Safe, Eco-Friendly, and Efficient Mining. Appl. Sci. 2023, 13, 7280. [Google Scholar] [CrossRef]
- Li, S.; Yu, L.; Dan, Z.; Yin, T.; Chen, J. The Recent Progress China Has Made in Mining Method Transformation, Part I: Shrinkage Method Transformed into Backfilling Method. Appl. Sci. 2024, 14, 10033. [Google Scholar] [CrossRef]
- Li, X.; Li, D.; Liu, Z.; Zhao, G.; Wang, W. Determination of the minimum thickness of crown pillar for safe exploitation of a subsea gold mine based on numerical modelling. Int. J. Rock Mech. Min. Sci. 2013, 57, 42–56. [Google Scholar] [CrossRef]
- Rysbekov, K.; Bitimbayev, M.; Akhmetkanov, D.; Yelemessov, K.; Barmenshinova, M.; Toktarov, A.; Baskanbayeva, D. Substantiation of mining systems for steeply dipping low-thickness ore bodies with controlled continuous stope extraction. Min. Miner. Depos. 2022, 16, 64–72. [Google Scholar] [CrossRef]
- Zhu, W.; Xu, J.; Xu, J.; Chen, D.; Shi, J. Pier-column backfill mining technology for controlling surface subsidence. Int. J. Rock Mech. Min. Sci. 2017, 96, 58–65. [Google Scholar] [CrossRef]
- Yuan, K.; Ma, C.; Guo, G.; Wang, P. Slope Failure of Shilu Metal Mine Transition from Open-Pit to Underground Mining under Excavation Disturbance. Appl. Sci. 2024, 14, 1055. [Google Scholar] [CrossRef]
- Li, S.; Xiang, Z.; Dan, Z.; Yin, T.; Chen, J. The Recent Progress China Has Made in Mining Method Transformation: Part II Sublevel Caving Method Transformed into Backfilling Method. Appl. Sci. 2024, 14, 9732. [Google Scholar] [CrossRef]
- Zhang, Z.-X. Lost-ore mining-A supplementary mining method to sublevel caving. Int. J. Rock Mech. Min. Sci. 2023, 168, 105420. [Google Scholar] [CrossRef]
- Jiang, N.; Wang, C.; Pan, H.; Yin, D.; Ma, J. Modeling study on the influence of the strip filling mining sequence on mining-induced failure. Energy Sci. Eng. 2020, 8, 2239–2255. [Google Scholar] [CrossRef]
- Hou, J.; Li, C.; Yuan, L.; Li, J.; Liu, F. Study on green filling mining technology and its application in deep coal mines: A case study in the Xieqiao coal mine. Front. Earth Sci. 2023, 10, 1110093. [Google Scholar] [CrossRef]
- Zhao, X.; Yu, W.; Zhao, Y.; Fu, S. Numerical Estimation of Shaft Stability and Surface Deformation Induced by Underground Mining Transferred from Open-Pit Mining in Jinfeng Gold Mine. Minerals 2023, 13, 196. [Google Scholar] [CrossRef]
- Chen, F.; Liu, J.; Zhang, X.; Wang, J.; Jiao, H.; Yu, J. Review on the Art of Roof Contacting in Cemented Waste Backfill Technology in a Metal Mine. Minerals 2022, 12, 721. [Google Scholar] [CrossRef]
- Yu, H.; Li, S.; Wang, X. The Recent Progress China Has Made in the Backfill Mining Method, Part I: The Theory and Equipment of Backfill Pipeline Transportation. Minerals 2021, 11, 1274. [Google Scholar] [CrossRef]
- Hou, D.; Xu, M.; Li, X.; Wang, J.; Wang, M.; Li, S. Study on filling mining technology for gently inclined thin to medium thick phosphorus deposits. Front. Earth Sci. 2023, 11, 1254509. [Google Scholar] [CrossRef]
- Aruga, K.; Islam, M.M.; Zenno, Y.; Jannat, A. Developing Novel Technique for Investigating Guidelines and Frameworks: A Text Mining Comparison between International and Japanese Green Bonds. J. Risk Financ. Manag. 2022, 15, 382. [Google Scholar] [CrossRef]
- Li, X.; Wang, Y.; Hu, Y.; Zhou, C.; Zhang, H. Numerical Investigation on Stratum and Surface Deformation in Underground Phosphorite Mining Under Different Mining Methods. Front. Earth Sci. 2022, 10, 831856. [Google Scholar] [CrossRef]
- Yin, S.; Shao, Y.; Wu, A.; Wang, H.; Liu, X.; Wang, Y. A systematic review of paste technology in metal mines for cleaner production in China. J. Clean. Prod. 2020, 247, 119590. [Google Scholar] [CrossRef]
- Vyazmensky, A.; Stead, D.; Elmo, D.; Moss, A. Numerical Analysis of Block Caving-Induced Instability in Large Open Pit Slopes: A Finite Element/Discrete Element Approach. Rock Mech. Rock Eng. 2010, 43, 21–39. [Google Scholar] [CrossRef]
- Baskari, T.L.; Zakaria, Z.; Sulaksana, N.; Muljana, B. Study on rheological constitutive model of cililin volcanic clay, indonesia in relation to long-term slope stability. Int. J. Geomate 2021, 21, 40–47. [Google Scholar] [CrossRef]
- Sultan, N.; Cochonat, P.; Canals, M.; Cattaneo, A.; Dennielou, B.; Haflidason, H.; Laberg, J.S.; Long, D.; Mienert, J.; Trincardi, F.; et al. Triggering mechanisms of slope instability processes and sediment failures on continental margins: A geotechnical approach. Mar. Geol. 2004, 213, 291–321. [Google Scholar] [CrossRef]
- Stead, D.; Eberhardt, E.; Coggan, J.S. Developments in the characterization of complex rock slope deformation and failure using numerical modelling techniques. Eng. Geol. 2006, 83, 217–235. [Google Scholar] [CrossRef]
- Nguyen, P.M.V.; Marciniak, M. Stochastic Rock Slope Stability Analysis: Open Pit Case Study with Adjacent Block Caving. Geotech. Geol. Eng. 2024, 42, 5827–5845. [Google Scholar] [CrossRef]
- Luo, Y.Z.; Wu, A.X.; Liu, X.P.; Wang, H.J. Stability and reliability of pit slopes in surface mining combined with underground mining in Tonglushan mine. J. Cent. South Univ. Technol. 2004, 11, 434–439. [Google Scholar] [CrossRef]
- Li, B.; Feng, Z.; Wang, G.; Wang, W. Processes and behaviors of block topple avalanches resulting from carbonate slope failures due to underground mining. Environ. Earth Sci. 2016, 75, 694. [Google Scholar] [CrossRef]
- Scholtes, L.; Donze, F.-V. Modelling progressive failure in fractured rock masses using a 3D discrete element method. Int. J. Rock Mech. Min. Sci. 2012, 52, 18–30. [Google Scholar] [CrossRef]
- Ding, Q.-L.; Peng, Y.-Y.; Cheng, Z.; Wang, P. Numerical Simulation of Slope Stability during Underground Excavation Using the Lagrange Element Strength Reduction Method. Minerals 2022, 12, 1054. [Google Scholar] [CrossRef]
- Johari, A.; Lari, A.M. System probabilistic model of rock slope stability considering correlated failure modes. Comput. Geotech. 2017, 81, 26–38. [Google Scholar] [CrossRef]
- Shen, J.; Karakus, M. Three-dimensional numerical analysis for rock slope stability using shear strength reduction method. Can. Geotech. J. 2014, 51, 164–172. [Google Scholar] [CrossRef]
- Gischig, V.; Amann, F.; Moore, J.R.; Loew, S.; Eisenbeiss, H.; Stempfhuber, W. Composite rock slope kinematics at the current Randa instability, Switzerland, based on remote sensing and numerical modeling. Eng. Geol. 2011, 118, 37–53. [Google Scholar] [CrossRef]
- Li, S.; Zhao, Z.; Hu, B.; Yin, T.; Chen, G.; Chen, G. Three-Dimensional Simulation Stability Analysis of Slopes from Underground to Open-Pit Mining. Minerals 2023, 13, 402. [Google Scholar] [CrossRef]
- Mortazavi, A.; Hassani, F.P.; Shabani, M. A numerical investigation of rock pillar failure mechanism in underground openings. Comput. Geotech. 2009, 36, 691–697. [Google Scholar] [CrossRef]
- Guo, X.; Chen, Q.; Gan, Q.; Niu, W.; Liu, C.; Xu, J. The Reissner-Ritz Method for Solving the Deflection Function of the Crown Pillar in the Stope and Its Application in the Crown Pillar Failure Analysis. Rock Mech. Rock Eng. 2024, 57, 5089–5107. [Google Scholar] [CrossRef]
- Hemant, K.; Debasis, D.; Chakravarty, D. Design of crown pillar thickness using finite element method and multivariate regression analysis. Int. J. Min. Sci. Technol. 2017, 27, 955–964. [Google Scholar] [CrossRef]
- Xu, S.; Suorineni, F.T.; An, L.; Li, Y.H.; Jin, C.Y. Use of an artificial crown pillar in transition from open pit to underground mining. Int. J. Rock Mech. Min. Sci. 2019, 117, 118–131. [Google Scholar] [CrossRef]
- Lavoie, T.; Eberhardt, E.; Pierce, M.E. Numerical modelling of rock mass bulking and geometric dilation using a bonded block modelling approach to assist in support design for deep mining pillars. Int. J. Rock Mech. Min. Sci. 2022, 156, 105145. [Google Scholar] [CrossRef]
- Wessels, D.G.; Malan, D.F. A Limit Equilibrium Model to Simulate Time-Dependent Pillar Scaling in Hard Rock Bord and Pillar Mines. Rock Mech. Rock Eng. 2023, 56, 3773–3786. [Google Scholar] [CrossRef]
- Guggari, V.B.; Kumar, H.; Budi, G. Stability analysis of crown pillar under the zone of relaxation around sub-level open stopes using numerical modelling. Geomat. Nat. Hazards Risk 2023, 14, 2234072. [Google Scholar] [CrossRef]
- Dintwe, T.K.M.; Sasaoka, T.; Shimada, H.; Hamanaka, A.; Moses, D.N.; Peng, M.; Meng, F.; Liu, S.; Ssebadduka, R.; Onyango, J.A. Numerical Simulation of Crown Pillar Behaviour in Transition from Open Pit to Underground Mining. Geotech. Geol. Eng. 2022, 40, 2213–2229. [Google Scholar] [CrossRef]
- Kwong, Y.T.J.; Apte, S.C.; Asmund, G.; Haywood, M.D.E.; Morello, E.B. Comparison of Environmental Impacts of Deep-sea Tailings Placement Versus On-land Disposal. Water Air Soil Pollut. 2019, 230, 287. [Google Scholar] [CrossRef]
- Hancock, G.R.; Martin Duque, J.F.; Willgoose, G.R. Mining rehabilitation-Using geomorphology to engineer ecologically sustainable landscapes for highly disturbed lands. Ecol. Eng. 2020, 155, 105836. [Google Scholar] [CrossRef]
- Dino, G.A.; Cavallo, A.; Rossetti, P.; Garamvolgyi, E.; Sandor, R.; Coulon, F. Towards Sustainable Mining: Exploiting Raw Materials from Extractive Waste Facilities. Sustainability 2020, 12, 2383. [Google Scholar] [CrossRef]
- Jiskani, I.M.; Cai, Q.; Zhou, W.; Lu, X.; Shah, S.A.A. An integrated fuzzy decision support system for analyzing challenges and pathways to promote green and climate smart mining. Expert Syst. Appl. 2022, 188, 116062. [Google Scholar] [CrossRef]
- Panchal, S.; Deb, D.; Sreenivas, T. Mill tailings based composites as paste backfill in mines of U-bearing dolomitic limestone ore. J. Rock Mech. Geotech. Eng. 2018, 10, 310–322. [Google Scholar] [CrossRef]
- Yang, L.; Qiu, J.; Jiang, H.; Hu, S.; Li, H.; Li, S. Use of Cemented Super-Fine Unclassified Tailings Backfill for Control of Subsidence. Minerals 2017, 7, 216. [Google Scholar] [CrossRef]
- Idris, M.A.; Saiang, D.; Nordlund, E. Stochastic assessment of pillar stability at Laisvall mine using Artificial Neural Network. Tunn. Undergr. Space Technol. 2015, 49, 307–319. [Google Scholar] [CrossRef]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Li, S.; Su, W.; Yin, T.; Dan, Z.; Peng, K. Research Progress and Typical Case of Open-Pit to Underground Mining in China. Appl. Sci. 2025, 15, 8530. https://doi.org/10.3390/app15158530
Li S, Su W, Yin T, Dan Z, Peng K. Research Progress and Typical Case of Open-Pit to Underground Mining in China. Applied Sciences. 2025; 15(15):8530. https://doi.org/10.3390/app15158530
Chicago/Turabian StyleLi, Shuai, Wencong Su, Tubing Yin, Zhenyu Dan, and Kang Peng. 2025. "Research Progress and Typical Case of Open-Pit to Underground Mining in China" Applied Sciences 15, no. 15: 8530. https://doi.org/10.3390/app15158530
APA StyleLi, S., Su, W., Yin, T., Dan, Z., & Peng, K. (2025). Research Progress and Typical Case of Open-Pit to Underground Mining in China. Applied Sciences, 15(15), 8530. https://doi.org/10.3390/app15158530