1. Introduction
By the end of the 13th Five-Year Plan, the mileage of the subway lines built in China is expected to exceed the set target. With rapid infrastructure development in urban areas, there is an increasing demand for the construction of subway tunnels that are adjacent to existing ones due to limited underground space. In this context, it is essential to ensure the safety and stability of existing tunnels during adjacent construction activities. Conditions caused by the construction of the adjacent tunnel, such as temporary overloading on the ground, will adversely affect the existing tunnel, and the changing stress balance of the tunnel will result in uneven settlement. When the tunnel stress field reaches a certain threshold, segmental rupture, leakage, segmental joint opening, and varying degrees of other damage will occur. Some damage can even affect the structure and normal operation of the subway tunnel. Several scholars [
1,
2,
3,
4,
5,
6,
7,
8,
9] have reported cases of tunnel structure damage caused by nearby ground surcharges. With the continuous increase in the mileage of subway lines, the development of surcharges along the subway tunnel will inevitably occur. The rapid and reliable prediction of the response of the existing tunnel structure to surface surcharge is an important subject to ensure the safe, stable, and normal operation of subways.
Ground overloading changes the stress state of the existing stratum and causes stress release by the soil, thus resulting in the nonuniform settlement deformation of the existing tunnel. Domestic and foreign scholars have used different methods to conduct in-depth analyses of the responses of existing tunnels to ground surcharge [
10,
11,
12,
13,
14]. Wu Qing et al. [
15] used physical model tests to analyze the deformation response of an existing tunnel subjected to surcharge under different conditions, such as the spacing between the ground surcharge and the existing tunnel and the buried depth of the tunnel. Zhang et al. [
13] carried out an equal-scale indoor model test to analyze the change in soil stress around the tunnel caused by ground surcharge. Their results show that the soil above the existing tunnel bears high pressure, and the earth pressure is positively distributed above the tunnel axis. As the distance from the tunnel axis increases, the earth pressure gradually decreases. Gao et al. [
16] carried out indoor model tests and demonstrated the applicability of the proposed theoretical method through indoor test simulations. The error between the model test results and the theoretical calculation results was less than 10%, which is within the allowable range.
Finite element analysis software can be used to fully simulate the geological conditions of a construction site, and the construction step sequence is widely studied. Zhang et al. [
13] used three-dimensional finite element software to simulate changes in the deformation and internal force of an existing tunnel subjected to ground overloading, and they verified the accuracy of the simulation by comparing the outputs with the results of indoor model tests. Kentaro et al. [
17] used finite element software to simulate the deformation responses of single and parallel tunnels under ground surcharge conditions and compared and analyzed them with published field data. Using the Port of Shanghai Small Lai channel fill project as the background, Lu et al. [
18] used 3D finite element software to simulate and analyze the ground using the Hardening Soil Model with small-strain Stiffness constitutive model (HSS model) of a soil–pile load response to an adjacent tunnel. They studied the influence of the relative positions of the pile and tunnel and the tunnel buried depth on the existing tunnel and observed that improving the soil stiffness could effectively reduce the action of the pile on tunnel deformation.
The results of these previous physical model tests and three-dimensional simulations, however, are only applicable to the specific cases researched in the above-mentioned studies. When the construction conditions change, the previous research results cannot be directly used to quantitatively evaluate the response of the existing tunnel to ground surcharge. Therefore, a simplified analytical method that can be used to directly predict the tunnel response to ground surcharge is urgently required.
The theoretical method has the advantages of a clear concept, convenient implementation, and time effectiveness, and it is often used to quickly predict the deformation response of a tunnel subjected to ground surcharge in the early stage of analysis and research. Dai et al. [
14] derived a longitudinal deformation balance equation of an existing tunnel subjected to ground surcharge based on a beam model with a Winkler elastic foundation, and they obtained the theoretical analytical solution of the longitudinal displacement of the existing tunnel through the finite difference method. The maximum displacement diagram of the existing tunnel for different ground surcharge distances was presented. The safe horizontal distance between the center of the existing tunnel and that of the surcharge was determined to be greater than 32 m. Li et al. [
19], treating the soil as an elastic layered foundation in half-space, considered the pipeline to be an elastic long beam based on the Winkler foundation model. They derived and solved the differential equation of pipeline deformation under high-fill conditions. By comparing the solution with the outputs of finite element simulations, the reliability of the proposed theoretical method was verified, and the theoretical prediction scheme could be applied to the same type of construction project. Kang Cheng et al. [
20] analyzed the accompanying shear deformation of the existing tunnel in the bending process and simplified the tunnel to a Timoshenko beam. An ordinary differential equation for the longitudinal deformation of an existing tunnel subjected to ground surcharge was established, and the analytical solution of the longitudinal deformation was obtained. The applicability of the proposed method was verified by comparing the results with field monitoring data and finite element software simulation analysis. In addition, the influence of ordinary differential equation parameters on tunnel longitudinal deformation was analyzed.
The theoretical analytical method typically uses the Winkler foundation model for the tunnel. However, as shown in
Figure 1, the drawback of this approach is the inherent discontinuity of adjacent springs, which does not reflect the mechanical properties of foundation soil materials. This assumption greatly simplifies the calculation and affects the prediction results.
In this paper, a new simplified analytical method is proposed to estimate the longitudinal displacement of a shield tunnel subjected to ground surcharge. A two-parameter foundation model, namely the Pasternak foundation model, was established. This model is capable of capturing continuity. In the proposed method, the existing shield tunnel is treated as a continuous Euler–Bernoulli long beam with reduced bending stiffness, resting on a Pasternak foundation. An analytical solution for a shield tunnel subjected to ground surcharge is derived. On the basis of existing research, assuming the continuity of the existing tunnel in the soil and based on an analysis of the tunnel and its interaction with the soil, the Pasternak model in
Figure 2 [
21] uses the Boussinesq elastic solution to obtain the ground-heaped load distribution in the additional load matrix at the tunnel location. The adjusted coefficient of the bed pressure is used to establish the differential equation of tunnel deformation, and the finite difference method is used to obtain the tunnel longitudinal displacement matrix. The reliability and applicability of the proposed method are verified by comparing field monitoring data, finite element simulation results, and the calculation results of three simplified elastic analysis methods based on different foundation bed coefficients. Based on these results, the parameters of the load–tunnel model are analyzed, and the effects of the buried depth, the size of the load, the relative positions of the load and tunnel, and the relative stiffness of the tunnel soil on the maximum displacement of the existing tunnel are discussed. An empirical formula for the maximum longitudinal displacement of the existing tunnel subjected to surface surcharge is proposed. The contents of this research can provide a basis for the theoretical verification of the deformation response of an existing tunnel subjected to adjacent surface surcharge.
2. Theory of Tunnel Deformation under Surcharge Loading
Ground surcharge will cause a change in the ground stress field, and, as a result, the existing tunnel will undergo settlement deformation.
Figure 3 shows the longitudinal deformation diagram of the existing tunnel under the action of ground surcharge loading. In the method proposed in this paper, Euler–Bernoulli beams are used to simulate the bending deformation of existing tunnels. To simplify the calculations, the Euler–Bernoulli beam model assumes that the tunnel section undergoing bending deformation is always perpendicular to the neutral axis, as shown in
Figure 4. The shear deformation at the segment joints is ignored, so only the longitudinal bending deformation of the tunnel is considered. The proper application of conservative Euler–Bernoulli beam theory can ensure the safety and stability of the tunnel to a large extent.
Then, the existing tunnel is simplified and incorporated into the Pasternak foundation model. As shown in
Figure 2, the Pasternak foundation model adds a shear layer to the Winkler foundation model, accounting for the continuous characteristics between soils.
The analytic solution for longitudinal tunnel deformation under the action of ground surcharge is derived with the following assumptions: (a) to simplify calculations, the tunnel is equivalent to an infinitely long Euler–Bernoulli beam; (b) the shear deformation of the layer occurs and does not produce compression deformation; (c) close contact between the soil and tunnel, tunnel deformation, and the contact deformation of soil is consistent; (d) the deformation is independent of the tunnel and the lateral friction force between soil; (e) the deformation is independent of the effects of tunnel and soil compression, such as consolidation settlement and creep.
The theory of longitudinal deformation of an existing tunnel under surface overloading adopts a two-stage analysis method. It is also a common analytical method in studying the response of adjacent construction to an existing tunnel. First, the additional load at the existing tunnel position caused by ground overloading is calculated; then, the calculated external load is applied to the existing tunnel, and the differential equation of longitudinal deformation of the existing tunnel is established. In this method, the longitudinal displacement solution matrix of the tunnel is obtained by using the finite difference method.
2.1. Additional Stresses Caused by Surface Stowage
Figure 4 shows the axis of the existing shield tunnel buried below the ground. Rectangular overloads on the ground above the existing tunnel are shown in
Figure 5. The overload length and width are expressed by
L and
B, respectively. The Boussinesq formula is used to calculate the additional stress caused by ground overloading while ignoring the influence of existing tunnels. Using the Boussinesq formula, the additional longitudinal stress along the axis of the shield tunnel can be obtained:
where
is the relative position between the centroid of the uniform ground load and any point on the tunnel axis:
In the formula, and are the abscissa and ordinate of the global coordinate system , respectively. is the distance between the tunnel axis and the ground.
To simplify the calculation, a local
coordinate system of the tunnel is established as in
Figure 1, and the origin of the coordinate system is located at a point on the tunnel axis. In the local coordinate system, the
x axis is coincident with the tunnel axis, and the
axis is perpendicular to the tunnel axis. The distance between the origin of the global coordinate system
and the origin of the local coordinate system
is
, the angle between the
axis of the tunnel and the global coordinate system
axis is
, and the angle between the connection of the origins of the two coordinate systems and the global coordinate system
axis is
. Considering the geometric relationship between the two coordinate systems, the transformation expressions of the horizontal and vertical coordinates between any point on the existing tunnel axis and the global coordinate system are obtained:
The external load at the existing tunnel position is obtained by coordinate transformation based on the Boussinesq solution surface surcharge .
2.2. Responses of Tunnels to External Loads
The load–tunnel calculation model is shown in
Figure 3. The existing tunnel is equivalent to a continuous Euler–Bernoulli beam placed on a Pasternak foundation. The method assumes that the tunnel is always in contact with the soil and that no slip occurs at the tunnel–soil interface in any direction. In addition, the soil is assumed to be an isotropic elastic material, and the plastic deformation of the soil is not considered. The longitudinal deformation differential equation of the existing shield tunnel based on a Pasternak foundation subjected to surface surcharge stress is as follows:
where
is the longitudinal deformation of the tunnel, and
is the external load acting on the tunnel.
is the tunnel diameter, and
is the equivalent bending stiffness of the tunnel.
Equation (4) is a high-order ordinary differential equation, which is not convenient to solve directly. In the proposed approach, the solution is determined using the finite difference method. First, as shown in
Figure 6, the finite difference method is carried out for tunnels and other elements. The tunnel is divided into
n + 5 units in equal proportion, of which 4 virtual units are located at the two ends of the tunnel (2 at each end), as shown in
Figure 2. The unit length is
. According to the finite difference principle, the finite difference form of Equation (4) is
where
,
,
,
, and
are the longitudinal displacements of the tunnel elements
,
,
,
, and
, respectively, and
is the external load acting on the units.
For the boundary conditions of the existing tunnel, it is assumed that both ends of the tunnel are free. Then, the bending moment
and the shearing force are 0 at both ends, and they are determined, respectively, as follows:
According to the finite difference principle,
The horizontal displacement expressions of the four newly added virtual elements can be obtained with (8a), (8b), (8c), and (8d):
Equation (5) is expressed in matrix form as
After sorting and merging similar items, the following results are obtained:
where
is the column vector of the longitudinal displacement of the tunnel,
;
is the column vector of the external load in the longitudinal direction caused by basement excavation; and
. The expressions of
,
, and
are obtained from the following virtual cell expression:
Let
; then, Equation (11) can be further rewritten:
where
is the inverse of
.
By solving (1)–(3), the external load at the existing tunnel position caused by the surcharge can be obtained. The longitudinal displacement of the existing tunnel caused by ground surcharge can be obtained by combining Equations (12)–(15).
5. Parameter Analysis
The feasibility of the proposed method was verified by comparing it with finite element simulation, which analyzes the influence of surface surcharge on the existing operating tunnel. A parameterized analysis was adopted in this experiment to further understand the influence of various factors in the surcharge load–soil–tunnel model on the existing tunnel. The main influencing factors include the relative positions of the tunnel and the load, the geometric size of the load, and the relative stiffness of the tunnel and soil. The relationship between the tunnel axis and the position of the load in the load–tunnel model is shown in
Figure 12. The shape of the load is rectangular, and the length
and width
are 48 m and 24 m, respectively. The existing tunnel is assumed to have an outer diameter
of 6.2 m, an inner diameter
of 5.5 m, an annulus width of 1.2 m, and an axis buried depth of
= 15 m. The spacing between the surface surcharge center and the tunnel axis d is 0. Poisson’s ratio
of the soil in the stratum in which the tunnel is located is 0.35, and the elastic modulus is 15 MPa. The calculated equivalent bending stiffness of the tunnel is 7.8 × 10
4 MN m
2, and the structural parameters of the tunnel are shown in
Table 2.
5.1. Tunnel–Surcharge Spacing
Assuming that the parameters of the new and existing tunnel models remain unchanged, five curves of tunnel buried depth and maximum longitudinal displacement were generated for different load–tunnel spacing
.
Figure 13 shows the variation curve of the maximum longitudinal displacement
for increasing tunnel buried depths
and different load–tunnel centerline spacing
. As shown in the figure, for a given spacing
, the maximum longitudinal displacement
of the tunnel decreases gradually with a varying slope as the tunnel buried depth
increases. The maximum longitudinal displacement
of the tunnel is different for different tunnel–load spacing
. When
= 0, the tunnel is located at the center of the surcharge, and the external load disturbance is the most significant. Therefore, the maximum longitudinal displacement of the existing tunnel caused by the surcharge is large, and it increases rapidly as the buried depth decreases. As can be seen from the figure, as the tunnel buried depth
increases, the maximum displacement change rate of the tunnel gradually decreases for different tunnel–surcharge spacing
. The reason is that the external load corresponding to the surcharge load has little influence on the tunnel with a small embedded depth.
5.2. Tunnel Buried Depth
Similarly,
Figure 14 shows the curve of the maximum longitudinal displacement of the tunnel and the tunnel–load spacing
. For different buried tunnel depths
, the maximum longitudinal displacement of the tunnel changes at different rates as the surface-to-tunnel spacing
increases, and the rate of change gradually increases. However, as the tunnel buried depth
increases, the change becomes less pronounced, indicating that the existing tunnel is relatively less affected by overloading.
5.3. Tunnel–Surcharge Angle
In the following analysis, the tunnel model in the previous analysis remains the same, and only the tunnel–surcharge included angle
is changed.
Figure 15 shows the relationship between the tunnel–surcharge angle
and the maximum longitudinal displacement
of the existing tunnel at different tunnel burial depths, where the tunnel–surcharge angle
ranges from
to
. As shown in
Figure 15, for different tunnel burial depths, the maximum longitudinal displacement
of the existing tunnel follows an “S-shaped curve” trend that decreases as the tunnel–surcharge angle
increases. For the same tunnel–surcharge angle
, as the tunnel burial depth increases, the maximum longitudinal displacement of the existing tunnel decreases proportionally, indicating that the influence of the surcharge on the tunnel is linearly related to the burial depth of the existing tunnel. Furthermore, when the tunnel depth
= 9 m, the maximum displacement of the existing tunnel caused by overloading is close to the standard allowable value of
. When the buried depth of the tunnel
= 24 m, the maximum longitudinal displacement of the tunnel is approximately 10 mm, indicating that the tunnel is still greatly affected by the overload. Therefore, changing the depth of the tunnel cannot completely remove the effect of the overload on the existing tunnel.
5.4. Surface Surcharge Size
Based on the model parameters of new and existing tunnels, only the tunnel–load spacing
is changed in the following analysis.
Figure 16 shows the relationship between the maximum longitudinal displacement of the tunnel and the length
of the surcharge. As shown in the figure, for a surcharge with a fixed width and the same surcharge and tunnel spacing, the maximum longitudinal displacement of the tunnel increases gradually as the length of the surcharge increases, but the growth rate gradually decreases. As the surcharge length increases from 8 m to 72 m, the maximum longitudinal displacement of the tunnel increases significantly. When the surcharge length increases from 72 m to 96 m, the increase in the maximum displacement is only 1%. For the same tunnel, when the length of the surcharge is greater than 72 m, the maximum displacement of the tunnel tends to be stable for different surcharge spacing
. As the tunnel–load spacing
increases, the maximum longitudinal displacement of the tunnel decreases considerably. The analysis shows that the maximum displacement of the existing tunnel is affected by the space between the overload and tunnel.
Similarly,
Figure 17 shows the relationship between the maximum displacement of the tunnel and the width of the load for different tunnel–load spacing and a constant load length. As the surface surcharge width increases from 8 m to 72 m, the maximum displacement of the tunnel gradually increases, and the change rate gradually decreases. As the load width increases to 96 m, the maximum displacement of the tunnel gradually decreases. The increase in maximum displacement tends to be stable when the load width is greater than 72 m. The values of maximum longitudinal displacement of the tunnel for different spacing
converge toward the same value, and the rate of change tends towards 0 as the width
increases. Therefore, the maximum longitudinal displacement of the tunnel is no longer affected by the tunnel–load spacing as the width of the load increases.
According to the above analysis, the maximum longitudinal displacement of the tunnel is related to the buried depth of the tunnel , the tunnel–surcharge spacing , the surcharge size , and the tunnel–surcharge angle . Next, previously published cases of the response of an existing tunnel to the overload are analyzed to verify the reliability and practicability of the prediction formula for the maximum longitudinal displacement of the tunnel.
7. Conclusions
This paper presents a theoretical method for efficiently predicting the longitudinal deformation of existing tunnels under overloading. The following conclusions can be drawn:
(1) The reliability and applicability of the proposed method were verified by comparing the results of finite element simulations of field test data and the calculation results of three simplified elastic analysis methods based on different foundation bed coefficients.
(2) Based on the Boussinesq elastic solution, the additional load on the existing tunnel was obtained. A Euler–Bernoulli beam on a Pasternak foundation was used as a simplified model to analyze the stress of the existing tunnel. Using the corrected reaction coefficient of the foundation bed, the differential equation of tunnel deformation was established, and the longitudinal displacement matrix of the tunnel was calculated using the finite difference method.
(3) The parameters of the surcharge load–tunnel model were analyzed, and the effects of the buried depth of the tunnel, the size of the surcharge load, the relative positions of the tunnel and surcharge, and the relative stiffness of the tunnel soil on the maximum displacement of the existing tunnel were calculated. An empirical formula for the maximum longitudinal displacement of the existing tunnel subjected to surface surcharge is proposed. The contents of this research can provide a basis for the theoretical verification of the deformation response of an existing tunnel subjected to adjacent surface surcharge. It can be used to quickly predict the response of a tunnel in the initial design stage.