Next Article in Journal
A Nonlinear CFD/Multibody Incremental-Dynamic Model for A Constrained Mechanism
Previous Article in Journal
Special Issue on “The Application of Quantum Mechanics in Reactivity of Molecules”
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Characterizing and Visualizing the Impact of Energy Storage on Renewable Energy Curtailment in Bulk Power Systems

1
Department of Electrical Engineering, Tsinghua University, Beijing 100084, China
2
State Grid Qinghai Electric Power Company, Xining 810008, China
3
New Energy Industry Research Center, Qinghai University, Xining 810016, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2021, 11(3), 1135; https://doi.org/10.3390/app11031135
Submission received: 25 December 2020 / Revised: 21 January 2021 / Accepted: 22 January 2021 / Published: 26 January 2021

Abstract

:
The uncertain natures of renewable energy lead to its underutilization; energy storage unit (ESU) is expected to be one of the most promising solutions to this issue. This paper evaluates the impact of ESUs on renewable energy curtailment. For any fixed renewable power output, the evaluation model minimizes the total amount of curtailment and is formulated as a mixed integer linear program (MILP) with the complementarity constraints on the charging and discharging behaviors of ESUs; by treating the power and energy capacities of ESUs as parameters, the MILP is transformed into a multi-parametric MILP (mp-MILP), whose optimal value function (OVF) explicitly maps the parameters to the renewable energy curtailment. Further, given the inexactness of uncertainty’s probability distribution, a distributionally robust mp-MILP (DR-mp-MILP) is proposed that considers the worst distribution in a neighborhood of the empirical distribution built by the representative scenarios. The DR-mp-MILP has a max–min form and is reformed as a canonical mp-MILP by duality theory. The proposed method was validated on the modified IEEE nine-bus systems; the parameterized OVFs provide insightful suggestions on storage sizing.

1. Introduction

The consumption of fuel fossils has considerably soared in the past few decades due to the industrialization and economic development worldwide, resulting in the issues of energy shortage and environmental pollution. Under this background, the sector of renewable energy generation (REG) springs up; by 2019, the global installed capacity of wind and solar generation, two dominating technologies of REG, expanded to 651 [1] and 627 GW [2], respectively. Such a high penetration level of REG will cause difficulties to the power system operation: On the one hand, the inherent uncertainty of renewable energy tests the supply reliability and operating security of the power grid [3,4]; on the other hand, the imbalance between supply and demand, as well as the transmission congestion, underutilizes the renewable energy and induces a lot of energy curtailment [5]. With the aim to reduce the renewable energy curtailment, researchers pin their hopes on the energy storage unit (ESU), which can store the excessive renewable energy and discharge it when needed, thus cutting down the spillage.
The planning of ESUs in support of reducing the renewable energy curtailment has been widely investigated. Dui X. et al. proposes a two-stage method to determine the optimal capacity of battery energy storage to decrease wind power curtailment in grid-connected wind farms [6]; the first stage schedules the unit commitment of thermal generators and the wind farm output, and the second stage optimizes the operational strategies of battery energy storage while penalizing the curtailment in the objective function. In Reference [7], a chance-constrained model is developed to address the energy storage sizing problem, where the constraint on total curtailment rate is satisfied given a confidence level. The optimal placement framework for ESU is proposed in Reference [8], which minimizes the hourly social cost and maximizes wind power utilization within a power system with high wind penetration.
In the area of operation, an ESU, together with demand response, is used in Reference [9] to reduce curtailed wind energy; moreover, the role of generation mix on the curtailed wind energy is analyzed; then, additional reductions in the curtailed wind energy by demand response are quantified. Pumped hydro storage is technically mature and economical for storing electrical energy on a large scale; it is optimally scheduled in Reference [10] to properly deal with wind energy curtailment cost, total social cost, and also the ESUs’ revenue. As a promising ESU, compressed air energy storage is being scrutinized as a viable and economically appealing option for mitigating wind curtailment [11]. Additionally, the feasibility and effectiveness of hybrid energy storage for smoothing photovoltaic power fluctuations are evaluated in Reference [12], considering active power curtailment.
In the REG-concerned problems, it is a critical issue to characterize the uncertainty of renewable power. Stochastic programming relies on representative scenarios to build an empirical probability distribution of uncertainty [13]. It is used in Reference [14], where the expected daily operation cost of the distribution network is minimized under the empirical distribution by sample average approximation; meanwhile, a stochastic chance-constraint is employed to ensure the amount of total energy-saving. In Reference [15], the stochastic capacity expansion planning of remote microgrids with wind farms and energy storage is explored; the scenarios are generated by Monte Carlo simulations. Another method is robust optimization, which describes the uncertainty with an uncertainty set that encloses all the possible candidates of uncertain realizations [16]. A typical application in power system is robust unit commitment; in Reference [17], a two-stage robust unit commitment model with wind power and pumped storage hydro is proposed, to accommodate wind output uncertainty, providing a robust day-ahead unit commitment schedule for the thermal generators that minimizes the total cost under the worst wind-power output scenario. Moreover, the robust energy and reserve dispatch under variable renewable generation are investigated in Reference [18]. Dehghan et al. propose a two-stage robust model for joint transmission and energy storage expansion planning in wind-farm-integrated power systems [19]; a polyhedral uncertainty set encapsulates all the possible values of wind power and demand.
Nonetheless, it is generally acknowledged that the performance of stochastic optimization depends on the size of samples; limited data will injure the exactness of empirical distribution, while incorporating too many scenarios may toughen the solution, especially when the stage-independence in a multi-period problem is considered via the scenario tree [20]. Furthermore, the application of robust optimization is limited by its conservativeness, because the worst case will hardly happen [21]. Therefore, distributionally robust optimization is developed [22], which assumes that the probability distribution of uncertainty varies within an ambiguity set that is a close neighborhood of the empirical distribution. In this regard, this method compromises the conservativeness of stochastic programming and robust optimization. In the area of power systems, distributionally robust optimization has been used in co-optimization of energy and reserve dispatch [23], energy hub planning [24] and operation [25], and hydro–thermal–wind economic dispatch [26].
Furthermore, the existing literature related to storage rarely characterizes the impact of storage capacities on specific indices, such as operational economy, system flexibility, system security margin, renewable energy utilization, and so on. Here, we expect to derive the explicit relation between renewable energy curtailment and the power/energy capacities of ESUs, which will be useful in practical applications. To this end, we used multi-parametric programming, which is a systematic theory and technique that subdivides the parameter set into characteristic regions where the optimal values are given as explicit functions of the parameters [27]; hence, if we treat the power and energy capacities as parameters, such functions provide the decision-maker with insightful information about the impact of ESU on renewable energy curtailment.
Multi-parametric programming has been used in some related works. In Reference [28], the impact of ESU on the operational economy of distribution network is discussed; similarly, Reference [29] focuses on the economic influence of ESU in energy hub; however, the complementarity constraints on the charging and discharging behaviors of ESUs are not imposed by binary variables in these two papers, which is not applicable in this paper, as illustrated in Section 2.3. The evaluation model in Reference [30] follows the scheme of robust optimization.
This paper combines the distributionally robust optimization and multi-parametric programming, and proposes a distributionally robust multi-parametric mixed-integer linear program (DR-mp-MILP) to assess the impact of energy storages on renewable energy curtailment under distributional uncertainty. The DR-mp-MILP has a max–min form and is reformed as a canonical mp-MILP by duality theory; the results from the IEEE nine-bus system tests validate the effectiveness and performance of our proposed method, and provide insightful suggestions on storage sizing.
The rest of this paper is organized as follows: In Section 2, the fundamental models of the power system are first introduced, followed by an illustrative example about the necessity to use binary variables to avoid simultaneous charging and discharging. In Section 3, the multi-parametric formulations are proposed. Section 4 presents the solution to mp-MILP, and Section 5 shows the results of case studies. Discussions are given in Section 6.

2. Basic Models

This section introduces the fundamental models for the problem under study. The operating constraints of power system are first given, followed by the objective function to optimize the renewable energy curtailment. The power flows in the network are described by the renowned direct-current power flow model, which is loss-less and neglects the reactive power distribution. We make some clarifications in the revised manuscript. Specifically, an example is designed to illustrative that it is inevitable to use binary variables to impose complementarity constraints on the discharging and charging behaviors of an ESU.

2.1. Operating Constraints

Considering the multi-period operation of a power system with renewable plants and ESUs, the constraints are gathered as shown below:
i G p i t g + j S ( p j t s d p j t s c ) + k W p k t r = q D p q t d , t T
f l i B π l i p i t n f l , l L , t T
p i g n p i t g p i g m , r i p i t + 1 g p i t g r i + , i G , t T
0 p j t s c P j s b j t s , 0 p j t s d P j s ( 1 b j t s ) , j S , t T
α j l E j s e j 0 + h τ = 1 t ( p j τ s c η j c p j τ s d / η j d ) E j s , j S , t T
t T p j t s c η j c = t T p j t s d / η j c , j S
0 p k t r p k t r m , Δ p k t r m = p k t r m p k t r , k W , t T
where (1) describes the system-wise power balance. Moreover, (2) says the active power flow in line l cannot exceed its transmission capacity; π l i is the power transfer distribution factor from bus i to line l ; p i t n represents the net power injection at bus i in period t , which depends on the production of generator ( p i t g ), the power exchange with ESU ( p i t s c / p i t s d ), the dispatched renewable power ( p i t r ), as well as the load ( p i t d ), if there is any. Moreover, (3) restricts the output and ramping rates of generators.
The charging and discharging behaviors of ESUs are constrained by (4), where P j s is the power capacity; when the binary indicator is b j t s = 1 / 0 , the ESU j operates under the charging/discharging mode in period t , with a corresponding power lower than P j s . The state-of-charge (SoC) dynamics of ESU is expressed by (5), where E j s is the energy capacity, and α j l is a constant coefficient indicating the lower bound of SoC; e j 0 is the initial level of SoC, and h is the duration of one time slot, i.e., one hour; besides, the terminal SoC is set to the initial state e j 0 , implied by (6).
In (7), p k t r m is the available renewable power in renewable plant k in period t , which is uncertain and determined by the weather conditions; hence, the dispatched renewable power, p k t r , cannot exceed p k t r m . Meanwhile, the curtailed renewable power is defined as Δ p k t r .

2.2. Objective Function

For the purpose of reducing the renewable energy curtailment, the objective function is as follows:
min h k W t Δ p k t r

2.3. Illustration: Necessary Charging–Discharging Complementarity Constraint

For a storage-concerned economic dispatch problem, the complementarity constraints on charging and discharging are, in most cases, naturally satisfied without using binary variables. However, in this paper, such binary variables are necessary because, in the renewable energy curtailment problem, simultaneous charging and discharging can act as a load, which consumes a certain amount of renewable energy and thus reduces the curtailment. Here, we give a simple example for illustration: The system consists of one bus, one ESU, and one wind turbine. Let T = 1, Ps = 1 MW, Es = 2 MWh, e0 = 2 MWh, ηc = ηd = 0.9, pd = 0.6MW, prm = 1MW; for brevity, the bus and time subscripts are omitted.
If we use the binary variable as (4), simultaneous charging and discharging is not permitted; meanwhile, the SoC level has reached its ceiling. Consequently, 0.6 MWh of wind energy is consumed by the load, and the rest 0.4 MWh is curtailed.
However, if we do not use the binary variable, consider the following strategy: p s c = 1   MW , p s d = 0.81   MW ; then, e 1 = e 0 + h ( p s c η c p s d / η d ) = 2   MWh . According to the power balance condition in (1), the dispatched wind power p r = 0.79   MW , and thus the curtailed wind energy, is 0.21 MWh. There is no doubt such a strategy is feasible while the curtailment is lower than that in the case with binary variable.
This example verifies that the binary complementarity indicator is necessary in this paper; otherwise, simultaneous charging and discharging will happen.

3. Multi-Parametric Formulations

This section proposes the deterministic and distributionally robust mp-MILP formulations.

3.1. Deterministic mp-MILP

To give the closed form of deterministic mp-MILP, we first define the following vectors:
  • Parameter variable vector: θ = [ P j s , E j s , j S ] T .
  • Binary variable vector: y ^ = [ b j t s , j S , t T ] T .
  • Uncertain variable vector: w ^ = [ p k t r m , k W , t T ] T .
  • Continuous variable vector: x ^ is a column vector and encloses all the remaining continuous variables in (1)–(7).
Then, any equality in (1)–(7) can be replaced by two opposite inequalities; for example, (6) is equivalent to the following:
t T p j t s c η j c t T p j t s d / η j c , t T p j t s c η j c t T p j t s d / η j c , j S
By far, the closed form of deterministic mp-MILP can be written as follows:
v D ( θ ) = min x ^ , y ^ c ^ T x ^ s . t . A ^ x ^ + B ^ y ^ b ^ + C ^ w + F ^ θ , θ Θ
where A ^ ,     B ^ ,     b ^ ,     C ^ ,     F ^ ,     and   c ^ are coefficient matrices or vectors derived from (1) to (8). Note that, in the deterministic model (10), w is given; θ is the parameter, so it is not decision variable. v D ( θ ) is the optimal value function parameterized in θ ; in other words, it gives the optimal value with any θ in Θ where the parameter set Θ is assumed to be a polyhedron:
Θ = { θ | S θ H }
Set Θ consists of the concerned constraints of decision-makers on θ . Basically, θ includes the power and energy capacities of ESUs, so it should be non-negative; taking the investment cost for example, which relates to the power and energy capacities, the total cost cannot exceed a given budget Π . Nevertheless, Θ can be freely defined.

3.2. Ambiguity Set

In reality, the vector w is uncertain due to the inherent natures of renewable power. Combining the scenario-based stochastic optimization and robust optimization, distributionally robust optimization is employed here to optimize the expected renewable energy curtailment, considering the worst probability distribution in a neighborhood of the empirical one built by the representative scenarios.
Given the set 𝒲 0 = { w s } s = 1 S composed of S representative scenario and their corresponding probabilities { ρ s } s = 1 S , we first build the empirical probability distribution, 𝒫 0 , by using the following:
𝒫 0 = 1 S s = 1 S δ ρ s 0
where δ ρ s 0 is the Dirac measure on ρ s 0 ; thus, 𝒫 0 is discrete and supported on 𝒲 0 .
To construct a neighborhood of P 0 , i.e., the ambiguity set, we need to define the distance between two probability distributions. Given an S -dimensional distribution 𝒫 supported on 𝒲 0 , whose s -th probability is ρ s , the conditions ρ s [ 0 , 1 ] and s = 1 S ρ s = 1 are satisfied. The infinite norm-based distance between 𝒫 and 𝒫 0 is as follows [31]:
d I ( 𝒫 , 𝒫 0 ) = 𝒫 𝒫 0
Thus, the ambiguity set based on (13) is developed as follows:
I ε ( 𝒫 0 ) = { 𝒫 | d I ( 𝒫 , 𝒫 0 ) ε , ρ [ 0 , 1 ] S , 1 T ρ = 1 } = { ρ s ρ s 0 ε , ρ s 0 ρ s ε , s = 1 , , S 0 ρ s 1 , s = 1 , , S ; s = 1 S ρ s = 1 }
where ρ = [ ρ 1 , , ρ S ] T and 1 is an all-one column vector with compatible dimensions; ε is an arbitrarily given radius of the ambiguity set, indicating that the infinite norm-based distance between 𝒫 and 𝒫 0 does not exceed ε; meanwhile, a larger ε reflects a higher model conservativeness because some worse distributions are considered. The value of ε can be chosen according to the following [31]:
ε = 1 2 S ln 2 S 1 β
where β is the confidence level; such a choice of ε guarantees the following:
Pr { 𝒫 𝒫 0 ε } β
Furthermore, I ε ( 𝒫 0 ) is a polyhedron and can be expressed as ( 𝒫 0 ) = { ρ | Q ρ U } , where Q and U are derived from (14).

3.3. Distributionally Robust mp-MILP and Reformulation

If we only consider the empirical distribution, 𝒫 0 , the expected renewable energy curtailment, i.e., s = 1 S ρ 0 ( c ^ T x ^ s ) , is minimized. As mentioned above, the distributionally robust formulation minimizes the expectation under the worst distribution in the ambiguity set I ε ( 𝒫 0 ) , giving rise to the following DR-mp-MILP:
v R ( θ ) = max ρ min x ^ s , y ^ s , s s = 1 S ρ s ( c ^ T x ^ ) s . t . A ^ x ^ s + B ^ y ^ s b ^ + C ^ w s + F ^ θ , s = 1 , S Q ρ U :   λ θ Θ
where the vectors with subscript s correspond to the representative scenario w s ; λ is the vector of dual variables.
An important feature in (17) is that, given a θ , the feasible set of outer maximization problem is disjoint from that of inner minimization problem; thus, dualizing the outer problem results in the single-level parametric problem shown below:
v R ( θ ) = min λ , x ^ s , y ^ s , s λ T U s . t . A ^ x ^ s + B ^ y ^ s b ^ + C ^ w s + F ^ θ , s = 1 , S Q T λ = [ c ^ T x ^ 1 , , c ^ T x ^ S ] ,   λ 0 θ Θ
Therefore, to calculate v R ( θ ) entails solving the mp-MILP(18). For brevity, we aggregate all the coefficients, variables, and constraints in (18), to rewrite it as the canonical mp-MILP:
v R ( θ ) = min x , y c T x s . t . A x + B y b + F θ ,   θ Θ
where x = [ x ^ 1 T , , x ^ S T , λ T ] T , y = [ y ^ 1 T , , y ^ S T ] T ; the coefficients A, B, b, F and c are accordingly assembled. Specifically, the term C ^ w s is merged into b .

4. Solution Methodology

The solution method in this section is based on the mild assumption that the system is feasible given any w s without ESUs ( θ = 0 ), or equivalently, without dispatching ESUs ( θ 0 ). This implies that (19) is always feasible regardless of y and θ .
Then, we discuss the properties of v R ( θ ) . Binary vector y denotes the charging and discharging pattern of ESUs, and has a finite number of candidates, written as Y = { y i } i = 1 I . Given any y i Y , mp-MILP (19) degenerates into an mp-LP as
v i R ( θ ) = min x , y c T x s . t . A x ( b B y i ) + F θ : γ θ Θ
where v i R ( θ ) is the corresponding optimal value function; γ is the vector of dual variables. As a result, v R ( θ ) in mp-MILP (19) can be calculated by comparing v i R ( θ ) , y i Y in a pointwise minimum way.
Given a θ , consider the dual problem of the mp-LP (20):
v i R ( θ ) = max γ Γ γ T ( b i + F θ ) θ Θ
where Γ = { γ | A T γ = c , γ 0 } , and b i = b B y i . The duality theory of linear programming indicates that the primal problem (20) and the dual problem (21) share the same optimal value v i R ( θ ) for any θ ; as θ varies in Θ , the optimal solution can always be found at one of the extreme points of Γ . Thus, v i R ( θ ) can be constructed as follows:
v i R ( θ ) = max { γ i T ( b i + F θ ) } ,   γ i vert ( Γ ) , θ Θ
Therefore, v i R ( θ ) is piecewise linear and convex because the point-wise maximum operation preserves convexity; each piece corresponds to a subset of Θ , called critical region (CR). Further, v R ( θ ) is also piecewise linear but generally not convex.
In Reference [32], a decomposed algorithm is proposed to solve mp-MILP (19), which takes the following four steps:
  • Step 1: Solve MILP by solving MILP (19) by regarding θ as decision variables; the optimal solution is y 1 .
  • Step 2: With the fixed y 1 , solve mp-LP (20) by POP(parametric optimization) toolbox [33]. The results include the piecewise linear v 1 R ( θ ) , in detail, the slopes, intercepts, and the corresponding M 1 CRs.
  • Step 3: For the m -th CR with its corresponding piece of v 1 m R ( θ ) , build the following MILP, to find a new y that gives a better optimal value, i.e.,
    min x , y , θ c T x s . t . A x + B y b + F θ ,   θ C R m c T x v 1 m R ( θ ) , y y 1 2 2 1
    where the last constraint excludes the solutions that have been found, and multiplies as the iteration process. The optimal solution of (23), if feasible, is y 1 m * , which, along with the m -th CR, solves an mp-LP like (20), whose optimal value function is v 1 m R * ( θ ) . Then, the pointwise minimum comparison between v 1 m R * ( θ ) and v 1 m R ( θ ) gives v 2 m R ( θ ) , as well as the corresponding CRs.
After checking M 1 CRs, the optimal value function of mp-MILP (19) updates to v 2 R ( θ ) with M 2 CRs.
  • Step 4: With v m 2 R ( θ ) , m = 1 , , M 2 and its corresponding m -th CR, go back to Step 3, until (19) finds no new for M K CRs, the algorithm terminates, and the solution of mp-MILP (19) is concluded as follows:
    v R ( θ ) = { ν 1 θ + μ 1 , θ C R M 1 ν K θ + μ K , θ C R M K
    where υ k / μ k is the slope/intercept of the k -th piece of v R ( θ ) .
Actually, v R ( θ ) is a pointwise minimum comparison among a group of piecewise linear convex functions, and every single CR in (24) is a convex set, while some CRs may share the same υ k / μ k . Interested readers are recommended Reference [32].

5. Results

To validate the proposed method, the modified IEEE nine-bus system is utilized, which is sketched in Figure 1. Two generators locate at Bus 1 and Bus 2; one wind farm and one ESU connect to Bus 3. The system data are provided in Table 1. Considering a time horizon of 24 h, i.e., T = 24   h , the load curve is drawn in Figure 2. Ten averagely weighted representative scenarios of wind power are generated by the weather data in Qinghai Province, China, 2019, as in Figure 3. Given β = 95 % , the value of ε is set to 0.3, according to (15). Complete data are provided in Reference [34].
Furthermore, we define the parameter set as follows:
Θ = { θ = [ P s ( MW ) , E s ( MWh ) ] T | 0 P s 100 , 0 E s 150 }

5.1. Results of Deterministic mp-MILP

Given different scenarios of wind power, (10) turns into a canonical mp-MILP like (19), and it can be solved by the algorithm in Section 4. Taking Scenario 3 as an example, the optimal value function is drawn in Figure 4.
It can be seen that, without an ESU, the total renewable energy curtailment under Scenario 3 reaches 45.5 MWh. By employing an ESU whose power/energy capacity is higher than 22.75 MW/81.83 MWh, respectively, the curtailment reduces to zero.
The parameter set is divided into three critical regions, named CR1, CR2, and CR3. The polyhedral representations of them are as follows:
C R 1 = { θ = [ P s , E s ] T | 0 P s 100 0 E s 81.83 E s 3.60 P s } C R 2 = { θ = [ P s , E s ] T | 0 P s 22.75 0 E s 150 3.60 P s E s } C R 3 = { θ = [ P s , E s ] T | 22.75 P s 100 81.83 E s 150 }
Then, the corresponding optimal value functions are the following:
v R ( θ ) = { 45.5 [ 0 , 0.56 ] θ ,   θ C R 1 45.5 [ 2.0 , 0 ] θ ,       θ C R 2 0 ,     θ C R 3
From (26), we see that the sensitivity of renewable energy curtailment to the capacities of ESU is different as θ changes. When θ falls into CR1, 1 MWh increment of energy capacity will lead to a 0.56 MWh decline of curtailment, while the increase of power capacity makes no sense, implying that the impact of power capacity has saturated; similarly, when θ falls into CR2, a 1 MWh increment of power capacity will cause a 2 MWh decline of curtailment, while raising the energy capacity does not take effect. Moreover, when θ falls into CR3, the curtailment is zero.
Furthermore, the boundary between CR1 and CR2, the red line in Figure 4b, gives valuable information. The points on this boundary are efficient in fully using the capacities of ESUs; from any point on this boundary, increasing power or energy capacity alone will not help reduce the curtailment. Specifically, on this boundary, the ratio of energy capacity to power capacity is 3.60; such a ratio is useful in sizing ESUs in practice.
From an economic perspective, consider the investment cost of ESU as Π = κ P P s + κ E E s , where κ P / κ E is the unit cost of power/energy capacity. Regardless of the value of κ P and κ E , the isocost curves are a cluster of parallel straight lines, as seen from the dashed lines in Figure 5. Combining with Figure 4a, we can find that, given a budget, the parameter on the red line enjoys the minimum renewable energy curtailment, as compared with other points that cost the same.

5.2. Results of Distributionally Robust mp-MILP

The optimal value function in mp-MILP (19) is visualized in Figure 6. The parameter set is divided into much more CRs, as compared with the situation in the above deterministic test. As mentioned in Section 4, v R ( θ ) is a pointwise minimum comparison among a group of piecewise linear convex functions; every single CR is a convex set, while some CRs share the same υ k / μ k , which are filled with the same color in Figure 6b.
Similarly to Figure 4a, we draw a red line in Figure 6a, on which the points are efficient in fully using the capacities of ESUs from an economic perspective; although this line is not strictly accurate, it does provide a reference for the ratio of energy capacity to power capacity 150/45.49 ≈ 3.3 in the sense of distributionally robustness.

5.3. Results with Different Values of ε

This part investigates the impact of parameter ε on the renewable energy curtailment. Parameter ε reflects the size of ambiguity set and the conservativeness of the distributionally robust mp-MILP. The value of ε recommended by (15) is 0.3; we set it to 0.06 (20% × 0.3), 0.18 (60% × 0.3), 0.3 (100% × 0.3), and 0.42 (140% × 0.3) for comparison. The respective optimal value functions are drawn in Figure 7. By observation, as the value of ε, the optimal value function is globally raised. From ε = 0.06 to ε = 0.42, the total renewable energy curtailment without ESUs increases from 116.3 to 142.5 MWh by 22.5%; if an ESU with power/energy capacity of 100 MW/150 MWh is installed, the curtailment rises up from 34.44 to 54.23 MWh by 57.46%.
According to (15), the value of ε is mainly determined by S, the size of representative scenarios; as the S approaches infinity, ε becomes zero, which means the ambiguity set only includes the empirical probability distribution that is supposed to be exact; meanwhile, the curtailment drops. This concludes the importance of data availability.

5.4. Results with Different Renewable Energy Penetration Levels

To explore the impact of renewable energy penetration levels on the curtailment, we introduce a ratio r = 0.4, 0.6, 0.8, 1.0, and 1.2 and multiply it with the wind power in every representative scenario; the respective optimal value functions are depicted in Figure 8. When r = 1.2, the renewable energy curtailment reaches 230.3 MWh without ESUs; when r = 0.4, only about 4 MWh of renewable energy is curtailed. For r = 0.4, 0.6, 0.8, the curtailment can be reduced to zero with some parameters in Θ .
More specifically, the optimal value functions can suggest the critical capacities of ESU that can eliminate the curtailment, as θ = [ 11.1 MW , 16.7 MWh ] for r = 0.4 and θ = [ 33.3 MW , 66.7 MWh ] for r = 0.6.

6. Discussion

This paper evaluates the impact of energy storage on renewable energy curtailment, using multi-parametric programming; the uncertainty of renewable power is characterized by the ambiguity from following the paradigm of distributionally robust optimization. The original max–min mp-MILP was reformulated into a canonical one by duality theory.
The tests on modified IEEE nine-bus corroborate that the multi-parametric programming framework calculates the explicit relation between ESU capacities and renewable energy curtailment, which enjoys admirable interpretability and convenience for visualization. Specifically, the reference for the ratio of energy capacity to power capacity is concluded; the ratio is about 3~4, with the aim to reduce renewable energy curtailment, although it is case by case.
Because that the proposed solution method of multi-parametric mixed-integer linear program relies on sampling points from the parameter space, the computational complexity is exponentially related to the size of parameter vector θ ; nevertheless, with any fixed θ , it entails solving a linear program, so computational time is generally moderate.
The visualization can be done in, at most, a three-dimensional space. With the growth of the size of θ , it could be difficult in visualization, but we can still derive the parameterized optimal value function, which helps explicitly characterize the impact of parameters.
The results derived from the proposed method, mainly the optimal value function v R ( θ ) , give valuable implications on storage sizing. To find the most effective sizing strategy in reducing the curtailment, the decision-maker can use the following sizing model:
min θ v R ( θ )   s . t .   θ Θ
To find the most cost-efficient one that means the highest ratio of curtailment reduction to investment cost, use this model:
max θ v R ( 0 ) v R ( θ ) γ T θ   s . t .   θ Θ
where v R ( 0 ) is the curtailment without storage, and γ is the column vector related to the unit investment cost of storage capacity.
To compromise the investment cost and the effectiveness of reducing the curtailment, we resort to the following Nash Bargaining model:
max θ ( Γ γ T θ ) ( v R ( 0 ) v R ( θ ) )   s . t .   θ Θ
Therefore, it is shown that the proposed method is helpful in practice. Furthermore, due to the distributionally robustness, an accurate forecast of renewable power output is not required; only an empirical distribution built by historical data is need. Our model considers all the distributions that are closed to the empirical one, and thus guarantees the performance of evaluation and sizing.

Author Contributions

Conceptualization, Z.G. and W.W.; methodology, W.W.; software, S.H.; validation, Z.G. and W.W.; writing—original draft preparation, Z.G.; writing—review and editing, W.W., S.H., and L.C.; supervision, S.M.; project administration, L.C., J.L. and M.W.; funding acquisition, S.H. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the special grant from the Headquarters of State Grid Corporation of China, grant number SGQH0000DKJS2000127.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Acknowledgments

This work is supported by the special grant from the Headquarters of State Grid Corporation of China (SGQH0000DKJS2000127).

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

The major symbols and notations used throughout the paper are defined below, for quick reference. Others are clarified after their first appearance, as required.
Indices and sets
t T Index of time periods
l L Index of transmission lines
i G Index of buses with generators
j S Index of buses with storages
k W Index of buses with renewable plants
q D Index of load buses
i B Index of buses
Abbreviations
CRCritical region
ESUEnergy storage unit
MILPMixed integer linear program
mp-MILPMulti-parametric MILP
DR-mp-MILPDistributionally robust mp-MILP
REGRenewable energy generation
Decision Variables
p i t g Production of generator i in period t
p j t s d / p j t s c Discharging/charging power of ESU j in period t
p k t r Dispatched renewable power of plant k in period t
Δ p k t r Curtailed renewable power of plant k in period t
Parameters
p k t r m Dispatchable renewable power of plant k in period t
p q t d Load at bus q in period t
f l Transmission capacity in line l
p i g n / p i g m Lower/upper bound of generation capacity of generator i
r i / r i + Downward/upward ramping rate limits of generator i
η j c / η j d Charging/discharging efficiency of ESU j in period t
P j s / E j s Power/energy capacity of ESU j

References

  1. Global Wind Statistic 2019. Available online: https://gwec.net/ (accessed on 25 March 2020).
  2. IEA-PVPS Annual Report 2019. Available online: http://www.iea-pvps.org/annual-reports/ (accessed on 9 April 2020).
  3. Xie, L.; Carvalho, P.; Ferreira, L. Wind integration in power systems: Operational challenges and possible solutions. Proc. IEEE. 2011, 99, 214–232. [Google Scholar] [CrossRef]
  4. Shrestha, T.; Karki, R. Utilizing energy storage for operational adequacy of wind-integrated bulk power systems. Appl. Sci. 2020, 10, 5964. [Google Scholar] [CrossRef]
  5. Burke, D.; O’Malley, M. Factors influencing wind energy curtailment. IEEE Trans. Sustain. Energy 2011, 2, 186–193. [Google Scholar] [CrossRef] [Green Version]
  6. Dui, X.; Zhu, G.; Yao, L. Two-stage optimization of battery energy storage capacity to decrease wind power curtailment in grid-connected wind farms. IEEE Trans. Power Syst. 2018, 33, 3296–3305. [Google Scholar] [CrossRef]
  7. Guo, Z.; Wei, W.; Chen, L.; Xie, R.; Mei, S. Sizing energy storage to reduce renewable power curtailment considering network power flows: A distributionally robust optimization approach. IET Renew. Power Gener. 2020, 14, 3273–3280. [Google Scholar] [CrossRef]
  8. Ghofrani, M.; Arabali, A.; Etezadi-Amoli, M.; Fadali, M. A framework for optimal placement of energy storage units within a power system with high wind penetration. IEEE Trans. Sustain. Energy 2013, 4, 434–442. [Google Scholar] [CrossRef]
  9. Bitaraf, H.; Rahman, S. Reducing curtailed wind energy through energy storage and demand response. IEEE Trans. Sustain. Energy 2018, 9, 228–236. [Google Scholar] [CrossRef]
  10. Hozouri, M.; Abbaspour, A.; Fotuhi-Firuzabad, M.; Moeini-Aghtaie, M. On the use of pumped storage for wind energy maximization in transmission-constrained power systems. IEEE Trans. Power Syst. 2015, 30, 1017–1025. [Google Scholar] [CrossRef]
  11. Cleary, B.; Duffy, A.; O’Connor, A.; Conlon, M.; Fthenakis, V. Assessing the economic benefits of compressed air energy storage for mitigating wind curtailment. IEEE Trans. Sustain. Energy 2015, 6, 1021–1028. [Google Scholar] [CrossRef] [Green Version]
  12. Ma, W.; Wang, W.; Wu, X. Optimal allocation of hybrid energy storage systems for smoothing photovoltaic power fluctuations considering the active power curtailment of photovoltaic. IEEE Access. 2019, 7, 74787–74799. [Google Scholar] [CrossRef]
  13. Rirge, J.; Louveaux, F. Introduction to Stochastic Programming; Springer: New York, NY, USA, 2011. [Google Scholar]
  14. Zhang, Y.; Ren, S.; Dong, Z.; Xu, Y.; Meng, K.; Zheng, Y. Optimal placement of battery energy storage in distribution networks considering conservation voltage reduction and stochastic load composition. IET Gener. Transm. Distrib. 2017, 11, 3862–3870. [Google Scholar] [CrossRef]
  15. Hajipour, E.; Bozorg, M.; Fotuhi-Firuzabad, M. Stochastic capacity expansion planning of remote microgrids with wind farms and energy storage. IEEE Trans. Sustain. Energy 2015, 6, 491–498. [Google Scholar] [CrossRef]
  16. Bertsimas, D.; Sim, M. The price of robustness. Oper. Res. 2004, 52, 35–53. [Google Scholar] [CrossRef]
  17. Jiang, R.; Wang, J.; Guan, Y. Robust unit commitment with wind power and pumped storage hydro. IEEE Trans. Power Syst. 2012, 27, 800–810. [Google Scholar] [CrossRef]
  18. Wei, W.; Liu, F.; Mei, S.; Hou, Y. Robust energy and reserve dispatch under variable renewable generation. IEEE Trans. Smart Grid 2015, 6, 369–380. [Google Scholar] [CrossRef] [Green Version]
  19. Dehghan, S.; Amjady, N. Robust transmission and energy storage expansion planning in wind farm-integrated power systems considering transmission switching. IEEE Trans. Sustain. Energy 2016, 7, 765–774. [Google Scholar] [CrossRef]
  20. Heltsch, H.; Romisch, W. Scenario tree reduction for multistage stochastic programs. Comput. Manag. Sci. 2009, 6, 117–133. [Google Scholar] [CrossRef] [Green Version]
  21. Wei, W.; Wang, J. Modeling and Optimization of Interdependent Energy Infrastructures; Springer: Cham, Switzerland, 2020. [Google Scholar]
  22. Delage, E.; Ye, Y. Distributionally robust optimization under moment uncertainty with application to data-driven problem. Oper. Res. 2010, 58, 595–612. [Google Scholar] [CrossRef] [Green Version]
  23. Wei, W.; Liu, F.; Mei, S. Distributionally robust co-optimization of energy and reserve dispatch. IEEE Trans Sustain. Energy 2016, 7, 289–300. [Google Scholar]
  24. Cao, Y.; Wei, W.; Wang, J.; Mei, S.; Shafie-khah, M.; Catalao, J.P. Capacity planning of energy hub in multi-carrier energy networks: A data-driven robust stochastic programming approach. IEEE Trans. Sustain. Energy 2020, 11, 3–14. [Google Scholar] [CrossRef]
  25. Zhao, P.; Gu, C.; Huo, D.; Shen, Y.; Hernando-Gil, I. Two-stage distributionally robust optimization for energy hub systems. IEEE Trans. Ind. Inform. 2020, 16, 3460–3469. [Google Scholar] [CrossRef]
  26. Chen, Y.; Wei, W.; Liu, F.; Mei, S. Distributionally robust hydro-thermal-wind economic dispatch. Appl. Energy 2016, 173, 511–519. [Google Scholar] [CrossRef]
  27. Filippi, C. An algorithm for approximate multiparametric linear programming. J. Optim. Theory Appl. 2004, 120, 73–95. [Google Scholar] [CrossRef]
  28. Wei, W.; Wu, D.; Wang, Z.; Mei, S.; Catalao, J. Impact of energy storage on economic dispatch of distribution systems: A multi-parametric linear programming approach and its implications. IEEE Open Access J. Power Energy 2020, 7, 243–253. [Google Scholar] [CrossRef]
  29. Chen, X.; Si, Y.; Liu, C.; Chen, L. The value and optimal sizes of energy storage units in solar-assist cogeneration energy hubs. Appl. Sci. 2020, 10, 4994. [Google Scholar] [CrossRef]
  30. Guo, Z.; Wei, W.; Chen, L.; Dong, Z.; Mei, S. Impact of energy storage on renewable energy utilization: A geometric description. IEEE Trans. Sustain. Energy 2020, in press. [Google Scholar] [CrossRef]
  31. Zhao, C.; Guan, Y. Data-driven stochastic unit commitment for integrating wind generation. IEEE Trans. Power Syst. 2016, 31, 2587–2596. [Google Scholar] [CrossRef]
  32. Dua, V.; Pistikopoulos, E. An algorithm for the solution of multiparametric mixed integer linear programming problems. Ann. Oper. Res. 2000, 99, 123–129. [Google Scholar] [CrossRef]
  33. Oberdieck, R.; Diangelakis, N.; Papathanasiou, M.; Nascu, I.; Pistikopoulos, E.N. POP-parametric optimization toolbox. Ind. Eng. Chem. Res. 2016, 55, 8979–8991. [Google Scholar] [CrossRef]
  34. Data-AS. Available online: http://github.com/ZhongjieGuo/Papers (accessed on 24 December 2020).
Figure 1. Sketch of the modified IEEE nine-bus system.
Figure 1. Sketch of the modified IEEE nine-bus system.
Applsci 11 01135 g001
Figure 2. Load curve.
Figure 2. Load curve.
Applsci 11 01135 g002
Figure 3. Ten representative scenarios of wind power.
Figure 3. Ten representative scenarios of wind power.
Applsci 11 01135 g003
Figure 4. Results in Scenario 3 of wind power (a) optimal value function and (b) critical regions.
Figure 4. Results in Scenario 3 of wind power (a) optimal value function and (b) critical regions.
Applsci 11 01135 g004
Figure 5. Critical regions with isocost curves.
Figure 5. Critical regions with isocost curves.
Applsci 11 01135 g005
Figure 6. Results of distributionally robust multi-parametric mixed integer linear program (mp-MILP) (a) optimal value function and (b) critical regions.
Figure 6. Results of distributionally robust multi-parametric mixed integer linear program (mp-MILP) (a) optimal value function and (b) critical regions.
Applsci 11 01135 g006aApplsci 11 01135 g006b
Figure 7. Comparison of optimal value functions with different values of ε.
Figure 7. Comparison of optimal value functions with different values of ε.
Applsci 11 01135 g007
Figure 8. Comparison of optimal value functions with different renewable-energy penetration levels.
Figure 8. Comparison of optimal value functions with different renewable-energy penetration levels.
Applsci 11 01135 g008
Table 1. System data.
Table 1. System data.
ParameterValue (Unit)ParameterValue (Unit)
p 1 g m 150 MW p 1 g m 150 MW
p 2 g n 30 MW p 2 g n 30 MW
r 1 + 60 MW/h r 1 −60 MW/h
r 2 + 60 MW/h r 2 −60 MW/h
T24 hNominal total load240 MW
Installed capacity of wind farm150 MW e 0 0.5 E s
η c 90% η d 90%
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Guo, Z.; Wei, W.; Wang, M.; Li, J.; Huang, S.; Chen, L.; Mei, S. Characterizing and Visualizing the Impact of Energy Storage on Renewable Energy Curtailment in Bulk Power Systems. Appl. Sci. 2021, 11, 1135. https://doi.org/10.3390/app11031135

AMA Style

Guo Z, Wei W, Wang M, Li J, Huang S, Chen L, Mei S. Characterizing and Visualizing the Impact of Energy Storage on Renewable Energy Curtailment in Bulk Power Systems. Applied Sciences. 2021; 11(3):1135. https://doi.org/10.3390/app11031135

Chicago/Turabian Style

Guo, Zhongjie, Wei Wei, Maochun Wang, Jian Li, Shaowei Huang, Laijun Chen, and Shengwei Mei. 2021. "Characterizing and Visualizing the Impact of Energy Storage on Renewable Energy Curtailment in Bulk Power Systems" Applied Sciences 11, no. 3: 1135. https://doi.org/10.3390/app11031135

APA Style

Guo, Z., Wei, W., Wang, M., Li, J., Huang, S., Chen, L., & Mei, S. (2021). Characterizing and Visualizing the Impact of Energy Storage on Renewable Energy Curtailment in Bulk Power Systems. Applied Sciences, 11(3), 1135. https://doi.org/10.3390/app11031135

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop