Effects of Individual Client’s Competencies on Construction Project Performance: Mediating Participation Attitude and Partnership
Abstract
:1. Introduction
2. Literature Review and Hypothesis Development
2.1. Individual Client’s Competency in Construction Projects
2.2. Competency, Participation Attitude, and Partnership
2.3. Participation Attitude, Partnership, and Project Performance
3. Method
3.1. Research Model
3.2. Measurement Tools and Data Collection
3.3. Demographic Information of Data
4. Results
4.1. Results of Reliability and Validity Analysis
4.2. Results of Structural Equation Model Analysis
4.3. Results of the Direct, Indirect, and Total Effects Analysis
5. Discussion
6. Conclusions
6.1. Research Implications
6.2. Research Limitations and Future Plans
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Acıkara, Turgut, Aynur Kazaz, and Serdar Ulubeyli. 2017. Evaluations of construction project participants’ attitudes toward quality management in Turkey. Procedia Engineering 196: 203–10. [Google Scholar] [CrossRef]
- Alaghbari, Wael, Abubaker Al-Sakkaf, and Basel Sultan. 2019. Factors affecting construction labour productivity in Yemen. International Journal of Construction Management 19: 79–91. [Google Scholar] [CrossRef]
- Al-Hammad, Abdul-Mohsen, and Ibrahim Al-Hammad. 1996. Interface problems between building owners and designers. Journal of Performance of Constructed Facilities 10: 123–26. [Google Scholar] [CrossRef]
- Aliakbarlou, Sadegh, Suzanne Wilkinson, and Seosamh Benedict Costello. 2017. Exploring construction client values and qualities: Are these two distinct concepts in construction studies? Built Environment Project and Asset Management 7: 234–52. [Google Scholar] [CrossRef]
- Aliakbarlou, Sadegh, Suzanne Wilkinson, and Seosamh Costello. 2018. Rethinking client value within construction contracting services. International Journal of Managing Projects in Business 11: 1007–25. [Google Scholar] [CrossRef]
- Alvesson, Mats, Dan Kärreman, Andrew Sturdy, and Karen Handley. 2009. Unpacking the client (s): Constructions, positions and client–consultant dynamics. Scandinavian Journal of Management 25: 253–63. [Google Scholar] [CrossRef]
- Alzahrani, Jaman, and Margaret Emsley. 2013. The impact of contractors’ attributes on construction project success: A post construction evaluation. International Journal of Project Management 31: 313–22. [Google Scholar] [CrossRef]
- Anyanwu, Columbus Ikechukwu. 2013. The role of building construction project team members in building projects delivery. Journal of Business and Management 14: 30–34. [Google Scholar] [CrossRef]
- Aritua, Bernard, Nigel J. Smith, and Denise Bower. 2009. Construction client multi-projects–A complex adaptive systems perspective. International Journal of Project Management 27: 72–79. [Google Scholar] [CrossRef]
- Assaad, Rayan, Islam El-Adaway, and Ibrahim Abotaleb. 2020. Predicting project performance in the construction industry. Journal of Construction Engineering and Management 146: 04020030. [Google Scholar] [CrossRef]
- Assaf, Sadi A., Mohammed Al-Khalil, and Muhammad Al-Hazmi. 1995. Causes of delay in large building construction projects. Journal of Management in Engineering 11: 45–50. [Google Scholar] [CrossRef]
- Awuzie, Bankole, Fady Farag, and Peter McDermott. 2018. Achieving social value through construction frameworks: The effect of client attributes. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law 171: 25–31. [Google Scholar] [CrossRef]
- Babu, Nipin Joseph. 2015. Factors affecting success of construction project. IOSR Journal of Mechanical and Civil Engineering 12: 2320–34. [Google Scholar]
- Babu, Sumesh Sudheer, and B. Sudhakar. 2016. Construction project management during economic crisis. International Journal of Management 7: 370–81. [Google Scholar]
- Baum, Robert, Edwin Locke, and Ken Smith. 2001. A multidimensional model of venture growth. Academy of Management Journal 44: 292–303. [Google Scholar] [CrossRef]
- Begum, Rawshan Ara, Chamhuri Siwar, Joy Jacqueline Pereira, and Abdul Hamid Jaafar. 2009. Attitude and behavioral factors in waste management in the construction industry of Malaysia. Resources, Conservation and Recycling 53: 321–28. [Google Scholar] [CrossRef]
- Belassi, Walid, and Oya Iemeli Tukel. 1996. A new framework for determining critical success/failure factors in projects. International Journal of Project Management 14: 141–51. [Google Scholar] [CrossRef]
- Black, Carolynn, Akintola Akintoye, and Eamon Fitzgerald. 2000. An analysis of success factors and benefits of partnering in construction. International Journal of Project Management 18: 423–34. [Google Scholar] [CrossRef]
- Blayse, Aletha, and Karen Manley. 2004. Key influences on construction innovation. Construction Innovation 4: 143–54. [Google Scholar] [CrossRef]
- Boyd, David, and Ezekiel Chinyio. 2008. Understanding the Construction Client. New York: John Wiley & Sons. [Google Scholar]
- Bresnen, Mike, and Nick Marshall. 2000. Partnering in construction: A critical review of issues, problems and dilemmas. Construction Management & Economics 18: 229–37. [Google Scholar]
- Bryde, David James, and Lynne Robinson. 2005. Client versus contractor perspectives on project success criteria. International Journal of Project Management 23: 622–29. [Google Scholar] [CrossRef]
- bt Zakaria, Intan Bayani, Mohamad Redhuan, Bin Mohamed, Nadira bt Ahzahar, and Siti Zubaidah bt Hashim. 2015. A study on leadership skills of project manager for a successful construction project. International Academic Research Journal of Social Science 1: 89–94. [Google Scholar]
- Cant, Robyn. 2009. Constructions of competence within dietetics: Trust, professionalism and communications with individual clients. Nutrition & Dietetics 66: 113–18. [Google Scholar]
- Carvalho, Marly Monteiro De, and Roque Rabechini Junior. 2015. Impact of risk management on project performance: The importance of soft skills. International Journal of Production Research 53: 321–40. [Google Scholar] [CrossRef]
- Challender, Jason, and Russell Whitaker. 2019. The Client Role in Successful Construction Projects. New York: Routledge. [Google Scholar]
- Chan, Albert, and Ada Chan. 2004. Key performance indicators for measuring construction success. Benchmarking: An International Journal 11: 203–21. [Google Scholar] [CrossRef]
- Chan, Albert, David Scott, and Ada Chan. 2004. Factors affecting the success of a construction project. Journal of Construction Engineering and Management 130: 153–55. [Google Scholar] [CrossRef]
- Chan, Daniel, and Mohan Kumaraswamy. 1996. An evaluation of construction time performance in the building industry. Building and Environment 31: 569–78. [Google Scholar] [CrossRef]
- Chandler, Gaylen, and Erik Jansen. 1992. The founder’s self-assessed competence and venture performance. Journal of Business Venturing 7: 223–36. [Google Scholar] [CrossRef]
- Chandr, Herry Pintardi, I. Wiguna, and Peter Koming. 2012. Model of stakeholder influence on project success: Finding from construction project in East Java. International Journal of Academic Research 4: 41–45. [Google Scholar]
- Chartered Institute of Building (CIOB). 1995. Chartered institute of building, and chartered institute of building. The chartered institute of building. In The Chartered Institute of Building Handbook and List of Members. London: CIOB, pp. 27–52. [Google Scholar]
- Cheng, Eddie, Heng Li, and Peter Love. 2000. Establishment of critical success factors for construction partnering. Journal of Management in Engineering 16: 84–92. [Google Scholar] [CrossRef]
- Cheng, Eddie, Neal Ryan, and Stephen Kelly. 2012. Exploring the perceived influence of safety management practices on project performance in the construction industry. Safety Science 50: 363–69. [Google Scholar] [CrossRef]
- Chinyio, Ezekiel, Paul Olomolaiye, Simon Kometa, and Frank Harris. 1998. A needs-based methodology for classifying construction clients and selecting contractors. Construction Management & Economics 16: 91–98. [Google Scholar]
- Chou, Jui-Sheng, and Jung-Ghun Yang. 2012. Project management knowledge and effects on construction project outcomes: An empirical study. Project Management Journal 43: 47–67. [Google Scholar] [CrossRef]
- Data Bridge Market Research. 2020. Available online: https://www.databridgemarketresearch.com/reports/global-building-and-construction-sheets-market (accessed on 23 April 2023).
- Davis, Kate. 2014. Different stakeholder groups and their perceptions of project success. International Journal of Project Management 32: 189–201. [Google Scholar] [CrossRef]
- Del Prette, Zilda, and Almir Del Prette. 2021. Social Competence and Social Skills. London: Springer. [Google Scholar]
- Demirkesen, Sevilay, and Beliz Ozorhon. 2017. Measuring project management performance: Case of construction industry. Engineering Management Journal 29: 258–77. [Google Scholar] [CrossRef]
- Dinis, Fabio Matoseiro, Luís Sanhudo, João Poças Martins, and Nuno M.M. Ramos. 2020. Improving project communication in the architecture, engineering and construction industry: Coupling virtual reality and laser scanning. Journal of Building Engineering 30: 101287. [Google Scholar] [CrossRef]
- El Ansari, Walid, Reza Oskrochi, and Ceri J. Phillips. 2010. One size fits all partnerships? What explains community partnership leadership skills? Health Promotion Practice 11: 501–14. [Google Scholar] [CrossRef]
- Evans, Martin, and Peter Farrell. 2023. A strategic framework managing challenges of integrating lean construction and integrated project delivery on construction megaprojects, towards global integrated delivery transformative initiatives in multinational organisations. Journal of Engineering, Design and Technology 21: 376–416. [Google Scholar] [CrossRef]
- Feria, Margarida, and Miguel Amado. 2019. Architectural design: Sustainability in the decision-making process. Buildings 9: 135. [Google Scholar] [CrossRef]
- Fernando, Sam, Kriengsak Panuwatwanich, and David Thorpe. 2020. Analyzing client-led innovation enablers in Australian construction projects. International Journal of Managing Projects in Business 13: 388–408. [Google Scholar] [CrossRef]
- Gade, Anne Nørkjær, and Alex Opoku. 2020. Challenges for implementing the sustainable development goals in the danish construction industry: Building owners’ perspective. Paper presented at ARCOM 2020-Association of Researchers in Construction Management, 36th Annual Conference 2020-Proceedings, Online, September 7–8; London: ARCOM, Association of Researchers in Construction Management. [Google Scholar]
- Garbharran, Hari, Jeevarathnam Govender, and Thulani Msani. 2012. Critical success factors influencing project success in the construction industry. Acta Structilia 19: 90–108. [Google Scholar]
- Global Industry Analysts, Inc. 2019. Available online: https://www.strategyr.com/market-report-construction-management-software-forecasts-global-industry-analysts-inc.asp (accessed on 23 April 2023).
- Gray, Barbara. 2007. The process of partnership construction: Anticipating obstacles and enhancing the likelihood of successful partnerships for sustainable development. In Partnerships, Governance and Sustainable Development. Reflections on Theory and Practice. Massachusetts: Edward Elgar Publishing, pp. 27–41. [Google Scholar]
- Gunduz, Murat, and Mohammed Almuajebh. 2020. Critical success factors for sustainable construction project management. Sustainability 12: 1990. [Google Scholar] [CrossRef]
- Ha, Thi Phuong Thao, and Manh Dung Tran. 2018. Review of impacts of leadership competence of project managers on construction project success. International Journal of Emerging Trends in Social Sciences 4: 15–25. [Google Scholar] [CrossRef]
- Han, Wai Soon, Aminah Md. Yusof, Syuhaida Ismail, and Ng Choon Aun. 2012. Reviewing the notions of construction project success. International Journal of Business and Management 7: 90–101. [Google Scholar]
- Harris, Michael, Shanan Gibson, and Sherrill Taylor. 2007. Examining the impact of small business institute participation on entrepreneurial attitudes. Journal of Small Business Strategy 18: 57–76. [Google Scholar]
- Harzallah, Mounira, Giuseppe Berio, and François Vernadat. 2005. Analysis and modeling of individual competencies: Toward better management of human resources. IEEE Transactions on Systems, Man, and Cybernetics-Part A: Systems and Humans 36: 187–207. [Google Scholar] [CrossRef]
- Havenvid, Malena Ingemansson, Kajsa Hulthén, Åse Linné, and Viktoria Sundquist. 2016. Renewal in construction projects: Tracing effects of client requirements. Construction Management and Economics 34: 790–807. [Google Scholar] [CrossRef]
- Hoffmann, Terrence. 1999. The meanings of competency. Journal of European Industrial Training 23: 275–86. [Google Scholar] [CrossRef]
- Johnson, Jean, and Peter Raven. 1996. Relationship quality, satisfaction and performance in export marketing channels. Journal of Marketing Channels 5: 19–48. [Google Scholar] [CrossRef]
- Josephson, Per-Erik, and Yngve Hammarlund. 1999. The causes and costs of defects in construction: A study of seven building projects. Automation in Construction 8: 681–87. [Google Scholar] [CrossRef]
- Jurik, Nancy, and Julie Cowgill. 2005. The construction of client identities in a post-welfare social service program: The double bind of microenterprise development. In Deserving and Entitled: Social Constructions and Public Policy. New York: State University of New York Press, pp. 173–96. [Google Scholar]
- Kerzner, Harold. 2017. Project Management: A systems Approach to Planning, Scheduling, and Controlling. Hoboken: John Wiley & Sons. [Google Scholar]
- Kilby, Peter. 1983. An entrepreneurial problem. The American Economic Review 73: 107–11. [Google Scholar]
- Kim, Daejin, Joonho Ko, and Yujin Park. 2015. Factors affecting electric vehicle sharing program participants’ attitudes about car ownership and program participation. Transportation Research Part D: Transport and Environment 36: 96–106. [Google Scholar] [CrossRef]
- Kim, Sungchul, Minjin Kong, Jinwoo Choi, Seungwoo Han, Hoyoung Baek, and Taehoon Hong. 2021. Feasibility analysis of COVID-19 response guidelines at construction sites in South Korea using CYCLONE in terms of cost and time. Journal of Management in Engineering 37: 04021048. [Google Scholar] [CrossRef]
- Kolltveit, Bjørn Johs, and Kjell Grønhaug. 2004. The importance of the early phase: The case of construction and building projects. International Journal of Project Management 22: 545–51. [Google Scholar] [CrossRef]
- Kometa, Simon, Paul Olomolaiye, and Frank Harris. 1995. An evaluation of clients’ needs and responsibilities in the construction process. Engineering, Construction and Architectural Management 2: 57–76. [Google Scholar] [CrossRef]
- Kometa, Simon, Paul O. Olomolaiye, and Frank Harris. 1996. A review of client-generated risks to project consultants. International Journal of Project Management 14: 273–79. [Google Scholar] [CrossRef]
- Le Deist, Françoise Delamare, and Jonathan Winterton. 2005. What is competence? Human Resource Development International 8: 27–46. [Google Scholar] [CrossRef]
- Lee, Suk-Won, and Jae-Keun Jeon. 2018. Dynamic relationships between mega projects and official development assistance: Case of South Korean infrastructure construction projects in ASEAN’s developing countries. Sustainability 10: 4491. [Google Scholar] [CrossRef]
- Levander, Erika, Susanne Engström, Ylva Sardén, and Lars Stehn. 2011. Construction clients’ ability to manage uncertainty and equivocality. Construction Management and Economics 29: 753–64. [Google Scholar] [CrossRef]
- Marzouk, Mohamed, and Mohamed Enaba. 2019. Text analytics to analyze and monitor construction project contract and correspondence. Automation in Construction 98: 265–74. [Google Scholar] [CrossRef]
- Matthews, Jason, Alan Tyler, and Antony Thorpe. 1996. Pre-construction project partnering: Developing the process. Engineering, Construction and Architectural Management 3: 117–31. [Google Scholar] [CrossRef]
- Mayo, Giel, and Raja Issa. 2012. BIM use and requirements among building owners. Computing in Civil Engineering. Virginia, USA: American Society of Civil Engineers Publishing, pp. 349–356. [Google Scholar] [CrossRef]
- Meng, Xianhai. 2012. The effect of relationship management on project performance in construction. International Journal of Project Management 30: 188–98. [Google Scholar] [CrossRef]
- Metochi, Melvina. 2002. The influence of leadership and member attitudes in understanding the nature of union participation. British Journal of Industrial Relations 40: 87–111. [Google Scholar] [CrossRef]
- Mia, Lokman. 1999. Managerial attitude, motivation and the effectiveness of budget participation. Accounting, Organizations and Society 13: 465–75. [Google Scholar] [CrossRef]
- Müller, Ralf, and Rodney Turner. 2010. Leadership competency profiles of successful project managers. International Journal of Project Management 28: 437–48. [Google Scholar] [CrossRef]
- Navarro, María Luisa Avargues, Mercedes Borda Mas, and Ana María López Jiménez. 2010. Working conditions, burnout and stress symptoms in university professors: Validating a structural model of the mediating effect of perceived personal competence. The Spanish Journal of Psychology 13: 284–96. [Google Scholar] [CrossRef]
- Nikjow, Mohammad Ajmal, Li Liang, Xijing Qi, and Samad Sepasgozar. 2021. Engineering procurement construction in the context of belt and road infrastructure projects in west Asia: A SWOT analysis. Journal of Risk and Financial Management 14: 92. [Google Scholar] [CrossRef]
- Odusami, Koleola Tunwase. 2002. Perceptions of construction professionals concerning important skills of effective project leaders. Journal of Management in Engineering 18: 61–67. [Google Scholar] [CrossRef]
- Ogunnusi, Mercy, Mercy Ogunnusi, Temitope Omotayo, Mansur Hamma-Adama, Bankole Osita Awuzie, and Temitope Egbelakin. 2021. Lessons learned from the impact of COVID-19 on the global construction industry. Journal of Engineering, Design and Technology 20: 299–320. [Google Scholar] [CrossRef]
- Olanipekun, Ayokunle Olubunmi, Albert Chan, Bo Xia, and Ernest Effah Ameyaw. 2017. Indicators of owner commitment for successful delivery of green building projects. Ecological Indicators 72: 268–77. [Google Scholar] [CrossRef]
- Oyewobi, Luqman Oyekunle, and Deji Rufus Ogunsemi. 2010. Factors influencing reworks occurrence in construction: A study of selected building projects in Nigeria. Journal of Building Performance 1: 1–20. [Google Scholar]
- Phua, Florence, and Steve Rowlinson. 2004. How important is cooperation to construction project success? A grounded empirical quantification. Engineering, Construction and Architectural Management 11: 45–54. [Google Scholar] [CrossRef]
- Roda, Irene, Marco Macchi, and Saverio Albanese. 2020. Building a Total Cost of Ownership model to support manufacturing asset lifecycle management. Production Planning & Control 31: 19–37. [Google Scholar]
- Rowlinson, Steve, and Peter McDermott. 2005. Procurement Systems: A Guide to Best Practice in Construction. London: Routledge, pp. 27–53. [Google Scholar]
- Ryd, Nina. 2014. Construction clients challenges–emphasizing early stages. Procedia-Social and Behavioral Sciences 119: 134–41. [Google Scholar] [CrossRef]
- Savickas, Mark. 2013. Career construction theory and practice. Career Development and Counseling: Putting Theory and Research to Work 2: 144–80. [Google Scholar]
- Shalleck, Ann. 1993. Constructions of the client within legal education. Stanford Law Review 45: 1731–53. [Google Scholar] [CrossRef]
- Shash, Ali Ali, and Salah Ibrahim Habash. 2020. Construction Contract Conversion: An Approach to Resolve Disputes. Journal of Engineering, Project & Production Management 10: 162–69. [Google Scholar]
- Shavelson, Richard. 2010. On the measurement of competency. Empirical Research in Vocational Education and Training 2: 41–63. [Google Scholar] [CrossRef]
- Silva, Susil Kumara, B. N. F. Warnakulasooriya, and Bhadra Arachchige. 2016. Criteria for construction project success: A literature review. Paper presented at 13th International Conference on Business Management (ICBM), Colombo, Sri Lanka, December 8. [Google Scholar]
- Siva, Jessica Pooi Sun, and Kerry London. 2011. Investigating the role of client learning for successful architect–client relationships on private single dwelling projects. Architectural Engineering and Design Management 7: 177–89. [Google Scholar] [CrossRef]
- Tabish, Syed Zafar Shahid, and Kumar Neeraj Jha. 2012. Success traits for a construction project. Journal of Construction Engineering and Management 138: 1131–38. [Google Scholar] [CrossRef]
- Takim, Roshana, and Hamimah Adnan. 2008. Analysis of effectiveness measures of construction project success in Malaysia. Asian Social Science 4: 74–91. [Google Scholar] [CrossRef]
- Thompson, Peter. 1991. The client role in project management. International Journal of Project Management 9: 90–92. [Google Scholar] [CrossRef]
- Toole, Michael, John Gambatese, and Deborah Abowitz. 2017. Owners’ role in facilitating prevention through design. Journal of Professional Issues in Engineering Education and Practice 143: 04016012. [Google Scholar] [CrossRef]
- Tran, Dai Q., Long Duy Nguyen, and Allen Faught. 2017. Examination of communication processes in design-build project delivery in building construction. Engineering, Construction and Architectural Management 24: 1319–36. [Google Scholar] [CrossRef]
- Wang, Xiaojin, and Jing Huang. 2006. The relationships between key stakeholders’ project performance and project success: Perceptions of Chinese construction supervising engineers. International Journal of Project Management 24: 253–60. [Google Scholar] [CrossRef]
- Ward, Ella, Song Yang, Jenni Romaniuk, and Virginia Beal. 2020. Building a unique brand identity: Measuring the relative ownership potential of brand identity element types. Journal of Brand Management 27: 393–407. [Google Scholar] [CrossRef]
- Williams, Terry. 2016. Identifying success factors in construction projects: A case study. Project Management Journal 47: 97–112. [Google Scholar] [CrossRef]
- Winkler, Rainer, Matthias Söllner, and Jan Marco Leimeister. 2021. Enhancing problem-solving skills with smart personal assistant technology. Computers & Education 165: 104148. [Google Scholar]
- Zalejska, Jonsson Agnieszka, and Rosane Hungria Gunnelin. 2019. Defects in newly constructed residential buildings: Owners’ perspective. International Journal of Building Pathology and Adaptation 37: 163–85. [Google Scholar] [CrossRef]
- Zanjirchi, Seyed Mahmod, and Mehrdad Moradi. 2012. Construction project success analysis from stakeholders’ theory perspective. African Journal of Business Management 6: 5218. [Google Scholar]
- Zavari, Masoud, and Mohammad Reza Afshar. 2023. The role of site manager transformational leadership in the construction project success. International Journal of Building Pathology and Adaptation 41: 1067–85. [Google Scholar] [CrossRef]
- Zhang, Jingxiao, Hui Li, Ayokunle Olubunmi Olanipekun, and Li Bai. 2019. A successful delivery process of green buildings: The project owners’ view, motivation and commitment. Renewable Energy 138: 651–58. [Google Scholar] [CrossRef]
Factors | Measurement Items | References |
---|---|---|
Personal Competency |
| Hoffmann (1999); Navarro et al. (2010); Winkler et al. (2021) |
Social Competency |
| Siva and London (2011); Meng (2012); Del Prette and Del Prette (2021) |
Professional Competency |
| Jurik and Cowgill (2005); Williams (2016); Awuzie et al. (2018) |
Participation Attitude |
| Metochi (2002); Begum et al. (2009); Acıkara et al. (2017) |
Partnership |
| Meng (2012); Black et al. (2000) |
Project Performance |
| Chan et al. (2004); Cheng et al. (2012); Demirkesen and Ozorhon (2017) |
Section | Frequency | Ratio (%) | |
---|---|---|---|
Gender | Male | 168 | 67.5 |
Female | 81 | 32.5 | |
Age | 20~29 | 2 | 0.80 |
30~39 | 15 | 6.10 | |
40~49 | 40 | 16.1 | |
50~59 | 88 | 35.3 | |
60’s and above | 104 | 41.7 | |
Education | High School | 4 | 1.60 |
Junior College | 61 | 24.5 | |
University | 131 | 52.6 | |
Master’s and Doctorate | 53 | 21.3 | |
Occupation | Office worker | 56 | 22.5 |
Self-employed | 79 | 31.7 | |
Professional specialist | 55 | 22.1 | |
Unemployed | 59 | 23.7 | |
Major | Major in Architecture | 47 | 18.9 |
Others | 202 | 81.1 | |
Construction project experiences | 1 time | 149 | 59.8 |
2–4 times | 70 | 28.2 | |
5 or more times | 30 | 12.0 | |
Construction project scale (average of the projects) | Less than 100 m2 | 40 | 16.1 |
100 m2–199 m2 | 132 | 53.0 | |
200 m2–299 m2 | 30 | 12.0 | |
300 m2 or higher | 47 | 18.9 | |
Construction project cost (average of the projects) | Less than US$7700 | 116 | 46.5 |
US$7700–22,000 | 70 | 28.2 | |
US$23,000–37,000 | 19 | 7.60 | |
US$38,000 or more | 44 | 17.7 |
Variables | Measurement Questions | Standard Loading | Standard Error | T Value (p) | CR | AVE | Cronbach α |
---|---|---|---|---|---|---|---|
Personal Competency | PC1 | 0.813 | 0.817 | 0.709 | 0.828 | ||
PC2 | 0.871 | 0.072 | 12.244 *** | ||||
PC3 | 0.802 | 0.065 | 10.372 *** | ||||
Social Competency | SC1 | 0.798 | 0.739 | 0.599 | 0.765 | ||
SC2 | 0.702 | 0.102 | 9.203 *** | ||||
SC3 | 0.787 | 0.097 | 9.683 *** | ||||
Professional Competency | PFC1 | 0.856 | 0.904 | 0.825 | 0.900 | ||
PFC2 | 0.958 | 0.054 | 19.196 *** | ||||
Participation Attitude | WB1 | 0.802 | 0.904 | 0.702 | 0.903 | ||
WB2 | 0.892 | 0.07 | 16.455 *** | ||||
WB3 | 0.913 | 0.069 | 16.953 *** | ||||
Partnership | PT1 | 0.832 | 0.883 | 0.715 | 0.880 | ||
PT2 | 0.836 | 0.068 | 15.905 *** | ||||
PT3 | 0.868 | 0.074 | 16.87 *** | ||||
Project Performance | PP1 | 0.848 | 0.902 | 0.698 | 0.899 | ||
PP2 | 0.873 | 0.055 | 17.44 *** | ||||
PP3 | 0.869 | 0.054 | 17.323 *** | ||||
PP4 | 0.745 | 0.069 | 13.648 *** |
AVE | PC | SC | PFC | PA | PT | PP | |
---|---|---|---|---|---|---|---|
Personal competency (PC) | 0.709 | 0.842 | |||||
Social competency (SC) | 0.599 | 0.580 ** | 0.774 | ||||
Professional competency (PFC) | 0.825 | 0.698 ** | 0.525 ** | 0.908 | |||
Participation attitude (PA) | 0.702 | 0.594 ** | 0.457 ** | 0.618 ** | 0.838 | ||
Partnership (PT) | 0.715 | 0.713 *** | 0.572 ** | 0.721 ** | 0.658 *** | 0.846 | |
Project performance (PP) | 0.698 | 0.613 ** | 0.493 ** | 0.555 ** | 0.562 ** | 0.750 ** | 0.835 |
Hypothesis (Path) | Path Coefficient | SRW 1 | t Value | Support (Y/N) | |
---|---|---|---|---|---|
H1 | Personal competency → Participation attitude | 0.778 | 0.204 | 3.821 *** | Accepted |
H2 | Social competency → Participation attitude | −0.003 | 0.134 | −0.020 | Rejected |
H3 | Professional competency → Participation attitude | 0.140 | 0.118 | 1.191 ** | Accepted |
H4 | Personal competency → Partnership | 0.599 | 0.141 | 4.259 *** | Accepted |
H5 | Social competency → Partnership | 0.098 | 0.091 | 1.076 * | Accepted |
H6 | Professional competency → Partnership | 0.201 | 0.082 | 2.457 ** | Accepted |
H7 | Participation attitude → Project performance | 0.091 | 0.062 | 1.472 * | Accepted |
H8 | Partnership → Project performance | 1.138 | 0.092 | 2.388 *** | Accepted |
Hypothesis (Path) | Direct Effect | Indirect Effect | Total Effect |
---|---|---|---|
Personal competency → Participation attitude | 0.121 *** | - | 0.121 |
Personal competency → Partnership | 0.209 *** | - | 0.209 |
Personal competency →Participation attitude → Project performance | 0.238 *** | 0.208 *** | 0.446 |
Personal competency → Partnership → Project performance | 0.121 ** | 0.103 *** | 0.224 |
Social competency → Participation attitude | 0.154 | - | 0.154 |
Social competency → Partnership | 0.138 ** | - | 0.138 |
Social competency → Participation attitude → Project performance | 0.025 | 0.043 | 0.068 |
Social competency → Partnership → Project performance | 0.076 * | 0.132 * | 0.208 |
Professional competency → Participation attitude | 0.248 *** | - | 0.248 |
Professional competency → Partnership | 0.267 ** | 0.267 | |
Professional competency → Participation attitude → Project performance | 0.232 ** | 0.157 ** | 0.389 |
Professional competency → Partnership → Project performance | 0.178 ** | 0.299 ** | 0.477 |
Participation attitude → Project performance | 0.197 *** | - | 0.197 |
Partnership → Project performance | 0.298 *** | - | 0.298 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Park, K.; Kim, B. Effects of Individual Client’s Competencies on Construction Project Performance: Mediating Participation Attitude and Partnership. Adm. Sci. 2024, 14, 40. https://doi.org/10.3390/admsci14030040
Park K, Kim B. Effects of Individual Client’s Competencies on Construction Project Performance: Mediating Participation Attitude and Partnership. Administrative Sciences. 2024; 14(3):40. https://doi.org/10.3390/admsci14030040
Chicago/Turabian StylePark, Kanghee, and Boyoung Kim. 2024. "Effects of Individual Client’s Competencies on Construction Project Performance: Mediating Participation Attitude and Partnership" Administrative Sciences 14, no. 3: 40. https://doi.org/10.3390/admsci14030040
APA StylePark, K., & Kim, B. (2024). Effects of Individual Client’s Competencies on Construction Project Performance: Mediating Participation Attitude and Partnership. Administrative Sciences, 14(3), 40. https://doi.org/10.3390/admsci14030040