Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting
Abstract
:1. Introduction
2. Project Overview and Subsoil Conditions
2.1. Site Description
2.2. Soil Conditions
2.3. Geotechnical Monitoring System and Construction Sequence
3. Site Observations
3.1. Building and Ground Settlements
3.2. Relationship between Maximum Wall Deflections and Maximum Settlements
4. Finite Element Analysis
4.1. Relationship between Maximum Wall Deflections and Maximum Settlements
4.2. Modeling the Equivalent CBP Wall
4.3. Modeling the Equivalent Ground Anchor
4.4. Modeling the Fluctuating Groundwater Levels
4.5. Modeling the Excavation Sequence
- Stage 1: The CBP wall installation was a ‘wish-in-place’ condition that assumed no changes in the geological stresses and hydrogeological pore water pressure surrounding the wall;
- Stage 2: In the real-life construction of a CBP wall, there was a need to introduce a continuous capping beam to tie the individual bored pile heads together. Therefore, an equivalent horizontal load was needed to be applied to the pile heads to simulate the restraining action. However, since there was no active pressure acting on the wall during the capping beam installation, the loading was not activated at this stage. In the 3D analysis, the wall was modeled as a continuous plate, hence the significance of the 3D restraining effect would have been automatically captured;
- Stage 3: The excavation process was modeled by deactivating the ‘excavated’ soil region. Since the soil pressures behind the wall acted as active pressures, the capping beam restraint was activated using a relevant restraining load, whose equivalent magnitude is discussed later;
- Stage 4: The node-to-node anchor and geogrid were activated. From the site observations, the installation of ground anchor had caused groundwater lowering. Therefore, the groundwater level behind the wall was deliberately drawn down through Z-water table method, in which the groundwater profiles from SEEP/W (see Figure 12) were re-produced in PLAXIS. Since the bored piles were socketed in phyllite with low permeability, the effect of groundwater flow through the wall toe can be disregarded [31,47]. This important finding ensures that the use of PLAXIS ‘z-water table’ method is validated;
- Stage 5: The pre-stress was activated and 293 kN/m was entered. If there was any adjustment to the groundwater table behind the wall, the Z-water table method described in Stage 4 would be repeated. The ground anchors were then activated at this stage and they were expected to play a more significant role than the capping beam [49];
- Stage 6: The second excavation of soil was removed by deactivating the soil region, and adjustment to the groundwater level, if any, was made; as described in Stage 4;
- Stage 7: GA2 was activated, similar to Stage 4;
- Stage 8: Pre-stress was activated, similar to Stage 5;
- Stage 9: The final excavation was simulated, similar to Stage 6.
4.6. Modeling the Individual Bored Pile and Continuous Capping Beam
4.7. Modeling the Capping Beam Restraining Load
5. Results and Discussion
5.1. Measured vs. Predicted Responses of CBPs 343, 424, 465, and 506
5.1.1. Measured and Predicted Deflection Profiles
5.1.2. Measured and Predicted Bending Moment Profiles
5.1.3. Key Observable Soil–Structure Interaction Behaviors
5.1.4. Summary on Measured and Predicted Pile Deflections and Bending Moment Profiles
5.2. Measured vs. Predicted Responses of Ground Markers (GM) and Building Markers (BM) in the Vicinity of CBPs 393, 424, 465, and 506
5.2.1. CBPs 424 and 465: Ground Markers (GM) and Building Markers (BM)
5.2.2. CBPs 393 and 506: Ground Markers (GM) and Building Markers (BM)
5.3. Cross-Verification of 2D and 3D Analyses against Measured Field Data
6. Conclusions
- (a)
- Groundwater drawdown due to leakage through the CBP walls had a considerable impact on the extent of wall deflections (small) and ground settlement (large). The ratio of δvm/δhm for building and ground were measured to be 14.8 and 14.5, respectively, considerably higher than typical δvm/δhm ratio of between 0.5 and 1.0 in a typical deep excavation project without through-the-wall seepage. This real-life observation has been successfully modeled using 2D and 3D finite element analyses, and the main causes have been attributed to the ground anchor installation process that had caused (i) groundwater loss and (ii) possible loss of soil particles (observed in CBP393 only);
- (b)
- The concept of equivalent wall permeability was successfully implemented to represent the through-the-wall hydrogeological seepage happening in real life. In this case, two modeling methods were used, namely, (i) flow-through ‘permeable wall’ mimicking gaps between successive bored piles and (ii) ‘impermeable wall’ but with leakage points at the locations of the ground anchor heads;
- (c)
- Transient or time-dependent seepage analyses have been adopted to successfully verify the applicability of the conventional “Z-water table” method based on the understanding that the piles were socketed in the low-permeability geology, typically the phyllite rock mass. The predicted groundwater and ground responses that reasonably matched the measured profiles effectively verified this modeling technique;
- (d)
- The presence of the capping beam effectively tied all the pile heads together and forced them to act in unison to resist the active lateral earth pressures from the retained side of the excavation. Through finite element back analyses and field measurements, the 1.5 m thick continuous capping beam was found to exert a representative, back-analyzed restraining line load of 50 kN/m. This implies that the capping beam is beneficial in resisting the induced CBP deflections and the induced ground settlement due to through-the-wall seepage;
- (e)
- The complex soil–structure interactions observed in this case study does not only stop at the wall deflection–ground settlement relationship, but also directly influencing the ground settlement–foundation settlement relationship in the challenging geological setting. In the unique case of CBP393, where the field-measured ground and building settlements were overly large despite being embedded in relatively competent sandy/silty ground (N = 4), the belief that localized liquefaction occurred during wash boring for ground anchor installation became more real, especially with the workers’ claim that locally washed-out materials were evident at that very location.
Author Contributions
Funding
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Finno, R.; Blackburn, J.; Roboski, J. Three-dimensional effects for supported excavations in clay. J. Geotech. Geoenviron. Eng. 2007, 133, 30–36. [Google Scholar] [CrossRef]
- Hashash, Y.M.A.; Whittle, A.J. Ground movement prediction for deep excavations in soft clay. J. Geotech. Eng. 1996, 122, 474–486. [Google Scholar] [CrossRef]
- Hsiung, B.-C.B.; Yang, K.-H.; Aila, W.; Ge, L. Three-dimensional effects of a deep excavation on wall defections in central Jakarta. Tunn. Undergr. Space Technol. 2018, 72, 84–96. [Google Scholar] [CrossRef]
- Ong, D.E.L.; Leung, C.; Chow, K. Time-dependent Pile Behavior Due to Excavation-Induced Soil Movement in Clay. In Proceedings of the 12th Pan-American Conference on Soil Mechanics and Geotechnical Engineering, Massachusetts Institute of Technology, Boston, MA, USA, 22–26 June 2003. [Google Scholar]
- Ong, D.E.L.; Leung, C.F.; Chow, Y.K. Piles subject to excavation-induced soil movement in clay. In Proceedings of the 13th European Conference on Soil Mechanics and Geotechical Engineering, Prague, Czech Republic, 25–28 August 2003; pp. 777–782. [Google Scholar]
- Ou, C.-Y.; Hsieh, P.-G.; Lin, Y.-L. A parametric study of wall deflections in deep excavations with the installation of cross walls. Comput. Geotech. 2013, 50, 55–65. [Google Scholar] [CrossRef]
- Hsiung, B.-C.B.; Yang, K.-H.; Aila, W.; Hung, C. Three-dimensional effects of a deep excavation on wall deflections in loose to medium dense sands. Comput. Geotech. 2016, 80, 138–151. [Google Scholar] [CrossRef]
- Nikolinakou, M.A.; Whittle, A.J.; Savidis, S.; Schran, U. Prediction and Interpretation of the Performance of a Deep Excavation in Berlin Sand. J. Geotech. Geoenviron. Eng. 2011, 137, 1047–1061. [Google Scholar] [CrossRef]
- Russo, G.; Nicotera, M.V.; Autuori, S. Three-Dimensional Performance of a Deep Excavation in Sand. J. Geotech. Geoenviron. Eng. 2019, 145, 05019001. [Google Scholar] [CrossRef]
- Richards, D.J.; Wiggan, C.A.; Powrie, W. Seepage and pore pressures around contiguous pile retaining walls. Géotechnique 2016, 66, 523–532. [Google Scholar] [CrossRef]
- Powrie, W.; Chandler, R.J.; Carder, D.R.; Watson, G.V.R. Back-analysis of an embedded retaining wall with a stabilizing base slab. Proc. Inst. Civ. Eng.-Geotech. Eng. 1999, 137, 75–86. [Google Scholar] [CrossRef]
- Richards, D.J.; Powrie, W.; Roscoe, H.; Clark, J. Pore water pressure and horizontal stress changes measured during construction of a contiguous bored pile multi-propped retaining wall in Lower Cretaceous clays. Géotechnique 2007, 57, 197–205. [Google Scholar] [CrossRef]
- Ho, A.; Wright, M.; Ng, S. Deep Excavation in Hong Kong–Cantilever Bored Pile Wall Design Using CIRIA Report No. C580. In Proceedings of the 18th International Conference on Soil Mechanics and Geotechnical Engineering, Paris, France, 2–6 September 2013; pp. 1813–1817. [Google Scholar]
- Ong, D.E.; Leung, C.E.; Chow, Y.K. Pile Behavior due to Excavation-Induced Soil Movement in Clay. I: Stable Wall. J. Geotech. Geoenviron. Eng. 2006, 132, 36–44. [Google Scholar] [CrossRef]
- Ong, D.E.L. Pile Behaviour Subject to Excavation-Induced Soil Movement in Clay. Ph.D. Thesis, National University of Singapore, Singapore, 2004. [Google Scholar]
- Ong, D.E.L.; Leung, C.F.; Chow, Y.K.; Ng, T.G. Severe Damage of a Pile Group due to Slope Failure. J. Geotech. Geoenviron. Eng. 2015, 141, 04015014. [Google Scholar] [CrossRef]
- Zdravkovic, L.; Potts, D.M.; St. John, H.D. Modelling of a 3D excavation in finite element analysis. Géotechnique 2005, 55, 497–513. [Google Scholar] [CrossRef]
- Lee, F.H.; Hong, S.H.; Gu, Q.; Zhao, P. Application of Large Three-Dimensional Finite-Element Analyses to Practical Problems. Int. J. Geomech. 2010, 11, 529–539. [Google Scholar] [CrossRef]
- Lee, F.H.; Yong, K.Y.; Quan, K.C.N.; Chee, K.T. Effect of Corners in Strutted Excavations: Field Monitoring and Case Histories. J. Geotech. Geoenviron. Eng. 1998, 124, 339–349. [Google Scholar] [CrossRef]
- Ou, C.-Y.; Lai, C.-H. Finite-element analysis of deep excavation in layered sandy and clayey soil deposits. Can. Geotech. J. 1994, 31, 204–214. [Google Scholar] [CrossRef]
- Hwang, R.; Moh, Z.-C.; Wang, C.H. Toe movements of diaphragm walls and correction of inclinometer readings. J. GeoEng. 2007, 2, 61–71. [Google Scholar] [CrossRef]
- Chong, E.E.-M.; Ong, D.E.-L. Data-Driven Field Observational Method of a Contiguous Bored Pile Wall System Affected by Accidental Groundwater Drawdown. Geosciences 2020, 10, 268. [Google Scholar] [CrossRef]
- Goh, K.H.; Mair, R.J. The horizontal response of framed buildings on individual footings to excavation-induced movements. In Geotechnical Aspects of Underground Construction in Soft Ground; CRC Press: Boca Raton, FL, USA, 2012; pp. 895–902. [Google Scholar] [CrossRef]
- Korff, M.; Mair, R.; Van Tol, F. Pile-Soil Interaction and Settlement Effects Induced by Deep Excavations. J. Geotech. Geoenviron. Eng. 2016, 142, 04016034. [Google Scholar] [CrossRef]
- Castaldo, P.; Jalayer, F.; Palazzo, B. Probabilistic assessment of groundwater leakage in diaphragm wall joints for deep excavations. Tunn. Undergr. Space 2018, 71, 531–543. [Google Scholar] [CrossRef]
- Clough, G.W.; O’Rourke, T.D. Construction Induced Movements of In-situ Walls. In Proceedings of the Conference Proceedings of Design and Performance of Earth Retaining Structures, New York, NY, USA, 18–21 June 1990; pp. 439–470. [Google Scholar]
- Ou, C.-Y.; Hsieh, P.-G.; Chiou, D.-C. Characteristics of ground surface settlement during excavation. Can. Geotech. J. 1993, 30, 758–767. [Google Scholar] [CrossRef]
- Zhang, W.; Wang, W.; Zhou, D.; Zhang, R.; Goh, A.T.C.; Hou, Z. Influence of groundwater drawdown on excavation responses–A case history in Bukit Timah granitic residual soils. J. Rock Mech. Geotech. Eng. 2018, 10, 856–864. [Google Scholar] [CrossRef]
- Khoiri, M.; Ou, C.-Y. Evaluation of deformation parameter for deep excavation in sand through case histories. Comput. Geotech. 2013, 47, 57–67. [Google Scholar] [CrossRef]
- Castaldo, P.; Gino, D.; Mancini, G. Nonlinear Numerical Analyses of Reinforced Concrete Structures: Safety Formats, Aleatory and Epistemic Uncertainties. In Reliability-Based Analysis and Design of Structures and Infrastructure; Farsangi, E.N., Noori, M., Gardoni, P., Takewaki, I., Varum, H., Bogdanovic, A., Eds.; CRC Press: Boca Raton, FL, USA, 2021; pp. 143–158. [Google Scholar]
- Hsiung, B.-C.B. A case study on the behaviour of a deep excavation in sand. Comput. Geotech. 2009, 36, 665–675. [Google Scholar] [CrossRef]
- Ong, D.E.L.; Choo, C.S. Sustainable construction of a bored pile foundation system in erratic phyllite. In Proceedings of the ASEAN Australian Engineering Congress, Sarawak, Malaysia, 25–27 July 2011. [Google Scholar]
- Geo-Field Engineering. Design and Build Negotiated Contract for Kuching City Central Wastewater Management System: Centralised Sewerage for Kuching City Centre (Package 1): Geotechnical Interpretative Report (Volume 1). Prepared for Hock Seng Lee Berhad. 2009.
- Geo-Field Engineering. Design and Build Negotiated Contract for Kuching City Central Wastewater Management System: Centralised Sewerage for Kuching City Centre (Package 1): Geotechnical Interpretative Report (Volume 2). Prepared for Hock Seng Lee Berhad. 2009.
- Choo, C.S.; Ong, D.E.L. Evaluation of Pipe-Jacking Forces Based on Direct Shear Testing of Reconstituted Tunneling Rock Spoils. J. Geotech. Geoenviron. Eng. 2015, 141, 04015044. [Google Scholar] [CrossRef]
- Choo, C.S.; Ong, D.E.L. Impact of highly weathered geology on pipe-jacking forces. Geotech. Res. 2017, 4, 94–106. [Google Scholar] [CrossRef]
- Choo, C.S.; Ong, D.E.L. Assessment of non-linear rock strength parameters for the estimation of pipe-jacking forces. Part 2. Numerical modeling. Eng. Geol. 2020, 265, 105405. [Google Scholar] [CrossRef]
- Ong, D.E.L.; Choo, C.S. Assessment of non-linear rock strength parameters for the estimation of pipe-jacking forces. Part 1. Direct shear testing and backanalysis. Eng. Geol. 2018, 244, 159–172. [Google Scholar] [CrossRef]
- Peerun, M.I.; Ong, D.E.L.; Choo, C.S. Interpretation of Geomaterial Behavior during Shearing Aided by PIV Technology. J. Mater. Civ. Eng. 2019, 31, 04019195. [Google Scholar] [CrossRef]
- Peerun, M.I.; Ong, D.E.L.; Choo, C.S.; Cheng, W.C. Effect of interparticle behavior on the development of soil arching in soil-structure interaction. Tunn. Undergr. Space Technol. 2020, 106, 103610. [Google Scholar] [CrossRef]
- Ong, D.E.L.; Sim, Y.S.; Leung, C.F. Performance of Field and Numerical Back-Analysis of Floating Stone Columns in Soft Clay Considering the Influence of Dilatancy. Int. J. Geomech. 2018, 18, 04018135. [Google Scholar] [CrossRef]
- Jacky, J. The coefficient of earth pressure at rest. J. Soc. Hung. Archit. Eng. 1944, 8, 355–358. (In Hungarian) [Google Scholar]
- Ng, L.T.; Ong, D.E.L.; Wong, W.S.H.; Gannilegedera, D.A.; BonJong, B.F.; Chua, H.S. Real-time monitoring and assessment of groundwater responses due to dewatering of an abandoned 7 m deep excavation pit in Kuching City. In Computer Methods and Recent Advances in Geomechanics, Proceedings of the 14th International Conference for Computer Methods and Recent Advances in Geomechanics, Kyoto, Japan, 22–25 September 2014; Oka, F., Murakami, A., Uzuoka, R., Kimoto, S., Eds.; Taylor & Francis Books Ltd.: London, UK, 2015; pp. 1205–1211. [Google Scholar]
- Ong, D.E.L. Benchmarking of FEM Technique Involving Deep Excavation, Pile-soil Interaction and Embankment Construction. In Proceedings of the 12th International Conference of International Association for Computer Methods and Advances in Geomechanics (IACMAG), Goa, India, 1–6 October 2008; pp. 154–162. [Google Scholar]
- Ong, D.E.L.; Leung, C.F.; Chow, Y.K.; Yang, D.Q. Effect of Limiting Soil Pressures on Pile Behaviour. In Proceedings of the 16th South-East Asian Geotechnical Conference (SEAGC), Kuala Lumpur, Malaysia, 8–11 May 2007; pp. 427–437. [Google Scholar]
- American Concrete Institute. Building Code Requirements for Structural Concrete (ACI 318-08) and Commentary; American Concrete Institute: Indianapolis, IN, USA, 2008. [Google Scholar]
- Ong, D.E.L.; Yang, D.Q.; Phang, S.K. Comparisons of Finite Element Modelling of a Deep Excavation Using SAGE-CRISP and PLAXIS. In Proceedings of the International Conference on Deep Excavations, Singapore, 28–30 June 2006. [Google Scholar]
- GEO-SLOPE International Ltd. Seepage Modeling with SEEP/W 2007: An Engineering Methodology, 4th ed.; GEO-SLOPE International Ltd.: Calgary, AB, Canada, 2010. [Google Scholar]
- Loh, C.K. Effect of a Corner in a Three-Dimensional Excavation. Ph.D. Thesis, National University of Singapore, Singapore, 2003. [Google Scholar]
- Leung, C.F.; Ong, D.E.; Chow, Y.K. Pile Behavior Due to Excavation-Induced Soil Movement in Clay. II: Collapsed Wall. J. Geotech. Geoenviron. Eng. 2006, 132, 45–53. [Google Scholar] [CrossRef]
- Ong, D.E.L.; Leung, C.F.; Chow, Y.K. Behavior of Pile Groups Subject to Excavation-Induced Soil Movement in Very Soft Clay. J. Geotech. Geoenviron. Eng. 2009, 135, 1462–1474. [Google Scholar] [CrossRef]
Stage | Construction Activity | Cumulative Days | |
---|---|---|---|
Wall E | Wall F | ||
1 | Installation of CBP Wall | 144 | 160 |
2 | Casting of Pile Capping Beam | 250 | 259 |
3 | Excavation to 0.5 m below GA1 (B1) (RL +0.5 m) | 292 | 309 |
4 | Installation of the first level of ground anchor (GA1) (RL +1.0 m) | 299 | 324 |
5 | Stressing of the first level of ground anchor (GA1) | 315 | 337 |
6 | Excavation to 0.5 m below GA2 (B2) (RL −3.5 m) | 320 | 345 |
7 | Installation of the second level of ground anchor (GA2) (RL −3.0 m) | 344 | 365 |
8 | Stressing of the second level of ground anchor (GA2) | 365 | 189 |
9 | Excavation to the formation level (B3) (RL −6.6 m) | 373 | 380 |
Material | SPT ‘N’ | γ (kN/m3) | E′ (kN/m2) | ν | c′ (kPa) | ϕ′ (°) | Ψ″ (°) | k (m/s) |
---|---|---|---|---|---|---|---|---|
Very soft silt | 0–4 | 18 | 5217 | 0.3 | 1 | 22 | 0 | 1 × 10−6 |
Firm silt | 5–10 | 18 | 6957 | 0.3 | 5 | 30 | 0 | 1 × 10−6 |
Hard silt | >35 | 18 | 86,957 | 0.3 | 15 | 32 | 2 | 1 × 10−6 |
Very loose sand | 0–4 | 17 | 5217 | 0.3 | 1 | 28 | 0 | 1 × 10−4 |
Medium-dense sand | 10–30 | 18 | 6957 | 0.3 | 1 | 30 | 0 | 1 × 10−4 |
Dense sand | >35 | 18 | 86,957 | 0.3 | 15 | 32 | 2 | 1 × 10−4 |
Phyllite | >50 | 22 | 250,000 | 0.3 | 45 | 46 | 16 | 1 × 10−8 |
Parameter | PLAXIS 2D | PLAXIS 3D |
---|---|---|
Element | Plate | Plate |
Material behavior | Elastic | Elastic |
Equivalent thickness, deq (m) | 0.606 | 0.606 |
Unit weight, g (kN/m3) | - | 6 |
Young’s modulus, Ep (kN/m2) | 2.8 × 107 | 2.8 × 107 |
Poisson’s ratio, ν | 0.15 | 0.15 |
Axial stiffness, EpAp (kN/m) | 1.44 × 107 | - |
Bending rigidity, EpIp, (kNm2/m) | 4.40 × 107 | - |
Weight, w (kN/m/m) | 1.290 | - |
Axial Stiffness, EaAa (kN) | Centre-to-Centre Spacing (m) | Pre-Stress Force (kN/m) |
---|---|---|
2.289 × 105 | 2.25 | 293 |
Parameter | PLAXIS 2D | PLAXIS 3D |
---|---|---|
Element | Geogrid | Embedded pile |
Axial stiffness, EbAb (kN/m) | 2.20 × 105 | - |
Material behavior | Elastic | Elastic |
Young’s modulus, Ea (kN/m2) | - | 2.8 × 107 |
Unit weight, g (kN/m3) | - | 24 |
Pile type | - | Predefined massive circular pile |
Diameter (m) | - | 0.15 |
Skin friction distribution | - | Linear |
Skin resistance at the top of the embedded pile, Ttop,max (kN/m) | - | 293.0 |
Skin resistance at the bottom of the embedded pile, Tbottom,max (kN/m) | - | 0 |
Base resistance, Fmax | - | 0 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Ong, D.E.L.; Chong, E.E.M. Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting. Geosciences 2023, 13, 304. https://doi.org/10.3390/geosciences13100304
Ong DEL, Chong EEM. Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting. Geosciences. 2023; 13(10):304. https://doi.org/10.3390/geosciences13100304
Chicago/Turabian StyleOng, Dominic Ek Leong, and Elizabeth Eu Mee Chong. 2023. "Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting" Geosciences 13, no. 10: 304. https://doi.org/10.3390/geosciences13100304
APA StyleOng, D. E. L., & Chong, E. E. M. (2023). Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting. Geosciences, 13(10), 304. https://doi.org/10.3390/geosciences13100304