1. Introduction
The construction of reservoirs on river channels inevitably disrupts the original water–sediment balance [
1]. After reservoir impoundment, the water level in front of a dam rises, resulting in reduced flow velocity and sediment-carrying capacity. Sediment is trapped and deposited within the reservoir, causing numerous adverse effects. As of 2018, the average sedimentation rate in Chinese reservoirs was 11.27%, with a particularly high rate of 36.76% in the Yellow River basin. Such excessive sedimentation severely undermines flood control and disaster resilience in reservoirs [
2]. For instance, the Aswan High Dam in Egypt experienced a 12% reduction in storage capacity because of sediment deposition between 1964 and 2013, which obstructed river navigation and diminished the flood discharge capacity of the dam [
3]. Similarly, sediment accumulation in reservoirs in the United States from the late 1980s to 2021 resulted in a decrease in the total storage capacity from 850 Gm
3 to 810 Gm
3, causing pressure on water supply and management [
4]. The Hirakud Reservoir in India lost approximately 22% of its effective storage capacity because of sedimentation, leading to reduced water storage capacity and increased flood risk [
5]. At the same time, the construction of reservoir dams inevitably brings ecological problems, such as changing the landform characteristics [
6] and runoff distribution [
7] of the downstream river, reducing the diffusion capacity of pollutants in the reservoir area, and easily producing water eutrophication [
8]. These examples highlight the global issue of the effect of sedimentation on reservoirs.
For reservoirs on sand-laden rivers, reducing sediment deposition is a major but challenging task. Water–sediment regulation is an important approach for controlling sedimentation and maintaining long-term effective storage capacity. Compared with sediment interception and artificial sediment excavation, water–sediment regulation is a highly efficient non-engineering measure that requires less investment, yields results rapidly, and is easier to implement [
9]. Unlike that in water regulation, the decision-making process in water–sediment regulation for reservoir operation aims to achieve optimal benefits in terms of sediment reduction and hydropower generation and considers scientific and rational water allocation in the reservoir while addressing the operational requirements of upstream and downstream reservoirs. In addition to reducing sediment deposition in the reservoir area, sediment deposition in downstream river channels should be minimised by utilising the regulatory function of the reservoir.
Studies on water–sediment regulation in reservoirs primarily focus on two aspects. First, joint optimisation models are established for multiple objectives, including sediment flushing and benefits. For instance, Jin et al. [
10] developed a multi-objective scheduling model for cascaded reservoirs on the upper Yellow River, considering sediment flushing, water supply, and hydropower generation. Hajiabadi et al. [
11] employed the non-dominated sorting genetic algorithm for multi-objective optimisation in the Sefid-Rud Reservoir in northern Iran, resulting in a 37-million-ton increase in sediment scouring. Chen et al. [
12] introduced new objective functions into the optimisation model to address severe sedimentation issues in the Sanmenxia–Xiaolangdi cascaded reservoirs on the Yellow River. However, the current challenge lies in the need for a comprehensive selection of scheduling objectives. Although economic benefits are partially considered, the description of reservoir conditions often relies on simple water balance equations and reservoir capacity relationships, which lack sufficient linkage with sediment-flushing mechanisms. Second, existing sediment-flushing schedules are improved by utilising the kinetic model of sediment transport, providing an understanding of the physical processes involved in erosion and sedimentation. Huang et al. [
13] simulated sediment scouring in the Paonia Reservoir in the mountainous area of Colorado using the SRH-1D sediment transport model. Zulfan et al. [
14] established a coupled hydrodynamic sediment transport model for the Pandanduri Reservoir, employing the MIKE21(2014)FM software to analyse changes in sediment deposition under different operating schemes. Faghihirad et al. [
15] explored water–sediment transport processes in the Hamidieh Reservoir using a three-dimensional turbulence-improved water–sediment model to investigate operation schemes involving various intakes and sluice gates. However, most of the research objects involved are gorge-type reservoirs, but there are few related studies on water–sediment regulation in plain-type reservoirs. Compared with gorge-type reservoirs, plain-type reservoirs have shallow water depths and large storage areas. During the storage period, they are less likely to generate density currents. Moreover, the hydraulic conditions for sediment scouring downstream during flood discharge and sediment-flushing periods are relatively weak. Because of these factors, inflowing sediment cannot be completely transported out of reservoir areas. How to realise the combined operation of water and sediment in plain reservoirs has become a difficult problem in research.
Therefore, water–sediment regulation approaches for plain-type reservoirs require further investigation. The plain-type reservoir of Haibowan on the upper reaches of the Yellow River is taken as an example in this study, and its water–sediment regulation approach is optimised, with the primary goals of extending the reservoir’s lifespan and effectively alleviating sediment deposition in downstream river channels. First, water–sediment regulation schemes are proposed to reduce reservoir sedimentation and enhance sediment transport capacity in downstream river channels. Second, a two-dimensional (2D) kinetic model of sediment transport is used to analyse the morphological changes and sediment deposition in each scheme. Finally, comprehensive comparisons of effective storage capacity and hydropower generation among different schemes are conducted, leading to an optimised water–sediment regulation approach for the reservoir. The flow of water–sediment regulation in Haibowan Reservoir is shown in
Figure 1. The results of this study provide essential support for water–sediment regulation in the Haibowan Reservoir and offer valuable insights into water–sediment regulation practices in similar plain-type reservoirs.
4. Results
4.1. Water–Sediment Regulation Control Indicators
Since its establishment and operation, the Haibowan Reservoir has generally followed the practice of controlling low-water levels during the flood season. Therefore, when determining the sediment-flushing period for the reservoir, a period with high inflow discharge or sediment load should be chosen for operation at low water levels. Although the reservoir does not have a specific sediment reduction task for the downstream river channel, efforts should be made to ease the aggravation of erosion and sedimentation in the downstream river channel caused by reservoir operation. The regulation of water and sediment should be determined depending on the relationship between inflow runoff and sediment. Based on the aforementioned principles, the following three key control indicators have been identified.
4.1.1. Regulation Time
Upstream of the Haibowan Reservoir, other reservoirs such as Longyangxia, Liujiaxia, and Qingtongxia have been constructed. The Longyangxia and Liujiaxia reservoirs generally operate below the flood limit water level from July to September [
20]. The sediment-flushing operation of the Qingtongxia Reservoir is performed in July and August by combining sand peak ‘through-flow’ and sediment flushing at the end of the flood season. Based on the propagation of upstream flood peaks and sediment peaks, the Haibowan Reservoir should lower its water level for sediment flushing, and the timing of sediment flushing should be kept consistent with the upstream reservoirs.
Figure 11 displays the statistics on the daily flow and sediment discharge at Shizuishan station from July to September for the period during 1987–2021. The data reveal a relatively flat distribution of flow but significant fluctuations in sediment discharge, especially in August. In that month, the average sediment discharge amounts to 6.0 t/s, which is noticeably higher than in other months. Failure to timely flush the sediment during this period would accelerate reservoir sedimentation. Therefore, August should be considered a key period for sediment flushing in the reservoir.
Based on the foregoing analysis, the sediment-flushing timing of upstream cascade reservoirs, and the intra-year distribution characteristics of inflow water and sediment, the sediment-flushing period for the Haibowan Reservoir was determined to be from July to September.
4.1.2. Outflow Discharge
Bed-forming discharge is a characteristic flow that is essential in shaping river channels [
21]. The bed-forming discharge in the Bayangol–Toudaoguai segment of the Yellow River has been approximately 2620 m
3/s from 2010 to 2019 [
22]. Fuqin proposed a minimum ecological flow of 300 m
3/s for the Inner Mongolia section of the Yellow River [
23]. The flood control discharge at the Sanshenggong–Toudaoguai segment, as proposed by the Yellow River Conservancy Commission, is considered a control indicator with a discharge of 5900 m
3/s [
24]. Therefore, during the sediment-flushing process in the Haibowan Reservoir, a maximum outflow discharge limit of 2620 m
3/s is considered to avoid over-bank flooding in the downstream river channel and the discharge should not exceed 5900 m
3/s. A minimum outflow discharge limit of 300 m
3/s is set for ecological purposes.
4.1.3. Water–Sediment Regulation Volume
To determine the flow and sediment concentration levels for water–sediment regulation, the inflow water and sediment data from 1987 to 2021 were classified into different levels based on the selected sediment-flushing period of July to September.
- (1)
Sediment-flushing discharge levels
The inflow sediment data were classified into different levels based on intervals of 500 m
3/s, as shown in
Table 3. Low levels, i.e., below 1500 m
3/s, have high frequencies, considerable proportions of water volume, and small sediment concentrations. These levels are suitable for hydropower generation and water supply purposes. High levels, i.e., those exceeding 1500 m
3/s, occur less frequently but have high sediment concentrations. Failure to timely flush the sediment during these levels can lead to reservoir sedimentation. In addition, high levels are associated with large flood flows and can be used for flushing the reservoir area to restore storage capacity. Therefore, when the inflow exceeds 1500 m
3/s, the reservoir should lower its water level for sediment flushing.
The bed-forming discharge at Shizuishan station was 2760 m
3/s from 2010 to 2019 [
22], indicating a strong scouring effect in the reservoir at that flow rate. The bed formation function of the reservoir is not only affected by water and sediment processes but also closely related to the operational mode of the reservoir [
25]. Thus, further control measures should be implemented for flow rates that exceed 1500 m
3/s. When the inflow discharge exceeds 2760 m
3/s, the reservoir should perform open spillage sediment flushing.
- (2)
Sediment-flushing concentration levels
The inflow sediment data were classified into different concentration intervals, as presented in
Table 4. The levels below 3 kg/m
3 have the highest frequency of occurrence, corresponding to the largest water volume, accounting for 52.8%, and a relatively lower sediment load, accounting for 26.2%. The levels that exceed 3 kg/m
3 have a higher sediment load, accounting for 73.8%.
Based on the hydropower generation benefits, the sediment-flushing concentration levels were determined as follows: when the inflow sediment concentration is lower than 3 kg/m3, the reservoir should utilise the water volume to maintain high water levels for power generation. When the inflow sediment concentration exceeds 3 kg/m3, the reservoir should lower its water level for sediment flushing, with normal storage water level as the benchmark. Specifically, when the sediment concentration ranges from 3 kg/m3 to 5 kg/m3, both water and sediment have a significant proportion. In this case, the reservoir water level should be reduced by 1–4 m for sediment flushing, while ensuring power generation. When the sediment concentration ranges from 5 kg/m3 to 10 kg/m3, the sediment has a high proportion. In this case, the reservoir should lower its water level by 3–5 m for sediment flushing. When the sediment concentration exceeds 10 kg/m3, the reservoir enters a critical period for water–sediment regulation and should open all sluices for sediment flushing.
4.2. Water–Sediment Regulation Scheme
4.2.1. Regulation Principles
- (1)
Hydropower generation and regulation principles
At the hydropower station at the Haibowan Reservoir, water discharge regulation has precedence over the power generation schedule. No consideration is given to peak load regulation. Each generating unit has a rated flow of 318.2 m3/s, and the full generation capacity of the four units is 1272.8 m3/s. To maximise hydropower generation, when the inflow discharge is less than 1272.8 m3/s, priority is given to discharging water through the power station. When the inflow discharge exceeds 1272.8 m3/s, priority is given to opening the sediment-flushing outlets of the power station. If the inflow discharge exceeds the sum of the required generation discharge and the sediment-flushing discharge (approximately 1600 m3/s), the sluices are opened. When the reservoir operates at a water level of 1069 m for sediment flushing, the power station ceases power generation and simultaneously opens the sediment-flushing outlets.
- (2)
Downstream irrigation requirements
The agricultural irrigation season in the downstream Yellow River irrigation districts of the Haibowan Reservoir extends from May to October each year. Because of the large water diversion flow, the downstream Sanshenggong conservancy hub has no regulation capacity. To ensure an uninterrupted water supply for irrigation in the downstream districts, the daily outflow discharge from the reservoir should be maintained uniformly to the extent possible.
- (3)
Flood control regulation principle
The Haibowan Reservoir has a small effective storage capacity, whereas the flood volume of the Yellow River is significant. Therefore, the reservoir does not have a flood control task, and flood control measures during the flood season are primarily aimed at ensuring the safety of the project.
- (4)
Sediment-flushing regulation principle
When the inflow sediment discharge is low, the reservoir operates at a high water level to maximise hydropower benefits. When the inflow sediment discharge is high, the reservoir operates at a low water level, simultaneously releasing water for power generation and sediment flushing, aiming to minimise reservoir sedimentation and maximise the regulated storage capacity.
4.2.2. Scheduling Scheme
The sediment-flushing ratio increases as the water level decreases in front of the dam [
26]. However, the operating water level range for the Haibowan Reservoir is only 7 m, i.e., from 1069 m to 1076 m. After considering the reservoir scheduling principles and the water–sediment regulation control indicators, the operating mode can only be optimised by adjusting the water level within a small range. Thus, the different water levels for July to September were controlled. Based on this, the following schemes for sediment flushing and operation of the reservoir were presented.
Scheme 1: For the Haibowan Reservoir, when the daily inflow discharge from July to September is less than 1500 m3/s or the inflow sediment concentration is less than 3 kg/m3, the reservoir operates at a water level of 1076 m. When the daily inflow discharge ranges between 1500 and 2760 m3/s, the inflow sediment concentration is categorised, and specific water level adjustments are made. For sediment concentrations in the range of 3 kg/m3 to 5 kg/m3, the water level is reduced to 1075 m in July and September and to 1072 m in August. For sediment concentrations in the range of 5 kg/m3 to 10 kg/m3, the water level is reduced to 1073 m in July and September, and to 1071 m in August. From July to September, when the inflow sediment concentration is equal to or exceeds 10 kg/m3, or the inflow discharge is equal to or exceeds 2760 m3/s, the water level is reduced to 1069 m by opening sluices for sediment flushing. The outflow discharge should be controlled uniformly from July to September and should not exceed 2620 m3/s.
Schemes 2 and 3 are similar to Scheme 1 in terms of regulation principles and control methods. However, when the inflow discharge ranges between 1500 m
3/s and 2760 m
3/s and the inflow sediment concentration ranges from 5 kg/m
3 to 10 kg/m
3, the water level in front of the dam are adjusted to 1072 and 1071 m, respectively. The details of the regulation schemes are presented in
Table 5.
4.3. Design of Representative Water–Sediment Series
The representative water–sediment series for the Haibowan Reservoir are selected based on the following principles: (1) preference should be given to using measured water–sediment series as they effectively align with the actual reservoir operation during regulation calculations; (2) measured water–sediment series after 1986 should be prioritised, owing to the significant impacts of the Longyangxia and Liujiaxia reservoirs on the downstream river channel [
27]. In particular, the regulation effect on water and sediment in the Inner Mongolia section of the Yellow River is noticeable after reservoir impoundment. In the meantime, water usage in the upstream Yellow River has been increasing, rendering the post-1986 riverbed conditions sufficiently representative of the current situation. (3) The design of the representative water–sediment series should include years with abundant, average, and low water–sediment conditions. Notably, similar water–sediment volumes should be obtained during the flood season and similar sediment volumes should be obtained during the non-flood season, with a large error margin for water volumes.
The P-III-type frequency curve was used to analyse the runoff and sediment discharge data from 1987 to 2021 at Shizuishan station via curve fitting,
Cv is the coefficient of variation,
Cs is the coefficient of skewness, and
Cs/
Cv was adjusted to obtain the optimal design values for water–sediment series, as presented in
Table 6. Based on the selection principles for the representative series, the measured water–sediment processes from 1987 to 2001 at Shizuishan station were selected through comprehensive analysis. Moreover, the sand transported by wind from the Ulan Buh Desert, estimated at 2 million t/a, was included in the sediment inflow to the reservoir, resulting in a 15-year representative water–sediment series.
4.4. Runoff Regulation and Power Calculation
Based on the regulation principles of the Haibowan Reservoir and the proposed water–sediment regulation schemes, three schemes were designed to regulate the inflow runoff series over 15 years. The reservoir was adjusted to account for the effects of reducing the water level during the flood season on power generation while ensuring the requirements for flood control, irrigation, ecological flow, and riverbed flow downstream. The water level was adjusted between normal and dead storage levels. The daily reservoir water level profiles for each scheme are shown in
Figure 12.
Based on the aforementioned hydropower generation regulation principles, the operational mode of the power station at the reservoir is as follows: From July to September, all four generating units are put into operation. When the outflow discharge is less than 1272.8 m
3/s, the generation discharge is equal to the outflow discharge. When the outflow discharge exceeds 1272.8 m
3/s, the generation discharge is fixed at 1272.8 m
3/s. For the remaining months, two to three generating units are put into operation.
Table 7 presents the power generation calculation based on the runoff regulation results.
4.5. Model Simulation Results
The calibrated two-dimensional (2D) kinetic model of sediment transport in the Haibowan Reservoir was used, and the designed water–sediment series from 1987 to 2001 and the results of regulating the reservoir water level for runoff were input into the model boundary. The sediment erosion and deposition of the reservoir were evaluated on an hourly basis. The sediment accumulation pattern based on Scheme 2 is shown in
Figure 13. The specific results of sediment accumulation calculations are presented in
Table 7.
Over time, a significant amount of sediment accumulated in the reservoir, gradually forming wide floodplains and a narrow primary channel. After 15 years of operation, the width of the primary channel was approximately 0.4 km to 0.5 km, demonstrating an accumulation pattern characterised by ‘patch-like sedimentation and linear erosion’. During these 15 years, the primary channel experienced both erosion and sedimentation, whereas the floodplains gradually rose in elevation. After the sand-laden water flowed over the floodplains, because of the different flow velocities between the floodplains and primary channel at the same cross section, variations in sediment exchange occurred between the floodplains, primary channel, and sand-laden water flow. The riverbed of the Haibowan Reservoir area is prone to sediment deposition and erosion. During peak flow or peak sediment conditions, noticeable variations in sediment erosion and deposition occur because of the lateral exchange of water and sediment along the floodplains and primary channel. The floodplains and primary channels influence the simultaneous movement of water and sediment differently. The low flow velocity on the floodplains causes sediment to deposit there first as the sand-laden water flow progresses. With increasing reservoir operation time, the floodplains experience significant sediment deposition, resulting in an overall increase in the elevation of the entire riverbed.
Specifically, after five years of reservoir operation, sediment accumulation in the reservoir area is primarily concentrated within approximately 6 km from the dam, characterised by ‘sedimentation in both the floodplains and primary channel’. The average sediment accumulation thickness exceeds 4 m. In particular, the thickness reaches 7–8 m within the 1–2 km range from the dam. In the range of 6–31 km from the dam, sedimentation is observed as ‘erosion in the primary channel and sedimentation on the floodplains’, with floodplain sediment thickness ranging from 1 m to 3 m. The primary channel of the reservoir experiences overall erosion, with its position remaining relatively stable and not undergoing significant deviation. Upstream inflows split into two branches approximately 10 km from the dam, with the right branch having a steeper longitudinal slope than the left. The sand-laden water flow follows the original sediment transport channel toward the dam. After 15 years of reservoir operation, the reservoir area exhibits an overall pattern of ‘sedimentation in both the floodplains and primary channel’. The floodplain sediment continues to rise within approximately 6 km from the dam, with an average sediment accumulation thickness exceeding 5 m. Sedimentation intensifies closer to the dam, with the most severe accumulation occurring within the 2 km range in front of the dam, where the riverbed elevation ranges only from 1067 m to 1069 m. Under all schemes, the primary channel swings towards the left, with the original primary channel becoming silted up approximately 10 km from the dam. The water flow breaks through the floodplain lips and creates a new primary channel in the left branch of the river. Because of the presence of a large backwater zone in the left branch, the water flow intensity is relatively low, ranging from 0.13 m/s to 0.72 m/s. After the sand-laden water flow enters this new channel, a significant amount of sediment accumulates on the floodplains, forming a stable new primary channel in the reservoir. In the tail section of the reservoir under all schemes, erosion ranges from 0 m to 0.8 m, indicating that even after an additional 15 years of operation, the Haibowan Reservoir is unlikely to face the upstream extension of reservoir sedimentation.
5. Discussion
5.1. Analysis of Simulation Results
The distribution of reservoir sedimentation is closely related to inflow water–sediment characteristics, underwater topography, and water level variations in front of the dam. The Liujiaxia [
28], Qingtongxia, Wanjiazhai [
29], Tianqiao [
30], Sanmenxia [
31], and Xiaolangdi reservoirs [
32] are located on the primary stream of the Yellow River, exhibiting similar inflow sediment characteristics to the Haibowan Reservoir. All of them have relatively high sediment concentrations during the flood season.
The Qingtongxia and Tianqiao reservoirs are low-head reservoirs with a planar distribution characterised by an ‘upper wide, lower narrow’ pattern. The longitudinal slope of the Qingtongxia Reservoir area does not vary significantly, whereas the longitudinal slope of the Tianqiao Reservoir area is steeper in the upper section than in the lower section. This leads to different patterns of sediment deposition in the two reservoirs: scouring dominates the front of the dam of the Qingtongxia Reservoir, whereas the area of the Tianqiao Reservoir is the primary sediment deposition area. At the same time, the sediment accumulation at the end of the reservoir did not extend. The Haibowan Reservoir also operates at a low head and exhibits a similar planar distribution with a steeper upper slope than the lower slope. The sediment simulation results show significant sediment deposition in front of the dam. There is no upstream extension of reservoir deposits, which is similar to the siltation distribution of the Tianqiao reservoir.
The Liujiaxia, Wanjiazhai, Sanmenxia, and Xiaolangdi reservoirs have large ranges of water level fluctuations, and the plane terrain distribution of the Xiaolangdi Reservoir is ‘upper narrow, lower wide’, while the plane terrain distribution of the other three reservoir reservoirs is ‘equal widths between upper and lower parts’. The sediment deposition is mainly distributed in the area in front of the dam, but the overall performance of the Xiaolangdi Reservoir is ‘erosion in the primary channel and sedimentation on the floodplains’. The other three reservoirs showed ‘sedimentation in both the floodplains and primary channel’. This is similar to the Haibowan Reservoir, which also has an ‘upper narrow, lower wide’ planar shape, with sediment deposition primarily occurring in front of the dam, and the performance is ‘equal widths between upper and lower parts’.
The comprehensive analysis demonstrates that the simulation results of the Haibowan Reservoir water–sediment model are reasonably accurate.
5.2. Recommended Optimal Scheme
During the preliminary design stage of the Haibowan Reservoir, the measured water–sediment data from Shizuishan station for the period of 1992–2002 were selected as the representative water–sediment series for reservoir sediment erosion and deposition calculations. Two years after impounding the reservoir, the design inflow water–sediment process from Shizuishan station for the periods of 1968–2006 and 1956–1966 were selected [
33] to calculate the sediment erosion and deposition process in the reservoir. The remaining effective reservoir capacities for each year are presented in
Table 7.
The different schemes were comprehensively compared. In terms of maintaining the effective reservoir capacity, Schemes 1, 2, and 3 had higher effective capacities than the initial design scheme. Unlike Scheme 1, Schemes 2 and 3 had higher effective capacities than the existing achieved scheme, rendering them more proactive in maximising the comprehensive benefits of the reservoir. In terms of hydropower generation benefits, Scheme 1 had the highest average annual hydropower generation, followed by Schemes 2 and 3. All schemes had average annual hydropower generation values greater than that of the preliminary design but slightly lower than the existing achieved hydropower generation. As the effective reservoir capacity tends to be larger than the existing achieved results after 20 years of operation, a slight loss in hydropower generation in the short term can ensure the continuous operation of the power station and maintain the long-term economic benefits of the reservoir.
The important principles for recommending the optimal scheme are to maintain the effective reservoir capacity in the long term and maximise the hydropower generation benefits. Scheme 1 achieved the best hydropower generation benefits but had a small effective capacity. After 20 years of operation, the difference in effective capacity was not significant compared with the initial design and was smaller than the existing achieved results, posing a certain risk during periods of low water inflow. Schemes 2 and 3 had larger remaining effective capacities than Scheme 3, which sacrificed some hydropower generation benefits. Scheme 2 satisfied the requirements for hydropower generation benefits but also maintained a larger effective reservoir capacity. Therefore, implementing Scheme 2 is recommended for the water–sediment regulation of the Haibowan Reservoir.
5.3. Limitations of Water–Sediment Regulation in Plain-Type Sand-Laden Reservoirs
The limitations of water–sediment regulation in plain-type sand-laden reservoirs are threefold. First, the storage period is usually to complete the task of water supply and power generation. Plain-type reservoirs are shallow, with a large amount of sediment flood into the reservoir congestion area, it is difficult to form a density difference with the reservoir water, resulting in less chance of heterogeneous flow, if there is sediment in the reservoir that is basically silted in the reservoir. Secondly, in order to fulfil a certain power generation or water supply task, the sand discharge period usually should not be too long. Plain-type reservoirs have a small topographic longitudinal ratio drop and limited water level changes in front of the dam, so the scouring effect of along-track scouring and backwater scouring is poorer, especially for plain-type reservoirs located on rivers, which are not able to empty the reservoir, and the scouring effect is further weakened. Third, soil and water conservation measures on both sides of the reservoir, such as vegetation cover, wind and sand, and slope erosion, also have an impact on sedimentation.
In summary, plain-type sand-laden reservoirs are easy to silt and difficult to scour. Therefore, when water and sand scheduling, it is recommended to maintain the low water level and high flow rate operation as far as possible during the period of big water and big sand, especially during the coordination period of water and sand peaks and emergence, to control the water flow not to roam the beach and avoid the loss of reservoir capacity in the beach, and to organise water–sediment regulation in time to increase the ratio of sand discharged from the reservoirs, to increase the effective capacity of the reservoir area, and to slow down the rate of siltation of the reservoirs. At the same time, increase the vegetation cover on both sides of the bank and lining slopes, reduce the amount of wind or gravity erosion into the reservoir sand; if necessary, supplemented by artificial sand dredging or human-made means of disturbing the sand discharge, etc., to increase the capacity of the main channel in the reservoir, scouring to control the depth of the main channel rushing and pulling the width of the reservoir, to extend the service life of the reservoir.
In the future, the Heishanxia Reservoir will be established about 350km upstream of the Haibowan Reservoir. The normal storage level of the Heishanxia reservoir in the first-level development plan is 1380m, the original storage capacity is 11.03 billion m3, and the long-term effective regulation storage capacity is about 5.90 billion m3. The primary task of the reservoir is to regulate the discharge during the flood season, solve the problem of flood prevention in the Inner Mongolia River section, coordinate the relationship between the water and sediment of the Yellow River, and improve the channel form so as to create conditions for flood control and flood prevention in the Yellow River. After the completion, it is bound to change the evolution trend of erosion and deposition of Haibowan Reservoir and downstream river and affect the process of water and sediment in the reservoir. Therefore, the study of water and sediment control in the Haibowan Reservoir is still in the initial stage, and the change of water and sediment conditions in the Haibowan Reservoir and its response to the evolution of erosion and deposition need to be further explored and practiced.