Type Selection between Arch Dam and Gravity Dam Based on Construction Simulation: A Case Study
Abstract
:1. Introduction
2. Methodology
2.1. Mechanism Description of Concrete Dam Construction Process
2.2. Theory on Construction Progress Simulation
2.3. Simulation Strategy of Concrete Dam Construction
2.4. The Arch Dam Construction Progress Simulation System
2.5. The RCC Gravity Dam Construction Progress Simulation System
3. Construction Conditions and Data
- (1)
- The Y2 arch dam
- (2)
- The Y2 RCC gravity dam
4. Comparison Method of Dam Types
5. Results
5.1. Calculation Results of the Arch Dam Construction
5.2. Calculation Results of the RCC Gravity Dam Construction
6. Discussion and Dam Type Selection
7. Conclusions
- (1)
- For each dam type in the arch dam and the RCC gravity dam, the construction progress attributes of the Y2 dam are compared to those of similar dams that have been built. It can be found that the construction period of the Y2 dam is rather close to that of the completed dam, in the case of having almost the same height and concrete volume. This indicates that the simulation results of the Y2 dam are consistent with actual construction, and verifies the reliability and accuracy of the simulation methods and systems used in this paper.
- (2)
- According to the simulation results, for the Y2 dam, the construction period of the arch dam is 34 months, and that of the RCC gravity dam is 28 months. From the perspective of construction progress, the Y2 dam type should select the RCC gravity dam.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Salehi, M. Global water shortage and potable water safety; Today’s concern and tomorrow’s crisis. Environ. Int. 2022, 158, 106936. [Google Scholar] [CrossRef] [PubMed]
- Qin, Y.; Mueller, N.D.; Siebert, S.; Jackson, R.B.; AghaKouchak, A.; Zimmerman, J.B.; Tong, D.; Hong, C.; Davis, S.J. Flexibility and intensity of global water use. Nat. Sustain. 2019, 2, 515–523. [Google Scholar] [CrossRef]
- Shi, H.; Chen, J.; Liu, S.; Sivakumar, B. The role of large dams in promoting economic development under the pressure of population growth. Sustainability 2019, 11, 2965. [Google Scholar] [CrossRef] [Green Version]
- Ansar, A.; Flyvbjerg, B.; Budzier, A.; Lunn, D. Should we build more large dams? The actual costs of hydropower megaproject development. Energy Policy 2014, 69, 43–56. [Google Scholar] [CrossRef] [Green Version]
- Schulz, C.; Adams, W.M. Debating dams: The World Commission on Dams 20 years on. Wiley Interdiscip. Rev.-Water 2019, 6, e1396. [Google Scholar] [CrossRef]
- Korkmaz, S. Evaluation of Concrete Face Rockfill Alternative for Dam Type Selection: A Case Study on Gökçeler Dam. Ph.D. Thesis, Middle East Technical University, Ankara, Turkiye, 2009. [Google Scholar]
- Jurecha, W.; Widmann, R. Optimization of dam concreting by cable-cranes. In Proceedings of the 11th International Congress on Large Dams, Madrid, Spain, 11–15 June 1973; pp. 43–49. [Google Scholar]
- Halpin, D.W. CYCLONE–method for modeling job site processes. J. Constr. Div. 1977, 103, 489–499. [Google Scholar] [CrossRef]
- Kalk, A. INSIGHT: Interactive Simulation of Construction Operations Using Graphical Techniques; Stanford University, Department of Civil Engineering: Stanford, CA, USA, 1980; Volume 238. [Google Scholar]
- Ioannou, P.G. UM-CYCLONE. Ann Arbor 1990, 1001, 1–29. [Google Scholar]
- McCahill, D.F.; Bernold, L.E. Resource-oriented modeling and simulation in construction. J. Constr. Eng. Manag. 1993, 119, 590–606. [Google Scholar] [CrossRef]
- Lu, M. Simplified discrete-event simulation approach for construction simulation. J. Constr. Eng. Manag. 2003, 129, 537–546. [Google Scholar] [CrossRef]
- Hajjar, D.; AbouRizk, S.M. Application framework for development of simulation tools. J. Comput. Civ. Eng. 2000, 14, 160–167. [Google Scholar] [CrossRef]
- Oloufa, A.A. Modeling operational activities in object-oriented simulation. J. Comput. Civ. Eng. 1993, 7, 94–106. [Google Scholar] [CrossRef]
- AbouRizk, S.; Halpin, D.; Mohamed, Y.; Hermann, U. Research in modeling and simulation for improving construction engineering operations. J. Constr. Eng. Manag. 2011, 137, 843–852. [Google Scholar] [CrossRef]
- Xu, B.; Zou, D.G.; Liu, H.B. Three-dimensional simulation of the construction process of the Zipingpu concrete face rockfill dam based on a generalized plasticity model. Comput. Geotech. 2012, 43, 143–154. [Google Scholar] [CrossRef]
- Zhong, D.; Li, J.; Zhu, H.; Song, L. Geographic Information System-Based Visual Simulation Methodology and Its Application in Concrete Dam Construction Processes. J. Constr. Eng. Manag. 2004, 130, 742–750. [Google Scholar] [CrossRef]
- Kamat, V.R.; Martinez, J.C. Visualizing simulated construction operations in 3D. J. Comput. Civ. Eng. 2001, 15, 329–337. [Google Scholar] [CrossRef]
- Lu, W.; Olofsson, T. Building information modeling and discrete event simulation: Towards an integrated framework. Autom. Constr. 2014, 44, 73–83. [Google Scholar] [CrossRef]
- Zhang, Y.; AbouRizk, S.M.; Xie, H.; Moghani, E. Design and implementation of loose-coupling visualization components in a distributed construction simulation environment with HLA. J. Comput. Civ. Eng. 2012, 26, 248–258. [Google Scholar] [CrossRef]
- Du, R.X.; Zhong, D.H.; Yu, J.; Tong, D.W.; Wu, B.P. Construction Simulation for a Core Rockfill Dam Based on Optimal Construction Stages and Zones: Case Study. J. Comput. Civ. Eng. 2016, 30, 05015002. [Google Scholar] [CrossRef]
- Guan, T.; Zhong, D.H.; Ren, B.Y.; Song, W.S.; Chu, Z.Q. Construction simulation of high arch dams based on fuzzy Bayesian updating algorithm. J. Zhejiang Univ.-Sci. A 2018, 19, 505–520. [Google Scholar] [CrossRef]
- Zhong, D.; Ren, B.; Li, M.; Wu, B.; Li, M. Theory on real-time control of construction quality and progress and its application to high arc dam. Sci. China Technol. Sci. 2010, 53, 2611–2618. [Google Scholar] [CrossRef]
- Flood, I.; Flood, P.D.L. Intelligent control of construction manufacturing processes using deep reinforcement learning. In Proceedings of the 12th International Conference on Simulation and Modeling Methodologies, Technologies and Applications (Simultech), Lisbon, Portugal, 14–16 July 2022; pp. 112–122. [Google Scholar]
- Fu, S.J.; He, T.; Wang, G.J.; Zhang, S.H.; Zou, L.C.; Chen, S.H. Evaluation of cracking potential for concrete arch dam based on simulation feedback analysis. Sci. China-Technol. Sci. 2011, 54, 565–572. [Google Scholar] [CrossRef]
- Fei, W.; Jinfei, L.; Xishuang, Y.; Yaosheng, T.; Tiangang, Z.; Zhiyue, Y.; Bo, F.; Xiaolong, Y. Intelligent scheduling for high arch dams. J. Tsinghua Univ. 2021, 61, 756–767. [Google Scholar]
- Albulescu, A.-C.; Minea, I.; Boicu, D.; Larion, D. Comparative Multi-Criteria Assessment of Hydrological Vulnerability—Case Study: Drainage Basins in the Northeast Region of Romania. Water 2022, 14, 1302. [Google Scholar]
- Axelsson, C.; Giove, S.; Soriani, S. Urban Pluvial Flood Management Part 1: Implementing an AHP-TOPSIS Multi-Criteria Decision Analysis Method for Stakeholder Integration in Urban Climate and Stormwater Adaptation. Water 2021, 13, 2422. [Google Scholar] [CrossRef]
- Wang, Z.; Zhang, H.; Wang, Y.; Zhou, C. Integrated Evaluation of the Water Deficit Irrigation Scheme of Indigowoad Root under Mulched Drip Irrigation in Arid Regions of Northwest China Based on the Improved TOPSIS Method. Water 2021, 13, 1532. [Google Scholar] [CrossRef]
- Kaewfak, K.; Huynh, V.N.; Ammarapala, V.; Charoensiriwath, C. A fuzzy AHP-TOPSIS approach for selecting the multimodal freight transportation routes. In Proceedings of the Knowledge and Systems Sciences, KSS 2019, Da Nang, Vietnam, 29 November–1 December 2019; pp. 28–46. [Google Scholar]
- Wang, H.; Liu, Q.; Zhang, H.Y.; Jin, Y.L.; Yu, W.Z. A Two-Stage Decision-Making Method Based on WebGIS for Bulk Material Transportation of Hydropower Construction. Energies 2022, 15, 1726. [Google Scholar] [CrossRef]
Parameters | Description |
---|---|
Dam monoliths | Dam body is divided into several dam sections through transverse joints |
Elevation | Elevation of the dam block |
Height | Height of each dam block |
Area | Upper surface area of each dam block |
Volume | Volume of each dam block |
Coordinates | Spatial coordinates of the corner points of each dam block |
Parameters | Description |
---|---|
Mechanical configuration | Two categories: concrete transportation machinery and pouring machinery, including the type and quantity of machinery. |
Concrete production system | Includes the layout location, capacity, and quantity of the production system. |
Meteorological conditions | Includes high winds, heavy rain, high temperature, etc., that affect the construction. |
Effective working hours | Refers to the actual number of construction days per month and the actual construction hours per day. |
Concrete cooling temperature | Poured concrete needs to be cooled to a certain temperature by water before subsequent construction can begin. |
Joint grouting constraint | The horizontal joints that exist after the dam body is poured in blocks are filled with concrete to make the dam form a whole. Generally, this takes 120–180 days. |
Interlayer intermittent | Waiting time of concrete pouring between upper block and lower block. Generally, this takes 3–7 days. |
Cantilever height constraint | The gap between the pouring elevation of a single dam monolith and the elevation of the grout cannot exceed a certain limit. Generally, this is 63–72 m. |
Pouring appearance restrictions | The gap between the pouring elevations between adjacent dam sections should not be excessive. Generally, this is 6–9 m. |
Environment Condition | Month | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |
Average temperature (°C) | 6.1 | 9.4 | 13.3 | 14.8 | 18.3 | 19.9 | 20 | 20 | 17.4 | 14.5 | 8.1 | 5.1 |
Maximum temperature (°C) | 22.2 | 29 | 28.8 | 35 | 37.8 | 38 | 36.2 | 39.1 | 33 | 28.4 | 21.4 | 19.5 |
Minimum temperature (°C) | −5 | −2 | 1 | 5.2 | 6 | 9.5 | 12 | 11.5 | 7.5 | 3.4 | −0.7 | −3.2 |
Average wind speed (m/s) | 0.4 | 0.5 | 0.6 | 0.8 | 0.6 | 0.4 | 0.3 | 0.3 | 0.2 | 0.5 | 0.3 | 0.2 |
Maximum wind speed (m/s) | 4 | 3 | 7 | 9 | 6 | 7 | 4 | 4 | 3 | 5 | 4 | 4 |
Effective working days | 23 | 26 | 24 | 25 | 26 | 25 | 26 | 25 | 28 | 28 | 26 | 25 |
Schemes | The Concrete Production Capacity (m3/h) | The Number of Cables |
---|---|---|
1 | 720 | 4 |
2 | 480 | 4 |
3 | 480 | 3 |
Name | Image | Description |
---|---|---|
Cable crane | The cable crane system uses the bearing cable tensioned between the main and auxiliary towers as the driving track of the load trolley to lift the concrete tank. It is usually arranged on both sides of the river valley, and plays a long-term role throughout the construction period. | |
Dump truck | Dump trucks are commonly used machinery in hydropower for transporting concrete, and are relatively mobile and flexible. For the low-line concrete of the dam body, dump trucks are often used to transport it directly into the storehouse surface from the concrete production system. | |
Vacuum chute | The vacuum chute is a concrete conveying machine with a simple structure, which is usually arranged on the dam shoulder, relying on the slope to convey concrete down quickly and safely, and is especially suitable for roller-compacted concrete. | |
Belt conveyor | The belt conveyor is a handling machine that continuously conveys concrete on a certain line. It can carry out horizontal, inclined, and vertical conveying, and can also form a space conveying line, and the conveyor line is generally fixed. The belt conveyor has a strong conveying capacity and a long transportation distance. | |
Tower belt crane | The tower belt crane is a consortium formed by adding a set of suspension belt conveyor systems to the tower crane. Pouring concrete with the tower belt crane integrates horizontal transportation and vertical transportation, and has a strong pouring concrete capacity, and is a commonly used concrete transportation machinery in recent years. |
Schemes | The Concrete Production Capacity (m3/h) | The Pouring Machinery of Concrete | ||
---|---|---|---|---|
Low-Line Elevation | Medium-Line Elevation | High-Line Elevation | ||
1 | 600 | Dump trucks | Chute and dump trucks | Chute and belt conveyors |
2 | 720 | Dump trucks | Chute and dump trucks | Chute and belt conveyors |
3 | 600 | Dump trucks | Chute and dump trucks | Tower belt crane |
Name | Description |
---|---|
TM | Total months of dam concrete construction |
TD | Total days of dam concrete construction |
PV | Pouring volume of concrete in the month with the highest pouring strength |
PVH | PV, at the high-line elevation of the RCC gravity dam |
PO | Proportion of old concrete in the dam body concrete |
WRH | Water retaining height before the flood period in the second year from the construction beginning |
RH | Average monthly rising height of the dam concrete |
Schemes | CPC (m3/h) | NC | TM (months) | TD (Days) | PV (m3/Month) | PO | WRH (m) |
---|---|---|---|---|---|---|---|
1 | 720 | 4 | 34 | 1009 | 68282 | 1.843 | 63 |
2 | 480 | 4 | 34 | 1016 | 61767 | 2.135 | 63 |
3 | 480 | 3 | 34 | 1021 | 63571 | 2.074 | 63 |
Schemes | CPC | NC | TM | TD | PV | PO | WRH | Sm | ||
---|---|---|---|---|---|---|---|---|---|---|
1 | 1.374 | 1.601 | 1.732 | 1.743 | 0.610 | 1.900 | 1.732 | 0.151 | 0.004 | 0.025 |
2 | 2.062 | 1.601 | 1.732 | 1.731 | 0.552 | 1.640 | 1.732 | 0.061 | 0.094 | 0.609 |
3 | 2.062 | 2.134 | 1.732 | 1.722 | 0.568 | 1.688 | 1.732 | 0.003 | 0.152 | 0.984 |
Schemes | CPC (m3/h) | MC (High-Line Elevation) | TM (Months) | TD (Days) | PV (m3/Month) | PVH (m3/Month) | RH (m/Month) | WRH (m) |
---|---|---|---|---|---|---|---|---|
1 | 600 | Chute and belt conveyors | 28 | 851 | 237550 | 103474 | 7.5 | 115 |
2 | 720 | Chute and belt conveyors | 28 | 841 | 242980 | 116020 | 7.5 | 118 |
3 | 600 | Tower belt crane | 31 | 934 | 237550 | 88377 | 6.77 | 115 |
Schemes | CPC | MC | TM | TD | PV | PVH | RH | WRH | Sm | ||
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 1.855 | 2.062 | 1.796 | 1.784 | 0.569 | 0.579 | 0.596 | 0.572 | 0.001 | 0.123 | 0.995 |
2 | 1.546 | 2.062 | 1.796 | 1.805 | 0.582 | 0.649 | 0.596 | 0.587 | 0.019 | 0.106 | 0.848 |
3 | 1.855 | 1.374 | 1.622 | 1.625 | 0.582 | 0.494 | 0.538 | 0.572 | 0.106 | 0.019 | 0.153 |
Dam Name | Height (m) | Number of Dam Monoliths | Concrete Volume (10,000 m3) | Average Rising Height Monthly (m/Month) | Pouring Period (Month) |
---|---|---|---|---|---|
Y2 dam | 210 | 17 | 150 | 6.18 | 34 |
Jinping I dam | 305 | 26 | 571 | 6.10 | 50 |
Baihetan dam | 289 | 31 | 892 | 5.67 | 51 |
Wudongde dam | 270 | 15 | 273 | 6.92 | 39 |
Dagangshan dam | 210 | 29 | 320 | 5.68 | 37 |
Dam Name | Height (m) | Concrete Volume (10,000 m3) | RCC Volume (10,000 m3) | Average Rising Height Monthly (m/Month) | Pouring Period (Month) |
---|---|---|---|---|---|
Y2 dam | 210 | 327.1 | 277.8 | 7.50 | 28 |
Longtan dam | 216.5 | 736.0 | 495.0 | 5.15 | 42 |
Huangdeng dam | 203 | 350.7 | 275.3 | 5.64 | 36 |
Guangzhao dam | 200.5 | 278.8 | 242.0 | 8.35 | 24 |
Guandi dam | 168 | 297.0 | 253.5 | 6.86 | 24.5 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Zhang, C.; Wang, H.; Cao, J.; Liu, Q.; Liu, F.; Wang, M. Type Selection between Arch Dam and Gravity Dam Based on Construction Simulation: A Case Study. Water 2023, 15, 1482. https://doi.org/10.3390/w15081482
Zhang C, Wang H, Cao J, Liu Q, Liu F, Wang M. Type Selection between Arch Dam and Gravity Dam Based on Construction Simulation: A Case Study. Water. 2023; 15(8):1482. https://doi.org/10.3390/w15081482
Chicago/Turabian StyleZhang, Chao, Hao Wang, Jiayun Cao, Quan Liu, Fang Liu, and Mingtao Wang. 2023. "Type Selection between Arch Dam and Gravity Dam Based on Construction Simulation: A Case Study" Water 15, no. 8: 1482. https://doi.org/10.3390/w15081482
APA StyleZhang, C., Wang, H., Cao, J., Liu, Q., Liu, F., & Wang, M. (2023). Type Selection between Arch Dam and Gravity Dam Based on Construction Simulation: A Case Study. Water, 15(8), 1482. https://doi.org/10.3390/w15081482