Article

Exploring the Influence of Construction Companies Characteristics on Their Response to the COVID-19 Pandemic in the Chilean Context

1
Departamento de Obras Civiles, Universidad Técnica Federico Santa María, Valparaiso 2390123, Chile
2
Civil Engineering Department, Pontificia Universidad Javeriana, Bogotá D.C. 111711, Colombia
3
Departamento de Ingeniería de Obras Civiles, Universidad de La Frontera, Temuco 4780000, Chile
4
Magister en Ciencias de la Ingeniería, Universidad de La Frontera, Temuco 4780000, Chile
*
Author to whom correspondence should be addressed.
Sustainability 2024, 16(8), 3417; https://doi.org/10.3390/su16083417
Submission received: 1 February 2024 / Revised: 12 April 2024 / Accepted: 15 April 2024 / Published: 19 April 2024

Abstract

:
The COVID-19 pandemic was a significant disruption to the construction industry around the globe with multiple impacts, such as workforce limitations and contractual conflicts. Multiple studies have explored the impacts of the pandemic in the construction sector so far. However, little is known about how construction companies responded to the pandemic and what companies’ characteristics may have influenced their responses. The objective of this study is to explore the impacts of COVID-19 and how construction companies responded to the pandemic. To do so, semi-structured interviews with experienced professional working in Chile are qualitatively analyzed to leverage their experience. Furthermore, characteristics of construction companies that influenced how companies responded to the pandemic, namely, size, experience, and financial standing, are explored. The results obtained suggest that the focus in responding to the pandemic was taking care of workers’ safety, improving the planning of projects under highly uncertain conditions, and dealing with the financial stress of developing construction projects. When looking at the influence of companies’ experience, size, and economic capacity, experienced and large companies’ responses were related to implementing teleworking and dealing with a limited workforce. Regarding the economic capacity of construction companies, the focus was placed on responding to the pandemic using multiple sources of financing. Differences identified in how construction companies responded to the pandemic emphasizes the importance of understanding attributes that led companies to having better responses to the pandemic and being prepared for the post-pandemic context.

1. Introduction

The pandemic due to COVID-19 was a global disruption that affected our society and how we lived and interacted [1,2,3]. In fighting the spread of COVID-19, social distancing was implemented, as well as quarantines, to minimize interactions among people, thus disrupting many industries that rely on the physical presence of their workers, such as the construction industry [4]. The construction industry was affected mainly during the pandemic, facing limited worker availability, delays in construction projects, impacts on workers’ productivity, financial stress for construction companies, and legal issues related to force majeure clauses [5,6,7].
In Chile, the context of this study, the pandemic began in March of 2020 with the first person affected by COVID-19. In response, the country implemented the “step-by-step” program that restricted the mobility of people and limited economic activities, impacting multiple industries, especially in the construction sector [8]. The impacts of COVID-19 on the financial stability of construction companies were influenced by internal reasons (e.g., how companies are managed) and the economic environment during the pandemic [7,9]. For instance, the restricted access to materials, safety, and health mandates to be implemented in construction sites influenced workers’ productivity [8]. Other issues were increasing prices of materials and transportation and supply chain problems [10]. Notably, the construction sector plays a significant role in the Chilean economy by representing approximately 6.5% of GDP and generating 8.5% of jobs in Chile [11]. In this context, the role of the construction industry in economic recovery is undoubtedly relevant, and as such, it is fundamental to understand how construction companies responded to the COVID-19 pandemic, namely their organization characteristics [12,13].
The effects of the COVID-19 pandemic in the construction sector have illustrated that it is fundamental for construction managers and companies to have contingency plans to mitigate the consequences of disruptive events such as the pandemic. In the literature, multiple researchers related to the construction industry focused on studying the impacts that the COVID-19 pandemic had on construction projects and companies, for instance, by exploring the construction sector’s effects, challenges, and standard practices and proposing potential solutions for emerging problems [13,14]. Other researchers have analyzed multiple management practices in construction, such as workforce education, digitalization, safety, and workers’ healthcare [15,16,17,18]. Similarly, existing studies have analyzed the impact of the economic response of small and medium-size construction companies [19,20]. Additionally, authors have focused on the consequences on construction projects, such as delays in the schedule, production rates, and workforce management [6,21,22,23,24].
In summary, literature related to the consequences of COVID-19 in the construction industry has focused on multiple dimensions, which generates a holistic understanding of the problem. However, it is crucial to study the impacts and practices implemented during the pandemic and how construction companies adapted and overcame them. In doing so, this study focused on exploring characteristics of construction companies that influence how companies responded to the COVID-19 pandemic, such as size, experience, and financial standing.

2. Literature Review

2.1. Construction Industry Response to COVID-19

The COVID-19 pandemic generated severe impacts among multiple sectors, the construction sector being one of the most affected [25,26]. The construction sector faced unprecedented challenges that required adjustments and adaptations in various areas, such as the financial impact placed on construction companies due to additional spending of companies to adapt to new safety and health protocols, delays in payments, and reduced income levels [8,27]. In this context, construction managers have implemented a wide range of strategies to maintain the operations of construction projects to ensure the financial feasibility of construction companies [28,29,30]. Such strategies have led to the elaboration of plans focused on adjusting construction processes and reducing the exposure to risks of construction workers [14]. As such, construction companies have had to adopt new technologies to improve their decision-making processes and the remote inspection and monitoring of construction sites [31,32,33]. Implementing these strategies has led to the need for training construction workers, more detailed planning, more flexibility with workers, and new safety protocols [34].
The COVID-19 pandemic challenged the construction industry’s supply chain, with significant delays and materials shortages that disrupted construction projects [35,36]. This situation was critical as construction projects require a large variety and quantity of materials [37]. To mitigate this challenge, multiple alternatives were explored, for instance, exploring alternative materials, diversifying the supply chain, and adopting digital tools to manage construction projects [38,39]. A strategy that has sparked a significant interest is integrating recycled materials from construction waste and demolition [40]. However, to implement this type of strategy, more dissemination is required about their implementation. Of note, the pandemic has presented an opportunity to move forward regarding implementing more sustainable practices in the industry [41]. Challenges due to the pandemic have incentivized the collaboration of the construction industry, government, and communities in seeking alternatives that promote innovation and sustainability in construction organizations and projects.
In response to the COVID-19 pandemic, the construction industry implemented significant changes in multiple areas of projects, such as communication, costs and finance of projects, safety, interactions with suppliers and subcontractors, workforce management, and implementing new technologies [42]. Although these changes have brought benefits such as better planning and workforce efficiency, their implementation in the long term may represent a challenge for construction stakeholders. Factors influencing this challenge include significant capital investments, the extension of project duration, and the need for new knowledge and skills among workers [14,43]. Additionally, construction companies typically experience resistance to changes within their organizations, especially when adapting new technologies and work methods [44].
The construction industry has faced a rapid and sudden challenge to adapt due to the COVID-19 pandemic context. Despite these challenges, multiple construction companies were capable of modifying their processes to respond and adapt to the pandemic context and, as such, improving their ability to adapt. This response and adaptation to the pandemic context were vital to ensuring the survival and continuity of the industry. Therefore, it is fundamental to study the characteristics of construction companies that responded and adapted to the pandemic context and, as such, provide a valuable guide for the construction industry on moving forward in a post-pandemic context.

2.2. Characteristics of Construction Companies

Construction projects are inherently diverse, allowing multiple companies to work on different types of projects and stages during the lifecycle of a project. As such, a wide range of company sizes exists in the construction industry [45]. Smaller construction companies tend to focus on specific tasks or projects [46], while larger companies can manage multiple projects simultaneously or large projects such as bridges, highways, and skyscrapers. As such, the classification of construction companies can be based on various parameters, such as the number of workers, the size of the business, the type of projects, or the skills required. Additional factors discussed in the literature include the workforce, political exposure, and the project’s variety of land [47]. Other elements that can contribute to characterizing construction companies may consist of the management approach used by the company, net value, workforce rotation, level of skills development among workers, and profitability of the company, among others [47,48,49]. This large set of characteristics to classify construction companies reinforces the complexity and dynamic aspect of the construction industry.
Interestingly, construction companies’ characteristics influenced the impact suffered due to the COVID-19 pandemic context. Recent literature indicates that small and medium-size construction companies typically have limited resources—i.e., money and workers—these companies have experienced significant disruption due to the pandemic. The decreasing demand for construction projects reduced profits for small and medium companies, generating challenging financial conditions [27,50]. Financial difficulties sometimes cause delays and the halting of construction projects. This context has been influenced by multiple factors, such as the financial assistance provided by governments, the pre-pandemic financial status of companies, relationships with suppliers, the number of employees, and perceptions toward the potential impacts of the pandemic [9]. For instance, the supply chain interruption generated a significant challenge for construction companies, exacerbated by concerns over future financial obligations. Furthermore, international transportation interruptions complicated the efficient procurement of equipment and materials [35]. Challenges in having access to construction materials have primarily impacted small and medium-sized construction companies, as suppliers tend to prioritize large companies due to the large orders placed by such companies. This context resulted in challenges to achieving schedules and budgets for construction projects due to the increases in the price of materials [36]. Conversely, large companies were affected by social distancing policies to prevent the spreading of COVID-19 among workers, which slowed down large projects and reduced the number of workers on the field [27]. Ultimately, it is emphasized that to manage future disruptions faced by the construction industry, it is fundamental to learn from the response of construction companies during the COVID-19 pandemic, accounting characteristics such as company experience, company size, and financial solvency. Therefore, research is required to understand better how construction companies responded to the pandemic, accounting for their characteristics.

2.3. Chilean Construction Industry and COVID-19

Before the pandemic in Chile, the macroeconomic context of financial conditions was favorable for construction sector activity. There was an increase in labor hiring, growth in construction materials sales, and dynamism in the areas approved for non-housing construction. In addition, Chile had an expansive monetary policy in 2019 [51]. In the MAch report (Macroeconomics and Construction of Chile) of May 2019, the result of the Monthly Construction Activity Index (IMACON) registered a variation of 1.3% during the first quarter of the year, a moderate growth compared to the evolution of 2018, while a construction unemployment rate of 8.3% at the end of 2019 and a construction investment of 3.3% of annual variation were forecast [51].
The arrival of the COVID-19 pandemic in Chile in March 2020 translated into a series of restrictions and government policies to deal with the pandemic that disrupted the construction sector [7,52,53]. Given this context, the Chilean Chamber of Construction proposed a safety and health protocol for construction projects to allow the continuity of projects. Then, even when most of the country was in a lockdown to prevent the spread of COVID-19, construction projects, namely infrastructure, were classified as fundamental for the country and were allowed to keep functioning. Despite these efforts, the construction sector experienced a decrease in its operations, leading to lower levels of construction projects and employment and a lower contribution to the country’s GDP [11]. The pandemic also led to shortages and delays in the supply of materials, which increased the prices of such materials and construction projects [11]. Generally, the construction industry contributes around 6.6% of GDP annually. In 2020, this percentage was only 5.7%. This was due to the stoppage of projects in execution for almost six months due to the pandemic. The Monthly Construction Activity Index (IMACON) had, in July 2020, the most significant annual percentage drop in its history, with a decrease of 16.5%. However, the yearly variation as of May 2021 was 16.2% [11]. In addition, the Monthly Construction Activity Index (IMACON) rebounded in the last part of 2021. Still, it fell again in 2022 with the uncertainty generated in the sector and the increase in interest rates, reaching a value of −10.4% [54]. Other essential data highlights the investment in construction, where in 2020 and 2021, this annual variation was −8.8% and 11.2%, respectively [55]. However, due to the continuation of sanitary competition, it dropped drastically to 2.5% per year by 2022 [56]. Unfortunately, since January 2020, the INE (National Institute of Statistics) no longer considers the question that until 2019 allowed identifying unemployment by economic sector. Thus, there is no information on construction unemployment and, therefore, on the sector’s unemployment rate. Therefore, the information for January and February is an estimate made with partial information from the INE, which projected a 9.6% unemployment rate in the construction sector for February [57]. The Chilean government implemented multiple public policies to minimize the impacts of the pandemic in the country. Among the relevant procedures for the construction sector, there was the provision of an emergency income for families affected by the pandemic. A temporal law was approved to protect employment during the pandemic and public funding for small and medium companies (i.e., funding of guarantee for small companies (FOGAPE)) to maintain the country’s economy. In this context, the construction sector experienced increases in the salary of construction workers to attract more workers to construction projects to show the industry’s flexibility and resiliency [54]. The construction industry has faced a significant challenge during the COVID-19 pandemic. Although some mitigation strategies were implemented to alleviate the challenge, the complete recovery may still need to be completed. This context emphasizes the need for studies to understand better the impact of the pandemic on the construction sector and how its companies responded.
Unfortunately, after the end of the COVID-19 health emergency in Chile, the recovery of post-pandemic sectoral investment lost strength due to various phenomena, such as the increase in the price of construction inputs, the rise in inflation, and higher interest rates, in addition to the political-regulatory uncertainties that are still present. The balance of the year 2023 showed a negative annual variation in construction investment of 4% concerning the previous year [56].
The Monthly Construction Activity Index (IMACON) also showed a downward trend. In April 2023, the IMACON had an annual variation of −7.9%; in December; it ended the year with a slight variation of −6.7%. The IMACON indicators with the most significant declines were retail sales of materials (22%) and non-housing building permits (−28.3%) [58]. For 2024, better economic conditions are expected, mainly due to lower inflation and interest rates and significant public investment. However, they cannot prevent construction from experiencing a second consecutive year with negative investment figures of approximately −0.4% [57].

3. Methods

3.1. Sampling and Data Collection

This study aimed to incorporate multiple viewpoints on how construction companies responded to the COVID-19 pandemic. As such, semi-structured interviews were selected as a data collection method due to their flexibility and interaction with interviewees, which facilitates the exploration of construction companies’ characteristics and government strategies in responding to the pandemic. The interview design was supported by organizational characteristics found in the literature review and information about strategies implemented by construction companies during the pandemic. Then, the interview was reviewed by three experts related to construction engineering and management to validate the questions included. The questions were open-ended and were aimed at identifying how construction companies responded to the pandemic and characteristics that were relevant while responding to the pandemic. Furthermore, questions incentivized the discussion about the interviewees’ experience during the pandemic. All questions used during the interviews are shown in Appendix A. Examples of questions formulated during the interviews are the following:
  • How has the financial situation of the construction company in which you are working changed since the pandemic began?
  • Concerning the strategies implemented by the government—e.g., social distancing—how have these affected the productivity of projects? How were these effects mitigated?
  • Regarding subcontractors, have you noticed changes in your interactions with them due to restrictions due to the pandemic?
Experienced professionals interviewed in this study occupy a wide range of positions in construction, such as project engineer, project manager, and contract manager, and worked at private and public companies. Of note, this study focused on professionals at the engineering and management level as they are in jobs that involve decision-making processes related to the companies in which they were working. In so doing, their opinions were more likely to capture how construction companies responded to the pandemic. Based on availability, experienced professionals were contacted by email and phone; interviews were performed online or in person between September and November 2022. Interviews ranged from 30 to 45 min, and all interviews were recorded with the approval of the interviewees.
Experienced professionals were selected based on their experience in construction using a minimum of 4 years and having worked since the beginning of the pandemic to the interview date. In so doing, they have experience in the response of construction companies to the pandemic in its entirety. In total, 19 interviews were collected for this study; interviewees had an average experience of 18 years, which emphasizes the value of the responses collected in our study. The size of the sample is within the range of existing literature using qualitatively analyzed interviews in the field of construction engineering and management (e.g., n = 5, Wang et al. [12]; n = 6, Quilia [59]; n = 18, Carlander and Thollander [60]; n = 25, Halder et al. [61]). Important to note, the referenced literature used interviews to collect experts’ opinions and explore and understand a topic. Results obtained from interviews are exploratory in nature and do not aim to be generalized. The sampling process was developed until the saturation point was achieved [62,63,64]. The concept of saturation refers to the point at which no new information emerges from new interviews [64]. Of note, existing literature suggests the saturation point might be typically reached approximately with 12 interviews [65]. Therefore, the sample size used in this study is supported by theory and comparable literature. Table 1 shows the interviewees’ characteristics.

3.2. Qualitative Analysis

Qualitative methods provide a high level of flexibility in understanding emerging phenomena and problems. As such, multiple researchers have used these methods to explore and understand the impacts of the COVID-19 pandemic on the construction sector (e.g., [8,13,29]). Construction professionals faced and managed most of the effects and consequences of the pandemic on construction companies and projects. To leverage those experiences into scientific knowledge, in this study, information from construction professionals was collected through semi-structured interviews that were qualitatively analyzed. Important to note, the purpose of using a qualitative analysis is to explore and understand how construction companies responded to the pandemic. The focus is on the quality of the information analyzed rather than the quantity; that is why so much work is put into looking for interviewees with experience that can provide valuable and informed opinions about the subject under study. As such, results obtained in this study provide a baseline of how companies responded to the pandemic in the Chilean context, yet our results are not generalizable to the entirety of the Chilean construction industry.
The qualitative analysis involves transcribing, reviewing, and coding emerging topics identified from the interviews. Once the interviews are transcribed, the coding process involves researchers reading and examining the interviews in detail to determine the main ideas and topics emerging from the interviews, following an inductive approach [64]. The main ideas and topics from the interviews are highlighted as excerpts to be classified into categories and corresponding subcategories. The coding process of excerpts into categories and subcategories followed an iterative approach that led to the development of a coding dictionary (see Table 2). Fifty-four subcategories were identified and classified into ten categories, of which eight were related to the response of the companies, and two categories were related to recommendations. Due to space limitations, Table 2 shows only the categories and corresponding subcategories. A more complete and detailed coding dictionary can be seen in the table in Appendix B of this document.
Excerpts are then counted to generate the frequencies for each category and subcategory. Of note, two types of frequencies are developed: the number of times an excerpt was mentioned during an interview (i.e., repetitions) and the number of interviewees that mentioned an excerpt (i.e., respondents). The aim of reporting these frequencies is to illustrate not only the level of awareness for topics and ideas by interviewees but also how many interviewees mentioned such topics and ideas. This study aims to explore and understand the characteristics of construction companies that influenced their responses to the COVID-19 pandemic. It also seeks to compare how the categories and subcategories’ frequencies varied for three construction companies’ characteristics: company size, experience, and financial standing. These characteristics were chosen for the following reasons. First, previously discussed literature about COVID-19 and construction recognized the influence that these characteristics had on how construction companies were able to manage their response to the pandemic. Furthermore, these characteristics are available for the large majority of construction companies. As such, they may facilitate the comparison and transferability of our results with studies from other geographical regions. Ultimately, interviewees discussed them in the subcategories influencing how construction companies adapted during the pandemic (see C3 in Table 2). Of note, this comparison was not performed for recommendations identified during the qualitative analysis, as the study focuses on analyzing the influence of such characteristics during the response to the pandemic.
The proposed characteristics are applied using the following criteria. The company size was defined using Chilean law to classify the size of companies (see Table 3), which depends on the volume of companies’ sales. Micro, small, and medium-size companies are those with sales under 100,000 UF, and large companies are those with over 100,000 UF (see Table 3). UF is a Chilean economic unit used to capture inflation. This classification captures the difference between large and small/medium companies. The economic capacity was defined based on the response from interviewees related to the company having the economic capacity to respond to the pandemic (see Appendix A). Ultimately, based on experience, companies are classified as having less than ten years of experience and ten or more years of experience. This is expected to capture companies that have faced challenges and have adapted before the occurrence of the pandemic and those for whom the pandemic might be their first big disruptive event to be managed.

3.3. Research Limitations

As with any study, this is subject to limitations that must be recognized and discussed. The first limitation might be related to the data collection process used, which was convenience sampling. This method was selected to aim for interviews with experienced professionals who worked during the pandemic context at engineering and management levels so as to qualitatively analyze responses from professionals with experience and exposure to the pandemic context under study. In doing so, one limitation is that our study was focused on professionals involved in decision-making processes in construction companies and, as such, did not include interviewees from other positions, such as onsite workers. This profile of interviewees was chosen as professionals at the engineering and management levels were closer to decisions made by construction companies during the pandemic.
Another limitation of this study is related to the relatively small sample size. The sample collected in this study heavily represents large construction companies with the participants being in management positions and in building construction (see Table 1). These limitations mean our findings may not be applicable to small construction companies and in infrastructure or industrial projects. Of note, the study reached theoretical saturation (i.e., saturation point) among the interviewees, and as such, suggests that contributions can be made to knowledge of construction engineering and management with what can be considered a small sample size. What is more, existing studies with qualitative methodologies and comparable sample sizes have made contributions to construction engineering and management as well (e.g., [8,12,60,61]). In doing so, they reinforce the notion of qualitative analyses in which the primary focus is the quality of the information analyzed versus pure quantity and the exploratory nature of qualitative studies where the main purpose is to understand better a problem instead of purely quantifying some variables of a problem.
Another limitation relates to the country in which this study is developed (i.e., Chile), so our results might not be directly transferable to other countries. Nonetheless, these results shed light on the impact of the pandemic in one country of the Latin American region, where limited studies exist about the consequences of the pandemic in the construction sector. Even though it covers only one country, the study still moves forward the limited understanding of how construction companies of this region of the globe responded to the pandemic.
Ultimately, we emphasize that our study aims to provide further understanding of how construction companies responded to the pandemic by looking at some of their characteristics that were identified from the same interviewees. However, our findings are not generalizable to the Chilean construction industry.

4. Results

Table 4 shows the frequencies in which each subcategory was mentioned (n = 679) and the number of interviewees that mentioned said subcategories (n = 19). Ten categories were obtained from the qualitative content analysis, eight categories referred to how companies responded to the pandemic, and two categories referred to recommendations for workers and companies about how to respond to the pandemic. Additionally, Table 5 shows the frequencies of categories and subcategories of how companies responded to the pandemic, accounting for the influence of experience, company size, and economic capacity of companies.

5. Discussion

5.1. Construction Companies’ Responses to COVID-19

Among the eight categories that focused on how construction companies responded to the pandemic, initiatives for workers (i.e., C2 in Table 4) had the highest frequency, with roughly 30% of responses (see Table 4). This result may be explained due to the extensive list of subcategories included in such a category (i.e., R3 to R19). The most frequent subcategories referred to the PCR test, the vaccination plan for workers, and the proper use of masks. These subcategories are highly related to the sanitary strategies proposed by the Chilean Chamber of Construction (CChC), joined with the Ministry of Health for construction companies, which were shown to be effective in minimizing the spread of COVID-19 and the responses to the virus due to massive vaccination campaigns. Regarding the PCR test and properly wearing masks, these activities were commonly applied as recommended practices in response to the pandemic, for instance, being recommended by the Association of General Contractors (AGC) and the Occupational Safety and Health Administration (OSHA) in the United States [13,14]. Notably, most existing studies were developed in the early stages of the pandemic before massive vaccination was implemented globally. As such, limited studies exist discussing vaccination as a response to the pandemic in the construction sector. Conversely, in Chile, as soon as the COVID-19 vaccine was available, the government and the construction industry highly incentivized construction workers to get vaccinated to be protected against the virus. For instance, one interviewee reported, “For us as a construction company, it was fundamental that our workers were vaccinated to be protected against the virus. Furthermore, for hiring purposes, all workers were required to be vaccinated”.
The category with the second highest frequency was project management (i.e., C4 in Table 4), with 13.8% of excerpts. This category is related to the challenges and consequences of managing construction projects due to restrictions during the pandemic. Subcategories in this category referred to payment statements, which were discussed by 100% of interviewees (see Table 4). Of note, interviewees reported satisfaction with how payments were handled during the pandemic. This finding opposes existing literature discussing delays in processing payments to construction companies [8]; this difference may be due to the timing of the study. This study was developed during the final stage of the pandemic. In contrast, the study of Araya and Sierra [8] was done in 2021, in the middle of the pandemic context, when financial struggles were more frequent among owners and construction companies. Regarding the subcategory of construction projects’ demand (i.e., R26 in Table 4), a large portion of interviewees discussed that construction companies aim to keep construction projects running despite the pandemic context limiting workers’ transportation and workers allowed on the field. The main reason for this result may be related to construction companies trying to maintain their expectations about developing projects despite increasing materials and workforce costs. Along the same lines, the subcategory associated with a budget increase (i.e., R24 in Table 4) showed a high frequency. This result was expected as increased costs of materials and workforce were faced during the pandemic, thus increasing the budgets of construction projects. This result aligns with existing literature where increased costs of construction projects were among the challenges to successfully managing construction projects during the pandemic [8,9,35,36].
Regarding the recommendations (i.e., REC1 and REC2 in Table 4), it can be seen that the most frequent recommendations were related to respecting the sanitary protocols and managing to take PCR and antigen tests for construction workers (see Table 4), which are aligned with how construction companies responded to the pandemic. These results suggest that the response from construction companies in Chile may have been correct in terms of providing a safe working environment to construction workers.
Based on these findings and follow-up discussions with some of the interviewees, two recommendations that are highlighted as improvements due to the pandemic experience are working to do a better planning process and understanding the safety of workers beyond purely physical aspects. The pandemic emphasized the key role that an adequate planning process may have in construction projects facing highly uncertain environments. This is an aspect that has been improved by some of the construction companies that survived the pandemic and that continue doing in the current post-pandemic context. The second aspect that has been improved by the pandemic is that construction companies are understanding the safety of construction workers as something more complex that only the physical dimension of safety and expanding it to include personal or emotional aspects of workers in construction. For instance, it was discussed as a recommendation that emotional support to workers must be provided by construction companies as the pandemic was a stressful period for construction workers. The fear of becoming infected and spreading the disease to their families or losing their jobs during the pandemic was a very difficult situation faced by construction workers.
Although the results of this study are based on the Chilean construction context, the pandemic was a phenomenon that impacted all countries with their corresponding construction sectors. In this context, the authors of this study believe that some of the findings of this study still might be transferable to other countries; for instance, countries with a similar cultural context (i.e., Latin American countries) or also countries classified as developing nations. For example, construction companies located either in Latin American or developing nations may benefit from adapting some of the recommendations made in this study, for instance, recognizing the importance of planning construction projects in highly uncertain environments or providing emotional support to improve construction workers’ safety. Of note, the recommendations may stand, but how these recommendations are implemented may differ among different countries.

5.2. Responses Based on Companies’ Experience

By looking at the influence of construction companies’ experience in how companies responded to the pandemic, this study aims to understand whether said experience contributed to companies being more prepared to face the pandemic. Table 5 shows the frequencies for the eight categories related to how construction companies responded to the pandemic according to the company’s experience. Of note, most respondents indicated that teleworking was implemented in their construction companies due to construction projects being halted at the beginning of the pandemic (see R1 in Table 5) and due to the sanitary protocol proposed by the Chilean Chamber of Construction [51]. Furthermore, experienced and non-experienced companies implemented teleworking for activities that could be performed virtually, emphasizing this approach’s value in developing activities in construction projects. For instance, an interviewee reported, “Teleworking was introduced when projects were halted. Currently, it is used for meeting in projects and with the owner. This approach is here to stay”. Our results emphasize that the application of virtual platforms and tools will facilitate more connectivity among the stakeholders involved in construction projects [7,13].
When looking at the companies’ adaptation capabilities, the company’s experience was the most frequent subcategory. Most respondents (i.e., 12 out of 19; 63%) reported that experience from the construction company and their workers facilitated adapting to the challenges brought by the pandemic (C3 in Table 5). However, adapting to the pandemic meant dealing with multiple challenges identified in our results for construction companies, such as increased budgets (i.e., R24) and increased salaries of construction workers (i.e., R38). Interviewees emphasized that experienced construction professionals generated ideas and initiatives in companies that allowed a better response of construction companies to the pandemic, which is aligned with existing literature suggesting that companies’ experience influenced construction companies’ economic performance during the pandemic [9].

5.3. Responses Based on Companies’ Size

Responses to the pandemic were organized by the construction companies’ size as previously discussed in small/medium size and large size. This was done using the criteria used by the Chilean Ministry of Economy (see Table 3). It can be noticed by looking at Table 5 that both small/medium and large construction companies faced struggles during the pandemic. Among the primary responses to the pandemic, it was noticed that construction budgets increased (i.e., R24 in Table 5) due to the financial challenges existing during the pandemic, such as the limited availability of materials and workforce and limited workers allowed to be on the field. Notably, this subcategory was the most frequent from the financing category (see Table 5). This result emphasizes the financial struggles faced by small and large construction companies during the pandemic, which has been discussed by existing literature [54] and reports from the Chilean Chamber of Construction (CChC) (2020). Similarly, another subcategory that was found relevant was delay in project durations (i.e., R25 in Table 5), which both groups of companies also struggled with. Our results show that roughly 75% of respondents discussed projects being delayed, which is aligned with challenges faced by construction companies in Chile [8] and around the globe [12,13].
Another category that showed many responses was subcontractors (i.e., C7 in Table 5). Subcategories that interviewees highly discussed were limited workforce and salary increases (see Table 5). More than 70% of respondents identified a limited workforce as a challenge for companies in responding to the pandemic, most of them related to companies classified as significant. As discussed by Valladares and Jaque [54], this result can be explained as new skills and competencies were identified to work on construction projects during the pandemic. Along the same lines, interviewees identified salary increases as a challenge, probably in response to the limited workforce previously discussed. Of note, these results suggest that construction companies’ response to the pandemic aimed to deal with multiple challenges during the pandemic.

5.4. Responses Based on Companies’ Economic Capacity

Concerning the influence of the economic capacity of construction companies while responding to the pandemic context, a binary classification was used: companies either had the financial capacity or did not. This characteristic was discussed as a factor influencing how construction companies adapted to the pandemic (see Table 5). In doing so, this study focused on categories related to economic performance during the pandemic.
For the financing category in Table 5, the most frequently discussed subcategories were related to the source of financing for construction projects for companies without economic capacity (see Table 5). The most discussed sources of financing were own capital and obtaining a loan from a bank. Of note, respondents also discussed the presence of banking restrictions to finance construction projects (see Table 5). The high frequencies found for both financing sources may suggest that the financing of projects was a combination of own capital and loans provided by banks, which emphasizes that construction companies are not capable of fully financing a construction project, thus becoming exposed to uncertain and stressful economic environments such as the pandemic.
For the category of suppliers (i.e., C8), the most frequent response was related to the increased cost of materials (see Table 5). Of note, this study could identify some responses from companies to deal with such an increased cost of materials. For instance, interviewees discussed overstocking construction projects with materials (i.e., R42) and buying materials in advance of projects (i.e., R44). These responses were observed primarily on projects with no economic capacity, which makes sense as construction projects with a limited economic capacity had to seek multiple alternatives to reduce the financial impacts of the pandemic. Furthermore, the uncertainty of not knowing what would occur with the construction materials prices may have supported construction companies in doing so.
For the category of social assistance (i.e., C6), the most frequent subcategory referred to the emergency family income (i.e., R34 in Table 5), a one-time economic benefit from the Chilean government for families due to financial struggles during the pandemic. Despite this social assistance aimed at Chilean families, it had some consequences for the construction sector, such as reduced available skilled workforce and increased expected salaries of skilled workers in construction.

5.5. Contributions of This Study

This study contributes to theory and practice. Results of this study contribute to theory by identifying construction companies’ characteristics that influenced their response to the COVID-19 pandemic. Namely, it was found that company size, experience, and economic capacity influenced how construction companies responded to the pandemic. Furthermore, this study revealed the reality of how construction companies responded in the context of a developing nation located in the Latin American region (i.e., Chile). There are limited studies (if any) in the literature that describe how construction companies in Latin America responded to the pandemic, and as such, this study provides valuable insights about how construction companies responded to the pandemic, consequently filling a gap in the existing literature. These findings also contribute to the literature by identifying characteristics from construction companies that were relevant in responding to a highly disruptive scenario (i.e., the COVID-19 pandemic). This knowledge may be valuable for the construction industry and companies to be prepared for potential future disruptive scenarios, for instance, future pandemics or disaster-like scenarios.
In practicality, this study contributes by providing specific characteristics that may assist construction companies in the industry to make better decisions in responding to future potential highly disruptive scenarios. Furthermore, this study emphasizes that differences identified in how construction companies responded to a disruptive scenario such as the pandemic are important to be studied to identify what led construction companies to having better responses and being prepared for future disruptive scenarios. Ultimately, alternatives to respond to disruptive scenarios must be tailored to the specific characteristics of each construction company.

6. Conclusions

This study explored the impacts of COVID-19 on how construction companies in Chile responded to the pandemic by qualitatively analyzing semi-structured interviews with experienced professionals involved in construction projects during the pandemic. The qualitative analysis resulted in eight categories related to how construction companies responded with their corresponding forty-four subcategories and two categories related to recommendations with their corresponding ten subcategories. Additionally, results of this study illustrated the influence of company experience, size, and economic capacity in how construction companies responded to the pandemic.
Additionally, results illustrated that the main topics related to how construction companies responded to the pandemic were associated with implementing teleworking for workers, managing to take PCR tests to workers, limiting the construction workforce and materials price increase, and managing increased construction budgets. These responses suggest that the focus in responding to the pandemic was taking care of workers’ safety, planning construction projects under a highly uncertain context, and dealing with the financial stress of developing construction projects. Similarly, recommendations about how to respond to a pandemic context were highly aligned with the main initiatives used by Chilean construction companies, emphasizing taking care of the safety and health of workers from a physical and emotional perspective and dealing with the financial stress of projects due to the pandemic.
When looking at the influence of companies’ experience, size, and economic capacity, it was found that the most common responses for experienced and large companies were related to implementing teleworking for workers and dealing with increased materials’ prices and a limited workforce. Regarding the economic capacity of construction companies, the main focus in responding to the pandemic was related to the source of financing construction projects. The financing of projects was a combination of obtaining a loan from a bank with the companies’ capital. Other interesting results suggest that social assistance benefits to workers may have had an undesired effect on construction by increasing the salaries of skilled workers and reducing the available skilled workforce.
Ultimately, future work to build upon the findings of this study should evaluate whether good practices learned by construction companies during the pandemic continue to be implemented in the current post-pandemic context.

Author Contributions

Conceptualization, F.A.; Methodology, F.A., P.P., L.A.S., L.S.-V. and Á.F.; Software, O.S.; Validation, L.A.S.; Formal analysis, P.P. and O.S.; Investigation, F.A., P.P. and L.A.S.; Resources, L.S.-V.; Data curation, Á.F.; Writing—original draft, F.A. and P.P.; Writing—review & editing, O.S., L.S.-V. and Á.F.; Visualization, O.S. and Á.F.; Supervision, L.A.S.; Funding acquisition, L.S.-V. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors on request.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A. Interview Questions

  • How many years of experience does your current company have?
  • In which regions is your company located?
  • What is approximately the annual billing of our current company?
  • What type of financing does your company use to finance current construction projects?
  • What is the average number of employees in your company?
  • How many subcontractors your company currently has?
  • What is the specialty of your company? It provides services to private owners, public owners, or both?
  • Since the start of the pandemic, how has the financial situation of your construction company changed?
  • How have you perceived the change in demand for your services since the pandemic began? If so, by how much?
  • Do you think the company experience contributed to adapting to the pandemic effects?
  • Based on your experience, how has the pandemic affected the payments made by the owner to the contractors?
  • Regarding subcontractors, have you noticed changes in your interactions with them due to restrictions due to the pandemic?
  • Regarding suppliers, have you noticed changes in materials stock, renting, or equipment leasing due to the pandemic?
  • Concerning teleworking, what role did it play in the company’s adaptation to the pandemic?
  • Did your company receive assistance from the government during the pandemic as payments and loans? If so, how did this contribute to the company?
  • Concerning the strategies implemented by the government—e.g., social distancing—how have these affected the productivity of projects? How were these effects mitigated?
  • In your opinion, how has your company handled the pandemic? What good practices can you highlight?

Appendix B. Coding Dictionary with Definition of Codes and Sample Responses

IdCriteriaDefinitionSample Response
Companies´ initiatives
C1TeleworkingStatements about the performance of services assisted by technology or telecommunication for employees in construction projects. “All meetings were online due to teleworking to avoid crowding in the field.”
C2Communication with ownerStatements related to communication with the owner due to problems during the pandemic. “Quick decisions could be made due to the direct communication with the owner.”
Initiatives for workers
C3Use of alcohol gelStatements about the usage of alcohol gel to avoid getting infected with COVID-19. “We had clean spots on key places in projects with alcohol gel to wash our hands.”
C4Emotional support to workers Statements about emotional support to workers during the pandemic to deal with the uncertainty of health and personal issues. “We permanently supported workers emotionally, encouraging self-care and support during the pandemic.”
C5Active listeningStatements about listening to workers, focusing on them, and providing emotional support. “Emotional support was provided by showing workers that the company was taking all precautions to care for them.”
C6Proper use of maskStatements about the proper use of masks, with the adequate size covering the nose and mouth of workers. “I highlight that all workers respected safety measures related to the correct use of masks.”
C7Use of multiple working shiftsStatements about the use of multiple times for workers to enter and leave the construction work site to minimize the number of workers. “Our shifts began at different times, namely, 7:30, 8:00, and 8:30 a.m. The same happened for lunch breaks and the time that work ended.”
C8Shifts to use bathrooms at workStatements about using multiple times for workers to use bathrooms to minimize the number of workers in these places. “The shifts to use the bathroom worked very well for us to spread the use of these facilities.”
C9Coordination for lunch breaksStatements about multiple lunch breaks for workers to minimize the number of workers eating lunch.“Time for lunch breaks was extended so all workers could eat their lunch according to the times they were assigned to eat lunch.”
C10Temperature controlStatements about the temperature control process using an infrared thermometer at the entrance and exit of the job site. “At the job site entrance, temperature control points were installed on all projects.”
C11Washing handsStatements related to workers washing their hands with water and soap frequently to avoid the spread of COVID-19. “We tried to have as many washing points as possible on strategic points at the job site.”
C12Signature at the entrance and exit of the workStatements about the process of signing to enter and leave the job site to manage traceability of workers. “As an initiative, workers had to sign to enter and leave the job site to have traceability in case workers got infected.”
C13PCR testStatements related to taking a PCR test to diagnose COVID-19 among construction workers. “All workers permanently took PCR tests to discard that workers on the project were sick.”
C14Vaccination planStatements related to incentivizing construction workers to get vaccinated with the government plan. “As vaccination could be taken to the construction field, workers were sent to public hospitals to be vaccinated during work hours.”
C15Traceability of workersStatements related to the traceability of workers in contact with a sick worker. “Workers showing symptoms were quickly tested to evaluate their health status and trace sources of COVID in the job site.”
C16Private transportationStatements related to private transportation of construction workers from their homes to their job site and vice versa due to sanitary protocols to fight COVID-19. “A private transportation service was hired to move our workers between the job site and their houses.”
C17Social distancingStatements related to limiting the distance around other workers according to sanitary initiatives to deal with COVID-19. “Social distancing required workers to adapt, especially by limiting the zones of each one.”
C18Crowd controlStatements about the number of workers allowed on different zones of the job site to minimize the spread of COVID-19. “Safety talks were more extended to reinforce the crowd control policies on the field.”
C19COVID testing (i.e., antigen)Statements related to applying an antigen COVID-19 test to assess whether workers were infected with COVID-19. “Antigen tests were frequently taken to workers directly on the field.”
Companies´adaptation capabilities
C20ExperienceStatements about the importance of experience for construction companies to adapt to and deal with the pandemic.“Experience from the company’s owners helped quite a lot by planning for the pandemic.”
C21Company sizeStatements related to the influence of the company size in adapting to and dealing with the pandemic. Size was referred to as annual billing and number of workers. “The size of the company helped us to respond to the pandemic economically.”
C22Economic supportStatements about financial resources available to deal with and adapt to the pandemic.“The economic capacity and support the company had allowed it to continue operating during the pandemic.”
Project management
C23Payment statementsStatements about the payments that owners make to contractors due to the physical advancement of construction projects. “We did not have problems with owners with the monthly payments of construction projects.”
C24Budget increasesStatements about the budget increase during a construction project due to materials, workforce, or administration. “In two projects that we currently have, budgets have been updated with increases of roughly 15–20%.”
C25Projects’ duration delayedStatements related to the extension of project duration due to the pandemic context. “As companies were learning how to deal with the pandemic, project durations were extended approximately 10%.”
C26Construction projects demandStatements about the quantity of construction projects required in the industry. “The number of projects demanded was maintained. In our case, it was between 20 to 30 projects simultaneously.”
Financing
C27Own capitalStatements about using companies’ funding to manage and develop construction projects. “We observed that the funding of construction projects was 80% with banks and 20% own capital.”
C28Loan from bankStatements related to companies asking for a loan from a bank to finance a construction project. “Our company uses roughly 40% of bank loans and 60% own capital to fund construction projects.”
C29House loanStatement related to loaning money to people wanting to buy a house. “At the pandemic’s beginning, house loans were easy to get, facilitating our business.”
C30Early paymentsStatements about the role of early payments given by the owner to the contractor often at the beginning of the project. “It depends on the project. [For our] own projects, we got funding from the bank. For private projects, we ask for early payments.”
C31Banking restrictionsStatements related to requirements from banks to provide financing to construction companies. “If your company had a good economic history, you could quickly access bank loans. Otherwise, the process was much slower.”
C32Public resourcesStatements about support from public resources to construction companies.“Public funding was provided to construction companies to assist them with their economic situation by the public budget direction.”
Social assistance
C33Law to protect jobs during COVID-19Statements related to procedures needed to be followed to access the law that protected jobs during the pandemic. “Several projects were delayed and halted due to their application to the law that protected jobs during the pandemic.”
C34Emergency family income (IFE in Spanish)Statements about the economic assistance provided by the government (i.e., IFE) to alleviate the economic situation of Chilean families. “IFEs affected the presence of workers on the field as the assistance allowed workers to stay at home and not have to go to work.”
C35Funding to support small companies (FOGAPE in Spanish)Statements related to government programs that assisted small companies affected by the pandemic with financial help. “The government provided the FOGAPE assistance to loan money to small companies at 0% interest and should be paid back in a couple of years. These help us to keep working in 2020.”
Subcontractors
C36Unqualified workforceStatements about the presence of unqualified workers on construction projects during the pandemic. “Unqualified workers began to be more common in construction projects, bringing problems with productivity and delays.”
C37Limited workforce Statements related to the limited qualified workforce in construction projects during the pandemic context. “The problem was the lack of a qualified workforce in projects. Workers did not want to continue working or switched jobs during projects.”
C38Salary increases Statements about the increased salaries of workers due to the limited offer of qualified workers and high demand of projects. “Subcontractors suffered with the salary increases of a qualified workforce. Workers did not want to work on the pre-pandemic salaries.”
Suppliers
C39Materials prices increase Statements about the increasing cost of materials during the pandemic due to high demand and limited supply. “The construction company was slow in reacting to the price increase.”
C40Transportation costs increaseStatements related to the increasing cost of transportation of materials. “We also had problems with transportation of materials due to importations and the increasing fuel cost.”
C41Limited stockStatements about the limited availability of construction materials due to all restrictions during the pandemic.“As our project began in 2021, we expected limited stocks, so we prepared a large warehouse with materials.”
C42OverstockStatements related to the massive buying of construction materials to stock construction projects.“We prepared our budget to overstock our project during the pandemic.”
C43Delays in deliveryStatements about delays in delivering materials to construction projects during the pandemic. “We had delays in the arrival of materials of approximately 1 or 2 months.”
C44Buying materials in advance of projectsStatements related to companies’ strategy of buying construction materials in advance of projects to avoid delays. “We always have bought materials in advance to have available all materials required on the field for construction projects.”
Recommendations to companies
C45Respect sanitary protocolsStatements about respecting the sanitary protocols established to deal with the COVID-19 pandemic.“I highlight the instructions provided by protocols to deal with COVID-19 in construction projects. Also, the role of safety engineers enforcing it.”
C46Buying materials in advance of projectsStatements related to buying materials in advance to avoid stock problems during construction projects. “Buying materials in advance is recommended as a good practice to ensure availability. It is important to have multiple suppliers.”
C47Planning based on objectivesStatements about planning for objectives in construction projects, especially when projects are subject to changes. “I recommend planning based on objectives and considering costs and time as a strategy to deal with big changes, such as a pandemic.”
C48Apply teleworking Statements about the use of teleworking in construction projects, especially for administrative jobs that are not required to be on the field. “I highlight the flexibility that teleworking provides to workers. Our company facilitated teleworking by providing all the equipment and software required to work from home.”
C49Manage to take PCR and antigen testsStatements related to the continuous checking of the health status of workers through PCR and antigen tests to minimize the spread of COVID-19. “At the beginning, the PCR test was widely implemented in projects, and then, during 2021, the antigen test was used to avoid the spread of COVID-19.”
C50Permanent communication with the ownerStatements about permanent interaction with the owner of projects to make joint decisions about the construction of projects.“Following the budget with the corresponding costs and low productivity during the pandemic allowed [us] to talk with the owner to negotiate the contract cost directly.”
Recommendations to workers
C51Respect and commitment to sanitary restrictions Statements about workers knowing how sanitary protocols contribute to COVID-19 and respecting sanitary protocols dealing with COVID-19. “I emphasize that workers knew each other and took care between them; a team spirit existed in the projects to accomplish the sanitary protocols.”
C52Emotional support and active listening Statements related to construction professionals having to listen to and support workers on the field to alleviate the emotional burden and uncertainty during the pandemic. “It is important to be conscious and have the patience to enforce sanitary protocols but that at the same time workers feel supported and listened to.”
C53Promote self-caringStatements about construction professionals promoting self-care among construction workers to deal with personal health, family, and coworkers. “Insist in self-care of workers; the need to permanently convince workers was the most challenging during the pandemic.”
C54Incentivize vaccination Statements about incentivizing construction workers to get vaccinated against COVID-19.“Our company was strict in requesting vaccinations to workers to prevent the spread of COVID-19 in our projects.”

References

  1. Li, R.; Zhang, F.; Wang, Q. How does the EU’s COVID-19 economic recession impact the renewable energy of other countries? The spillover effect. Energy Strat. Rev. 2022, 40, 100825. [Google Scholar] [CrossRef]
  2. Silva, P.H.N.; de Araújo, J.M. Inflation, perception of economic uncertainty and COVID-19: Evidence from Central Bank communication. Cent. Bank Rev. 2023, 23, 100108. [Google Scholar] [CrossRef]
  3. Chen, N.; Zhou, M.; Dong, X.; Qu, J.; Gong, F.; Han, Y.; Qiu, Y.; Wang, J.; Liu, Y.; Wei, Y.; et al. Epidemiological and clinical characteristics of 99 cases of 2019 novel coronavirus pneumonia in Wuhan, China: A descriptive study. Lancet 2020, 395, 507–513. [Google Scholar] [CrossRef] [PubMed]
  4. Wu, F.; Liang, X.; Lei, J. Modelling COVID-19 epidemic with confirmed cases-driven contact tracing quarantine. Infect. Dis. Model. 2023, 8, 415–426. [Google Scholar] [CrossRef]
  5. Maqbool, R.; Patil, K. UK Construction Industry Standing in the COVID-19 Era: Understanding the Impacts on Projects. J. Urban Plan. Dev. 2023, 149, 04023014. [Google Scholar] [CrossRef]
  6. Amien, D.H.; Elbeltagi, E.; Mashhour, I.M.; Ehab, A. Impact of COVID-19 on Construction Production Rate. Buildings 2023, 13, 1127. [Google Scholar] [CrossRef]
  7. Ayat, M.; Malikah; Kang, C.W. Effects of the COVID-19 pandemic on the construction sector: A systemized review. Eng. Constr. Archit. Manag. 2021, 30, 734–754. [Google Scholar]
  8. Araya, F.; Sierra, L. Influence between COVID-19 Impacts and Project Stakeholders in Chilean Construction Projects. Sustainability 2021, 13, 10082. [Google Scholar] [CrossRef]
  9. Pazdzior, A.; Sokol, M.; Styk, A. The Impact of the COVID-19 Pandemic on the Economic and Financial Situation of the Micro and Small Enterprises from the Construction and Development Industry in Poland. Eur. Res. Stud. J. 2021, XXIV, 751–762. [Google Scholar] [CrossRef]
  10. Araya, F.; Sierra, L.; Basualto, D. Identifying the Impacts of COVID-19 on Chilean Construction Projects. Lect. Notes Civ. Eng. 2023, 251, 623–635. [Google Scholar] [CrossRef]
  11. Valladares, R.; Barahona, P. Chile: Informe Sector Construcción e Inmobiliario. Grupo Security. 2021. Available online: https://www.inversionessecurity.cl/sites/inversiones/files/documentos_descargables/Informe%20Sector%20Construcci%C3%B3n%20e%20Inmobiliario%2008.2021_1.pdf (accessed on 6 March 2024).
  12. Wang, L.; Zhao, D.; Zhong, Y. Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19. Sustainability 2021, 13, 6481. [Google Scholar] [CrossRef]
  13. Assaad, R.; El-Adaway, I.H. Guidelines for Responding to COVID-19 Pandemic: Best Practices, Impacts, and Future Research Directions. J. Manag. Eng. 2021, 37, 06021001. [Google Scholar] [CrossRef]
  14. Raoufi, M.; Fayek, A.R. New Modes of Operating for Construction Organizations during the COVID-19 Pandemic: Challenges, Actions, and Future Best Practices. J. Manag. Eng. 2022, 38, 04021091. [Google Scholar] [CrossRef]
  15. Almohassen, A.S.; Alkhaldi, M.S.; Shaawat, M.E. The effects of COVID-19 on safety practices in construction projects. Ain Shams Eng. J. 2023, 14, 101834. [Google Scholar] [CrossRef]
  16. Duan, P.; Goh, Y.M.; Zhou, J. The impact of COVID-19 pandemic on construction safety in China and the U.S.: A comparative study. Saf. Sci. 2023, 161, 106076. [Google Scholar] [CrossRef] [PubMed]
  17. Ko, C.H.; Abdulmajeed, H.A. Improving Construction Safety: Lessons Learned from COVID-19 in the United States. Sustainability 2022, 14, 7137. [Google Scholar] [CrossRef]
  18. Kim, S.; Lee, M.; Yu, I.; Son, J.W. Key Initiatives for Digital Transformation, Green New Deal and Recovery after COVID-19 within the Construction Industry in Korea. Sustainability 2022, 14, 8726. [Google Scholar] [CrossRef]
  19. Ahmad, T.; Haroon, H.; Baig, M.; Hui, J. Coronavirus Disease 2019 (COVID-19) Pandemic and Economic Impact. Pak. J. Med. Sci. 2020, 36, S73. [Google Scholar] [CrossRef]
  20. Alara, S.A. Organizational characteristics and COVID-19 safety practices among small and medium construction enterprises (SMEs) in Nigeria. Front. Eng. Built Environ. 2021, 1, 41–54. [Google Scholar] [CrossRef]
  21. Tekin, H. The impact of COVID-19 on construction labor productivity: The case of Turkey. Eng. Constr. Archit. Manag. 2022, 29, 3775–3806. [Google Scholar] [CrossRef]
  22. Fekry Youssef, M.; Fathy Eid, A.; Mohamed Khodeir, L. Challenges affecting efficient management of virtual teams in construction in times of the COVID-19 pandemic. Ain Shams Eng. J. 2023, 14, 102008. [Google Scholar] [CrossRef]
  23. Mahind, S.D.; Patil, D. COVID-19—Assessment of Economic and Schedule Delay Impact in Indian Construction Industry Using Regression Method. Lect. Notes Civ. Eng. 2023, 260, 283–297. [Google Scholar] [CrossRef]
  24. Gara, J.A.; Zakaria, R.; Aminudin, E.; Yahya, K.; Sam, A.R.M.; Loganathan; Munikanan, V.; Yahya, M.A.; Wahi, N.; Shamsuddin, S.M. Effects of the COVID-19 Pandemic on Construction Work Progress: An On-Site Analysis from the Sarawak Construction Project, Malaysia. Sustainability 2022, 14, 6007. [Google Scholar] [CrossRef]
  25. Mahasuar, K. COVID-19 and its impact on Indian construction industry: An event study approach. Constr. Manag. Econ. 2023, 41, 428–444. [Google Scholar] [CrossRef]
  26. Gumusburun Ayalp, G.; Çivici, T. Factors affecting the performance of construction industry during the COVID-19 pandemic: A case study in Turkey. Eng. Constr. Archit. Manag. 2022, 30, 3160–3202. [Google Scholar] [CrossRef]
  27. Ling, F.Y.Y.; Zhang, Z.; Yew, A.Y.R. Impact of COVID-19 Pandemic on Demand, Output, and Outcomes of Construction Projects in Singapore. J. Manag. Eng. 2022, 38, 04021097. [Google Scholar] [CrossRef]
  28. Waheeb, R.A.; Wheib, K.A.; Andersen, B.S.; Al-Suhiili, R. Impact of Pandemic SARS COVID-19 on Different Construction Project Management: Problems and Solutions. Public Work. Manag. Policy 2022, 28, 306–338. [Google Scholar] [CrossRef]
  29. Stride, M.; Renukappa, S.; Suresh, S.; Egbu, C. The effects of COVID-19 pandemic on the UK construction industry and the process of future-proofing business. Constr. Innov. 2023, 23, 105–128. [Google Scholar] [CrossRef]
  30. Li, Z.; Jin, Y.; Li, W.; Meng, Q.; Hu, X. Impacts of COVID-19 on construction project management: A life cycle perspective. Eng. Constr. Archit. Manag. 2022, 30, 3357–3389. [Google Scholar] [CrossRef]
  31. AbdulLateef, O.; Sanmargaraja, S.; Oni, O.; Anavhe, P.; Mewomo, C.M. An association rule mining model for the application of construction technologies during COVID-19. Int. J. Constr. Manag. 2023, 24, 2212420. [Google Scholar] [CrossRef]
  32. Qureshi, A.H.; Alaloul, W.S.; Wing, W.K.; Saad, S.; Musarat, M.A.; Ammad, S.; Kineber, A.F. Automated progress monitoring technological model for construction projects. Ain Shams Eng. J. 2023, 14, 102165. [Google Scholar] [CrossRef]
  33. Mhmoud Alzubi, K.; Salah Alaloul, W.; Malkawi, A.B.; Al Salaheen, M.; Hannan Qureshi, A.; Ali Musarat, M. Automated monitoring technologies and construction productivity enhancement: Building projects case. Ain Shams Eng. J. 2023, 14, 102042. [Google Scholar] [CrossRef]
  34. Kassem, M.A.; Radzi, A.R.; Pradeep, A.; Algahtany, M.; Rahman, R.A. Impacts and Response Strategies of the COVID-19 Pandemic on the Construction Industry Using Structural Equation Modeling. Sustainability 2023, 15, 2672. [Google Scholar] [CrossRef]
  35. Farooq, S.A.; Indhu, B.; Jagannathan, P. Impact of COVID-19 on supply chain management in construction industry in Kashmir. Asian J. Civ. Eng. 2023, 24, 429–438. [Google Scholar] [CrossRef]
  36. Sutterby, P.; Wang, X.; Li, H.X.; Ji, Y. The impact of COVID-19 on construction supply chain management: An Australian case study. Eng. Constr. Archit. Manag. 2023, 30, 3098–3122. [Google Scholar] [CrossRef]
  37. Herrera, R.F.; Sánchez, O.; Castañeda, K.; Porras, H. Cost overrun causative factors in road infrastructure projects: A frequency and importance analysis. Appl. Sci. 2020, 10, 5506. [Google Scholar] [CrossRef]
  38. Lv, Z.; Chen, D.; Lv, H. Smart City Construction and Management by Digital Twins and BIM Big Data in COVID-19 Scenario. ACM Trans. Multimed. Comput. Commun. Appl. 2022, 18, 1–21. [Google Scholar] [CrossRef]
  39. Gartoumi, K.I.; Aboussaleh, M.; Zaki, S. Building Information Modelling: A key approach for the recovery of the architecture, engineering construction industry post COVID-19. Proc. Inst. Civ. Eng. Eng. Sustain. 2022, 176, 82–93. [Google Scholar] [CrossRef]
  40. Ramos, M.; Martinho, G. Relation between construction company size and the use of recycled materials. J. Build. Eng. 2022, 45, 103523. [Google Scholar] [CrossRef]
  41. Ebekozien, A.; Aigbavboa, C.; Aigbedion, M. Construction industry post-COVID-19 recovery: Stakeholders perspective on achieving sustainable development goals. Int. J. Constr. Manag. 2021, 23, 1376–1386. [Google Scholar] [CrossRef]
  42. Zhang, X.; Yang, E. Have housing value indicators changed during COVID? Housing value prediction based on unemployment, construction spending, and housing consumer price index. Int. J. Hous. Mark. Anal. 2023, 17, 242–260. [Google Scholar] [CrossRef]
  43. Kisi, K.P.; Sulbaran, T. Construction Cost and Schedule Impacts Due to COVID-19. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2022, 14, 04522024. [Google Scholar] [CrossRef]
  44. Sierra, F. COVID-19: Main challenges during construction stage. Eng. Constr. Archit. Manag. 2022, 29, 1817–1834. [Google Scholar] [CrossRef]
  45. Guo, B.H.W.; Yiu, T.W.; González, V.A. Does company size matter? Validation of an integrative model of safety behavior across small and large construction companies. J. Saf. Res. 2018, 64, 73–81. [Google Scholar] [CrossRef]
  46. Waqar, A.; Hannan Qureshi, A.; Othman, I.; Saad, N.; Azab, M. Exploration of challenges to deployment of blockchain in small construction projects. Ain Shams Eng. J. 2023, 15, 102362. [Google Scholar] [CrossRef]
  47. Kamal, E.M.; Flanagan, R. Key Characteristics of Rural Construction SMEs. J. Constr. Dev. Ctries. 2014, 19, 1–13. [Google Scholar]
  48. Bailey, M.; Booth, C.A.; Horry, R.; Vidalakis, C.; Mahamadu, A.M.; Awuah, K.G.B. Opinions of small and medium UK construction companies on environmental management systems. Proc. Inst. Civ. Eng. Manag. Procure. Law 2020, 174, 23–34. [Google Scholar] [CrossRef]
  49. Giménez, Z.; Herrera, R.F.; Sánchez, O. Value generation analysis within the design process of construction projects in Chile. Ain Shams Eng. J. 2023, 15, 102332. [Google Scholar] [CrossRef]
  50. Krajníková, K.; Smetanková, J.; Ručinský, R.; Mésároš, P.; Zemanová, L. Comparison of the Impacts of the Financial Crisis and the COVID-19 Pandemic Crisis on Selected Financial Indicator of Construction Companies. In Proceedings of the EAI International Conference on Management of Manufacturing Systems, Bratislava, Slovakia, 24–26 October 2023; pp. 197–208. [Google Scholar] [CrossRef]
  51. Hurtado, J. Informe MACh 50. 2019. Available online: https://cchc.cl/uploads/archivos/archivos/MACh50-2019.pdf (accessed on 6 March 2024).
  52. Hartmann, A.J.; Gangl, K.; Kasper, M.; Kirchler, E.; Kocher, M.G.; Mueller, M.; Sonntag, A. The economic crisis during the COVID-19 pandemic has a negative effect on tax compliance: Results from a scenario study in Austria. J. Econ. Psychol. 2022, 93, 102572. [Google Scholar] [CrossRef] [PubMed]
  53. Cámara Chilena de la Construcción. Informe de macroeconomía y construcción (MACh 52). 2020. Available online: https://cchc.cl/uploads/archivos/archivos/INFORME_MACh52_abril_2020.pdf (accessed on 1 July 2023).
  54. Valladares, R.; Jaque, F. Revisión Sectores Construcción e Inmobiliario. 2022. Available online: https://www.inversionessecurity.cl/sites/inversiones/files/documentos_descargables/Informe%20Inmobiliario%2006-2022.pdf (accessed on 6 March 2024).
  55. Cámara Chilena de la Construcción. MACh 61. 2022. Available online: https://cchc.cl/uploads/archivos/archivos/Informe-MACh-61.pdf (accessed on 6 March 2024).
  56. Cámara Chilena de la Construcción. MACh 64. 2023. Available online: https://cchc.cl/uploads/archivos/archivos/Informe_MACh64.pdf (accessed on 6 March 2024).
  57. Cámara Chilena de la Construcción. MACh 65. 2024. Available online: https://cchc.cl/uploads/archivos/archivos/a-Informe-MACh-65.pdf (accessed on 6 March 2024).
  58. Koljatic, J. Revisión Sectores Construcción e Inmobiliario. Departamento de Estudios. 2023. Available online: https://www.inversionessecurity.cl/sites/inversiones/files/documentos_descargables/Informe%20Construcci%C3%B3n%20e%20Inmobiliario%20%28jul-23%29.pdf (accessed on 6 March 2024).
  59. Quilia, V. Desafíos en la Gestión Empresarial de las Mypes en Tiempos de COVID-19; Universidad César Vallejo: Trujillo, Peru, 2020. [Google Scholar]
  60. Carlander, J.; Thollander, P. Barriers to implementation of energy-efficient technologies in building construction projects—Results from a Swedish case study. Resour. Environ. Sustain. 2023, 11, 100097. [Google Scholar] [CrossRef]
  61. Halder, S.; Afsari, K.; Chiou, E.; Patrick, R.; Hamed, K.A. Construction inspection & monitoring with quadruped robots in future human-robot teaming: A preliminary study. J. Build. Eng. 2023, 65, 105814. [Google Scholar] [CrossRef]
  62. Hennink, M.; Kaiser, B.N. Sample sizes for saturation in qualitative research: A systematic review of empirical tests. Soc. Sci. Med. 2022, 292, 114523. [Google Scholar] [CrossRef] [PubMed]
  63. Corbin, J.; Strauss, A. Basics of Qualitative Research: Techniques and Procedures for Developing Grounded Theory, 4th ed.; San Jose State University: San Jose, CA, USA; SAGE Publications, Inc.: Thousand Oaks, CA, USA, 2014. [Google Scholar]
  64. Saldaña, J. The Coding Manual for Qualitative Researchers, 2nd ed.; SAGE Publications Ltd.: London, UK, 2013. [Google Scholar]
  65. Galvin, R. How many interviews are enough? Do qualitative interviews in building energy consumption research produce reliable knowledge? J. Build. Eng. 2015, 1, 2–12. [Google Scholar] [CrossRef]
  66. Ministerio de Economía de Chile. Antecedentes para la Revisión de los Criterios de Clasificación del Estatuto Pyme. 2014. Available online: https://www.economia.gob.cl/wp-content/uploads/2014/04/Boletin-Revision-Clasificacion-Estatuto-Pyme.pdf (accessed on 1 March 2023).
Table 1. Interviewees’ characteristics.
Table 1. Interviewees’ characteristics.
IdPositionProfessionYears of
Experience
Organization Category
1Facility ManagerCivil Engineer19Public Organization
2Project ManagerConstruction Engineer4Building Construction
3Senior Project EngineerConstruction Engineer19Real Estate
4Facility ManagerCivil Engineer35Faculty
5Project ManagerConstruction Engineer17Building Construction
6Project ManagerConstruction Engineer21House Building
7Senior Project EngineerConstruction Engineer30Industrial Assembly
8Supply Chain ManagerConstruction Engineer12Building Construction
9Project ManagerConstruction Engineer12Building Construction
10Project ManagerConstruction Engineer28Building Construction
11Project ManagerConstruction Engineer21Technical Inspection
12Project ManagerConstruction Engineer24Building Construction
13Field EngineerConstruction Engineer12Building Construction
14Project ManagerCivil Engineer14Building Construction
15General ManagerConstruction Engineer7Building Construction
16Contract ManagerCivil Engineer11Design
17Owner Representative Architect24Technical Inspection
18Construction ManagerConstruction Engineer21Building Construction
19Bidding ManagerCivil Engineer20Industrial Assembly
Table 2. Categories and subcategories of construction companies’ responses to the COVID-19 pandemic.
Table 2. Categories and subcategories of construction companies’ responses to the COVID-19 pandemic.
IdCategoriesIdSubcategories
C1Companies’ initiativesR1Teleworking
R2Communication with owner
C2Initiatives for workersR3Use of alcohol gel
R4Emotional support to workers
R5Active listening
R6Proper use of mask
R7Use of multiple working shifts
R8Shifts to use bathrooms at work
R9Coordination for lunch breaks
R10Temperature control
R11Washing hands
R12Signatura at the entrance and exit of the work
R13PCR test
R14Vaccination plan
R15Traceability of workers
R16Private transportation
R17Social distancing
R18Crowd control
R19COVID testing (i.e., antigen)
C3Companies’ adaptation capabilities R20Experience
R21Company size
R22Economic support
C4Project managementR23Payment statements
R24Budget increases
R25Projects’ duration delayed
R26Construction projects demand
C5FinancingR27Own capital
R28Loan from bank
R29House loan
R30Early payments
R31Banking restrictions
R32Public resources
C6Social assistanceR33Law to protect jobs during COVID-19
R34Emergency family income (IFE in Spanish)
R35Funding to support small companies (FOGAPE in Spanish)
C7SubcontractorsR36Unqualified workforce
R37Limited workforce
R38Salary increases
C8SuppliersR39Materials prices increase
R40Transportation costs increase
R41Limited stock
R42Overstock
R43Delays in delivery
R44Buying materials in advance of projects
REC1Recommendations to companiesR45Respect sanitary protocols
R46Buying materials in advance of projects
R47Planning based on objectives
R48Apply teleworking
R49Manage to take PCR and antigen tests
R50Permanent communication with the owner
REC2Recommendations to workers R51Respect and commitment to sanitary restrictions
R52Emotional support and active listening
R53Promote self-caring
R54Incentivize vaccination
Table 3. Chilean stratification of companies. Source: Ministerio de Economía de Chile [66].
Table 3. Chilean stratification of companies. Source: Ministerio de Economía de Chile [66].
Company SizeClassification According to SalesClassification According to the Number of Employees
Micro0–2400 UF0–9
Small2400.01 UF–25,000 UF10–25
Medium25,000.01 UF–100,000 UF25–200
Large100,000.01 UF or more200 or more
Table 4. Frequency of categories and subcategories from the qualitative analysis.
Table 4. Frequency of categories and subcategories from the qualitative analysis.
IdCategoriesIdSubcategoriesRepetitionsRespondents
Frequency%Frequency%
C1Companies’ initiatives (8.1%)R1Teleworking446.5%19100.0%
R2Communication with owner111.6%842.1%
C2Initiatives for workers (29.9%)R3Use of alcohol gel 81.2%736.8%
R4Emotional support to workers91.3%736.8%
R5Active listening50.7%421.1%
R6Proper use of mask213.1%1052.6%
R7Use of multiple working shifts 202.9%1157.9%
R8Shifts to use bathrooms at work 60.9%631.6%
R9Coordination for lunch breaks192.8%1368.4%
R10Temperature control 182.7%1157.9%
R11Washing hands60.9%631.6%
R12Signature at the entrance and exit of the work 20.3%210.5%
R13PCR test253.7%1578.9%
R14Vaccination plan 213.1%947.4%
R15Traceability of workers 30.4%315.8%
R16Private transportation 101.5%842.1%
R17Social distancing 111.6%947.4%
R18Crowd control162.4%1052.6%
R19COVID testing (i.e., antigen)30.4%315.8%
C3Companies’ adaptation capabilities (3.7%)R20Experience152.2%1368.4%
R21Company size60.9%631.6%
R22Economic support40.6%421.1%
C4Project management (13.8%)R23Payment statements 233.4%19100.0%
R24Budget increases 304.4%1578.9%
R25Projects duration delayed 223.2%1473.7%
R26Construction projects demand 192.8%1894.7%
C5Financing (7.2%)R27Own capital 121.8%1052.6%
R28Loan from bank 162.4%1473.7%
R29House loan 40.6%210.5%
R30Early payments 71.0%736.8%
R31Banking restrictions91.3%842.1%
R32Public resources 10.1%15.3%
C6Social assistance (6.5%)R33Law to protect jobs during COVID-19152.2%947.4%
R34Emergency family income (IFE in Spanish)274.0%1894.7%
R35Funding to support small companies (FOGAPE in Spanish)20.3%210.5%
C7Subcontractors (8.1%)R36Unqualified workforce172.5%1157.9%
R37Limited workforce355.2%1473.7%
R38Salary increases 233.4%1263.2%
C8Suppliers (12.4%)R39Materials prices increase 365.3%1263.2%
R40Transportation costs increase101.5%736.8%
R41Limited stock131.9%842.1%
R42Overstock121.8%947.4%
R43Delays in delivery71.0%631.6%
R44Buying materials in advance of projects60.9%421.1%
REC1Recommendations to companies (5.2%)R45Respect sanitary protocols131.9%1368.4%
R46Buying materials in advance of projects20.3%210.5%
R47Planning based on objectives30.4%210.5%
R48Apply teleworking 60.9%526.3%
R49Manage to take PCR and antigen tests81.2%842.1%
R50Permanent communication with the owner30.4%315.8%
REC2Recommendations to workers (2.2%)R51Respect and commitment to sanitary restrictions 40.6%421.1%
R52Emotional support and active listening 50.7%526.3%
R53Promote self-caring20.3%210.5%
R54Incentivize vaccination 40.6%315.8%
Total679 19
Table 5. Frequency of responses from the Chilean construction industry to COVID-19.
Table 5. Frequency of responses from the Chilean construction industry to COVID-19.
IdCategoriesIdSubcategoriesExperience (Years)Company Size (UF)Economic Capacity (Yes/No)
Repetitions *Respondents **Repetitions *Respondents **Repetitions *Respondents **
≤10>10≤10>10≤100,000>100,000≤100,000>100,000YesNoYesNo
C1Companies’ initiativesR1Teleworking3412171529613935415
R2Communication with owner2917564411017
Total55021720356131045415
C2Initiatives for workersR3Use of alcohol gel 080735340807
R4Emotional support to workers271618163634
R5Active listening050414131413
R6Proper use of mask120193182831828
R7Use of multiple working shifts 41611051538119110
R8Shifts to use bathrooms at work 060624242424
R9Coordination for lunch breaks31611251458217211
R10Temperature control 21611051338117110
R11Washing hands151515151515
R12Signature at the entrance and exit of the work 020211110202
R13PCR test124114916510520312
R14Vaccination plan 417182191861527
R15Traceability of workers 030312120303
R16Private transportation 0100819171917
R17Social distancing 01109110182927
R18Crowd control0160105113731328
R19COVID testing (i.e., antigen)030312120303
Total181851164715651231172413
C3Companies’ adaptationR20Experience11411251058213211
R21Company size060633330606
R22Economic support040413134040
Total124117916613619415
C4Project manajementR23Payment statements 221217617613617415
R24Budget increases 129114921510525411
R25Projects’ duration delayed 319212715311517410
R26Construction projects demand 217216712612316315
Total88621729656131975415
C5FinancingR27Own capital 0120101111921028
R28Loan from bank 115113412311313311
R29House loan 040231113111
R30Early payments 161643432516
R31Banking restrictions090827262726
R32Public resources 010101011010
Total24721714356131336415
C6Social assistanceR33Law to protect jobs during COVID-19411182131831227
R34Emergency family income (IFE in Spanish)324216918612621414
R35Funding to support small companies (FOGAPE in Spanish)020202020202
Total7372161133612935414
C7SubcontractorsR36Unqualified workforce11611071047215110
R37Limited workforce1341137284101619410
R38Salary increases 02301222111141939
Total27311616594132253413
C8SuppliersR39Materials prices increase 0360129273953139
R40Transportation costs increase0100728254625
R41Limited stock01308211175826
R42Overstock1111857273936
R43Delays in delivery070625151615
R44Buying materials in advance of projects060424132413
Total18311622624132064413
* n = 585; ** n = 19.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Araya, F.; Poblete, P.; Salazar, L.A.; Sánchez, O.; Sierra-Varela, L.; Filun, Á. Exploring the Influence of Construction Companies Characteristics on Their Response to the COVID-19 Pandemic in the Chilean Context. Sustainability 2024, 16, 3417. https://doi.org/10.3390/su16083417

AMA Style

Araya F, Poblete P, Salazar LA, Sánchez O, Sierra-Varela L, Filun Á. Exploring the Influence of Construction Companies Characteristics on Their Response to the COVID-19 Pandemic in the Chilean Context. Sustainability. 2024; 16(8):3417. https://doi.org/10.3390/su16083417

Chicago/Turabian Style

Araya, Felipe, Paula Poblete, Luis Arturo Salazar, Omar Sánchez, Leonardo Sierra-Varela, and Álvaro Filun. 2024. "Exploring the Influence of Construction Companies Characteristics on Their Response to the COVID-19 Pandemic in the Chilean Context" Sustainability 16, no. 8: 3417. https://doi.org/10.3390/su16083417

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop