Next Article in Journal
Woodfuel Consumption in Refugee Hosting Areas and Its Impact on the Surrounding Forests—The Case of Uganda
Previous Article in Journal
The Effect of Pine Wood Nematode Bursaphelenchus xylophilus (Steiner and Buhrer) Nickle on Intestinal Bacterial Community of Insect Vector Monochamus saltuarius (Coleoptera: Cerambycidae)
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Introducing New Index in Forest Roads Pavement Management System

by
Mohammad Javad Heidari
1,*,
Akbar Najafi
1 and
Jose G. Borges
2
1
Department of Forest Science and Technology, Faculty of Natural Resources and Marine Sciences, Tarbiat Modares University, Tehran P.O. Box 14115-111, Iran
2
Forest Research Centre, School of Agriculture, University of Lisbon, 1649-004 Lisbon, Portugal
*
Author to whom correspondence should be addressed.
Forests 2022, 13(10), 1674; https://doi.org/10.3390/f13101674
Submission received: 26 August 2022 / Revised: 22 September 2022 / Accepted: 27 September 2022 / Published: 12 October 2022
(This article belongs to the Section Forest Operations and Engineering)

Abstract

:
Forest road pavement needs an evaluation methodology based on a comprehensive assessment of road conditions. This research was conducted to evaluate the performance of a method for rating the surface condition of forest roads and eventually to adapt the method to the situation prevailing in a forest road network. The rating method selected as the basis for this experiment was the pavement condition index (PCI) developed by the U.S. Army Corps of Engineers for urban roads. In addition, unpaved road condition index (URCI) that has a good index for unpaved road evaluation used for comparison. A 53 km of forest roads were selected containing the most influential factors and variability of conditions. Eventually, 201 road segments were delineated between 150–300 m in length. Within the given segments, sample plots were set 20 m in length consecutively. It was concluded that the panel scores for distress and surface condition of sample unit and section differed from the forest road pavement condition index (FRPCI), URCI, and PCI. Linear regression was used to derive equations between distress and URCI and PCI scores to determine effective FRPCI parameters that provide a numerical rating for the condition of road segments within the road network, where 0 worlds are the worst possible condition, and 100 is the best possible condition best. In addition, regression analysis showed that the FRPCI model with a 0.77 correlation for the total of the road is a performance index used for the first time in forest roads. This study showed a range of FRPCI from 7.8 to 96.3, different from PCI and URCI ratings (0.85–45 and 1.2–53). The FRPCI index helps forest managers in road maintenance, harvesting, and planning to use road information.

1. Introduction

Forest roads are a fundamental prerequisite for the sustainable management of forest resources [1]. Forest roads provide many benefits, such as access to timberland, timber removal, fire prevention, recreation, protection, and research. These benefits have led to an increasing demand to construct new roads, and further extend the forest road network. One of the most important road construction components is the pavement layer of the road, which plays an important and effective role in load bearing and trafficability. The forest roads pavement is a type of structure that includes layers of different natural materials, and the main purpose of its implementation is to reduce the stress caused by car wheels, as well as valuable investment in forest management, which spends a lot of money on their maintenance every year [1]. However, road construction and maintenance are generally some of the more expensive activities in the timber transportation process [2]. Due to budget limitations and increasing pavement maintenance and rehabilitation challenges, Pavement Management System (PMS) has become a beneficial management tool for road maintenance agencies. Well-considered pavement management strategies can only accomplish pavement design by utilizing low-cost and up-to-date principles for material usage of forest roads. Concerning this, appropriate rules must be established in the pavement management of forest roads. Comparing the difference between the needed and the actual expenses for maintaining standard conditions of the pavement, the proper strategy and the optimum timing can be chosen [3].
The performance of forest road pavements has long been recognized as an essential parameter during design and maintenance operations. In order to measure and develop a model for pavement performance, it is necessary to clearly define the pavement performance [4]. Pavement performance is defined as “the serviceability trend of pavement over a design period, where serviceability indicates the ability of the pavement to serve the demand of the traffic in the existing conditions” [5]. Pavement performance can be obtained by observing its structural and functional performance or predicting pavement serviceability from its initial service time to the desired evaluation time [4]. Pavement deterioration can be attributed to age, climatic variables, traffic, environment, material properties, pavement thickness, pavement strength, and subgrade properties that affect mechanical characteristics [1].
The pavement condition assessment is a qualitative relationship between the pavement condition and the influential factors [6]. The pavement condition is helpful in developing a pavement management system (PMS) or Maintenance Priority Index (MPI). The Pavement condition index (PCI) prioritizes the pavement maintenance schedule based on distress severity and its condition [7]. The PCI is a subjective method of evaluation based on an inspection of the road segment. However, it is neither a complex nor time-consuming exercise [8]. Knowledgeable and experienced public works officials drive the road network and systematically evaluate its condition. The data are entered into a database to calculate the PCI of road segments [6]. Road pavement should be evaluated using PCI annually to evaluate changes in the road conditions [9]. In order to evaluate pavement conditions, the road network must be divided into manageable segments. The sections with relatively uniform pavement structures, design, and traffic volumes will have similar performance characteristics [10]. A pavement deterioration model, which acts as the hub of the analysis component, is the engine of the whole management activity [11]. It is an analytical method for rating the surface condition to support where, when, and why to implement maintenance and repair actions. Unfortunately, the matter of rating surface conditions has scarcely been treated in the literature. It was probably owing to two facts: (a) the cost of surface rating made according to an adopted method may seem to be prohibitive if compared with an overall subjective evaluation made by an experienced technician, and (b) the actual task and value of objective rating methods have not yet been appraised by management authorities. The U.S. Army Corps of Engineers, the American Public Works Association, and others have developed pavement management systems (PMSs) such as PCI for unpaved roads. These PMSs cannot currently be used for forest or gravel (unpaved) roads because of the nature of the PCI method, which does not include all situations of unpaved roads [12]. An unsurfaced road component that can stand alone or be used with any of these PMSs would provide local highway agencies with a comprehensive roadway management system that would be more suitable for their needs. For unpaved roads, researchers [13,14] introduced the Unpaved Road Condition Index (URCI), by which the types of distress found in unpaved roads are categorized and listed in the manual forum. There is a description of the type and severity level, an illustration, and a measurement method for each type of distress listed. The manual also includes inspecting unsurfaced road conditions, a field inspection worksheet, and a family of deduct-value curves for the distress types and associated severity levels. The rating method on the URCI method and strategies are compatible with the PAVER PMS developed by the U.S. Army Corps of Engineers and the American Public Works Association. for forest roads, a different situation is dominant regarding heavy vehicle passes, heavy rainfall, unpaved roads, tree harvesting, the canopy of trees, and topographic problems (high aspect, slope, and elevation) [1]. A forest road component that can stand alone or be used with any of PMSs would provide local agencies with a comprehensive road management system that would be more suitable for their needs. For these reasons, the mentioned indexes may not be suitable for evaluating forest road pavement conditions. The aim of this research was to develop a method for rating forest road pavement conditions to prioritize maintenance operations.

2. Materials and Methods

2.1. Reviewing PCI and URCI

The PCI procedure is the road industry standard and the military to visually assess the current pavement condition. The procedure described by the American Society for Testing and Materials (ASTM) D6433-09 (2009) has been used in this study. The PCI provides a numerical rating for road segment properties (e.g., distress, drainage, ditch) within each road network, where 0 is the worst possible condition and 100 is the best (Table 1) [15].
All indexes are used to:
  • Identify immediate maintenance and rehabilitation needs;
  • Monitor pavement condition over time;
  • Develop a network preventive maintenance strategy;
  • Develop road maintenance budgets;
  • Evaluate pavement materials and designs.
In URCI field manual (Figure 1) identified six unsurfaced road distresses and two drainage-related distresses, each with a separate index. As a result of the field validation, the manual was modified by combining the two indices to list the following seven distresses: Improper cross-section, Roadside drainage, Corrugations, Dust, Potholes, Rutting, and Loose aggregate. A deduct value is a number from 0 to 100, with 0 meaning that the distress has no impact on the road condition and 100 meaning that the road has completely failed [13].
PCI and URCI are calculated by HDM-4 software, a software package, and associated documentation that will serve as the primary tool for the analysis, planning, management, and appraisal of road maintenance, improvements, and investment decisions that are only suitable for public and rural roads. Because this software is calibrated for URCI and PCI, we used it to calculate these indexes and cannot use it for the FRPCI index.

2.2. Forest Road Pavement Condition Index (FRPCI)

Surface condition is related to several factors, including structural integrity, capacity, distress, and rate of deterioration [1]. Direct measurement of all these factors requires expensive equipment and skilled experts. However, these factors can be assessed by observing and measuring (directly) the distress of the surface.
a.
FRPCI. The FRPCI is a numerical indicator on a scale of 0 to 100.
The FRPCI indicates the road’s integrity and surface operational condition. Its scale and associated ratings, Table 2, are identical to the Pavement Condition Index (PCI) for surfaced roads.
b.
Determination of FRPCI. The FRPCI is determined by measuring surface distress.
The current study evaluated the performance of FRPCI on a 185 km forest road.
The FRPCI index achieves from the average weight of all sections and shows the rating of the branch. For example, if a skilled expert collected the following information:
A pothole (12 cm), rutting (5 cm), protrusion (6 cm), ditch (not fill), drainage (fill), shoulder (0.35 m), trench (fall), canopy (10%), rise fall (40 m/km), and severe embankment damage. According to Table 2, the FRPCI of this segment will achieve:
1.1 + 6.5 + 5.5 + 10 + 2 + 7 + 1 + 9 + 5.2 + 2.5 = 49.8 (Fair Condition)

2.3. Forest Road Survey

A forest road network with a 185 km length was selected to evaluate the performance of FRPCI. Before the forest road network was inspected, it was divided into branches, sections, and sample units (Figure 2). The road hierarchy is composed of branches, sections, and sample units. The data were obtained once this division was completed.
Branch: A branch is an identifiable part of the forest road network, a single entity with a distinct function. For example, individual roads, depot areas, and range roads are separate branches of a forest road network [1].
Section: A section is a branch division with specific and consistent characteristics throughout its area or length. These characteristics are (1) Structural composition (thickness and materials), (2) Construction history, (3) Traffic, (4) Surface condition [1].
Sample unit: A sample unit is an identifiable area of the forest road section; it is the shortest length of the forest road network. For forest roads, a sample unit is defined as an area of approximately 100 m2. Detailed sample unit measurements should be conducted to compute the ratings annually. These measurements must be made at the same time of year when the roads are in their best and most consistent condition. To make the measurements, the inspector must recognize certain kinds of problems called distresses. Table 2 shows the ten distress types of forest roads.
The sample unit shown in Figure 2 has 20 m of severe improper cross-section. The equipment needed to do a survey was a hand odometer (measuring wheel) used to measure distress lengths and areas, a straight edge, and a ruler to measure the depths of potholes, ruts, or loose aggregate according to the FRPCI distress guide. If two or more distresses occur together, each one was measured separately. If it was hard to determine what distress was observed, a reasonable estimate was made that the system is flexible enough to calculate an accurate rating. Since the FRPCI is based on these descriptions, the inspector must follow information closely when doing an inspection, including 20 m of right-of-way width, included for measuring the trench slope (hill and fill slope) and canopy of trees.

2.4. Study Area

This research was conducted in Chob-kaghaz Mazandaran, which maintains approximately 400 km of primary gravel-surfaced low-volume roads located in three separate watersheds in Mazandaran province north of Iran (Figure 3). Altitude ranges from 150 to 850 m a.s.l. with average annual precipitation of 850 mm. The area is located between 48°44′36″ and 48°49′58″ of longitude and 37°37′23″ and 37°42′31″ of latitude, and other features showed in Table 3.

2.5. Data Collection

Following an intensive field survey, the present study selected forest roads in five districts: Aleshrood, Zengaldareh, Sangdarka, Angetarood, and Hamsava. The length of each section or branch was not the same. Each section was further divided into 30 to 60 of 20 m sample units. Intensive surveys have been carried out on all five road sections. Road Inventory included Pavement Condition (rut, pothole, and protrusion), shoulders condition, soil properties soil of roadbed, rainfall, channel (status of filled), properties of shoulders (width), surface drainage arrangement, traffic, the thickness of the pavement, type of material, percent of crown and slope, sub-base, base, and type adjoining land. In addition, surface drainage ratings and shoulders have been observed. In the Pavement Condition, rut depth, pothole depth, and protrusion have been measured. Different types of traffic have been counted at the road entrance.
Pavement Condition Survey of all the roads has also been completed by measuring rutting, pothole, and protrusion in the central portion of each subsection and edge drop. Traffic data of all the roads have been taken, consisting of an average of 3 days’ traffic for different vehicle classes. Trucks (2-Axle and 3-Axle), Jeeps, Cars, and Tractor-trailer [16]. The data has been taken six times during peak period (P) and standard (N). Data are presented in Table 3.
The following parameters have been considered for determining FRPCI values: Rutting, Pothole, Protrusion, Condition of the shoulder, and Rise fall. The weighting given to various parameters is: For parameters of the shoulder condition and surface drainage arrangement, weights have been given based on excellent, very good, fair, poor, and failed condition (5 for Excellent, 4 for Very Good… and 1 for Failed). For parameters of Rutting, Pothole, Protrusion, Shoulder, and Rise fall, the weighting has been given based on Min. and Max. Values [1]:
(a)
For Rutting: Min. 0.2 cm and Max. 20 cm (10-1)
(b)
For Pothole: Min. 1.1 cm and Max. 15.5 cm (10-1)
(c)
For Protrusion: Min. 0.1 cm and Max. 13.5 cm (10-1)
(d)
For rising fall: Min. 3 m and Max. 140 m (10-1)

3. Results

The statistical analysis of the data (regression model) presented in Table 4, Table 5 and Table 6 has been completed. Weightings (sum score of each section) have been given to various parameters related to the pavements. Forest roads pavement condition index (FRPCI) has been calculated based on weights.
The score of parameters cited in Table 4 is presented below (calculated from Table 3). Table 4 weightings of each district are calculated based on score catchment from Table 3, and these scores show the rating and value of FRPCI variables.
Determination of FRPCI value for forest roads district is calculated by summing the values in Table 4 and comparing them with the PCI and URCI indices presented in Table 5. The FRPCI value is calculated by the sum of min and max weights from Table 4, and the mean of them calculates the final FRPCI; also, URCI and PCI were calculated by HDM-4 software.
The FRPCI index has higher values than the PCI and URCI indices, which indicates that the condition of forest roads has been better estimated using this index because, in forest roads, the desired standards are much lower than rural and highways roads. Figure 3 shows the FRPCI value in five districts of the forest roads network. Figure 4 shows that FRPCI varies among the forest road network (7.8 to 96.3). The maximum and minimum FRPCI were obtained at the Aleshrood and the Hamsava branch, respectively. Although the Aleshrood branch had various scores, the final FRPCI showed a maximum score (of 64.95).

Regression Analysis

The regression analysis has been done considering FRPCI as a function of traffic, annual rainfall, the volume of timber harvesting, forest road management history, and slope as independent variables on total the district.
Table 6 gives data regarding FRPCI and independent variables for various roads used for regression analysis at the section level, regression analysis for the Hamsava branch showed that parameters had a positive relationship with distress severity for the forest roads pavement in this branch shown in Table 7 and other parameters were not significant on FRPCI.

4. Discussions

A relationship was found between distress values attributed to the sample units by the FRPCI values obtained as a function of distress density. The same thing applies to the section: the section score agrees with the FRPCI rating (Table 7). The experiment was done with roads in use, and lacked the necessary amplitude of distress density to test the whole range of possibilities. Another drawback of the experiment is its size. A larger giant experiment will be necessary for calibrating FRPCI values. The experiment should be large enough to guarantee a sufficient number of distresses of each kind.
This research showed that the Sangdarka branch had the highest correlation value, although this site is the second rating according to the FRPCI index (Table 3 and Table 4). The sample units in this branch were riverine, and distress had a normal disturbance. The Angetarood branch is the worst among the five sections based on the FRPCI index with a good correlation (0.75). A notable point in the forest network was that all sample units with fewer scores have the same feature. For example, in sample units in Aleshrood, Sangdarka, Angetarood, Zengaldareh, and Hamsava branch with more than 250 vehicles, inadequate drainage, and fewer than six months of maintenance scored lower, as was expected from the parameter’s score.
The intensive traffic on selected forest road pavements had the most negative influence on the performance of forest roads. Hence the causes for the distress of these roads can be identified as drainage and construction quality [17]. Field tests have shown that the proper placement of FRPCI depends on general data, which is shown in Table 1. The frequency of traffic and road activities such as maintenance grading, ditching, and mowing can result in FRPCI, URCI, and PCI [18].
The result of the survey represents all the maintenance operations needed to upgrade the forest road network. The sum of the maintenance interventions on each road branch represents one possible alternative in the ranking procedures. The field survey shows that 8% of the total extension of the forest road network is in good condition, while the remaining 92% requires maintenance interventions. Fewer than 855 maintenance interventions have been identified among 201 sections that show FRPCI needs proposed parameter for FRPCI in our paper to explain the situation of forest roads. Poor drainage due to improper side drain, road chamber, and damaged culvert lead to Pavement deterioration. It occurred when FRPCI scored less than 65.
The ratings calculated using this procedure can be used to effectively manage forest roads’ maintenance. Each forest manager can set stockholder FRPCI ratings to establish a maintenance strategy [19]. For example, a rating of 50 on a road would require maintenance action to restore the road to a rating of 75 or higher.
This technique could be used as a stand-alone or manual pavement management system, or it could be used in conjunction with other traditional methods or any other automated PMS developed in the future [1].
Forest roads are complex engineering structures on which transport efficiency and reliable access to the forest both depend. The construction of forest roads involves high capital expenditure and, in addition, there is continuing cost for road maintenance [20]. Forest road maintenance is essential, especially in the Caspian Forest with hilly areas and weather conditions such as rainfall. Therefore, FRPCI should be carried out with close observation of the economic aspect and the topographic difficulty, such as forest terrain.
The method of rating unsurfaced roads has been developed and field-validated in five test areas. The current method can be used alone to rate forest roads or incorporated into automatic, computer-aided pavement maintenance management systems for road use. This method should provide the data necessary for the optimum allocation of resources and the maintenance of forest roads in the best possible condition at the least cost.
The distresses “improper cross-section” and “inadequate roadside drainage” should be treated differently from other distresses because they are not distressing themselves but rather sources of distress. A vehicle can travel by a good cross-section with comfort and security. The same is true with inadequate roadside drainage. For all distresses, the density should ideally be dimensionless, with no exception. In the FRPCI method the distresses were “improper cross-section,” “inadequate roadside drainage,” and “potholes.” Based on Table 6, the combined regression equation for five districts separately and whole districts showed a good significant value for FRPCI (Figure 2). The result in Table 5 shows that rainfall, traffic, slope, the volume of timber harvested, and management experience could be used for quickly calculating forest road conditions because these parameters had the most significant effect on the FRPCI.
From the analysis in Table 5, we observed that the FRPCI is technology-based and widely used to determine isolated conditions. However, when combined parameters are used, we found that rainfalls negatively impact road conditions. Slope, traffic, and the volume of timber also have a higher effect on FRPCI rating. The least factors in Table 7 showed include shoulder condition, drainage as well as the overall condition which actually are visually observed. This finding is almost the reality that for forest roads, using visuals to judge road condition is more subjective. The findings also concur with the conclusion proposed by Heidari et al. [1] that potholes, protrusion, and rutting are the most common distress seen on the surface of forest road pavement. The FRPCI and distress data are all independent variables, and therefore the study on the sensitivity of FRPCI to the distress of road surface also concludes that the influence of the road distress on FRPCI is a function of the selected variable applied on this study. It is also observed that when a single parameter is used (Table 6), about 40% of the road network is in bad condition. This value is increased to 95% when combined parameters are used.

5. Conclusions

The main objective of this study was to calculate FRPCI for forest roads. The FRPCI decision matrix provides specific guidelines for the improvements required for various road classifications. Using the FRPCI can help identify trigger points for preventive maintenance that can stop a road from deteriorating to the point that it needs expensive rehabilitation [21]. The FRPCI identifies roads exhibiting distress at the network level that can help categorize maintenance and rehabilitation requirements for budgeting and planning.
The application of the proposed condition method is a cost-effective and straightforward procedure. Defects are evaluated under objective and efficient techniques that result in reduced survey times and good quality data, as proven during the validation process of the forest roads survey guidelines. In addition, the use of linear equations to estimate the FRPCI simplifies the evaluation process and avoids any misunderstanding while applying the method. The method is flexible and adaptable to different locations. When designing the condition limits for unbound gravel, stabilized gravel, and earth roads, multiple climates were considered. In addition, equations were developed, considering and not considering roughness measures assessed with response-type devices because some agencies lack the resources to survey all forest networks with response-type equipment. Such devices are available in most developed countries but not necessarily in developing countries. The FRPCI equations and condition limits were validated from questionnaires and a field visit, and the method was improved significantly as a result. Final regressions presented high correlation levels, with R2 > 0.70, good overall significance evaluated with an F-test at a 95% confidence level. Because the method is quite complex in that it involves many distresses and damped additivity of their effects, some degree of determinism may be present. For this reason, an attempt to calibrate the model with field experiments may always have poor coherence. However, its logical foundation is solid, and experts must calibrate it. A similar method could be adapted to other forest road conditions with a larger experiment and an expert panel.

Author Contributions

Conceptualization, A.N.; Data curation, M.J.H.; Investigation, A.N. and J.G.B.; Resources, J.G.B.; Software, M.J.H.; Supervision, A.N.; Visualization, J.G.B.; Writing—original draft, A.N.; Writing—review & editing, J.G.B. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Heidari, M.J.; Najafi, A.; Alavi, S. Pavement deterioration modeling for forest roads based on logistic regression and artificial neural networks. Croat. J. For. Eng. J. Theory Appl. For. Eng. 2018, 39, 271–287. [Google Scholar]
  2. Akay, A.E.; Wing, M.G.; Sessions, J. Estimating Sediment Reduction Cost for Low-Volume Forest Roads Using a Lidar-Derived High-Resolution DEM. Balt. J. Road Bridg. Eng. 2014, 9. [Google Scholar] [CrossRef]
  3. Kosztka, M. Maintenance Management System of Forest Roads. In Environmentally Sound Forest Roads and Wood Transport; FAO: Sinaia, Romania, 1996; pp. 101–105. [Google Scholar]
  4. Adlinge, S.; Gupta, A. Pavement Deterioration and its Causes. Int. J. Innov. Res. Dev. 2013, 2, 9–15. [Google Scholar]
  5. Transportation Officials. AASHTO Guide for Design of Pavement Structures; Aashto: Washington, DC, USA, 1993. [Google Scholar]
  6. Elhadidy, A.A.; Elbeltagi, E.E.; Ammar, M.A. Optimum analysis of pavement maintenance using multi-objective genetic algorithms. HBRC J. 2014, 11, 107–113. [Google Scholar] [CrossRef] [Green Version]
  7. McManus, K.J. A policy for sustainability of low volume traffic roads in an Australian context. In Forum on Public Policy: A Journal of the Oxford Round Table; Forum on Public Policy: Urbana, IL, USA, 2008. [Google Scholar]
  8. Shahnazari, H.; Tutunchian, M.A.; Mashayekhi, M.; Amini, A.A. Application of Soft Computing for Prediction of Pavement Condition Index. J. Transp. Eng. 2012, 138, 1495–1506. [Google Scholar] [CrossRef]
  9. Arhin, S.A.; Williams, L.N.; Ribbiso, A.; Anderson, M.F. Predicting Pavement Condition Index Using International Roughness Index in a Dense Urban Area. J. Civ. Eng. Res. 2015, 5, 10–17. [Google Scholar]
  10. Mulry, B.; Jordan, M.; O’Brien, D. Automated Pavement Condition Assessment Using Laser Crack Measurement System (LCMS) on Airfield Pavements in Ireland. In Proceedings of the 9th International Conference on Managing Pavement Assets, Washington, DC, USA, 18–21 May 2015. [Google Scholar]
  11. Peshkin, D.G. Guidelines for the Preservation of High-Traffic-Volume Roadways; Transportation Research Board: Washington, DC, USA, 2011. [Google Scholar]
  12. Obeng, D.A.; Tuffour, Y.A. Prospects of alternative funding sourcing for maintenance of road networks in developing countries. Transp. Res. Interdiscip. Perspect. 2020, 8, 100225. [Google Scholar] [CrossRef]
  13. Eaton, R.A.; Gerard, S.; Dattilo, R.S. A Method for Rating Unsurfaced Roads. North. Eng. 1988, 21, 30. [Google Scholar]
  14. Miller, J.S.; Bellinger, W.Y. Distress Identification Manual for the Long-Term Pavement Performance Program (No. FHWA-RD-03-031); United States. Federal Highway Administration. Office of Infrastructure Research and Development: Washington, DC, USA, 2003. [Google Scholar]
  15. McGarragh, T.G.; Hudson, W.R. A Pavement Design and Management System for Forest Service Road: A Conceptual Study; Council for Advanced Transportation Studies: Singapore, 1974. [Google Scholar]
  16. Giroud, J.P.; Han, J. Design Method for Geogrid-Reinforced Unpaved Roads. II. Calibration and Applications. J. Geotech. Geoenviron. Eng. 2004, 130, 787–797. [Google Scholar] [CrossRef]
  17. Furl, C.; Sharif, H.; Jeong, J. Analysis and simulation of large erosion events at central Texas unit source watersheds. J. Hydrol. 2015, 527, 494–504. [Google Scholar] [CrossRef]
  18. Grace, J.M., III; Clinton, B.D. Protecting Soil and Water in Forest Road Management. Trans. ASABE 2007, 50, 1579–1584. [Google Scholar] [CrossRef] [Green Version]
  19. Wade, C.R.; Bolding, M.C.; Aust, W.M.; Lakel, W.A.; Schilling, E.B. Comparing Sediment Trap Data with the USLE-Forest, RUSLE2, and WEPP-Road Erosion Models for Evaluation of Bladed Skid Trail BMPs. Trans. ASABE 2012, 55, 403–414. [Google Scholar] [CrossRef] [Green Version]
  20. Cao, L.; Zhang, K.; Dai, H.; Liang, Y. Modeling Interrill Erosion on Unpaved Roads in the Loess Plateau of China. L. Degrad. Dev. 2015, 26, 825–832. [Google Scholar] [CrossRef]
  21. Teramoto, Y.; Shimokawa, E.; Ezaki, T.; Chun, K.-W.; Kim, S.-W. Factors controlling sediment production from a yarding road and its temporal pattern in an abandoned clear-cut plantation forest in the Shirasu (pyroclastic flow deposits) area, Kagoshima Prefecture, Japan. For. Sci. Technol. 2015, 11, 54–60. [Google Scholar] [CrossRef]
Figure 1. URCI survey checklist.
Figure 1. URCI survey checklist.
Forests 13 01674 g001
Figure 2. Forest Road with the branch, section, and sample units [1].
Figure 2. Forest Road with the branch, section, and sample units [1].
Forests 13 01674 g002
Figure 3. Location of the study site in the Central Caspian region of northern Iran (a). Study site, including different forest roads composition, including 1 to 3 degrees considered for 200 section, and a total of 3000 sample units considered in the forest (b). Major damages in forest road survey with tree species canopy on road (c).
Figure 3. Location of the study site in the Central Caspian region of northern Iran (a). Study site, including different forest roads composition, including 1 to 3 degrees considered for 200 section, and a total of 3000 sample units considered in the forest (b). Major damages in forest road survey with tree species canopy on road (c).
Forests 13 01674 g003
Figure 4. FRPCI in All Districts of Forest Road Network define sections and FRPCI values.
Figure 4. FRPCI in All Districts of Forest Road Network define sections and FRPCI values.
Forests 13 01674 g004
Table 1. PCI rating.
Table 1. PCI rating.
PCIRating
85–100Excellent
70–85Very good
55–70Good
40–55Fair
25–40Poor
10–25Very poor
00–10Failed
Table 2. Forest Road Pavement Condition Index Calculating.
Table 2. Forest Road Pavement Condition Index Calculating.
RatingFailedPoorFairVery GoodExcellent
FRPCI0–1010.1–4040.1–6565.1–8585.1–100
Factors and Weights
DistressSeverity of Distress
FailedPoorFairGoodExcellent
0–11.1–3.94–6.46.5–8.48.5–10
Pothole (cm)>128–125–83–5<3
Rutting (cm)>1512–15 8–12 5–8 <5
Protrusion(cm)>107–10 5–7 3–5 <3
Ditch ratingNFull Half Full Quarter full Not full
Drainage ratingNFull Half Full Quarter full Not full
Shoulder (m)N0.10.2–0.30.3–0.4>0.4
Trench StatusFallFall into RoadFall into ValleyFall into DitchN
Canopy on Road %>6050–6040–5030–400–30
Rise Fall (m/km)>8050–8020–5010–20<10
Embankment damageVery SevereSevereModerateLowN
Total Weights0–1011–4041–6566–8585–100
Table 3. General information and Pavement Survey Data in section division of study area.
Table 3. General information and Pavement Survey Data in section division of study area.
Name of RoadAleshrood
(50 Sections)
Zengaldareh
(27 Sections)
Sangdarka
(50 Sections)
Angetarood
(40 Sections)
Hamsava
(30 Sections)
Wide (m)5–5.84.3–4.94.2–54–4.54.5–5.5
Shoulder (m)0.3–0.50.4–0.60.2–0.50–0.10.2–0.4
Canopy %0–655–8012–853–745–90
Embankments (m)4:1–1.5:0.23.5:1–0.50:0.13:0.7–2:0.18:1.5–6:19:3.2–2.1:0
MaterialMix–RiverineRiverineRiverine–MixRiverine–Mountain Mix–Mountain
Thickness (cm) 85–20065–16060–13045–10030–120
Rating of DrainagePoor–ExcellentFaire–PoorFaire–GoodFaire–PoorFailed–Good
Length of Road (km)14713118
Embankment
Damage
Poor–ExcellentPoor–FairFailed–PoorFailed–PoorFailed–Good
Trench StatusPoor–ExcellentFailed–GoodPoor–ExcellentFailed–GoodFailed–Poor
Effectiveness of ditch arrangementFailed–GoodFair–PoorPoor–FailedPoor–FailedExcellent–Poor
Rainfall (mm)840–880860–920930–980990–1100810–870
Timber Harvesting (m3)150–2450190–3012125–22655–285045–1006
Management
Experience (month)
2–625–482–554–5310–65
Traffic (MADT)98–82750–51174–76335–74828–508
Pavement Condition Survey
Rutting (cm)2.5–205.5–15.31.4–163–17.20.2–15.1
Pothole (cm)1.6–122.5–131.1–12.82.8–13.41.2–15.5
Protrusion (cm)0.1–9.51.5–11.61.1–122.1–10.60.2–13.5
Rise Fall (m per km)5–963–1026–854–1406–112
Number of units750450750500550
Table 4. Weightings (V and W showed value and weighting of each parameter).
Table 4. Weightings (V and W showed value and weighting of each parameter).
Name of RoadAleshroodZengaldarehSangdarkaAngetaroodHamsava
V *W *VWVWVWVW
Rating of Surface DrainageExcellent-
Poor
10-4Fair-Poor6-4Good-Fair8-6Fair-Poor6-4Good-Failed8-1
Embankment StatusExcellent-
Poor
10-4Fair-Poor6-4Good-Failed8-1Poor-Failed4-1Good-Failed8-1
Effectiveness of ditch
arrangement
Good-Failed8-1Fair-Poor6-4Poor-Failed4-1Poor-Failed4-1Excellent-
Failed
10-1
Rating of
Drainage
Excellent-
Poor
10-4Fair-Poor6-4Good-Fair8-6Fair-Poor6-4Good-Failed8-1
Trench StatusExcellent-
Poor
10-4Good-Failed8-1Excellent-
Poor
10-4Good-Failed8-1Poor-Failed4-1
Pavement Condition Survey
Rutting (cm)2.5–200–95.5–15.30.9–6.71.4–160.1–9.63–17.20–8.60.2–15.10.9–10
Pothole (cm)1.6–121–9.42.5–130.1–91.1–12.80.2–9.62.8–13.40–8.81.2–15.50–9.5
Protrusion (cm)0.1–9.51.3–9.91.5–11.60–9.41.1–120–9.52.1–10.60.4–8.80.2–13.50–10
Rise Fall (m/km)5–961–103–1021–106–851–104–1401–106–1121–10
Shoulder (m)0.3–0.56–100.4–0.68.5–100.2–0.54–100–0.10–40–0.40–8.5
* V and W showed qualitative and quantitative of each parameter.
Table 5. Value of PCI for All of Forest Roads Pavement.
Table 5. Value of PCI for All of Forest Roads Pavement.
Name of RoadAleshroodZengaldarehSangdarkaAngetaroodHamsava
Mean of Parameters and Sum of Them together in Table 2 (Weights)
(FRPCI Value)96.3
33.6
76.9
28.4
86.7
24.2
68.2
12
84
7.8
(URCI Value)4540433540
4.51.61.20.856
(PCI Value)5348503745
158101.29
Final FRPCI64.9552.6555.4540.145.9
Final URCI4533362931
Final PCI3428301927
Table 6. Combined Regression Equation for Five Districts and Total District.
Table 6. Combined Regression Equation for Five Districts and Total District.
Name of RoadEquationCorrelation (R2)
AleshroodY = 0.008X1 + 0.232X2 + 1.2X3 − 0.0195X40.71
ZengaldarehY = 0.2X1 − 1.32X2 + 0.3X3 − 0.0001X40.75
SangdarkaY = 0.45X1 − 2.12X2 + 8.45X3 + 0.049X40.81
AngetaroodY = 0.04X1 − 0.95X2 − 0.07X3 − 0.006X4 + 0.35X50.75
HamsavaY = 0.12X1 − 0.29X2 − 1.65X3 + 0.004X4 + 0.02X50.70
Total of Forest RoadsY = 0.01X1 + 0.3X2 + 0.95X3 − 0.0183X4 + 0.001X50.77
X1 = Rainfall (mm), X2 = Traffic, X3 = Slope, X4 = Volume of timber harvested and X5 = Management experience.
Table 7. Result of Regression Analysis.
Table 7. Result of Regression Analysis.
BranchVariableCoefficientS.E.p-Value
AleshroodIntercept156.1835.180.0561
Rainfall−0.3750.0230.0485
Traffic0.1540.0510.0376
Slope0.7020.8530.0126
Volume of timber harvested0.1690.0700.0102
Management experience75.32125.2390.0766
ZengaldarehIntercept203.0240.1180.0113
Rainfall−0.3260.0270.0520
Traffic0.1090.0630.0104
Slope0.6850.8370.0742
Volume of timber harvested0.2750.0560.0335
Management experience86.23628.3410.0421
SangdarkaIntercept145.1141.2050.0143
Rainfall−0.3080.0280.0426
Traffic0.1880.0500.0312
Slope0.8350.8170.0452
Volume of timber harvested0.1140.0620.0237
Management experience89.14327.6590.0782
AngetaroodIntercept89.2040.0230.0722
Rainfall−0.5360.0180.0447
Traffic0.2810.0550.0542
Slope0.6350.7920.0278
Volume of timber harvested0.2250.0480.0755
Management experience80.65226.3070.0352
HamsavaIntercept279.5447.143<0.0001
Rainfall−0.4960.0120.0333
Traffic0.1610.0440.0206
Slope0.7470.8220.0089
Volume of timber harvested0.1830.0530.0006
Management experience80.65223.2480.0612
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Heidari, M.J.; Najafi, A.; Borges, J.G. Introducing New Index in Forest Roads Pavement Management System. Forests 2022, 13, 1674. https://doi.org/10.3390/f13101674

AMA Style

Heidari MJ, Najafi A, Borges JG. Introducing New Index in Forest Roads Pavement Management System. Forests. 2022; 13(10):1674. https://doi.org/10.3390/f13101674

Chicago/Turabian Style

Heidari, Mohammad Javad, Akbar Najafi, and Jose G. Borges. 2022. "Introducing New Index in Forest Roads Pavement Management System" Forests 13, no. 10: 1674. https://doi.org/10.3390/f13101674

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop