Next Article in Journal
The Role of Renewable Gas Energy Communities in Austria’s Energy Transformation
Previous Article in Journal
Practical Verification of the Approximation Method of the Influence of Guillotine and Laser Cutting and Core Dimensions on Losses and Magnetization of Induction Motor Cores
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Capacity Planning Method for Distributed Photovoltaics Considering the User Grid Connection Locations

1
School of Electrical and Information Engineering, Zhengzhou University, Zhengzhou 450001, China
2
China Southern Power Grid Co., Ltd., UHV Transmission Company Liuzhou Bureau, Liuzhou 545006, China
3
State Grid Henan Electric Power Company, Sanmenxia Power Supply Company, Sanmenxia 472099, China
4
Henan Electric Power Transmission & Transformation Construction Co., Ltd., Zhengzhou 450003, China
5
State Grid Shangshui Power Supply Company, Zhoukou 466100, China
*
Author to whom correspondence should be addressed.
Energies 2025, 18(18), 4865; https://doi.org/10.3390/en18184865
Submission received: 22 July 2025 / Revised: 8 September 2025 / Accepted: 9 September 2025 / Published: 12 September 2025
(This article belongs to the Section A2: Solar Energy and Photovoltaic Systems)

Abstract

To address the conflicts between high-penetration distributed photovoltaics (PV) integration causing voltage limit violations, reverse power flow issues, and the grid connection needs of industrial and commercial users, this paper proposes an optimal capacity planning method for distributed PV considering the user’s grid connection locations. This method effectively increases the acceptance capacity of the distribution transformer network for distributed PV while ensuring the safe and stable operation of the distribution network. First, the source–load uncertainty is considered, and the k-means clustering algorithm is used to select multiple typical daily probability scenarios. Then, the PV optimal connection node range is obtained through a PV site selection and sizing model. For the planning of nodes within the optimal range, an optimal capacity planning model focusing on the economic benefits of users is established. This model aims to optimize the improvement of wheeling cost and maximize the economic benefits of grid-connected users by determining the optimal PV access capacity for each node. Finally, for PV users outside this range, after determining the maximum allowable capacity for each node, the capacity margin and static voltage stability are comprehensively considered to evaluate the network access scheme. Simulation examples are used to verify the effectiveness of the proposed method, and the simulation results show that the proposed method can effectively increase the acceptance capacity of the distribution network for photovoltaic systems. By fully considering the wheeling cost collection strategy, the distributed PV acceptance capacity is increased by 20.14%, while both user benefits and the operational safety and economic performance of the distribution network are significantly improved, ultimately resulting in a 27.77% increase in total revenue.

1. Introduction

With the promotion of the dual carbon strategy, the installed capacity of distributed PV has increased dramatically. This large-scale grid connection has led to a series of issues such as voltage limits and reverse power flow, and existing policies have become increasingly stringent in restricting additional PV capacity. Industrial and commercial users adopting the “self-generation and self-consumption + surplus electricity to the grid” model can achieve considerable benefits, resulting in the widespread grid connection of distributed PV in industrial parks. Research on PV grid connection location selection methods and optimal capacity planning is of great significance in attracting user investment and expanding the grid’s acceptance capacity for PV, while ensuring the safe and stable operation of the power grid.
In the early stage of PV grid connection, when the penetration rate of PV in the distribution network is low, the PV site selection and capacity determination method focuses on the overall grid planning perspective, emphasizing economic factors while considering safety factors to determine the grid connection location and capacity of distributed PV. Reference [1] considers the impact of distributed PV access on the distribution network voltage and applies an improved particle swarm algorithm with parameter self-adaptation strategy for site selection and capacity determination of distributed PV. References [2,3] comprehensively consider the investment cost of distributed PV and the grid’s safe operation indicators, using a multi-objective particle swarm algorithm to obtain the Pareto solution set and then selecting the optimal PV configuration through decision-making measures. Reference [4] uses economic objectives for planning and voltage deviation, voltage fluctuation, and harmonic indices as constraints, employing a multi-population genetic algorithm for planning and solution. Reference [5] first divides the year into multiple scenarios through clustering, then uses an improved particle swarm algorithm to carry out site selection and capacity planning for multiple types of distributed energy sources, aiming to minimize the annual comprehensive cost.
The problems caused by the high penetration of PV grid connection, such as voltage violations and reverse power flow in the distribution network, prompt grid operators to limit the maximum allowable capacity for distributed PV based on the load-carrying capacity of each distribution transformer network [6].Traditional methods [7,8,9] based on capacity-to-load ratio, empirical formula, load adjustment, and rule-based approaches primarily focus on the operational safety of the distribution network, using the total investment and operational costs of distributed PV as the objective function, with voltage deviation, line, and distribution capacity as constraints. These constraints are set too rigidly, leading to overly conservative results for the maximum allowable capacity. Distributed PV capacity planning methods considering source–load uncertainty [10,11], hierarchical multi-objective capacity planning methods for distributed energy systems [12], and maximum capacity planning methods for distributed PV [13] all take the maximum integration capacity of distributed PV as the objective function. The results obtained from these methods, which consider grid security as a constraint, show an improvement over traditional approaches while ensuring safe operation of the distribution network. However, all of these methods focus solely on planning from the grid-wide perspective and fail to comprehensively consider the costs and benefits of PV grid integration from the user’s perspective.
With the decline in PV investment costs and the gradual removal of national PV subsidies, the increasingly competitive PV market requires a more rational user–grid transaction model. Currently, the transaction model has expanded from the simple benchmark feed-in tariff to include two additional modes: direct trading and electricity consignment. Research on the economic efficiency of transaction models has recently promoted the development of optimal PV integration capacity in distribution networks. Reference [14] considers the impact of each PV user on system incremental network losses to establish an annual dynamic wheeling cost, thereby determining the PV integration capacity at each node and the starting point for fee collection. Reference [15] first derives the initial maximum admissible PV capacity based on a full-year temporal assessment, and then establishes a PV plant revenue evaluation model accounting for curtailment, emphasizing economic profitability, to determine the optimal PV capacity that maximizes plant revenue, which exceeds the more conservative maximum admissible capacity. References [16,17] optimize the mechanism based on the wheeling cost, respectively proposing the wheeling cost model considering basic usage charges, congestion, and cross-subsidy costs, and a model accounting for losses of grid franchise rights, using fee variations to guide users in optimizing PV integration, providing an effective approach.
This paper first fully considers the source–load uncertainty and uses the k-means algorithm to cluster the annual light radiance and load data of a certain area, obtaining multiple typical daily scenarios to provide a basis for subsequent distributed PV grid connection capacity planning. Secondly, from a global perspective of power grid planning, a distributed PV site selection and capacity planning model optimizing the annual comprehensive operation cost is established, and the resulting range of connection nodes is used as a reference for subsequent detailed planning schemes. Furthermore, from the perspective of grid-connected users, for industrial and commercial users within the access node range, an optimal capacity planning model emphasizing economic benefits is developed, guided by the improvement of wheeling cost and considering both the costs and benefits of PV integration, with the optimal capacity allocation for each node determined using an improved gray wolf optimization algorithm. For industrial and commercial users outside the access range, the optimal grid connection locations are determined based on a comprehensive index that considers node margins and system voltage stability. This method is applied to an IEEE 33-node simulation, and the simulation results show that the proposed method can increase the distribution network’s acceptance of distributed PV, improve the overall benefits for users and the grid, and effectively promote the transformation of the distribution network into a clean grid.

2. A Method for Constructing Multi-Typical Daily Scenarios Considering Source–Load Uncertainty

Currently, stochastic programming, fuzzy programming, robust optimization, and scenario analysis methods [18,19,20,21] are commonly used to consider the impact of source–load uncertainty on subsequent planning, improving the adaptability and flexibility of the planning and enhancing the system’s ability to handle complex uncertainties. In this context, scenario analysis retains multiple representative scenarios through the steps of scenario generation and reduction. The planning model performs objective function calculations under the conditions of each scenario, and the results are weighted and summed according to the proportion of each scenario. This method fully considers the characteristics of each scenario and has the advantages of clear principles and strong operability. It has been widely used in power system analysis [22]. The k-means algorithm, as an efficient unsupervised machine learning method, is widely used in scenario generation and reduction. Its core function lies in measuring the Euclidean distance between historical data points, automatically classifying them into several clusters, using the centroid of each cluster as a typical scenario and the proportion of original data points within the cluster as the probability of the scenario’s occurrence. Therefore, the k-means algorithm is an effective technique for converting raw uncertain data into the input format required for scenario analysis [23,24].
The real load and light radiance data for a specific region are normalized, and a year-round load level and light radiance dataset is created on a daily basis. The k-means clustering algorithm is used to generate multiple typical daily scenarios. The k-means algorithm is one of the most commonly used methods for unsupervised clustering. Its main feature is that, after specifying k cluster numbers, it continuously optimizes the k cluster centroids during iterations, ultimately achieving the optimal clustering solution. The steps are as follows:
(1)
k samples are randomly selected from the dataset as the initial mean vectors, denoted as uk, which serve as the centroids for the initial clusters;
(2)
Based on the existing mean vectors uk, each sample is assigned to the cluster whose mean vector is closest to it, resulting in the initial clustering, as shown in the following equation:
J = i N k = 1 K r i k x i u k 2
r i j = 1 , x i j 0 , x i j
Equation (1) represents the objective function of the k-means algorithm, which calculates the sum of the Euclidean distances between all data points in the sample and their corresponding cluster mean vectors, with the variable being the cluster membership code rij. When data xi is assigned to cluster j, the value of its cluster code rij is 1, and 0 otherwise. When J reaches its minimum value, the corresponding cluster membership set should partition the data points into the closest clusters;
(3)
The cluster membership codes rik determined by the partitioning result of step (2) are used to update the cluster mean vectors uk, with the goal of minimizing J;
(4)
Repeat steps (2) and (3) until the preset number of iterations is reached or the mean vectors of the clusters no longer change, and then output the clustering results.
In the k-means clustering algorithm, the setting of the number of clusters needs to consider both the characteristics of the original data and the computational cost. The Davies–Bouldin index (DB index) is selected to evaluate clustering quality and compare the performance of different cluster numbers [25]. The DB index, a widely used metric for evaluating clustering quality, quantitatively assesses both the separation between clusters and the compactness within clusters. A lower DB Index value indicates better clustering performance, with optimal clustering structures typically corresponding to DB Index values approaching zero. The formula for the DB index is
D B = 1 k i = 1 , j i k max ( σ i + σ j d ( u i , u j ) )
In the formula, σi is the sum of the average distances from all points in cluster i to the mean vector of that cluster, and d(ui,uj) is the distance between the mean vectors of clusters i and j. The DB index represents the ratio of the intra-cluster distance to the inter-cluster distance, with a smaller DB value indicating better clustering performance.

3. Optimal Planning Method for Distributed PV Grid Integration

Distributed PV planning includes both grid connection location decision-making and optimal capacity planning [26]. First, a site selection and capacity determination model considering source–load uncertainty is constructed to determine the optimal access node range and capacity. For users within the optimal access point range, a distributed PV optimal grid connection capacity planning model is proposed, aiming to maximize user benefits by considering the wheeling cost and achieving the optimal connection capacity. For users at non-optimal access points, a comprehensive index is established, considering the capacity margin of grid nodes and the impact of PV integration on voltage stability, to evaluate the access location and make a connection decision. The overall flowchart of the optimal planning method for distributed PV grid integration is shown in Figure 1.

3.1. A Distributed PV Site Selection and Capacity Planning Model Considering Source–Load Uncertainty

In the previously obtained multiple typical daily scenarios, a distributed PV site selection and capacity planning model is constructed, with the total investment and operational cost across multiple scenarios as the objective function and grid security operation as the constraint. The objective function is
C g r i d = s S p s ( C P V I + C P V O M + C b u y )
In the equation, S represents the set of typical daily scenarios, ps is the proportion of this scenario in all scenarios, CPVI and CPVOM are the investment cost and operation and maintenance cost of distributed PV, and Cbuy is the cost of purchasing electricity from the upper level. The cost calculation formulas are as follows:
C P V I = r ( 1 + r ) n ( 1 + r ) n 1 c i n v _ P V i Ω P V P i , P V
In this equation, r represents the discount rate, n is the service life of the PV equipment, cinv_PV indicates the construction cost per kilowatt of PV equipment, and Pi,PV refers to the PV installation capacity at node i.
C P V O M = c o p e _ P V i Ω P V P i , P V
In this equation, cope_PV represents the operation and maintenance cost per kilowatt of PV equipment.
C b u y = s S p s t Ω S , T c b u y P s b ( t ) , i f ( P s b ( t ) ) 0 0 , f ( P s b ( t ) ) 0
In this equation, Psb(t) represents the inflow power at the interconnection node between the main grid and the distribution network at time t. When its value is negative, it indicates that the distribution network is delivering power back to the main grid, in which case the distribution network’s electricity purchase cost is considered to be 0.
The constraints are as follows:
i i j 2 u i 2 = P i j 2 + Q i j 2 u j = u i 2 ( r i j P i j + x i j Q i j ) + ( r i j 2 + x i j 2 ) i i j 2 P j = ( P i j i i j 2 r i j ) j l P j l Q j = ( Q i j i i j 2 x i j ) j l Q j l
U i min U i U i max
S min , x S x S max , x
i E P P V , i P 0
Equation (8) is an equality constraint that specifies that the relationship between the voltage at each node, branch currents, active power, and reactive power in the system must strictly follow the power flow calculation formula. Equations (9)–(11) are inequality constraints that stipulate that the node voltage and branch power must remain within certain ranges, and the PV capacity involved in grid connection cannot exceed a set capacity limit, which is a proportion of the total load of the distribution network.
The improved particle swarm optimization algorithm, which adaptively adjusts inertia weight and learning factors, is used to optimize the distributed PV site selection and sizing model [27], resulting in the optimal locations and capacities for distributed PV integration in the distribution network.

3.2. Optimal Distributed PV Capacity Planning Model for Distribution Networks Guided by Wheeling Cost

The current wheeling cost policy is based on the difference in transmission and distribution prices between different voltage levels. The wheeling cost is calculated by subtracting the transmission and distribution price of the user’s voltage level from the highest voltage level involved in the power transaction. This policy aims to compensate for the increased costs of the grid when distributed energy is fed back to the upper-level grid, without considering other impacts of distributed energy on grid connection. Relevant improvements have been made to the wheeling cost structure in terms of grid losses and electricity sale rights [14,15,16,17]. This paper considers the impact of distributed PV on grid loss and electricity sale rights loss to improve the wheeling cost and uses its dynamic changes to guide grid-connected users to install PV systems reasonably, with the goal of maximizing user benefits, and constructs an optimal distributed PV capacity planning model for the distribution network.

3.2.1. Objective Function

Considering the PV power generation revenue, investment and operation maintenance costs, and wheeling cost, the objective function of the planning model under multiple scenarios is as follows:
C u s e r = max ( C r e v _ P V C i n v C o p e C int )
In the equation, Cuser represents the total user revenue, Crev_PV represents the distributed PV generation revenue, Cinv represents the distributed PV investment cost, Cope represents the operation and maintenance cost, and Cint represents the wheeling cost.
The revenue from PV power generation is divided into two situations: when the PV output at a certain moment is less than the load at that moment, the revenue is reflected as a reduction in the user’s commercial electricity purchase cost; when the PV output at a certain moment is greater than the load at that moment, the revenue is the sum of the reduced total load expenditure and the revenue from selling electricity to the grid, as follows:
C r e v _ P V = s S p s t Ω S , T c p u r ( t ) i Ω i P s , i , t P V , i f ( P s , i , t P V P s , i , t l o a d ) 0 s S p s t Ω S , T c p u r ( t ) i Ω i P s , i , t l o a d + c P V t Ω S , T i Ω i ( P s , i , t P V P s , i , t l o a d ) , i f ( P s , i , t P V P s , i , t l o a d ) 0
In the equation, Ω S , T represents the set of 24 time periods in a day, cpur(t) is the electricity price for the user to purchase from the grid at time t, Ω i is the set of nodes, P s , i , t P V is the PV output at node i at time t under typical daily scenario s, P s , i , t l o a d is the load at node i at time t under typical daily scenario s, and cPV is the electricity selling price. The PV output is calculated from meteorological data using Formula (24):
P P V = r A η
In the equation, r represents the light radiance, W/m2; light radiance refers to the intensity of light striking a surface, emphasizing the distribution of light power through unit area; A is the area of a single PV panel, m2; η is the photoelectric conversion efficiency of the PV panel.
The PV investment and operation and maintenance costs are as follows. In the equation, for convenience in comparing multiple scenarios on a typical day, the investment cost is converted to a daily cost.
C i n v = r ( 1 + r ) n ( 1 + r ) n 1 c i n v _ P V i Ω P V P i , PV 365 n
C o p e = c o p e _ P V i Ω P V P i , PV 365
The impact of distributed PV systems as a power source integrated into the distribution network on network losses should be considered. In addition, PV participation in grid-connected electricity sales affects the grid’s franchising rights. Based on these two considerations, the design of the wheeling cost is as follows:
C int = C P V l o s s + C m a g
In the equation, CPVloss represents the network loss cost that the PV user needs to share for the distribution network, and Cmag is the cost of loss to the grid’s franchising rights caused by the PV user’s participation in direct electricity sales to the grid.
C P V l o s s = s S p s t Ω S , T i Ω i P s , i , t P V _ g r i d P s , i , t all _ g r i d P s , i , t loss c b u y
In the equation, P s , i , t P V _ g r i d represents the output of the grid-connected distributed PV system, P s , i , t all _ g r i d is the total power supply of the distribution network, P s , i , t loss represents the network loss value, and cbuy is the unit electricity price for the grid purchasing power from the upper level.
C m a g = s S p s t Ω S , T i Ω i ( c s e l l ( t ) c b u y ) P s , i , t P V _ g r i d
In the equation, csell(t) is the time-of-use electricity price the grid charges the user at time t, and Cgreen is the grid’s green certificate revenue. The green certificate revenue Cgreen is composed of the following Equation (20), where P s , i , t l o a d is the total electricity fed into the grid at that moment, and kgreen is the new energy quota coefficient. The new energy quota coefficient refers to the ratio of renewable energy generation to the total power fed into the grid, and the grid can trade any surplus generation exceeding this ratio in the green certificate market to obtain revenue. Therefore, the franchising loss should only include the portion within the new energy quota. The grid network fee cost, after subtracting the green certificate revenue, reflects the space for the grid to offer discounts to the users, thus further reducing the user’s wheeling cost.
C g r e e n = c g r e e n s S p s t Ω S , T ( i Ω i P s , i , t P V _ g r i d k g r e e n i Ω i P s , i , t l o a d )

3.2.2. Constraints

In addition to the flow constraints, branch power constraints, and distribution transformer capacity constraints from the maximum admissible capacity model, the constraints of the optimal capacity planning model include a reverse power flow constraint. This means that the power fed back from the distribution network to the upper-level grid cannot exceed the rated capacity of the transformer at the connection point with the main grid, as shown below:
P i P V _ g r i d P T , i
In the Equation, P a l l P V _ g r i d represents the total installed PV capacity of the distribution network, and PT,E represents the rated capacity of the transformer at the connection point between the distribution network and the upper-level grid.
Under the above constraints, the decision variables of the planning model are the PV capacities installed at each node within the optimal access range. The distributed PV planning scheme is obtained through optimization using the improved GWO algorithm, and the flowchart is shown in Figure 2.

3.3. Grid-Connected Location Decision-Making Methods

For users at non-optimal connection points, the grid provides several selectable grid connection nodes based on the user’s geographical location, without considering the node’s capacity to accommodate PV systems and the impact of PV integration on the distribution network’s voltage. To address this issue, a grid connection location decision-making method that takes into account node capacity margins and voltage stability is proposed.

3.3.1. Model for Calculating the Maximum Access Capacity of Distributed PV at Each Node

To account for the capacity margin at each node, it is necessary to calculate the maximum permissible capacity of distributed PV at each node. The maximum permissible capacity refers to the maximum capacity that can be connected at each node under the constraints of system voltage, network loss, power flow, etc. [13]. The decision variable of the maximum permissible capacity calculation model is the distributed PV capacity connected at each node in the distribution network, and the objective function is the minimization of network loss across multiple scenarios for the entire distribution network:
f i t n e s s = s S p s x = 1 M P x , 1 2 + Q x , 1 2 U x , 1 2 ( R x + j X x )
In addition to the constraints in the previously mentioned site selection and capacity determination model, to prevent the power fed back into the grid by the PV system from exceeding the rated power of the distribution transformer at node i, the connected PV capacity PPV,i must be less than the rated capacity PT,i of the distribution transformer at node i. This adds the constraint on the distribution transformer capacity:
P P V , i P T , i
The improved gray wolf optimization (GWO) algorithm [28] is used for solving the calculation, effectively avoiding the situation of getting stuck in local optima during the computation process, and obtaining the maximum permissible capacity value at each node of the distribution network.

3.3.2. Decision-Making Method for Grid-Connected Location Based on Comprehensive Evaluation Indexes

The static voltage stability (SVS) index is selected to assess the impact of distributed PV integration on the system voltage [29,30].
The radial distribution network branch circuit model is shown in Figure 3:
Assuming that power flows from node i to node j, the voltage relationship between the two nodes is
U ˙ i = U ˙ j + ( R i j + j X i j ) ( P i j j Q i j ) U * j
In the Equation, U ˙ i and U ˙ j represent the voltage phasors at nodes i and j, Rij and Xij are the resistance and reactance between the two nodes, and Pij and Qij are the active and reactive power flowing into node j through the branch ij. When node j connects to distributed PV, the expression for active power Pij is
P i j = P L , j + P C , j P P V , j
In the equation, PL,j represents the load at node j, PC,j is the transmission power flowing from node j to other branches, and PPV,j is the PV output connected to node j.
Expanding Equation (14) and simplifying it to an Equation with U ˙ j as the variable, we obtain
U j 4 + 2 ( P i j R i j + Q i j X i j ) U i 2 U j 2 + ( P i j R i j + Q i j X i j ) 2 + ( P i j X i j + Q i j R i j ) 2 = 0
At this point, determining the stability of the voltage at node j can be transformed into determining whether Uj in Equation (26) has a solution. If no power flow solution exists, it indicates that the node voltage is unstable. Therefore, based on the root discriminant of the equation, the condition for voltage stability is
Δ = 2 ( P i j R i j + Q i j X i j ) U i 2 2 4 [ ( P i j R i j + Q i j X i j ) 2 + ( P i j X i j + Q i j R i j ) 2 ] 0
Simplify to obtain:
S V S j = 4 [ ( P i j X i j Q i j R i j ) 2 + ( P i j R i j + Q i j X i j ) U i 2 ] U i 4 1
Equation (28) is the widely used SVS index for determining the static voltage stability of nodes. If SVSj 1, it indicates that the voltage at node j has a power flow solution and is stable, with a smaller index indicating better stability. When SVSj = 1, the voltage at node j is in a critical stable state, and further increasing the load at the node will lead to voltage instability and eventual collapse. Therefore, the static voltage stability index of the entire distribution network should be the maximum value of the SVSj indices of all nodes.
After considering the impact of distributed PV grid integration on the voltage level of the distribution network, the node capacity margin index Cm(t) for different schemes is calculated using the maximum admissible capacity model as
C m ( t ) = P P V t ( i ) P P V , 0 P P V , max P P V , 0
In the equation, PPVt(i) represents the maximum PV admissible capacity at the connection point i in the grid connection scheme t, PPV,0 represents the PV capacity applied for by the user, and PPV,max represents the maximum value of the maximum PV admissible capacity for all nodes. The larger the Cm(t) index, the greater the capacity margin of the connection point selected in this scheme, allowing for future user connection demands.
Similarly, the static voltage stability index of the distribution network for scheme t, CSVS(t), is given by
C S V S ( t ) = 1 S V S ( t )
Finally, by assigning weights and summing Equations (29) and (30), the comprehensive index for evaluating the grid connection scheme is obtained:
C ( t ) = w 1 C m ( t ) + w 2 C S V S ( t )
In the equation, w1 and w2 represent the weights of the two indices, and it is ensured that the sum of the weights equals 1. The scheme with the largest comprehensive index C(t) among the alternatives is selected as the final grid connection scheme. The flowchart is shown in Figure 4.

4. Validation Case Study

4.1. Clustering Results for Typical Day Multi-Scenarios

This paper conducts case analysis based on the improved IEEE33-node system [16]. The system consists of 32 load nodes, with node 1 being the balance node connected to the upper-level grid. The total system load is 3715 + j2315 kVA. Nodes 8, 11, 16, 22, 25, 27, 30, 31, 32, and 33 are designated as industrial and commercial user nodes with the potential for PV integration, while the remaining nodes are residential user nodes, as shown in Figure 5.
The annual residential load data and industrial and commercial load data from a certain region in China are introduced and normalized to obtain the annual load trend curve for the region, as shown in Figure 6. These data are applied to the IEEE33-node system, and the annual load data for each node are calculated. Additionally, local annual light radiance data are integrated to complete the light radiance input, as shown in Figure 7.
The k-means clustering algorithm is used to cluster the user load and light radiance data multiple times by varying the number of clusters k. The values of k and the corresponding changes in the DB index are shown in Figure 8. According to the definition of the DB index, as the number of clusters increases infinitely, the DB index trend decreases monotonically. Therefore, the upper limit for the number of typical days is set to 30, and the lower limit is set to 2.
As shown in Figure 8, when the number of typical days is 16, the optimal DB index is obtained within the range of [2,30], thus determining the number of scenarios as 16. The final clustering results are presented in Figure 9, Figure 10 and Figure 11.
The 16 typical load scenarios and their corresponding PV output scenarios are shown in Figure 9, Figure 10 and Figure 11. Among them, scenarios 6, 7, and 16 correspond to situations of excess PV supply due to high PV output and low load demand. In these scenarios, the PV power cannot be absorbed in time, which may lead to the distribution network feeding power back to the main grid. Scenarios 5 and 11 represent situations of insufficient PV supply due to low PV output and high load demand. In these cases, there is not enough PV power to supply, requiring power purchase from the main grid, which results in economically inefficient operation of the distribution network. Therefore, if the proportion of PV capacity in the power supply of the grid is either too high or too low, it will have a negative impact. Hence, during PV planning, it is necessary to fully consider the proportion of different scenarios and load demands to achieve a more reasonable planning solution.

4.2. Optimal Grid Connection Capacity Planning Simulation for Distributed PV Systems

Based on the location and sizing model considering the uncertainty of power and load, the locations and capacities for distributed PV integration are shown in Table 1. Most of the distributed PV installations are located at the ends of distribution network feeders, and these nodes have high load demands, which are positively correlated with the planned capacity. The voltage levels at the end nodes of the feeders are generally low, and the integration of distributed PV can improve the voltage levels at these nodes, reducing the voltage deviation between the beginning and end of the lines and decreasing system losses.
For the grid-connected users within the optimal PV access node range obtained from the location and sizing model considering source–load uncertainty, a distributed PV optimal grid connection capacity planning model is used for simulation analysis of the grid connection capacity optimization at each node. The PV-related parameters are shown in Table 2, and the electricity price-related parameters are shown in Table 3.
To verify the effectiveness of the proposed planning method, the PV site selection and sizing model from Section 3.1 is selected as Method 1, and the PV optimal capacity planning model proposed in Section 3.2 is selected as Method 2. The differences in user benefits between the two planning schemes are compared.
The configuration results for the distributed PV systems at each optimal PV access node obtained from the two methods are shown in Table 4.
The correlation coefficients between the installed distributed PV capacity and the load demand at each node for the two methods are calculated and shown in Table 5.
As shown in Table 3 and Table 4, Method 2 proposed in this paper accepts 20.14% more distributed PV systems compared to Method 1, and the correlation between the installed distributed PV capacity and the load demand at each node is also higher than in Method 1. This indicates that the proposed method not only allows the distribution network to accommodate more PV but also provides better planning and layout of PV than traditional site selection and sizing methods.
An analysis of the economic benefits obtained from implementing the two methods is carried out, with the costs and benefits for the PV grid-connected users shown in Table 6. Since Method 1 does not consider the wheeling cost in its optimization planning, the wheeling cost for Method 1 is calculated according to the fixed wheeling cost collection method specified in the document “Notice on Carrying out Pilot Market-oriented Transactions for Distributed Power Generation.”
According to Table 6, it can be observed that with the increased installation of distributed PV capacity in Method 2, both the PV investment cost Cinv and operation and maintenance cost Cope rise by 20.14% compared to Method 1. The increase rate matches the proportion of the additional PV installation, and the daily cost amount is not substantial. The user benefit Crev_PV increases by 25.16%, and the rate of benefit increase is higher than the increase in PV installation, indicating that the additional planning for distributed PV grid connection can still result in positive growth in benefits. Regarding wheeling cost, the wheeling cost collection strategy in Method 2 comprehensively considers grid loss allocation costs and grid operation rights loss costs, so the wheeling cost Cint is 22.19% higher than the fixed wheeling cost. Ultimately, the total benefit Cuser is still 27.77% higher than in Method 1, indicating that the proposed wheeling cost collection strategy can drive users to reasonably plan their distributed PV configuration, resulting in better benefits when more distributed PV are installed compared to the traditional site selection and capacity setting methods.
The total voltage deviation and total network loss of the distribution network in typical daily scenario 1 are selected as the two indicators to analyze the impact of distributed PV grid integration on the distribution network. The comparison of the indicators is shown in Table 7. From Table 7, it can be observed that Method 2, with a larger PV capacity connected to the grid, slightly outperforms Method 1 in terms of improving the system voltage deviation and network loss. Moreover, it is less likely to experience excessive voltage during peak PV generation periods, which effectively ensures the safe operation of the distribution network.

4.3. Distributed Power Grid Connection Selection Simulation

From Table 1, it can be seen that the industrial and commercial user nodes not within the optimal connection node range are 11, 27, 31, 32, and 33. For the grid connection decision regarding these non-optimal connection nodes, the maximum allowable capacity model for distributed PV described in Section 3.3.1 is applied, and the maximum allowable PV capacity for these nodes is obtained, as shown in Table 8.
A user applies to install a 100 kW distributed PV system. After on-site verification, the available connection nodes for the user are 31, 32, and 33. By using the grid connection location decision method based on comprehensive evaluation indicators from Section 3.3.2, the capacity margin index Cm(t) and the static voltage stability index CSVS(t) for the three schemes are calculated, and the comprehensive index values for the three schemes are shown in Table 9.
From Table 8 and Table 9, it can be seen that among the three schemes, the maximum admissible capacity value is at node 32, and the minimum is at node 33. However, because node 33 is closer to the end of the main distribution line, its connection to distributed PV systems can reduce the long-distance transmission of electricity to a greater extent, contributing more to improving voltage stability. Therefore, the static voltage stability index CSVS at node 33 is the highest, and the final comprehensive index is slightly higher than that of node 32. Based on the analysis in Section 3.3.2, it can be concluded that the higher the comprehensive index C(t) for evaluating the grid connection scheme, the better the scheme. Therefore, the power grid selects node 33 as the final connection node for this user.

5. Conclusions

With the gradual rollback of PV preferential policies and improvements in the market trading mechanism, new changes have occurred in the development pattern of distributed PV grid integration. There is an urgent need for reasonable planning of distributed PV grid connection. This paper proposes an optimal grid integration capacity planning method for distributed PV, conducting multi-scenario simulations for typical days after fully considering the uncertainty of load and PV output in the IEEE 33 node system, leading to the following conclusions:
  • The scenario analysis method is used to construct multiple typical daily scenarios based on annual load and sunlight data. K-means clustering is performed, and the DB index is used to select the optimal number of clusters, ultimately obtaining typical daily scenarios that effectively reflect the annual load and sunlight information, fully considering the uncertainty of source and load.
  • After obtaining the optimal PV access node range using the traditional site selection and capacity determination method, for nodes within the optimal PV access range, the primary guidance is to charge users a wheeling cost. A distributed PV optimal capacity planning model, considering the maximization of users’ economic benefits, is adopted to optimize the PV grid connection planning.
  • For users applying for grid connection outside this range, the maximum admissible capacity for each node is first calculated. A comprehensive indicator that considers both node capacity margin and static voltage stability of the distribution network is used to evaluate the grid connection scheme, and the scheme is quantitatively assessed to decide the user’s grid connection plan.
Based on the actual load conditions and local weather data for a certain region in China, multiple typical daily scenarios are set in the modified IEEE33 node system. The PV optimal capacity planning method proposed in this paper is compared with the traditional PV site selection and capacity determination method. The results show that the proposed method can guide users in grid connection under more realistic conditions. Compared to traditional methods, it provides a greater improvement for the PV grid connection scheme in grid planning. With the consideration of the wheeling cost strategies, the method increases the distributed PV acceptance capacity by 20.14%. Additionally, user benefits and the operational safety and economic efficiency of the distribution network are significantly improved, leading to a 27.77% increase in total revenue. This research explores methods for the integration of distributed PV into the distribution grid under the new circumstances.
This study has achieved certain results in the planning of distributed PV access capacity, but there is still room for further research. Future work may explore the coordinated planning of PV-storage systems, the optimized configuration of energy storage under dynamic electricity pricing, and regional adaptive capacity allocation schemes. In terms of algorithms, the performance of intelligent algorithms can be compared with traditional methods to assess their applicability in large-scale scenarios. Furthermore, with the development of the distributed energy market, it is worth researching PV-storage coordinated planning methods under multi-agent game theory in the market environment, to enhance the practical application value of the results.

Author Contributions

Conceptualization, X.C. and Y.L.; Methodology, X.C. and Y.Z.; Software, Y.Y.; Validation, C.L. and X.J.; Formal analysis, J.L., Y.Y., X.J. and Y.L.; Investigation, Y.Z. and P.H.; Resources, Y.Y. and P.H.; Data curation, C.L. and Y.Z.; Writing—original draft, C.L.; Writing—review & editing, J.L.; Supervision, X.C.; Project administration, J.L.; Funding acquisition, J.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

Author Yichen Yao was employed by the China Southern Power Grid Co., Ltd., UHV Transmission Company Liuzhou Bureau. Author Yuan Zhao was employed by the State Grid Henan Electric Power Company, Sanmenxia Power Supply Company. Author Pengwei He was employed by the company Henan Electric Power Transmission & Transformation Construction Co., Ltd. Author Yuhan Li was employed by the State Grid Shangshui Power Supply Company. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Liu, Y. Research on Steady-State Voltage Control Strategy of Distribution Network Based on Distributed PV and Reactive Power Optimal Configuration. Master’s Thesis, Xi’an University of Science and Technology, Xi’an, China, 2020. Available online: https://link.cnki.net/doi/10.27397/d.cnki.gxaku.2020.000554 (accessed on 1 January 2025).
  2. Zhu, X. Analysis of Optimal Site Selection for Distributed PV. Master’s Thesis, Shandong University of Technology, Zibo, China, 2020. Available online: https://link.cnki.net/doi/10.27276/d.cnki.gsdgc.2020.000529 (accessed on 4 December 2024).
  3. Yan, H. Site Capacity of Distribution Network Based on IPSO. Master’s Thesis, Northeast Agricultural University, Harbin, China, 2022. Available online: https://link.cnki.net/doi/10.27010/d.cnki.gdbnu.2022.000829 (accessed on 10 May 2025).
  4. Sheng, W.; Liu, K.; Ma, X.; Li, Y.; Dong, W.; Yang, L. Planning Research of Distributed PV Source Access Distribution Network Based on Multi-Population Genetic Algorithm. Acta Energiae Solaris Sin. 2021, 42, 146–155. [Google Scholar] [CrossRef]
  5. Li, Z.; Chu, Z.; Bai, W. Optimal siting and sizing of distributed generations considering uncertainties and environmental factors. Power Syst. Prot. Control 2017, 45, 34–41. [Google Scholar]
  6. Gawlak, A.; Kornatka, M. The Impact of Photovoltaic Installations on Changes in Voltage Levels in the Low-Voltage Network. Energies 2025, 18, 3072. [Google Scholar] [CrossRef]
  7. Zhu, D.; Zhou, Q.; Wang, C. Research on high-proportion distributed photovoltaic access planning method considering voltage over limit risk. In Proceedings of the 2022 International Conference on Power System and Energy Technology (ICPSET 2022), Guangzhou, China, 12–14 August 2022; p. 012037. [Google Scholar] [CrossRef]
  8. Yu, H.; Li, K.; Guo, X.; Quan, S. Evaluation Method of Distributed Photovoltaic Carrying Capacity in Distribution Network Based on Voltage Sensitivity Ranking. In Proceedings of the 2022 IEEE 5th International Electrical and Energy Conference (CIEEC), Nanjing, China, 27–29 May 2022; pp. 238–243. [Google Scholar] [CrossRef]
  9. Chen, D.; Shi, Y.; Xu, W.; Xiao, Y. Multi-objective optimization method for location and capacity of a distribution network with distributed photovoltaic energy based on an improved FPA algorithm. Power Syst. Prot. Control 2022, 50, 120–125. [Google Scholar] [CrossRef]
  10. Su, X.; Gong, X.; Miao, C.; Wu, H. Optimal Planning Method of Distributed Photovoltaic Access Distribution Network Based on Power Data. In Proceedings of the 2021 6th International Conference on Power and Renewable Energy (ICPRE), Shanghai, China, 17–20 September 2021; pp. 677–683. [Google Scholar] [CrossRef]
  11. Ge, L.; Li, Y.; Yan, J. Adjustable Robust Optimization for Large-Scale Photovoltaics Planning in Smart Distribution Networks. IEEE Trans. Sustain. Comput. 2025, 10, 717–729. [Google Scholar] [CrossRef]
  12. Li, Y.; Gao, B.; Qin, Y.; Chen, N. A hierarchical multi-objective capacity planning method for distributed energy system considering complementary characteristic of solar and wind. Int. J. Electr. PowerEnergy Syst. 2022, 141, 108200. [Google Scholar] [CrossRef]
  13. Wang, Y.; Cheng, J.; Fan, F.; Chen, Z. Maximum PV Access Capacity Planning Method for Rural Power Grid Considering Overload Risk. In Proceedings of the 2019 IEEE 3rd Conference on Energy Internet and Energy System Integration (EI2), Changsha, China, 8–10 November 2019; pp. 387–391. [Google Scholar] [CrossRef]
  14. Liu, W.; Lv, X.; Bai, Y.; Zhang, S. A Coordinated Optimization Method for Distributed PV Grid-connected Capacity Based on Dynamic Over-grid Charges. J. North China Electr. Power Univ. 2024, 1–16. Available online: https://link.cnki.net/urlid/13.1212.tm.20240123.1023.002 (accessed on 2 June 2025).
  15. Li, Z.; Guan, Y.; Zhang, D.; Yu, J. Research on the Photovoltaic Integration Capacity and Optimal Sizing of Distribution Network Nodes Based on Annual Temporal Curves. J. Sol. Energy 2021, 42, 200–208. [Google Scholar] [CrossRef]
  16. Wei, Z.; Niu, W.; Luo, Z. Network Fee Mechanism Design for Distribution Network Based on Multi-stage Investment Planning with Network-Source Cooperation. Autom. Electr. Power Syst. 2023, 48, 194–204. [Google Scholar]
  17. Feng, C.; Zhan, B.; Lin, Z.; Shao, X.; Wen, F. Peer-to-peer transaction model for prosumers considering franchise of distribution company. Electr. Power Autom. Equip. 2023, 43, 158–166. [Google Scholar] [CrossRef]
  18. Lin, B.; Huang, Y.; Yu, D.; Fu, C.; Chen, C. Stochastic Distributionally Robust Optimization Scheduling of High-Proportion New Energy Distribution Network Considering Detailed Modeling of Energy Storage. Processes 2025, 13, 2230. [Google Scholar] [CrossRef]
  19. Wu, R.; Liu, S. Robust Optimization of Active Distribution Networks Considering Source-Side Uncertainty and Load-Side Demand Response. Energies 2025, 18, 3531. [Google Scholar] [CrossRef]
  20. Liang, Z.; Chung, C.; Wang, Q.; Chen, H. Fortifying renewable-dominant hybrid microgrids: A bi-directional converter based interconnection planning approach. Engineering 2025, 51, 130–143. [Google Scholar] [CrossRef]
  21. Wu, S.; Wang, Q.; Chen, Q.; Yu, C. Cyber-physical integrated planning of distribution networks considering spatial-temporal flexible resources. Prot. Control. Mod. Power Syst. 2024, 9, 142–156. [Google Scholar] [CrossRef]
  22. Aghaei, J.; Niknam, T.; Azizipanah-Abarghooee, R.; Arroyo, J.M. Scenario-based dynamic economic emission dispatch considering load and wind power uncertainties. Int. J. Electr. Power Energy Syst. 2013, 47, 351–367. [Google Scholar] [CrossRef]
  23. Wang, W.; Dou, F.; Wang, L.; Xia, K. Scenario analysis of photovoltaic power output based on improved K-means algorithm. In Proceedings of the Ninth International Conference on Mechanical Engineering, Materials, and Automation Technology (MMEAT 2023), Dalian, China, 9–11 June 2023; p. 1280157. [Google Scholar] [CrossRef]
  24. Luo, N.; Gao, H.; Zhang, Y. Research on Optimal Configuration of Distributed Photovoltaic with Typical Day Scene Generation Technology. In Proceedings of the 11th International Conference on Power and Energy Systems (ICPES), Shanghai, China, 18–20 December 2021; pp. 756–760. [Google Scholar] [CrossRef]
  25. Zhang, X.; Kang, L.; Wang, X.; Liu, Y.; Huang, S. Capacity Optimization Configuration of Hybrid Energy Storage Systems for Wind Farms Based on Improved k-means and Two-Stage Decomposition. Energies 2025, 18, 795. [Google Scholar] [CrossRef]
  26. Chen, C.; Peng, W.; Xie, C.; Dong, S.; Hua, Y. Photovoltaic Hosting Capacity Assessment of Distribution Networks Considering Source–Load Uncertainty. Energies 2025, 18, 2134. [Google Scholar] [CrossRef]
  27. Li, J.; Yao, Y.; Qin, J.; Chen, J.; Zhao, Y.; Ren, J.; Li, Z. Research on control strategy of distributed photovoltaic cluster based on improved particle swarm-gray wolf coupling algorithm. Front. Energy Res. 2023, 11, 1292899. [Google Scholar] [CrossRef]
  28. Liu, J.; Wei, X.; Huang, H. An improved grey wolf optimization algorithm and its application in path planning. IEEE Access 2021, 9, 121944–121956. [Google Scholar] [CrossRef]
  29. Wang, Y.; Yu, L.; Zhao, Z.; Wang, H.; Xie, J.; Zhang, L. Uncertainty Characterization Method of Static Voltage Stability Margin in Power Systems with High Percentage of Renewable Energy Based on the Multi-Fidelity Models. Energies 2025, 18, 1614. [Google Scholar] [CrossRef]
  30. Li, S.; Lu, Y.; Ge, Y. Static Voltage Stability Zoning Analysis Based on a Sensitivity Index Reflecting the Influence Degree of Photovoltaic Power Output on Voltage Stability. Energies 2023, 16, 2808. [Google Scholar] [CrossRef]
Figure 1. The optimal planning flowchart for distributed PV grid integration.
Figure 1. The optimal planning flowchart for distributed PV grid integration.
Energies 18 04865 g001
Figure 2. Flowchart of optimal capacity planning for distributed PV.
Figure 2. Flowchart of optimal capacity planning for distributed PV.
Energies 18 04865 g002
Figure 3. Distribution network branch circuit model.
Figure 3. Distribution network branch circuit model.
Energies 18 04865 g003
Figure 4. Flowchart for evaluating distributed PV grid-connected solutions.
Figure 4. Flowchart for evaluating distributed PV grid-connected solutions.
Energies 18 04865 g004
Figure 5. Improved IEEE33 node system diagram.
Figure 5. Improved IEEE33 node system diagram.
Energies 18 04865 g005
Figure 6. Annual Load Trend Curve for the Region: (a) Annual Load Variation Trends for Residential Users in the Study Area; (b) Annual Load Variation Trends for Industrial and Commercial Users in the Study Area.
Figure 6. Annual Load Trend Curve for the Region: (a) Annual Load Variation Trends for Residential Users in the Study Area; (b) Annual Load Variation Trends for Industrial and Commercial Users in the Study Area.
Energies 18 04865 g006
Figure 7. Annual light irradiance in the region.
Figure 7. Annual light irradiance in the region.
Energies 18 04865 g007
Figure 8. Plot of DB indicators against number of individuals.
Figure 8. Plot of DB indicators against number of individuals.
Energies 18 04865 g008
Figure 9. Typical daily scenario for area residential loads.
Figure 9. Typical daily scenario for area residential loads.
Energies 18 04865 g009
Figure 10. Typical daily scenario for regional commercial and industrial loads.
Figure 10. Typical daily scenario for regional commercial and industrial loads.
Energies 18 04865 g010
Figure 11. Typical daily scenario for regional light radiance.
Figure 11. Typical daily scenario for regional light radiance.
Energies 18 04865 g011
Table 1. Initial PV location and capacity planning scheme.
Table 1. Initial PV location and capacity planning scheme.
Node NumberCapacity (kW)
8367.96
16306.43
22418.56
25402.53
30403.45
Table 2. Parameters related to PV.
Table 2. Parameters related to PV.
ParametersValue
Area of a single PV module/m22.41
Peak power/W510
PV conversion efficiency21%
Discount rate0.1
Useful life of PV equipment/year20
Unit distributed PV investment cost/CNY per kilowatt3500
O&M costs per kilowatt of PV equipment/CNY per kilowatt·year48
Table 3. Electricity price-related parameters.
Table 3. Electricity price-related parameters.
Electricity Price/CNY per kWhParameters
Residential CustomerCommercial and Industrial CustomerPower Distribution Network
Peak electricity price0.681.06-
Shoulder electricity price0.40.69-
Off-peak electricity price0.230.35-
Tariffs for electricity price purchased from the main grid--0.44
Generation and sale of electricity trading electricity price--0.35
Table 4. Distributed PV configuration results.
Table 4. Distributed PV configuration results.
NodesMethod 1 Capacity to Be ConstructedMethod 2 Capacity to Be Constructed
8367.96520.26
16306.43149.24
22418.56238.79
25402.53800
30403.45573.02
Total capacity to be constructed/kW1898.932281.31
Table 5. Correlation coefficients between distributed PV allocation results and load demand.
Table 5. Correlation coefficients between distributed PV allocation results and load demand.
MethodCorrelation Coefficient
10.4326
20.8978
Table 6. Distributed PV grid-connected customer economic benefits and costs.
Table 6. Distributed PV grid-connected customer economic benefits and costs.
MethodConverted to Daily Amount/CNY
Crev_PVCinvCopeCintCuser
14295.72106.94249.721519.282419.78
25376.61128.48300.011856.363091.76
Table 7. Comparison of voltage deviation and network loss indicators in the distribution network.
Table 7. Comparison of voltage deviation and network loss indicators in the distribution network.
MethodTotal Voltage Deviation/p.u.Total Network Loss/kW
Before the PV grid connection29.44261082.56
120.51931004.73
219.7807988.40
Table 8. Maximum access capacity of distributed PV at each node.
Table 8. Maximum access capacity of distributed PV at each node.
Node NumberCapacity (kW)
1179.76
2727.23
31251.20
32320.15
33242.45
Table 9. Values of indicators for different programs.
Table 9. Values of indicators for different programs.
Grid Connection Node ProgramCmCSVSC
310.5040.04176290.9582153
320.7340.04176580.9582318
330.4750.04178010.9582322
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Li, J.; Li, C.; Cheng, X.; Yao, Y.; Zhao, Y.; Jian, X.; He, P.; Li, Y. Optimal Capacity Planning Method for Distributed Photovoltaics Considering the User Grid Connection Locations. Energies 2025, 18, 4865. https://doi.org/10.3390/en18184865

AMA Style

Li J, Li C, Cheng X, Yao Y, Zhao Y, Jian X, He P, Li Y. Optimal Capacity Planning Method for Distributed Photovoltaics Considering the User Grid Connection Locations. Energies. 2025; 18(18):4865. https://doi.org/10.3390/en18184865

Chicago/Turabian Style

Li, Jingli, Chenxu Li, Xian Cheng, Yichen Yao, Yuan Zhao, Xiaodong Jian, Pengwei He, and Yuhan Li. 2025. "Optimal Capacity Planning Method for Distributed Photovoltaics Considering the User Grid Connection Locations" Energies 18, no. 18: 4865. https://doi.org/10.3390/en18184865

APA Style

Li, J., Li, C., Cheng, X., Yao, Y., Zhao, Y., Jian, X., He, P., & Li, Y. (2025). Optimal Capacity Planning Method for Distributed Photovoltaics Considering the User Grid Connection Locations. Energies, 18(18), 4865. https://doi.org/10.3390/en18184865

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop