Economical Regulating Strategies Based on Enhanced EVM Model in Electric Substation Construction Projects
Abstract
1. Introduction
2. Principles and Methods
2.1. Unbalanced Bidding
2.2. Target Costing
2.3. Earned Value Management (EVM)
2.3.1. Calculation of Traditional Earned Value Parameters and Evaluation Metrics
- (1)
- Calculation of Traditional Earned Value Parameters
- (2)
- Earned Value Analysis Curve (S-Curve)
2.3.2. Improved Model of Earned Value Method with Quality Indicators
- (1)
- Addition of New Key Variables and Measurements
- (2)
- Measurement of Earned Quality Indicator
- Assigning weights to each subtask: Since quality differs across subtasks, affecting project cost and schedule in various ways, each subtask must be assigned a weight. This weight is determined by a random forest-based weight allocation model in machine learning. The proposed random forest-based machine-learning model for weight allocation effectively mitigates human bias by leveraging historical data patterns and dynamically adapting to diverse project conditions, thereby ensuring more reliable and data-driven weight determination compared to traditional subjective judgment approaches.
- b.
- Assessing quality level of specified subtasks: The quality of each specified subtask is assessed.
- c.
- Calculation of BH: By multiplying the above two factors, the specified project quality level BH is obtained. The actual project quality level (AH) is obtained by applying the same calculation approach based on the actual quality inspection results.
- (3)
- New Deviation Analysis Variables Resulting from Quality Indicators
- (4)
- Evaluation Process of the Improved Earned Value Analysis Method
3. Case Analysis
3.1. Project Overview
3.2. Optimization at the Bidding Decision Stage
3.2.1. Adjusting Project Item Prices Based on Completion Time to Ensure Timely Payments
- (1)
- Present value of payments under standard pricing:
- (2)
- Present value of payments under unbalanced bidding:
3.2.2. Sensitivity Analysis
- (1)
- Single-Factor Sensitivity Analysis
- (2)
- Multi-Factor Sensitivity Analysis (Worst-Case Scenario)
3.3. Optimization at the Construction Preparation Stage
3.3.1. Defining and Decomposing Target Costs
3.3.2. Cost Analysis Results
3.4. Optimization During the Construction Phase
3.4.1. Integration of Progress and Cost Management Using Earned Value Method
3.4.2. Enhanced Earned Value Analysis Incorporating Quality Indicators
4. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Ghiyasi, M.; Rouyendegh, B.D.; Özdemir, Y.S. Local and Global Energy Efficiency Analysis for Energy Production Based on Multi-Plant Generalized Production Technology. IEEE Access 2021, 9, 58208–58215. [Google Scholar] [CrossRef]
- Yang, F.; Kang, J.; Zhao, C.; Tang, Y. Team Performance Analysis of Provincial Electric Power Company Considering Production Cost. Procedia Comput. Sci. 2023, 228, 670–678. [Google Scholar] [CrossRef]
- Li, W.; Zhu, J.; Zhu, Z. The Energy-saving Benefit Evaluation Methods of the Grid Construction Project Based on Life Cycle Cost Theory. Energy Procedia 2012, 17, 227–232. [Google Scholar] [CrossRef]
- Wahyu Hayati, D.; Chen, J.-H.; Chen, Y.-C.; Li, S.; Machsus, M.; Khoiri, M.; Wang, Q.-C.; Wei, H.-H. Smart cost estimation: Empirical case for extra-high voltage transmission towers. Heliyon 2024, 10, e31466. [Google Scholar] [CrossRef] [PubMed]
- He, W.; King, M.; Luo, X.; Dooner, M.; Li, D.; Wang, J. Technologies and economics of electric energy storages in power systems: Review and perspective. Adv. Appl. Energy 2021, 4, 100060. [Google Scholar] [CrossRef]
- Wei, W.; Wu, X.; Li, J.; Jiang, X.; Zhang, P.; Zhou, S.; Zhu, H.; Liu, H.; Chen, H.; Guo, J.; et al. Ultra-high voltage network induced energy cost and carbon emissions. J. Clean. Prod. 2018, 178, 276–292. [Google Scholar] [CrossRef]
- Jin, S.W.; Li, Y.P.; Huang, G.H.; Nie, S. Analyzing the performance of clean development mechanism for electric power systems under uncertain environment. Renew. Energy 2018, 123, 382–397. [Google Scholar] [CrossRef]
- Jasiūnas, J.; Láng-Ritter, I.; Heikkinen, T.; Lund, P.D. Case beyond historical severity: Winds, faults, outages, and costs for electric grid. Appl. Energy 2024, 373, 123884. [Google Scholar] [CrossRef]
- Cattell David, W.; Bowen Paul, A.; Kaka Ammar, P. Proposed Framework for Applying Cumulative Prospect Theory to an Unbalanced Bidding Model. J. Constr. Eng. Manag. 2011, 137, 1052–1059. [Google Scholar] [CrossRef]
- Kádárová, J.; Teplická, K.; Durkáčová, M.; Vida, M. Target Costing Calculation and Economic Gain for Companies. Procedia Econ. Financ. 2015, 23, 1195–1200. [Google Scholar] [CrossRef]
- Moradi, N.; Mousavi, S.M.; Vandani, B. An earned value model with risk analysis for project management under uncertain conditions. J. Intell. Fuzzy Syst. 2017, 32, 97–113. [Google Scholar] [CrossRef]
- Perrier, N.; Benbrahim, S.-E.; Pellerin, R. The core processes of project control: A network analysis. Procedia Comput. Sci. 2018, 138, 697–704. [Google Scholar] [CrossRef]
- Almeida, R.; Abrantes, R.; Romão, M.; Proença, I. The Impact of Uncertainty in the Measurement of Progress in Earned Value Analysis. Procedia Comput. Sci. 2021, 181, 457–467. [Google Scholar] [CrossRef]
- Cattell David, W.; Bowen Paul, A.; Kaka Ammar, P. Review of Unbalanced Bidding Models in Construction. J. Constr. Eng. Manag. 2007, 133, 562–573. [Google Scholar] [CrossRef]
- Sha, Y.; Ma, Q.; Xu, C.; Tan, X.; Yan, J.; Zhang, Y. Research on the balance optimization of investment demand and investment capability of power grid enterprises. Energy Rep. 2023, 9, 943–950. [Google Scholar] [CrossRef]
- Bock, S.; Pütz, M. Implementing Value Engineering based on a multidimensional quality-oriented control calculus within a Target Costing and Target Pricing approach. Int. J. Prod. Econ. 2017, 183, 146–158. [Google Scholar] [CrossRef]
- Eshghi, A.; Mousavi, S.M.; Mohagheghi, V. A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study). Neural Comput. Appl. 2019, 31, 5109–5133. [Google Scholar] [CrossRef]
- Kuchta, D.; Zabor, A. A New Approach to Z-Number Based Earned Value Management. Fuzzy Inf. Eng. 2022, 14, 361–378. [Google Scholar] [CrossRef]
- DL/T 5218-2012; Technical Code for the Design of 220 kV-750 kV Substation. National Energy Administration: Beijing, China, 2012.
- GB 50059-2011; Code for Design of 35kV~110kV Substation. Ministry of Housing and Urban-Rural Development: Beijing, China, 2011.
- Gao, L.; Zhao, Z.-Y.; Li, C. An Investment Decision-Making Approach for Power Grid Projects: A Multi-Objective Optimization Model. Energies 2022, 15, 1112. [Google Scholar] [CrossRef]
- Ding, B.; Li, Z.; Li, Z.; Xue, Y.; Chang, X.; Su, J.; Sun, H. Cooperative Operation for Multiagent Energy Systems Integrated with Wind, Hydrogen, and Buildings: An Asymmetric Nash Bargaining Approach. IEEE Trans. Ind. Inform. 2025, 1–12. [Google Scholar] [CrossRef]
- Zhai, X.; Li, Z.; Li, Z.; Xue, Y.; Chang, X.; Su, J.; Jin, X.; Wang, P.; Sun, H. Risk-averse energy management for integrated electricity and heat systems considering building heating vertical imbalance: An asynchronous decentralized approach. Appl. Energy 2025, 383, 125271. [Google Scholar] [CrossRef]
- Rezaee Jordehi, A.; Mansouri, S.A.; Tostado-Véliz, M.; Iqbal, A.; Marzband, M.; Jurado, F. Industrial energy hubs with electric, thermal and hydrogen demands for resilience enhancement of mobile storage-integrated power systems. Int. J. Hydrogen Energy 2024, 50, 77–91. [Google Scholar] [CrossRef]
Traditional Earned Value Parameters | Calculation Formula | Note | |
---|---|---|---|
Cost Variance (CV) | BCWP − ACWP | (1) | BCWP = Budgeted Cost of Work Performed BCWS = Budgeted Cost of Work Scheduled ACWP = Actual Cost of Work Performed |
Schedule Variance (SV) | BCWP − BCWS | (2) | |
Cost Performance Index (CPI) | BCWP/ACWP | (3) | |
Schedule Performance Index (SPI) | BCWP/BCWS | (4) |
Deviation Analysis Variables | Calculation Formula | |
---|---|---|
(9) | ||
(10) | ||
(11) |
Serial Number | Divisional Project Name | Unbalanced Quotation | Normal Quotation |
---|---|---|---|
1 | Total price contract part | 2,781,476 | 1,926,190 |
1.1 | Measure item | 2,781,476 | 1,926,190 |
2 | Unit contract portion | 14,557,700 | 154,129,092 |
2.1 | Primary and secondary production systems | 9,307,558 | 9,841,365 |
2.1.1 | Master communication building | 386,541 | 528,139 |
2.1.2 | 1# Relay room | 268,350 | 272,836 |
2.1.3 | 2# Relay room | 364,960 | 368,534 |
2.1.4 | Substation electricity and 220 kV switchgear room | 167,292 | 156,548 |
2.1.5 | Fire pump house | 178,397 | 182,722 |
2.1.6 | Main transformer valve room | 116,805 | 113,180 |
2.1.7 | General drawing | 1,937,234 | 2,282,545 |
2.1.8 | Structure, support and equipment foundation | 4,959,086 | 5,065,582 |
2.1.9 | Water and electricity installation | 889,830 | 845,238 |
2.1.10 | HVAC installation | 39,063 | 26,041 |
2.2 | Individual works related to the site | 5,250,141 | 5,573,021 |
2.2.1 | Field leveling and pile foundation works | 5,250,141 | 5,573,021 |
2.2.1.1 | Field leveling | 1,377,503 | 1,033,051 |
2.2.1.2 | Pile foundation engineering | 3,872,639 | 4,538,569 |
Total tender price | 17,339,176 | 17,339,176 |
Single-Factor Changes | PV1 (Normal Bidding) | PV2 (Unbalanced Bidding) | PV Difference (PV2-PV1) | Difference Rate |
---|---|---|---|---|
Baseline (6.56%) | 16,758,096 | 16,785,273 | +27,177 | +0.16% |
Interest Rate Change (5.56%) | 16,821,078 | 16,848,907 | +27,829 | +0.17% |
Interest Rate Change (7.56%) | 16,696,120 | 16,722,563 | +26,443 | +0.15% |
Civil Works Delay (1 Month) | 16,725,504 | 16,752,171 | +26,667 | +0.15% |
Site Leveling −10% | 16,747,927 | 16,773,123 | +25,196 | +0.15% |
Scenario | PV1 (Normal Bidding) | PV2 (Unbalanced Bidding) | PV Difference (PV2-PV1) | Difference Rate |
---|---|---|---|---|
Worst-Case Scenario | 16,680,742 | 16,705,924 | +25,200 | +0.15% |
Construction Costs | Direct Labor Cost | Direct Material Cost | Machinery Operating Cost | Other Direct Cost | Indirect Cost | Total |
---|---|---|---|---|---|---|
Planned expenditure | 319.54 | 1162.54 | 105.58 | 34.85 | 56.02 | 1678.53 |
Planned expenditure | 308.03 | 1165.57 | 105.81 | 33.57 | 44.37 | 1657.35 |
Deviation rate | −3.66% | 0.26% | 0.22% | −3.67% | −20.8% | −1.26% |
Phase | Cumulative Actual Cost (USD) | Cumulative VAT (USD) | Total Actual Investment (USD) | Planned Progress | Actual Progress |
---|---|---|---|---|---|
Phase I | 523,846.5 | 3740.1 | 527,586.6 | 10% | 8% |
Phase II | 1,574,288.8 | 141,292.3 | 1,715,581.2 | 35% | 25% |
Phase III | 6,509,248.3 | 1,026,792.9 | 7,536,041.2 | 70% | 78% |
Phase IV | 8,389,995.0 | 1,026,807.9 | 9,416,802.9 | 90% | 95% |
Phase V | 8,950,607.5 | 1,026,793.0 | 9,977,400.4 | 100% | 100% |
Project Code | Item | Weight | BH | AH |
---|---|---|---|---|
A | Distribution Cabinet Installation | 0.3 | 90 | 92 |
B | Enclosed Bus Installation | 0.2 | 85 | 90 |
C | Cable Tray Installation | 0.05 | 90 | 72 |
D | Cable Laying | 0.1 | 85 | 86 |
E | Conduit Installation | 0.1 | 80 | 67 |
F | Cable Pulling in Conduit | 0.05 | 85 | 82 |
G | Fireproof Seal | 0.05 | 80 | 72 |
H | Lightning and Grounding System | 0.15 | 85 | 83 |
Integral Project | 1 |
Project Code | BCWS | ACWP | BCWP | CV | He | BCWPH | HV | SV’ | HCV |
---|---|---|---|---|---|---|---|---|---|
A | 1,071,588.2 | 514,674.4 | 765,420.2 | 250,745.8 | 1.022222 | 782,429.3 | 17,009.2 | −289,158.9 | −233,736.7 |
B | 714,392.2 | 343,116.2 | 510,280.1 | 167,163.9 | 1.058824 | 540,296.8 | 30,016.7 | −174,095.3 | −137,147.2 |
C | 178,598.0 | 85,779.1 | 127,570.0 | 41,791.0 | 0.8 | 102,056.0 | −25,514.0 | −76,542.0 | −67,305.0 |
D | 357,196.1 | 171,558.1 | 255,140.1 | 83,581.9 | 1.011765 | 258,141.8 | 3001.7 | −99,054.3 | −80,580.2 |
E | 357,196.1 | 171,558.1 | 255,140.1 | 83,581.9 | 0.8375 | 213,679.8 | −41,460.3 | −143,516.3 | −125,042.2 |
F | 178,598.0 | 85,779.1 | 127,570.0 | 41,791.0 | 0.964706 | 123,067.6 | −4502.5 | −55,530.5 | −46,293.4 |
G | 178,598.0 | 85,779.1 | 127,570.0 | 41,791.0 | 0.9 | 114,813.0 | −12,757.0 | −63,785.0 | −54,548.0 |
H | 535,794.1 | 257,337.2 | 382,710.1 | 125,372.9 | 0.976471 | 373,705.3 | −9004.8 | −162,088.8 | −134,377.7 |
Integral project | 3,571,960.8 | 1,715,581.2 | 2,551,400.6 | 835,819.4 | 0.984302 | 2,511,348.7 | −40,051.9 | −1,060,612.1 | −875,871.3 |
Category | Objective | Target Achievement | Remarks |
---|---|---|---|
Overall Quality | Comply with national standards | Achieved | Technical code for the design of 220~750 kV substation (DL/T 5218-2012) Code for design of 35~110 kV substation (GB 50059-2011) |
Schedule Time | Take the time determined by the owner as the baseline | Achieved | |
Cost | Achieve 1–3% cost saving | 1.7% | |
Safety | “Zero accident” construction | Achieved | |
Construction Waste Recycling Rate | ≥80% | 90% | |
Social Responsibility Objectives | Minimize disturbance to residents | Achieved | Noise complies with Environmental Noise Emission Standard for Construction Sites Temporary sheds and power supply comply with fire protection codes, etc. |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Xin, H.; Wan, Z.; Huang, Y.; Zhang, J. Economical Regulating Strategies Based on Enhanced EVM Model in Electric Substation Construction Projects. Energies 2025, 18, 3795. https://doi.org/10.3390/en18143795
Xin H, Wan Z, Huang Y, Zhang J. Economical Regulating Strategies Based on Enhanced EVM Model in Electric Substation Construction Projects. Energies. 2025; 18(14):3795. https://doi.org/10.3390/en18143795
Chicago/Turabian StyleXin, Hongyan, Zhengdong Wan, Yan Huang, and Jinsong Zhang. 2025. "Economical Regulating Strategies Based on Enhanced EVM Model in Electric Substation Construction Projects" Energies 18, no. 14: 3795. https://doi.org/10.3390/en18143795
APA StyleXin, H., Wan, Z., Huang, Y., & Zhang, J. (2025). Economical Regulating Strategies Based on Enhanced EVM Model in Electric Substation Construction Projects. Energies, 18(14), 3795. https://doi.org/10.3390/en18143795