Next Article in Journal
Evaluation of Fast Charging Efficiency under Extreme Temperatures
Previous Article in Journal
Impact of Shear Zone on Rockburst in the Deep Neelum-Jehlum Hydropower Tunnel: A Numerical Modeling Approach
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Case Report

Strengths and Weaknesses of Existing Building Green Retrofits: Case Study of a LEED EBOM Gold Project

1
Metaamo Studio/School of Urban Design, Wuhan University, Wuhan 430072, China
2
School of Engineering and Built Environment, Griffith University, Gold Coast, QLD 4215, Australia
3
Department of Architecture and Civil Engineering, City University of Hong Kong, Hong Kong, China
4
Department of Architecture, National University of Singapore, Singapore 117 566, Singapore
*
Author to whom correspondence should be addressed.
Energies 2018, 11(8), 1936; https://doi.org/10.3390/en11081936
Submission received: 29 June 2018 / Revised: 17 July 2018 / Accepted: 23 July 2018 / Published: 25 July 2018

Abstract

:
This study investigated the process of existing building green retrofits through examining a Leadership in Energy and Environmental Design for Existing Building: Operations and Maintenance (LEED EBOM) Gold project. The project demonstrated a standard green retrofit process for existing buildings, which includes energy auditing, building performance simulation, and measurement and verification. In this project, four energy conservation measures were applied to improve energy performance: light-emitting diode (LED) lighting, window films, green roofs, and chilled water plant upgrading and optimization. The expected energy saving was 30% after the retrofit; while the actual energy saving was 16%. The error of building performance simulation was one of uncertainties in this retrofit project. Occupancy conditions might be the main reason for this uncertainty. Strengths, weaknesses, opportunities and threats were identified and discussed for the green retrofit. The research results could be used to optimize the existing building retrofit process for better energy performance.

1. Introduction

Existing buildings, especially non-residential buildings, contribute to a significant portion of greenhouse gas emissions [1]. There is an urgent call for reducing the environmental impact of existing buildings via retrofitting [2]. It is well known that the majority of existing buildings last for 50–100 years [3] and that retrofitting existing buildings is more resource-efficient and sustainable than building new green constructions [4,5]. Through modifications, demolition and rebuilding could be avoided; consequently, less construction wastes are generated and less material resources are required [6].
Retrofitting was defined as some modification or conversion instead of a complete replacement of an existing process, facility or structure [7]. It might involve additions, deletions, rearrangements or replacements of one or more parts of the facility [8]. The retrofitting of existing buildings usually includes enhancing efficacy of the air-conditioning system [9,10,11], upgrading the lighting system [12,13], implementing lighting controls [14,15], and improving thermal insulation of building envelopes [16] and roof systems [17]. Studies showed that these retrofits could significantly reduce energy consumptions of existing buildings and energy costs while enhance occupants’ comfort [18].
Typically, a retrofit project involves three key steps: energy auditing, building simulation and measurement and verification (M & V). An energy audit is the process of inspecting, surveying and analyzing the current situation of energy uses in a building; it is the first step to identify opportunities to reduce energy uses [19]. It plays a key role in understanding existing building energy uses and proposing cost-effective Energy Conservation Measures (ECMs). ASHRAE [20] recommended three levels of energy auditing: Level 1: “walk-through” which includes a review of utility bills or other operating data and a walk-through of the facility to identify issues related to energy waste or inefficiency; Level 2: “energy survey and analysis” that adds detailed energy calculations and financial analyses of proposed ECMs; and Level 3: “detailed analysis of capital intensive modifications” which focuses on an engineering analysis of the potential capital-intensive projects identified in Level 2.
Identifying ECMs and evaluating their effectiveness are most important in an energy audit project [21]. Krarti [22] categorized common ECMs on the following building elements: building envelopes, electrical systems, HVAC systems, compressed air systems, energy management controls, indoor water management and new technologies. To understand their effectiveness of improving energy performance, building performance simulation is used as an instrument in the retrofitting process [23]. The building simulation can help to predict the peak values and load profiles of heating/cooling loads of buildings which could be used as the basis for the upgrading HVAC equipment, systems, and plants [24]. Furthermore, innovative strategies for energy saving such as reflective roof, daylighting, free-cooling, solar hot-water heating, heat recovery, and thermal storage can be evaluated before implementation [25]. Last but not least, after the retrofit, measurement and verification should take place to verify the effectiveness of the retrofit.
At the same time, the building retrofit or refurbishment faces many challenges and uncertainties, such as climate change, services changes, users’ behavioral changes and technological changes, all of which directly affected the selection of retrofit techniques and hence the success of a retrofit project [26,27]. Other challenges might include financial barriers and long payback periods [28]. One important strategy to reduce the retrofit risks and uncertainties is adopting green building certification [7,29,30]. In recent years, LEED has been emerging as a popular rating system to evaluate the environmental performance of a building and encourage market transformation towards sustainable design [31]. LEED has established a number of programs aiming for different real estate markets, one of which is dedicated to existing building retrofits: LEED EBOM. LEED EBOM defines the green retrofit as “an upgrade at an existing building to improve energy and environmental performance, reduce water use, improve comfort and quality of space in terms of natural lighting, air quality and noise” [32]. Similar to other green rating tools, LEED EBOM covers six aspects (Figure 1). Among all aspects, Energy and Atmosphere is the most important and accounts for the largest portion of points. Table 1 shows the specific credits and points involved in Energy and Atmosphere. More details of this program could be found in the reference guide of LEED EBOM [33].
A number of studies have been conducted to verify the impact of LEED certification on building energy and environmental performance [34,35,36]. These studies showed the benefits of an existing building retrofit and green building certification to building owners, tenants and occupants [37]. The present study, investigating into a LEED EBOM certified project, intends to understand the methodology and process of an existing building green retrofit project. The present study also aims to disclose the strengths and weakness of each retrofitting step and to optimize the retrofit process to increase the effectiveness of retrofitting. Although many studies can be found in the subject of energy retrofit, they mainly used building simulation to verify the ECMs and their related outcomes theoretically. This study, using a real project and a longitudinal investigation through the whole retrofit process, provides first-hand empirical data and facts on each stage of retrofitting. Furthermore, based on the real case, this paper summarizes the methodological strengths and weaknesses of the green retrofit process.

2. Methodology: Case Study

To meet the research objective, this paper investigated a LEED EBOM project which had gone through a rigorous green retrofit process. The data for this paper were collected from the whole retrofitting process. The building selected for this study is the Chow Yei Ching (CYC) Building (Figure 2) which belongs to the University of Hong Kong. The University of Hong Kong sets sustainability goals, one of which is to significantly reduce the energy consumption of existing buildings. The CYC building was selected for an energy efficient retrofit to achieve LEED EBOM Gold certification (Table 2). The CYC building is located on the main campus of the University of Hong Kong. It was built in 1993 and now it is a multi-purpose academic building which comprises offices, lecture rooms and different types of laboratories. It has a total of 13 floors from LG4/F to its highest 8/F. The GFA is around 13,168 m2. Hong Kong is located at latitude 22.2783° N and longitude 114.1747° E. Hong Kong’s climate is sub-tropical. August and September are the hottest months with high humidity, which are the highest energy consumption period due to the need of cooling. The major energy consumers of this building are the air conditioning system, lighting system and office equipment. To conduct the retrofit project, the university employed an energy service company to manage the technical and funding issues. Other parties such as Estate Office, electrical/electronic technicians, and LEED consultants were involved to follow the energy measurements, to supervise the implementation and to ensure the achievement of LEED certification. The CYC project went through a standard retrofit process. A walk-through assessment and an energy survey were conducted in the year of 2011 before the retrofit was implemented. Based on the energy audit, several ECMs were recommended. Building performance simulation was conducted to look at detailed cost-effectiveness of these ECMs. The retrofit period was March 2012 to July 2013. The operation period after the retrofit was August 2013 to August 2014, during which the measurement and verification was conducted.

3. Results

3.1. Energy Audit

The energy audit was conducted to find the current condition of the CYC building. The content of the energy audit is shown in Table 3. Different methods, such as “walk through”, “on-site measurement” and “electricity bill reading”, were used in the energy auditing process, based on which ECMs were recommended for the retrofit.
The energy auditing started from the building envelope. The exterior walls consisted of 150 mm thick concrete blocks with face brick exteriors. The windows consisted of a combination of single pane glass with aluminum frame. Large window areas were found facing north (440 m2) and south (388 m2). The roof construction consisted of 150 mm thick concrete blocks. The total surface area of roof floor was around 1013 m2.
The major part of the energy audit was focused on mechanical and electrical systems, such as chiller plant, AHU, VF, FCU, lighting and lifts. A chiller plant located at the roof floor provided the cooling of the whole building. The chiller plant consisted of four air-cooled 180 tons chillers, four primary chilled water pumps and three secondary chilled water pumps. The chiller plant was installed with Honeywell building management system. It was found that some of the sensors such as temperature sensors and flow sensors were mal-functional. The chiller plant could not be operated fully automatically. Due to the operation requirements in laboratories and facilities such as computer servers, the plant was in 24 h operation to maintain suitable conditions.
Various types of lighting fixtures were installed at CYC. Most of them were T8 tubes with electronic ballasts. All lighting fixtures were controlled by conventional timers according to the pre-set time schedule. A total of four lifts are installed in the CYC building. One of them is a service lift. Power factor is one of the major concerns for good power quality within a building. It affects the demand side management and also the electricity costs. During the site visit, the power quality was in good condition with the power factor at 0.98.
The building was occupied by around 700 staff from 8:30 a.m. to 7:00 p.m. Monday to Friday and 8:30 a.m. to 12:30 p.m. on Saturday. To better understand the IEQ in the CYC Building, the research conducted on-site measurements before the retrofit. The measurement was conducted at different locations covering individual offices, open-plan offices, laboratories, corridors, toilets, and entrances/exits during occupied conditions. For small spaces such as individual offices, the measurement took place nearby the seat positions of the occupants; while for large spaces such as open-plan offices and laboratories, the measurement took place at several different seat positions to cover window, middle and isle seats. In total, 47 points were measured. The measurement was conducted during office hours. Figure 3 shows the measurement results. Compared to the temperature set point which was 24 °C, many spaces were warmer than expected, especially corridors, entrances/exists and some offices on the top floors, while some individual offices and laboratories were colder. The occupancy and floor conditions were the main reason for the temperature variation. Higher occupancy load in open-plan offices and laboratories resulted in higher heat dissipations both from human bodies and equipment. Higher floors, especially the top floors, too, had more heat gains from the roofs. The private offices and lower floors, on the contrary, had less heat gains and consequently lower temperature. The relative humidity and carbon dioxide concentration had similar trend.
The retrofitting project was expected to be conducted during the year 2010 to 2011, so energy consumption data from the closest year 2009 were analyzed. Figure 3 shows the electricity data for the CYC building in the year of 2009. The total electricity use was 3,742,860 kWh at a total cost of HK$4,695,048 (with the charge at HK$1.254 per kWh). Table 4 breaks down the energy use. The air-conditioning system took up more than 40% of the building energy use. Lighting accounted for 16% and lifts consumed 10%.
Based on the energy auditing and diagnostics of the CYC building, four ECMs were selected to reduce its energy consumption.
  • Lighting Retrofit: Currently in the CYC Building, 90% of the general lighting fixtures used fluorescent tubes. LED, a semiconductor light source, is considered as the ultimate general lighting solution due to a low power consumption, high efficiency and long life span.
  • Green Roofs: The poor thermal insulation of the roofs which was flat with 150 mm concrete blocks caused solar heat gains in offices at top floors. It was suggested to build a green roof at the flat roof area.
  • Window Film Coating: The SHGC for windows was approximately 0.82. The large value of coefficient resulted in large amount of heat transfer. It was proposed to coat windows with 3MTM Night Vision window films that allow 35% daylight in (3M NV 35). The total area of the window film coating was approximately 843 m2.
  • Updating Chiller Plant and Building Management System Installation: The existing chiller plant was low efficiency with COP at 2.6 (0.7 kW/ton); for a well-designed all variable speed plant, the COP should be above 5.0 (i.e., 1.35 kW/ton). A new plant was to be built the replace the old one.

3.2. Building Performance Simulation

In order to determine the benefits of proposed ECMs to the CYC building, building energy simulation was conducted using EnergyPlus. In the project, the latest Version of Energy Plus v8.1/8.0 was employed. This version was authorized by U.S. Department of Energy and Building Technologies Program. In this research, the building information model was created in DesignBuilder and then exported into EnergyPlus for energy simulation. The simulation process is shown in Figure 4.
In the simulation model, the thermal zone was defined according to the partitions of the space and the function of the space. The major thermal zones in each floor of CYC were identified as office, laboratory, service room, bathroom, lobby and corridor, AHU and lecture room. For each thermal zone of the floor, the total number of lighting fixtures and occupants were counted based on the energy audit result. The power densities of equipment and lighting were calculated according to the ASHRAE Standard. Table 5 summarizes the building information settings using ASHRAE 90.1 as a baseline [38]. Other building information such as occupant schedule, lighting schedule and equipment schedule were collected through the energy audit process as discussed before.
Validation was conducted to verify the simulation by comparing the simulation results with the actual energy use in 2009. Validation is an essential task to ensure that building systems are properly modeled and integrated for the purpose of simulating the building energy consumption [39]. Table 6 shows the simulated energy use data compared with the actual data of 2009.
The error of the total yearly energy consumption between simulated results and the actual data was 2.8%. The measured monthly energy consumption was within 15% of the simulated monthly energy consumption. This demonstrates that the predictions were in good agreement with the actual energy consumption data of the CYC Building. Thus this modeling and simulation technique can be used for the evaluation of different energy conservation retrofits and their energy performance analysis. This error should be also considered in the measurement and verification process.
There are four ECMs applied to the CYC project: lighting system retrofit; window film; green roof; and chilled plant and related building management system upgrading. To evaluate and analyze the result of each retrofit, the research compared the existing building’s energy consumption with each retrofit respectively while the other four aspects keeping the same. At last, the research also compared the existing building’s energy consumption with the one after all four retrofits applied in order to study the integrated effect.
  • Lighting System Retrofits
LEDs with 35W power were to be installed in the CYC Building to replace the original T8 lightings. The lighting power density before and after the Lighting retrofit were calculated in Table 7. Figure 5 compares the simulation result of the annual energy consumption breakdown by LED energy efficient lamps with the base model. From the simulation result, it can be seen that after the lighting system retrofit, the cooling consumption and the interior lighting consumption were reduced by 16% and 44%, respectively.
  • Window Film
In the CYC Building, some windows were to be coated with the 3M NV 35. The specifications of the original glazing and window film coated glazing are shown in Table 8. From the simulation results as shown in Figure 6, it can be seen that after the window film coating, the cooling consumption and the fans energy consumption were reduced by 6% and 6.5%, respectively.
  • Green Roof
In the CYC Building, an intensive green roof system was designed to reduce solar radiation on the original flat concrete roof. Table 9 shows the specification of the green roof system. From the simulation results as shown in Figure 7, it can be seen that after greening the roof, the annual energy consumption was not reduced obviously. It might because the area of the green roof was too small (only 100 m2) and it did not have much influence on the whole building’s energy consumption.
  • Chiller Plant Upgrading
The COP of chiller plant was to be updated from 2.6 to 5.0 by the plant replacement. Table 10 compares the monthly electricity consumption due to this upgrade. As shown in Figure 8, chiller plant updating can reduce a significant portion of cooling load in summer, especially in June, July, August, September and October. The cooling energy consumption was reduced by 27.4%.
  • Combined Energy Conservation Measures
From the simulation results (Figure 9), it can be seen that after combining the four measures, the cooling consumption and the interior lighting consumption were reduced by respectively 42% and 45%. The total energy saving was 1,256,259 kWh per year which could be translated to a reduction of 853 tons of CO2 emission per year.

3.3. Measurement and Verification

The determination of energy savings requires both accurate measurement and replicable methodology, known as a measurement and verification protocol. Based on the M & V protocol [40], this project measured and verified the effectiveness of isolated retrofit strategy as well as energy use of the whole retrofitted building.
The M & V of the lighting retrofit was conducted before and after the retrofit. The M & V chose three areas to do the comparison study before and after the retrofit: study area, rest area and kitchen area. The three areas were measured several times before and after retrofits under artificial illumination only. A CHROMA Meter CL-200 (Konica Minolta Sensing Americas, Ramsey, Inc., NJ, USA) was used to measure illuminance levels. The result is disclosed in Figure 10. After the retrofit, the illuminance was increased at the same place. The M & V also tested 30 T8 tubes (the main lighting sources before the retrofit) and 30 LED tubes (the main lighting sources after the retrofit). The average wattage of LED tubes was 35 W and that of T8 tubes was about 67 W, which means that LED saved more electricity to achieve the same illuminance level.
Most windows were tinted with films to reduce solar heat gains; however, while some of windows were kept unchanged for comparison. M & V was conducted to compare transmission properties of windows with and without films. This measurement was conducted on 21 October 2012 during 12:00–13:00 p.m. The windows on each façade north, south, east and west were selected to conduct the measurement. A Solar Transmission & BTU Power Meter (EDTM SP2065, EDTM, Inc., Toledo, OH, USA) was used to measure the two types of windows on each façade. Figure 11 shows the comparative study; it indicates that the windows with films significantly reduced the solar heat gains.
The retrofitting was completed in 2012. Energy use data for the year 2014 were collected. Through the comparison of the actual energy use data before and after the retrofit, the energy savings could be verified. Figure 12 compares the monthly electricity bill of the year 2009 and that of the year 2014 as well as the simulation result. It is observed that the energy use after the retrofit was reduced from 2009 to 2014. However, the reduction was not that significant as the simulation predicted. Figure 13 further summarizes the three results and found that the simulation expected 30% energy saving while the actual energy saving was 16%. There was still 14% gap between the real energy reduction and the simulated reduction. The simulation validation study mentioned in Section 3.2 showed that there was some error (15%) in the simulation result, which might explain the performance gap. Kaplan and Canner [41] suggested the difference between the predicted energy consumption by simulation and the actual energy consumption data fall into the range of 10% to 25%. Xu et al. [42] suggested that the acceptable error for building simulation model when using ASHRAE standard should be within 5% for monthly energy data.

4. Discussion

From this case study, the strengths and weaknesses of the key stages of the retrofit project can be summarized as in Table 11. Energy auditing is the foremost part of a retrofit process to identify the ECMs. It is based on direct evidence: visual inspections and direct utility costs. However, it does not tell the effectiveness of the ECMs. Therefore, it should be followed by the next stage: building performance simulation to analyze and compare the ECMs. The concern is that the energy audit is confined to budget and manpower and the selection of ECMs consequently may miss some opportunities. For example, in this project, due to the budget and manpower limitations, only four ECMs were selected. To better identify ECMs, a stakeholder approach is recommended to reduce the risks of missing opportunities. The stage of building performance simulation is instrumental in analyzing and comparing the selected ECMs; based on the analysis, the effectiveness and outcome of ECMs can be estimated. However, the building simulation has a large variety of parameters and complexity of factors such as non-linearity, discreteness, and uncertainty. In this study, it is found that the building simulation overestimated the energy savings through the ECMs. The main reason for this overestimation is occupancy condition. In simulation, the assumed occupancy hours are 9am-5pm; while in reality, overtime working is normal in both academic offices and laboratories. This accounted for the overestimation of energy reduction. It is almost impossible to precisely predict the real occupancy condition. Therefore, the energy simulation for retrofitting should be flexible to accommodate this unpredictability. Furthermore, although the building simulation can provide results corresponding to what the user inputs, they cannot provide suggestions to improve design [24]. Finally, the measurement and verification stage verifies the effectiveness and outcomes predicted by the building simulation. It can compare the physical environments and utility costs before and after the retrofit. The concern is that there are many factors (including occupancy condition change) contributing to the variation of the before- and after- performances. Therefore, to find out the reasons for the success or failure, the non-building factors should be controlled.
The rigorous process demonstrated typical energy efficiency practice on commissioning analysis and implementation, which helped this project achieve the LEED EBOM Gold certification. The four ECMs, too, helped to reduce the energy uses to achieve the credits in “Optimize Energy Performance”. However, the four ECMs were confined to active strategies (mainly mechanical systems) while there were no significant passive strategies such as natural ventilation and daylighting which could significantly reduce energy demanding, which handicapped this project for further achievement towards a higher certification level such as Platinum.

5. Conclusions

This research described the detailed process of the retrofitting and energy conservation measurements of a LEED EBOM project. Through this project, a systematic method of energy efficient retrofits for existing buildings can be concluded and applied to other projects. This case study demonstrated that the energy audit and analysis process provided detailed information to choose the optimized energy conservation measures for existing buildings. Energy conservation measures were proposed on lighting, chiller plant, windows and green roof. The building computer simulation evaluated the energy saving for each energy conservation measure. Specifically, the lighting retrofit was expected to achieve 21% energy saving; the chiller plant COP increase from 2.6 to 5 was expected to reduce 7% of the total energy use; window film coating was expected to reduce 3% of the energy consumption; while a green roof with little area had no significant influence on the energy consumption. After the retrofit, the measurement and verification process was conducted to verify the outcome. As a result, in the year after the retrofit, the CYC building energy consumption has reduced by 16% which is an obvious success to reduce the energy use. However, there is still 14% gap. The gap was similar to the error of 15% found in the simulation calibration using electricity bills. Occupancy condition such as overtime working has been found as the main reason for the gap [43,44].
Although the project successfully reduced the energy consumption by 16% through the green retrofitting, it was scope for even more energy efficiency compared to the green building standard. There are more opportunities for this building to push its energy performance. Particularly, most retrofit measures proposed in this project were active design strategies focusing on building services or fixed envelope components; passive measures, such as natural ventilation and daylighting which could be more effective in reducing energy consumption were not considered in this project, [45]. Of course, these strategies might have limited application in high-rise high-dense urban environments with hot humid climates. Further studies are needed to look at more radical retrofitting measures to significantly reduce building energy consumptions in a cost-effective way.

Author Contributions

X.S. and Z.G. conceived and designed the experiments, performed the experiments. X.S. and Z.G. drafted the paper. Y.L. and Y.T. reviewed the research and provided useful comments.

Funding

This research received no external funding.

Acknowledgments

The authors are indebted to the generous support from Siemens Limited Hong Kong (SLHK) for helping data collection. Many thanks are also due to University of Hong Kong Estate Office. There is no conflict of interest from authors. The authors did not receive any funding to report this project.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

AHUAir Handling Unit
ASHRAEAmerican Society of Heating, Refrigerating and Air-Conditioning Engineers
BMSBuilding Management System
COPCoefficient of Performance
EBOMExisting Buildings: Operations & Maintenance
ECMsEnergy Conservation Measures
FCUFan Coil Unit
GFAGross Floor Area
HVACHeating, Ventilation and Air-Conditioning
IEQIndoor Environment Quality
kWhKilowatt Hours
LEEDLeadership in Energy and Environmental Design
LEDLight Emitting Diode
LPDLighting Power Density
M & VMeasurement & Verification
PAUPre-cooling Air Unit
SHGCSolar Heat Gain Coefficient
VFVentilation Fans

References

  1. EIA. International Energy Outlook 2017; U.S. Energy Information Administration: Washington, DC, USA, 2017. [Google Scholar]
  2. Navid, G.; Folke, B. Sustainable refurbishment in building technology. Smart Sustain. Built Environ. 2012, 1, 241–252. [Google Scholar]
  3. Cha Hee, S.; Kim Ki, H.; Kim Chan, K. Case study on selective demolition method for refurbishing deteriorated residential apartments. J. Constr. Eng. Manag. 2012, 138, 294–303. [Google Scholar] [CrossRef]
  4. Peter, L.; Peter Arthur, B. Toward the sustainable adaptation of existing facilities. Facilities 2009, 27, 357–367. [Google Scholar]
  5. Evonne, M.; Laurie, B. Retrofitting commercial office buildings for sustainability: Tenants’ perspectives. J. Prop. Invest. Financ. 2008, 26, 552–561. [Google Scholar]
  6. Asadi, E.; da Silva, M.G.; Antunes, C.H.; Dias, L. Multi-objective optimization for building retrofit strategies: A model and an application. Energy Build. 2012, 44, 81–87. [Google Scholar] [CrossRef]
  7. Jagarajan, R.; Abdullah Mohd Asmoni, M.N.; Mohammed, A.H.; Jaafar, M.N.; Lee Yim Mei, J.; Baba, M. Green retrofitting—A review of current status, implementations and challenges. Renew. Sustain. Energy Rev. 2017, 67, 1360–1368. [Google Scholar] [CrossRef]
  8. Gou, Z. Green building for office interiors: Challenges and opportunities. Facilities 2016, 34, 614–629. [Google Scholar] [CrossRef]
  9. Vakiloroaya, V.; Samali, B.; Fakhar, A.; Pishghadam, K. A review of different strategies for HVAC energy saving. Energy Convers. Manag. 2013, 77, 738–754. [Google Scholar] [CrossRef]
  10. Minh Thu, H.T.; Sato, H. Proposal of an eco-friendly high-performance air-conditioning system. Part 1. Possibility of improving existing air-conditioning system by an evapo-transpiration condenser. Int. J. Refrig. 2013, 36, 1589–1595. [Google Scholar] [CrossRef]
  11. Ma, G.; Zhou, F.; Liu, T.; Wang, L.; Liu, Z. Energy-saving evaluation of a thermosyphon heat recovery unit for an air-conditioning system. Heat Transf. Asian Res. 2013, 42, 377–388. [Google Scholar] [CrossRef]
  12. Benya, J. Lighting Retrofit and Relighting: A Guide to Green Lighting Solutions; Wiley: Hoboken, NJ, USA, 2011. [Google Scholar]
  13. Nan Chen, H.S.-H.; Chung, H.S.-H. A driving technology for retrofit led lamp for fluorescent lighting fixtures with electronic ballasts. IEEE Trans. Power Electron. 2011, 26, 588–601. [Google Scholar] [CrossRef]
  14. Poland, E.C. Advanced lighting controls: A new frontier in building management systems. ASHRAE Trans. 2014, 120, 1. [Google Scholar]
  15. Ye, X.; Xia, X.; Zhang, L.; Zhu, B. Optimal maintenance planning for sustainable energy efficiency lighting retrofit projects by a control system approach. Control Eng. Pract. 2015, 37, 1–10. [Google Scholar] [CrossRef] [Green Version]
  16. Cetiner, I.; Özkan, E. An approach for the evaluation of energy and cost efficiency of glass façades. Energy Build. 2005, 37, 673–684. [Google Scholar] [CrossRef]
  17. Al-Sallal, K.A. Comparison between polystyrene and fiberglass roof insulation in warm and cold climates. Renew. Energy 2003, 28, 603–611. [Google Scholar] [CrossRef]
  18. Perino, M.; Quenard, D.; Wakili, K.G. Building retrofit: Energy conservation, comfort and sustainability. Energy Build. 2017, 152, 40. [Google Scholar] [CrossRef]
  19. Ma, Z.; Cooper, P.; Daly, D.; Ledo, L. Existing building retrofits: Methodology and state-of-the-art. Energy Build. 2012, 55, 889–902. [Google Scholar] [CrossRef]
  20. ASHRAE. ANSI/ASHRAE/IES Standard 100-2015: Energy Efficiency in Existing Buildings; American Society of Heating, Refrigerating and Air-Conditioning Engineers: Atlanta, GA, USA, 2015. [Google Scholar]
  21. Alajmi, A. Energy audit of an educational building in a hot summer climate. Energy Build. 2012, 47, 122–130. [Google Scholar] [CrossRef]
  22. Krarti, M. Energy Audit of Building Systems: An Engineering Approach; CRC Press: Boca Raton, FL, USA; London, UK; New York, NY, USA, 2011. [Google Scholar]
  23. Khoshbakht, M.; Gou, Z.; Dupre, K. Cost-benefit prediction of green buildings: SWOT analysis of research methods and recent applications. Procedia Eng. 2017, 180, 167–178. [Google Scholar] [CrossRef]
  24. Hong, T.; Chou, S.K.; Bong, T.Y. Building simulation: An overview of developments and information sources. Build. Environ. 2000, 35, 347–361. [Google Scholar] [CrossRef]
  25. Xie, X.; Gou, Z. Building performance simulation as an early intervention or late verification in architectural design: Same performance outcome but different design solutions. J. Green Build. 2017, 12, 45–61. [Google Scholar] [CrossRef]
  26. Flourentzou, F.; Roulet, C.A. Elaboration of retrofit scenarios. Energy Build. 2002, 34, 185–192. [Google Scholar] [CrossRef]
  27. McArthur, J.J.; Jofeh, C.G.H. Portfolio retrofit evaluation: A methodology for optimizing a large number of building retrofits to achieve triple-bottom-line objectives. Sustain. Cities Soc. 2016, 27, 263–274. [Google Scholar] [CrossRef]
  28. Tobias, L.; Vavaroutsos, G. Retrofitting Office Buildings to Be Green and Energy-Efficient: Optimizing Building Performance, Tenant Satisfaction, and Financial Return; Urban Land Institute (ULI): Washington, DC, USA, 2009. [Google Scholar]
  29. Gou, Z.; Lau, S.S.-Y. Contextualizing green building rating systems: Case study of Hong Kong. Habitat Int. 2014, 44, 282–289. [Google Scholar] [CrossRef]
  30. Jin, X.; Meng, C.; Wang, Q.; Wei, J.; Zhang, L. A study of the green retrofit industry chain. Sustain. Cities Soc. 2014, 13, 143–147. [Google Scholar] [CrossRef]
  31. Gou, Z.; Xie, X. Evolving green building: Triple bottom line or regenerative design? J. Clean. Prod. 2017, 153, 600–607. [Google Scholar] [CrossRef]
  32. USGBC. LEED for Existing Buildings: Operations & Maintenance Recertification Guidance; U.S. Green Building Council: Washington, DC, USA, 2009. [Google Scholar]
  33. USGBC. LEED Core Concepts Guide; U.S. Green Building Council: Washington, DC, USA, 2014. [Google Scholar]
  34. Rastogi, A.; Choi, J.-K.; Hong, T.; Lee, M. Impact of different LEED versions for green building certification and energy efficiency rating system: A multifamily midrise case study. Appl. Energy 2017, 205, 732–740. [Google Scholar] [CrossRef]
  35. Scofield, J.H. Efficacy of LEED-certification in reducing energy consumption and greenhouse gas emission for large New York City office buildings. Energy Build. 2013, 67, 517–524. [Google Scholar] [CrossRef]
  36. Heidarinejad, M.; Dahlhausen, M.; McMahon, S.; Pyke, C.; Srebric, J. Cluster analysis of simulated energy use for LEED certified U.S. Office buildings. Energy Build. 2014, 85, 86–97. [Google Scholar] [CrossRef]
  37. Michael, M.; Zhang, L.; Xia, X. An optimal model for a building retrofit with LEED standard as reference protocol. Energy Build. 2017, 139, 22–30. [Google Scholar] [CrossRef]
  38. ASHRAE. ANSI/ASHRAE/IES Standard 90.1-2016—Energy Standard for Buildings except Low-Rise Residential Buildings; American Society of Heating, Refrigerating and Air-Conditioning Engineers: Atlanta, GA, USA, 2007. [Google Scholar]
  39. Higgins, J.A. M&V modeling. (Column: Energy modeling). ASHRAE J. 2013, 55, 88. [Google Scholar]
  40. IPMVP. International Performance Measurement & Verification Protocol: Concepts and Options for Determining Energy and Water Savings; International Performance Measurement & Verification Protocol Committee: Oak Ridge, TN, USA, 2002. [Google Scholar]
  41. Kaplan, M.; Caner, P. Guidelines for Energy Simulation of Commercial Buildings: Final; Bonneville Power Administration: Portland, OR, USA, 1992. [Google Scholar]
  42. Xu, P.; Shen, Y.; Hua, J. Effectiveness of Energy Retrofit Methods in Public Buildings in China; Johnson Controls, Inc.: Washington, DC, USA, 2012. [Google Scholar]
  43. Newsham, G.R.; Mancini, S.; Birt, B.J. Do LEED-certified buildings save energy? Yes, but…. Energy Build. 2009, 41, 897–905. [Google Scholar] [CrossRef] [Green Version]
  44. Scofield, J.H. Do LEED-certified buildings save energy? Not really…. Energy Build. 2009, 41, 1386–1390. [Google Scholar] [CrossRef]
  45. Gou, Z.; Gamage, W.; Lau, S.; Lau, S. An investigation of thermal comfort and adaptive behaviors in naturally ventilated residential buildings in tropical climates: A pilot study. Buildings 2018, 8, 5. [Google Scholar] [CrossRef]
Figure 1. LEED EBOM aspects (Data Source: USGBC 2014).
Figure 1. LEED EBOM aspects (Data Source: USGBC 2014).
Energies 11 01936 g001
Figure 2. The CYC building: north façades (left) and south façades (right) (Photo by authors).
Figure 2. The CYC building: north façades (left) and south façades (right) (Photo by authors).
Energies 11 01936 g002
Figure 3. Indoor environment quality of the CYC building. (a) Temperature; (b) Carbon Dioxide and Relative Humidity.
Figure 3. Indoor environment quality of the CYC building. (a) Temperature; (b) Carbon Dioxide and Relative Humidity.
Energies 11 01936 g003
Figure 4. Simulation process.
Figure 4. Simulation process.
Energies 11 01936 g004
Figure 5. Annual energy consumption before and after the lighting retrofit.
Figure 5. Annual energy consumption before and after the lighting retrofit.
Energies 11 01936 g005
Figure 6. Annual energy consumptions before and after the windows coating.
Figure 6. Annual energy consumptions before and after the windows coating.
Energies 11 01936 g006
Figure 7. Annual energy consumption before and after the roof retrofit.
Figure 7. Annual energy consumption before and after the roof retrofit.
Energies 11 01936 g007
Figure 8. Annual energy consumption before and after the chiller plant upgrading.
Figure 8. Annual energy consumption before and after the chiller plant upgrading.
Energies 11 01936 g008
Figure 9. Annual energy consumption before and after the combined retrofits.
Figure 9. Annual energy consumption before and after the combined retrofits.
Energies 11 01936 g009
Figure 10. Lighting before and after the retrofit.
Figure 10. Lighting before and after the retrofit.
Energies 11 01936 g010
Figure 11. Solar transmission comparisons between windows with and without films.
Figure 11. Solar transmission comparisons between windows with and without films.
Energies 11 01936 g011
Figure 12. Monthly electricity use in the year 2009, 2014 and the simulation result.
Figure 12. Monthly electricity use in the year 2009, 2014 and the simulation result.
Energies 11 01936 g012
Figure 13. Total electricity use in the year 2009, 2014 and the simulation result.
Figure 13. Total electricity use in the year 2009, 2014 and the simulation result.
Energies 11 01936 g013
Table 1. Credits and Points of Energy and Atmosphere in LEED EBOM (Data Source: USGBC 2014).
Table 1. Credits and Points of Energy and Atmosphere in LEED EBOM (Data Source: USGBC 2014).
Energy and AtmospherePoint (s)
PrerequisiteEnergy Efficiency Best Management PracticesRequired
PrerequisiteMinimum Energy PerformanceRequired
PrerequisiteBuilding-Level Energy MeteringRequired
PrerequisiteFundamental Refrigerant ManagementRequired
CreditExisting Building Commissioning—Analysis2
CreditExisting Building Commissioning—Implementation2
CreditOngoing Commissioning3
CreditOptimize Energy Performance20
CreditAdvanced Energy Metering2
CreditDemand Response3
CreditRenewable Energy and Carbon Offsets5
CreditEnhanced Refrigerant Management1
Total38
Table 2. LEED facts for the CYC project (Source: https://www.usgbc.org/projects/hku-chow-yei-ching-building).
Table 2. LEED facts for the CYC project (Source: https://www.usgbc.org/projects/hku-chow-yei-ching-building).
LEED O+M: Existing Buildings (v2009); Certification Awarded: Jun 2015
CategoriesPossible CreditsAchieved Credits
Sustainable Sites2617
Water efficiency1413
Energy & Atmosphere3519
Material & Resources105
Indoor Environmental Quality156
Innovation65
Regional Priority Credits44
Integrative Process Credits10
In total10669 (Gold)
Table 3. The content of the energy audit.
Table 3. The content of the energy audit.
ContentDetails
Building EnvelopeExterior wallsgeometrical configuration, construction materials, u value, window/wall ratio
Windows
Doors
Roof
System/EquipmentChiller Planttype, capacity
AHUspecifications, number, schedule
Ventilation Fans
FCU
Lighting System
Lift Systemtypes, speed, number, duty
Power Quality Systempower factor
Energy UseElectricity Billmonthly electricity bills
Occupancy PatternOperating Hoursday time and after–hours
weekdays and weekends
Occupancy Number
Occupancy Schedule
Indoor Environment QualityTemperature, Relative Humidity, Ventilation rate, CO2occupied areas
Table 4. Energy use breakdown.
Table 4. Energy use breakdown.
EquipmentAnnual Consumption (kWh)Percentage
Chiller Plant918,79324%
AHU152,8024%
PAU67,6632%
VF183,1415%
FCU146,1894%
Split Unit59,2272%
Lighting System604,29116%
Lift System374,29610%
Others (lab facilities)1,236,45833%
Total3,742,860100%
Table 5. CYC building construction and services information.
Table 5. CYC building construction and services information.
ItemExisting Building DescriptionBase Line (ASHRAE Standards 90.1-2007)
External Walls
TypeSolid Concrete Brick WallSteel-Framed
U-Value (W/m2·K)0.6000.705
Roof
Type150 mm Concrete Deck Flat RoofInsulation Entirely above Deck
U-Value (W/m2·K)0.4500.273
Fenestration
Glazing Type6mm Single Glazing, clear glass, no shading, with Aluminum window frameGlazing with metal framing
WWR25.6%0–40%
U-Value (W/m2·K)6.1484.26
SHGC0.820.25
Interior Partitions
TypeSlab on grade (unheated)Slab on grade(unheated)
F-factor (W/m2·K)1.3601.264
LPD (W/m2)
Lecture/Meeting/Library room1214
Office1012
Laboratory1415
Service/Rest Room810
Corridor/Staircase45
Lobby814
Temperature Set Point
Cooling Set Point (°C)2424
Cooling Set Back (°C)2837
Occupancy Density (m2/person)
Meeting/Library Room42.8
Lecture Room1.51.4
Office811.1
Laboratory59.3
Table 6. Simulated Energy Consumption Data Compared with Actual Data in the year 2009.
Table 6. Simulated Energy Consumption Data Compared with Actual Data in the year 2009.
MonthElectricity Consumption (kWh)
Actual Use in 2009Simulation
January208,980265,704
February224,400251,498
March258,280297,455
April275,740276,036
May324,240333,229
June384,660338,807
July371,210334,860
August400,820353,737
September418,230323,596
October349,380317,671
November296,280293,468
December230,640253,116
In Total3,742,8603,639,177
Table 7. Lighting Power Density for the existing condition and after the lighting retrofit.
Table 7. Lighting Power Density for the existing condition and after the lighting retrofit.
ItemBefore (W/m2)After (W/m2)
Lecture/meeting/library room128
Office106
Laboratory148
Service/rest Room84
Corridor/staircase44
Lobby84
Table 8. Glazing specifications in the base model and retrofit model.
Table 8. Glazing specifications in the base model and retrofit model.
Glazing PropertiesBefore the RetrofitAfter the Retrofit
WWR25.60%25.60%
U-Value (W/m2·K)6.1481.06
Solar Heat Gain Coefficient (SHGC)0.820.38
Total Solar Transmission0.820.38
Direct Solar Transmission0.790.25
Light Transmission0.8810.35
Shading Coefficient0.90.49
Table 9. Specification of the green roof.
Table 9. Specification of the green roof.
ItemValue
Area (m2)100
Thickness (m)0.15
Conductivity of Dry Soil (W/m·K)0.35
Specific heat of Dry Soil (J/kg·K)1200
Thermal Absorptance0.9
Solar Absorptance0.7
Leaf Reflectivity0.22
Leaf Emissivity0.95
Minimum Stomatal Resistance (s/m)180
Table 10. Cooling electricity consumptions before and after the upgrade.
Table 10. Cooling electricity consumptions before and after the upgrade.
MonthBeforeAfter
Chiller Plant COP 2.6Chiller Plant COP 5.0
9 January46,12423,842
9 February44,05722,962
9 March58,91238,983
9 April68,28950,264
9 May86,85568,016
9 June96,12875,128
9 July98,35878,464
9 August100,33979,330
9 September91,72771,764
9 October81,29861,512
9 November62,99844,396
9 December48,59826,243
Table 11. SWOT analysis of the key retrofitting stages.
Table 11. SWOT analysis of the key retrofitting stages.
Key Stages1. Energy Auditing2. Building Simulation3. Measurement & Verification
ObjectivesIdentify ECMsAnalyze ECMsExamine ECMs
StrengthsDirect evidencePredictionDirect evidence
WeaknessesLack of assumptionsUncertaintiesGenerality
OpportunitiesCombined with building simulationCalibration with electricity billsCompare with pre-retrofit bills and simulations
ThreatsMissing opportunitiesOverestimating energy savingsMissing specific reasons for success and/or failure

Share and Cite

MDPI and ACS Style

Sun, X.; Gou, Z.; Lu, Y.; Tao, Y. Strengths and Weaknesses of Existing Building Green Retrofits: Case Study of a LEED EBOM Gold Project. Energies 2018, 11, 1936. https://doi.org/10.3390/en11081936

AMA Style

Sun X, Gou Z, Lu Y, Tao Y. Strengths and Weaknesses of Existing Building Green Retrofits: Case Study of a LEED EBOM Gold Project. Energies. 2018; 11(8):1936. https://doi.org/10.3390/en11081936

Chicago/Turabian Style

Sun, Xiaonuan, Zhonghua Gou, Yi Lu, and Yiqi Tao. 2018. "Strengths and Weaknesses of Existing Building Green Retrofits: Case Study of a LEED EBOM Gold Project" Energies 11, no. 8: 1936. https://doi.org/10.3390/en11081936

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop