Next Article in Journal
Dynamic Thermal Features of Insulated Blocks: Actual Behavior and Myths
Next Article in Special Issue
Re-Creating Waves in Large Currents for Tidal Energy Applications
Previous Article in Journal
Parameter Identification of Electrochemical Model for Vehicular Lithium-Ion Battery Based on Particle Swarm Optimization
Previous Article in Special Issue
Simulating Extreme Directional Wave Conditions
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Cost Assessment Methodology and Economic Viability of Tidal Energy Projects

1
Escuela de Ingenieros Industriales de Albacete, Universidad de Castilla-La Mancha, 02071 Albacete, Spain
2
Escuela Técnica Superior de Ingenieros Navales, Universidad Politécnica de Madrid, 28040 Madrid, Spain
*
Author to whom correspondence should be addressed.
Energies 2017, 10(11), 1806; https://doi.org/10.3390/en10111806
Submission received: 15 September 2017 / Revised: 24 October 2017 / Accepted: 6 November 2017 / Published: 9 November 2017
(This article belongs to the Special Issue Marine Energy)

Abstract

:
The exploitation of technologies with which to harness the energy from ocean currents will have considerable possibilities in the future thanks to their enormous potential for electricity production and their high predictability. In this respect, the development of methodologies for the economic viability of these technologies is fundamental to the attainment of a consistent quantification of their costs and the discovery of their economic viability, while simultaneously attracting investment in these technologies. This paper presents a methodology with which to determine the economic viability of tidal energy projects, which includes a technical study of the life-cycle costs into which the development of a tidal farm can be decomposed: concept and definition, design and development, manufacturing, installation, operation and maintenance and dismantling. These cost structures are additionally subdivided by considering their sub-costs and bearing in mind the main components of the tidal farm: the nacelle, the supporting tidal energy converter structure and the export power system. Furthermore, a technical study is developed in order to obtain an estimation of the annual energy produced (and, consequently, the incomes generated if the electric tariff is known) by considering its principal attributes: the characteristics of the current, the ability of the device to capture energy and its ability to convert and export the energy. The methodology has been applied (together with a sensibility analysis) to the particular case of a farm composed of first generation tidal energy converters in one of the Channel Island Races, the Alderney Race, in the U.K., and the results have been attained by means of the computation of engineering indexes, such as the net present value, the internal rate of return, the discounted payback period and the levelized cost of energy, which indicate that the proposed project is economically viable for all the case studies.

Graphical Abstract

1. Introduction

There has been, in recent years, an increasing concern about global climate change, the importance of reducing greenhouse gas emissions, the current dependency on and limited life span of fossil fuels and the current increase in energy prices [1,2,3]. Renewable energies play a key role in this framework, and this has been recognized by the European Union (EU), which in 2009 established the need to reduce 20% of energy consumption and 20% of carbon dioxide (CO 2 ) emissions with the objective of 20% of the EU’s final energy consumption originating from renewable sources in 2020 [4,5]. This milestone was a definite boost as regards the promotion of clean renewable technologies for electricity generation. It led to the fixing of legally-binding targets that marked a path for the future, with continuity beyond 2020, and opened up a horizon of opportunities for the development of new sources and renewable technologies, as well as economic sectors linked to renewable energies. It is, therefore, necessary to attain and increase the aforementioned renewable energy percentages in the near future, and there is consequently a growing interest in the contribution of other types of renewable energy that are currently less developed and will remain so for the next five years, since their technologies are still in the development and demonstration phases [6,7,8]. One of these is ocean energy whose exploitation could provide the following opportunities and benefits [9,10,11]: energy independence, decarbonization, job creation and being a complement to other renewable sources within the global energy mix (improved predictability, decreased variability, spatial concentration and socio-economic benefits) [12,13].
This research is focused on tidal energy, which, although its technologies are at the prototype and pre-commercial demonstration at sea phases, will have considerable possibilities in the future thanks to its enormous potential for electricity production and its high predictability [14,15,16]. In this respect, any system based on renewable sources that is intended for commercialization must first pass through an economic assessment in order to achieve a consistent quantification of the costs of these technologies, to verify the profitability of the system while simultaneously attracting investment and to allow commercialization [17]. However, limited experience hinders the evaluation of tidal energy projects with an adequate level of confidence owing to the current lack of data and the high level of uncertainty [18]. We should note that, despite the potential benefits of this renewable energy source, very few studies have focused specifically on the economic feasibility of these systems and how to estimate them. Issues such as costs [19], the net present value [20] (NPV), the internal rate of return (IRR) [21], the discounted payback-period (DPBP) [22], the levelized cost of energy (LCOE) [23] or the life-cycle costs (LCC)—from an economical [24] or an environmental [25] point of view, among others—have been developed in previous works that were principally focused on other products/process and other sorts of renewable energy sources [26]. With regard to tidal energy projects, several authors have performed studies for tidal farms, indicating the general percentages of influences of each cost, but without providing a specific methodology with which to calculate the cost involved in a tidal farm [27,28]. A more detailed description of the development of the economic viability of marine energy farms is found in [29], which includes interesting information regarding how to obtain the annual energy produced (AEP) and to determine the costs of the main components of a marine energy farm. However, with regard to the AEP, this research does not include information about aspects such as the stele effect, blend effect, velocity deficit or effects related to the tidal farm topology, among others, which have a great influence on the determination of the final value of the AEP. Furthermore, with regard to the determination of the costs of the main components of the tidal farm, the aforementioned research does not provide detailed information with which to compute detailed aspects of the costs of the main sub-components of which the tidal farm is composed (turbine, foundation, export energy system), and this influences the final value of the cost incurred by the energy farm during its service life. Under these premises, and with the intention of covering this lack, the main contributions to the state of the art of this research are the following: (i) a methodology with which to determine the economic viability of tidal energy projects and that includes a technical study of the LCC, defined by modifying the recommendations proposed in [30], since this normative is focused on a product rather than a process. Bearing in mind the aforementioned consideration, the main stages into which the development of a tidal farm can be decomposed are: concept and definition, design and development, manufacturing, installation, operation and maintenance (O&M) and dismantling. These cost structures are additionally subdivided by considering their sub-costs and bearing in mind the main components of the tidal farm: the nacelle, the supporting tidal energy converter (TEC) structure and the export power system. Specific expressions have been included in order to increase the detail involved in calculating the LCC for tidal energy projects, which is rarely found in other studies. A technical study is then performed in order to describe the estimation of the AEP in detail (and, consequently, the incomes generated if the electric tariff is known) by considering its principal attributes: the characteristics of the current, the ability of the device to capture energy and its ability to convert and export the energy. Additionally, (ii) the proposed methodology has been used to discover the economic viability of a tidal farm located in one of the Channel Island Races, the Alderney Race, in the U.K. A sensitivity analysis was also carried out. The results obtained through the use of engineering indexes such as NPV, IRR, DPBP and LCOE indicate that the project is economically feasible for all the case studies. Finally, the remainder of the paper is structured as follows: Section 2 illustrates the proposed methodology for the economic evaluation of tidal energy projects. Section 3 shows a case case study of a 50-MW tidal farm in the Alderney Race. Section 4 depicts the numerical results obtained for the case study, and finally, Section 5 shows our conclusions and proposals for future works.

2. Proposed Methodology of the Evaluation of Tidal Energy Projects

The methodology proposed for the economic feasibility of these energy projects is based on the LCC of the project and the determination of the AEP. The aim of attaining the LCC is to provide useful criteria for decision-making at any or all of the stages that comprise the life-cycle of the project. In essence, the LCC represents an accounting structure that contains mathematical expressions with which to estimate the associated costs of a project during its service life [31,32]. We should emphasize that the development of a methodology for the economic assessment of projects based on LCC is a simplified representation of the real world based on the main characteristics and relations of the project and their corresponding estimation costs. In order to carry out an adequate LCC for tidal energy projects from the perspective of environmentally sustainable economic efficiency, it is fundamental to understand the life-cycle of this sort of project and the activities to be performed at all the stages. All the decisions made as regards the design, manufacture, operation, maintenance, and so on, including environmental impact, may therefore affect the total cost in a substantial manner [33,34]. The stages of which the proposed methodology are composed are the following (See Figure 1): (i) concept and definition costs: C 1 ; (ii) design and development costs: C 2 ; (iii) manufacturing costs: C 3 ; (iv) installation costs: C 4 ; (v) operation and maintenance costs: C 5 ; and (vi) decommissioning costs: C 6 . Once these costs have been computed, the total LCC of a tidal energy project yields the following result:
L C C T E P = C 1 + C 2 + C 3 + C 4 + C 5 + C 6
Furthermore, the information concerning the site (water depth, tidal energy resource, weather windows, distance from shore, etc.), the device (geometry, configuration, power, materials, etc.) and the export energy system (farm topology, connectors, cables, transformation platform, converters, etc.) makes it possible to estimate the AEP and, consequently, the incomes obtained from the possible commercial exploitation of the tidal energy project. All the aforementioned information is then analyzed by means of several indicators (NPV, IRR, DPBP and LCOE) that will have a decisive influence on the decision to invest in the tidal energy project and will allow comparative studies with other renewable energy sources to take place. It is important to note that the estimated costs and the estimation of the AEP included in the methodology for the economic feasibility of tidal energy projects have been obtained by studying the current scientific literature, internal technical reports generated at the Escuela Técnica Superior de Ingenieros Navales of the Universidad Politécnica de Madrid and information provided by companies that specialize in tidal energy projects and shipyards. The following subsections deal with all the details required to describe the proposed methodology.

2.1. Concept and Definition Costs ( C 1 )

The concept and definition costs are attributed to various activities whose objective is to guarantee the project’s viability. If we focus on tidal energy projects, the following costs are typically included:
  • Market research costs ( C 11 ): It is necessary to determine the current state of the market as regards tidal energy generation and to analyze the economic viability of the tidal energy project on the basis of environmental information, site information (water depth, tidal energy resource, weather windows, distance from shore, etc.), device information (geometry, configuration, power, materials, etc.), export power system information (farm topology, connectors, cables, transformation platform, converters, etc.), and so on. This cost is modeled as a constant value, i.e.,
    C 11 = C M R
    where C M R is defined as a constant value.
  • Project management costs ( C 12 ): These include the completion and obtaining of certificates and regulations, such as environmental studies (seabed surveys, local species and ecosystem surveys, coastal process surveys, etc.), social impact surveys and the authorization of the installation. These costs are usually constant, with the exception of the authorization of the installation of the tidal farm, which depends on the surface required to install the tidal energy project. These costs are, therefore, modeled as:
    C 12 = C C S + C A I · S T E P
    where C C S denotes a constant value in €, C A I expresses the cost per m 2 in €/m 2 and S T E P defines the surface required to install the tidal energy project in m 2 .
  • Conception of the tidal farm and design analysis costs ( C 13 ): This comprises the cost of obtaining the preliminary solution for the tidal energy project. One or more possible solutions are synthesized at this stage and are then evaluated with regard to the restrictions imposed. This cost is modeled as a constant value, i.e.,
    C 13 = C C D A
    where C C D A denotes a constant value in €.
  • Project requirements’ specification costs ( C 14 ): At this stage, the main components of the tidal energy project and their interactions are determined in sufficient detail to be able to carry out an objective evaluation of the project proposal. In the particular case of tidal farms, it is necessary to consider site information (water depth, tidal energy resource, weather windows, distance from shore, etc.), device information (geometry, configuration, power, materials, etc.), export power system information (farm topology, connectors, cables, transformation platform, converters, etc.), and so on. This cost is again modeled as a constant value, i.e.,
    C 14 = C P R S
    where C P R S expresses a constant value in €.
Once these costs have been attained, the concept and definition costs, C 1 , are obtained as follows:
C 1 = C 11 + C 12 + C 13 + C 14

2.2. Design and Development Costs ( C 2 )

The design and development costs are those related to fulfilling the specification of the project requirements and providing proofs of its compliance. They typically include costs regarding: (i) project management ( C 21 ); (ii) engineering design ( C 22 ), the inclusion of reliability, maintainability and activities for environmental protection; (iii) detailed documentation for the design ( C 23 ); (iv) determining the manufacturing steps required for the park ( C 24 ); (v) the selection of the suppliers ( C 25 ); or (vi) quality management ( C 26 ). All these costs can be modeled as a constant value, i.e.,
C 2 = C 21 + C 22 + C 23 + C 24 + C 25 + C 26 = C D D
where C D D defines a constant value in €.

2.3. Manufacturing Costs ( C 3 )

The manufacturing costs comprise all the costs involved in manufacturing the elements from which the tidal farm will be constructed. In the case of tidal energy projects, the main costs considered at this stage are the following:
  • Nacelle ( C 31 ): This cost (see Figure 2) is estimated by considering the following sub-costs associated with the structure of the nacelle ( C 311 ): power take off (PTO) frame ( C 312 ), fairing ( C 313 ), PTO ( C 314 ), auxiliary systems ( C 315 ) and rotor ( C 316 ). They are estimated as follows:
    Structure of the nacelle ( C 311 ): This cost is estimated by considering the number of TECs manufactured, N M , the cost per kg of the carbon steel produced, C S D , in €/kg, and the mass of the structure (front cover, horizontal and vertical cylinders, longitudinal and transversal reinforcements, etc.) of the nacelle, m S D , in kg, i.e.,
    C 311 = N M · m S D · C S D
    PTO frame ( C 312 ): This cost is estimated by considering the number of TECs manufactured, the cost per kg of the carbon steel produced for this element, C P T O F , in €/kg, and the mass of this element, m P T O F , in kg, i.e.,
    C 312 = N M · m P T O F · C P T O F
    Fairing ( C 313 ): This cost is estimated by considering the number of TECs manufactured, the cost per kg of the fiberglass produced for this element, C F , in €/kg, and the mass of this element, m F , in kg, i.e.,
    C 313 = N M · m F · C F
    PTO ( C 314 ): This cost considers the number of TECs manufactured and the costs of the thrust bearing, the gearbox, the high-speed shaft, the slip ring system, the brake system, the electrical generator, etc., of each TEC [35,36,37,38]. The main variables required to estimate these costs are included in a nonlinear function depending on the number of TECs manufactured, the power of each TEC, P T , the cost per MW of the thrust bearing, C T B , in €/MW, the cost per MW of the high-speed shaft, C H S S , in €/MW, the cost per MW of the gearbox, C G , in €/MW, the cost per MW of the brake system, C B S , in €/MW, and the cost per MW of the electrical generator, C E G , in €/MW, i.e.,
    C 314 = N M · P T · C T B + C B S + C H S S + C E G + P T 1 . 2 · C G
    Auxiliary systems ( C 315 ): This cost considers the number of TECs manufactured and the costs of the yaw system, cooling system, pressure oil system, protection and connection switches, bilge system, compressed air system, circuit board, control system, condition monitoring systems and added elements. The main variables required to estimate this cost are the number of TECs manufactured, the power of each TEC, the mass of the yaw system, m Y S , in kg, the cost per kg for this element, C Y S , in €/kg, the cost per MW of the cooling system, C C O S , in €/MW, the cost per MW of the pressure oil system, C P O S , in €/MW, the mass of the protection and connection switches m S W T in kg, the cost per kg of these elements, C S W T , in €/kg, the mass of the bilge system m B I S in kg, the cost per kg of this element, C B I S , in €/kg, the mass of the compressed air system m A C S in kg, the cost per kg of this element, C A C S , in €/kg, the mass of the circuit board m C B in kg, the cost per kg of this element, C C B , in €/kg, the mass of the control system m C T S in kg, the cost per kg of these elements, C C T S , in €/kg, the cost per MW of the condition monitoring system, C C M S , in €/MW, the mass of the added elements m A E in kg, and the cost per kg of this element, C A E , in €/kg, i.e.,
    C 315 = N M · m Y S · C Y S + m C T S · C C T S + P T C C O S + C P O S + C C M S + m S W T · C S W T + m B I S · C B I S + m A C S · C A C S + m C B · C C B + m A E · C A E
    Rotor ( C 316 ): This cost is estimated by considering the number of TECs manufactured, the costs of the blades, the pitch system and the core of the rotor. The main variables required to estimate these costs are included in a nonlinear function depending on the number of TECs manufactured, the radius of the rotor, R R , in m, the cost per m of each blade, C B , in €/m, the number of blades per TEC, N B , the cost per m of the pitch system, C P S , in €/m, the cost per m of the low-speed shaft, C L S S in €/m, and the cost per m of the core of the rotor, C C R , in €/m, i.e.,
    C 316 = N M · N B · R R 2.7 · C B + R R · C P S + C L S S + C C R
  • Supporting TEC structure ( C 32 ): This cost is estimated by considering the following sub-costs (see Figure 3) associated with the base support ( C 321 ), the transition structure ( C 322 ), the vertical column ( C 323 ), the concrete ballasts ( C 324 ) and the special concrete bags ( C 325 ). They are estimated as follows:
    Base support ( C 321 ): This cost is estimated by considering the number of TECs installed, N I , the cost per kg of the steel produced, C T B S , in €/kg, and the mass of the structure, m T B S , in kg, i.e.,
    C 321 = N I · m T B S · C T B S
    Transition structure ( C 322 ): This cost is estimated by considering the number of TECs installed, the cost per kg of the steel produced, C T T S , in €/kg, and the mass of the structure, m T T S , in kg, i.e.,
    C 322 = N I · m T T S · C T T S
    Vertical column ( C 323 ): This cost is estimated by considering the number of TECs installed, the cost per kg of the steel produced, C T V C , in €/kg, and the mass of the structure, m T V C , in kg, i.e.,
    C 323 = N I · m T V C · C T V C
    Concrete ballasts ( C 324 ): This cost is estimated by considering the number of TECs installed, the amount of concrete ballast per TEC, N C B , the cost per kg of the concrete produced, C E C , in €/kg, and the mass of the ballast, m E C , in kg, i.e.,
    C 324 = N I · N C B · m E C · C E C
    Special concrete bags ( C 325 ): This cost is estimated by considering the number of TECs installed, the amount of special concrete bags per TEC, N B G , the cost per kg of the concrete contained in the special bags, C B G , in €/kg, and the mass of the concrete produced for the special bags, m B G , in kg, i.e.,
    C 325 = N I · N B G · m B G · C B G
  • Export power system ( C 33 ): This cost is estimated by considering the following sub-costs associated with the electrical equipment in the nacelle ( C 331 ), the electrical equipment in the base support ( C 332 ), the umbilical cables ( C 333 ), the transformation platform and the converters ( C 334 ) and the exportation cable ( C 335 ). They are estimated as follows:
    Electrical equipment in the nacelle ( C 331 ): This cost is estimated by considering the number of TECs manufactured, the power of each TEC, the cost per MW of the protection switch, C P S W , in €/MW, the mass of the submarine connector, m S C , in kg, and the cost per kg of this element, C S C , in €/kg, i.e.,
    C 331 = N M · P T · C P S W + m S C · C S C
    Electrical equipment in the base support ( C 332 ): This cost is estimated by considering the number of TECs installed, the mass of the submarine connector installed in the base, m B S C , in kg, the cost per kg of this element, C B S C , in €/kg, the mass of the internal wiring, m I W , in kg, the cost per kg of this element, C I W , in €/kg, the mass of the connection box, m C B X , in kg and the cost per kg of this element, C C B X , in €/kg, i.e.,
    C 332 = N I · m B S C · C B S C + m I W · C I W + m C B X · C C B X
    Umbilical cables ( C 333 ): This cost is estimated by considering the length of the umbilical cables, L U C , in m, and the cost per m of this element, C U C , in €/m, i.e.,
    C 333 = L U C · C U C
    Transformation platform and converters ( C 334 ): This cost is estimated by considering the number of TECs installed, the power of each TEC, the cost per MW of the rectifiers, C R , in €/MW, the cost per MW of the inverters, C I , in €/MW, the cost per MW of the electrical boxes, C E B , in €/MW, the number of transformers, N T F , the cost per MW of the transformers, C T F , in €/MW, the mass of the transformation platform, m T P , in kg, and the cost per kg of this element, C T P , in €/kg, i.e.,
    C 334 = N I · P T · C R + C I + C E B + N T F · C T F + m T P · C T P
    Exportation cables ( C 335 ): This cost is estimated by considering the number of submarine exportation cables, N S E C , the length of the submarine exportation cables, L S E C , in m, the cost per m of this element, C S E C , in €/m, the length of the ground exportation cables, L G E C , in m, and the cost per m of this element, C G E C , in €/m, i.e.,
    C 335 = N S E C · L S E C · C S E C + L G E C · C G E C
Once these costs have been attained, the manufacturing costs, C 3 , are obtained as follows:
C 3 = C 31 + C 32 + C 33

2.4. Installation Costs ( C 4 )

The estimation of the installation costs for tidal farms is of particular difficulty owing to the characteristics and uncertainties of the offshore operations and the volatility costs of the vessels used in these operations. Several concepts need to be considered if these costs are to be estimated in an appropriate manner:
  • Specialized vessels: The evolution of offshore wind farms and the development of advanced offshore technologies result in progressions in infrastructure and the attainment of specific solutions for these particular sectors. When designing the installation and O&M procedures, it is therefore essential to search for specialized vessels with which to perform these activities. Without the existence of these specialized vessels, the costs of these operations would be so high that the economic viability of these offshore systems might be seriously compromised.
  • Base port: When studying of the implementation of a tidal farm, it is very important to determine the location of nearby industrial base ports. These ports need to be equipped with sufficient means for the reception of materials and components and have the capabilities to load and upload these materials and components, along with the means to perform TEC maintenance tasks. The location of the port base has a great influence as regards ensuring a reduction in the installation and O&M costs.
  • Weather windows: Weather phenomena, such as wind velocity, wave height and tidal current velocity, need to be studied in order to perform the installation and the O&M procedures in safe conditions. The definition of favorable weather windows throughout the different seasons of the year is fundamental if an adequate and a safe planning of the installation and the O&M tasks is to take place.
Bearing the previous considerations of the cost structure in mind, the following costs are considered at this stage:
  • Installation of the transformation platform and converters ( C 41 ): In order to evaluate this activity, it is necessary to include the cost of leasing the vessels (specialized installation vessel, cable-laying vessel, remotely-operated vehicles (ROVs), etc.), C V I P C , the cost of technical labor (technical specialist, divers, etc.), C T L I P C , the cost of operations in the port (excavators, winches, trucks, etc), C P O I P C , which depend on the distance from the tidal farm to the base port, d P T F , and the weather windows, W W ; i.e.,
    C 41 = C V I P C d P T F , W W + C T L I P C d P T F , W W + C P O I P C d P T F , W W
  • Installation of the submarine cables ( C 42 ): This cost has a similar structure to that explained previously. In order to estimate this activity, it is necessary to include the cost of leasing the vessels, C V I S C , the cost of technical labor, C T L I S C , the cost of operations in the port, C P O I S C , which depend on the distance from the tidal farm to the base port, and the weather windows; i.e.,
    C 42 = C V I S C d P T F , W W + C T L I S C d P T F , W W + C P O I S C d P T F , W W
  • Installation of the ground exportation cable ( C 43 ): In order to evaluate this activity, it is again necessary to include the cost of leasing the vessels, C V I G E C , the cost of technical labor, C T L I G E C , the cost of operations in the port, C P O I G E C , which depend on the distance from the tidal farm to the base port, and weather windows:
    C 43 = C V I G E C d P T F , W W + C T L I G E C d P T F , W W + C P O I G E C d P T F , W W
  • Installation of the TECs ( C 44 ): Finally, and using a similar procedure to that described above, the evaluation of this cost structure is the following (cost of leasing the vessels, C V I T E C , the cost of technical labor, C T L I T E C , the cost of operations in the port, C P O I T E C , which depend on the distance from the tidal farm to the base port, and weather windows):
    C 44 = C V I T E C d P T F , W W + C T L I T E C d P T F , W W + C P O I T E C d P T F , W W
Once these costs have been attained, the installation costs, C 4 , are obtained as follows:
C 4 = C 41 + C 42 + C 43 + C 44 .

2.5. Operation and Maintenance Costs ( C 5 )

In the case of tidal energy projects, O&M procedures suppose an important part of the design of the TECs and will have a direct and important repercussion as regards the time it takes to get the TECs working properly and, consequently, the energy generation capacity of the tidal farm. The reduction in the time spent on these tasks substantially influences the reduction in the cost of energy [39]. Additionally, and as explained in the previous section, the performance of the maintenance tasks should be carried out in periods of small tidal currents in order to ensure safe conditions when raising the nacelle and carrying out insertion operations on it and to minimize energy losses during the time spent on these operations [40]. During the development of an effective maintenance plan for the tidal farm (and the cost structure), it is necessary to estimate the downtimes that each component requires, the failure probability of each component, the specialized vessels used in these tasks and the weather windows in which these tasks can be performed [41,42]. Furthermore, it is very important to include the insurance costs and fixed expenses in the operation and maintenance cost structure, because they are some of the most expensive factors in the offshore renewable energy sector [17]. The computation of this cost structure has been performed in accordance with the procedures developed in [43,44]. Bearing the previous considerations regarding the cost structure in mind, the following costs are considered at this stage:
  • Blade cleaning ( C 51 ): This concerns the removal of algae, microorganisms and fouling from the blades of the TEC. This cost depends on the number of TECs manufactured, the downtimes spent on this process, D B C , the weather windows, the transport costs, C T B C , the labor costs, C L B C , and the costs incurred as the result of production losses, C P L B C , i.e.,
    C 51 = N M · C T B C D B C , W W + C L B C D B C , W W + C P L B C D B C , W W
  • Light preventive maintenance ( C 52 ): This involves light general maintenance (grease changes, review of painting defects, etc.) in the TECs (nacelle + supporting structure) and the export energy system. The estimation of this cost category is carried out by considering the number of TECs manufactured, the downtimes spent on this process, D L P M , the weather windows, W W , the transport costs, C T L P M , the labor costs, C L L P M , the material costs, C M L P M , and the costs incurred as the result of production losses, C P L L P M , i.e.,
    C 52 = N M · C T L P M D L P M , W W + C L L P M D L P M , W W + C M L P M D L P M , W W + C P L L P M D L P M , W W
  • High preventive maintenance ( C 53 ): This implies more in-depth maintenance (bearing replacements, inspection of the nacelle and the structure components, etc.) in the TECs (nacelle + supporting structure) and the export energy system. As in the previous category, the estimation of this cost category is carried out by considering the number of TECs manufactured, the downtimes spent on this process, D H P M , the weather windows, W W , the transport costs, C T H P M , the labor costs, C L H P M , the material costs, C M H P M , and the costs incurred as the result of production losses, C P L H P M , i.e.,
    C 53 = N M · C T H P M D H P M , W W + C L H P M D H P M , W W + C M H P M D H P M , W W + C P L H P M D H P M , W W
  • Corrective maintenance ( C 54 ): This concerns repairing the TECs (nacelle + supporting structure) and the export energy system, The computation of this cost category is developed by including the number of TECs manufactured, the failure probability of the i-component of the tidal farm, P F i , the downtimes spent on this process, D C M , the weather windows, W W , the transport costs, C T C M , the labor costs, C L C M , the material costs, C M C M , and the costs incurred as the result of production losses, C P L C M , i.e.,
    C 54 = N M · C T C M D C M , W W + C L C M D C M , W W + C M C M D C M , W W + C P L C M D C M , W W
  • Insurance costs and fixed expenses ( C 55 ): The estimation of this cost is an area that needs to be studied in depth within the offshore renewable energy sector. According to the scientific literature, two possible metrics can be used to estimate these costs [17]: (a) % of the total capital expenditure (CAPEX, an expenditure whose benefit extends beyond one year; this concept will be explained in detail in Section 2.8); or (b) €/MWh. For example, in [45], the cost of insurance is estimated as 2% of the CAPEX, while [46] includes an estimation of the insurance cost of 15,000 €per MW. In our case, the insurance costs and fixed expenses have been estimated as a percentage of the CAPEX.
Once these costs have been attained, the operation and maintenance costs, C 5 , are obtained as follows:
C 5 = C 51 + C 52 + C 53 + C 54 + C 55 .

2.6. Decommissioning Costs ( C 6 )

This stage includes all the costs incurred during the removal and disposal of the project components and leaving the sea as it was initially. It is expected that this will occur in approximately 20 years [47]. The decommissioning costs incurred are typically the following: (i) stopping the system ( C 61 ); (ii) dismantling the transformation platform and converters ( C 62 ); (iii) dismantling the submarine cables ( C 63 ); (iv) dismantling the exportation cable ( C 64 ); (v) dismantling the TECs ( C 65 ). At this stage, it is necessary to include the incomes obtained from the sales of the main components (steel, converters, etc.) of the tidal farm ( C 66 ). This value will be modeled as a negative value in the cost structure. Once these costs have been attained, the decommissioning costs, C 6 , are obtained as follows:
C 6 = C 61 + C 62 + C 63 + C 64 + C 65 + C 66 .
As occurred with the installation costs and the operation and maintenance costs, the estimation of the decommissioning costs for tidal farms is of particular difficulty owing to the characteristics and uncertainties of the offshore operations, the volatility costs of the vessels used in these operations, the weather windows, etc. Additionally, there is currently no accurate information about the quantification of the economic costs of offshore tidal farms owing to the fact that no offshore tidal farm has, as yet, been dismantled.
Another possible option is the renewal/total inspection of the devices and platforms in such a way that the service life of the tidal farm can be extended. This is a very interesting option because some of the investments made will barely need renewal. The cost of energy of the tidal farm during this elongated service life would, therefore, substantially decrease, thus making the project more profitable.
Bearing the aforementioned considerations and the uncertainties currently involved at this stage in mind, the dismantling cost will not be included in the case study performed.

2.7. Annual Energy Produced

One of the most important items, and a clear indicator for decision-making during the installation of a tidal farm, is the achievement of the AEP. In order to estimate the AEP (and consequently, the incomes generated if the electric tariff is known), it is necessary to determine a model that considers the characteristics of the current (speed, direction, distribution, etc.), the ability of the device to capture energy and its ability to convert and export energy. The following items are required to estimate the AEP (see Figure 4):
  • Estimation of the current velocity at the depth of the rotor. During the computation of this parameter, it is necessary to consider the following aspects:
    Histograms of the current velocity: These histograms provide information about the frequency (number of hours) with which a given current velocity is repeated in a year. They provide useful information as regards estimating the energy produced by a TEC [48].
    Current profile at the operating depth: A relation of 1 / 7 is used to adapt the measured current velocities at the surface (represented in the aforementioned histograms) to the operating depth [49].
    V r = V h Z r Z h 1 7
    where V r represents the rotor velocity in m/s, V h denotes the velocity at the sea surface in m/s, Z r is the rotor depth in m and Z h expresses the depth of the water column.
    Stele effect, blend effect and velocity deficit: When the flow passes through the rotor, it transfers energy to it, but it simultaneously undergoes diverse hydrodynamic phenomena that result in a flow speed deficit downstream of the rotor. It additionally generates a stele with a great turbulence that causes disturbances in the flow. This effect appears when the flow passes through each TEC and, consequently, when it passes each row of the tidal farm. The last rows of the tidal farms will, therefore, receive a lower quality flow, signifying that the TECs will capture less energy [50]. This is obtained by employing the following expression:
    a = 1 1 C t
    A s = 1 0.5 a 1 a A r
    V s = ( 1 a ) V r
    where a is the stele coefficient, C t represents the buoyancy coefficient, V r denotes the input flow velocity in m/s, A r is the surface of the rotor in m 2 , V s denotes the output flow velocity in m/s and A s expresses the output flow surface in m 2 . Once this effect has been estimated, it is necessary to take into account the blend effect between the perturbed flow and the free flow downstream of the rotor by considering the configuration of the tidal farm and applying the energy conservation law. The following result is obtained:
    A s V s 2 + A t A r V r 2 = A t V z 2
    where A t denotes the total frontal surface of the device and V z expresses the final velocity of the blended flow in m/s. The velocity deficit is then computed as:
    V x = V s V z e 0.2 x D
    with an exponential decay model for an intermediate point (x, V x ) located between the rotor output (stele effect) and the blend flow downstream and where D denotes the diameter of the rotor [51]. The usual values of velocity deficit are around 5% when the flow passes through a row of TECs.
  • Performance of the PTO: When the tidal current velocity is small, the PTO of the TEC is working in a partial regime that only captures a part of its nominal power, and its performance is, therefore, considerably reduced. This effect needs to be considered in order to estimate a realistic value of the AEP and to characterize the cut-in velocity (the cut-in velocity of a TEC can be defined as the minimum velocity required to generate energy with which to feed at least the auxiliary systems that allow the TEC to operate) of the device.
  • Additional requirements when estimating the total energy produced: Several requirements need to be considered when estimating a realistic value of the total energy:
    Availability factor: The TEC does not always work properly owing to device breakdowns and maintenance periods. This availability factor needs to be estimated on the basis of the information obtained from the maintenance procedures used, weather windows, and so on.
    Tidal farm topology: This influences the final value of the AEP, and it is necessary to evaluate the performance of each TEC on the basis of the position (row, column) that it occupies within the tidal farm.
    Performance of the power export system: The last stage involved in obtaining the AEP for the tidal farm is its exportation and conversion into quality energy. The performance of the export power system from the generators of the TECs to the water-to-wire point therefore needs to be included.

2.8. Viability Analysis

After computing the LCC and the AEP of the project, it is necessary to perform a feasibility analysis, which is done by studying several economic and technical indicators. The conclusions obtained from this study will have a decisive influence on the decision-making process, showing the current value of the benefits, the profitability of the project and the possibility of performing comparative studies with other renewable energy sources. Of the various economic and technical indicators, we include the following: (i) net present value (NPV); (ii) internal rate of return (IRR); (iii) discounted payback period (DPBP); and (iv) levelized cost of energy (LCOE). The NPV, IRR and DPBP are indicators that usually depend on market conditions. However, the LCOE is independent of market conditions and is frequently used in the study of renewable energy projects. The following subsections deal with the definition of these indicators.

2.8.1. Net Present Value

The NPV is represented by the difference between the present value of cash inflows (given by the total investment costs and the operational costs) and the present value of cash outflows (obtained from the cost of the electricity and the tidal resource) [52]. The NPV is usually used to analyze the profitability of a project or a projected investment. It is obtained by means of the following expression:
N P V = C 0 + t = 1 n C t · ( 1 + k ) t
where C 0 denotes the initial investment costs (€), C t represents the net cash flow during the period t in years (€), k is the annual discount rate and n expresses the number of time periods.

2.8.2. Internal Rate of Return

The IRR is defined as the annual discount rate that makes the NPV of all net cash flows equal to zero [52]. It is also used to analyze the profitability of investing in the project. From a financial perspective, the IRR provides a measure of the gross annual relative profitability per monetary unit involved in the project. Mathematically, it is expressed as follows:
0 = C 0 + t = 1 n C t · ( 1 + r ) t r = I R R
Owing to the nature of Expression (43), the IRR must be calculated by employing an iterative process or using programmed mathematical software.

2.8.3. Discounted Payback Period

The DPBP provides the number of years it takes to break even after the initial expenditure [52]. It is configured as a suitable method with which to evaluate risk investments that allows the profitability analysis performed with the NPV and the IRR to be carried out. It is obtained by means of the following expression:
D P B P = A + B C
where A denotes the last year with a negative discounted cumulative cash flow, B represents the absolute value of discounted cumulative cash flow at the end of the year A and C is the discounted cash flow during the year after A.

2.8.4. Levelized Cost of Energy

The LCOE is a useful tool with which to compare the unit cost of different technologies throughout their economic life and serves as a benchmarking or ranking tool with which to compare different technological alternatives that could be achieved by different investments and time operations. It should be studied on the basis of specific countries (or even the same place) [53,54]. The LCOE is defined as the life-cycle cost divided by lifetime energy production and is computed as follows [55]:
L C O E = C C A P E X + t = 1 n C O P E X t · ( 1 + k ) t t = 1 n E t · ( 1 + k ) t
where CAPEX (capital expenditure) signifies an expenditure whose benefit extends beyond one year. C C A P E X mostly includes the general costs, the cost of the PTO and ancillary/mooring systems, the main support structure of the TEC, base and/or mooring, other device units, the installation of the TEC and other units, the TEC farm hub platform and the energy transportation systems, among others [38]. OPEX (operational expenditures) involves the ongoing cost of running the tidal energy project. C O P E X includes administrative costs, scheduled and unscheduled O&M costs, insurance, taxes, rent payments and shipping and shore facilities. The C O P E X values have a high uncertainty owing to the lack of precision and the lack of available published data and have a tendency to increase when equipment ages [56]. C C A P E X denotes the capital expenditures in €; C O P E X t expresses the operating expenditures in year tin €; and E t represents the production of energy in years texpressed in kWh.

3. Case Study in the Alderney Race

3.1. The Alderney Race

Alderney is one of the islands in the English Channel whose surface is almost 10 km 2 and is dependent on the British Crown. It is located approximately 18 km to the west of the Cape of La Hague (France), 37 km to the northwest of Guernsey and 110 km to the south of the English coast. The tidal farm is planned to be located in the orange square illustrated in Figure 5a. The strait in this place has a width of 13 km and a minimum depth of 17 m, while the proposed zones are 30–40 m in depth. The search for a relatively plain zone with the adequate depth is essential for the location of the tidal farm. Moreover, the seabed in this location is composed of large plates of hard flat rocks [57].
Furthermore, the marine currents in the Alderney Race can flow in both directions depending on the tide. This phenomenon is continuously repeated according to the period of the tides. What is more, the current velocity is almost always greater than 1 ms 1 (see Figure 5b), which will be translated into high electricity production for a high percentage of time. The information provided about the current velocities, distance to shore and the seabed compositions allowed us to conclude that this site is a very good candidate for the construction and commercial exploitation of a tidal farm.

3.2. Configuration of the Proposed First Generation Tidal Farm

The proposed tidal farm is composed of 42 TECs of 1.2 MW. The TECs selected have an open rotor configuration whose axis is parallel to the flow (see Figure 6). The nacelle of the TEC can be separated from the structure in order to facilitate the maintenance tasks, but when the nacelle is mounted on the structure, its orientation is fixed, thus making it mandatory for it to have a pitch controllable blade system so as to maximize the energy captured in both current directions. The diameter of the blades is 20 m, and the TEC is fixed to the seabed by gravity, i.e., the structure that supports the TEC is supported on the seabed by means of a substantial mass. Finally, the tidal farm will be composed of a small number of rows, with 11, 10, 11, 10 TECs per row, in order to minimize the shadow effect in the last rows and maximize the total energy captured by the tidal farm.

3.3. Installation Procedures

For the case study developed, the following considerations and installation procedures have been kept in mind for the tidal farm during its expected service life of 20 years [47]:

3.3.1. Previous Considerations

Bearing the assumptions made in Section 2 in mind, the following considerations have been included to develop the installation and the O&M costs:
  • Vessels: We have selected the HF4 vessel designed by MojoMaritime® for this purpose. This vessel is characterized by its dynamic positioning and the fact that it is able to work under extreme conditions. The use of this vessel makes it possible to obtain larger weather windows for the development of the installation and O&M procedures and, consequently, helps substantially reduce the total life-cycle costs. An additional advantage of the vessel selected is that it allows the transportation of all the equipment required to install one TEC or the transportation of three nacelles at the same time (see Figure 7), which helps reduce the maintenance tasks.
  • Base port: The port selected for its operative qualities is the Port of Cherburg in France. The distance from the base port to the location of the tidal farm is approximately 39 km. This distance, although small, cannot be ignored since, owing to the nominal velocity of the vessel selected (14 knots), it would spend 1.5 h on the displacements.
  • Weather windows: Bearing the vessel characteristics and the climatological considerations in mind, we have obtained the percentages of time during which operations can be performed in each season. These are the following: (a) spring: 75% (68 days); (b) summer: 95% (87 days); (c) autumn: 50% (46 days); and (d) winter: 15% (14 days). These percentages show that it is possible to operate around 215 days a year, which is sufficient time to satisfy the installation and maintenance procedures of the tidal farm.

3.3.2. Installation Sequence

After studying the seabed on which the tidal farm will be located, it is necessary to study the zones in which the TECs will be situated in order to find the optimal route for the cables that belong to the TECs and the umbilical cables that join the TECs to the transformation platform, as well as to define the optimal route for the exportation cable. Figure 8 illustrates an example of the installation procedure of the TECs.

3.4. Maintenance Procedures

For the case study developed, the following maintenance plan is considered for the tidal farm during its expected service life:

3.4.1. Blade Cleaning

The colonization of algae, microorganisms and fouling will lead to a reduction in the hydrodynamic efficiency of the rotor surfaces. Although the blades should be protected with copper paint, which acts as a biocide, one of the essential tasks is that of cleaning the blades in order to guarantee the performance of the system. The task of removing the algae, microorganisms, etc., is performed once or twice a year through the use of pressurized water in the installation vessel. It is also necessary to consider the processes of recovering and lowering the nacelle during this procedure.

3.4.2. Light Preventive Maintenance

All the components need a general maintenance and periodical inspection about every two years. We plan light preventive maintenance every two years, and this includes the following operations: changing the grease in the thrust bearing and the gearbox, filling the bottles of compressed air, inspecting all of the components, blade cleaning or checking the paint for defects.

3.4.3. High Preventive Maintenance

This procedure is more complicated than that described above, and it is necessary to perform more complex operations on the nacelle. This procedure is carried out every four years. In this case, the nacelle is moved from the tidal farm to the base port and is then completely disassembled. The following operations are carried out: bearing replacement of the thrust bearing and the gearbox, the replacement of grease in the seal ring, a detailed inspection of all the nacelle components, painting the entire nacelle, etc.

3.4.4. Corrective Maintenance

On a medium size tidal farm, it is supposed that faults may occur in a TEC that were not foreseen in the maintenance plans. The greater or lesser speed of action needed to solve the problem depends on factors such as the availability of the vessel, the particular weather window at that time, the current climate conditions and even the availability of an additional nacelle. It should be noted that, although this will probably occur, it is expected that it will be limited owing to the consideration of PTO with redundancy.

3.5. Annual Energy Produced

Bearing in mind the considerations explained in Section 2.7 as regards the estimation of the current velocity at the depth of the rotor ( V r ), the performance of the power drive train ( η P T O ), the availability factor ( η A F ), the performance of the power export system ( η P E S ) and the tidal farm topology, the AEP obtained for the TECs in each of the four rows of which the tidal farm is composed is illustrated in Figure 9, where the following values have been taken into consideration: Z r = 20 m, Z h = 40 m, C t = 0.716 , A s = 452 m 2 , A r = 314 m 2 , A t = 4000 m 2 (separation between devices of 100 m and total depth of 40 m), D = 20 m, x = 30 m, C P = 0.45 , ρ = 1025 kg/m 3 , η P T O = 0.39 , η A F = 0.97 and η P E S = 0.946 .

4. Numerical Results

The LCC obtained for the case study is summarized in Table 1, while all the numerical values used in the model have been included in Appendix A. Furthermore, Figure 10 depicts a percentage distribution of these costs (CAPEX and OPEX), which is highly illustrative as regards showing the offshore situation of the proposed tidal energy project. Upon analyzing the manufacturing results obtained for the tidal energy farm, which are shown in Figure 11, it will be observed that the highest costs correspond to the most important components in the energy conversion system. Furthermore, the steel used in the manufacturing process of the nacelle also makes a significant contribution to the total costs.
Furthermore, in order to study the economic indicators, the following assumptions have been considered:
  • Although the current inflation values are lower than normal (typical values are between 1% and 3%), in this study, a value of 2% has been considered for the rate of inflation. This term is taken into consideration in the computation of the cash-flows through the use of the following expression [58]:
    k = 1 + k ^ 1 + i 1
    where i denotes the inflation rate and k ^ represents the nominal annual discount rate.
  • In order to attain the cash-flows, the electric tariff considered is 0.09 €/kWh, and this increases by 1.5% every year.
  • All the costs are increased by 1.5% each year.
  • The service life of the tidal farm considered is 20 years, although, as explained previously, if conditions for the continuation of its exploitation are favorable, it could last up to five more years.
Figure 12 illustrates different NPV curves depending on the value of the nominal interest rate k. The greater the values of the parameter k, the greater the risks and the uncertainties of the project. It will be observed that the initial investment is, in all cases recovered, between the 7.5th and 12th year. The results obtained, N P V > 0 , k < I R R = 0.149 and acceptable DPBD values for all cases, indicate that the tidal energy project is economically feasible for all scenarios and that a good profitability is additionally achieved for a renewable energy project in its experimental stage.
Furthermore, with regard to the technical indicators, in the case of a tidal energy project in a non-commercial stage and, therefore, with higher risks and uncertainties (high values of the k parameter), the value obtained for the LCOE indicator is close to 0.15 €/kWh (see Figure 13). This value is quite acceptable for this type of project. In fact, in the case of the current generation of devices that harness energy from the ocean currents, values of between 0.10 €/kWh and 0.20 €/kWh for the LCOE, with core values of between 0.12 €/kWh and 0.15 €/kWh are predicted [59].
Note that, as occurred with wind energy, there is a high margin for improvement if the installed capacity is increased and more efficient technical advances are made and exploitation procedures produced [60,61,62,63]. It is expected that when the installed capacity increases to 1 GW, the LCOE will have values of around 0.09 €/kWh (by that time, the risks and the uncertainties of the project will have been substantially reduced, moving to the smaller k values), thus making it possible to obtain cost values similar to those of the traditional renewable energy sources, whose values are between 0.05 €/kWh and 0.10 €/kWh [59].
In conclusion, after comparing all the economic and technical indicators, along with considering the commercialization of the tidal energy project, we conclude that the proposed tidal energy project is economically and technically feasible for all the case studies.

5. Conclusions

Tidal energy is a promising technological field thanks to its enormous potential for electricity production and its high predictability. Although the tidal energy industry has only just begun to demonstrate full-scale devices and device arrays, the nascent status of these technologies implies that they have not yet obtained a sufficient level of reliability, feasibility and survivability to be marketable when compared to other renewable technologies. The economic assessment of tidal energy technologies is very important as regards achieving a coherent quantification of the costs of these technologies, discovering their economic viability and simultaneously attracting investment in these technologies. It is currently complicated to find studies that focus particularly on the cost assessment and economic feasibility of tidal energy projects. In order to cover this gap, in this research, we propose a methodology for the economic assessment of tidal energy projects. This methodology is based on the LCC of these projects and proposes a cost structure that coincides with the main stages of the tidal energy project during its life-cycle. These costs are: (i) concept and definition costs; (ii) design and development costs; (iii) manufacturing costs; (iv) installation costs; (v) operation and maintenance costs; and (vi) decommissioning costs. Furthermore, these costs are subdivided into sub-cost structures, taking into consideration the main components into which the tidal farm is divided: nacelle, base support and export power system. The proposed model, meanwhile, determines the AEP (and, consequently, the incomes generated) by considering the following characteristics: (i) site current properties (speed, direction, distribution, etc.); (ii) the ability of the device to capture energy; and (iii) its ability as regards energy conversion and energy exportation. All these data are used to determine the feasibility analysis of the project with the use of different economic and technical indicators. This allows the profitability of the project to be attained along with making it possible to perform comparative studies with other renewable energy sources. The proposed methodology has been used to study the viability of a tidal farm in the Alderney Race, where the tidal resource is high. The results obtained after carrying out an analysis of the economic indicators (NPV, IRR, DPBP and LCOE) are the following: (i) the project is economically feasible for all the scenarios studied; (ii) there is good profitability for a tidal renewable energy project in an experimental phase; (iii) bearing in mind that these sorts of projects are still in their infancy, if we are able to advance in the learning curve and the installed capacity is increased (around 1 GW), a relative decrease in the installation and maintenance costs (around 30–40%) can be predicted, with an increase in the ability to capture and export tidal energy, which would lead to an increase in the profitability of the project. Finally, our future research will focus on applying this methodology to new technical solutions for tidal technologies developed by the research group in the field of the automation of emersion/immersion TEC maneuvers in order to quantify its economic viability and to attract investors.

Acknowledgments

This research has been supported by the Spanish Ministerio de Economía y Competitividad under Research Grants DPI2014-53499-R.

Author Contributions

E.S., R.M. and J.A.S. conceived, designed and performed methodology and the case study. Additionally, E.S., R.M. and J.A.S. analyzed the data and participated in writing the paper.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A. Values of the Variables Used in the Case Study

Table A1. Values of the variables in the case study.
Table A1. Values of the variables in the case study.
VariableConceptValueUnits
C M R Market research costs250,000
C C S Cost of certificates and surveys4,000,000
C A I Cost per m 2 of the surfaces of the farm2.0€/m 2
S T E P Surface of the tidal energy farm in m 2 1,000,000 (1000 m width × 1000 m length)m 2
C C D A Cost of conception and design analysis600,000
C P R S Cost of project requirements specifications500,000
C D D Cost of design and development200,000
N M Number of TECs manufactured43
C S D Cost per kg of the carbon steel manufactured for the structure of the nacelle8.0€/kg
m S D Mass of the structure of the nacelle23,830kg
C P T O F Cost per kg of the manufactured carbon steel for the PTO frame4.0€/kg
m P T O F Mass of the PTO frame3600kg
C F Cost per kg of the manufactured fiberglass for the fairing10.0€/kg
m F Mass of the fairing1240kg
P T Power of each TEC1.2MW
C T B Cost per MW of the thrust bearing40,000€/MW
C B S Cost per MW of the brake system2000€/MW
C E G Cost per MW of the electrical generator180,000€/MW
C G Cost per MW of the gearbox35,000€/MW
C H S S Cost per MW of the high-speed shaft3000€/MW
C Y S Cost per kg of the yaw system12€/kg
m Y S Mass of the yaw system60kg
C C O S Cost per MW of the cooling system15,000€/MW
C P O S Cost per MW of the pressure oil system15,000€/MW
C C M S Cost per MW of the condition monitoring system110,000€/MW
C S W T Cost per kg of the protection and connection switches12€/kg
m S W T Mass of the protection and connection switches124kg
C C T S Cost per kg of the control system12€/kg
m C T S Mass of the control system30kg
C B I S Cost per kg of the bilge system12€/kg
m B I S Mass of the bilge system260kg
C A C S Cost per kg of the compressed air system12€/kg
m A C S Mass of the compressed air system110kg
C C B Cost per kg of the circuit board12€/kg
m C B Mass of the circuit board90kg
C A E Cost per kg of the added elements3€/kg
m A E Mass of the added elements1000kg
N B Number of blades per TEC3
R R Radius of the rotor10m
C B Cost per m of each blade40€/m
C P S Cost per m of the pitch system500€/m
C C R Cost per m of the core of the rotor1000€/m
C L S S Cost per m of the low-speed shaft500€/kg
N I Number of TECs installed42
C T B S Cost per kg of the base support of the TEC structure3€/kg
m T B S Mass of the base support of the TEC structure87,200kg
C T T S Cost per kg of the transition structure of the TEC3€/kg
m T T S Mass of the transition structure of the TEC39,500kg
C T V C Cost per kg of the vertical column of the TEC3€/kg
m T V C Mass of the vertical column of the TEC29,800kg
N C B Number of concrete ballast per TEC2
C E C Cost per kg of the elaborated concrete of the ballast0.2€/kg
m E C Mass of the concrete of the ballast113,200kg
N B G Number of special concrete bags per TEC4
C B G Cost per kg of the special concrete bags0.3€/kg
m B G Mass of the special concrete bags6300kg
C P S W Cost per MW of the protection switch25,000€/MW
C S C Cost per kg of the submarine connector25€/kg
m S C Mass of the submarine connector300kg
C B S C Cost per kg of the submarine connector installed in the base of the TEC12€/kg
m B S C Mass of the submarine connector installed in the base of the TEC300kg
C I W Cost per kg of the internal wiring12€/kg
m I W Mass of the internal wiring150kg
C C B X Cost per kg of the connection box12€/kg
m C B X Mass of the connection box150kg
C U C Cost per m of the umbilical cables250€/m
L U C Length of the umbilical cables11,350m
C R Cost per MW of the rectifiers100,000€/MW
C I Cost per MW of the inverters100,000€/MW
C E B Cost per MW of the electrical boxes20,000€/MW
N T F Number of transformers per TEC4
C T F Cost per MW of the transformers40,000€/MW
m T P Mass of the transformation platform4,000,000kg
C T P Cost per kg of the transformation platform3€/kg
N S E C Number of submarine exportation cables2
C S E C Cost per m of the submarine exportation cables500€/m
L S E C Length of the submarine exportation cables11,000m
C G E C Cost per m of the ground exportation cables150€/m
L G E C Length of the ground exportation cables5000m
C V I P C Cost of leasing the vessels (installation of the transformation platform)2,900,000
C T L I P C Cost of technical labor (installation of the transformation platform)300,000
C P O I P C Cost of operations in the port (installation of the transformation platform)500,000
C V I S C Cost of leasing the vessels (installation of the submarine cables)3,150,000
C T L I S C Cost of technical labor (installation of the submarine cables)150,000
C P O I S C Cost of operations in the port (installation of the submarine cables)300,000
C V I G E C Cost of leasing the vessels (installation of the ground exportation cable)3,150,000
C T L I G E C Cost of technical labor (installation of the ground exportation cable)150,000
C P O I G E C Cost of operations in the port (installation of the ground exportation cable)300,000
C V I T E C Cost of leasing the vessels (installation of the TECs)14,700,000
C T L I T E C Cost of technical labor (installation of the TECs)700,000
C P O I T E C Cost of operations in the port (installation of the TECs)1,400,000
C T B C Transport costs (blade cleaning)81,120
C L B C Labor costs (blade cleaning)4080
C P L B C Cost incurred as result of production losses (blade cleaning)1256.4
C T L P M Transport costs (light preventive maintenance)533,512.45
C L L P M Labor costs (light preventive maintenance)53,659.63
C M L P M Material costs (light preventive maintenance)142,293.45
C P L L P M Cost incurred as result of production losses (light preventive maintenance)32,394.14
C T H P M Transport costs (high preventive maintenance)777,458.31
C L H P M Labor costs (high preventive maintenance)39,454.02
C M H P M Material costs (high preventive maintenance)22,1784.22
C P L H P M Cost incurred as result of production losses (high preventive maintenance)25,669.26
C T C M Transport costs (corrective maintenance)197,122.85
C L C M Labor costs (corrective maintenance)7068.15
C M C M Material costs (corrective maintenance)0
C P L C M Cost incurred as result of production losses (corrective maintenance)10,918.47

References

  1. Fernández, L. A diversified portfolio: Joint management of non-renewable and renewable resources offshore. Resour. Energy Econ. 2005, 27, 65–82. [Google Scholar] [CrossRef]
  2. Considine, T.J.; Heo, E. Price and inventory dynamics in petroleum product markets. Energy Econ. 2000, 22, 527–548. [Google Scholar] [CrossRef]
  3. Castro-Santos, L.; Prado, G.; Díaz-Casas, V. Methodology to study the life cycle cost of floating offshore wind farms. In Proceedings of the 10th Deep Sea Wind R&D Conference, Trondheim, Norway, 24–25 January 2013. [Google Scholar]
  4. Directive 2009/28/EC of the European Parliament and of the Council of 23 April 2009 on the promotion of the use of energy from renewable sources and amending and subsequently repealing directives 2001/77/EC and 2003/30/EC. Official Journal of the European Union, 5 June 2009; 16–60.
  5. Orlandini, V.; Pierobon, L.; Schløer, S.; De Pascale, A. Dynamic performance of a novel offshore power system integrated with a wind farm. Energy 2016, 109, 236–247. [Google Scholar] [CrossRef] [Green Version]
  6. Bacelli, G.; Coe, R.G.; Patterson, D.; Wilson, D. System Identification of a Heaving Point Absorber: Design of Experiment and Device Modeling. Energies 2017, 10, 472. [Google Scholar] [CrossRef]
  7. Luo, Y.; Liu, X.; Wang, Z.; Xiao, Y.; He, C.; Zhang, Y. Optimization of the Runner for Extremely Low Head Bidirectional Tidal Bulb Turbine. Energies 2017, 10, 787. [Google Scholar] [CrossRef]
  8. Younesian, D.; Alam, M.-R. Multi-stable mechanisms for high-efficiency and broadband ocean wave energy harvesting. Appl. Energy 2017, 197, 292–302. [Google Scholar] [CrossRef]
  9. Stegman, A.; de Andres, A.; Jeffrey, H.; Johanning, L.; Bradley, S. Exploring Marine Energy Potential in the UK Using a Whole Systems Modelling Approach. Energies 2017, 10, 1251. [Google Scholar] [CrossRef]
  10. Giorgi, S.; Ringwood, J.V. Can Tidal Current Energy Provide Base Load? Energies 2013, 6, 2840–2858. [Google Scholar] [CrossRef]
  11. MacGillivray, A.; Jeffrey, H.; Hanmer, C.; Magagna, D.; Raventos, A.; Badcock-Broe, A. Ocean Energy Technology: Gaps and Barriers; Strategic Initiative for Ocean Energy (SI Ocean): Brussels, Belgium, 2013. [Google Scholar]
  12. Badcock-Broe, A.; Flynn, R.; George, S.; Gruet, R.; Medic, N. Wave and Tidal Energy Market Deployment Strategy for Europe; Strategic Initiative for Ocean Energy (SI Ocean): Brussels, Belgium, 2014. [Google Scholar]
  13. Mofor, L.; Goldsmith, J.; Jones, F. Ocean Energy. Technology Readiness, Patents, Deployment Status and Outlook; International Renewable Energy Agency (IRENA): Abu Dhabi, UAE, 2014. [Google Scholar]
  14. Mofor, L.; Goldsmith, J.; Jones, F. Annual Report-2014. Implementing Agreement on Ocean Energy Systems; Ocean Energy Systems, International Energy Agency OES-IEA: Lisboa, Portugal, 2014. [Google Scholar]
  15. Somolinos, J.A.; López, A.; Núñez, L.R.; Morales, R. Dynamic model and experimental validation for the control of emersion maneuvers of devices for marine currents harnessing. Renew. Energy 2017, 107, 333–345. [Google Scholar] [CrossRef]
  16. Morris, C.E.; O’Doherty, D.M.; O’Doherty, T.; Mason-Jones, A. Kinetic energy extraction of a tidal stream turbine and its sensitivity to structural stiffness attenuation. Renew. Energy 2016, 88, 30–39. [Google Scholar] [CrossRef]
  17. O’Connor, M.; Lewis, T.; Dalton, G. Operational expenditure costs for wave energy projects and impacts on financial returns. Renew. Energy 2013, 50, 1119–1131. [Google Scholar] [CrossRef]
  18. Mueller, M.; Wallace, R. Enabling science and technology for marine renewable energy. Energy Policy 2008, 36, 4376–4382. [Google Scholar] [CrossRef]
  19. Segura, E.; Morales, R.; Somolinos, J.A.; López, A. Techno-economic challenges of tidal energy conversion systems: Current status and trends. Renew. Sustain. Energy Rev. 2017, 77, 536–550. [Google Scholar] [CrossRef]
  20. Trapero, J.R.; Horcajada, L.; Linares, J.J.; Lobato, J. Is microbial fuel cell technology ready? An economic answer towards industrial commercialization. Appl. Energy 2017, 185, 698–707. [Google Scholar] [CrossRef]
  21. Castro-Santos, L.; Díaz-Casas, V. Life-cycle cost analysis of floating offshore wind farms. Renew. Energy 2014, 16, 41–48. [Google Scholar]
  22. Castro-Santos, L.; Díaz-Casas, V. Sensitivity analysis of floating offshore wind farms. Energy Convers. Manag. 2015, 101, 271–277. [Google Scholar] [CrossRef]
  23. Magagna, D.; Uihlein, A. Ocean energy development in Europe: Current status and future perspectives. Int. J. Mar. Energy 2015, 11, 84–104. [Google Scholar] [CrossRef]
  24. Kleyner, A.; Sandborn, P. Minimizing life cycle cost by managing product reliability via validation plan and warranty return cost. Int. J. Prod. Econ. 2008, 112, 796–807. [Google Scholar] [CrossRef]
  25. Wee, H.; Lee, M.; Yu, J.C.P. Optimal replenishment policy for a deteriorating green product: Life cycle costing analysis. Int. J. Prod. Econ. 2011, 133, 603–611. [Google Scholar] [CrossRef]
  26. Castro-Santos, L.; Filgueira-Vizoso, A.; Carral-Couce, L.; Fragela-Formoso, J.A. Economic feasibility of floating offshore wind farms. Energy 2016, 112, 868–883. [Google Scholar] [CrossRef]
  27. Radfar, S.; Panahi, R.; Javaherchi, T.; Filim, S.; Mazyaki, A.R. A comprehensive insight into tidal stream energy farms in Iran. Renew. Sustain. Energy Rev. 2017, 79, 323–338. [Google Scholar] [CrossRef]
  28. Neary, V.S.; Lawson, M.; Previsic, M.; Copping, A.; Hallett, K.C.; LaBonte, A.; Rieks, J.; Murray, D. Methodology for design and economic analysis of marine energy conversion (MEC) technologies. In Proceedings of the 2nd Marine Energy Technology Symposium (METS2014), Seattle, WA, USA, 15–18 April 2014. [Google Scholar]
  29. Maslov, N.; Charpentier, J.-F.; Claramunt, C. A modelling approach for a cost-based evaluation of the energy produced by a marine energy farm. Int. J. Mar. Energy 2015, 9, 1–19. [Google Scholar] [CrossRef]
  30. National Standards Authority of Ireland. Dependability Management Part 3-3: Application Guide—Life Cycle Costing; IEC 60300-3-3:2004; National Standards Authority of Ireland: Ireland, UK, 2004. [Google Scholar]
  31. Barringer, H.P. A Life Cycle Cost Summary. In Proceedings of the International Conference of Maintenance Societies (ICOMS 2003), Perth, Australia, 20–23 May 2003; pp. 1–10. [Google Scholar]
  32. Fabrycky, W.; Blanchard, B. A Life Cycle Cost Summary. In Life-Cycle Cost and Economic Analysis; Prentice-Hall: Upper Saddle River, NJ, USA, 1991. [Google Scholar]
  33. Dhillon, B.S. Life-Cycle Costing for Engineers; CRC Press, Taylor and Francis Group: Boca Raton, FL, USA, 2010. [Google Scholar]
  34. Vail Farr, J. Systems Life Cycle Costing—Economic Analysis, Estimation and Management; CRC Press, Taylor and Francis Group: Boca Raton, FL, USA, 2011. [Google Scholar]
  35. Fingersh, L.; Hand, M.; Laxson, A. Wind Turbine Design Cost and Scaling Model; NREL/TP-500-40566; National Renewable Energy Laboratory: Golden, CO, USA, 2006.
  36. Ricci, P.; López, J.; Villate, J.L.; Stallard, T. Deliverable D7.1. Summary of Attributes of Cost Models Used by Different Stakeholders; Commission of the European Communities: Brussels, Belgium, 2009. [Google Scholar]
  37. Acorn Bearings Web Page. 2017. Available online: www.acornbearings.co.uk/price-lists/skf/page/12 (accessed on 15 August 2017).
  38. BVG Associates. A Guide to an Offshore Wind Farm; The Crown Estate: London, UK, 2010. [Google Scholar]
  39. Astariz, S.; Iglesias, G. The economics of wave energy: A review. Renew. Sustain. Energy Rev. 2015, 45, 397–408. [Google Scholar] [CrossRef]
  40. Lyding, P.; Faulstich, S.; Hahn, B.; Callies, D. Offshore–WMEP: Monitoring offshore wind energy use European Offshore Wind. In Proceedings of the European Offshore Wind 2009 Conference & Exhibition, Stockholm, Sweden, 14–16 September 2009. [Google Scholar]
  41. Abdulla, K.; Skelton, J.; Doherty, K.; O’Kane, P.; Doherty, R.; Bryans, G. Statistical Availability Analysis of Wave Energy Converters. In Proceedings of the The Twenty-first International Offshore and Polar Engineering Conference, Maui, HI, USA, 19–24 June 2011; pp. 572–578. [Google Scholar]
  42. Brook, J. Wave Energy Conversion; Elsevier Ltd: Oxford, UK, 2003. [Google Scholar]
  43. O&M Aspects of the 500 MW Offshore Wind Farm at NL7. Available online: https://www.ecn.nl/fileadmin/ecn/units/wind/docs/dowec/10090_001.pdf (accessed on 15 August 2017).
  44. Obdam, T.; Braam, H.; Van De Pieterman, R.; Rademakers, L. O&M Cost Estimation & Feedback of Operational Data, Wind Farm—Technical Regulations, Potential Estimation and Siting Assessment; InTech: Vienna, Austria, 2011. [Google Scholar]
  45. Carbon Trust. Oscillating water column wave energy converter evaluation report. In The Carbon Trust; ARuP: London, UK, 2005. [Google Scholar]
  46. The Irish Wind Energy Association (IWEA) Web Page. Available online: www.iwea.com/index.cfm/page/planning_regulationsandadminis (accessed on 15 August 2017).
  47. Det Norske Veritas (DNV). DNV–OS–J101 Design of Offshore Wind Turbine Structures; Det Norske Veritas: Hovik, Norway, 2010; pp. 1–142. [Google Scholar]
  48. ABPmer, Atlas for UK Marine Renewables. Available online: http://www.renewables-atlas.info/ (accessed on 15 August 2017).
  49. Winter, A. Speed Regulated Operation for Tidal Turbines with Fixed Pitch Rotors. In Proceedings of the IEEE Oceans Conference, Waikoloa, HI, USA, 19–22 September 2011. [Google Scholar]
  50. Rathmann, O.; Frandsen, S.; Barthelmie, R. Wake modeling for intermediate and large wind farms. In Proceedings of the EWEC 2007 Wind Energy Conference and Exhibition, Milan, Italy, 7–10 May 2007. Paper BL3.199. [Google Scholar]
  51. Sun, X.; Chick, J.P.; Bryden, I.G. Laboratory-scale simulation of energy extraction from tidal currents. Renew. Energy 2008, 33, 1267–1274. [Google Scholar] [CrossRef]
  52. Short, W.; Packey, D.; Holt, T. A Manual for the Economic Evaluation of Energy Efficiency and Renewable Energy Technologies; NREL/TP-462-5173; National Renewable Energy Laboratory: Golden, CO, USA, 1995.
  53. Ouyang, X.; Lin, B. Levelized Cost of Electricity (LCOE) of Renewable energies and required subsidies in China. Energy Policy 2014, 70, 64–73. [Google Scholar] [CrossRef]
  54. Castro-Santos, L.; Prado-García, G.; Estanqueiro, A.; Justino, P.A.P.S. The Levelized Cost of Energy (LCOE) of Wave Energy Usig GIS Based Analysis: The case study of Portugal. Int. J. Electr. Power Energy Syst. 2015, 65, 21–25. [Google Scholar] [CrossRef]
  55. Davey, T.; Harrison, G. Procedures for Economic Evaluation; Equitable Testing and Evaluation of Marine Energy Extraction Devices Deliverable D7.2.1; Commission of the European Communities: Brussels, Belgium, 2009. [Google Scholar]
  56. Levitt, A.; Kempton, W.; Smith, A.P.; Musial, W.; Firestone, J. Pricing offshore wind power. Energy Policy 2011, 39, 6408–6421. [Google Scholar] [CrossRef]
  57. Sánchez, G. Diseño de un Dispositivo Para el Aprovechamiento de la Energía de las Corrientes (DAEC) y su Integración en un Parque Marino. Master’s Thesis, Escuela Técnica Superior de Ingenieros Navales Universidad Politécnica de Madrid (ETSIN-UPM), Madrid, Spain, 2014. [Google Scholar]
  58. Davis Langdon Management Consulting. Towards a Common European Methodology for Life Cycle Costing (LCC)—Literature Review; Davis Langdon Management Consulting: London, UK, 2007. [Google Scholar]
  59. Fraenkel, P. Marine Current Turbines: Pioneering the Development of Marine Kinetic Energy Converters. Proc. Inst. Mech. Eng. Part A J. Power Energy 2007, 221, 159–169. [Google Scholar] [CrossRef]
  60. López, A.; Núñez, L.R.; Somolinos, J.A. Modelado energético de convertidores primarios para el aprovechamiento de las energías renovables marinas. Rev. Iberoam. Autom. Inform. Ind. 2011, 11, 224–235. [Google Scholar] [CrossRef]
  61. Morales, R.; Segura, E.; Somolinos, J.A.; Núñez, L.R.; Sira-Ramírez, H. Online signal filtering based on the algebraic method and its experimental validation. Mech. Syst. Signal Proc. 2016, 66, 374–387. [Google Scholar] [CrossRef]
  62. Somolinos, J.A.; López, A.; Portilla, M.P.; Morales, R. Dynamic model and control of a new underwater three-degree-of-freedom tidal energy converter. Math. Probl. Eng. 2015, 2015, 948048. [Google Scholar] [CrossRef]
  63. Morales, R.; Fernández, L.; Segura, E.; Somolinos, J.A. Maintenance Maneuver Automation for an Adapted Cylindrical Shape TEC. Energies 2016, 9, 746. [Google Scholar] [CrossRef]
Figure 1. Cost and sub-costs for the proposed methodology. LCC, life-cycle costs; TEC, tidal energy converter.
Figure 1. Cost and sub-costs for the proposed methodology. LCC, life-cycle costs; TEC, tidal energy converter.
Energies 10 01806 g001
Figure 2. Distribution of the main elements within the nacelle.
Figure 2. Distribution of the main elements within the nacelle.
Energies 10 01806 g002
Figure 3. Supporting TEC structure.
Figure 3. Supporting TEC structure.
Energies 10 01806 g003
Figure 4. Summary of the computation of the annual energy produced (AEP).
Figure 4. Summary of the computation of the annual energy produced (AEP).
Energies 10 01806 g004
Figure 5. Alderney Race: (a) delimited zone for the tidal farm; (b) current velocity in the Alderney Race.
Figure 5. Alderney Race: (a) delimited zone for the tidal farm; (b) current velocity in the Alderney Race.
Energies 10 01806 g005
Figure 6. (a) Proposed TEC; (b) view of proposed tidal farm.
Figure 6. (a) Proposed TEC; (b) view of proposed tidal farm.
Energies 10 01806 g006
Figure 7. (a) HF4 installation vessel transporting the equipment needed to install the TEC; (b) HF4 installation vessel transporting nacelles.
Figure 7. (a) HF4 installation vessel transporting the equipment needed to install the TEC; (b) HF4 installation vessel transporting nacelles.
Energies 10 01806 g007
Figure 8. Installation procedure: (a) controlled descent of the base structure; (b) support structure on the seabed and deposited guide wires; (c) controlled descent of the nacelle; (d) removing the tool for nacelle installation and unstressing the guide wires.
Figure 8. Installation procedure: (a) controlled descent of the base structure; (b) support structure on the seabed and deposited guide wires; (c) controlled descent of the nacelle; (d) removing the tool for nacelle installation and unstressing the guide wires.
Energies 10 01806 g008
Figure 9. Energy generation of a TEC placed in the different rows of the tidal farm.
Figure 9. Energy generation of a TEC placed in the different rows of the tidal farm.
Energies 10 01806 g009
Figure 10. Cost distribution of the tidal farm: (a) CAPEX costs; (b) OPEX costs.
Figure 10. Cost distribution of the tidal farm: (a) CAPEX costs; (b) OPEX costs.
Energies 10 01806 g010
Figure 11. Manufacturing costs of the nacelle.
Figure 11. Manufacturing costs of the nacelle.
Energies 10 01806 g011
Figure 12. NPV values for different values of the rate of return in the interval between k = 3% and k = 11% and for different years of operation.
Figure 12. NPV values for different values of the rate of return in the interval between k = 3% and k = 11% and for different years of operation.
Energies 10 01806 g012
Figure 13. LCOE values for different values of the rate of return in the interval between k = 3% and k = 11%.
Figure 13. LCOE values for different values of the rate of return in the interval between k = 3% and k = 11%.
Energies 10 01806 g013
Table 1. Summary of the cost of the tidal farm in the Alderney Race.
Table 1. Summary of the cost of the tidal farm in the Alderney Race.
Cost Category Total Value (€)
Concept and Definition Costs ( C 1 ) 7,350,000
Design and Development Costs ( C 2 ) 200,000
Manufacturing Costs ( C 3 ) 103,613,935.88
Nacelle 39,563,655.88
Supporting TEC Structure 21,938,280
Export Power System 42,112,000
Installation Costs ( C 4 ) 27,700
Transformation Platform and Converters 3700
Submarine and Ground Exportation Cables 7200
TECs 16,800
O&M Costs ( C 5 ) 4,905,070.07
Material CostsTransport CostsLabor CostsProduction Losses Costs
Blade Cleaning081,12040801256.4086,456.4
Light Preventive Maintenance142,293.45533,512.4553,659.6332,394.14761,859.67
High Preventive Maintenance221,784.22777,458.3139,454.0225,669.261,064,365.81
Corrective Maintenance0197,122.857068.1510,918.47215,109.47
Insurance Costs and Fixed Expenses 2,777,278.72
Decommissioning Costs ( C 6 ) 0

Share and Cite

MDPI and ACS Style

Segura, E.; Morales, R.; Somolinos, J.A. Cost Assessment Methodology and Economic Viability of Tidal Energy Projects. Energies 2017, 10, 1806. https://doi.org/10.3390/en10111806

AMA Style

Segura E, Morales R, Somolinos JA. Cost Assessment Methodology and Economic Viability of Tidal Energy Projects. Energies. 2017; 10(11):1806. https://doi.org/10.3390/en10111806

Chicago/Turabian Style

Segura, Eva, Rafael Morales, and José A. Somolinos. 2017. "Cost Assessment Methodology and Economic Viability of Tidal Energy Projects" Energies 10, no. 11: 1806. https://doi.org/10.3390/en10111806

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop