Next Article in Journal
The Formation of Biofilm and Bacteriology in Otitis Media with Effusion in Children: A Prospective Cross-Sectional Study
Next Article in Special Issue
Examining the Relationship between Mindfulness, Personality, and National Culture for Construction Safety
Previous Article in Journal
Trade-Off and Projecting Effects of Land Use Change on Ecosystem Services under Different Policies Scenarios: A Case Study in Central China
Previous Article in Special Issue
Influencing Factors, Mechanism and Prevention of Construction Workers’ Unsafe Behaviors: A Systematic Literature Review
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Barriers of Occupational Safety Implementation in Infrastructure Projects: Gaza Strip Case

by
Yazan Issa Abu Aisheh
1,
Bassam A. Tayeh
2,*,
Wesam Salah Alaloul
3 and
Amro Fareed Jouda
2
1
Civil Engineering Department, Middle East University, Amman 11831, Jordan
2
Civil Engineering Department, Faculty of Engineering, Islamic University of Gaza, Gaza PO Box 108, Palestine
3
Department of Civil and Environmental Engineering, Universiti Teknologi PETRONAS, Bandar Seri Iskandar, Tronoh 32610, Malaysia
*
Author to whom correspondence should be addressed.
Int. J. Environ. Res. Public Health 2021, 18(7), 3553; https://doi.org/10.3390/ijerph18073553
Submission received: 16 December 2020 / Revised: 26 January 2021 / Accepted: 29 January 2021 / Published: 29 March 2021
(This article belongs to the Special Issue Occupational Safety and Risks in Construction)

Abstract

:
Infrastructure projects are the foundation for essential public services and have an influential position in societal development. Although the role of infrastructure projects is substantial, they can involve complexities and safety issues that lead to an unsafe environment, and which impacts the project key stakeholders. Therefore, this study aimed to evaluate the barriers to implementing occupational safety in infrastructure projects in the Gaza Strip, which cause serious threats and reduce project performance. To evaluate the barriers, 39 items were highlighted and modified as per the construction context and environment, and which later were distributed in the form of a questionnaire, to get feedback from consultants and contractors. The analysis shows that in the safety policy barriers group, consultants and contractors both ranked the item “a contractor committed to an occupational safety program is not rewarded” first. In the management barriers group, consultants and contractors both ranked the item “safety engineer does not have significant powers, such as stopping work when needed” in the first place. In the behavior and culture barriers group, consultants and contractors both ranked the item “workers who are not committed to occupational safety are not excluded” in the first place. Overall, both consultants and contractors shared the same viewpoint in classifying the barriers in the working environment. The outcome of this study is beneficial for Palestinian construction industry policymakers, so they can monitor the highlighted barriers in on-going infrastructure projects and can modify the safety guidelines accordingly.

1. Introduction

The construction industry contributes a valuable amount to the economy of any country, however, it is still badly affected by several issues such as cost overrun [1,2], time overrun [3,4,5], price fluctuation due to inflation [6,7,8], and most importantly due to poor safety performance [9]. Despite these severe issues, a project gets completed, but is not declared successful because the project failed to achieve the projects’ objectives [10,11]. Neglecting safety measures can result both in physical damage to workers and financial losses, which can increase the direct and indirect cost of the project [12,13]. As per the International Labour Organization (ILO), 2.3 million workers die each year worldwide due to occupational accident, impacting 4% of world GDP [14]. To successfully implement safety guidelines within a company, an equal effort is required by all the stakeholders of the construction industry [15]. In developed countries, considerable attention is provided to health and safety [16]. Whereas, in developing or underdeveloped countries the condition varies as the consideration of health and safety is far behind in its implementation [17,18,19]. The scenario can be different if collaborative work for occupational health and safety is performed between developed and developing countries, where sharing of information is done to bring major reforms [20,21].
One of the most important functions of infrastructure projects is to develop public services and improve the daily situation, necessary to support economic and social activity. In Palestine, infrastructure projects differ from the rest of the world due to the scarcity of financial resources and the density of population distribution. Infrastructure projects require continuous management and experience of the long-term planning and development of projects in line with plans. Infrastructure projects require substantial financial investment, time commitment, and significant human and material resources. Infrastructure development in Palestine is affected by many obstacles and problems that hinder current projects and plans, and the implementation of basic and public services [22]. One of the biggest challenges is the Israeli occupation, which controls the arrival of basic construction materials (cement, steel, and aggregates) to the Gaza Strip through long-term coordination mechanisms, requiring complex and time-consuming processes, which hinder current and future infrastructure projects [23]. Infrastructure projects in the Gaza Strip have been severely affected by lack of construction materials, in addition to the destruction incurred during military operations.
The Gaza Strip is the south western part of Palestine, which is located on the south-eastern coast of the Mediterranean Sea. The area of the Gaza Strip is about 365 km2, with an approximate length of 45 km, and a width between 6 and 12 km. It is confined between the Mediterranean Sea in the west, Egypt in the south, and occupied Palestine since 1948 in the east and the north, as shown in Figure 1. The Gaza Strip is located between longitudes 34°2″ and 34°25″ E, and latitudes 31°16″ and 31°45″ N [24].
The lack of planning and poor management in the selection and implementation of infrastructure projects suitable to current and future conditions are the problems that the Gaza Strip suffers, as there are no clear and effective criteria in determining the priorities for infrastructure projects. No priorities and long-term plans are explained for the stages of implementation of infrastructure projects [22]. According to the last report of the Palestinian Contractors Union [25], there were 294 classified contractors in the Gaza Strip in 2019. The construction activities are divided into five categories (roads, buildings, electromechanical, water/sewage, public works, and maintenance). Each one of these categories has five classes (from one to five). The contractor can have more than one classification in different categories of the above-mentioned five categories. The contractors of the first, second, and third classes for infrastructure works totaled 122 in the Gaza Strip in 2019.
The Gaza Strip suffers from a fragile infrastructure, however, there is growing interest in infrastructure development in various large projects, ranging from road projects, sewage plants, water desalination, electricity and others. This development should be accompanied by parallel attention to the requirements of occupational safety, especially since infrastructure projects have special characteristics among construction projects, as they relate to the public, whether in the stages of construction, maintenance, or demolition. Keeping to the discussion in consideration, a research question was established: “What are the barriers that hinder the occupational safety implementation in infrastructure projects in Gaza Strip”? Therefore, this research aims to assess the barriers to implementing occupational safety in infrastructure projects in the Gaza Strip from the consultants’ and contractors’ point of view, and with the set hypothesis: “The barriers affect the implementation of safety practices in the infrastructure sector in the Gaza Strip”.

2. Literature Review

In infrastructure projects, factors and conditions surrounding construction sites vary significantly compared with other projects; the workers must perform dangerous jobs that require high physical and mental strength for long periods. In addition to unsanitary conditions, unavailable services, messy work environments, and exposure to bad weather conditions, the impression of infrastructure construction sites is that they are disorganized and dangerous [26]. Delivering projects on time requires effective planning of occupational safety, without exceeding costs and without significant risks or harm to the safety of workers on the project site. These are not easy targets, because construction sites are complex and crowded, and because of the constant pressures of time and constant changes in the work environment [27,28]. An accident at work is an unexpected event caused by an external reason, resulting in injury or death, which takes place in connection with work. In general, lack of knowledge, training, poor supervision, and the lack of safe means to carry out activities are the main causes of work accidents. In addition to negligence, complete recklessness, and indifference, the construction industry is inherently short-term, complex, and diverse, and lacks internal and external oversight. All these factors have an impact on the performance of occupational safety within the workplace [29]. In construction, unsafe behavior is the most important factor in the occurrence of construction accidents, which leads directly from the fact that a safety culture does not exist on the worksite [30]. Accidents are associated with a variety of reasons, and deviation from the essence of the work may be the main cause [31]. Masayuki [32] recognized one of the methods for inculcating a safety culture in the workplace is by giving awards to the workers. Active communication and information transfer between management and workers have been suggested to produce better safety standards, and improve safety policies [33]. Discussing occupational safety in frequent meetings raises the level of safety in planning, which leads to the significant development of occupational safety; while reviewing occupational safety during progress meetings makes predicting problems easy and specific [34]. Wong and Gray [35], Tam and Zeng [36], and Ghani and Baki [37] listed various responsibilities and specifications that safety engineers should undertake to ensure the occupational safety of a project, such as: the number of safety engineers should be appropriate to the volume of project, and the safety engineer should have powers to stop all events in the projects in case of hazards happening.
There are four categories of barrier affecting safety performance in infrastructure projects that should be investigated; these are: (1) management, (2) safety culture, (3) behavior, and (4) awareness [38]. Safety performance can be influenced by factors including the top management’s and project managers’ poor safety awareness, poor safety resources, absence of training, and irresponsible operations [36]. Safety management can be regarded as the totality of practices implemented by the management of an organization to control hazards, so that occupational accidents and injuries are ultimately prevented, i.e., different strategies and activities focusing on the safety of the workers [39]. Safety management, thus, involves a wide range of both formal and informal practices, focusing on standardized activities, such as risk assessment on the one hand, and managers actively showing a commitment to safety on the other [40]. Safety management relates to the actual practices, roles, and functions associated with remaining safe [41]. The application of effective occupational safety management in the workplace makes the existing system safer and less susceptible to accidents and injuries. Most of the research conducted on occupational safety systems has shown a clear increase in injury rates due to insufficient occupational safety regulations in the workplace [42,43].
The contractor should perform an internal audit of their safety management program, and take advantage of past safety experience to periodically update safety plans [44]. The selection of contractors bidding for construction projects should be based on occupational safety considerations, including an assessment of the contractor’s previous occupational safety performance, current programs and practices, and the contractor’s attitude towards safety [45,46]. The safety management needs to be aware of an accident and record it, to establish a better course of action for future accident or incident prevention. If the accident is not reported or detailed, it is impossible to identify the causes [47].
The negligence of workers is a cause of workplace accidents, but is not the only reason, as failure to control occupational safety within the project is a shared responsibility with management. It is assumed that occupational safety systems have a financial allocation to the fullest extent possible, and that the management is fully aware of the cost involved, measure the level of accidents, and improve the safety performance of the project, through reduced risks and the number of injuries [48].
In Kuwait, construction company management believed that occupational safety procedures and requirements increase the cost of construction. However, it was also found that the costs of accidents and safety measures were not considered in the contractor’s offer, and only the cost of insurance of the project was considered, among all elements of occupational safety [49]. Improving the quality of occupational safety needs the adoption of an effective and complete safety approach at the management level; this approach should be clear, through careful consideration of each serious activity identified at the design stage or subsequent stages, in addition to holding training programs on occupational safety and health for old and new workers, where the training is based on the correct decisions in dealing with accidents associated with their workplace [50]. Infrastructure and construction risks generally coincide with many things, but infrastructure is affected by many restrictions, requirements, and safety aspects that are generally not fully controlled, such as in terms of infrastructure, or occupational safety related to the care of “third party” public security. These restrictions may be related to political or social matters [51]. Knowing and evaluating past incidents and preparing their records is critical for management that wants to minimize future incidents in their company. Writing reports, directing them to the competent department, and reviewing them to take the correct action has a significant role in minimizing accidents, in addition to a follow-up program for evaluating the effectiveness of the procedures.
Safety climate is a summary concept describing the safety ethic in a company or workplace which is reflected in workers “beliefs about safety and is supposed to forecast the way workers behave concerning safety in that workplace” [50]. The study conducted by Dedobbeleer and Béland [52] on construction workers, suggested that the management’s commitment to safety, and workers’ involvement in safety were the two most important factors impacting the safety climate. In a study on road workers, two separate sets of principles were found for workers and supervisors, both of which include attitudes towards occupational safety, and supplied variables in labor requirements and occupational safety as part of the work [53].
Important requirements include alerting new workers to potential hazards during their work and making an effort to comply with safety regulations, including wearing personal protective equipment (such as safety glasses and hard hats), placing barricades, and deploying warning signs around drilling places [54]. The training of administrative staff, with appropriate awareness and competence for the requirements of occupational safety, leads to obtaining an effective program and plan for the performance of occupational safety and its implementation, especially to senior management because they are drawing the outlines of a positive occupational safety culture, and applying it to the work and workers as required [55].
Implementation of occupational safety requirements on the worksite needs a true safety culture and appropriate feedback from workers. Activating occupational safety training and guidance programs is essential to improving the workers’ safety culture and attitudes towards safety, in addition to educating workers about safety rules and procedures, and training workers on safe working methods. Well-trained workers are allowed to carry out dangerous and important work. Workers’ participation in occupational safety programs should be mandatory, as they are exposed to daily work hazards [56].
Pratt and Fosbroke [57] emphasized that the best technique to develop occupational safety in the workplace is to change the behavior and performance of individuals with the requirements of occupational safety. The development of occupational safety is reactive and behavior-based, and is an effective tool for increasing occupational safety in the workplace; this includes allowing workers to monitor each other to support the development of safety habits through discussion and analysis tools. This method might be considered to have a limited impact, due to the many variations that occur daily in the workplace, so that the proposed improvements are not feasible, this therefore may require the increased behavioral awareness of supervisors, to be more aware of existing physical risks [58].
A main cause of accidents is the poor safety performance of the workers, as one from a combination of contributing causes [38]. Moreover, in recent years safety performance has increasingly come to center around the safety-related behaviors of workers [59]. Occupational safety behaviors give a clear indication of the presence or absence of occupational safety in the workplace [60]. These behaviors, in turn, are often located in a broader social and organizational context, where a multitude of conditions affect safety outcomes [61].
Difficulties in communication with foreign workers can also cause accidents on the construction site [62]. The safety issue faced is due to some of the workers not speaking or understanding the local language. Effective communication might help both parties, namely the safety supervisor and the worker, to have better coordination at the construction site [37]. Good communication affects the implementation of the safety program; when the management communicates openly with the worker, the worker will report on unsafe working practices and hazardous environments [63].
Unsafe behaviors are often the source of many accidents, together with poor working conditions, malfunctioning equipment, poor systems, and poorly designed processes; all of which can encourage unsafe behaviors. While, a company’s attitude towards safe work is an important factor affecting the implementation of occupational safety requirements. It is not enough to provide safe equipment, systems, and procedures if the culture does not promote safe and healthy work [64]. A vast majority of the studies focusing on safety climate and safety culture thus have pointed towards the importance of safety management, including a leadership style that promotes trust and open communication, and makes safety a prioritized area [65]. From the literature review carried out, various barriers were highlighted and modified, as shown in Table 1, as per the working environment of the Gaza Strip.

3. Methodology

In this study, descriptive, analytical, and cross-sectional design were utilized, as these are the appropriate design techniques to describe relationships in the collected data [76]. Qualitative and quantitative survey methods were implemented to check the set hypothesis to evaluate the barriers in infrastructure projects in the Gaza Strip. For study purpose, five governorates were selected within the Gaza Strip, i.e., the KhanYounis governorate, Northern governorate, Middle governorate, Rafah governorate, and Gaza governorate. The methodology of this research consisted of six main steps, as shown in Figure 2.

3.1. Questionnaire Design and Development

Initially, factors were identified from the literature review stage, and then modified through a pilot survey. In the questionnaire design stage, validity and reliability were reviewed to form a final questionnaire. The questionnaire was presented to the Institutional Review Committee (IRC), and the details of the committee are provided in Table A1, Appendix A. The IRC checked the questionnaire fulfilled the code of ethics, and that no sensitive questions were involved. Final IRC approval was given after a check of the questionnaire’s suitability to the study scope, and all the questionnaire’s questions were required to achieve the study objectives.

3.2. Study Population and Sample Size

Consultants and contractors who are involved in infrastructure projects in the Gaza Strip were selected as the only respondents for this study, where a random selected among the population was made. Due to the large population size, Equation (1) was utilized to establish the sample size [77]:
S S = Z 2 × P × 1 P C 2
where “SS” is the sample size, “Z” is the Z value (i.e., 1.96 at 95% confidence level), “P” is the percentage picking a choice (0.5 taken in this case), and “C” is the confidence interval (0.05 ± 5). Using Equation (1), the sample size comes to 384, whereas, for correction for a finite population, Equation (2) was utilized:
N e w   S S = ss 1 + s s 1 p o p u l a t i o n
Using Equation (2), the sample size came to 53 for 62 consultants, based on a 95% confidence level. A distribution of 53 questionnaires was made among consultants, of which only 36 gave feedback, a 67.92% response rate.
In the same manner as for consultants, the sample size was calculated by Equation (2) for 122 contractors, and the size came to 96, at a 95% confidence level. The distribution was made among the 96 contractors, and 100% feedback was received. The questionnaire was developed based on the literature review, and was modified through interviews with field experts. Their suggestions were carefully taken into consideration, and based on which, modifications were made before making the distribution. Figure 3 shows the study distribution among the population. The 132 responses were gathered from the Gaza Strip and were statistically analyzed, based on which conclusions were made.

3.3. Validity and Reliability of Study Instruments

To check that the content of the questionnaire was valid, face validity was performed, where field experts judged the questionnaire content. For checking the consistency of the data, reliability analysis was performed. By these means, much useful information came out, which was incorporated in the developed questionnaire. Statistical Package for Social Science (SPSS-V22) was used to perform the following data analyses on the gathered information: frequency, mean, standard deviation, relative importance index, normal distribution, and Pearson’s correlation coefficient.

4. Results and Discussion

4.1. Validity and Reliability Analysis

Before making the full distribution, it is better to observe the feedback of a limited population, which tells us whether the questionnaire portrays what it is meant for. For this purpose, a pilot survey was made among 30 individuals, i.e., consultants and contractors of the construction industry.
Two statistical tests were applied to ensure questionnaire validity. The first was internal validity, and the second was structural validity. Internal validity was assessed to measure the correlation coefficient between every item. Whereas, structural validity was to examine the correlation between every dimension and whole dimensions which have a similar scale.
Table 2 shows the correlation coefficient and p-value for each item of the duties of competent authorities in safety practices in the infrastructure sector, referring to the internal validity. The p-values are less than 0.05, so the correlation coefficients of each item are significant at α = 0.05. Thus, it can be said that the items of each item are consistent and valid to measure what they were set for.
As shown in Table 3, the significance values are less than 0.05, thus the fields are structurally valid, and further assessment can be performed.
Reliability is the degree of consistency, and is performed to measure the consistency of the data. A value of 0.7 and above is considered as acceptable. For this purpose, Cronbach’s coefficient alpha was used. For each item, the Cronbach’s coefficient alpha (Cα) was computed, where every value was above 0.7 as shown in Table 4. Thus, the outcome shows the questionnaire reliability.

4.2. General Information of Study Participants

The distribution of 132 responses is shown in Figure 4.
It was observed that most of the companies were keeping their safety budget at less than 1% of their project cost, showing negligence by the higher authorities in implementing safety within the construction projects. Though it seems a tactic to save the money, it later results in miserable effects, in terms of project cost or a higher fatality rate.

4.3. Research Hypothesis

Hypothesis. 
The barriers affect the implementation of safety practices in the infrastructure sector in the Gaza Strip at a significance level of 0.05.

4.3.1. Safety Policy Barriers

This part consists of eight items to assess safety policy barriers in improving safety performance in construction projects in the Gaza Strip. From Table 5, it is seen that “A contractor committed to an occupational safety program is not rewarded” was ranked first by both the consultants and contractors, with 0.674 Relative Importance Index (RII). Even with a separate rank by each, this factor stood first, with 0.694 and 0.709 RII. This indicates the importance of motivation in occupational safety programs, and shortcomings in this matter reflected negatively on the development of occupational safety, which is what Patrick [72] pointed out; that legislation and regulation implementation will not reduce the number of accidents unless there is a sufficient budget provided for health and safety management and its implementation.
On the other hand, it is shown that “The contractor does not punish those who are not committed to occupational safety” was placed second by both the consultants and contractors, with 0.683 RII. In a separate rank by each, this factor stood as third, with 0.667 and 0.678 RII. This is identical to Fang and Huang [78], where it was said that to prevent the workers from repeating their offences; they should be penalized.
“The contractor should not allocate a special budget for occupational safety” was ranked in the third position by both the consultants and contractors, with RII of (0.673). The responding contractors ranked this factor in the second position, with RII of (0.683), while it was ranked in the sixth position by the responding consultants, with RII of (0.650). This indicates the need for a real orientation to make the safety budget a priority in infrastructure projects. Foo [69] concluded that without an adequate budget covering OSH (Occupational Safety and Health) requirements and their implementation, implementing regulations will not be sufficient and will not reduce accidents.
Last, “There is no insurance policy for the project and the workers” was ranked last by both the consultants and contractors, with 0.484 RII. Additionally, each of them separately ranked it in the last position, with RII of (0.511) and (0.484), respectively. This is because insurance is applicable in most infrastructure projects.
For factors in the safety policy barriers group, the correlation coefficient comes to 0.762, with a 0.000 p-value (Sig.). As the p-value is less than the significance value, i.e., α = 0.05, this indicates that there is a relationship among the contractors and the consultants within this group.

4.3.2. Management Barriers

This part consists of 20 items to assess the management barriers to improving safety performance in construction projects in the Gaza Strip. From Table 6, it is seen that “The safety engineer does not have significant powers, such as stopping work when needed” was placed first by both the consultants and contractors, with 0.718 RII. In addition, in a separate rank by each, this factor again stood first, with 0.672 and 0.737 RII. This relates to the powers given to the safety engineer, his greater role indicates a real interest in occupational safety in the project. Wong and Gray [35] said that the safety engineer should have powers to stop all events in the projects in case of hazards happening.
On the other hand, it is shown that “The number of safety engineers does not match the size of the project” was ranked second by both the consultants and contractors, with 0.708 RII. A separate rank of this factor by the contractors ranked this factor as second, with 0.725 RII, while it was placed fourth by the consultants, with 0.663 RII. This should be referred to in the contractual papers as binding between the parties, depending on the size and quality of the project. This is consistent with what Tam and Zeng [36] explained.
“There is no real partnership between the parties of the project to commit to safety.” was ranked third by both the consultants and contractors, with 0.693 RII. In a separate ranking by contractors, this factor placed third, with 0.710 RII, while it was placed seventh by the consultants, with 0.650 RII. Vinodkumar and Bhasi [39] noted the importance of cooperation in the work environment. This is often caused by the negative atmosphere in the work environment, and a lack of real concern for occupational safety, and considered as a secondary to the costs and speed of delivery.
Last, “The owner does not care about the application of occupational safety program” was ranked last by both the consultants and contractors, with 0.553 RII. In addition, it stood last in a separate ranking by each, with 0.539 and 0.548 RII. This makes sense for the owner to ensure that his work is done without any problems or dangers.
For factors in the management barriers group, the correlation coefficient came to 0.550, with 0.012 p-value (Sig.). As the p-value is less than significance value, i.e., α = 0.05, this indicates that there was a relationship among the contractors and the consultants within this group.

4.3.3. Behavioral and Cultural Barriers

This part consists of 11 items to assess behavioral and cultural barriers to improving safety performance in construction projects in the Gaza Strip. From Table 7, it is seen that “Workers who are not committed to occupational safety are not excluded” was ranked first by both the consultants and contractors, with 0.718 RII. In addition, in a separate rank by each, this factor stood first, with 0.744 and 0.737 RII. This high percentage demonstrates the importance of these barriers, and it can be said that the lack of stringent laws, and perhaps the operating system in infrastructure projects based on kinship and friendship, adds to this challenge.
On the other hand, it is shown that “The new worker is more exposed to occupational safety accidents” was placed second by both the consultants and contractors, with 0.711 RII. In a separate rank by the contractors, this factor stood third, with 0.708 RII, while it was placed sixth by the consultants, with 0.644 RII. Inexperience is dangerous, because dealing with equipment and machinery needs a high level, especially in a specialized matter, such as infrastructure, even with the use of simple tools. Due to this, experts added this factor to the questionnaire.
“Government agencies do not give adequate instructions to contractors and workers about safety regulations” was ranked third by both the consultants and contractors, with 0.702 RII. In a separate rank by the contractors, this factor stood second, with 0.723 RII, while it was placed fifth by the consultants, with 0.650 RII. This drives the government to pay more attention and improve safety factors, and enact appropriate laws to improve the work environment.
Last, “Language and culture are a barrier in strengthening occupational safety within the project” was placed last by both consultants and contractors, with RII. In addition, in a separate rank by each, this factor stood last, with 0.578 and 0.607 RII. Difficulties in communication with foreign workers can also cause accidents at the construction site. However, not including this item as a barrier is of great importance because the environment of the Gaza Strip is in one language and one culture.
For factors in behavior and culture barriers group, the correlation coefficient came to 0.598, with 0.002 p-value (Sig.). As the p-value was less than the significance value, i.e., α = 0.05, this indicates that there is a relationship among the contractors and the consultants within this group.

5. Conclusions

In this research, barriers to implementing occupational safety in infrastructure projects were evaluated. A questionnaire comprised of 39 barriers was made to get feedback from consultants and contractors in the Gaza Strip. After performing an analysis via SPSS, the results revealed that in “Safety policy barriers” both consultants and the contractors ranked “A contractor committed to an occupational safety program is not rewarded” as first. In “Management barriers”, the item “The safety engineer does not have significant powers, such as stopping work when needed” was ranked first. While in “Behavioral and cultural barriers”, the item “Workers who are not committed to occupational safety are not excluded” was ranked first by both the consultants and the contractors, showing the importance of these barriers in the infrastructure projects, and that negligence can cause serious threats to the project. Looking at the responses made by both consultants and contractors, a strong convergence of views can be seen, which gives a clear indication of the extent to which the problems they face are shared. A single environment and the forced closure of the Gaza Strip may be one of the reasons for this convergence, as well as the relative tradition among all construction work institutions in public policies, plans, and procedures. Occupational safety cannot be determined in infrastructure projects without the elimination of the existing barriers. This study sets a benchmark for construction stakeholders, especially policymakers, to observe the influential factors causing distress, and to make the changes in their planning, accordingly. The outcome of this study is also useful for countries having a similar geography.

6. Future Direction

It is recommended to deeply investigate occupational safety during other phases (design, operation, and demolition) in infrastructure projects in the Gaza Strip. The relationship between project parties (owner, consultant, contractor, worker) separately for each, and their impact on the application of occupational safety can be evaluated. The study can further be extended in field projects by developing a checklist of all the barriers which need to be cleared on-site. Moreover, a comparison of these barriers can be made with the existing health and safety guidelines in Palestine, and any lack must be eliminated to support the occupational safety implementation in infrastructure projects. Once the barriers are fully addressed then this research could be further extended, and a correlation of the existing issues could be made with developing countries’ construction industries.

Author Contributions

All authors contributed equally to conduct this research. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data has been provided in this paper.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

Table A1. Details of Institutional Review Committee.
Table A1. Details of Institutional Review Committee.
S. NoPositionEducationInstitutionExperience (Years)
1ProfessorPhDUniversity30
2Associate Prof.PhDUniversity26
3Assistant Prof.PhDUniversity19
4Project ManagerMscContracting Company25
5ConsultantMscConsultant office27

References

  1. Albhaisi, M.A.; Tayeh, B.A.; El-Hallaq, K. Factors Causing Variation Orders in Construction Projects in Gaza Strip (Case Study: Qatar Projects). Int. J. Eng. Manag. Res. 2016, 6, 262–270. [Google Scholar]
  2. Catalão, F.P.; Cruz, C.O.; Sarmento, J.M. The determinants of cost deviations and overruns in transport projects, an endogenous models approach. Transp. Policy 2019, 74, 224–238. [Google Scholar] [CrossRef]
  3. Musarrat, M.A.; Inderyas, O.; Khan, S.; Shah, A.A. Causes of delay in the execution phase of construction projects in Khyber Pukhtoonkhwa Pakistan. Sarhad Univ. Int. J. Basic Appl. Sci. 2017, 4, 62–70. [Google Scholar]
  4. Tayeh, B.A.; Al-Hallaq, K.; Al-Faqawi, A.H.; Alaloul, W.S.; Kim, S.Y. Success Factors and Barriers of Last Planner System Implementation in the Gaza Strip Construction Industry. Open Constr. Build. Technol. J. 2018, 12, 389–403. [Google Scholar] [CrossRef]
  5. Pilger, J.D.; Machado, Ê.L.; de Assis, L.-R.A.; Zappe, A.L.; Rodriguez-Lopez, D.A. Environ-mental impacts and cost overrun derived from adjustments of a road construction project setting. J. Clean. Prod. 2020, 256, 120731. [Google Scholar] [CrossRef]
  6. Musarat, M.A.; Alaloul, W.S.; Liew, M. Impact of inflation rate on construction projects budget: A review. Ain Shams Eng. J. 2020. [Google Scholar] [CrossRef]
  7. Tayeh, B.A.; Alaloul, W.S.; Muhaisen, W.B. Challenges Facing Small-Sized Construction Firms in the Gaza Strip. Open Civ. Eng. J. 2019, 13, 51–57. [Google Scholar] [CrossRef]
  8. Tayeh, B.A.; Salem, T.J.; Abu Aisheh, Y.I.; Alaloul, W.S. Risk Factors Affecting the Performance of Construction Projects in Gaza Strip. Open Civ. Eng. J. 2020, 14, 94–104. [Google Scholar] [CrossRef]
  9. Meng, X.; Chan, A.H. Demographic influences on safety consciousness and safety citizenship behavior of construction workers. Saf. Sci. 2020, 129, 104835. [Google Scholar] [CrossRef]
  10. Tayeh, B.A.; Al-Hallaq, K.; Alaloul, W.S.; Kuhail, A.R. Factors Affecting the Success of Construction Projects in Gaza Strip. Open Civ. Eng. J. 2018, 12, 301–315. [Google Scholar] [CrossRef]
  11. Tayeh, B.A.; Al-Hallaq, K.; Zahoor, H.; Al-Faqawi, A.H. Techniques and benefits of implementing the last planner system in the Gaza Strip construction industry. Eng. Constr. Arch. Manag. 2019, 26, 1424–1436. [Google Scholar] [CrossRef]
  12. Awolusi, I.G. Active Construction Safety Leading Indicator Data Collection and Evaluation. Ph.D. Thesis, University of Alabama, Tuscaloosa, AL, USA, 2017. [Google Scholar]
  13. Chen, Y. The development and validation of a human factors analysis and classification system for the construction industry. Int. J. Occup. Saf. Ergon. 2020, 1–15. [Google Scholar] [CrossRef]
  14. The ILO’s Social Finance Programme. Annual Report 2017; ILO: Geneve, Switzerland, 2018. [Google Scholar]
  15. Talini, D.; Baldasseroni, A. Workplace health promotion. Med. Lav. 2019, 110, 321–324. [Google Scholar] [CrossRef] [PubMed]
  16. Kheni, N.A.; Gibb, A.G.; Dainty, A.R. Health and safety management within small-and medium-sized enterprises (SMEs) in developing countries: Study of contextual influences. J. Constr. Eng. Manag. 2010, 136, 1104–1115. [Google Scholar] [CrossRef] [Green Version]
  17. Azhar, S.; Choudhry, R.M. Capacity building in construction health and safety research, education, and practice in Pakistan. Built Environ. Proj. Asset Manag. 2016, 6, 92–105. [Google Scholar] [CrossRef]
  18. Kumie, A.; Amera, T.; Berhane, K.; Samet, J.; Hundal, N.; Michael, F.G.; Gilliland, F. Occupational Health and Safety in Ethiopia: A review of Situational Analysis and Needs Assessment. Ethiop. J. Health Dev. 2016, 30, 17–27. [Google Scholar] [PubMed]
  19. Sorensen, G.; Nagler, E.M.; Pawar, P.; Gupta, P.C.; Pednekar, M.S.; Wagner, G.R. Lost in translation: The challenge of adapting integrated approaches for worker health and safety for low- and middle-income countries. PLoS ONE 2017, 12, e0182607. [Google Scholar] [CrossRef] [Green Version]
  20. Partanen, T.J.; Hogstedt, C.; Ahasan, R.; Aragón, A.; Arroyave, M.E.; Jeyaratnam, J.; Kurppa, K.; Loewenson, R.; Lundberg, I.; Ngowi, A.V.F. Collaboration between developing and developed countries and between developing countries in occupational health research and surveillance. Scand. J. Work. Environ. Health 1999, 25, 296–300. [Google Scholar] [CrossRef] [Green Version]
  21. Ugwu, O.O.; Haupt, T.C. Key performance indicators for infrastructure sustainability–A comparative study between Hong Kong and South Africa. J. Eng. Des. Technol. 2005, 3, 30–43. [Google Scholar] [CrossRef]
  22. El-Sawalhi, N.I.; Sarhan, M.S. Causes of Non-Prioritization of Infrastructure Projects in the Gaza Strip. J. Civ. Constr. Environ. Eng. 2018, 3, 29–38. [Google Scholar] [CrossRef] [Green Version]
  23. UNDP (United Nations Development Programme). Spatial Visioning Reflections Gaza. Urban Plan. 2015, 2, 41–52. [Google Scholar]
  24. Dentoni, M. Risk Analysis and Mitigation of Seawater Intrusion for the Gaza Strip Coastal Aquifer under Climate Induced Changes. P-arch. 2013. Available online: http://www.p-arch.it/handle/11050/904 (accessed on 11 March 2021).
  25. PCU (Palestinian Contractors Union). Gaza. 2019. Available online: http://www.pcu.ps (accessed on 11 March 2021).
  26. Eppenberger, M.; Haupt, T. The older construction worker–A study of injuries and their underlying causes. In Proceedings of the CIDB 1st Postgraduate Conference, Port Elizabeth, South Africa, 13 October 2003. [Google Scholar]
  27. Hare, B.; Cameron, I.; Duff, A. Integration of Health and Safety planning in construction project management through the development of a best practice “Gateway” model. Postgrad. Res. 2003, 201. [Google Scholar]
  28. Tayeh, B.A.; Durdyev, S.; Abuzuhri, I.O.; Hosseini, M.R.; Thurnell, D. Contractors’ attitudes towards the factors affecting sustainability performance: Evidence from Palestine. Bus. Strat. Dev. 2019, 2, 173–179. [Google Scholar] [CrossRef]
  29. Hinze, J. Construction safety. Saf. Sci. 2008, 46, 565. [Google Scholar] [CrossRef]
  30. Langford, D.; Rowlinson, S.; Sawacha, E. Safety behaviour and safety management: Its influence on the attitudes of workers in the UK construction industry. Eng. Constr. Archit. Manag. 2000, 7, 133–140. [Google Scholar] [CrossRef]
  31. Hinze, J.; Gambatese, J.A. Addressing Construction Worker Safety in Project Design; Bureau of Engineering Research, University of Texas at Austin: Austin, TX, USA, 1996. [Google Scholar]
  32. Masayuki, N. Current Activities for Improvement of Construction Occupational Health and Safety in Japan, 4th ed.; Quarter Master Builders Association Malaysia: Kuala Lumpur, Malesia, 2006; pp. 88–95. [Google Scholar]
  33. Holt, A.S.J.; Holt, A.S.J. Principles of Construction Safety; Blackwell Science: London, UK, 2001. [Google Scholar]
  34. Hassanein, A.A.; Hanna, R.S. Safety Performance in the Egyptian Construction Industry. J. Constr. Eng. Manag. 2008, 134, 451–455. [Google Scholar] [CrossRef] [Green Version]
  35. Wong, J.Y.Y.; Gray, J.; Sadiqi, Z. Barriers to good occupational health and safety (OHS) practices by small construction firms. J. Constr. Manag. 2015, 30, 55–66. [Google Scholar]
  36. Tam, C.; Zeng, S.; Deng, Z. Identifying elements of poor construction safety management in China. Saf. Sci. 2004, 42, 569–586. [Google Scholar] [CrossRef]
  37. Ghani, M.A.; Baki, S.; Alias, C.C.; Ibrahim, E.A.; Hamid, A.E.; Rahim, A.A.; Kamar, K.M.; Zain, M.M. Strategies in reducing hazards at construction sites. ICCBT 2008 B 2008, 12, 137–148. [Google Scholar]
  38. Mahfuth, K.; Loulizi, A.; Tayeh, B.A.; Al-Hallaq, K. Unacceptable forms of work for safety in the construction sector Palestinian National Authority. Int. J. Civ. Eng. 2018, 9, 328–341. [Google Scholar]
  39. Vinodkumar, M.; Bhasi, M. Safety management practices and safety behaviour: Assessing the mediating role of safety knowledge and motivation. Accid. Anal. Prev. 2010, 42, 2082–2093. [Google Scholar] [CrossRef]
  40. Mahfuth, K.; Loulizi, A.; Al Hallaq, K.; Tayeh, B.A. Implementation Phase Safety System for Minimising Construction Project Waste. Buildings 2019, 9, 25. [Google Scholar] [CrossRef] [Green Version]
  41. Mearns, K.; Whitaker, S.M.; Flin, R. Safety climate, safety management practice and safety performance in offshore environments. Saf. Sci. 2003, 41, 641–680. [Google Scholar] [CrossRef]
  42. Mahfuth, K.; Loulizi, A.; Tayeh, B.A.; Al-Hallaq, K.; Abu, A.Y.I. Using Safety System during the Design Phase to Minimize Waste in Construction Projects. J. King Saud Univ. Eng. Sci. 2020. [Google Scholar] [CrossRef]
  43. Alaloul, W.S.; Musarat, M.A.; Liew, M.S.; Zawawi, N.A.W.A. Influential Safety Performance and Assessment in Construction Projects: A Review. In Proceedings of the 1st Indo-China Research Series in Geotechnical and Geoenvironmental Engineering, China, 18 May 2020; Garg, A., Solanki, C.H., Bogireddy, C., Liu, J., Eds.; Springer: Berlin/Heidelberg, Germany, 2019; pp. 719–728. [Google Scholar]
  44. Hassel, A. Implementation of HSE Management Practices at Construction Sites in Developing Countries. Master’s Thesis, Norwegian University of Science and Technology, Trondheim, Norway, 2016. [Google Scholar]
  45. The Hartford. Owner’s Responsibility to Construction. Technical Information Paper Series, 2002. S140.003. Available online: https://www.noao.edu/safety/itt_hartford_risk_management_resources/owners_responsiblity_to_construction.pdf (accessed on 11 March 2021).
  46. Din, Z.; Rahman, R.A.; Gibson, E. Comparative study of university courses on construction safety at under-graduate level. In Proceedings of the 6th CSCE-CRC International Construction Specialty Conference 2017 as Part of the Canadian Society for Civil Engineering Annual Conference and General Meeting 2017, Vancouver, BC, Canada, 31 May–3 June 2017. [Google Scholar]
  47. Yilmaz, F.; Çelebi, U.B. The importance of safety in construction sector: Costs of occupational accidents in construction sites. Bus. Econ. Res. J. 2015, 6, 25. [Google Scholar]
  48. Baxendale, T.; Jones, O. Construction design and management safety regulations in practice—Progress on implementation. Int. J. Proj. Manag. 2000, 18, 33–40. [Google Scholar] [CrossRef]
  49. Kartam, N.; Flood, I.; Koushki, P. Construction safety in Kuwait: Issues, Procedures, Problems, and Recommendations. Saf. Sci. 2000, 36, 163–184. [Google Scholar] [CrossRef]
  50. Reese, C.D.; Eidson, J.V. Handbook of OSHA Construction Safety and Health; CRC Press: Boca Raton, FL, USA, 2006. [Google Scholar]
  51. Campbell, J.M. Safety Hazard and Risk Identification and Management in Infrastructure Management. Ph.D. Thesis, University of Edinburgh, Edinburgh, UK, 2008. [Google Scholar]
  52. Dedobbeleer, N.; Béland, F. A safety climate measure for construction sites. J. Saf. Res. 1991, 22, 97–103. [Google Scholar] [CrossRef]
  53. Bhattacharjee, S.; Ghosh, S.; Young-Corbett, D. Safety improvement approaches in construction industry: A review and future directions. In Proceeding of the 47th ASC Annual International Conference, Omaha, NE, USA, 6–9 April 2011. [Google Scholar]
  54. Eich, W.G. Safety Practices of Large Construction Firms. Master’s Thesis, University of Washington, Seattle, WA, USA, 1996. [Google Scholar]
  55. Kam, C. Integrating Behaviourism and Cognitivism: A Paradigmatic Reconciliation of Occupational Safety-Technical Seminar on Occupational Safety; The Hong Kong Institution of Engineers: Hong Kong, China, 2003. [Google Scholar]
  56. Hassouna, A.M. Improving Safety Performance in Construction Projects in the Gaza Strip. Master’s Thesis, The Islamic University of Gaza, Gaza, Palestine, 2005. [Google Scholar]
  57. Pratt, S.G.; Fosbroke, D.E.; Marsh, S.M. Building safer highway work zones; measures to prevent worker injuries from vehicles and equipment. DHHS Publ. 2001, 128. Available online: https://elcosh.org/record/document/1388/d000461.pdf (accessed on 11 March 2021).
  58. Purdue. Behavior-based Safety in Construction. Prof. Saf. 2004, 65, 48–52. [Google Scholar]
  59. Christian, M.S.; Bradley, J.C.; Wallace, J.C.; Burke, M.J. Workplace safety: A meta-analysis of the roles of person and situation factors. J. Appl. Psychol. 2009, 94, 1103. [Google Scholar] [CrossRef] [PubMed]
  60. Beus, J.M.; McCord, M.A.; Zohar, D. Workplace safety: A review and research synthesis. Organ. Psychol. Rev. 2016, 6, 352–381. [Google Scholar] [CrossRef]
  61. Dahl, Ø. Safety compliance in a highly regulated environment: A case study of worker’s knowledge of rules and procedures within the petroleum industry. Saf. Sci. 2013, 60, 185–195. [Google Scholar] [CrossRef] [Green Version]
  62. Li, H.; Lu, M.; Hsu, S.-C.; Gray, M.; Huang, T. Proactive behavior-based safety management for construction safety improvement. Saf. Sci. 2015, 75, 107–117. [Google Scholar] [CrossRef]
  63. Peyton, R.X.; Rubio, T.C. Construction Safety Practices and Principles; Van Nostrand Reinhold Company: New York, NY, USA, 1991. [Google Scholar]
  64. Aboul, F.A.M.; Ismail, N.A.; Ez, E.H.S.; Wassif, G. Assessment of patient safety culture among health-care providers at a teaching hospital in Cairo, Egypt. EMHJ East. Mediterr. Health J. 2012, 18, 372–377. [Google Scholar] [CrossRef]
  65. Nygren, M. Safety Management on Multi-Employer Worksites: Responsibilities and Power Relations in the Mining Industry. Ph.D. Thesis, Luleå Tekniska Universitet, Lulea, Sweden, 2018. [Google Scholar]
  66. Tayeh, B.A.; Yaghi, R.O.; Abu, A.Y.I. Project Manager Interventions in Occupational Health and Safety During the Pre-construction Phase in the Gaza Strip. Open Civ. Eng. J. 2020, 14, 20–30. [Google Scholar] [CrossRef] [Green Version]
  67. Enshassi, A.; Arain, F.; Tayeh, B. Subcontractor Prequalification Practices in Palestine. Int. J. Constr. Manag. 2010, 10, 45–74. [Google Scholar] [CrossRef]
  68. Al-Kilani, F.M. Improving Safety Performance in Construction Projects in Libya (Case Study: In Tripoli City). Master’s Thesis, Diponegoro University, Semarang, Indonesia, 2011. [Google Scholar]
  69. Foo, C. Budgeting for occupational safety and health management and its implementation. In Proceedings of the MBAM Annual Safety Conference, Kuala Lumpur, Malaysia, 31 December 2005. [Google Scholar]
  70. Zhou, Q.; Fang, D.; Mohamed, S. Safety Climate Improvement: Case Study in a Chinese Construction Company. J. Constr. Eng. Manag. 2011, 137, 86–95. [Google Scholar] [CrossRef]
  71. Levitt, R.E.; Samelson, N.M. Construction Safety Management; John Wiley & Sons: Hoboken, NJ, USA, 1993. [Google Scholar]
  72. Patrick, W. Expresses Concern on Overall Safety at Construction Sites; Master Builder Association Malaysia: Kuala Lumpur, Malesia, 2008. [Google Scholar]
  73. Byaruhanga, A.; Basheka, B.C. Contractor Monitoring and Performance of Road Infrastructure Projects in Uganda: A Management Model. J. Build. Constr. Plan. Res. 2017, 5, 30–44. [Google Scholar] [CrossRef] [Green Version]
  74. Wilson, J.M.; Koehn, E. Safety Management: Problems Encountered and Recommended Solutions. J. Constr. Eng. Manag. 2000, 126, 77–79. [Google Scholar] [CrossRef]
  75. Hassan, F.; Ismail, Z.; Zaini, A.A.; Hassan, S.; Maisham, M. A critical assessment of the challenges of developing the Malaysian construction workforce through training. In Proceedings of the 2011 IEEE Colloquium on Humanities, Science and Engineering, Penang, Malaysia, 5–6 December 2011. [Google Scholar]
  76. Polit, D.F.; Beck, C.T. Nursing Research: Generating and Assessing Evidence for Nursing Practice; Lippincott Williams & Wilkins: Philadelphia, PA, USA, 2008. [Google Scholar]
  77. De Vaus, D. Surveys in Social Research; Allen and Unwin: Crow’s Nest, Australia, 2002. [Google Scholar]
  78. Fang, D.P.; Huang, X.Y.; Hinze, J. Benchmarking Studies on Construction Safety Management in China. J. Constr. Eng. Manag. 2004, 130, 424–432. [Google Scholar] [CrossRef]
Figure 1. Location map of the Gaza Strip [24].
Figure 1. Location map of the Gaza Strip [24].
Ijerph 18 03553 g001
Figure 2. Research Flowchart.
Figure 2. Research Flowchart.
Ijerph 18 03553 g002
Figure 3. Population size and study sample.
Figure 3. Population size and study sample.
Ijerph 18 03553 g003
Figure 4. Distribution of study participants.
Figure 4. Distribution of study participants.
Ijerph 18 03553 g004
Table 1. List of barriers that hinder the implementation of safety practices in the infrastructure sector.
Table 1. List of barriers that hinder the implementation of safety practices in the infrastructure sector.
NoIdentified Barriers from the Literature ReviewCommentReference
Safety policy barriers
1The contractor does not have a clearly stated occupational safety policySelected[66,67]
2Weak contractor implementation of occupational safety policySelected[68]
3The contractor should not allocate a special budget for occupational safetySelected[69]
4The contractor does not punish those who are not committed to occupational safetySelected[70,71]
5A contractor committed to an occupational safety program is not rewardedSelected[72]
6Staff ignorance of the occupational safety policySelected[67]
7There is no insurance policy for the project and the workersSelected[73]
8Work injuries are not documented within the projectSelected[47]
Management barriers
9The owner does not care about the application of occupational safety program.Selected[50,68]
10The contractor does not care about the application of the occupational safety program.Selected[50,74]
11The consultant is not interested in implementing the occupational safety program.Selected[50,68]
12Government agencies do not monitor the occupational safety program in projects.Selected[50,68]
13There is no safety engineer in the project.Selected[29]
14Safety rules are not respected.Selected[29]
15There are no regular Occupational Safety and Health (OSH) meetings within the project.Selected[34]
16No occupational safety meetings are held within the project.Selected[34]
17Those who are committed to an occupational safety program are not motivated.Selected[32]
18Poor coordination between different project teams.Selected[33]
19The number of safety engineers does not match the size of the project.Selected[35,36,37]
20The safety engineer does not have significant powers, such as stopping work when needed.Selected[35,36,37]
21There is no real partnership between the parties of the project to commit to safety.Selected[39]
22Safety plans are not updated after the end of each project.Selected[44,47]
23The safety procedures do not include the third party (public).Selected[51]
24The contractor’s occupational safety history is not important in awarding the tender.Selected[45]
25Tenders do not include mandatory safety requirements.Selected[49]
26No safety courses are given before the start of the project.added-
27Staff do not receive training courses to deal with equipment and machinery within the project.added-
28Modern technology is not used to provide safety.added-
Behavioral and cultural barriers
29Project staff lack full awareness of occupational safety.Selected[47,55,75]
30Staff do not meet occupational safety instructions.Selected[71]
31The staff do not have a thorough knowledge of the use of machinery and equipment.Selected[54,56]
32Staff do not have experience in dealing with emergencies.Selected[54]
33Employees accept working in an environment that does not respect safety standards.Selected[64]
34Government agencies do not give adequate instructions to contractors and workers about safety regulations.added-
35Work pressure and productivity ensure reduced commitment to occupational safety.Selected[54]
36Use of tools and machinery that are dangerous to workers.Selected[64]
37Language and culture are a barrier in strengthening occupational safety within the project.added-
38The new worker is more exposed to occupational safety accidents.added-
39Workers who are not committed to occupational safety are not excluded.added-
Table 2. Internal validity of barriers that hinder the implementation of safety practices in the infrastructure sector.
Table 2. Internal validity of barriers that hinder the implementation of safety practices in the infrastructure sector.
No.FieldsCorrelation Coefficientp-Value
Safety policy barriers
1The contractor does not have a clearly stated occupational safety policy.0.6840.000 *
2Weak contractor implementation of occupational safety policy.0.6940.000 *
3The contractor should not allocate a special budget for occupational safety.0.6520.000 *
4The contractor does not punish those who are not committed to occupational safety.0.6650.000 *
5A contractor committed to an occupational safety program is not rewarded.0.6230.000 *
6Staff ignorance of the occupational safety policy.0.6850.000 *
7There is no insurance policy for the project and the workers.0.5130.000 *
8Work injuries are not documented within the project.0.6540.000 *
Management barriers
9The owner does not care about the application of the occupational safety program.0.5270.000 *
10The contractor does not care about the application of the occupational safety program.0.5300.000 *
11The consultant is not interested in implementing the occupational safety program.0.4900.000 *
12Government agencies do not monitor the occupational safety program in projects.0.5640.000 *
13There is no safety engineer in the project.0.5560.000 *
14Safety rules are not respected.0.6310.000 *
15There are no regular OSH meetings within the project.0.6060.000 *
16No occupational safety meetings are held within the project.0.5890.000 *
17Those who are committed to an occupational safety program are not motivated.0.5360.000 *
18Poor coordination between different project teams.0.5600.000 *
19The number of safety engineers does not match the size of the project.0.6120.000 *
20The safety engineer does not have significant powers, such as stopping work when needed.0.5070.000 *
21There is no real partnership between the parties of the project to commit to safety.0.6600.000 *
22Safety plans are not updated after the end of each project.0.6540.000 *
23The safety procedures do not include the third party (public).0.6940.000 *
24The contractor’s occupational safety history is not important in awarding the tender0.5130.000 *
25Tenders do not include mandatory safety requirements.0.6640.000 *
26No safety courses are given before the start of the project.0.6090.000 *
27Staff do not receive training courses to deal with equipment and machinery within the project.0.5980.000 *
28Modern technology is not used to provide safety.0.5650.000 *
Behavior and culture barriers
29Project staff lack full awareness of occupational safety.0.6550.000 *
30Staff do not meet occupational safety instructions.0.6970.000 *
31The staff do not have a thorough knowledge of the use of machinery and equipment.0.6440.000 *
32Staff do not have experience in dealing with emergencies.0.7100.000 *
33Employees accept working in an environment that does not respect safety standards.0.6670.000 *
34Government agencies do not give adequate instructions to contractors and workers about safety regulations.0.6320.000 *
35Work pressure and productivity ensure reduced commitment to occupational safety.0.6890.000 *
36Use of tools and machinery that are dangerous to workers.0.6720.000 *
37Language and culture are a barrier in strengthening occupational safety within the project.0.6170.000 *
38The new worker is more exposed to occupational safety accidents.0.6330.000 *
39Workers who are not committed to occupational safety are not excluded.0.5130.000 *
* the significance values of p-Value are less than 0.05.
Table 3. Structure validity of the questionnaire.
Table 3. Structure validity of the questionnaire.
DimensionsCorrelation Coefficientp-Value
Barriers that hinder the implementation of safety practices in the infrastructure sector
Safety policy barriers0.6570.000 *
Management barriers0.9170.000 *
Behavioral and cultural barriers0.8670.000 *
* the significance values of p-Value are less than 0.05.
Table 4. Cronbach’s coefficient alpha for reliability (Cα).
Table 4. Cronbach’s coefficient alpha for reliability (Cα).
DimensionsCronbach’s Alpha (Cα)p-Value
Barriers that hinder the implementation of safety practices in the infrastructure sector
Safety policy barriers0.7680.000 *
Management barriers0.8700.000 *
Behavioral and cultural barriers0.8590.000 *
Total0.9110.000 *
* the significance values of p-Value are less than 0.05.
Table 5. Rank and Relative Importance Index (RII) of items related to safety policy barriers.
Table 5. Rank and Relative Importance Index (RII) of items related to safety policy barriers.
NoFactorsBoth ConsultantContractor
RIIRankRII RankRII Rank
1The contractor does not have a clearly stated occupational safety policy.0.63860.66150.6286
2Weak contractor implementation of occupational safety policy.0.66440.66740.6634
3The contractor should not allocate a special budget for occupational safety.0.67330.65060.6832
4The contractor does not punish those who are not committed to occupational safety.0.68320.69410.6783
5A contractor committed to an occupational safety program is not rewarded.0.69710.66730.7091
6Staff ignorance of the occupational safety policy.0.64750.67820.6355
7There is no insurance policy for the project and the workers.0.48480.51180.4748
8Work injuries are not documented within the project.0.49670.55470.4767
All items0.623 0.635 0.618
Table 6. Rank and RII of items related to management barriers.
Table 6. Rank and RII of items related to management barriers.
NoFactorsBoth Consultant Contractor
RII RankRII RankRII Rank
1The owner does not care about the application of the occupational safety program.0.553200.539200.54820
2The contractor does not care about the application of the occupational safety program.0.614180.644110.60218
3The consultant is not interested in implementing the occupational safety program.0.556190.578180.55919
4Government agencies do not monitor the occupational safety program in projects.0.655120.66150.65315
5There is no safety engineer in the project.0.663110.644120.67011
6Safety rules are not respected.0.67190.628150.6887
7There are no regular OSH meetings within the project.0.67370.633130.6896
8No occupational safety meetings are held within the project.0.667100.617160.6878
9Those who are committed to an occupational safety program are not motivated.0.67280.66160.67710
10Poor coordination between different project teams.0.654130.611170.67012
11The number of safety engineers does not match the size of the project.0.70820.66340.7252
12The safety engineer does not have significant powers, such as stopping work when needed.0.71810.66920.7371
13There is no real partnership between the parties of the project to commit to safety.0.69330.65070.7103
14Safety plans are not updated after the end of each project.0.68940.66730.6984
15The safety procedures do not include the third party (public).0.651150.629140.65914
16The contractor’s occupational safety history is not important in awarding the tender.0.68050.65080.6915
17Tenders do not include mandatory safety requirements.0.636160.561190.66513
18No safety courses are given before the start of the project.0.67860.67210.6809
19Staff do not receive training courses to deal with equipment and machinery within the project.0.652140.65090.65316
20Modern technology is not used to provide safety.0.623170.650100.61217
All items0.655 0.634 0.664
Table 7. Rank and RII of items related to behavioral and cultural barriers.
Table 7. Rank and RII of items related to behavioral and cultural barriers.
NoFactorsBoth ConsultantContractor
RIIRankRIIRankRIIRank
1Project staff lack full awareness of occupational safety.0.64780.62290.6577
2Staff do not meet occupational safety instructions.0.65270.66720.6468
3The staff do not have a thorough knowledge of the use of machinery and equipment.0.616100.63370.60910
4Staff do not have experience in dealing with emergencies.0.66660.65040.6726
5Employees accept working in an environment that does not respect safety standards.0.68340.65330.6935
6Government agencies do not give adequate instructions to contractors and workers about safety regulations0.70230.65050.7232
7Work pressure and productivity ensure reduced commitment to occupational safety.0.67950.62880.6994
8Use of tools and machinery that are dangerous to workers.0.61790.606100.6229
9Language and culture are a barrier in strengthening occupational safety within the project.0.598110.578110.60711
10The new worker is more exposed to occupational safety accidents.0.71120.64460.7083
11Workers who are not committed to occupational safety are not excluded.0.71810.74410.7371
All items0.663 0.643 0.670
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Abu Aisheh, Y.I.; Tayeh, B.A.; Alaloul, W.S.; Jouda, A.F. Barriers of Occupational Safety Implementation in Infrastructure Projects: Gaza Strip Case. Int. J. Environ. Res. Public Health 2021, 18, 3553. https://doi.org/10.3390/ijerph18073553

AMA Style

Abu Aisheh YI, Tayeh BA, Alaloul WS, Jouda AF. Barriers of Occupational Safety Implementation in Infrastructure Projects: Gaza Strip Case. International Journal of Environmental Research and Public Health. 2021; 18(7):3553. https://doi.org/10.3390/ijerph18073553

Chicago/Turabian Style

Abu Aisheh, Yazan Issa, Bassam A. Tayeh, Wesam Salah Alaloul, and Amro Fareed Jouda. 2021. "Barriers of Occupational Safety Implementation in Infrastructure Projects: Gaza Strip Case" International Journal of Environmental Research and Public Health 18, no. 7: 3553. https://doi.org/10.3390/ijerph18073553

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop