Development of the Protocol of the Occupational Risk Assessment Method for Construction Works: Level of Preventive Action
Abstract
:1. Introduction
- Identification of the potential dangers
- Assessment and quantification of the risk
- Categorization
2. Methodology
- The first phase of the protocol defines a characteristic value of the risk inherent to the work situation being observed. Starting from the quantification of the qualitative parameters that define the probability and consequences of the risk.
- The second phase assesses the impact on the risk of the documentary environment, construction environment, and the social environment. Starting from the calculated characteristic value, said value will be required higher or lower depending on the incidence regarding the assessed risk.
- The third phase indicates the criteria for preventive action control, using the value obtained from the Level of Preventive Action (Lpac) in relation to absolute risk (Abr), as a deviation from the initial preventive action. This value indicates the amount of preventive action that is required to achieve an optimal control situation of preventive action during construction. The control of preventive action may be determined precisely in the assessed risk or, more generally, in each of the observation environments or, globally, with respect to the general situation of the construction.
- The fourth phase indicates the recommendations for action, based on the amount of preventive action that is required to be provided to achieve optimal control of the preventive action. Preventive actions may be established on the assessed risks, the preventive environments, or on the work in general.
- And in the fifth phase, the improvement of the preventive action during the work process is verified. Depending on the risks that are assessed and the immediate nature of the new risk assessment method, the improvements can be verified once the preventive actions have been implemented.
2.1. Phases of the Investigation
- Preliminary investigation phase. It began in 2013, from the analysis of different risk assessment methodologies and their usability in construction works. The evaluation was carried out on three construction systems with a high incidence of accidents [10,13,17,18,19,25,32] and on the most characteristic risks in construction sites [6,8,10,11]. The evaluation was carried out from the written and photographic documentation of three real construction works, already completed at that time. The construction works that were worked on were a detached house (644.81 m2 and completed in 2013), the rehabilitation of the facades, roofs and pavement of a street (with a total area of 2379.71 m2 and completed in 2011), and a public school (2741.68 m2 and completed in 2010) [21,36,37]. The conclusions of this preliminary research work evidenced the enormous disparity regarding the results of the risk assessment for the different methodologies [21,36,37].
- Experimental design phase. A new mathematical formula developed from the method of William T. Fine [40,44] is proposed. New prevention environments are incorporated into the definition of risk that depends on the probability and consequences: the documentary environment, the constructive environment, and the social environment. These environments determine the degree of correction in terms of prevention, defining the new parameter of Evaluation of the Level of Preventive Action during the construction process [36].
- Implementation phase of the new risk assessment method adapted to construction works, Level of Preventive Action. Specialized technical data is collected and a simple psychosocial survey is carried out in a real construction site with which there is no contractual link (see Acknowledgments), to guarantee greater objectivity in data collection. The construction site was visited once or twice every two weeks, even twice on the same day. The visiting hours were random. It was documented photographically and the results and recommendation criteria for the control of preventive action were communicated to the responsible personnel. The average time for evaluating each construction system was three hours (data collection and office work).
2.2. Investigation Procedure
- Photography, analysis, and assessment of the risk situation from outside the construction.
- Photography, analysis, and assessment of the risk situation of each construction system that was being carried out.
- Photography, analysis, and assessment of the risk situation of the protection and prevention systems; both collectively and individually.
- Photography, analysis, and assessment of the interest of building workers and agents in occupational health and safety regarding their participation.
- Psychosocial survey on the perception of the emotional state and the perception of risks, of workers and building agents.
- The risks that the evaluator determines to be appropriate are evaluated.
- From the spreadsheet, the quantitative and graphical results of the parameters of the risk assessment and the Level of Preventive Action are obtained.
- We proceed to determine the degree of demand in preventive action.
- The characteristic values for the preventive action controls are obtained.
- The Preventive Action Level results are offered for each risk, for risk groups (Occupational Safety, Industrial Hygiene, Ergonomics, and Psychosociology), and for all the risks evaluated.
- The recommendations for the control of preventive action cover the documentary environment, the constructive environment, the social environment, and in all the parameters evaluated.
- The recommendations must establish communication strategies that generate a preventive culture and establish principles for improving the perception of risk with the participation of workers and building agents.
3. Parameters of the New Risk Assessment Method
- Probability (P): estimation of the risk tolerance in terms of the probability of an injury occurring.
- Consequences (C): estimation of the risk tolerance in terms of the expected consequences of the injury which could occur.
- Absolute Risk (Abr): estimation that is performed at the start of project implementation using the Health and Safety at Work Plan drafted by the construction company. It is the absolute documentary environment and serves as the basis for comparison for the rest of the parameters.
- Relative Risk (Rr): preventive parameter which interprets the complexity of the construction safety typical of the unit of work and which increases the value of the absolute risk.
- Borderline Risk (Br): preventive parameter which interprets the location of the unit of work and its impact on the environment, and which increases the value of the absolute risk.
- Degree of Exposure (E): parameter which assesses the amount of time used in completing the unit of work and whether workers are exposed to the risk several times during implementation of the work unit, increasing the value of the absolute risk.
- Economic Capacity (Ec): parameter which assesses the amount of economic resources in constructive prevention systems; and which decreases the value of the absolute risk.
- Participatory Interest (Pi): parameter which assesses the interest in the participation of the different workers and agents involved in a construction project, by obtaining their perception of health and safety; and which decreases the value of the absolute risk.
- Level of Satisfaction (Ls): parameter which looks at general aspects of behavior, state of mind and human attitude which have a significant influence, or may have a significant influence on the generation of risks; and which decreases the value of the absolute risk.
4. Protocol
4.1. Quantification of the Absolute Risk
- Low probability and slightly damaging consequence f(0) = 1
- Medium probability and damaging consequence f(1) = 3
- High probability and extremely damaging consequence f(2) = 5
4.2. Quantification of the Preventive Action Assessment
- The first phase of the protocol defines a characteristic value inherent to the work situation being observed
- The second phase assesses the impact on the risk of the construction environment and the social environment
- The third phase indicates the criteria for preventive action control, using the value obtained from the Level of Preventive Action (Lpac) in relation to absolute risk (Abr), as a deviation from the initial preventive action (Figure 2)
- The fourth phase indicates the recommendations for action
- The fifth phase verifies the improvement of the preventive action during the work process
4.2.1. First Phase: The Characteristic Value
4.2.2. Characteristic Value of Relative Risk
4.2.3. Characteristic Value of Borderline Risk
- The actual height between the working plane and ground level. This concept is independent of the quantity of work that exists. The height is measured according to its true size and the depth in absolute terms.
- Location of the worker in relation to the situation of potential risk. This concept depends on the theoretical distance between the worker or workers and the dangerous situation. It is worth highlighting that there are safe and unsafe areas on work platforms. The characteristic value identifies the intermediate area between the safe area and the unsafe area, which is the borderline area.
- For a working plane height of up to 1.0 m, the borderline area is established at a distance of 100 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area
- For a working plane height of up to 3.0 m, the borderline area is established at a distance of 100 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area
- For a working plane height of up to 5.0 m, the borderline area is established at a distance of 125 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area
- For a working plane height of up to 9.0 m, the borderline area is established at a distance of 150 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area.
- For a working plane height of up to 15.0 m, the borderline area is established at a distance of 175 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area
- For a working plane height of more than 15.0 m, the borderline area is established at a distance of 200 cm from the risk, and from this point there are 25 cm to the safe area and 25 cm to the unsafe area
4.2.4. Characteristic Value of the Degree of Exposure
- In relation to observation for low-intensity exposure: in the case of never, the worker is not exposed to a situation of risk at work and there are neither internal nor external risks on the way to the job; the characteristic value is 1. In the case of rare, the worker is exposed to risk once or twice at work during the period of observation, there are no risks in executing the unit of work but there are low risks on accessing the place of work or there are low risks in executing the unit of work and no risks on accessing the place of work; the characteristic value is 3.
- In relation to observation for medium intensity exposure: in the case of unusual, the worker is exposed to risk between two and five times at work during the period of observation, there are low risks in executing the unit of work and low risks on accessing the place of work; the characteristic value is 5. In the case of occasional, the worker is exposed to risk more than five times at work during the period of observation, there are high risks in executing the unit of work and low risks on accessing the place of work or there are low risks in executing the unit of work and high risks on accessing the place of work; the characteristic value is 9.
- In relation to observation for high-intensity exposure: in the case of frequent, the worker remains intermittently exposed to the risk during the period of observation, there are high risks in executing the unit of work and high risks on accessing the place of work; the characteristic value is 15. In the case of continual, the worker remains exposed to the risk during the execution of the unit of work, the risks during the execution of the unit of work are dangerous and the risks on accessing the place of work are dangerous; the characteristic value is 25.
4.2.5. Characteristic Value of the Economic Capacity
- Analysis is carried out into whether there is an uncoordinated situation between the workers during the execution of the unit of work. This indicates that there is interrupted work and little organization, which in turn implies an increase in the exposure to risks. This will result in delays to project progress.
- Analysis is carried out into whether there is insufficient order during project execution which would imply that there is confusion between workers.
- Analysis is carried out into whether there is order during the execution of the unit of work. The risks decrease by ensuring that the company’s economic investment remains in line with the project planning.
- Analysis is carried out into whether there is coordination between the on-site workers. This implies a significant reduction in the risks, which is reflected in the execution time and in the company’s economic investment.
- Analysis is carried out into whether the tasks are being executed accurately, which generates less risk and improves both the project execution time and economic return.
4.2.6. Characteristic Value of Participative Interest
4.2.7. Characteristic Value of the Level of Satisfaction
- What do you consider your state of mind to be?
- What would you say is your current energy level?
- What is your level of personal satisfaction? (outside the construction environment)
- What is your level of job satisfaction? (within the construction environment).
- What level of complexity or difficulty do you associate with the work that you are doing? and
- What is the level of danger associated with the work that you do?
- How high is your level of participation in your own safety?
- How high is your level of participation in your colleagues’ safety?
- To what level do you consider your individual protective equipment to be complete?
- To what level do you consider the collective protection systems to be complete?
4.3. Second Phase: The impact on the Risk
- Safety, 010 Risk of people falling from a different height
- Safety, 020 Risk of people falling from the same height
- Safety, 040 Risk of objects falling during handling
- Safety, 110 Risk of entrapment by or between objects
- Hygiene, 350 Risk due to thermal stress
- Hygiene, 380 Risk due to inadequate lighting
- Ergonomics, 420 Risk due to movement
- Ergonomics, 440 Risk due to incorrect load handling
- Psychosociology, 560 Risk due to personal relationships
- Psychosociology, 570 Risk due to incorrect work organization
4.4. Third Phase: Basis for Controlling Preventive Action
- Optimal control of preventive action
- Adequate control of preventive action
- More control of preventive action
- Greater control of preventive action
- Intense control of preventive action
- Exhaustive control of preventive action
4.5. Fourth Phase: Recommendation Criteria
4.6. Fifth phase: Verification of Project Results Progress
5. Results and Discussion. Participation
6. Conclusions
Author Contributions
Funding
Acknowledgments
Conflicts of Interest
Appendix A
Appendix B
References
- Lyons, T.; Skitmore, M.; Skitmore, M. Project risk management in the Queensland engineering construction industry: A survey. Int. J. Proj. Manag. 2004, 22, 51–61. [Google Scholar] [CrossRef] [Green Version]
- Mahabadi, H.A.; Khosravi, Y.; Hassanzadeh-Rangi, N.; Hajizadeh, E.; Behzadan, A.H. Factors affecting unsafe behavior in construction projects: Development and validation of a new questionnaire. Int. J. Occup. Saf. Ergon. 2018, 26, 219–226. [Google Scholar] [CrossRef] [PubMed]
- Silva, S.A.; Araújo, A.; Costa, D.; Meliá, J.L. Safety climates in construction industry: Understanding the role of construction sites and workgroups. Open J. Saf. Sci. Technol. 2013, 3, 80–86. [Google Scholar] [CrossRef] [Green Version]
- Paolillo, A.; Silva, S.A.; Carvalho, H.; Pasini, M. Exploring patterns of multiple climates and their effects on safety performance at the department level. J. Saf. Res. 2020, 72, 47–60. [Google Scholar] [CrossRef]
- Mohammadi, A.; Tavakolan, M. Identifying safety archetypes of construction workers using system dynamics and content analysis. Saf. Sci. 2020, 129, 104831. [Google Scholar] [CrossRef]
- Martínez-Aires, M.D.; Rubio-Gamez, M.; Gibb, A. Prevention through design: The effect of European Directives on construction workplace accidents. Saf. Sci. 2010, 48, 248–258. [Google Scholar] [CrossRef] [Green Version]
- Zhi, H. Risk management for overseas construction projects. Int. J. Proj. Manag. 1995, 13, 231–237. [Google Scholar] [CrossRef]
- Allen, E.; Iano, J. Fundamentals of Building Construction: Materials and Methods; John Wiley & Sons, Inc.: Hoboken, NJ, USA, 2019. [Google Scholar]
- Gao, Y.; González, V.A.; Yiu, T.W. Exploring the relationship between construction workers’ personality traits and safety behavior. J. Constr. Eng. Manag. 2020, 146, 04019111. [Google Scholar] [CrossRef]
- Haslam, R.; Hide, S.; Gibb, A.; Gyi, D.; Pavitt, T.; Atkinson, S.; Duff, A. Contributing factors in construction accidents. Appl. Ergon. 2005, 36, 401–415. [Google Scholar] [CrossRef] [Green Version]
- Fakhratov, M.; Sinenko, S.; Akbari, M.; Asayesh, F. Determination of fundamental criteria in the selection of a construction system. In Proceedings of the E3S Web of Conferences, Khabarovsk, Russia, 24–26 October 2019. [Google Scholar] [CrossRef] [Green Version]
- Forteza, F.J.; Sesé, A.; Carretero-Gómez, J.M. CONSRAT. Construction sites risk assessment tool. Saf. Sci. 2016, 89, 338–354. [Google Scholar] [CrossRef]
- Tepeli, E.; Taillandier, F.; Breysse, D. Multidimensional modelling of complex and strategic construction projects for a more effective risk management. Int. J. Constr. Manag. 2019, 1–22. [Google Scholar] [CrossRef]
- Mohamed, S.; Ali, T.; Tam, W. National culture and safe work behaviour of construction workers in Pakistan. Saf. Sci. 2009, 47, 29–35. [Google Scholar] [CrossRef]
- Bhandari, S.; Hallowell, M.R.; Van Boven, L.; Welker, K.M.; Golparvar-Fard, M.; Gruber, J. Using augmented virtuality to examine how emotions influence construction-hazard identification, risk assessment, and safety decisions. J. Constr. Eng. Manag. 2020, 146, 04019102. [Google Scholar] [CrossRef]
- Neal, A.F.; Griffin, M.A.; Hart, P. The impact of organizational climate on safety climate and individual behavior. Saf. Sci. 2000, 34, 99–109. [Google Scholar] [CrossRef]
- Trinh, M.T.; Feng, Y. Impact of project complexity on construction safety performance: Moderating role of resilient safety culture. J. Constr. Eng. Manag. 2020, 146, 04019103. [Google Scholar] [CrossRef]
- Birhane, G.E.; Yang, L.; Geng, J.; Zhu, J. Causes of construction injuries: Review. Int. J. Occup. Saf. Ergon. 2020, 1–26. [Google Scholar] [CrossRef]
- Rozenfeld, O.; Sacks, R.; Rosenfeld, Y.; Baum, H. Construction job safety analysis. Saf. Sci. 2010, 48, 491–498. [Google Scholar] [CrossRef]
- Tixier, J.; Dusserre, G.; Salvi, O.; Gaston, D. Review of 62 risk analysis methodologies of industrial plants. J. Loss Prev. Process. Ind. 2002, 15, 291–303. [Google Scholar] [CrossRef] [Green Version]
- Carpio-de-los-Pinos, A.-J.; González-García, M.N.; Moreu-de-la-Vega, C.; Hosokawa-Menendez, K.H. Idoneidad y discrepancia de métodos de evaluación de riesgos en seguridad y salud aplicados en obras de construcción. Dyna 2017, 92, 214–219. [Google Scholar] [CrossRef] [Green Version]
- Forteza, F.J.; Sesé, A.; Carretero, J.M. Herramienta global para la evaluación de obras de construcción. In Proceedings of the 15th International Conference on Occupational Risk Prevention, Santiago de Chile, Chile, 23–26 November 2015; Available online: https://www.prevencionintegral.com/canal-orp/papers/orp-2015/ (accessed on 31 August 2020).
- Pinto, A. QRAM a Qualitative Occupational Safety Risk Assessment Model for the construction industry that incorporate uncertainties by the use of fuzzy sets. Saf. Sci. 2014, 63, 57–76. [Google Scholar] [CrossRef]
- Farid, W.; Kureshi, N.I.; Babar, S.; Mahmood, S. Critical risk factors of construction industry of Pakistan for improving project outcome. Mehran Univ. Res. J. Eng. Technol. 2020, 39, 71–80. [Google Scholar] [CrossRef] [Green Version]
- Segarra, M.; Villena, B.M.; González, M.N.; Romero, Á.; Rodríguez, Á. Occupational risk-prevention diagnosis: A study of construction SMEs in Spain. Saf. Sci. 2017, 92, 104–115. [Google Scholar] [CrossRef]
- Zadeh, L. Fuzzy sets. Inf. Control. 1965, 8, 338–353. [Google Scholar] [CrossRef] [Green Version]
- Reyes, J.P.; San-José, J.T.; Cuadrado, J.; Sancibrian, R.; Lombera, J.T.S.J. Health & Safety criteria for determining the sustainable value of construction projects. Saf. Sci. 2014, 62, 221–232. [Google Scholar] [CrossRef]
- Sousa, V.; Almeida, N.; Dias, L.A. Risk-based management of occupational safety and health in the construction industry—Part 1: Background knowledge. Saf. Sci. 2014, 66, 75–86. [Google Scholar] [CrossRef]
- Salanova, M.; Gracia, E.; Lorente, L. Riesgos psicosociales en trabajadores de la construcción. Gestión Práctica Riesgos Labor. 2007, 44, 12–19. [Google Scholar]
- Úbeda de Mingo, P. Espacio: Roles, Ritos y Valores entre los Constructores de Edificios; Colegio Oficial de Aparejadores y Arquitectos Técnicos de Granada: Granada, Spain, 2002; pp. 1–286. [Google Scholar]
- De Oliveira, C.G. Proposta de uma Metodologia Integrada de Avaliação de Riscos Profissionais. Ph.D. Thesis, University of Leon, Leon, Spain, 2019. [Google Scholar]
- Sanni-Anibire, M.O.; Mahmoud, A.S.; Hassanain, M.A.; Salami, B.A. A risk assessment approach for enhancing construction safety performance. Saf. Sci. 2020, 121, 15–29. [Google Scholar] [CrossRef]
- Lucchini, R.G.; London, L. Global occupational health: Current challenges and the need for urgent action. Ann. Glob. Heal. 2014, 80, 251–256. [Google Scholar] [CrossRef] [Green Version]
- Avdiu, B.; Nayyar, G. When Face-To-Face Interactions Become an Occupational Hazard: Jobs in the Time of COVID-19; World Bank Policy Research Working Paper No. 9240. Available online: https://ssrn.com/abstract=3599547 (accessed on 31 August 2020).
- Claudino Véras, J. Método para la Evaluación de Riesgos Laborales en Obras de Construcción de Grandes Viaductos. Ph.D. Thesis, Universitat Politècnica de Catalunya. Departament d’Enginyeria de la Construcció, Barcelona, Spain, 2012. [Google Scholar]
- Carpio, A.J. Nueva Metodología de Evaluación de Riesgos Laborales Adaptada a Obras de Edificación: Nivel de la Acción Preventiva. Ph.D. Thesis, Universidad Politécnica de Madrid, Madrid, Spain, 2017. [Google Scholar] [CrossRef] [Green Version]
- Carpio, A.J.; González, M.N. Critical analysis of risk assessment methods applied to construction works. Rev. Constr. 2017, 16, 104–114. [Google Scholar] [CrossRef]
- Lee, W.; Migliaccio, G.C.; Lin, K.-Y.; Seto, E. Workforce development: Understanding task-level job demands-resources, burnout, and performance in unskilled construction workers. Saf. Sci. 2020, 123, 104577. [Google Scholar] [CrossRef]
- Espinheira, I.; Duarte, J.; Baptista, J.S. Risk assessment associated with the use of manual commands in an industry. In Occupational and Environmental Safety and Health II. Studies in Systems, Decision and Control; Arezes, P., Ed.; Springer: Cham, Switzerland, 2020; Volume 277, pp. 115–121. [Google Scholar]
- Fine, W.T. Mathematical Evaluations for Controlling Hazards. J. Safety Res. 1971, 3, 157–166. [Google Scholar] [CrossRef]
- Fernández, M.D.; Larrañaga, E.G.; Goméz, E.F.; Fernández, J.M.; Alonso, F.R. Implicación de las Personas en la Evaluación de Riesgos Laborales; INSST: Madrid, Spain, 1996; pp. 1–13. [Google Scholar]
- Nogareda, C. NTP 210: Análisis de las Condiciones de Trabajo: Método de la A.N.A.C.T; INSST, Ministerio de Trabajo y Asuntos Sociales: Madrid, Spain, 1988. [Google Scholar]
- Chavarría, R. NTP-176: Evaluación de las Condiciones de Trabajo: Método de los Perfiles de Puestos; INSST, Ministerio de Trabajo y Asuntos Sociales: Madrid, Spain, 1986. [Google Scholar]
- Bestratén, M. Evaluación de las Condiciones de Trabajo en Pequeñas y Medianas Empresas. Metodología Práctica; INSST, Ministerio de Trabajo y Asuntos Sociales: Madrid, Spain, 2000; pp. 1–21. [Google Scholar]
- Jannadi, O.A.; Almishari, S. Risk assessment in construction. J. Constr. Eng. Manag. 2003, 129, 492–500. [Google Scholar] [CrossRef]
- Prieto, M. Educar contra el estrés. Sal Terrae Rev. Teol. Pastor. 2006, 94, 373–384. [Google Scholar]
- Martín, P.; Salanova, M.; Peiró, J.M. El estrés laboral: ¿Un concepto cajón-de-sastre? Proy. Soc. Rev. Relac. Labor. 2003, 10–11, 167–186. [Google Scholar]
- Thayer, R.E. The Origin of Everyday Moods. Managing Energy, Tension and Stress; Oxford University Press, Inc.: New York, NY, USA, 1996. [Google Scholar]
- Lorento, L.; Salanova, M.; Martínez, I.M. La relación entre el exceso de confianza y los accidentes laborales en trabajadores de la construcción: Un estudio cualitativo. Gestión Práctica Riesgos Labor. 2011, 86, 8–13. [Google Scholar]
- Supriadi, L.S.R.; Sui Pheng, L. Mainstream theories: Implementation by contractors. In Business Continuity Management in Construction; Management in the Built Environment; Springer: Singapore, 2018; pp. 101–116. [Google Scholar] [CrossRef]
- Oswald, D.; Ahiaga-Dagbui, D.D.; Sherratt, F.; Smith, S.D. An industry structured for unsafety? An exploration of the cost-safety conundrum in construction project delivery. Saf. Sci. 2020, 122, 104535. [Google Scholar] [CrossRef]
Number of Inspection | Date | Num. | Constructive Systems | Workers Surveyed |
---|---|---|---|---|
1 | 2016-06-17 | 1 | Foundations | 9 |
2 | 2016-06-23 | 2 | Sewer inst. | 9 |
3 | Plumbing Inst. | |||
4 | Foundations | |||
3 | 2016-07-01 | 5 | Foundations | 10 |
6 | Slab | |||
4 | 2016-07-06 | 7 | Facade | 8 |
8 | Foundations | |||
5 | 2016-07-12 | 9 | Foundations | 10 |
10 | Urbanization | |||
6 | 2016-07-14 | 11 | Facade | 14 |
12 | Foundations | |||
7 | 2016-07-26 | 13 | Foundations | 9 |
14 | Foundations | |||
8 | 2016-08-01 | 15 | Slab | 8 |
9 | 2016-08-10 | 16 | Facade | 5 |
10 | 2016-08-19 | 17 | Facade | 8 |
11 | 2016-08-26 | 18 | Slab | 6 |
19 | Facade | |||
12 | 2016-09-06 | 20 | Slab | 5 |
13 | 2016-09-14 | 21 | Facade | 5 |
14 | 2016-09-22 | 22 | Slab | 8 |
23 | Facade | |||
24 | Partitions | |||
15 | 2016-10-06 | 25 | Stairs | 8 |
26 | Facade | |||
27 | Stairs | |||
16 | 2016-10-14 | 28 | Partitions | 7 |
29 | Partitions | |||
17 | 2016-10-18 | 30 | Partitions | 4 |
18 | 2016-10-26 | 31 | Roof | 4 |
19 | 2016-11-08 | 32 | Roof | 7 |
33 | Partitions | |||
20 | 2016-11-17 | 34 | Roof | 7 |
35 | Plumbing Inst. | |||
21 | 2016-11-21 | 36 | Roof | 4 |
37 | Roof | |||
22 | 2016-12-16 | 38 | Roof | 11 |
39 | Roof | |||
40 | Plumbing Inst. | |||
23 | 2017-01-04 | 41 | Coating | 12 |
42 | Partitions | |||
43 | Facade | |||
24 | 2017-02-12 | 44 | Coating | 7 |
45 | Partitions | |||
25 | 2017-01-19 | 46 | Facade | 10 |
47 | Coating | |||
48 | Urbanization | |||
26 | 2017-01-25 | 49 | Flooring | 8 |
50 | Partitions | |||
27 | 2017-02-03 | 51 | Flooring | 7 |
52 | Facade | |||
28 | 2017-02-17 | 53 | Flooring | 10 |
54 | Electricity Inst | |||
29 | 2017-02-24 | 55 | Urbanization | 13 |
56 | Plumbing Inst. | |||
57 | Coating | |||
58 | Coating | |||
59 | Coating | |||
30 | 2017-03-02 | 60 | Coating | 6 |
61 | Flooring | |||
62 | Roof | |||
31 | 2017-03-16 | 63 | Flooring | 12 |
64 | Facade | |||
32 | 2017-03-30 | 65 | Partitions | 11 |
66 | Coating | |||
67 | Facade | |||
68 | Foundations | |||
33 | 2017-04-10 | 69 | Coating | 11 |
70 | Foundations | |||
34 | 2017-04-27 | 71 | Urbanization | 6 |
72 | Coating | |||
73 | Urbanization |
Risk Estimation | Severity of the Consequences | |||
---|---|---|---|---|
Slightly Damaging | Damaging | Extremely Damaging | ||
Probability | Low | Trivial risk | Tolerable risk | Moderate risk |
Medium | Tolerable risk | Moderate risk | Significant risk | |
High | Moderate risk | Significant risk | Intolerable risk |
Risk Estimation | Severity of the Consequences | |||||||
---|---|---|---|---|---|---|---|---|
Slightly Damaging | Damaging | Extremely Damaging | ||||||
1 | 3 | 5 | ||||||
Probability | Low | 1 | Trivial | 1 | Tolerable | 3 | Moderate low | 5 |
Medium | 3 | Tolerable | 3 | Moderate high | 9 | Significant | 15 | |
High | 5 | Moderate low | 5 | Significant | 15 | Intolerable | 25 |
Relative Risk–Complexity of the Unit of Work Observed | ||||||||
---|---|---|---|---|---|---|---|---|
Construction Factor | Low Complexity | Medium | High Complexity | Characteristic Value | ||||
1 | 3 | 5 | 9 | 15 | 25 | |||
Graphics | Without graphics | Verbal indication | Sketch | Technical detail | Formal plan | Technical equipment | 9 | Average: |
Setting-out | Without reformulation | Reformulation by workman | Reformulation by supervisor | Reformulation by project manager | Technical equipment | Technical precision | 5 | 8.25 |
Workers | 1 | 2 | 3 | 4 | 5 | ≥6 | 9 | |
Qualification | Laborer | Foreman | Supervisor | Manager | Project Manager | Expert | 5 | |
Auxiliary Systems Level | Ground level | ≤1 m | ≤3 m | ≤5 m | ≤9 m | >9 m | 15 | Total: |
Tools, Machinery | None | Handheld tool | Hand-operated machine | Average vehicle | Heavy vehicle | HGV | 15 | 9 |
Material Weight | Light | ≤9 kg | ≤50 kg | ≤150 kg | ≤500 kg | >500 kg | 3 | |
Manageability | 1 person | 2 people | 3 people | With a machine | With a crane | Complex system | 5 |
Borderline Risk–Position of the Unit of Work Under Observation | |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Place | Specification | Height from the Ground | Characteristic Value | ||||||||||||
<1 m | <3 m | <5 m | <9 m | <15 m | >15 m | ||||||||||
Safe Area | Within Safe Area (S) | >125 | 1 | >125 | 2 | >150 | 4 | >175 | 7 | >200 | 12 | >225 | 19 | Height | 6 |
Borderline Area | Close to Borderline Area (BA) | 125 | 1 | 125 | 2 | 150 | 4 | 175 | 8 | 200 | 14 | 225 | 21 | 5 | |
Borderline (B) | 100 | 1 | 100 | 3 | 125 | 5 | 150 | 9 | 175 | 15 | 200 | 22 | Area | 6 | |
Close to Area of Risk (AR) | 75 | 2 | 75 | 4 | 100 | 6 | 125 | 10 | 150 | 16 | 175 | 23 | R | ||
Area of Risk | Within Area of Risk (R) | <75 | 2 | <75 | 4 | <100 | 6 | <125 | 11 | <150 | 18 | <175 | 25 | 6 |
Degree of Exposure to Risk | ||||||
---|---|---|---|---|---|---|
Intensity of the Exposure | Number of Times that Workers are Exposed to the Risk During the Observation Period | Characteristic Value | ||||
During the Execution of the Unit of Work | In the Work Environment and Accesses to It | |||||
High | Continual | The worker remains exposed to the risk | Dangerous internal and/or external risks | 25 | 25 | 12 |
Frequent | The worker remains intermittently exposed | There is a high internal risk and high external risks | 15 | 15 | ||
Medium | Occasional | The worker is exposed to the risk more than 5 times during observation | There are high internal risks and/or low external risks | 9 | 9 | 15 |
Unusual | The worker is exposed to the risk between 2 and 5 times during observation | There is a low internal riskand low external risk | 5 | 5 | ||
Low | Rare | The worker is exposed to the risk 1 or 2 times during observation | There is no internal risk and/or there is a low external risk | 3 | 3 | |
Never | The worker is not exposed to the situation of risk | There are neither internal nor external risks | 1 | 1 |
Economic Capacity-Organizational Procedure for Work Execution and Safety | ||||||||
---|---|---|---|---|---|---|---|---|
Procedures | Low | Medium | High | Characteristic Value | ||||
1 | 3 | 5 | 9 | 15 | 25 | |||
Individual Organization | Significant error | Highly disorganized | Little order | Order | Coordinated | Accurate | 9 | 5.40 |
Team Organization | Errors | Disorganized | Little order | Order | Coordinated | Accurate | 5 | |
Work Organization | Errors | Disorganized | Little order | Order | Coordinated | Accurate | 5 | |
Individual Protection | None | 2 teams | 4 teams | 5 teams | 6 teams | >6 teams | 3 | 5 |
Collective Safeguards | None | Very high risk | High risk | Medium risk | Low risk | 100% free of risk | 5 |
Participative Interest–Participative Interest in Risk Prevention | ||||||||
---|---|---|---|---|---|---|---|---|
Procedure | Low | Medium | High | Characteristic Value | ||||
1 | 3 | 5 | 9 | 15 | 25 | |||
Worker Information | No Information | Little Information | Adequate Information | A lot of Information | Significant Information | Demands Information | 5 | 3.50 |
Individual Participation | Does not participate | Barely participates | Participates a little | Participates a lot | Participates significantly | Demands safety | 5 | |
Group Participation | Do not participate | Barely participate | Participate a little | Participate a lot | Participate significantly | Demand safety | 3 | 3 |
External Appearance of Site | No safety | Scarce safety | Little safety | Offers safety | Significant safety | Well maintained | 1 |
Level of Satisfaction—1. Survey Carried Out On-Site | ||||||||||||||||||||||||||||||
Personal Perception | Perception of Risk | Congruence | ||||||||||||||||||||||||||||
Perception of the Environment | Perception of Safety | |||||||||||||||||||||||||||||
Emotional States | Energy | Personal Satisfaction | Job Satisfaction | Difficulty of the unit of work | Danger of the environment of the unit of work | Individual participation in safety of unit of work | Group participation in site safety in general | Complete Individual Protective Equipment | Collective safeguards | Personal Perception | Worker’s perception of risk | Assessor’s perception of risk | Total | |||||||||||||||||
Laborer | Assessor | Laborer | Assessor | Laborer | Assessor | Laborer | Assessor | Laborer | Assessor | Laborer | Assessor | |||||||||||||||||||
6 | 6 | 6 | 6 | 1 | 1 | 3 | 5 | 6 | 25 | 5 | 15 | 6 | 25 | 5 | 15 | 9 | 0.1 | 0.3 | 13 | |||||||||||
9 | 9 | 9 | 9 | 4 | 9 | 5 | 15 | 1 | 1 | 2 | 3 | 1 | 1 | 1 | 1 | 1 | 3 | |||||||||||||
Level of Satisfaction—2. Congruence of the Perception of Risk | ||||||||||||||||||||||||||||||
Influence | Zero | Very slight | Slight | Notable | Considerable | High | Characteristic Value | |||||||||||||||||||||||
Personal Perception | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 13 | 12.33 | |||
Congruence of Safety | 0 | 0.2 | 0.4 | 0.6 | 0.8 | 1 | 1.2 | 1.4 | 1.6 | 1.8 | 2 | 0.6 | ||||||||||||||||||
Perception of Safety | 1 | 3 | 5 | 9 | 15 | 25 | 15 | 9 | 5 | 3 | 1 | 9 | 15 | |||||||||||||||||
Congruence of the Environment | 0 | 0.2 | 0.4 | 0.6 | 0.8 | 1 | 1.2 | 1.4 | 1.6 | 1.8 | 2 | 1.1 | ||||||||||||||||||
Perception of the Environment | 1 | 3 | 5 | 9 | 15 | 25 | 15 | 9 | 5 | 3 | 1 | 15 |
Risks to Assess | Observation environments | Preventive Action | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Absolute | Documentary | Construction | Social | |||||||||
Code | Description | C | P | Abr | Rr | Br | E | Ec | Ri | Ls | Apac | Lpac |
Characteristic values | ||||||||||||
9 | 6 | 15 | 5 | 3 | 5 | 3.60 | ||||||
010 | Different level | 5 | 5 | 25 | 8 | 7 | 15 | 4 | 4 | 12 | 4.38 | 18% |
020 | Same level | 3 | 3 | 9 | 10 | 5 | 12 | 4 | 4 | 12 | 3.13 | 35% |
040 | Handling | 3 | 5 | 15 | 9 | 5 | 12 | 6 | 4 | 14 | 1.61 | 11% |
110 | Entrapment | 1 | 3 | 3 | 10 | 5 | 12 | 5 | 4 | 15 | 2.00 | 67% |
350 | Thermal | 3 | 3 | 9 | 7 | 5 | 12 | 4 | 4 | 16 | 1.64 | 18% |
380 | Lighting | 1 | 5 | 5 | 8 | 5 | 13 | 4 | 4 | 13 | 2.50 | 50% |
420 | Movement | 3 | 3 | 9 | 10 | 5 | 16 | 6 | 4 | 12 | 2.78 | 31% |
440 | Loads | 1 | 5 | 5 | 9 | 5 | 15 | 4 | 4 | 12 | 3.52 | 70% |
560 | Relationships | 1 | 5 | 5 | 8 | 2 | 12 | 4 | 4 | 15 | 0.80 | 16% |
570 | Organization | 1 | 3 | 3 | 10 | 2 | 14 | 6 | 4 | 16 | 0.73 | 24% |
Levels of Control | Exigency Factor for Controlling Preventive Action | |||||||
---|---|---|---|---|---|---|---|---|
Color | ε = 0.4 | ε = 1 | ε = 2 | ε = 4 | ε = 5.4 | ε = 10 | ε = 20 | |
Exhaustive control | 10.0 | 25.0 | 50.0 | 100.0 | 135.0 | 250.0 | 500.0 | |
Intensive control | 6.0 | 15.0 | 30.0 | 60.0 | 81.0 | 150.0 | 300.0 | |
Greater control | 3.6 | 9.0 | 18.0 | 36.0 | 49.0 | 90.0 | 180.0 | |
More control | 1.2 | 5.0 | 10.0 | 20.0 | 27.0 | 50.0 | 100.0 | |
Adequate control | 0.4 | 3.0 | 3.0 | 12.0 | 16.0 | 30.0 | 60.0 | |
Optimal control | 0.1 | 1.0 | 2.0 | 4.0 | 5.0 | 10.0 | 20.0 |
Code | Risk | Tolerance | Apac | Lpac | Control | Technique | Lpac |
---|---|---|---|---|---|---|---|
010 | Different level | Intolerable | 4.38 | 18% | More control | Safety | 32% |
020 | Same level | Moderate high | 3.13 | 35% | Intensive control | ||
040 | Handling | Significant | 1.61 | 11% | Adequate control | ||
110 | Entrapment | Tolerable | 2.00 | 67% | Exhaustive control | ||
350 | Thermal | Moderate high | 1.64 | 18% | More control | Hygiene | 34% |
380 | Lighting | Moderate | 2.50 | 50% | Intensive control | ||
420 | Movement | Moderate high | 2.78 | 31% | Greater control | Ergonomics | 51% |
440 | Loads | Moderate | 3.52 | 70% | Exhaustive control | ||
560 | Relationships | Moderate | 0.80 | 16% | More control | Psychology | 20% |
570 | Organization | Tolerable | 0.73 | 24% | Greater control |
© 2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Carpio-de los Pinos, A.J.; González-García, M.d.l.N. Development of the Protocol of the Occupational Risk Assessment Method for Construction Works: Level of Preventive Action. Int. J. Environ. Res. Public Health 2020, 17, 6369. https://doi.org/10.3390/ijerph17176369
Carpio-de los Pinos AJ, González-García MdlN. Development of the Protocol of the Occupational Risk Assessment Method for Construction Works: Level of Preventive Action. International Journal of Environmental Research and Public Health. 2020; 17(17):6369. https://doi.org/10.3390/ijerph17176369
Chicago/Turabian StyleCarpio-de los Pinos, Antonio José, and María de las Nieves González-García. 2020. "Development of the Protocol of the Occupational Risk Assessment Method for Construction Works: Level of Preventive Action" International Journal of Environmental Research and Public Health 17, no. 17: 6369. https://doi.org/10.3390/ijerph17176369
APA StyleCarpio-de los Pinos, A. J., & González-García, M. d. l. N. (2020). Development of the Protocol of the Occupational Risk Assessment Method for Construction Works: Level of Preventive Action. International Journal of Environmental Research and Public Health, 17(17), 6369. https://doi.org/10.3390/ijerph17176369