1. Introduction
Amid rapid economic growth and continuous urbanization, cities are witnessing an influx of people, which leads to urban syndromes such as an over-saturated population, congested building spaces, and dwindling green areas [
1,
2]. Underground spaces provide a safe and comfortable supplementary environment for human life; their effective utilization can alleviate urban syndromes while generating substantial economic benefits. Since the 21st century, China has experienced accelerated underground space construction, particularly in urban tunnels, with 406 urban tunnels built across 82 cities by 2021 [
3], as shown in
Figure 1. However, due to the complexity of city environments and limited underground space availability, numerous urban tunnels must coexist within a single region, resulting in the emergence of a new tunnel structure form—the urban intersection tunnel. With its ability to meet actual engineering construction requirements, reduce engineering volume, and accommodate diverse terrain conditions [
4,
5], intersection tunnel construction is progressively increasing in cities, including Beijing, Guangdong, and Chongqing, where they have been incorporated into underground engineering projects.
Constructing urban intersection tunnels is more challenging compared to ordinary highway tunnels. On the one hand, the unique structure of urban intersection tunnels leads to repeated disturbances to the surrounding rock during construction, impacting the stability of existing and under-construction tunnels. On the other hand, these projects have distinctive geological environments, with rock strata deformation induced by construction activities posing threats to the safety of ground buildings. Consequently, ensuring the stability and safety of existing tunnels, under-construction tunnels, and ground buildings is a critical challenge in urban intersection tunnel construction.
Numerous scholars have investigated the construction stability of urban intersection tunnels, focusing on mechanical behavior, spatial position relationships, intersection angles, and excavation methods through theoretical analysis, on-site measurements, and numerical simulation methods [
6,
7,
8]. Song and Wu [
9] carried out dynamic monitoring of the cross-section of a soft rock tunnel with a small vertical distance and analyzed the stress and strain characteristics of the surrounding rock and supporting structure. Based on the Zou Magang highway tunnel project, Chen et al. [
10] conducted dynamic monitoring measurements on excavating tunnel and existing tunnel, respectively, during cross-section tunnel construction, then obtained mechanical behavior characteristics of surrounding rock and supporting structure of the tunnels. By means of numerical simulation, Li et al. [
11] studied variations of stress, displacement, and plastic zone of surrounding rock before and after deep-buried intersection tunnel excavation in long-span highway tunnel engineering. It was considered that the angle between axial and horizontal stress and the cross angle were the two most important factors affecting the stability of the surrounding rock in the cross-section. Nonomura et al. [
12] analyzed the stress state of the surrounding rock and supporting structure of the cross-section tunnel and obtained a variation range of stress, displacement, and plastic zone of surrounding rock in cross-section before and after the new tunnel construction. Sharifzadeh et al. [
13] utilized a three-dimensional numerical simulation to analyze the stability of surrounding rock in cross-sections of large-span city tunnels with soft rock in the process of tunnel excavation with the CD method and the SD method.
Building a tunnel in an urban area, especially in a Central Business District (CBD), would involve the tunnel through or near existing ground buildings. In order to research the influence of tunnel construction on the stability of adjacent structures, scholars have analyzed the deformation characteristics of adjacent structures by numerical simulation, on-site measurement, and monitoring [
14,
15,
16]. Shi et al. [
17] applied the random medium theory to analyze surface movement and deformation along the tunnel’s vertical and horizontal direction caused by the excavation of a shallow buried section in Tong You Mountain multi-arch tunnel engineering and evaluated the influence of tunnel excavation on upper surface buildings. Taking the existing independent foundation frame structure on the upper part of the tunnel as the research object, Liu [
18] analyzed the formation disturbance mechanism, calculated the additional internal force of the frame structure under uneven settlement, and obtained the variation curve of the formation settlement with time through similar model testing. Then, a series of protection measures for rock strata and buildings were proposed. Mroueh and Shahrour [
19] utilized three-dimensional finite element and finite difference methods to perform numerical simulation on shield tunnel construction and surrounding buildings, studied the influence of weight and stiffness of buildings on surface displacement and believed that subsidence would occur in the area where buildings exist. Richard et al. [
20] proposed a rolling beam model to analyze the deformation of ground three-dimension frame structures caused by deep excavation and evaluated damage to the buildings by considering the types of buildings and positions of doors and windows, beams, and columns.
Existing studies and fieldwork indicate that appropriate construction methods can mitigate stress concentrations and rock strata deformation, making them essential for addressing these challenges [
21,
22]. The New Austrian Tunneling Method (NATM), known for its minimal construction disturbance and rapid closure, is frequently employed in tunnel projects characterized by complex geological and construction conditions [
23]. NATM encompasses various excavation techniques, including the full-section method, step method, and center cross diagram (CRD) method, each of which exerts a varying degree of impact on the surrounding rock. Consequently, investigating the influence of construction methods on the stability of surrounding rock can serve as a foundation for selecting the appropriate construction method. In this study, we investigate an underground circular road engineering project located in the CBD of Chongqing, China. Our objective is to assess the impact of different construction methods on the safety and stability of urban intersection tunnels through numerical simulations. Subsequently, we validate these numerical simulation results by conducting field monitoring measurements. Lastly, we discuss the effects of the three construction methods on the safety and stability of urban intersection tunnel construction. Our study not only confirms the minimal disturbance to the surrounding rock achieved through NATM but also explores the variations in stress and deformation within the rock strata under different construction methods. Ultimately, we derive the most suitable construction method for the engineering project. These findings offer valuable insights for the selection of construction methods for urban intersection tunnels and present a practical approach for evaluating such methods.
This paper comprises six interrelated sections, each providing a comprehensive perspective on the research.
Section 1 offers an overview of the research’s significance and its current status.
Section 2 describes the NATM theory and common urban tunnel construction methods. The project overview of the urban intersection tunnel is presented in
Section 3. Information on the numerical model and simulation results are shown in
Section 4.
Section 5 provides an assessment of the three construction methods, along with a description of the field monitoring process. Finally,
Section 6 wraps up our study with a comprehensive conclusion.
3. Project Overview
The CBD, established in 1997 in Chongqing, China, faced several traffic challenges, including insufficient parking spaces, scattered parking garages, numerous garage entrances and exits, and difficult driving conditions. To address these issues and ensure smooth traffic flow, an underground circular roads project was constructed in the CBD, utilizing the principles of utilization, transformation, and local new construction. The project included a 2580 m long excavation tunnel, comprised of one main tunnel and five branch tunnels, several of which intersected. The mileage segment K1+000~K1+160 of the main tunnel and mileage segment K0+380~K0+420 of the branch tunnel 1# intersected vertically at 40 m underground, as shown in
Figure 3. The hydrogeological conditions of the project were simple, and the groundwater was mainly bedrock fissure water. The surrounding rock of the intersection tunnel was mainly sandstone with two groups of fractures, classified as soft rock of grade IV. The surface plain fill was 4 m thick; the physical and mechanical parameters of each soil layer are shown in
Table 1. The main tunnel was 9.5 m in width and 5.5 m in height, the branch tunnel #1 was 7.0 m in width and 5.5 m in height, and the cross-sections of both were semicircular arch. The main tunnel was excavated after completion of the branch tunnel #1. There was an affected ground building with a height of 35 m and depth of 10 m, 7 floors on the ground, and 2 floors underground north of the intersection section tunnel, and the minimum distance between it and the ground projection of the intersecting section was 5 m.
In constructing the main tunnel, the safety of the tunnel itself, the disturbance effect on branch tunnel #1, and the stability of the nearby ground building had to be taken into account. The choice of tunnel construction method was crucial in ensuring the safety and stability of the tunnel structure and the ground building. To provide a basis for selecting a suitable construction method, a numerical simulation work was conducted to analyze the impact of different construction methods on the stability of tunnel construction. The simulation work would consider factors such as rock conditions, tunnel dimensions, and proximity to ground structures, ultimately providing valuable insights into the most appropriate construction method for the intersection tunnel engineering project. By selecting the optimal construction method, the project can ensure the safety of the tunnel structure, minimize disturbance to adjacent tunnels, and maintain the stability of nearby ground buildings.
5. Discussion
In the construction of urban intersection tunnels, the choice of appropriate excavation methods is crucial for ensuring the safety and stability of the excavating tunnel, the existing tunnel, and ground buildings. Thus, it was necessary to evaluate the construction methods from the perspective of engineering safety and stability.
5.1. Evaluation Criterion
Excavating tunnel safety could be evaluated by comparing the extreme stress of surrounding rock with the safety strength of the lining materials, such as concrete C30. This comparison would determine the safety degree of the excavating tunnel under different construction methods. The safety strength of concrete C30 is shown in
Table 5. For instance, when the maximum compressive stress of the surrounding rock exceeds 14.30 MPa, the excavating tunnel would be crushed, resulting in vault collapse.
In the matter of structural stability of the existing tunnel, which followed the guidelines of China’s national standard, “GB50911-2013 Code for monitoring measurement of urban rail transit engineering”, as shown in
Table 6. Considering the importance of the underground circular roads project, the stability of branch tunnel 1# was evaluated by comparing whether the vault settlement and horizontal convergence of the tunnel exceeded 3 mm. Once the deformation of the existing tunnel (either vault settlement or horizontal convergence) exceeded 3 mm, the tunnel was in a state of instability, and collapse occurred.
In addition, the safety of the affected ground building followed China’s national standard, “GB50007-2011 Code for design of building foundation”, and analogical engineering subway project in Beijing [
36], as shown in
Table 7. It could be evaluated by comparing the foundation settlement value and overall gradient value with the allowable deformation values of 10 mm and 0.0015, respectively. If the deformation of the ground building reached any of these indicators, it signified an extremely unstable condition. Disasters would occur without reinforcement measures.
Lastly, we established a comprehensive safety evaluation criterion encompassing surrounding rock stress, lining displacement, and ground building deformation for underground circular road engineering, as summarized in
Table 8.
5.2. Construction Methods Analysis
The surrounding rock stress and branch tunnel 1# deformation and ground building deformation under the three construction methods are shown in
Figure 12. By analyzing surrounding rock stress, the CRD method was found to be more suitable for urban intersection tunnel construction, as it resulted in lower maximum compressive and tensile stresses on surrounding rock compared to the full-section method and step method. Although all three methods were within the allowable criterion of surrounding rock stress, the CRD method offered a higher degree of safety. By analyzing ground building deformation, all three methods were considered suitable for urban intersection tunnel construction, as the overall gradient values and maximum foundation settlement values were within the allowable criterion for each method. The differences in deformation amounts among the methods were minimal. By analyzing branch tunnel 1# deformation, the CRD method was found to be more suitable for urban intersection tunnel construction, as it resulted in the smallest maximum vault subsidence and horizontal convergence values. Although none of the methods exceeded the safety allowable value of 3 mm, the CRD method provided a higher degree of stability for the branch tunnel 1#.
The comprehensive analysis showed that while all three methods (full-section method, step method, and CRD method) did not negatively affect the safety of the urban intersection tunnel engineering, the CRD excavation method had less influence on the structural stability of both the excavating tunnel and the existing tunnel. As a result, the CRD method was considered more suitable for urban intersection tunnel engineering.
5.3. Field Monitoring
The CRD method, as indicated by the comprehensive analysis, provided greater construction stability for urban intersection tunnels and was subsequently utilized in urban intersection tunnel engineering. The deformation of tunnel sections was monitored on-site during construction. Section K0+415 of branch tunnel 1# was selected for monitoring, as it was 5 meters away from the intersecting section and could represent the maximum deformation of branch tunnel 1#. The vault subsidence and horizontal convergence of section K0+415 within 30 days were monitored and displayed in
Figure 13.
The cumulative vault subsidence amount and cumulative horizontal convergence value both displayed a similar variation trend, increasing gradually with time. The variation curves were divided into three stages. In the rapid deformation stage, the cumulative deformation amounts increased rapidly from the 1st day to the 12th day, with an average daily vault subsidence amount of 0.19 mm and an average daily horizontal convergence value of 0.15 mm. In the slow deformation stage, the cumulative deformation amounts increased slowly from the 13th day to the 25th day, with both the average daily vault subsidence amount and average daily horizontal convergence value being 0.03 mm. In the stable stage, the cumulative deformation amounts remained stable from the 26th day to the 30th day, with both the daily vault subsidence amount and daily horizontal convergence value being close to 0 mm.
Based on these monitoring observations, it was determined that the maximum vault subsidence amount and maximum horizontal convergence value of section K0+415 were 2.480 mm and 2.110 mm. The numerical simulation showed that the corresponding deformation values were 2.361 mm and 2.157 mm, respectively, as shown in
Figure 14. The simulated results were in close agreement with the monitoring data. The error between simulation results and monitoring data was less than 5%, as shown in
Table 9. This consistency validated the accuracy of the numerical simulation.