Next Article in Journal
Determining the Interruptible Load with Strategic Behavior in a Competitive Electricity Market
Previous Article in Journal
Optimal Scheduling of Domestic Appliances via MILP
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Dynamic Economic Dispatch Model Incorporating Wind Power Based on Chance Constrained Programming

School of Mechanical Engineering, Shanghai University of Engineering Science, Shanghai 201620, China
*
Author to whom correspondence should be addressed.
Energies 2015, 8(1), 233-256; https://doi.org/10.3390/en8010233
Submission received: 30 September 2014 / Accepted: 18 December 2014 / Published: 29 December 2014

Abstract

:
In order to maintain the stability and security of the power system, the uncertainty and intermittency of wind power must be taken into account in economic dispatch (ED) problems. In this paper, a dynamic economic dispatch (DED) model based on chance constrained programming is presented and an improved particle swarm optimization (PSO) approach is proposed to solve the problem. Wind power is regarded as a random variable and is included in the chance constraint. New formulation of up and down spinning reserve constraints are presented under expectation meaning. The improved PSO algorithm combines a feasible region adjustment strategy with a hill climbing search operation based on the basic PSO. Simulations are performed under three distinct test systems with different generators. Results show that both the proposed DED model and the improved PSO approach are effective.

Graphical Abstract

1. Introduction

Dynamic economic dispatch (DED), which determines the optimal generation scheme to meet the predicted load demand over a time horizon satisfying the constraint such as ramp-rate limits of generators between time intervals, is crucial for power system operation [1,2,3]. Prior to the widespread use of alternate sources (solar, wind) of energy, the DED problem involved only conventional generators. In recent years, wind power has experienced an explosive growth, and has shown great potential in fuel savings and environmental protection. However, its uncertainty and intermittency also makes it challenging to find a proper dispatch scheme for a wind penetrated power system.
The key issue associated with the incorporation of wind power is how to deal with its fluctuation and intermittence considering the required reliability and security of power systems [2]. Up to now, different authors have proposed models to solve economic dispatch (or unit commitment) problems for wind-penetrated power systems [4,5,6,7,8,9,10,11,12,13,14,15,16]. Chen [4] proposed a method to incorporate wind generators into the generation scheduling problem. Special reserve constraints are established to operate the power system within the required stability margin, which is also adopted by Zhou et al. [5] and Jiang et al. in [6]. These models are deterministic and cannot accurately describe the effect of wind fluctuations on system operation.
To effectively and safely use wind power, researchers usually forecast the wind speed or wind generation over a time horizon in advance, and then obtain the statistic distribution of wind speed or wind generation. Based on the distribution function and estimated loads, researchers can determine the dispatch scheme. Hetzer et al. presented an ED model incorporating wind power with the stochastic wind speed characterization based on the Weibull probability density function [7]. Penalty costs for overestimation and underestimation of available wind energy are also considered. In [8], a modified ED optimization model with wind power penetration is presented, and risk-based up and down spinning reserve constraints are presented considering the uncertainties of available wind power, load forecast error and also generator outage rates. It has been discussed in [9,10,11] that forecasted wind generation usually follows a beta distribution function, and following this, the authors of [12] and [13] proposed ED models incorporating the impact of wind variability. Miranda and Hang developed in [14] an ED model including wind generators using concepts from the fuzzy set theory, and they added a penalty cost factor for not using the available wind power capacity. It is noted clearly in references [7,8,12,13,14] that the constraints of ramp rates are not taken into account. In [15] and [16], a scenario-based approach is utilized to model the uncertainty of wind power and stochastic models are proposed to solve the optimal scheduling of the generators in wind penetrated power system. This scenario approach requires a large number of scenarios to ensure the quality of solution, and usually suffers huge computation cost.
Chance constrained programming (CCP) is a kind of stochastic optimization approach [17]. It is suitable for solving optimization problems with random variables either included in constraints or in the objective function. CCP has been studied to solve the transmission planning problem in [17,18] and the stochastic unit commitment problem with uncertain wind power output in [19]. In [17] and [18], the same formulation of chance constraint is applied to transmission planning, and it is in the form that the not-overload probability for transmission line is required to be more than a specified confidence level. In [19], the chance constraint is applied to describe policies to ensure the utilization of wind power, and a two stage stochastic optimization is presented to solve the unit commitment problem. In this paper, the chance constraint is used to describe that the probability that actual wind generation is greater than or equal to the scheduled wind power is more than a given confidence level.
In a manner somewhat similar to the wind model in [12] and [13], this paper uses a beta distribution to characterize the actual wind generation for each individual period. Up spinning reserve (USR) and down spinning reserve (DSR) are required to deal with the forecasting errors in load and the sudden fluctuations in wind generation [15]. In general, the reserve requirement with respect to forecast errors in load is defined to be a fixed percentage [5] (e.g., 5%) of the load demand. As to the reserve requirements caused by variation of wind generation, up reserve requirement (URR) induced by the sudden fall in wind generation and down reserve requirement (DRR) induced by the sudden raise in wind generation are both taken into account in our work. The conditional expectation when actual wind generation is smaller than the scheduled wind is calculated, and URR is defined as the difference between the scheduled wind power and the conditional expectation of wind power. Similarly, DRR is defined as the difference between the conditional expectation when actual wind generation is greater than or equal to the scheduled wind power and the scheduled wind power.
This paper proposes a stochastic DED model based on chance constraints in wind power penetrated systems. New formulations of the spinning reserve constraints are considered under the expected meaning. An improved particle swarm optimization (PSO) approach is proposed to optimize the model. In order to demonstrate the efficacy of the proposed model and the PSO approach, various comparisons are performed under two different test systems. Results show that the above-mentioned model is effective and the proposed PSO approach is able to solve such model.
The rest of this paper is organized as follows: in Section 2, the stochastic DED model is formulated. Section 3 introduces the beta distribution as the basis of the equivalent transformation of the proposed DED model, and a deterministic DED model is obtained. In Section 4, an improved PSO approach including feasible region adjustment (FRA) strategy and hill climbing search operation (HCSO) is applied to solve the deterministic model. Section 5 presents a discussion of the numerical results. Finally, conclusions are drawn in Section 6.

2. DED Problem Formulation

In this section, the objective function of DED problem is described and the DED model based on CCP is formulated.

2.1. Objective Function

In wind penetrated power systems, wind production is usually regarded as zero cost, the DED model with the valve point effect usually takes the following form [20,21,22,23,24]:
min   f cos t = t = 1 T i = 1 I [ C i ( p i , t ) + E i ( p i , t ) ]
where:
  • f cos t is the total generation cost over the whole time horizon;
  • T is the number of periods;
  • I is the number of thermal units;
  • p i , t is the power output (MW) of the i th unit corresponding to time period t ;
  • C i ( p i , t ) is the generation cost of the i th unit corresponding to time period t ;
  • E i ( p i , t ) is the valve point loading effect of the i th unit corresponding to time period t ;
For the thermal units, the generation cost can be approximated by a quadratic function of the power output, which is practical for most of the cases, and is given by:
C i ( p i , t ) = a i p i , t 2 + b i p i , t + c i
where a i , b i and c i are cost coefficients for the i th unit. E i ( p i , t ) is expressed as follows:
E i ( p i , t ) = | e i sin [ f i ( p i min p i , t ) ] |
where e i and f i are coefficients related to valve point effect of the ith unit. p i min is the minimum generation limit of unit i.

2.2. System and Unit Constraints

This DED problem is subjected to a variety of system and unit constraints, which include power balance constraints, generation limits of units, ramp rate limits and spinning reserve constraints. These constraints are discussed below.

2.2.1. Power Balance Constraints

Total power generation must equal the load demand pd,t in all time period:
i = 1 I p i , t + p w , t = p d , t
where pw,t is the scheduled wind power of wind farm at time t.

2.2.2. Generation Limits of Thermal Units and Wind Farm

The output of each thermal unit and wind farm must lie in between a lower and an upper bound. These constraints are represented as follows:
p i min p i , t p i max
0 p w , t w max
where p i max is the maximum generation limit of thermal unit i, and wmax is the installed capacity of wind farm.

2.2.3. Chance Constraint on Wind Power

Due to the stochastic nature of wind power, the schedule for wind may not be realized on a scheduled day. So we introduce the following chance constraint:
P { w t p w , t } ρ
where wt is a random variable representing the wind power generation at time t. ρ is the confidence level. Equation (7) defines the probability that the scheduled wind power can be realized is greater than or equal to ρ. Furthermore, Equation (7) sets a reasonable upper bound for wind power generation, and the probability that this upper bound can be realized is no less than ρ. The larger the confidence level is, the less stochastic the wind power is, and hence the more reliable the power system is. Especially, when ρ = 1, there is no wind power in system, and the DED problem is changed into a deterministic one.

2.2.4. Ramp Rate Limits of Thermal Units

The ramp rate limits restrict the operating range of all the units for adjusting the generation between two periods. The generation may adjust the dispatch level as:
Δ i , d × T 60 p i , t p i , t 1 Δ i , u × T 60
where p i , t 1 is the output of unit i at time t 1 , and Δ i , u and Δ i , d are the upper and lower ramp rate limits, respectively. T60 is the operating period, i.e., 1 h.

2.2.5. Spinning Reserve Constraints

Due to the penetration of wind power and its intermittent nature, additional reserve needs to be provided to support the wind generation variation [15]. The USR supports the forecast errors in load and a sudden decrease in wind power, and the DSR contributes to the sudden raise in wind power. Both the USR and DSR are supplied by the ramping capacity of thermal units, and are formulated by Equations (9) and (10) respectively:
i n min ( p i , t max p i , t , Δ i , u × T 10 ) p r , t + r w , t u
i n min ( p i , t p i , t min , Δ i , d × T 10 ) r w , t d
where p r , t is the reserve level to support forecast error in demand. T10 is 10 min. p i , t max and p i , t min are upper and lower generation limits of unit i including ramp rate limits at time t, and p i , t max = min ( p i max , p i , t 1 + Δ i , u ) , p i , t min = max ( p i min , p i , t 1 Δ i , d ) . r w , t u and r w , t d are the URFW and the DRRW to follow the sudden decrease and increase in wind power at time t.
Figure 1 shows the conceptual illustration of r w , t u and r w , t d . r w , t u is calculated by the difference between the scheduled wind power and conditional expectation of wind power when the actual wind generation is less than scheduled, and is shown in Equation (11):
r w , t u = p w , t E ( w t | w t < p w , t )
The conditional expectation is obtained by the following equation:
E ( w t | w t < p w ) = 0 p w , t w t f W t ( w t ) d w t 0 p w , t f W t ( w t ) d w t
where f W t ( w t ) is the probability density function of wind power at time t.
Similarly, r w , t d is calculated using the two equations as mentioned in Equations (13) and (14):
r w , t d = E ( w t | w t p w , t ) p w , t
E ( w t | w t p w ) = p w , t w max w t f W t ( w t ) d w t p w , t w max f W t ( w t ) d w t
Figure 1. Concept illustration of r w , t u and r w , t d .
Figure 1. Concept illustration of r w , t u and r w , t d .
Energies 08 00233 g001
Taking a closer look at the optimization model (1)–(14), it contains chance constraint and thus is a stochastic DED model. In the next section we will discuss the equivalent transformation of the stochastic model to a deterministic one.

3. Equivalent Transformation of the DED Model

3.1. Beta Distribution of Wind Power

In the real word, the actual wind generation is a function of wind speed that randomly changes all the time [13]. In our study, normalized wind power in each period is regarded as a random variable which follows beta distribution [9,10,11,12,13]. We denote the probability density function (PDF) by f X t ( x t ) as follows:
f X t ( x t ) = { 1 B ( α , β ) x t α 1 ( 1 x t ) β 1 , 0 < x t < 1 0 ,                                otherwise
where x t = w t / w max , and x t [ 0 , 1 ] . α > 0 , β > 0 , and B ( α , β ) is the well-known beta function defined as:
B ( α , β ) = 0 1 u α 1 ( 1 u ) β 1 d u
Parameters α and β can be determined by following equations:
{ μ t w max = α α + β ( σ t w max ) 2 = αβ ( α + β ) 2 ( α + β + 1 )
where μ t and σ t are the mean value and standard deviation of the predicted wind generation at time t on the scheduling day, respectively. The cumulative density function (CDF) of X can be easily obtained as shown below:
F X t ( x ) = { 0 ,   < x 0 1 B ( α , β ) 0 x u α 1 ( 1 u ) β 1 d u ,   0 < x < 1 1 ,    x 1

3.2. Equivalent Transformation

Putting the aforementioned discussion of the beta distribution, we can get the following CDF ( F W ( w t ) ) of w t :
F W t ( w t ) = P { W t w t } = P { w max X t w t } = F X t ( w t / w max )
Then, Equations (12) and (14) are transformed into the following equations as expressed in Equations (20) and (21) respectively:
E ( w t | w t < p w , t ) = E ( w max x t | x t < p w , t / w max ) = w max 0 p w , t / w max x t f X t ( x t ) d x t 0 p w , t / w max f X t ( x t ) d x t
E ( w t | w t p w , t ) = w max p w , t / w max w max x t f X t ( x t ) d x t p w , t / w max w max f X t ( x t ) d x t
Both Equations (20) and (21) will be solved using numerical integration methods because of the complexity. In addition, we rewrite the Equation (7) as follows:
P { w t p w , t } =   F X t ( z ) ρ
where p w , t / w max = z , form F X t ( z ) = ρ , we learn that z is the upper quantile of F X t ( x t ) , then we get p w , t w max F X t 1 ( 1 ρ ) , and thus obtain the following constraint of scheduled wind power:
0 p w , t w max F X t 1 ( 1 ρ )
Given all that, the equivalent transformation of the stochastic DED model is mathematically represented as:
{ min t = 1 T i = 1 I { a i p i , t 2 + b i p i , t + c i + | e i sin [ f i ( p i min p i , t ) ] | } s . t .    i = 1 I p i , t + p w , t = p d , t p i min p i , t p i max 0 p w , t w max F X t 1 ( 1 ρ ) Δ i , d × T 60 p i , t p i , t 1 Δ i , u × T 60 i I min ( p i , t max p i , t , Δ i , u × T 10 ) p r , t + p w , t w max 0 p w , t / w max x t f X t ( x t ) d x t 0 p w , t / w max f X t ( x t ) d x t i I min ( p i , t p i , t min , Δ i , d × T 10 ) w max p w , t / w max 1 x t f X t ( x t ) d x t p w , t / w max 1 f X t ( x t ) d x t p w , t

4. Improved PSO Approach

The problem in Equation (24) is a high-dimension and non-convex optimization problem, so it is very difficult to find analytical solutions. In recent decades, many salient approaches have been developed to solve such problems, such as genetic algorithm [20,21], differential evolution [22], evolutionary programming [25,26], and PSO [6,27,28,29,30,31,32]. PSO, first introduced by Kennedy and Eberhart, is a population-based optimization technique, and conducts its search using a population of particles [27,28]. Each particle is a candidate solution to the problem and is moved toward the optimal point by adding a velocity with its position. The position and the velocity of the jth particle in the D dimensional search space can be expressed as Y j = [ y j 1 , y j 2 , , y j D ] T and V j = [ v j 1 , v j 2 , , v j D ] T , respectively. Each particle has its own best position ( p b e s t j k , j = 1 , 2 , J ) corresponding to the personal best objective value obtained at generation k. The global best particle is denoted by g b e s t k , which represents the best particle found so far at generation k among the whole population. The new velocity and position of each particle at generation k + 1 are calculated as shown below [6,29]:
V j k + 1 = ω ( k ) V j k + φ 1 ( k ) r a n d 1 k ( p b e s t j k Y j k ) + φ 2 ( k ) r a n d 2 k ( g b e s t k Y j k )
Y j k + 1 = Y j k + V j k + 1   , 1 j J
where:
  • J is the population size;
  • ω ( k ) is the dynamic inertia weight factor, and can be dynamically set with the following equation [6]:
ω ( k ) = ω max ( ω max ω min ) k / K
where ω max and ω min are initial and final inertia weight factors and set to 0.9 and 0.4 respectively. K is the maximum iteration number. φ 1 ( k ) and φ 2 ( k ) are time-varying acceleration coefficients corresponding to cognitive and social behavior [6], and are set with the following equations shown in Equations (28) and (29):
φ 1 ( k ) = φ 1 i + ( φ 1 f φ 1 i ) k / K
φ 2 ( k ) = φ 2 i + ( φ 2 f φ 2 i ) k / K
where φ 1 i , φ 2 i are the initial values of φ 1 ( k ) and φ 2 ( k ) , and are set to 2.5 and 0.5 respectively; φ 1 f , φ 2 f are the final values of φ 1 ( k ) and φ 2 ( k ) , and are set to 0.5 and 2.5 respectively.
It is not always effective to solve the problem with equality and inequality constraints using basic PSO, and the particles (solutions) which satisfy the inequality constraints usually violate the equality constraints. In this section, we propose a FRA strategy over these particles which violate equality constraints. In addition, in order to improve the quality of the best solution, HCSO is applied to update the global best particle along with the iteration. In subsections 4.1 and 4.2, we will separately discuss the FRA strategy and the HCSO in detail.

4.1. Feasible Region Adjustment Strategy

Let us rewrite the position of the jth particle as the following matrix:
Y j = [ y 1 , 1 y 1 , 2 y 1 , t y 1 , T y 2 , 1 y 2 , 2 y 2 , t y 2 , T           y m , 1 y m , 2 y m , t y m , T   y I , 1   y I , 2   y I , t     y I , T y M , 1 y M , 2 y M , t y M , T ] = [ p 1 , 1 p 1 , 2 p 1 , t p 1 , T p 2 , 1 p 2 , 2 p 2 , t p 2 , T         p i , 1 p i , 2 p i , t p i , T         p I , 1 p I , 2 p I , t p I , T p w , 1 p w , 2 p w , t p w , T ]
where M is the number of generators including thermal units and one wind farm, i.e., M = I + 1, and M·T = D. The element of matrix ymt is the output of the mth generator at time t. The row vectors represent the output of the individual generator each hour one day.
The sum of the output of individual generator (i.e., power supply) each hour must be equal to the demand, i.e., i = 1 I p i , t + p w , t = p d , t , t = 1 , 2 , , T . If the power supplied in each hour is greater or smaller than the demand, the FRA strategy will be applied to the jth particle. The FRA strategy is described as follows:
(1) if i = 1 I p i , t + p w , t < p d , t
We use the following equation to adjust the output of the thermal units and the wind farm as shown in Equation (31):
p i , t * = p i , t + p i , t max p i , t i p i , t max + w max F X t 1 ( 1 ρ ) i p i , t p w , t ( p d , t i p i , t p w , t )
In Equation (31), p i , t max p i , t is the range that the output of thermal unit i can be increased at time t. p i , t max p i , t i p i , t max + w max F X t 1 ( 1 ρ ) i p i , t p w , t refers to the fraction of the adjustable range of unit i compared with the total adjustable range of all generators. p i , t max p i , t i p i , t max + w max F X t 1 ( 1 ρ ) i p i , t p w , t ( i p i , t + p w , t p d , t ) is the adjustable value of unit i. It can be easily seen that the value of p d , t i p i , t p w , t i p i , t max + w max F X t 1 ( 1 ρ ) i p i , t p w , t is less than 1, so the value of p i , t * after adjusted still satisfies p i , t * p i , t max .
Similar to Equation (31), we use the Equation (32) to adjust the output of the wind farm, as shown below:
p w , t * = p w , t + w max F X t 1 ( 1 ρ ) p w , t i p i , t max + w max F X t 1 ( 1 ρ ) i p i , t p w , t ( p d , t i p i , t p w , t )
and the output of wind farm p w , t * after adjusted is still smaller than w max F X t 1 ( 1 ρ ) .
(2) if i = 1 I p i , t + p w , t > p d , t
Similar analysis can be applied to the condition i = 1 I p i , t + p w , t > p d , t . We use the following Equations (33) and (34) to adjust the output of the thermal units and the wind farm respectively:
p i , t * = p i , t p i , t p i , t min i p i , t + p w , t i p i , t min ( i p i , t + p w , t p d , t )
p w , t * = p w , t p w , t i p i , t + p w , t i p i , t min ( i p i , t + p w , t p d , t )
and we can obtain that p i , t min p i , t * and p w , t * 0 .
From above discussion, we can learn that the FRA strategy ensures that the particles after adjusted still satisfy the generation limit constraints.

4.2. Hill Climbing Search Operation

Hill climbing is an optimization technique which belongs to the local search family. It is an iterative algorithm that starts with an arbitrary solution, and then attempts to find a better solution by incrementally changing a single element of the solution. In our work, in order to obtain a better solution, we adopt HCSO to update the global best particle along with the iteration. When the fitness of the global best particle does not change continuously for a fixed number of times, HCSO can be used as explained in Equations (35) and (36):
p m , t ´ = p m , t + min ( Δ m , Δ n ) ε
p n , t ´ = p n , t min ( Δ m , Δ n ) ε
where p m , t and p n , t are generations of thermal unit m and n, which belong to the same period and are randomly selected from all the thermal units. p m , t ´ and p n , t ´ are generations of thermal units after hill climbing operation. Δ m and Δ n are the upper ramp rates of unit m and n. In this paper, we adopt the upper ramp rates in simulation. However, the lower ramp rates can be used either. min ( Δ m , Δ n ) ε is the linear decrease step size of hill climbing operation and ε is listed in Table 2 in Section 5. Both Equations (35) and (36) have the same step size and the opposite direction, which ensures that the global best particle will not violate equality constraints after hill climbing operation.

4.3. DED Constraints Handling Using PSO-HCSO

The fitness function of particle is the generation cost bounded with the penalty functions as shown in Equation (37):
f i t n e s s = f cos t + g = 1 6 λ t = 1 T P F g , t
and:
P F 1 , t = max ( 0 , | i = 1 I p i , t + p w , t p d , t | )
P F 2 , t = max ( 0 , p i min p i , t ) + max ( 0 , p i , t p i max )
P F 3 , t = max ( 0 , p w , t ) + max ( 0 , p w , t w max F X t 1 ( 1 ρ ) )
P F 4 , t = max ( 0 , Δ i , d × T 60 p i , t + p i , t 1 ) + max ( 0 , p i , t p i , t 1 Δ i , u × T 60 )
P F 5 , t = max ( 0 , p r , t + p w , t w max 0 p w , t / w max x t f X t ( x t ) d x t 0 p w , t / w max f X t ( x t ) d x t i I min ( p i , t max p i , t , Δ i , u × T 10 ) )
P F 6 , t = max ( 0 , w max p w , t / w max 1 x t f X t ( x t ) d x t p w , t / w max 1 f X t ( x t ) d x t p w , t i I min ( p i , t p i , t min , Δ i , d × T 10 ) )
where λ is the penalty factor corresponding to the constraints. Here, we use uniform penalty factor for P F g , t , i.e., λ = 1 e + 8 ; P F g , t is the penalty function. It is noted that the solution should not contain any penalty for the constraint violation.

4.4. The Procedure of Improved PSO Approach

The procedures for implementing the PSO approach are given as the following steps:
Step 1: Initialize the parameters, such as population size J, the maximum iteration number K, and the maximum number of hill climbing search operation H. Set the sequence number of iteration K = 1 and the number of times that the global best particle does not change continuously h c o u n t = 1 .
Step 2: Create a swarm of particles as the initial population, including random position and velocity. For any particle which violates the equality constraints, FAR strategy is utilized. Evaluate the fitness of particles and obtain the initial g b e s t 0 and p b e s t j 0 , j = 1 , 2 , , J .
Step 3: Calculate ω ( k ) , φ 1 ( k ) and φ 2 ( k ) , and then update the position and velocity of each particle among the population according to Equations (25) and (26). FAR strategy is applied to any particle which violates the equality constraints.
Step 4: Evaluate the fitness of particles and update p b e s t j k , j = 1 , 2 , J and g b e s t k of the population. Check g b e s t k . If hcount reaches the fixed number of times, hill climbing search operation is applied until the maximum number H is reached; otherwise, set h c o u n t = 1 .
Step 5: k = k + 1, if k > K, stop the algorithm and output the global best solution ( g b e s t k ) with the best fitness value; otherwise, go back to step 3.

5. Simulation Results and Discussions

In order to verify the effectiveness of the proposed DED model with wind power, three distinct test systems (i.e., system 1, system 2 and system 3) are employed in this paper. System 1 contains six thermal units and one wind farm (WF) which is also used in system 2 and 3. System 2 contains 15 thermal units. The characteristics of the 6 and 15 thermal units can be obtained from [27]. System 3 has 26 thermal units derived for a IEEE 24-bus system. The wind farm is located in the Inner Mongolia Autonomous Region in China, and contains 132 wind turbines. The total installed capacity is 198 MW. Table 1 gives the hourly expected value and standard deviation of wind power forecast on the scheduled day, and also the corresponding beta parameters which are calculated by Equation (17).
The parameters of improved PSO are shown in Table 2. In the table, h is the sequence number of Hill climbing search operation. The improved PSO approach has been implemented on a personal computer with four processors running at 3.2 GHz and equipped with 4 GB of RAM memory using Matlab 7.9.0.
Table 1. Hourly expected value and standard deviation of wind power forecast and beta parameters.
Table 1. Hourly expected value and standard deviation of wind power forecast and beta parameters.
PeriodExpected Value (MW)Standard Deviation (MW)αβPeriodExpected Value (MW)Standard Deviation (MW)αβ
170.417.2510.3818.8113133.2433.254.582.23
255.5013.8711.2428.8714129.5032.374.882.58
334.509.6310.4349.4515147.1536.753.371.17
428.310.236.4238.4716140.735.403.861.57
542.110.5412.3545.7317133.433.254.582.22
659.5014.8710.9025.3718108.527.136.685.51
770.5617.1710.5118.991984.721.068.8311.81
880.5020.129.0913.272077.319.259.4414.74
994.5023.627.898.642166.516.6210.3020.36
10112.428.845.994.572242.210.512.5046.14
11126.731.535.172.912335.38.7513.2060.82
12130.532.624.802.482463.815.7510.8022.72
Table 2. Parameters for improved PSO algorithm.
Table 2. Parameters for improved PSO algorithm.
JKHhcountε
402002004h/(H+0.00001)

5.1. Comparisons Among the Three Cases of the DED Model

In each test system, we perform 50 trials using the improved PSO approach considering three cases as follows:
  • Case (1): the DED model without considering wind power;
  • Case (2): the DED model without considering wind effect in the reserve constraint;
  • Case (3): the proposed DED model in this paper.
Both casea (1) and (2) can be derived from case (3). The first case can be obtained by setting the confidence level (ρ) of case (3) to 1, and the latter is obtained by removing the URFW and DRRW in the reserve constraint. Comparison results among three cases mentioned above are shown in Table 3.
Table 3. Comparisons among the three cases in the three systems.
Table 3. Comparisons among the three cases in the three systems.
CasesConfidence LevelAverage Generation Cost ($)
System 1System 2System 3
Case (1)1278,903.3311736,673.0726952,079.3252
Case (2)0.9264,895.0451723,729.9923939,455.4055
0.5258,950.8628719,280.7467928,252.2498
0.1253,792.2061717,075.4436921,874.4037
Case (3)0.9265,158.6006724,077.6842937,747.6542
0.5260,537.2281720,665.7621930,092.0212
0.1257,194.5871717,358.1034920,580.2708
It is evident that the average generation cost in case (1) is the highest among the three systems; this is because that no wind power is utilized in case (1). Wind power in cases (2) and (3) affords a certain proportion of the load and thus reduces the fuel consumption. Average generation cost decreases gradually as the confidence level decreases for cases (2) and (3) among the three systems. The smaller the confidence is, the lower the average generation cost is. Taking system 1 for example, the average cost in cases (2) and (3) decreases by 5.02% and 4.93%, respectively, compared to case (1) when ρ = 0.9. When ρ decreases to 0.1, the average generation cost decreases by 9.00% and 7.78%, respectively, compared to case (1).
Figure 2, Figure 3 and Figure 4 show the average cost change trend for different confidence level scenarios for cases (2) and (3) among the three systems. As seen in the figures, the average cost in the three systems increases gradually while the confidence level increases. There is not much difference in the average cost between case (3) and case (2), however, case (3) considers the URFW and DRRW in the reserve constraints, and this makes the systems more reliable.
Figure 2. Average generation cost under different confidence level in system 1.
Figure 2. Average generation cost under different confidence level in system 1.
Energies 08 00233 g002
Figure 3. Average generation cost under different confidence level in system 2.
Figure 3. Average generation cost under different confidence level in system 2.
Energies 08 00233 g003
Figure 4. Average generation cost under different confidence level in system 3.
Figure 4. Average generation cost under different confidence level in system 3.
Energies 08 00233 g004
We choose the solutions with the minimum generation cost from 50 trials as the optimal solutions by varying ρ from 0.1 to 0.9. The optimal solutions (power output during each period for each unit and wind farm) for system1 and 2 under ρ = 0.9 are shown in Figure 5 and Figure 6. Power outputs for period 1, 5, 9, 13, 17, 21 in system 3 are listed in Table 4.
Figure 5. Optimal generation output of units and wind farm in system 1 with ρ = 0.9.
Figure 5. Optimal generation output of units and wind farm in system 1 with ρ = 0.9.
Energies 08 00233 g005
Figure 6. Generation output of units and wind farm in system 2 with ρ = 0.9.
Figure 6. Generation output of units and wind farm in system 2 with ρ = 0.9.
Energies 08 00233 g006
Table 4. Optimal output of units and wind farm (WF) in system 3 with ρ = 0.9.
Table 4. Optimal output of units and wind farm (WF) in system 3 with ρ = 0.9.
Unit IndexOutput/MW (t = 1)Output/MW (t = 5)Output/MW (t = 9)Output/MW (t = 13)Output/MW (t = 17)Output/MW (t = 21)
16.30272.41453.84403.19067.10556.0383
22.40013.85853.09193.89674.21764.7125
35.08522.40412.40515.33156.96805.5158
42.40052.40013.71322.42459.10815.4245
52.40082.40002.40017.70752.71512.4124
64.03289.17594.00177.537514.54617.5095
77.06164.033413.61438.226516.34426.4664
811.47584.002415.010813.53854.10288.2579
94.00054.00944.002513.935514.79544.0497
1019.225247.096275.982075.984875.938952.5536
1118.342355.203161.061053.554775.607031.5227
1275.889615.467573.210375.994875.629853.2694
1344.398162.594521.528940.111562.938675.9777
1429.068278.585367.591675.043693.066191.2458
1525.168725.078799.700858.689680.763669.7929
1666.913625.113790.004460.338378.677297.6501
17111.891154.4301150.9160129.1319151.3966102.5665
18127.212891.5275119.8840105.7696155.0000148.3436
1982.491181.7769142.5084101.8499149.4214104.2932
20103.216484.7880154.9953152.8019136.8211102.9801
21149.425679.754994.8661176.8049163.8401167.1249
22131.0308142.1999108.1115171.1631182.412784.5785
23127.8570125.8213135.2337154.7178163.3203153.6023
24276.5693158.4972306.4523290.2500284.4019287.2902
25239.6986270.5251379.2529328.7933398.3654331.9537
26359.0842372.9581320.0320329.1593378.8603275.4983
WF19.357219.383754.585362.052463.636027.8695

5.2. Wind Penetration as a Function of the Confidence Level Under Two Systems

Comparisons between wind penetration ( p w , t × 100 % / p d , t ) and wind penetration limits ( w max F X t 1 ( 1 ρ ) × 100 % / p d , t ) under the optimal solutions in each system are shown in Figure 7, Figure 8 and Figure 9. As shown, wind penetration in each system under ρ = 0.9 is the lowest, because under that situation each system requires the highest reliability and security. As the confidence level decreases, wind penetration almost increases and does not exceed the wind penetration limits in the three systems.
Figure 7. Wind penetration and its limit under different confidence levels in System 1.
Figure 7. Wind penetration and its limit under different confidence levels in System 1.
Energies 08 00233 g007
Figure 8. Wind penetration and its limit under different confidence levels in System 2.
Figure 8. Wind penetration and its limit under different confidence levels in System 2.
Energies 08 00233 g008
Figure 9. Wind penetration and its limit under different confidence levels in System 3.
Figure 9. Wind penetration and its limit under different confidence levels in System 3.
Energies 08 00233 g009

5.3. Discussion about the Optimal Reserve Allocation

Due to the stochastic and intermittent nature of wind power, the USR and DSR are used to ensure the reliability and security of systems with wind farms. According to Inequations (9) and (10), the USR, DSR, URFW and DRRW for each period are calculated based on the optimal solutions when ρ = 0.9 serves as an example. Figure 10 and Figure 11 show the optimal USR and DSR allocation for 24 h in system 1 respectively. Figure 12 and Figure 13 give the optimal USR and DSR allocation for 24 h in system 2. It can be learned that the USR and DSR provided by thermal units in both systems can effectively cover the sudden fall and increase in wind power. The same conclusion can also be drawn for system 3, so the corresponding figures for USR and DSR are not displayed.
Figure 10. The optimal USR allocation and URR plus reserve for load forecast error in system 1 with ρ = 0.9.
Figure 10. The optimal USR allocation and URR plus reserve for load forecast error in system 1 with ρ = 0.9.
Energies 08 00233 g010
Figure 11. The optimal DSR allocation and DRR for 24 h in system 1 with ρ = 0.9.
Figure 11. The optimal DSR allocation and DRR for 24 h in system 1 with ρ = 0.9.
Energies 08 00233 g011
Figure 12. The optimal USR allocation and URR plus reserve for load forecast error for 24 h in system 2 with ρ = 0.9.
Figure 12. The optimal USR allocation and URR plus reserve for load forecast error for 24 h in system 2 with ρ = 0.9.
Energies 08 00233 g012
Figure 13. The optimal DSR allocation and DRR for 24 h in system 2 with ρ = 0.9.
Figure 13. The optimal DSR allocation and DRR for 24 h in system 2 with ρ = 0.9.
Energies 08 00233 g013

5.4. Comparisons between the PSO-HCSO and PSO without HCSO

In order to investigate the effect of the parameter H on the improved PSO algorithm, we set H as 100, 200, 300, 400 and perform the algorithm on system 1 with ρ = 0.9 for 50 trials. The average generation cost and average time are listed in Table 5. The average generation costs decrease gradually and average time increases as H increases.
Table 5. Effect of H on the improved PSO algorithm with ρ = 0.9.
Table 5. Effect of H on the improved PSO algorithm with ρ = 0.9.
HAverage Generation Cost ($)Average Time (s)
100269,280.7296328.2577
200265,158.6006386.8114
300262,533.7753436.2356
400261,153.0924538.3722
Finally, in order to show the effectiveness of HCSO, PSO without HCSO is used for comparison. Parameter K for PSO without HCSO is set as 300. Results of the proposed DED model under three confidence levels are shown in Table 6. Although PSO without HCSO consume less computation time than PSO-HCSO, it leads to much higher generation costs. From this point of view, the improved PSO algorithm is more efficient.
Table 6. Comparisons between PSO-HCSO and PSO without HCSO among three systems.
Table 6. Comparisons between PSO-HCSO and PSO without HCSO among three systems.
ApproachConfidence LevelAverage Generation Cost ($)Average Time (s)
PSO-HCSOPSO without HCSOPSO-HCSOPSO without HCSO
System 10.9265,158.6006273,039.6325386.8114336.6071
0.5260,537.2281263,514.4852359.3236308.3647
0.1257,194.5871262,368.0024373.6618317.1135
System 20.9724,077.6842731,239.0336418.3461409.6045
0.5720,665.7621727,088.0353402.1863386.9233
0.1717,358.1034720,196.5471447.1164422.8967
System 30.9937,747.6542945,013.2889456.7289420.0858
0.5930,092.0212938,816.0995428.3801416.1260
0.1920,580.2708929,187.2603470.2236436.2757

6. Conclusions

Wind power provides energy savings and environmental protection benefits. However, the intermittency and uncertainty of wind power generation require that conventional units provide additional reserve to ensure the stability and reliability of a wind power-penetrated power system. This paper formulates a DED model incorporating wind power based on CCP. The uncertain nature of wind generation is represented by a beta distribution function. In order to ensure the reliability of the power system, a chance constraint is included, and conditional expectation is presented to calculate the up and down spinning reserves. The proposed DED model is then numerically solved using an improved PSO approach in three different test systems. Results show that the proposed model can effectively respond to sudden wind power falls or raises. The improved PSO approach is fit to solve the DED model.
The results also show that the average generation cost and wind penetration are dependent on the confidence level. If the confidence level is increased, the wind penetration will be reduced, which results in higher reliability of the power system, and the average generation cost will be increased. Conversely, if the confidence level is decreased, less reliability allows more wind power to be incorporated in the power system. The average generation cost will be reduced.

Acknowledgments

The authors gratefully acknowledge the support of the National Natural Science Foundation of China (61305149).

Author Contributions

All the authors contributed to this paper. Haifeng Zhang formulated the DED model, performed experiments and edited the manuscript. Wushan Cheng reviewed and revised the manuscript.

List of Abbreviations and Symbols

Abbreviations

ED
Economic dispatch
DED
Dynamic economic dispatch
USR
Up spinning reserve
DSR
Down spinning reserve
URR
Up reserve requirement
DRR
Down reserve requirement
PSO
Particle swarm optimization
HCSO
Hill climbing search operation
PSO-HCSO
Particle swarm optimization with hill climbing search operation
PDF
Probability density function
CDF
Cumulative density function
FRA
Feasible region adjustment

Symbols

T
Number of Periods
I
Number of thermal units
t
Index of time period, t = 1 , 2 , , T
i
Index of thermal unit, t = 1 , 2 , , I
f cos t
Total generation cost
p i , t
Power output of thermal unit i at time t
p w , t
Scheduled wind power of wind farm at time t
p d , t
Load demand at time t
C i ( p i , t )
Generation cost of thermal unit i at time t
a i , b i , c i
Cost coefficients of thermal unit i
E i ( p i , t )
Valve point loading effect of thermal unit i at time t
e i , f i
Coefficients related to valve point effect of thermal unit i
p i min , p i max
Minimum and Maximum generation limits of thermal unit i
w t
Actual wind generation, a random variable
w max
Installed capacity of wind farm
ρ
Confidence level
Δ i , u , Δ i , d
Upper and lower ramp rate limits of thermal unit i
T10, T60
10 min and 1 h respectively
r w , t u
URFW at time t
r w , t d
DRRW at time t
α, β
Parameters of the beta function
μ t , σ t
Mean value and the standard deviation
f W t , F W t
PDF and CDF of actual wind generation at time t
f X t , F X t
PDF and CDF of normalized actual wind generation at time t
D
Dimension of the particle
k, K
Current number and maximum number of iteration
V j k , Y j k
Velocity and position of the jth particle at generation k
ω ( k )
Dynamic inertia weight factor
φ 1 ( k ) , φ 2 ( k )
Acceleration coefficients corresponding to cognitive and social behavior
p b e s t j k
Personal best position of jth particle at generation k
g b e s t k
Global best position at generation k in the whole population
λ
Penalty factor
P F g , t
Penalty functions
H
Maximum number of the HCSO
h c o u n t
The number of times that g b e s t does not change continuously

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Ren, B.Q.; Jiang, C.W. A review on the economic dispatch and risk management considering wind power in power market. Renew. Sustain. Energy Rev. 2009, 13, 2169–2174. [Google Scholar] [CrossRef]
  2. Xia, X.; Elaiw, A. Optimal dynamic economic dispatch of generation: A review. Electr. Power Syst. Res. 2010, 80, 975–986. [Google Scholar] [CrossRef]
  3. Guo, C.X.; Zhan, J.P.; Wu, Q.H. Dynamic economic emission dispatch based on group search optimizer with multiple producers. Electr. Power Syst. Res. 2012, 86, 8–16. [Google Scholar] [CrossRef]
  4. Chen, C.L. Optimal wind-thermal generating unit commitment. IEEE Trans. Energy Convers. 2008, 23, 273–280. [Google Scholar] [CrossRef]
  5. Zhou, W.; Peng, Y.; Sun, H.; Wei, Q.H. Dynamic economic dispatch in wind power integrated system. Proc. CSEE 2009, 29, 3–18. [Google Scholar]
  6. Jiang, W.; Yan, Z.; Hu, Z. A novel improved particle swarm optimization approach for dynamic economic dispatch incorporating wind power. Electr. Power Compon. Syst. 2010, 39, 461–477. [Google Scholar] [CrossRef]
  7. Hetzer, J.; Yu, C.D.; Bhattarai, K. An economic dispatch model incorporating wind power. IEEE Trans. Energy Convers. 2008, 23, 603–611. [Google Scholar] [CrossRef]
  8. Zhou, W.; Sun, H.; Peng, Y. Risk reserve constrained economic dispatch model with wind power penetration. Energies 2010, 3, 1880–1894. [Google Scholar] [CrossRef]
  9. Bofinger, S.; Luig, A.; Beyer, H.G. Qualification of wind power forecasts. In Proceedings of the Global Wind Power Conference, Paris, France, 2–5 April 2002; pp. 2–5.
  10. Bludszuweit, H.; Dominguez-Navarro, J.A.; Llombart, A. Statistical analysis of wind power forecast error. IEEE Trans. Power Syst. 2008, 23, 983–991. [Google Scholar] [CrossRef]
  11. Fabbri, A.; Roman, T.G.S.; Abbad, J.R.; Quezada, V.H.M. Assessment of the cost associated with wind generation prediction errors in a liberalized electricity market. IEEE Trans. Power Syst. 2005, 20, 1440–1446. [Google Scholar] [CrossRef]
  12. Wu, D.L.; Wang, Y.; Guo, C.X.; Liu, Y. An economic dispatching model considering wind power forecast errors in electricity market environment. Autom. Electr. Power Syst. 2012, 36, 23–28. [Google Scholar]
  13. Liu, X. Impact of beta-distributed wind power on economic load dispatch. Electr. Power Compon. Syst. 2011, 39, 768–779. [Google Scholar] [CrossRef]
  14. Miranda, V.; Hang, P.S. Economic dispatch model with fuzzy wind constraints and attitudes of dispatchers. IEEE Trans. Power Syst. 2005, 20, 2143–2145. [Google Scholar] [CrossRef]
  15. Pappala, V.S.; Erlich, I.; Rohrig, K.; Dobschinski, J. A stochastic model for the optimal operation of a wind-thermal power system. IEEE Trans. Power Syst. 2009, 24, 940–950. [Google Scholar]
  16. Bouffard, F.; Galiana, F.D. Stochastic security for operations planning with significant wind power generation. IEEE Trans. Power Syst. 2008, 23, 306–316. [Google Scholar] [CrossRef]
  17. Yang, N.; Wen, F. A chance constrained programming approach to transmission system expansion planning. Electr. Power Syst. Res. 2005, 75, 171–177. [Google Scholar] [CrossRef]
  18. Yu, H.; Chung, C.Y.; Wong, K.P.; Zhang, J.H. A chance constrained transmission network expansion planning method with consideration of load and wind farm uncertainties. IEEE Trans. Power Syst. 2009, 24, 1568–1576. [Google Scholar] [CrossRef]
  19. Wang, Q.; Guan, Y.; Wang, J. A chance-constrained two-stage stochastic program for unit commitment with uncertain wind power output. IEEE Trans. Power Syst. 2012, 27, 206–215. [Google Scholar] [CrossRef]
  20. Walters, D.C.; Sheble, G.B. Genetic algorithm solution of economic dispatch with valve point loading. IEEE Trans. Power Syst. 1993, 8, 1325–1332. [Google Scholar] [CrossRef]
  21. Chiang, C.L. Improved genetic algorithm for power economic dispatch of units with valve-point effects and multiple fuels. IEEE Trans. Power Syst. 2005, 20, 1690–1699. [Google Scholar]
  22. Coelho, L.S.; Mariani, V.C. Combining of chaotic difference evolution and quadratic programming for economic dispatch optimization with valve-point effect. IEEE Trans. Power Syst. 2006, 22, 1273–1282. [Google Scholar]
  23. Victoire, T.A.A.; Jeyakumar, A.E. Reserve constrained dynamic dispatch of units with valve-point effects. IEEE Trans. Power Syst. 2005, 22, 1273–1282. [Google Scholar] [CrossRef]
  24. Chakraborty, S.; Senjyu, T.; Yona, A.; Saber, A.Y. Solving economic load dispatch problem with valve-point effects using a hybrid quantum mechanics inspired particle swarm optimization. IET Gener. Trans. Distrib. 2011, 5, 1042–1052. [Google Scholar]
  25. Nidul, S.; Chakrabarti, R.; Chattopadhyay, P.K. Evolutionary programming techniques for economic load dispatch. IEEE Trans. Evol. Comput. 2003, 7, 83–94. [Google Scholar] [CrossRef]
  26. Attaviriyanupap, P.; Kita, H.; Tanaka, E. A hybrid EP and SQP for dynamic economic dispatch with nonsmoooth fuel cost function. IEEE Trans. Power Syst. 2002, 17, 411–416. [Google Scholar] [CrossRef]
  27. Gaing, Z.L. Particle swarm optimization to solving the economic dispatch considering the generator constraints. IEEE Trans. Power Syst. 2003, 18, 1187–1195. [Google Scholar] [CrossRef]
  28. Lee, T.Y. Optimal spinning reserve for a wind-thermal power system using PSO. IEEE Trans. Power Syst. 2007, 22, 1612–1621. [Google Scholar] [CrossRef]
  29. Park, J.B.; Lee, K.S.; Shin, J.R.; Lee, K.Y. A particle swarm optimization for economic dispatch with non-smooth cost functions. IEEE Trans. Power Syst. 2005, 20, 34–42. [Google Scholar] [CrossRef]
  30. Li, X.H.; Jiang, C.W. Short-term operation model and risk management for wind power penetrated system in electricity market. IEEE Trans. Power Syst. 2011, 26, 932–939. [Google Scholar] [CrossRef]
  31. Panigrahi, B.K.; Pandi, V.R.; Das, S. Adaptive particle swarm optimization approach for static and dynamic economic load dispatch. Energy Convers. Manag. 2008, 49, 1407–1415. [Google Scholar] [CrossRef]
  32. Park, J.B.; Jeong, Y.W.; Shin, J.R.; Lee, K.Y. An improved particle swarm optimization for nonconvex economic dispatch problems. IEEE Trans. Power Syst. 2010, 25, 156–166. [Google Scholar] [CrossRef]

Share and Cite

MDPI and ACS Style

Cheng, W.; Zhang, H. A Dynamic Economic Dispatch Model Incorporating Wind Power Based on Chance Constrained Programming. Energies 2015, 8, 233-256. https://doi.org/10.3390/en8010233

AMA Style

Cheng W, Zhang H. A Dynamic Economic Dispatch Model Incorporating Wind Power Based on Chance Constrained Programming. Energies. 2015; 8(1):233-256. https://doi.org/10.3390/en8010233

Chicago/Turabian Style

Cheng, Wushan, and Haifeng Zhang. 2015. "A Dynamic Economic Dispatch Model Incorporating Wind Power Based on Chance Constrained Programming" Energies 8, no. 1: 233-256. https://doi.org/10.3390/en8010233

Article Metrics

Back to TopTop