Next Article in Journal
Where Renewable Energy Sources Funds are Invested? Spatial Analysis of Energy Production Potential and Public Support
Next Article in Special Issue
Design, Analysis and Implementation of the Tapped-Inductor Boost Current Converter on Current Based System
Previous Article in Journal
“Oil is the New Data”: Energy Technology Innovation in Digital Oil Fields
Previous Article in Special Issue
Hybrid Ship Unit Commitment with Demand Prediction and Model Predictive Control
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Techno-Economic Optimization Analysis of an Autonomous Photovoltaic Power System for a Shoreline Electrode Station of HVDC Link: Case Study of an Electrode Station on the Small Island of Stachtoroi for the Attica–Crete Interconnection

by
Panagiota M. Deligianni
1,
George J. Tsekouras
1,2,*,
Costas D. Tsirekis
1,3,
Vassiliki T. Kontargyri
2,
Fotis D. Kanellos
4 and
Panagiotis A. Kontaxis
1,2
1
Department of Electrical and Electronics Engineering, University of West Attica, 250 Thivon Str., 12241 Athens, Greece
2
School of Electrical and Computer Engineering, National Technical University of Athens, Heroon Polytechniou 9, 15780 Athens, Greece
3
Hellenic Independent Power Transmission Operator, Dyrrachiou 89 & Kifissou, 10443 Athens, Greece
4
School of Electrical and Computer Engineering, Technical University of Crete, University Campus, Akrotiri, 73100 Chania, Greece
*
Author to whom correspondence should be addressed.
Energies 2020, 13(21), 5550; https://doi.org/10.3390/en13215550
Submission received: 22 August 2020 / Revised: 29 September 2020 / Accepted: 7 October 2020 / Published: 23 October 2020
(This article belongs to the Special Issue Energy Management in the Multi-Source Systems)

Abstract

:
A lot of autonomous power systems have been designed and operated with different power levels and with special requirements for climatic conditions, availability, operation/maintenance cost, fuel consumption, environmental impacts, etc. In this paper a novel design of an autonomous power system with photovoltaic panels and electrochemical batteries for a shoreline electrode station is analyzed. This station will be constructed on the small island of Stachtoroi for the new high voltage direct current (HVDC) link of Attica–Crete in Greece. The general guidelines of the International Council on Large Electric Systems (CIGRE) and of the International Electrotechnical Committee (IEC) for the power system of lighting and auxiliary loads for these HVDC stations are supplied from the medium voltage or the low voltage distribution network, whereas they do not take into account the criticality of this interconnection, which will practically be the unique power facility of Crete island. The significance of Crete power system interconnection demands an increased reliability level for the power sources, similar to military installations and hospital surgeries. In this research a basic electrical installation design methodology is presented. First, the autonomous photovoltaic power system with the energy storage system (ESS) consisting of electrochemical batteries is preliminary designed according to the relative bibliography. The station power and energy consumption are analytically determined taking into consideration the daily temperature variation annually. Afterwards, a techno-economic optimization process based on a sensitivity analysis is formed modifying the size/power of photovoltaic panels (PVs), the type and the energy capacity of the batteries taking into consideration the operation cycle of PVs—batteries charge and discharge and the battery ageing based on the relationship between battery cycles—the depth of discharge, the daily solar variation per month, the installation cost of PVs and batteries, the respective maintenance cost, etc., while the reliability criteria of expected loss of load power and of load energy are satisfied. Using the proposed methodology the respective results are significantly improved in comparison with the preliminary autonomous power system design or the connection with the distribution power system.

1. Introduction

During the last three decades many renewable isolated power systems have been installed powering a small electric machine, i.e., air conditioner [1] or a house [2] of a few kilowatts to an autonomous power system for a community [3] or an island [4] of megawatts (MW). The photovoltaic plants with energy storage systems can serve various purposes, i.e., avoiding transmission network expansion [5], transforming traditional load customers into active consumers [6], and providing reserve services to distribution network [7].
However, the main research effort focuses on the sizing and efficient operation of the autonomous photovoltaic (PV) system, the principal limitations of high capital investment for PV panels (PVs) and energy storage systems (ESSs) of low reliability and the satisfaction of electrical load requirements [8]. More specifically it deals with:
  • The optimization methods for the sizing of PVs and energy storage items, which can be:
    Simplified for preliminary studies based on a typical daily electric load demand and meteorological data (solar irradiation and ambient temperature) [9,10,11],
    Numerical iterative, which simulate several combinations of stand-alone photovoltaic (SAPV) components size based on the electric load demand and meteorological data of a typical year in the hourly or daily time step, with one or more objective functions and conditions, as technical (i.e., loss of load probability, loss of energy expected, and PV panel tilt angle), economic (i.e., annualized life cost, net present value, levelized cost of energy, life cycle cost, and life cost unit cost), environmental (i.e., life cycle assessment, embodied energy, and CO2 emissions), and social (i.e., job creation) [2,12,13,14],
    Analytical optimization methods with one or more objective functions and conditions that represent the components of technical and economic specifications with mathematical equations having the additional difficulty of coefficients determination [1,3,8],
    Non-conventional including a stochastic [15], artificial neural network [16], hybrid with the Pareto method and hierarchy process [17].
    In any case the separating limits between the methods are not always clear, as a great number of methods, indicators, constraints, and data are involved [18,19,20,21,22,23,24,25,26]. Additional methods for off-grid hybrid power systems [27,28,29,30] and for energy storage systems [31,32] can be also found in the literature.
  • The configuration of PVs and ESSs, where the connection can be through either a DC bus for small electric load demand installation (smaller than 3 kW [10]) using DC–DC converters and energy storage chargers, or an AC bus for bigger electric load demand installation (bigger than 3 kW [10]) using rectifiers, inverters, and energy storage charger/de-chargers. The ESSs are:
    Usually batteries, i.e., lead acid, absorbed glass mat (AGM), lithium-ion [8], nickel-cadmium [10], etc.,
    More rarely hydrogen storage tanks with an electrolyzer and fuel cells [33,34],
    Combination of hydrogen storage tanks and batteries [35,36],
    More rarely a pumped-storage hydroelectric plant [13,37],
    More rarely compressed air energy storage [13,38],
    Combination of hydrogen storage tanks, a pumped-storage hydroelectric plant, and batteries [39].
    In the case of energy storage combination the batteries are used for short-term operation, while the other storage systems for long-term operation. The addition of other sources beyond the PV one, such as wind turbine [21,38], diesel generators [36], hydro plants [21], biogas and biomass generators [4,21], fuel cells without an electrolyzer and storage tank [21], and forms of the hybrid autonomous power system instead of SAPV.
  • The design principles of SAPV for specific installations, as:
    Special electrical equipment, i.e., an air conditioner [1], pumping system [40], and milk chiller [41],
    Households [2,3,12,39], school [3], health center [3], islands [4,37], and communities [36],
    Electric vehicles [19],
    Electrochemical reforming of ethanol–water solutions [33], the chemical industrial process [34], and the desalination system [42],
    Stratospheric airship for long duration missions [43].
In this paper the design principles of SAPV for the off-grid power supply of the lighting and auxiliary loads for the shoreline electrode station of a high voltage direct current (HVDC) link is presented. Furthermore, the type and the optimum size of PVs and ESSs are determined by the proper numerical iterative sensitivity analysis method. The idea has arisen by the design of the electrode station on the small island of Stachtoroi for the new HVDC link of Attica–Crete in Greece [44]. The design procedure has shown the shortages of the International Council on Large Electric Systems (CIGRE) [45] and International Electrotechnical Committee (IEC) [46] general guidelines for the power system of HVDC stations being supplied by a medium or low voltage distribution network and not by an autonomous system. Additionally, these guidelines do not take into account the criticality of such interconnections, as HVDC links are usually supplementary supplies of backcountry areas, and the specific link will be practically the unique power facility of Crete Island. These define new requirements for the respective autonomous system, as will be explained in Section 2. In Section 3, the SAPV design methodology is presented including the electric power and energy consumption, taking into consideration the daily temperature variation as well as the proposed type of PVs and ESSs [47] and the configuration of the electrical installation. In Section 4, the main techno-economic optimization process is formed modifying the size/power of PVs and the type and the energy capacity of the batteries based on sensitivity analysis. Moreover, different issues are taken into consideration such as: (1) the operation cycle of PVs—batteries, (2) the battery ageing based on the relation between battery cycles and the depth of discharge, (3) the daily solar variation, 4) the installation cost of PVs and batteries, (5) the respective maintenance cost, etc. At the same time the expected loss of load power and energy should be zero in case of a null forced outage rate for all SAPV elements. In Section 5, the results and the discussion for the respective case study of a SAPV power system for the shoreline electrode station of the small island of Stachtoroi is presented. The adopted dimensioning method is compared with the respective classical dimensioning SAPV methods [10,11,12]. Finally, general conclusions are drawn and discussed in Section 6. The major contributions of this paper are:
  • The definition of the electrical and architectural design principles of SAPV configuration for the off-grid power supply of the load demand for the shoreline electrode station of a HVDC link with very high requirements of availability,
  • The proposed techno-economic optimization process, which can jointly determine the type and the size of PVs and batteries from real technical data directly based on the equivalent annual total cost minimization taking into account all possible combinations iteratively. Even if this numerical method looks simple, it should overcome a large number of problems, i.e., the calculation of the capital cost for different PV configurations, which can include various converters, roof expanding, etc. In other relative research works [3,4,8,9,10,11,12,13,14,15,16,17] the discrete cost of the converters, roof expanding, etc., are ignored using typical capital cost functions for PVs panels, batteries, etc.
  • The proposed sensitivity analysis, which is based on the variation of the equivalent annual total cost with respect to (a) the size of the PVs and of the batteries for every possible type combination of PVs and batteries and (b) the interest rate without inflation. The parametric interest rate allows the evaluation of the stability of the configuration of PVs and batteries for different financial scenarios.
  • The mathematical formulation of PV power production, where the available solar irradiation for a time period of a specific day is calculated by the proposed solar radiation modification factor based on the respective available mean monthly irradiation. In this way different timescales for available data (i.e., temperature and solar radiation, which influence the load demand and the power production respectively) are bridged.
  • The estimation of the economic lifetime of the battery, which takes into consideration (a) the battery capacity degradation and (b) the operation failure of the SAPV due to energy deficiency of the PVs-batteries system. The energy deficiency avoidance ensures high reliability in the operation of the SAPV system from the energy supply capacity point of view.

2. Design Principles for an Electrode Station of the HVDC Link: The Case of the Small Island of Stachtoroi for the Attica–Crete Interconnection

2.1. General Issues of the HVDC Attica–Crete Inteconnection, Greece

The main target is securing the electric power supply of Crete Island in Greece by the continental Greek power system, while the thermal diesel oil units are shut down for environmental reasons, especially with regard to CO2 emissions nullification in the city of Heraklion. The mean demand load of Crete is about 340 MW with a peak load of 600 MW approximately with increment trends because of the growth of tourism and the industrialization of agriculture. Additionally, wind parks and photovoltaic parks of 2 GW can be installed in the island, which can cover the load demand whilst the excess power should be stored in long-term operation energy storage system, i.e., hydro-pumped plants, and be transmitted to the continental system of Greece. These reasons have led to the design and construction of two interconnections, as shown in Figure 1:
  • Interconnection Peloponnese–Crete: 2 three-phase 132 km transmission lines with a cross-linked polyethylene (XLPE) cable technology at a maximum depth of 980 m with nominal apparent power 2×200 MVA, at a nominal voltage of 150 kV, with a frequency of 50 Hz and high voltage gas insulated substations (GIS).
  • Interconnection Attica–Crete: a 380 km bi-directional HVDC link with a bipolar heteropolar configuration with ground return beyond the sea, with a mass impregnated non-drain (MIND) or XLPE cable technology at a maximum depth of 1250 m with a nominal power of 2×500 MW, at a nominal voltage of ±500 kV DC and voltage source converters.
The last connection will be the main one and it could be an integral part of the EuroAsia power interconnection between Greece–Cyprus–Israel [44], while the interconnection Peloponnese–Crete has a supplementary role, as it cannot supply the total island load demand with its renewable energy sources (REs) without the thermal units operation or the HVDC interconnection for power adequacy and stability issues [48].
Using the sea as a “return” cable in the Attica–Crete interconnection, there is a saving of 200 M€, while the total budget is 1200 M€. The cost of the construction of the two shoreline/pond electrode stations in Korakia, Crete and in Stachtoroi island, Attica [44] ranges from 2 to 5 M€.

2.2. General Guidelines by CIGRE and IEC for the Design of the Power Supply for the HVDC Eletrode Station

The general guidelines for HVDC electrode design by CIGRE [45] and IEC [46] are focused on the:
  • Electrode type selection, which is influenced by the distance between the converter station and the prospective electrode site, the soil resistivity in the area of the converter station, the operational duties of electrode operation and its limitations, the operation and maintenance processes, the expected cost, the land use limitations, the safety at the electrode site, and the possible adverse affections at the infrastructure elements.
  • Site selection, which is influenced by the site exclusion for environmental reasons and neighboring electromechanical infrastructures, human settlements, culturally sensitive areas, etc., the technical, economic, geophysical, geological, and hydrological aspects.
  • Local and remote impacts of electrodes operation, which includes corrosion of infrastructures, saturations of electrical transformers, potential rise and surface potential gradient at the land–sea infrastructures and the safety risks for humans, plants, animal, and marine life, soil or water overheating and the respective chemical reactions, etc.
On the contrary the instructions for connection between the electrode station and converter station for electrode stations are limited. More specifically, the guidelines of CIGRE ([45], chapter 7) for the design of the electrode of HVDC stations are limited to the requirements for electrode site monitoring, station AC and DC services, and communication links to the HVDC station or to central supervisory facility. However, the guidelines do not take into consideration the type of the electrode, the number and type of monitoring systems required at the site for facilitating HVDC scheme operation, the electrode line monitoring scheme, and the utility or owners operational and maintenance practices. The respective proposed solution for the power supply of a shoreline electrode station for the Greek distribution network would be a low voltage feeder of 230/400 V, which can cover a demand lower than 150 kVA sufficiently. The off-site service will be typically a medium voltage (MV) feeder of 20 kV. A typical single line diagram for the station service of a site with a building and back-up diesel generator according to ([45], paragraph 7.2) is shown in Figure 2 satisfying the reliability criterion of “n + 1” power sources.
Typically, non-availability of the auxiliary power system should not impact the performance of the grounding electrode negatively, and the HVDC link should operate in a degraded mode reliably without the auxiliary systems available with little or no operator intervention ([45], paragraph 7.1). However, in the HVDC link between Attica and the island of Crete the reliability level should not be decreased, because in the final operation stage the Hellenic Independent Power Transmission Operator (H-IPTSO) requires the thermal power plants in Crete to be shut down, while the HVAC Peloponnese–Crete interconnection cannot handle the load demand alone. So, another design is necessary based on the reliability criterion of “2 × n” power sources, which is used in navy ships [49], hospital operation rooms, and intensive care units [50]. Additionally, the shoreline electrode station in Stachtoroi Island is isolated and cannot be easily connected with the medium or low voltage distribution network.

2.3. Proposed Special Guidelines for the Design of the Power Supply for the HVDC Eletrode Station

Taking into consideration the aforementioned issues of the last paragraph the respective guidelines should be improved in two axes:
  • HVDC interconnection with high reliability levels: The power supplies for normal and emergency operation are duplicated, which means that it will be two network feeders and two back-up sources, i.e., one generator and one big energy storage system or two generators. The vital loads for the HVDC interconnection, such as the control system, communication system, heating–ventilation–air condition (HVAc), etc., should be duplicated. For example, the programmable logic controller (PLC) system for the HVDC electrodes switchgear control is constructed by two similar units, which operate in the master–slave mode and their power supply is realized by two different power sources. Similarly the HVAc system for the main electrode station room consists of two units, where each one can cover the heating/cooling load completely. The essential loads, i.e., water pumps, can be supplied by two sources, while the non-essential loads, i.e., sockets for cleaning/maintenance purposes, can be divided to the two sources. Additionally, the proper circuit breaker between AC buses or DC buses must exist for alternative supply of essential and non-vital loads. The basic idea is presented in Figure 3.
  • Isolated/off-grid power supply for electrode stations: The connection, with the distribution network or the formation of an autonomous power system, should be decided based on minimization of the total construction, operation and maintenance cost taking into consideration technical limitations, i.e., the loss of load probability, economic, i.e., construction capital limitation, environmental, i.e., CO2 emissions reduction, etc., optimizing the selection of the type and of the size of the REs and ESSs. It is noted that the alternative autonomous system can be formed by classic thermal units, especially diesel oil generators between 10 and 25 kVA, which is the most common power plant for this power supply, or by REs, especially wind turbines and PVs, combined with ESSs, i.e., batteries or more rarely hydrogen tanks with fuel cells and electrolyzer modules, and a hydro-pumped storage power plant.
Additionally, some complicated conditions should be ensured, such as:
A remote control for the autonomous power system,
A dedicated electrode station building design, which includes:
The limitation of the energy consumption beyond the respective regulation requirements, i.e., category A [51] reducing the autonomous power size (ideally zero energy building),
No use of structural steel and metallic mechanical settlements because of the danger for electrochemical corrosion of metallic structures by the direct current flow between electrode stations [45] (i.e., concrete with glass fiber reinforced polymers can be suitable).
Protection with the highest significance factor against environmental dangers, i.e., floods, earthquakes, etc.,
Proper building orientation for PV production maximization,
Proper foundation insulation material, i.e., asphalt, as damp proofing against humidity and electrical insulator against direct current flow between electrode stations and step voltage [45], etc.
Reduction of fire risk. This can be succeeded by:
The increment of fire-resistance because of ESSs existence and electrode station isolation,
The supplementary of the autonomous fire-fighting system, specialized in the presence of high voltage and active electric circuits [52], with energy storage systems [53] and crucial computer/control systems [54]. The use of dedicated fire-fighting agents, as inert gas (i.e., FM200, Novec 1230) [55,56] and special equipment, such as sprinklers [57] and impulse fire-fighting guns [58], are necessary.
It is noted that fire-protection codes do take into account the usual urban and suburban environment, but not the isolated and unapproachable area of the electrode station. So, the architecture design should proceed beyond the respective codes and may require the separation between energy storage systems, the main electrode station, the engine room, the control room, etc.
Generally, the following steps for the design of the electrode station building can be proposed:
  • Preliminary architecture design of the electrode station building based on engineers’ experience for similar buildings taking into account concrete, antiseismic, energy saving legislation, etc., and rules for electrical–mechanical equipment and distribution, etc.
  • Optimum minimization of the total cost function with respect to technical, environmental, economic limitations, formatting the connection of distribution network, or the autonomous power system including the type and the size of their main elements.
  • Examination of whether the selected power supply and supplementary settlements are satisfied by the preliminary architecture design, go to the next step, otherwise go to the first step to correct the architecture design.
  • Examination of economic viability through feasibility studies, taking into account interest rate, life cycle, construction and maintenance cost, etc.
  • Selection of the optimum architecture design.
Here, the second step for the design methodology of the electrode station building will be analyzed in the next sections for the SAPV system.

2.4. Special Conditions for the Small Island of Stachtoroi for the Attica–Crete Interoconnection

The electrode station of Attica has been placed on the island of Stachtoroi in the Saronic Golf, because of its adjacency to the Koumoundorou converter station in Eleusis, Attica. Simultaneously, it is quite far from residential and industrial settlements for the avoidance of electrochemical corrosion of metallic structures by the direct current flow between electrode stations [44]. The distance between this uninhabited small island with no settlements and the nearest residential area (Aegina) is 7.8 km, as it can be seen in Figure 4.
Taking into consideration the aforementioned circumstances the electrode station can be supplied either by a medium voltage three phase cable from Aegina through a step down transformer and having a back-up diesel generator power plant and a proper back-up energy storage system of at least for 48 h, or by an autonomous power system. The first solution requires the architectural design of Figure 5, which includes the main electrode station room, the Hellenic Electricity Distribution Network Operator’s (H-EDNO) medium voltage switchboard room, the electrode station medium voltage switchboard room, a transformer room, a low voltage switchboard room, a control/accommodation room, a battery room, a back-up diesel generator room, a storage room, a water and pump room, a water closet (W.C.), etc. The sheltered solution for the distribution connection equipment has been chosen for sea salinity protection.
Alternatively, the autonomous system can involve PVs, two batteries subsections and two back-up diesel generators according to the reliability criterion of “2 × n” power sources (see Section 2.2). Wind generators cannot be used, because Stachtoroi is a protected sanctuary for seagulls. The PVs should be suitable for marine applications because they are put near to the seaside (5–10 m from the shore). The batteries can be valve regulated lead acid (VRLA) ones or AGM ones, but not classical flooded lead acid ones because of the maintenance issues or lithium-ion ones because of serious difficulties in the case of fire, which is why the National Fire Protection Association (NFPA) rules propose a small capacity of 50 kWh per fire protective segment [53]. For the same fire risk reasons, solutions as hydrogen tanks are not proposed, while a hydro-pumped storage plant cannot be placed because of a small height difference in the island. The respective architecture solution is presented in Figure 6, which includes the main electrode station room, the control/accommodation room, two battery rooms, two back-up diesel generator rooms, a storage room, a water and pump room, a W.C., etc.
The occupied area of the second architecture design is smaller by 15% than the respective area of the first one. In both cases additional special requirements have been included beyond the respective ones of Section 2.3 and Section 2.4 because of the shoreline position of the electrode station:
  • A small breakwater and port facility is formed because of building protection from sea waves and to allow for ships calling at the installation and maintenance.
  • All rooms have proper ventilation and dehumidifier equipment.
  • External lighting is necessary, including one aviation obstruction light buoy, according to International Aviation Organization (ICAO) guidelines because of adjacency to a Hellenic Navy practice field.
  • Three 40 m3 underground tanks are constructed for firefighting and water cleanness reasons, as well as a small underground 2 m3 sewage water tank on the opposite site.
Especially for the SAPV solution, the following is also needed:
  • The building has southern exposure for the better PVs operation.
  • The PVs inclination is put at 3° for rain/water follow out, adapted to the roof, without any frame, obstructing seagulls constructing nests.

3. Classical Design Methodology for Stand Alone Photovoltaic Panels with Batteries

3.1. Basic Steps of the Classical Design Methodology

The basic steps for the sizing of the power system with PVs and batteries are:
  • Daily electric energy consumption: The power system total daily peak load PA and the daily energy Eday are calculated as:
    P i n s t a l l i = N i × C i n s t a l l i
    P A i = P i n s t a l l i × ζ i × σ i
    P A i = P A i / r i
    E i = m i × P A i × T
    P A = i = 1 N P A i
    E d a y = i = 1 N E i
    where Cinstall-i is the installed power of the ith electric consumer, Νi the consumer population, Pinstall-i the total install power of the ith consumer type, ζi the demand factor, σi the coincidence factor per consumer category, PA-i the peak load per consumer category, ri the participation factor at the power system total peak load, mi the mean load factor for time period under study T (=24 h), PA-i the partition peak load per consumer category at the power system total peak load, and Ei the energy demand per consumer category.
  • Optimized selection of the inclination angle/slope a for PVs based on the time period optimized operation and PVs azimuth angle: The slope a is connected with latitude φ and daily solar radiation with no-linear process:
    Solar declination δ calculation for the current day of the year for the calculation of daily solar irradiation (DoY; i.e., DoY = 1 for 1 January):
    δ ° = 23.45 ° × s i n ( 360 ° 365 × ( D o Y 81 ) )
    Total mean solar irradiation Hm at the horizontal level in the Earth surface determination either by an experimental process, or by a bibliography for the specific area in kWh/m2 per month [11].
    Time sunset ωs calculation:
    ω s = c o s 1 ( t a n δ × t a n φ )
    Mean monthly extraterrestrial solar irradiation Hom at the horizontal level without the Earth atmosphere in kWh/m2 per month [11]:
    H o m = M m × 24 × I o π × ( 1 + 0.0333 × c o s ( 360 ° 365 × D o Y ) ) × ( c o s φ × c o s δ × s i n ω s + s i n φ × s i n δ × π ω s 180 ° )
    where Μm is the population of days of the mth month and Ιο the solar constant or otherwise the long-term average extraterrestrial total solar irradiance equal to 1367 W/m2 [10].
    Lucidity Km calculation as the ratio between the mean monthly solar irradiation Hm at the horizontal level in the Earth surface and respective extraterrestrial solar irradiation Hom at the same level:
    K m = H m H o m
    Determination of the ratio between diffused solar irradiation Hmd at the horizontal level in the Earth surface and the respective total solar irradiation Hm based on Lala’s function ([11], Equation (2.48)):
    H m d H m = 1446 2965 × K m + 1727 × K m 2
    Calculation of correction factor RB of the total direct mean monthly solar irradiation for the south-facing PVs with slope a with respect to the total mean monthly solar irradiation for horizontal PVs:
    R B = c o s ( φ a ) × c o s δ × s i n ω s + s i n ( φ a ) × s i n δ × π 180 ° × ω s c o s φ × c o s δ × s i n ω s + s i n φ × s i n δ × π 180 ° × ω s
    where ωs′ is the hourly sunset angle for the day DoY for the south-facing PVs with slope a:
    ω s = min { ω s , cos 1 ( tan δ × tan ( φ a ) ) }
    Calculation of correction factor RM of the total mean monthly solar irradiation for the south-facing PVs with slope a with respect to the total mean monthly solar irradiation for horizontal PVs ([11], Equation (2.47)):
    R M = ( 1 H m d H m ) × R B + H m d H m × 1 + c o s a 2 + ρ × 1 c o s a 2
    where ρ is the solar radiation reflection factor with a typical value of 0.2 for land use, 0.05 for asphalt, sea, dark-colored rocks, etc., and 0.60 for light-colored rocks, etc.
    Calculation of total mean solar irradiation Hm-panel for the south-facing PVs with slope a in the Earth surface ([11], Equation (2.51)):
    H m p a n e l = R M × H m
According to the previous subsection, PVs inclination has been adapted to the roof, without any frame, so the respective angle of the obstacles’ shadow is null and the total mean solar irradiation has not been modified according to ([10], p. 264, eq. (35), [11], Equation (2.47), [11], and Equation (2.51)).
   ➢
Calculation of total mean solar irradiation Hm-panel-Tp for the time period under optimized operation Tp:
H m p a n e l T p = m T p M m × H m p a n e l
For different combinations of slope a with the null shadow angle, the maximum total mean solar radiation for the time period optimized operation is selected.
It is noted that Equation (7) to Equation (16) can be used either for the monthly solar irradiation, or the daily one or another time period. In the case of the month of study, a typical DoY is equal to 15, 46, 74, 105, 135, 166, 196, 227, 258, 288, 319, and 349 for January, February,…, and December respectively.
  • Calculation of the daily available solar irradiation/energy Hm-panel-day for the selected slope a with the null shadow angle:
    H m p a n e l d a y = H m p a n e l M m
  • Calculation of the population of PVs with nominal power PnomPV, nominal voltage VnomPV, and nominal InomPV at standard test conditions (STC: 1.5 AM, PSTC = 1000 W/m2, 25 °C): The essential power supply Ρα_mon by the PVs is given by:
    P a _ m o n = σ i n _ E d a y × E d a y × P S T C σ T o t L o s s P V × σ T r a n _ e l _ l o s s e s × H m p a n e l d a y × M m M m n
    where the autonomy population of days n varies from 5 to 10 (for critical settlements), the PV daily energy increment factor σin_Eday with typical values range from 115% up to 125% depending on the accuracy of the estimation for the daily electrical energy consumption, the PV transmission electrical losses correction factor σTran_el_losses with typical values range from 75% up to 99% depending on the existence of DC or AC buses, converters–inverters batteries ([10], p. 406, Table 9), the factor of the total loss of PVs σTotLossPV is given by:
    σ T o t L o s s P V = σ p o l l u t i o n × σ a g e i n g × σ b l o c k i n g _ d i o d e × σ n o _ h o m o g e n e i t y × σ c a b l e × σ T e m p
    where the PV pollution correction factor σpollution with typical values range from 80% up to 95%, the PV ageing correction factor σageing with a typical annual degradation 1%, the blocking diode losses correction factor σblocking_diode with a typical value of 99%, the PV lack of homogeneity factor σno_homogeneity with a typical value of 98%, the PV cables losses factor σcables with typical values range from 97% up to 99%, the PV temperature correction factor σTemp is given by the mean monthly temperature Tmonth when the temperature difference between the environment and PVs is DTen-PV, the environment temperature Tref-en, and the typical power decrease factor fd_Temp [10]:
    σ T e m p = 1 ( T m o n t h + D T e n P V T r e f e n ) × f d _ T e m p
    The necessary population of PVs Npanel is calculated by:
    N p a n e l = P a _ m o n P n o m P V
  • Capacity calculation of the battery storage system based on autonomy population of days n and battery depth of discharge DoD: The essential battery capacity Cnom of the ESSs with operation nominal voltage VnomESS is given by:
    C n o m = 1 k T e m p × σ i n _ E d a y _ E S S × E d a y × ( n + D ) σ a g e i n g _ E S S × σ T r a n _ e l _ l o s s e s _ E S S × D o D × V n o m E S S
    where the indirect PV service of the electric consumption factor D with typical values range from 0% up to 100% (typical value 80% in case that PVs supply the 20% from electrical load consumption directly), the battery daily energy increment factor σin_Eday_ESS with typical values range from 115% up to 125% depending on the accuracy of the estimation for the daily electrical energy consumption, the battery transmission electrical losses correction factor σTran_el_losses_ESS with typical values range from 90% up to 97% depending on the existence of DC or AC buses, converters–inverters ([10], p. 417), the battery ageing correction factor σageing_ESS with a typical value of 80% for lead acid batteries ([10], p. 415), the battery temperature correction factor kTemp is given with respect to the annual temperature Tyear:
    k T e m p = { 1 , T y e a r 20   ° C 1 20   ° C   T y e a r 160   ° C , T y e a r < 20   ° C
  • Calculation of electrical installation elements: The configuration and the number of battery elements and of PVs, the dimensions of cables, converters, battery chargers, and control systems are determined taking into consideration the electroscience principles, i.e., the cable dimensions include the insulation level based on maximum operation voltage, the conductor cross section based on the maximum thermal operation current, maximum short circuit current, voltage drop, protection system design, etc. [50].

3.2. Daily Electric Energy Consumption for the Electrode Station of Stachtoroi Island

In case of a SAPV system, each electric consumption of the electrode station should be studied during different seasons (winter, summer, and autumn–spring) and different operational modes (stand alone mode and maintenance mode). At the maintenance mode the electrode station is inhabited by H-IPTSO personnel for a few hours per month, while the operation of back-up diesel-electric generators is necessary for the generators maintenance. The heating and cooling split units operate for keeping the temperature between 10 and 30 °C in battery rooms and the electrode station room for all modes, and between 20 and 26 °C in the accommodation room during the maintenance mode. The extreme external temperature is 0 °C for the winter and 40 °C for the summer season. Lighting, heating, cooling, ventilation, and dehumidifier loads are estimated per each room based on its dimensions of Figure 6 and the respective electric consumer is formed. In Table 1, Table 2 and Table 3 the respective consumers per room with area A and the respective power and energy demand are presented. The total daily peak load and the daily energy were calculated by Equation (1) to Equation (6).
It is noted that the participation factor at the power system total peak load ri was equal to 1 because of a lack of experimental data, so in this case the peak load PA-i per ith consumer was equal to the partition peak load PA-i. The only exception involves sockets, where it is acceptable that 2 sockets lines can be in operation at peak load from a total of 11 lines at the maintenance mode, which means that the respective factor was equal to 5.5. From the respective results the following remarks could be mentioned:
  • For the normal operation mode the total daily peak load was 4.8 kW during spring–autumn without split units in operation, 8.44 kW during winter with split units in maximum heating operation and 8.5 kW during summer with split units in maximum cooling operation, whereas the maximum daily energy load consumption was 11.93, 40.16, and 47.64 kWh respectively.
  • For the maintenance mode with diesel-electric generators in operation the total daily peak load was 17.3 kW during spring–autumn, 22.02 kW during winter and 22.25 kW during summer, whereas the maximum daily energy load consumption was 34.44, 79.99, and 98.47 kWh respectively, even if its practical value was limited to the fuel oil tank dimensions because of only a few hours of operation.
In this case the maximum peak load was 22.25 kW with typically an inductive power factor of 0.8, the respective maximum apparent power was 27.8 kVA, which means that one back-up 25 kVA diesel engine electric generator power unit with 10% overload capability for small time periods should be used. The respective engine room can receive the power unit. Otherwise, H-EDNO should give a three-phase typical power supply of 25 kVA.

3.3. Preliminary Study of Stand-Alone Photovoltaic with Batteries for the Electrode Station of Stachtoroi Island

After the calculation of the daily electric energy consumption (Section 3.2), the total monthly mean solar irradiation Hm-panel for the south-facing PVs with slope a in the Earth surface can be realized by Equation (7) to Equation (16) with a reflection factor equal to 0.2 because of the mixed environment (sea, light-colored earth) without the shadow angle in Stachtoroi Island, Attica (longitude −23.361770°, latitude 37.815199°). In this case the PVs slope was set at 3° for rain/water run-off, adapted to the roof, without any frame, with a null shadow angle, obstructing seagulls to construct nests causing mediocre solar radiation for the winter months (see Hm-panel in Table 4). It is noted that the best slope was 28° annually, whilst for the summer period the slope should be small and for the winter period big at 60°.
Next, the photovoltaic panel Sxp154Q or Sxp154L by Solbian [60] was chosen, which is suitable for marine applications with PnomPV = 154 W, VnomPV = 18.2 V, InomPV = 8.5 A at STC, open circuit voltage Voc = 23.0 V, short circuit current Isc = 9.1 A, DTen-PV = 30 °C, Tref-en = 25 °C, fd_Temp = 0.38%/°C, and dimensions 1046 mm × 996 mm × 2 mm or 1523 mm × 683 mm × 2 mm, respectively [60]. The autonomy population of days n was equal to 10 because of the critical settlements, the PV daily energy increment factor σin_Eday was 115% and the battery daily energy increment factor σin_Eday_ESS was 115% because of the high accuracy of the estimation for the daily electrical energy consumption estimation, the PV transmission electrical losses correction factor σTran_el_losses was 85% and the battery transmission electrical losses correction factor for energy storage system σTran_el_losses_ESS was 91% because of the existence of AC bus with inverters batteries, etc., the PV pollution correction factor σpollution was 90% because of the small inclination and of the use of cleanliness water sprinkler system, the PV old age correction factor σold_age was 90% because of a typical marine PVs time life of 10 years, while the rest factors had typical values (σblocking_diode = 99%, σno_homogeneity = 98%, σcables = 98%, σTemp by Equation (20), σold_age_ESS = 80%, D = 80%, and kTemp by Equation (23)). The battery nominal voltage VnomESS was 110 V, because of the H-IPTO battery system standardization reasons, while the available depth of discharge DoD was 70% for 7–10 autonomy days ([10], p. 416, Table 16). The respective population of PVs was calculated by Equation (18) to Equation (21), while the battery capacity by Equation (22) and the results are presented in Table 4, where daily energy Eday per month varied, because the heating–cooling electric load of split units was modified linearly with respect to the monthly mean temperature Tmonth.
From the respective results the PV nominal power should be 19.48 kW, which means 128 panels Sxp154Q practically in 4 parallel branches with 32 panels in series succeeding a maximum open circuit voltage of 864.4 V with the 115% safety factor, maximum short circuit current of 11.38 A per branch with the 125% safety factor, nominal operation voltage of 582.4 V at maximum power, maximum nominal operation current of 10.63 A at maximum power for cables dimensions, etc. The nominal power per branch was 4928 kW and the maximum one 6.16 kW (+25% for solar radiation superabundance). So, if each inverter serves two branches, its nominal power should be 12.4 kW at 400 V AC/50 Hz and two inverters is needed typically. Each inverter with two branches forms a PV power plant, as it is shown in Figure 7. The building roof should be also expanded by 1.0 m per each dimension so as to be 14.30 m × 8.60 m, as it is presented in Figure 8. Other PV formations need more area.
For the battery system a capacity of 3724 Ah at 110 V should be formed. If the 12 V 100 Ah AGM VRLA battery element is chosen by Narada Company [61], 342 VLRA elements will be needed—38 parallel branches with 9 elements in series. So, two battery storage systems are formed with 17 parallel branches × 9 elements in series. Alternatively, if the 2 V 1360 Ah gel form RES 8 SOPzV 1360 battery element is chosen by Sunlight Company [62], 165 elements will be needed—3 parallel branches with 55 elements in series forming three battery storage systems, respectively. The division of PVs and energy storage system in parts improves reliability behavior generally. In case of failure of one battery system the remaining ones should cover the total load demand, i.e., if two ESSs exist, their chargers/dechargers nominal power can be equal to the peak load or if three ESSs exist, their chargers/dechargers nominal power can be equal to the half of the peak load.
Additionally, two back-up diesel-engine generator sets of 25 kVA are put in with a fuel oil tank of 1000 L for each one, for reliability reasons. They are going to serve the load demand rarely, either in the maintenance mode or in case of a total failure of the autonomous system operation. The respective interconnections between AC buses or DC buses are presented in Figure 7.
However, this preliminary design does not ensure that the proposed system is the optimized one with technical-economic criterions, while crucial elements have been ignored or simplified such as the PVs and battery lifetime, degradation of the battery capacity based on the depth of discharge, battery self-discharge, PV power production variation because of seasonal and daily solar radiation variance, load demand variation because of seasonal and daily temperature variance, etc. In the next section the proposed methodology will confront these issues.

4. Proposed Design Methodology for Stand Alone Photovoltaic Panels with Batteries

4.1. Basic Goals of Proposed Design Methodology for SAPV with Batteries

The basic goal of the proposed methodology is to minimize the total cost of construction, operation, and maintenance of the stand-alone photovoltaic panels with batteries that supply the electrode station at the Stachtoroi Island, varying the PVs population and the type and the capacity of batteries, taking into consideration simultaneously:
  • The daily operation process of the respective power system with the technical limitations of PVs, inverters, batteries, etc.,
  • The seasonal and daily variation of the electrode station load demand with respect to the available temperature (here the average three hours temperature for 15 years are available from the neighboring meteorological station),
  • The seasonal and daily variation of PV power production with respect to the available radiation (here the mean monthly irradiation is available in the neighboring area from [11] and its time-scale is properly adjusted through the process of Section 4.3),
  • The reliability level from an energy point of view, where the SAPV operation will be failed if the load demand is supplied by the back-up diesel-engine generator sets because of energy deficiency of the PVs-batteries system (the generator sets should operate only in case of forced outages).
  • The environmental limitation of CO2 emissions reduction, which is succeeded indirectly as the generator sets are going to operate only for maintenance and SAPV forced outage reasons, not for energy supply systematically, which means that CO2 emissions are nullified practically.
Next, the respective mathematical description will be presented.

4.2. Mathematical Formulation of the SAPV Daily OPERATION Process

Each SAPV configuration, which consists of a specific PVs population Npanel, of the battery type (i.e., AGM VRLA, and gel), and of the battery capacity Cnom, is studied during its operation. During the time period under study Tp for each time step t with a time duration of dt the PVs power production PPV(t) is constant, and is determined by the solar radiation of that time step and the daily hour in Section 4.3, while the load demand Pload(t) is also constant and its value is calculated with respect to the environmental temperature Ttemp(t) taking into consideration the electrical consumptions of Table 1, Table 2 and Table 3 with emphasis in split-units operation, where the respective load demand Pload_split_unit is formed as:
P l o a d _ s p l i t _ u n i t ( t ) = { P l o a d _ s p l i t _ u n i t _ w i n t e r , T t e m p ( t ) T w i n t e r 2 P l o a d _ s p l i t _ u n i t _ w i n t e r × T w i n t e r 1 T t e m p ( t ) T w i n t e r 1 T w i n t e r 2 , T w i n t e r 2 T t e m p ( t ) T w i n t e r 1 0 , T w i n t e r 1 T t e m p ( t ) T s u m m e r 1 P l o a d _ s p l i t _ u n i t _ s u m m e r × T t e m p ( t ) T s u m m e r 1 T s u m m e r 2 T s u m m e r 1 , T s u m m e r 1 T t e m p ( t ) T s u m m e r 2 P l o a d _ s p l i t _ u n i t _ s u m m e r , T s u m m e r 2 T t e m p ( t )
where during the winter period the maximum power load demand by split-unit is Pload_split_unit_winter at temperature Twinter2 and its operation starts under temperature Twinter1, while during the summer period the respective maximum power load demand by split-unit is Pload_split_unit_summer at temperature Tsummer2 and its operation starts above temperature Tsummer1.
The battery stored energy E(t) at the time step t is formed with respect to the previous time step (t − 1) and operation phase (charge, discharge, and no-operation) by:
Charge   phase :   E ( t ) = ( 1 n r ) × E ( t 1 ) + n c h × P c h ( t ) × d t
Discharge   phase :   E ( t ) = ( 1 n r ) × E ( t 1 ) P d i s ( t ) n d i s × d t
No-operation   phase :   E ( t ) = ( 1 n r ) × E ( t 1 )
Under the following conditions:
Power   balance   for   all   phases :   P c h ( t ) + P l o a d ( t ) + P a d d ( t ) = P d i s ( t ) + P P V ( t ) + P L O E ( t )
Only   one   phase   existence :   P d i s ( t ) × P c h ( t ) = 0
Battery   power   limitations   during   the   charge   phase :   0 P c h ( t ) P c h m a x
Battery   power   limitations   during   the   discharge   phase :   0 P d i s ( t ) P d i s m a x
Battery   energy   limitations :   0 S o C j j ( t ) ( t ) j j ( t ) m a x m i n
Produced   PV   power   loss   limitation :   P a d d ( t ) × u ( S o C j j ( t ) ( t ) m a x ( ) )
Load   demand   power   loss   limitation :   P L O E ( t ) × u ( E ( t ) S o C j j ( t ) m i n ( ) )
Under the following definitions:
State   of   charge   S o C ( t ) / Depth   of   discharge   D o D ( t ) :   S o C ( t ) = 1 D o D ( t ) = E ( t ) C n o m × V n o m E S S
Produced   PV   energy   loss :   E a d d = t = 1 T p P a d d ( t ) × d t
Load   demand   energy   loss :   E L O E = t = 1 T p P L O E ( t ) × d t
where Pch(t) is the battery charge power, nch the charge efficiency factor, Pdis(t) the battery discharge power, ndis the discharge efficiency factor, nr the self-discharge rate (i.e., 2–20% per month for lead acid batteries), Padd(t) the produced PV power loss in case of maximum state of battery charge and Εadd the respective energy, PLOE(t) the load demand power loss in case of the minimum state of battery charge and ΕLOE the respective energy, SoC(t) the state of battery charge, which is connected with the depth of discharge DoD(t) univocally by Equation (35), Cj′ the remaining capacity of battery for the jth day of the time period under study, Vj/(t) the respective battery voltage, SoCmin and SoCmax the minimum and the maximum state of battery charge (i.e., 20% and 95% for lead acid batteries) respectively, Pch-max the maximum battery charge power (which is determined by the nominal characteristics of charger and the battery nominal current that varies between 1% and 500% of the nominal discharge current in 10 h for lead acid batteries), and Pdis-max the maximum battery discharge power (which is determined by the nominal characteristics of the charger and the maximum battery nominal discharge current. In our case, for 10 days of autonomy the mean discharge current lasts more than 100 h, which is the biggest duration usually listed by manufacturers [61,62]). u(x) is the classical step function.
The aforementioned steps are repeated until either the lifetime of elements (usually of the battery) is exhausted according to the elements ageing process (see Section 4.4 for battery degradation and Equation (63)) or the load demand power loss is not zero, so back-up generators should be operated because of energy inadequacy. The energy deficiency of the PVs-battery system also determines the economic lifetime of crucial elements such as batteries, even if their physical lifetime have not been exhausted, and it will be the alternative stopping criterion of steps repetition. Practically the maximum Tp is found, when the multiplicands of Equation (34) are null marginally. Simultaneously, the reliability level of energy adequacy is satisfied as the load demand power loss and the energy loss are ensured to be zero until that time step.

4.3. Mathematical Formulation of the PV Panels Power Production

The available solar radiation data is the mean monthly irradiation Hm-panel by Table 4, which gives the daily available solar irradiation Hm-panel-day by Equation (17) easily. In order to find out the PVs power production during t and t + dt hours the respective available solar irradiation Hm-panel-day(t, t + dt) is calculated based on Hm-panel-day and the proposed solar radiation modification factor fHmday(t, t + dt):
H m p a n e l d a y ( t , t + d t ) = f H m d a y ( t , t + d t ) × H m p a n e l d a y
f H m d a y ( t , t + d t ) = t a n δ × t a n φ × ( ω ( t + d t ) ω ( t ) ) + ( s i n ( ω ( t + d t ) ) s i n ( ω ( t ) ) ) 2 × ( t a n δ t a n φ ω s + s i n ω s ) 0
Under the conditions for sunrise and sunset hours:
ω s ω ( t ) ω s   &   ω s ω ( t + d t ) ω s
This happens because the sun angle position (altitude) during the day is given by:
s i n β = s i n δ × s i n φ + c o s δ × c o s φ × c o s ω
So, the daily available solar irradiation Hm-panel-day for the selected a angle inclination with the null shadow angle is calculated based on the solar declination δ by Equation (7), the ωs sunset, the (−ωs) sunrise, the Μm population of days of the mth month, and the Io-mday solar radiation intensity and it is:
H m p a n e l d a y = H m p a n e l M m = I o m d a y × ω s ω s ( s i n δ × s i n φ + c o s δ × c o s φ × c o s ω ) × d ω
where the parameters a1 and a2 are determined as:
a 1 = I o m d a y × s i n δ × s i n φ
a 2 = I o m d a y × c o s δ × c o s φ
From the combination of Equations (43) and (44):
a 1 = a 2 × t a n δ × t a n φ
From the combination of Equations (41) and (43):
H m p a n e l d a y = ω s ω s ( a 1 + a 2 × c o s ω ) × d ω = a 1 × 2 × ω s + a 2 × 2 × s i n ω s
From the combination of Equations (45) and (46):
a 2 = 1 2 × H m p a n e l d a y s i n ω s + ω s × t a n δ × t a n φ
Under conditions of Equation (40) the available solar irradiation Hm-panel-day(t, t + dt) between t and t + dt hours is equal to:
H m p a n e l d a y ( t , t + d t ) = I o m d a y × ω ( t ) ω ( t + d t ) ( s i n δ × s i n φ + c o s δ × c o s φ × c o s ω ) × d ω                            H m p a n e l d a y ( t , t + d t ) = ω ( t ) ω ( t + Δ d t ) ( a 1 + a 2 × c o s ω ) × d ω H m p a n e l d a y ( t , t + d t ) = a 1 × ( ω ( t + d t ) ω ( t ) ) + a 2 × ( s i n ( ω ( t + d t ) ) s i n ( ω ( t ) ) )
H m p a n e l d a y ( t , t + d t )                             = I o m d a y × t a n δ × t a n φ × ( ω ( t + d t ) ω ( t ) ) + ( s i n ( ω ( t + d t ) ) s i n ( ω ( t ) ) ) 2 × ( t a n δ × t a n φ × ω s + s i n ω s )
Next, the PVs power production PPV(t) is calculated by:
P P V ( t ) = σ T o t L o s s P V × σ i n v × σ P V × H m p a n e l d a y ( t , t + d t ) d t × N p a n e l × A p a n e l
Under the condition:
P P V ( t ) P P V m i n
where σinv is the PV inverter efficiency factor (i.e., typically 0.92), σPV is the PVs efficiency factor (i.e., typically 0.147 for Sxp154Q panel), Apanel the area of one PVs (i.e., 1.041816 m2 for Sxp154Q), and PPVlim the lowest operational limit for PVs (it usually corresponds to solar irradiance 200 W/m2).

4.4. Mathematical Formulation of the Battery Capacity Degradation

The batteries manufacturers advertise a nominal lifetime Tbat_life of 5–20 years for lead acid batteries without mentioning the ageing phenomena because of charge–discharge cycles. In reality the battery storage and usage lead on static and dynamic degradation, respectively [63,64,65]. The first one is caused by the deterioration of the functional characteristics of the battery materials without any operation (only discharge can exist), mostly the electrodes corrosion and the electrolyte oxidation, while the second one is mainly affected by the electrical and thermal forces due to the battery cycle, environment conditions (especially temperature), and depth of discharge. The battery life loss rate can be divided to static and dynamic ones being formulated in years−1 [63]. Here, the mathematical formulation is based on days−1 because one battery cycle is practically realized every day, as during daylight the battery is charged by PVs, while during night it is discharged. The daily static loss rate γs′ is calculated by:
γ s = 1 T b a t _ l i f e [ d a y s ]
The daily dynamic loss rate γd-j′ is estimated by:
γ d j = i = 1 n j 1 N D j
where ND-j′ indicates the maximum number of cycles allowed for the actual remaining capacity of the battery corresponding to its discharge depth remaining between specific upper and lower limits of the nominal capacity, while nj is the number of cycles during a day. In case of one main cycle per day Equation (53) is simplified as:
γ d j = 1 N D j
The maximum number of cycles ND mainly depends on the depth of discharge DoD [63,64,65] and secondarily on the environment temperature [64]. Here, only DoD is considered because the temperature effect involves extra laboratory tests. The respective function can be exponential [65], double-exponential [62], simplified hyperbolic [10], hyperbolic, and power one respectively:
N D = a × e x p ( b × D o D ) :   a ,   b > 0
N D = a 1 × e x p ( b 1 × D o D ) + a 2 × e x p ( b 2 × D o D ) :   a 1 ,   a 2 ,   b 1 ,   b 2 > 0  
N D = V N D D o D D o D : V N D D o D > 0
N D = c D o D + d :   c ,   d > 0
N D = e × D o D f :   e ,   f > 0
where a, b, a1, a2, b1, b2, VND·DoD, c, d, e, and f can be estimated by the least square errors (LSE) method. The best adaptation for the ND–DoD curves is determined by the criteria of the mean square error J and correlation index r for nd experimental values pairs:
J = 1 n d × i = 1 n d ( N D i N D i , r e a l ) 2
r = i = 1 n d ( N D i N D ¯ ) × ( N D i , r e a l N D , r e a l ¯ ) i = 1 n d ( N D i N D ¯ ) 2 × i = 1 n d ( N D i , r e a l N D , r e a l ¯ ) 2
where the parameters with subscript “real” are the experimental data (or from data sheets), the NDi are estimated by LSE method, and the upper line parameter is the respective mean value.
It is noted that the batteries data sheets provide the value of the parameter VND·DoD as a constant product between the maximum number of cycles ND and the depth of discharge DoD [10,11,61,62], i.e., between 1200 and 1500 for VRLA batteries, while Equation (58) is overwhelmed by Equation (57). Sometimes Equation (56) presents poor behavior in extrapolation, so it will be avoided.
The daily degradation loss rate γa-j′ is calculated by the sum of the static and dynamic loss ones:
γ α j = γ s + γ d j
The battery system must be redrawn, if it loses its total life duration after NB days on operation:
j = 1 N B γ α j = 100 %
Furthermore, the remaining capacity of battery Cj′ for the jth day is estimated using the daily degradation loss rate γa-j′:
C j = { C n o m , j = 1 C n o m × k = 2 j ( 1 γ α ( k 1 ) ) , j > 1

4.5. Mathematical Formulation of the Cost Function

Each SAPV configuration, which consists of a specific PVs population Npanel, of the battery type and of the battery capacity Cnom, is checked not only from an operational point of view but also from a financial one taking into consideration the construction, operation, and maintenance costs for the whole life cycle. For this purpose the equivalent annual total cost TCannual should be minimized given by:
A c a p j = C c a p j × ( 1 + i r ) T j × i r ( 1 + i r ) T j 1
T C a n n u a l = j ( A c a p j + C f i x j ( P A ) + c o p j × t o p j )
where Ccap-j is the initial capital value of jth equipment with the equivalent withdrawal cost after the economic lifetime, Tj the respective economic lifetime (i.e., 10 years for marine PVs, 25 years for building roof, variable for batteries with respect to their ageing, etc.), Acap-j the equivalent fixed annual capital payment, ir the interest rate without inflation, Cfix-j the fixed annual cost of jth equipment for maintenance, personnel wages, etc., which can depend on the peak load PA, cop-j the operation cost of jth equipment, which is analog to the annual operation hours top-j and depends on maintenance. The operation cost, which depends on fuel and oil cost, is ignored because the back-up diesel generators operate only for maintenance reasons.

4.6. Basic Steps of Proposed Design Methodology for SAPV with Batteries

The basic steps of the proposed analytical design methodology for the sizing of the SAPV power system based on the sensitivity analysis regarding PVs population Npanel, the battery type, and the battery capacity Cnom, are the following:
  • Initialization of the range of PVs population: The population of PVs can receive specific values Npanel1, Npanel2, , NpanelK. The type of PVs has been preselected as the Sxp154Q panel by Solbian [60] because it is a marine application and this panel is the biggest one. It can be easily modified involving further types of PVs.
  • Initialization of the battery type and of the range of battery capacity for specific nominal voltage: The type of battery has been preselected as lead acid AGM and gel VRLA ones because they satisfy maintenance and safety against fire risk criterions, while the constructors choice is based on certificates, capital cost, technical criterions such as the typical life cycle, initial capital cost, etc. Next, the battery capacity can receive specific values Cnom1, Cnom2, …, CnomL, with respect to the battery data sheets [61,62].
  • Initialization of the interest rate and of other parameters: The interest rate without inflation can receive specific values ir1, ir2, …, irM, while other parameters, such as the PV daily energy increment factor σin_Eday, the battery daily energy increment factor σin_Eday_ESS, etc. are predetermined.
  • Determination of the solar radiation modification factor: The solar radiation modification factor fHmday(t, t + dt) is calculated by Equation (39) according to the process of Section 4.4 and it has the same value for the same current day of a month for different years and it is calculated once.
  • Estimation of the economic lifetime of the battery: For each SAPV configuration (specific PVs population Npanel, battery type, and battery capacity Cnom) the respective economic lifetime of the battery is going to be determined as the other elements (PVs, electrical installations, etc.) have a constant lifetime. Next, the following subroutine is executed:
    • The jinitialth day is set as 1, the available days with temperatures are ND_Temp, while the best function of Equations (55), (58), and (59) for the ND–DoD curves of the specific battery is chosen with respect to the criterions of the mean square error J and correlation index r from Equations (60) and (61).
    • The jinitialth day is chosen as the initial current day from the 15 years temperature data, while the necessary initialization is realized, i.e., the initial state of the battery charge (i.e., 80%), etc.
    • For the jth current day for each time step t the available solar irradiation Hm-panel-day(t, t + dt) is estimated by Equations (38) and (39) and the PVs power production PPV(t) is calculated by Equation (50) with respect to Equation (51). Similarly, the respective load demand Pload(t) is estimated taking into consideration the temperature-dependent load variation by Equation (24). Next, for each time step the investigation of the phase kind is carried out:
      If PPV(t) > Pload(t) → charge phase, otherwise discharge phase/no operation phase
In case of the charge phase Equations (25), (28), (30), (32), (33), and (36) are applied with Pdis(t) = PLOE(t) = 0. In case of the discharge phase Equations (26), (38), (31), (32), (34), and (37) are applied with Pch(t) = Padd(t) = 0. The no operation case occurs in the equality condition of Equation (67) and is the same with the discharge phase practically.
   4.
At the end of the jth current day the daily degradation loss rate γa-j′ is calculated by Equations (52), (54), and (62), the remaining capacity of battery Cj′ by Equation (64) and the depth of discharge DoD by Equation (35) taking into consideration the smallest battery energy E(t) during the jth current day.
   5.
At the end of the jth current day the total life duration of the battery is checked by Equation (63) not to be exhausted and the load demand power loss is checked to be zero by Equation (28). If one of the criterions is not satisfied, the economic battery lifetime Tecon_bat(jinitial) is determined as j-jinitial because of ageing/reliable energy inadequacy reasons, respectively, and the subroutine goes to step 6. Otherwise the jth current day is increased by one, and the subroutine returns to step 3. It is noted that if the jth current day becomes bigger than ND_Temp days after the increment, the jth current day becomes 1, while the difference of the lifetime (j-jinitial) is modified to (j-jinitial + ND_Temp).
   6.
The jinitialth day is increased by one and the subroutine returns to step 2, except all available days have been examined as initial ones. If all available days have been examined as initial, the total minimum economic battery lifetime Tecon_bat_min is estimated as:
Tecon_bat_min = min{Tecon_bat(jinitial)}
  • Estimation of the total cost function: For each SAPV configuration (specific PVs population Npanel, battery type, and battery capacity Cnom) the respective equivalent annual total cost TCannual is calculated by Equations (65) and (66) with respect to the different components costs (i.e., capital, withdrawal, maintenance, etc.) and economic lifetime of elements, where the battery lifetime is determined by Equation (68), while the other ones are constant. From all possible configurations the minimum equivalent annual total cost can be determined easily, while a sensitivity analysis can be carried out.
The basic advantage of the proposed methodology is that the optimization process of the SAPV system sizing selects elements (panels and battery elements) from a pool with real technical data at the expense of computational time.

5. Results and Discussion for the Proposed Design Methodology for Stand Alone Photovoltaic Panels with Batteries

5.1. Available Data for the Stand-Alone Photovoltaic with Batteries for the Electrode Station of Stachtoroi Island

Stachtoroi is a small uninhabited island that presents difficulties of accessibility for humans. Small animals and seagulls are its main population. There is a severe lack of meteorological data forcing the authors to use the three hours temperatures for the last 15 years from a near meteorological station in Attica, which were given by H-IPTSO, while the solar radiation are given free of charge as the mean monthly extraterrestrial solar irradiation at the horizontal sea level by [11]. In Table 5 the solar radiation modification factor fHmday(t, t + dt) for the typical day of each month was calculated indicatively. The daily electric energy consumption for electrode station was calculated similarly with the peak load estimation in Section 3.2 taking into consideration Equation (24) and the three hour environmental temperature Ttemp(t).
The PVs for marine applications are constructed by Solbian indicatively using the biggest panel Sxp154Q with a typical cost of 755 €/panel and economic lifetime of 10 years [60]. The inverters are constructed by SMA Solar Technology AG indicatively using different types with respect to the PVs population, i.e., two inverters SMA Sunny Tripower 8000 TL were chosen in case of 100 Sxp154Q with a total cost of 4916 € [66]. In Table 6 the inverters cost for different PVs population was registered, while the respective economic lifetime was 20 years for all cases. Next the total cost of PVs and inverters was accreted by 10% indicatively (usually from 5% to 15%) because of the control system, cables, and switchboards installations. Additionally, if the PVs need more area than the available roof of Figure 6, the roof is expanded and the necessary civil construction works cost 250€/m2 (roof area) with a typical lifetime equal to 25 years.
The battery system can be formed by AGM lead acid elements or by gel form ones. Indicatively in case of AGM elements the AGM VRLA 12 V 100 Ah C20 by Narada [61] was used with a typical cost of 180 €/element, nominal lifetime of 6 years, and self-discharge rate of 5% per month. In case of the gel form series RES SOPzV by Sunlight [62] was used with different capacities of 2 V elements [62]. In Table 7 the 110 V RES SOPzV battery system cost for a different total capacity was registered, while the respective nominal lifetime was 10 years and a self-discharge rate of 2% per month for all cases. It is noted that the economic lifetime was determined by Section 4.4 and Section 4.6.
It is noted that for every battery element the adaptation between the maximum number of cycles ND and the depth of discharge DoD was realized through the process of Section 4.4. Indicatively the experimental data of the respective NDDoD is given in Table 8. If the LSE method is applied with the exponential function of Equation (55), the hyperbolic one of Equation (58), and the power one of Equation (59), the mean square error J and correlation index r will be calculated by Equations (60) and (61) in Table 8, from which it is obvious the inferiority of the exponential one, while the others have similar values with a slight dominance of the hyperbolic function.
The batteries chargers were constructed by GSA Industries indicatively using different types with respect to the battery capacities [67], i.e., the total cost of two chargers for a battery capacity of 2600–3800 Ah was 22 k€, for 1800–2400 Ah was 18 k€, for 1400–1700 Ah was 15 k€, and for smaller than 1300 Ah was 12 k€, respectively. The economic lifetime was 20 years.
The constant maintenance cost per year for photovoltaic panels and batteries amounts to 1200 €, while the operation cost was equal to zero (back-up generators’ operation for service reasons and for forced outages of the SAPV system is ignored because it is very small and practically constant in all cases, if the energy adequacy is satisfied by SAPV system).

5.2. Determination of the Range for the Crucial Parameters of the Proposed Design Methodology

The preliminary idea is that the range of its crucial parameter should be expanded from zero (or almost zero) to a big value, bigger than the preliminary study one by a multiplier factor of 1.5–2.0. In the area of the preliminary study one the proposed values should be thicker. From the sensitivity analysis the values can change repeating the process. Taking into consideration the results of the preliminary study, where the PVs population should be 128 and the 110 V battery capacity should be 3724 Ah, the following ranges of the crucial parameters were proposed:
  • PVs population: The population of PVs Npanel could be 25, 50, 75, 80, 85, 90, 95, 100, 105, 110, 115, 120, 125, 130, 135, 140, 145, 150, 155, 160, 165, 175, and 200, which means 23 values.
  • Capacity for the 108 V AGM VRLA battery system by Narada: The capacity could be 200, 400, 600, 800, 1000, 1200, 1400, 1600, 1800, 2000, 2200, 2400, 2600, 2800, 3000, 3200, 3400, 3600, 3800, 4000, 4200, 4400, 4700, and 6000 Ah, which means 25 values.
  • Capacity for 110 V gel RES SOPzV battery system by Sunlight: The capacity could be 290, 436, 558, 838, 1116, 1396, 1676, 1954, 2232, 2342, 2676, 2931, 3348, 3513, 4014, 4464, 4684, 5352, 5855, and 6690 Ah, which means 20 values.
  • Interest rate without inflation: It could be 0%, 0.5%, …, and 10% with a typical value of 3% and 21 values.

5.3. Estimation of the Economic Lifetime of the Battery

For each combination of PVs and the battery system the economic lifetime was calculated examining different scenarios of an initial day and choosing the most unfavorable one by Equation (68). Here, the historical temperature data of 15 years were given analytically, so 5478 (=12 × 365 + 3 × 366) different initial days were available forming 5478 cases per combination. Indicatively six combinations are shown in Figure 9, where the progress of the remaining capacity is presented with respect to the current days. The remaining capacity curve stopped to be traced and either the total life duration of the battery was exhausted or the load demand power loss was not zero satisfying the reliability criterion of energy adequacy. Simultaneously, the economic lifetime of the battery was determined. It is obvious that the increase of PVs and of the battery capacity improved the battery lifetime, while there was a slight superiority of gel RES SOPzV battery against AGM VRLA one. In Table 9 the respective arithmetic results were registered, where it was found out that the increase of PVs and the decrease of the battery capacity resulted in bigger mean daily produced PV energy loss Εadd-day, while the initial and the last day for the most unfavorable scenario were not the same for the different combinations.
The improvement of the battery economic lifetime was assertive not as a linear phenomenon as it can be seen in Figure 10 with the PVs variation for AGM VRLA battery with capacity of 2400 Ah and in Figure 11 with the capacity variation with 120 PVs. In Figure 10 the lifetime is stabilized at 3.7 years for a PVs population equal to 125, while in Figure 11 it was stabilized at 3.7 years for a capacity equal to 2600 Ah with a very small increase until 3.77 years at a capacity of 6000 Ah.
By studying the 23 × 25 = 575 combinations the respective results can be generalized in three-dimension Figure 12, where the economic lifetime for SAPV system is presented with respect to the capacity of 108 V AGM VRLA battery system (200, 400, …, 4200, 4400, 4700, and 6000 Ah) and PVs population (80, 85, …, and 165). It is obvious that the SAPV system presents energy inadequacy for battery capacities of 1400 Ah and smaller. Afterwards, significant improvement is presented reaching the “saturated” value of 3.75 years, which can be succeeded for a big population of PVs (above 145) with a capacity equal to 1600 Ah, for big capacities (above 4400 Ah) with a PV population equal to 95, and for value pairs (PV population and battery capacity) that were located in the imaginary line between points (145, 1600) and (100, 4000).
The same conclusion for the improvement of the battery economic lifetime could be drawn in case of the gel RES SOPzV battery where 23 × 20 = 460 combinations were carried out. The respective results were generalized in three-dimensions in Figure 13, where the economic lifetime for SAPV system is presented with respect to the capacity of the 110 V RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165). The SAPV system presents energy inadequacy for battery capacities of 1400 Ah and smaller again. Afterwards, significant improvement is presented reaching the “saturated” value of 4.7 years, which it can be succeeded for a big population of PVs (above 145) with a capacity equal to 1600 Ah, for big capacities (above 4464 Ah) with a PV population equal to 90, and for value pairs (PVs population and battery capacity) that were located in the imaginary line between points (145, 1600) and (90, 6000).
The area limitations of a big battery economic lifetime for both battery types were quite similar, but the gel RES SOPzV battery presents more improved behavior than the AGM VRLA significantly, as the respective lifetime was increased by 25%. However, this as not sufficient for battery selection, as the gel RES SOPzV had significantly bigger capital cost and the criterion of an equivalent annual total cost must be applied for all combinations.

5.4. Estimation of the Equivalent Annual Total Cost and Selection of the Optimized Configuration

For each combination of PVs and the battery system the equivalent annual total cost was calculated by Equations (65) and (66) for different values of interest rate without inflation. Indicatively the connection between this cost and the interest rate is presented in Figure 14 for the six combinations of Figure 9 and Table 9. In all cases the equivalent annual total cost was increased with the interest rate increment almost linearly. However, the respective slope was not the same, as it got bigger when the nominal capacity enlarged, while the slope for gel RES SOPzV battery was bigger than AGM VRLA one because of its bigger capital cost for the same nominal capacity. Additionally, the increase of PVs and the decrease of the battery capacity result for the same type battery could decrease the total cost.
The equivalent annual total cost had no-linear behavior as it could be seen in the three-dimensions in Figure 15 with the PV variation for the AGM VRLA battery with a capacity of 2400 Ah and in the three-dimensions in Figure 16 with the capacity variation with 120 PVs. In Figure 15 the minimum cost was succeeded for 120 panels if the interest rate was 0.5% and above, while in Figure 16 it was achieved at a capacity of 2000 Ah in the case of an interest rate of 2% and above and at 2200 Ah in the case of an interest rate of 1.5% and below. Alternatively, all possible 575 combinations for PV population and for a battery capacity of the 108 V AGM VRLA battery system were examined for a specific interest rate. Indicatively in the three-dimensions in Figure 17 the annual equivalent annual total cost is presented with respect to the capacity of the 108 V AGM VRLA battery system (200, 400, …, 4400, 4700, and 6000 Ah) and PV population (80, 85, …, and 165) for an interest rate equal to 3% and the minimum value occurred for a capacity of 1600 Ah and 140 PVs.
In Table 10 the best selection of the SAPV system with AGM VRLA batteries is presented with respect to the equivalent annual total cost, where the battery capacity was equal to 1600 Ah in all cases, while the population of PVs should be 145 for an interest rate of 2.5% and below, 140 between 3% and 5.5%, and 130 between 6% and 10%. This means that the proposed configuration varied, because the population of PVs decreased as the interest rate increased, while the battery capacity was stable in the case of the AGM VRLA battery type. Additionally, the proposed configuration was different from the preliminary study one, as more PVs were required (an increase of 13%), while battery capacity was decreased by 57%.
In the case of the gel RES SOPzV battery the same process for the selection of the best configuration was applied examining 460 combinations for each value of interest rate without inflation. Indicatively in three-dimensions in Figure 18 the equivalent annual total cost is presented with respect to the capacity of the 110 V gel RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165) for an interest rate equal to 3% and the minimum value occurred for a capacity of 2676 Ah and 115 PVs.
In Table 10 the best selection of the SAPV system with gel RES SOPzV batteries was also registered with respect to the equivalent annual total cost. Now the behavior was more complicated, because the battery capacity was equal to 1676 Ah for an interest rate of 1.5% and below and 2676 Ah for an interest rate of 2.0% and above, while the population of PVs should be 140 for an interest rate of 1.5% and below, 115 between 2.0% and 5.5%, and 110 between 6% and 10%. This means that the proposed configuration varied, because the population of PVs decreased as the interest rate increased, while the battery capacity increased as the interest rate increased. Furthermore, the proposed configuration was different from the preliminary study one, as battery capacity decreased until 55%, while the behavior of the PV population was more complicated, as it varied from 86% to 109% during the interest rate decrease.
Comparing the two types of batteries with respect to the equivalent annual total cost in Table 10 it was found out that the best configuration using gel RES SOPzV batteries was superior than the respective one of the AGM VRLA battery for every interest rate, while the proposed configurations by the application of the proposed methodology were not the same for both battery types.
Additionally, the SAPV system with RES SOPzV batteries needs a smaller population of PVs and a bigger battery capacity than the respective configuration for the AGM VRLA battery at the same interest rate.

5.5. Comparison of the Proposed SAPV System with a Battery against the Medium Voltage Submarine Connection with the Aegina Island

The proposed design methodology discovered a superior solution to the preliminary design method for the SAPV system with batteries. However, is this solution better than the classical one, which involves a medium voltage (MV) feeder of 20 kV power supply of the off-site electrode station from the Greek distribution network by the Aegina island according to the guidelines by CIGRE ([45], chapter 7), as presented in Section 2.2. This power supply demands the construction of an MV submarine cable with a length of 8 km approximately, a transformer between 25 and 30 kVA with the respective MV and low voltage (LV) switchboards, as it has been shown in Figure 2 and Figure 5, where the feeder was one, the respective back-up diesel generator was only one, and the battery system could supply the vital loads for 48 h. The submarine cable was the most expensive element, as its installation cost varied between 200 and 350 k€/km with a typical value of 250 k€/km, while other materials, such as concrete matrix blocks and uraducts for submarine cables crossings, transformers, switchboards, building expansion, etc., amounted to 80 k€ approximately, which means that the respective capital investment was about 2080 k€ according to the H-IPTSO data. The maintenance cost was 300 € per year because of the transformer service, while the power and the electricity charges could be ignored as it might not be evaluated by H-EDNO separately as the public benefit service. The respective economic life was 50 years.
Next, the equivalent annual total cost for the submarine cable connection between Aegina-Stachtoroi was carried out by Equations (65) and (66) for a different interest rate without inflation and it was compared with the respective cost of SAPV system with a battery in Figure 19. It was obvious that the proposed autonomous system for both battery types was superior for all rates with significant divergence, which increased no-linearly as the interest rate increased from 0% to 10%. This means that the SAPV system with gel RES SOPzV batteries could be used if the respective interest rate was provided.

6. Conclusions

In this paper, a numerical iterative techno-economic optimization methodology based on a sensitivity analysis is presented for the formation of an autonomous power system with PVs and battery, which is going to supply an isolated shoreline electrode station of the HVDC link. The basic advantages of the proposed methodology are:
  • The optimization process of the SAPV system sizing selects elements (panels, battery modules) from a pool with real technical data at the expense of computational time.
  • The optimized solution is realized through the modification of the PVs type and population and of the battery type and capacity based on a sensitivity analysis.
  • Scarcely available meteorological data is used introducing the solar radiation modification factor fHmday(t, t + dt) for the calculation of the available solar irradiation Hm-panel-day(t, t + dt) for the time interval (t, t + dt), so the PV produced power is estimated during the respective time interval.
  • The daily electric energy consumption for the shoreline electrode station is carried out for each season (winter, summer, and autumn–spring) and different operation modes (stand-alone one and maintenance one) taking into consideration all electrical consumers of the station analytically with high precision.
  • Many significant issues are taken into consideration by the proposed methodology, which are ignored or simplified by the classical ones [10], such as:
    The lifetime, the capital, installation, maintenance, operation, and withdrawal costs for system elements (i.e., inverters, PVs, chargers, etc.),
    The operation of PVs-battery charging cycle,
    The battery ageing based on the relationship between battery cycles and depth of discharge,
    The remaining capacity because of the battery degradation,
    The battery auto-discharge rate,
    The adoption of hyperbolic, exponential, and power functions for the battery cycles–depth of discharge curves for each battery with respect to the criteria of the mean square error and correlation index,
    The determination of the battery economic lifetime based on ageing/reliable energy inadequacy reasons,
    The technical limitations of the system’s elements (i.e., maximum power of chargers/inverters), etc.
  • The SAPV system operation is simulated from an energy point of view for every day during the under study period satisfying the reliability criterion directly, where the SAPV operation will be failed, if the load demand is supplied by the back-up diesel-engine generator sets because of energy deficiency of the PVs-batteries system.
  • The environmental limitation of CO2 emissions reduction is succeeded indirectly, as the generator sets are going to operate only for maintenance and SAPV forced outage reasons, not for energy supply systematically, which means that CO2 emissions are nullified practically.
  • The result comparison proves its superiority against the classical one with respect to the equivalent annual total cost.
Additionally, the configuration of the electrical installation for lighting and auxiliary services of the electrode station was analyzed facing the shortages of the general guidelines of the CIGRE [45] and of the IEC [46] for the power system of the electrode stations of HVDC links. These guidelines imposed the power supply by the MV/LV distribution network and not by the autonomous system. Taking into consideration HVDC interconnections with high reliability levels and isolated/off-grid power supply for electrode stations new electrical installation configurations were proposed including renewable energy sources and energy storage systems and remote control. A dedicated electrode station building design is recommended for:
  • The limitation of the energy consumption,
  • The prevention of the danger for electrochemical corrosion of metallic structures by the direct current flow between electrode stations with no use of structural steel and metallic mechanical settlements,
  • The protection with the highest significance factor against environmental dangers,
  • The reduction of fire risk by the increment of fire-resistance and by supplementation of a fire-fighting system because of ESSs existence and electrode station isolation, etc.
Finally, a design process for the electrode station building was proposed with five steps, as it was presented in Section 2.3.
The aforementioned methodology was applied for the shoreline electrode station, which will be constructed on the small island of Stachtoroi for the new HVDC link of Attica–Crete in Greece. The proposed autonomous system can involve PVs, two batteries, and two back-up diesel generators for reliability reasons. Wind generators could not be used, because Stachtoroi is a protected sanctuary for seagulls. The PVs should be suitable for marine applications because of the short distance from the seaside (5–10 m). The batteries can be AGM VRLA ones or gel VRLA ones, but not classical flooded lead acid ones because of the maintenance issues or lithium-ion ones or hydrogen tanks because of serious difficulties in case of fire, while hydro-pumped storage plant cannot be placed because of a small height difference in island. The respective architecture solution is presented in Figure 6, which includes the main electrode station room, a control/accommodation room, two back-up diesel generator rooms, two battery rooms, a storage room, a water and pump room, a W.C., etc.
Following this, the population of PVs (23 values), the type (Narada AGM VRLA, SunLight gel RES SOPzV), and the capacity of the battery (25 and 20 respectively) were modified and 1035 combinations were examined determining the battery economic lifetime by examining for each combination with 5478 different scenarios of an initial day and by choosing the most unfavorable one. From the sensitivity analysis, it was found out that for each battery type the capacity reached a “saturated” value, which it could be succeeded for a big population of PVs with constant capacity, for big capacities with a constant PV population, while an imaginary border line could be expanded between them. Finally, for each combination of PVs and the battery system the equivalent annual total cost was calculated for 21 different values of an interest rate without inflation (i.e., 0%, 0.5%, …, and 10%). For both battery types the proposed configuration was different than the preliminary study one, while the battery capacity and PV population changed significantly, as the interest rate varied. The best configuration using gel RES SOPzV batteries was superior to the respective one of the AGM VRLA battery for every interest rate. The first one needed a smaller population of PVs and a bigger battery capacity than the second one for the same interest rate (see Table 10). At the end, the shoreline electrode station on the Stachtoroi island was proposed to be supplied by an autonomous power system with 115 PVs type Sxp154Q by Solbian, with two inverters SMA SUNNY TRIPOWER 10,000 TL, and two 110 V SunLight gel RES 6 SOPzV 850 battery systems (one parallel branch-55 elements in series per system) with two respective GSA industries chargers for the typical interest rate 3%. Additionally, if the SAPV system is compared with the classical solution, which involves an MV feeder of 20 kV of power supply with a 25 kVA, 20 kV/400 V three-phase transformer for the off-site electrode station from the Greek distribution network by Aegina Island according to the guidelines by CIGRE ([45], chapter 7), the proposed system for both batteries types is superior for all rates with significant divergence, which increases non-linearly as the interest rate increases.

Author Contributions

Conceptualization, P.M.D., G.J.T. and C.D.T.; methodology, P.M.D., G.J.T. and V.T.K.; software, P.M.D., G.J.T. and F.D.K.; validation, P.M.D., G.J.T. and P.A.K.; formal analysis, P.M.D., G.J.T. and V.T.K.; investigation, P.M.D.; resources, P.M.D., G.J.T. and P.A.K.; data curation, C.D.T.; writing—original draft preparation, P.M.D., G.J.T., V.T.K. and P.A.K.; writing—review and editing, P.M.D., G.J.T. and F.D.K.; visualization, P.M.D., G.J.T. and V.T.K.; supervision, G.J.T. and C.D.K.; project administration, G.J.T.; funding acquisition, C.D.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by H-IPTSO, grant number 191102.

Acknowledgments

The authors would like to thank the H-IPTSO for the meteorological and economic data availability.

Conflicts of Interest

The authors declare no conflict of interest. The funders (H-IPTSO) had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript, or in the decision to publish the results.

Nomenclature

AbbreviationExplanation
ACAlternating Current
AGMAbsorbed Glass Mat (for batteries)
CIGREInternational council on large electric systems
DCDirect Current
DoDDepth of Discharge (for battery)
ESS(s)Energy Storage System(s)
FM2001,1,1,2,3,3,3-Heptafluoropropane, also called heptafluoropropane, HFC-227ea (ISO name), HFC-227, apaflurane (INN), which is a colorless, odorless gaseous halocarbon, commonly used as a gaseous fire suppression agent.
GISGas Insulated Substation
H-EDNOHellenic Electricity Distribution Network Operator
H-IPTSOHellenic Independent Power Transmission Operator
HVACHigh Voltage Alternative Current
HVAcHeating–Ventilation–Air condition
HVDCHigh Voltage Direct Current
ICAOInternational Aviation Organization
IECInternational Electrotechnical Committee
LVLow Voltage
LSELeast Square Errors (method)
MINDMass Impregnated Non-Drain (for cables)
MVMedium Voltage
NFPANational Fire Protection Association (for USA)
SAPVStand-Alone Photovoltaic
SoCState of Charge (for battery)
STCStandard Test Conditions (1,5 AM, PSTC = 1000 W/m2, 25 °C)
PLCProgrammable Logic Controller
PVPhotovoltaic
PVsPhotovoltaic panel(s)
REsRenewable Energy Sources
VRLAValve Regulated Lead Acid (for batteries)
W.C.Water Closet
XLPECross-Linked Polyethylene (for cables)
SymbolExplanation
Acap-jequivalent fixed annual capital payment of jth equipment
Ccap-jinitial capital value of jth equipment with the equivalent withdrawal cost after the economic lifetime
Cinstall-iinstalled power of the ith electric consumer
Cfix-jfixed annual cost of jth equipment for maintenance, personnel wages, etc. with respect to PA
Cjremaining capacity of battery for the jth day of the time period under study
Cnomessential battery capacity of the ESSs
CostInvinverters total cost
CostRESbattery system total cost
DoD(t)battery depth of discharge at time step t
DoYcurrent day of the year for the calculation of daily solar irradiation
DTen-PVtemperature difference between the environment and PV panel
ELOEenergy loss that does not supply the load demand in case of minimum state of battery charge
Eaddenergy loss that is produced by PV in case of maximum state of battery charge
Eadd_daydaily energy loss that is produced by PV in the case of the maximum state of battery charge during the time period Tecon_bat_min
Edaydaily energy
Eienergy demand for the time period under study per ith consumer category
E(t)battery stored energy at the time step t
Hmtotal mean solar irradiation at horizontal level in the Earth surface determination
Hmddiffused solar irradiation at horizontal level in the Earth surface
Hommean monthly extraterrestrial solar irradiation at the horizontal level without the Earth atmosphere
Hm-paneltotal mean solar irradiation for the south-facing PV panel with slope a in the Earth surface
Hm-panel-daydaily available solar irradiation/energy for the selected slope a with the null shadow angle
Hm-panel-day(t, t + dt)available solar irradiation during t and t + dt hours
Hm-panel-Tptotal mean solar irradiation for the time period under optimized operation Tp
InomPVnominal current at nominal power for the PV panel at STC: 1.5 AM, PSTC = 1000 W/m2, 25 °C
Iosolar constant or long-term average extraterrestrial total solar irradiance (=1367 W/m2)
Io-mdaysolar radiation intensity
Jmean square error
Kmlucidity of the mth month
Mmpopulation of days of the mth month
NBnumber of days on battery operation
NDmaximum number of charge–discharge cycles for battery
NDiestimated maximum number of charge–discharge cycles for battery by LSE method
NDi,realexperimental maximum number of charge–discharge cycles for battery
N D ¯ mean value of the estimated maximum number of charge–discharge cycles for the battery by the LSE method
N D , r e a l ¯ mean value of experimental maximum number of charge–discharge cycles for battery
ND-jmaximum number of cycles allowed for the actual remaining capacity of the battery corresponding to its discharge depth remaining between the specific upper and lower limits of the nominal capacity
ND_Tempavailable days with temperatures
Niconsumer population per ith consumer category
Npanelnecessary population of PV panels
Nparparallel branches for the battery system
Nserseries elements for the battery branch system
PApower system total daily peak load
PA-ipeak load per ith consumer category
PA-ipartition peak load per ith consumer category at the power system total peak load
PLOE(t)load demand power loss in case of minimum state of battery charge at time step t
PPV(t)PV panels power production at time step t
PPVminlowest operational limit for power production of PVs power production
Pα_monessential power supply by the PVs
Padd(t)produced PV power loss in the case of the maximum state of battery charge at time step t
Pch-maxmaximum battery charge power
Pch(t)battery charge power at time step t
Pdis-maxmaximum battery discharge power
Pdis(t)battery discharge power at time step t
Pinstall-itotal install power of the ith consumer type
PnomPVnominal power for PV panel at STC: 1.5 AM, PSTC = 1000 W/m2, 25 °C
Pload(t)load demand at time step t
Pload_split_unit(t)load demand from split-units at time step t
Pload_split_unit_summermaximum power load demand by a split-unit at temperature Tsummer2
Pload_split_unit_wintermaximum power load demand by a split-unit at temperature Twinter2
RBcorrection factor of the total direct mean monthly solar irradiation for the south-facing PV panel with slope a with respect to the total mean monthly solar irradiation for the horizontal PV panel
RMcorrection factor of the total mean monthly solar irradiation for the south-facing PV panel with slope a with respect to the total mean monthly solar irradiation for the horizontal PV panel
SoCmaxmaximum state of battery charge
SoCminminimum state of battery charge
SoC(t)battery state of charge at time step t
Ttime period
TCannualequivalent annual total cost
Tecon_bat(jinitial)economic battery lifetime
Tecon_bat_mintotal minimum economic battery lifetime
Tjeconomic lifetime of jth equipment
Tmonthmean monthly temperature
Tptime period under optimized operation
Tref-enenvironment temperature for the PV panel
Tsummer1temperature, for which the split-unit starts its operation during the summer period
Tsummer2temperature, for which the split unit consumes the maximum power during the summer period
Ttemp(t)environmental temperature at time step t
Twinter1temperature, for which the split-unit starts its operation during winter period
Twinter2temperature, for which the split unit consumes its maximum power during the winter period
Tyearannual temperature
Vj′(t)battery voltage for the jth day of the time period under study
VND·DoDconstant product between the maximum number of cycles ND and the depth of discharge DoD
VnomESSoperation nominal voltage for ESS (battery)
VnomPVnominal voltage at the nominal power for the PV panel at STC: 1.5 AM, PSTC = 1000 W/m2, 25 °C
a, a1, a2mathematical parameters
b, b1, b2mathematical parameters
cmathematical parameter
cop-joperation cost of jth equipment, which is analog to the annual operation hours top-j and depends on the maintenance
dmathematical parameter
dttime duration
emathematical parameter
fmathematical parameter
fHmday(t, t + dt)solar radiation modification factor
fd_Temptypical power decrease factor for PVs because of temperature variation
iith consumer category, index for the sum
irinterest rate without inflation
jjth day, index for the sum
jinitialinitial day of the available temperature data for the estimation of the economic lifetime of the battery
kindex for the product
kTempbattery temperature correction factor
Dindirect PV service of the electric consumption factor
mmth month
mimean load factor for the time period under study per ith consumer category
nautonomy population of days
nchcharge efficiency factor
ndexperimental values pairs (DoD, ND)
ndisdischarge efficiency factor
njnumber of battery cycles during a day
nrself-discharge rate
rcorrelation index
riparticipation factor at the power system total peak load per ith consumer category
ttime step
top-jannual operation hours of jth equipment
u(x)classical step function
ainclination angle/slope for the PV panel
βsun angle position (altitude) during the day
γa-jdaily degradation loss rate
γd-jdaily dynamic loss rate
γsdaily static loss rate
δsolar declination δ
ζidemand factor per ith consumer category
ρsolar radiation reflection factor
σTempPV temperature correction factor
σTotLossPVfactor of the total loss of PVs
σTran_el_lossesPV transmission electrical losses correction factor
σTran_el_losses_ESSbattery transmission electrical losses correction factor
σageingPV ageing correction factor
σageing_ESSbattery ageing correction factor
σblocking_diodeblocking diode losses correction factor
σcablesPV cables losses factor
σicoincidence factor per ith consumer category
σin_EdayPV daily energy increment factor
σin_Eday_ESSbattery daily energy increment factor
σno_homogeneityPV lack of homogeneity factor
σpollutionPV pollution correction factor
φlatitude
ωstime sunset
ωshourly sunset angle for the day DoY for the south-facing PV panel with slope a

References

  1. Huang, B.J.; Hou, T.F.; Hsu, P.C.; Lin, T.H.; Chen, Y.T.; Chen, C.W.; Li, K.; Lee, K.Y. Design of direct solar PV driven air conditioner. Renew. Energy 2016, 88, 95–101. [Google Scholar] [CrossRef]
  2. Kazem, H.A.; Khatib, T.; Sopian, K. Sizing of a standalone photovoltaic photovoltaic/battery system at minimum cost for remote housing electrification in Sohar, Oman. Energy Build. 2013, 61, 108–115. [Google Scholar] [CrossRef]
  3. Benavente, F.; Lundlad, A.; Campana, P.E.; Zhang, Y.; Cabrera, S.; Lindbergh, G. Photovoltaic/battery system sizing for rural electrification in Bolivia: Considering the suppressed demand effect. Appl. Energy 2019, 235, 519–528. [Google Scholar] [CrossRef]
  4. Tsai, C.T.; Beza, T.M.; Molla, E.M.; Kuo, C.C. Analysis and sizing of mini-grid hybrid renewable energy systems for islands. IEEE Access 2020, 8, 70013–70029. [Google Scholar] [CrossRef]
  5. Sato, S.; Weidlich, A. Analysis of avoided transmission through decentralized photovoltaic and battery storage systems. IEEE Trans. Sustain. Energy 2020, 11, 1922–1929. [Google Scholar] [CrossRef]
  6. Achiluzzi, E.; Kobikrishna, K.; Sivabalan, A.; Sabillon, C.; Venkatesh, B. Optimal asset planning for prosumers considering energy storage and photovoltaic (PV) units: A stochastic approach. Energies 2020, 13, 1813. [Google Scholar] [CrossRef] [Green Version]
  7. Alnaser, S.W.; Althaher, S.Z.; Long, C.; Zhou, Y.; Wu, J. Residential community with PV and batteries: Reserve provision under grid constraints. Int. J. Electr. Power Energy Syst. 2020, 119, 105856. [Google Scholar] [CrossRef]
  8. Ridha, H.M.; Gomes, C.; Hizam, H.; Ahmadipour, M. Sizing and implementing off-grid stand-alone photovoltaic/battery systems based on multi-objective optimization and techno-economic (MADE) analysis. Energy 2020, 207, 118163. [Google Scholar] [CrossRef]
  9. Rahman, M.M.; Islam, A.K.M.S.; Salehin, S.; Al-Matin, M.A. Development of a model for techno-economic assessment of a stand-alone off-grid solar photovoltaic system in Bangladesh. Int. J. Renew. Energy Res. 2016, 6, 140–149. [Google Scholar]
  10. Dervos, C.T. Photovoltaic Systems—From Theory to Practice, 1st ed.; University Press NTUA: Athens, Greece, 2013; pp. 1–526. (In Greek) [Google Scholar]
  11. Mpizionis, V.D.; Mpizionis, D.V. Alternative Power Sources, 1st ed.; Tziolas Press: Thessaloniki, Greece, 2011; pp. 1–744. (In Greek) [Google Scholar]
  12. Sarhan, A.; Hizam, H.; Mariun, N.; Ya’acob, M.E. An improved numerical optimization algorithm for sizing and configuration of stand-alone photo-voltaic system components in Yemen. Renew. Energy 2019, 134, 1434–1446. [Google Scholar] [CrossRef]
  13. Katsaprakakis, D.E. Energy Systems Synthesis, 1st ed.; Hellenic Academic Books: Athens, Greece, 2015; pp. 1–398. (In Greek) [Google Scholar]
  14. Rossi, F.; Heleno, M.; Basosi, R.; Sinicropi, A. Environmental and economic optima of solar home systems design: A combined LCA and LCC approach. Sci. Total Environ. 2020, 744, 140569. [Google Scholar] [CrossRef] [PubMed]
  15. Cabral, C.V.T.; Filho, D.O.; Diniz, A.S.A.C.; Martins, J.H.; Toledo, O.M.; Neto, L.V.B.M. A stochastic method for stand-alone photovoltaic sizing. Sol. Energy 2010, 84, 1628–1636. [Google Scholar] [CrossRef]
  16. Khatib, T.; Elmenreich, W. An improved method for sizing stand-alone photovoltaic systems using reneralized regression neural network. Int. J. Photoenergy 2014, 2014. [Google Scholar] [CrossRef]
  17. Ridha, H.M.; Gomes, C.; Hizam, H.; Ahmadipour, M.; Muhsen, D.H.; Ethaib, S. Optimum design of a stand-alone solar photovoltaic system based on novel integration of iterative-PESA-II and AHP-VIKOR methods. Processes 2020, 8, 367. [Google Scholar] [CrossRef] [Green Version]
  18. Mandelli, S.; Barbieri, J.; Mereu, R.; Colombo, E. Off-grid systems for rural electrification in developing countries: Definitions, classification and a comprehensive literature review. Renew. Sustain. Energy Rev. 2016, 58, 1621–1646. [Google Scholar] [CrossRef]
  19. Goel, S.; Sharma, R. Performance evaluation of stand-alone, grid connected and hybrid renewable energy systems for rural population: A comparative review. Renew. Sustain. Energy Rev. 2017, 78, 1378–1389. [Google Scholar] [CrossRef]
  20. Luna-Rubio, R.; Trejo-Perea, M.; Vargas-Vazquez, D.; Rios-Moreno, G.J. Optimal sizing of renewable hybrids energy systems: A review of methodologies. Sol. Energy 2012, 86, 1077–1088. [Google Scholar] [CrossRef]
  21. Al-falahi, M.D.A.; Jayasinghe, S.D.G.; Enshaei, H. A review on recent size optimization methodologies for standalone solar and wind hybrid renewable energy system. Energy Convers. Manag. 2017, 143, 252–274. [Google Scholar] [CrossRef]
  22. Fadaee, M.; Radzi, M.A.M. Multi-objective optimization of a stand-alone hybrid renewable energy system by using evolutionary algorithms: A review. Renew. Sustain. Energy Rev. 2012, 16, 3364–3369. [Google Scholar] [CrossRef]
  23. Ridha, H.M.; Gomes, C.; Hizam, H.; Ahmadipour, M.; Heidari, A.A.; Chen, H. Multi-objective optimization and multi-criteria decision-making methods for optimal design of standalone photovoltaic system: A comprehensive review. Renew. Sustain. Energy Rev. 2021, 135, 110202. [Google Scholar] [CrossRef]
  24. Khan, F.A.; Pal, N.; Saeed, S.H. Review of solar photovoltaic and wind hybrid energy systems for sizing strategies optimization and cost analysis methodologies. Renew. Sustain. Energy Rev. 2018, 52, 937–947. [Google Scholar] [CrossRef]
  25. Khatib, T.; Ibrahim, I.A.; Mohamed, A. A review on sizing methodologies of photovoltaic array and storage battery in a standalone photovoltaic system. Energy Convers. Manag. 2016, 120, 430–448. [Google Scholar] [CrossRef]
  26. Singh, G.K. Solar power generation by PV (photovoltaic) technology: A review. Energy 2013, 53, 1–13. [Google Scholar] [CrossRef]
  27. Lian, J.; Zhang, Y.; Ma, C.; Yanga, Y.; Chaima, E. A review on recent sizing methodologies of hybrid renewable energy systems. Energy Convers. Manag. 2019, 199, 112027. [Google Scholar] [CrossRef]
  28. Banik, R.; Das, P. A Review on Architecture, Performance and Reliability of Hybrid Power System. J. Inst. Eng. Series B 2020, 101, 527–539. [Google Scholar] [CrossRef]
  29. Siddaiah, R.; Saini, R.P. A review on planning, configurations, modeling and optimization techniques of hybrid renewable energy systems for off grid applications. Renew. Sustain. Energy Rev. 2016, 58, 376–396. [Google Scholar] [CrossRef]
  30. Mahesh, A.; Sandhu, K.S. Hybrid wind/photovoltaic energy system developments: Critical review and findings. Renew. Sustain. Energy Rev. 2015, 52, 1135–1147. [Google Scholar] [CrossRef]
  31. Bullich-Massagué, E.; Cifuentes-García, F.J.; Glenny-Crende, I.; Cheah-Mañé, M.; Aragüés-Peñalba, M.; Díaz-González, F.; Gomis-Bellmunt, O. A review of energy storage technologies for large scale photovoltaic power plants. Appl. Energy 2020, 274, 115213. [Google Scholar] [CrossRef]
  32. Katsaprakakis, D.A.; Dakanali, I.; Condaxakis, C.; Christakis, D.G. Comparing electricity storage technologies for small insular grids. Appl. Energy 2019, 251, 113332. [Google Scholar] [CrossRef]
  33. Gutierrez-Martin, F.; Calcerrada, A.B.; de Lucas-Consuerga, A.; Dorado, F. Hydrogen storage for off-grid power supply based on solar PV and electrochemical reforming of ethanol-water solutions. Renew. Energy 2020, 147, 639–649. [Google Scholar] [CrossRef]
  34. Leon, D.R.F.; Cavaliero, C.K.N.; da Silva, E.P. Technical and economical design of PV system and hydrogen storage including a sodium hypochlorite plant in a small community: Case of study of Paraguay. Int. J. Hydrog. Energy 2020, 45, 5474–5480. [Google Scholar] [CrossRef]
  35. Hassani, H.; Zaouche, F.; Rekioua, D.; Belaid, S.; Rekioua, T.; Bacha, S. Feasibility of a standalone photovoltaic/battery system with hydrogen production. J. Energy Storage 2020, 31, 101644. [Google Scholar] [CrossRef]
  36. Dawood, F.; Shafiullah, G.M.; Anda, M. Stand-alone microgrid with 100% renewable energy: A case study with hybrid solar PV-battery-hydrogen. Sustainability 2020, 12, 2047. [Google Scholar] [CrossRef] [Green Version]
  37. Ma, T.; Yang, H.; Lu, L.; Peng, J. Pumped storage-based standalone photovoltaic power generation system: Modeling and techno-economic optimization. Appl. Energy 2015, 137, 649–659. [Google Scholar] [CrossRef]
  38. Zhao, P.; Xu, W.; Zhang, S.; Wang, J.; Dai, Y. Technical feasibility assessment of a standalone photovoltaic/wind/adiabatic compressed air energy storage based hybrid energy supply system for rural mobile base station. Energy Convers. Manag. 2020, 206, 112486. [Google Scholar] [CrossRef]
  39. Bhayo, B.A.; Al-Kayiem, H.H.; Gilani, S.I.U.; Ismail, F.B. Power management optimization of hybrid solar photovoltaic-battery integrated with pumped-hydro-storage system for standalone electricity generation. Energy Convers. Manag. 2020, 215, 112942. [Google Scholar] [CrossRef]
  40. Loubna, A.; Riad, T.; Salima, M. Standalone photovoltaic array fed induction motor driven water pumping system. Int. J. Electr. Comput. Eng. 2020, 10, 4534–4542. [Google Scholar] [CrossRef]
  41. Sidney, S.; Thomas, J.; Dhasan, M.L. A standalone PV operated DC milk chiller for Indian climate zones. Sadhana 2020, 45, 110. [Google Scholar] [CrossRef]
  42. Baaqeel, H.; Abdelhady, F.; Alghamdi, A.; El-Halwagi, M.M. Optimal design and scheduling of a solar-assisted domestic desalination systems. Comput. Chem. Eng. 2020, 132, 106605. [Google Scholar] [CrossRef]
  43. Shan, C.; Lv, M.; Sun, K.; Gao, J. Analysis of energy system configuration and energy balance for stratospheric airship based on position energy storage strategy. Aerosp. Sci. Technol. 2020, 101, 105844. [Google Scholar] [CrossRef]
  44. Ariadni Interconnection. Technical Description of Shoreline Electrodes for HVDC Link Attica-Crete, 1st ed.; Ariadni Interconnection: Athens, Greece, 2019; pp. 1–30. [Google Scholar]
  45. CIGRE Working Group B4.61. General Guidelines for HVDC Electrode Design, 1st ed.; CIGRE: Paris, France, 2017; Volume 675, pp. 1–150. [Google Scholar]
  46. International Electrotechnical Commission. IEC/TS 62344—Design of Earth Electrode Stations for High Voltage Direct Current (HVDC) Links—General Guidelines, 1st ed.; IEC: Geneva, Switzerland, 2013; pp. 1–91. [Google Scholar]
  47. Lupangu, C.; Bansal, R.C. A review of technical issues on the development of solar photovoltaic systems. Renew. Sustain. Energy Rev. 2017, 73, 950–965. [Google Scholar] [CrossRef]
  48. Kabouris, J.; Karystianos, M.; Nomikos, B.; Tsourakis, G.; Mantzaris, J.; Sakellaridis, N.; Voumvoulakis, E. Power system static and dynamic security studies for the 1st phase of Crete Island Interconnection. J. Energy 2018, 67, 33–43. [Google Scholar]
  49. Woud, H.K.; Stapersma, D. Design of Propulsion and Electric Power Generation Systems, 1st ed.; IMarEST Publications: London, UK, 2002; pp. 1–494. [Google Scholar]
  50. ABB. Switchgear Manual, 11th ed.; ABB AG: Berlin, Germany, 2008; pp. 1–896. [Google Scholar]
  51. Official Gazette. Building Energy Saving Regulations, 2nd ed.; Ministerial Decree; B.2367/12.7.2017; Official Gazette: Elláda, Greece, 2017.
  52. National Fire Protection Association. NFPA 72, National Fire Alarm Code; NFPA: Quincy, MA, USA, 2007; p. 272. [Google Scholar]
  53. National Fire Protection Association. NFPA 855, Standard for the Installation of Stationary Energy Storage Systems; NFPA: Quincy, MA, USA, 2020. [Google Scholar]
  54. National Fire Protection Association. NFPA 75, Standard for the Protection of Electronic Computer/Data Processing Equipment; NFPA: Quincy, MA, USA, 1999; p. 18. [Google Scholar]
  55. Rajput, S.; Saikia, P.P. Fire Extinguishing Agents: Sort and Comparison. Int. J. Res. Appl. Sci. Eng. Technol. 2018, 6, 557–567. [Google Scholar] [CrossRef]
  56. National Fire Protection Association. NFPA 2001, Standard on Clean Agent Fire Extinguishing Systems; NFPA: Quincy, MA, USA, 2000; p. 106. [Google Scholar]
  57. National Fire Protection Association. NFPA 13, Standard for the Installation of Sprinkler Systems; NFPA: Quincy, MA, USA, 2000; p. 746. [Google Scholar]
  58. The Impulse Firefighting Gun and Its Supply Units. Available online: https://www.ifex3000.com/en/impulse-firefighting-gun/ (accessed on 2 August 2020).
  59. Map of Attica Greece. Available online: https://www.in2greece.com/mappages/stereaellada/attica.htm (accessed on 2 August 2020).
  60. SOLBIAN SXp154L Panel. Available online: https://solbian.gr/index.php?route=product/product&path=20_62&product_id=74 (accessed on 1 May 2020).
  61. Technologies. Available online: http://en.naradapower.com/index.php/technologies?ctype=75 (accessed on 1 May 2020).
  62. Reserve Power Batteries. Available online: https://www.systems-sunlight.com/product/applications/ups/spb-agm-batteries/# (accessed on 1 May 2020).
  63. Yang, Y.; Lian, C.; Ma, C.; Zhang, Y. Research on Energy Storage Optimization for Large-Scale PV Power Stations under Given Long-Distance Delivery Mode. Energies 2019, 13, 27. [Google Scholar] [CrossRef] [Green Version]
  64. Wang, S.; Liu, S.; Yang, F.; Bai, X.; Yue, C. Novel Power Allocation Approach in a Battery Storage Power Station for Aging Minimization. Front. Energy Res. 2020, 7, 166. [Google Scholar] [CrossRef]
  65. Hein, K.; Yan, X.; Wilson, G. Optimal multi-objective scheduling of hybrid ferry with shore to shore power supply considering energy storage degradation. Electronics 2020, 9, 849. [Google Scholar] [CrossRef]
  66. SMA Sunny Tripower 8000 TL. Available online: http://www.europe-solarshop.com/inverters/sma/sma-sunny-tripower-8000tl.html (accessed on 1 May 2020).
  67. GSA 110 VDC Battery Charger. Available online: https://www.indiamart.com/proddetail/110-vdc-battery-charger-10100011155.html (accessed on 1 May 2020).
Figure 1. Geographical map of interconnections between Crete and the continental Greece power systems.
Figure 1. Geographical map of interconnections between Crete and the continental Greece power systems.
Energies 13 05550 g001
Figure 2. Typical single line diagram of the auxiliary power IT (isolated or impedance-earthed neutral) system supplied by the medium voltage distribution system according to International Council on Large Electric Systems (CIGRE; [45], similar to Figure 7.1).
Figure 2. Typical single line diagram of the auxiliary power IT (isolated or impedance-earthed neutral) system supplied by the medium voltage distribution system according to International Council on Large Electric Systems (CIGRE; [45], similar to Figure 7.1).
Energies 13 05550 g002
Figure 3. Proposed typical single line diagram of the auxiliary power IT system supplied by the medium voltage distribution system with high reliability requirements.
Figure 3. Proposed typical single line diagram of the auxiliary power IT system supplied by the medium voltage distribution system with high reliability requirements.
Energies 13 05550 g003
Figure 4. Geographical map of Attica mentioning the electrode station and converter station [59].
Figure 4. Geographical map of Attica mentioning the electrode station and converter station [59].
Energies 13 05550 g004
Figure 5. Layout of the electrode station building in Stachtoroi, Saronic Gulf, Attica in case of connection with the distribution network.
Figure 5. Layout of the electrode station building in Stachtoroi, Saronic Gulf, Attica in case of connection with the distribution network.
Energies 13 05550 g005
Figure 6. Layout of the electrode station building in Stachtoroi, Saronic Gulf, Attica in case of the stand-alone photovoltaic (SAPV) system with back-up diesel generators.
Figure 6. Layout of the electrode station building in Stachtoroi, Saronic Gulf, Attica in case of the stand-alone photovoltaic (SAPV) system with back-up diesel generators.
Energies 13 05550 g006
Figure 7. Typical single line diagram of an autonomous power system (back-up diesel engine electric generator—G, photovoltaic panels—FV, and battery storage system—B) for the electrode station building in Stachtoroi, Attica. (D: disconnector, F: fuse, CB: circuit breaker, Di: blocking diode, Mcb: mini circuit breaker, RCCB: residual current circuit breaker, R: relay switch, Ca: cable, Co: converter, Ch: charger, Fv: photovoltaic panel branch, B: battery, L: line, and Τ = interconnection).
Figure 7. Typical single line diagram of an autonomous power system (back-up diesel engine electric generator—G, photovoltaic panels—FV, and battery storage system—B) for the electrode station building in Stachtoroi, Attica. (D: disconnector, F: fuse, CB: circuit breaker, Di: blocking diode, Mcb: mini circuit breaker, RCCB: residual current circuit breaker, R: relay switch, Ca: cable, Co: converter, Ch: charger, Fv: photovoltaic panel branch, B: battery, L: line, and Τ = interconnection).
Energies 13 05550 g007
Figure 8. Roof expansion and positioning of 128 PVs type Sxp154Q by Solbian, 16 PVs in the East–West axis and 8 PVs in the North–South axis with 3 corridors with a width of 41 cm and nominal power 19,712 W.
Figure 8. Roof expansion and positioning of 128 PVs type Sxp154Q by Solbian, 16 PVs in the East–West axis and 8 PVs in the North–South axis with 3 corridors with a width of 41 cm and nominal power 19,712 W.
Energies 13 05550 g008
Figure 9. Remaining capacity of the battery with respect to the current days on operation for different combinations of PVs (100 or 130), battery type (AGM VRLA or gel RES SOPzV), and capacities (2400 or 3800 Ah).
Figure 9. Remaining capacity of the battery with respect to the current days on operation for different combinations of PVs (100 or 130), battery type (AGM VRLA or gel RES SOPzV), and capacities (2400 or 3800 Ah).
Energies 13 05550 g009
Figure 10. Battery economic lifetime for the SAPV system with respect to the PV population while the capacity of the 108 V AGM VRLA battery system is 2400 Ah.
Figure 10. Battery economic lifetime for the SAPV system with respect to the PV population while the capacity of the 108 V AGM VRLA battery system is 2400 Ah.
Energies 13 05550 g010
Figure 11. Battery economic lifetime for the SAPV system with respect to the capacity of the 108 V AGM VRLA battery system while the PV population is 120.
Figure 11. Battery economic lifetime for the SAPV system with respect to the capacity of the 108 V AGM VRLA battery system while the PV population is 120.
Energies 13 05550 g011
Figure 12. Battery economic lifetime for the SAPV system with respect to the capacity of the 108 V AGM VRLA battery system (200, 400, …, 4200, 4400, 4700, and 6000 Ah) and PV population (80, 85, …, and 165).
Figure 12. Battery economic lifetime for the SAPV system with respect to the capacity of the 108 V AGM VRLA battery system (200, 400, …, 4200, 4400, 4700, and 6000 Ah) and PV population (80, 85, …, and 165).
Energies 13 05550 g012
Figure 13. Battery economic lifetime for the SAPV system with respect to the capacity of the 110 V gel RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165).
Figure 13. Battery economic lifetime for the SAPV system with respect to the capacity of the 110 V gel RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165).
Energies 13 05550 g013
Figure 14. Equivalent annual total cost with respect to the interest rate without inflation combinations of PVs (100 or 130), battery type (AGM VRLA or gel RES SOPzV), and capacities (2400 or 3800 Ah).
Figure 14. Equivalent annual total cost with respect to the interest rate without inflation combinations of PVs (100 or 130), battery type (AGM VRLA or gel RES SOPzV), and capacities (2400 or 3800 Ah).
Energies 13 05550 g014
Figure 15. Equivalent annual total cost with respect to the interest rate without inflation and to the PVs population while the capacity of the 108 V AGM VRLA battery system is 2400 Ah.
Figure 15. Equivalent annual total cost with respect to the interest rate without inflation and to the PVs population while the capacity of the 108 V AGM VRLA battery system is 2400 Ah.
Energies 13 05550 g015
Figure 16. Equivalent annual total cost with respect to the interest rate without inflation and to the capacity of the 108 V AGM VRLA battery system while the PVs population is 120.
Figure 16. Equivalent annual total cost with respect to the interest rate without inflation and to the capacity of the 108 V AGM VRLA battery system while the PVs population is 120.
Energies 13 05550 g016
Figure 17. Equivalent annual total cost with respect to the capacity of the 108 V AGM VRLA battery system (200, 400, …, 4200, 4400, 4700, and 6000 Ah) and PV population (80, 85, …, and 165) for an interest rate without inflation at 3%.
Figure 17. Equivalent annual total cost with respect to the capacity of the 108 V AGM VRLA battery system (200, 400, …, 4200, 4400, 4700, and 6000 Ah) and PV population (80, 85, …, and 165) for an interest rate without inflation at 3%.
Energies 13 05550 g017
Figure 18. Equivalent annual total cost with respect to the capacity of the 110 V gel RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165) for an interest rate without inflation at 3%.
Figure 18. Equivalent annual total cost with respect to the capacity of the 110 V gel RES SOPzV battery system (see Table 7) and PV population (80, 85, …, and 165) for an interest rate without inflation at 3%.
Energies 13 05550 g018
Figure 19. Equivalent annual total cost with respect to the interest rate without inflation for the best combinations of PVs, battery type (AGM VRLA or gel RES SOPzV), and capacities (according to Table 10) against the medium voltage submarine connection with the Aegina Island (classical solution).
Figure 19. Equivalent annual total cost with respect to the interest rate without inflation for the best combinations of PVs, battery type (AGM VRLA or gel RES SOPzV), and capacities (according to Table 10) against the medium voltage submarine connection with the Aegina Island (classical solution).
Energies 13 05550 g019
Table 1. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Table 1. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Normal Mode with PVs and BatteriesMaintenance Mode with Diesel-Electric Units in Operation
Room/A Electric ConsumptionCinstall-iΝi…nstall-iζiσimiPA-iΕiσimiPA-iΕi
(m2)(–)(W)(–)(W)(–)(–)(–)(W)(Wh)(–)(–)(W)(Wh)
Generator 1 or 2/6.00Lighting162321.00.00.00.00.01.00.532384
Ventilation 1131131.01.01.0133121.00.4913153
Ventilation 211022201.00.00.00.00.01.00.512202693
Sockets3500135001.00.00.00.00.00.30.011050252
Dehumidifier22.5122.51.01.00.622.53241.00.522.5270
Tank 1 or 2/3.24Lighting161161.00.00.00.00.01.00.051619.2
Ventilation131131.01.00.413124.81.00.413124.8
Motors9191.00.00.00.00.01.00.069.012.96
Sockets3500135001.00.00.00.00.00.30.0051050126
Dehumidifier22.5122.51.01.00.3322.5178.21.00.3322.5178.2
Storage/3.20Lighting161161.00.00.00.00.01.00.051619.2
Ventilation131131.01.00.413124.81.00.413124.8
Motors1900119001.00.00.00.00.01.00.0051900228
Sockets3500135001.00.00.00.00.00.30.0051050126
Dehumidifier22.5122.51.01.00.3222.5172.81.00.3222.5172.8
Water and fire pump/8.14Lighting164641.00.00.00.00.01.00.056476.8
Ventilation 1131131.01.01.0133121.00.9913309
Ventilation 224522201.00.00.00.00.01.00.01490117.6
Water pump1000220000.51.00.0110002401.00.021000480
Jockey fire pump1000110001.01.00.0011000241.00.001100024
Air-compressor 2000120001.01.00.0012000481.00.001200048
FM200 fire station 110011001.01.00.101002401.00.10100240
Sockets3500135001.00.00.00.00.00.30.0051050126
1 Ventilation without any diesel engine operation. 2 Cooling and air combustion ventilation during diesel engine operation.
Table 2. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Table 2. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Normal Mode with PVs and BatteriesMaintenance Mode with Diesel-Electric Units in Operation
Room/A Electric ConsumptionCinstall-iΝi…nstall-iζiσimiPA-iΕiσimiPA-iΕi
(m2)(–)(W)(–)(W)(–)(–)(–)(W)(Wh)(–)(–)(W)(Wh)
Battery 1 or 2/6.00Lighting162321.00.00.00.00.01.00.532384
Ventilation131131.01.01.0133121.01.013312
Sockets3500135001.00.00.00.00.00.30.0051050126
Dehumidifier22.5122.51.01.00.622.53241.00.622.5324
Split unitSummer1240112401.01.00.22124065471.00.2212406547
Split unitWinter1200112001.01.00.20120057601.00.2012005760
Electrode station/24.5Lighting1681281.00.00.00.00.01.00.3128921.6
Ventilation301301.01.01.0307201.01.030720
PLC System10021001.01.00.520024001.00.51002400
Control system10011001.01.00.810019201.00.51001920
Sockets3500135001.00.00.00.00.00.30.110502520
Dehumidifier22.52451.01.01.04510801.01.0451080
Split unitSummer1240112401.01.00.76124022,6181.00.76124022,618
Split unitWinter1200112001.01.00.58120016,7041.00.58120016,704
Control-accommodation/11.5Lighting164641.00.00.00.00.01.00.364460.8
Ventilation251251.01.01.0256001.01.025600
FM200 fire station 2501501.01.00.10501201.00.1050120
Small cooker3000130001.00.00.00.00.01.00.0430002880
Heater4000140001.00.00.00.00.01.00.0440003840
Sockets3500135001.00.00.00.00.00.30.110502520
Dehumidifier22.5122.51.01.01.022.55401.01.022.5540
Split unitSummer1240112401.00.00.00.00.01.00.95124028,272
Split unitWinter1200112001.00.00.00.00.01.00.60120017,280
Table 3. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Table 3. Daily peak power and energy consumption for the electrode station in Stachtoroi Island, Attica.
Normal Mode with PVs and BatteriesMaintenance Mode with Diesel-Electric Units in Operation
Room/A Electric ConsumptionCinstall-iΝi…nstall-iζiσimiPA-iΕiσimiPA-iΕi
(m2)(–)(W)(–)(W)(–)(–)(–)(W)(Wh)(–)(–)(W)(Wh)
SurroundingAviation obstruction light buoy1010101.01.01.0102401.01.010240
Lighting13101301.00.00.00.00.01.00.51301560
Sockets3500135001.00.00.00.00.00.30.0051050126
SeasonAutumn/springTotal484411,932Total17,29034,490
Summer maximum856447,64422,25098,474
Winter maximum844440,15622,09079,994
Table 4. Calculation of the essential photovoltaic panels (PVs) power supply of the population of PVs and of the battery capacity with respect to mean monthly solar radiation with an angle inclination of 3° and null shadow angle in Stachtoroi Island, Attica.
Table 4. Calculation of the essential photovoltaic panels (PVs) power supply of the population of PVs and of the battery capacity with respect to mean monthly solar radiation with an angle inclination of 3° and null shadow angle in Stachtoroi Island, Attica.
MmEdayHm-panelHm-panel-dayTmonthσTempσTotLossPVΡα_monNpanelCnom
Month(–)(kWh/d)(kWh/(m2∙month))(kWh/(m2∙d))(°C)(–)(–)(W)(–)(A∙h)
January3116.07967.882.19010.030.94290.806818,1771193724
February2815.91175.892.71010.240.94210.806215,3261003685
March3114.438123.283.97711.610.93690.80179044593344
April3012.178160.025.33415.540.92190.78895873392821
May3111.968196.436.33619.660.90630.77554864322772
June3012.470214.367.14524.900.88640.75854669312888
July3114.224218.817.05827.830.87530.74905374353294
August3114.165198.696.40927.800.87540.74915893393281
September3012.174159.835.32824.130.88930.76106094402820
October3111.965110.33.55819.070.90850.77748639572771
November3012.51268.452.28214.490.92590.792314,046922898
December3114.75158.421.88511.390.93770.802419,4831273417
Annual36549511652.374.52718.06Maximum19,4831273724
Table 5. Calculation of solar radiation modification factor fHmday(t, t+dt) for the typical current day of the year for the calculation of daily solar irradiation (DoY) of each month.
Table 5. Calculation of solar radiation modification factor fHmday(t, t+dt) for the typical current day of the year for the calculation of daily solar irradiation (DoY) of each month.
Solar Time
12:00–15:00 or 9:00–12:0015:00–18:00 or 6:00–9:0018:00–21:00 or 3:00–6:0021:00–24:00 or 0:00–3:00
DoYa1/Io-mdaya2/Io-mdayfHmday(t, t+dt)
Month(–)(–)(–)
January15−0.2643480.8749920.4110950.0889050.0000000.000000
February46−0.1257420.6859570.3862880.1137120.0000000.000000
March74−0.0203110.5315170.3598870.1401130.0000000.000000
April1050.0531630.4131040.3338630.1627490.0033880.000000
May1350.0910950.3449430.3154570.1725770.0119660.000000
June1660.1057640.3162090.3066600.1756820.0176570.000000
July1960.1001720.3273740.3101630.1745610.0152760.000000
August2270.0722800.3796360.3252120.1679620.0068260.000000
September2580.0143390.4772630.3487380.1510490.0002130.000000
October288−0.0817870.6230960.3763600.1236400.0000000.000000
November319−0.2197140.8153390.4039690.0960310.0000000.000000
December349−0.3154570.9421980.4184760.0815240.0000000.000000
Table 6. Indicative SMA SUNNY TRIPOWER x000 TL inverters total cost CostInv (€) per PVs population Npanel [66].
Table 6. Indicative SMA SUNNY TRIPOWER x000 TL inverters total cost CostInv (€) per PVs population Npanel [66].
Npanel25507580859095100105110115120125130140150175200
CostInv [€]245824582817491649164916491649165634563456345634563456347374845184519832
Table 7. Indicative 110 V Sunlight RES SOPzV battery system total cost CostRES (€) and configuration (parallel branches Npar and series elements Nser) with respect to the total capacity Cnom (Ah) [62].
Table 7. Indicative 110 V Sunlight RES SOPzV battery system total cost CostRES (€) and configuration (parallel branches Npar and series elements Nser) with respect to the total capacity Cnom (Ah) [62].
Cnom (Ah)TypeNparNserCostRES (€)Cnom (Ah)TypeNparNserCostRES (€)
290Res 2 SOPZV15025593502676Res8 SOPZV136025543,670
436Res 3 SOPZV22525512,3202931Res 7 SOPZV99035552,800
558Res 2 SOPZV18025513,9703348Res8 SOPZV113535558,575
838Res 3 SOPZV42525519,2503513Res 7 SOPZV119035561,050
1116Res 4 SOPZV56525522,5504014Res8 SOPZV136035565,505
1396Res 5 SOPZV71025526,9504464Res8 SOPZV113545578,100
1676Res 6 SOPZV85025530,0304684Res 7 SOPZV119045581,400
1954Res 7 SOPZV99025535,2005352Res8 SOPZV136045587,340
2232Res8 SOPZV113525539,0505855Res 7 SOPZV1190555101,750
Table 8. Experimental values between the maximum number of cycles ND and the depth of discharge DoD for AGM VRLA battery system (see Table 6.7 in [11]), the functions between cycles NDDoD adapted by LSE method and the respective values of the mean square error J and the correlation index r.
Table 8. Experimental values between the maximum number of cycles ND and the depth of discharge DoD for AGM VRLA battery system (see Table 6.7 in [11]), the functions between cycles NDDoD adapted by LSE method and the respective values of the mean square error J and the correlation index r.
ND (–)180008100520037502800220018001500
DoD (%)1020304050607080
Function N D = 17015 exp ( 3.308 D o D ) N D = 1822.9 / D o D 811.9 N D = 12017 D o D 1.189
J (–)4,500,22448,50049,540
r (–)0.949050.999600.99972
Table 9. Battery economic lifetime, initial and last day for the worst scenario, remaining capacity at the end of the battery economic lifetime, the total produced PV energy loss Εadd for the all economic lifetime, and the mean daily produced PV energy loss Εadd-day for indicative different combinations of PVs (100 or 130), battery type (absorbed glass mat (AGM) valve regulated lead acid (VRLA) or gel RES SOPzV), and capacities (2400 or 3800 Ah).
Table 9. Battery economic lifetime, initial and last day for the worst scenario, remaining capacity at the end of the battery economic lifetime, the total produced PV energy loss Εadd for the all economic lifetime, and the mean daily produced PV energy loss Εadd-day for indicative different combinations of PVs (100 or 130), battery type (absorbed glass mat (AGM) valve regulated lead acid (VRLA) or gel RES SOPzV), and capacities (2400 or 3800 Ah).
NpanelBattery TypeCnom (Ah)Battery Lifetime (Years)Initial and Last Day for the Worst ScenarioRemaining Capacity (Ah-% with Respect to Cnom)Εadd (kWh)Εadd-day (kWh)
130VRLA38003.752167–35361396.97—36.76%66,70148.72
100VRLA38003.30986–21931622.00—42.68%39,54932.77
130VRLA24003.691280–2626882.54—36.77%61,71745.78
100VRLA24001.711565–21931625.88—67.74%234,9437.59
128RES SOPzV38004.632167–38571396.45—36.75%81,12848.00
100RES SOPzV24002.261367–21931608.74—67.03%26,38831.95
Table 10. Proposed configuration of the SAPV system with a battery system (PV population Npanel, battery nominal capacity Cnom) with respect to equivalent total equivalent cost TCannual for a different interest rate without inflation ir, for the 108 V Narada AGM VRLA battery and for the 110 V Sunlight gel RES SOPzV battery system.
Table 10. Proposed configuration of the SAPV system with a battery system (PV population Npanel, battery nominal capacity Cnom) with respect to equivalent total equivalent cost TCannual for a different interest rate without inflation ir, for the 108 V Narada AGM VRLA battery and for the 110 V Sunlight gel RES SOPzV battery system.
108 V Narada AGM VRLA Battery System110 V Sunlight Gel Res SOPzV Battery System
ir (–)Npanel (–)Cnom (Ah)TCannual (€)Npanel (–)Cnom (Ah)TCannual (€)
0.00%145160022,089140167621,387
0.50%145160022,619140167621,908
1.00%145160023,157140167622,438
1.50%145160023,705140167622,978
2.00%145160024,263115267623,499
2.50%140160024,821115267624,000
3.00%140160025,378115267624,509
3.50%140160025,943115267625,025
4.00%140160026,517115267625,547
4.50%140160027,099115267626,077
5.00%140160027,689115267626,613
5.50%140160028,287115267627,156
6.00%130160028,890110267627,695
6.50%130160029,463110267628,234
7.00%130160030,042110267628,778
7.50%130160030,629110267629,328
8.00%130160031,222110267629,883
8.50%130160031,821110267630,445
9.00%130160032,426110267631,011
9.50%130160033,038110267631,583
10%130160033,655110267632,161
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Deligianni, P.M.; Tsekouras, G.J.; Tsirekis, C.D.; Kontargyri, V.T.; Kanellos, F.D.; Kontaxis, P.A. Techno-Economic Optimization Analysis of an Autonomous Photovoltaic Power System for a Shoreline Electrode Station of HVDC Link: Case Study of an Electrode Station on the Small Island of Stachtoroi for the Attica–Crete Interconnection. Energies 2020, 13, 5550. https://doi.org/10.3390/en13215550

AMA Style

Deligianni PM, Tsekouras GJ, Tsirekis CD, Kontargyri VT, Kanellos FD, Kontaxis PA. Techno-Economic Optimization Analysis of an Autonomous Photovoltaic Power System for a Shoreline Electrode Station of HVDC Link: Case Study of an Electrode Station on the Small Island of Stachtoroi for the Attica–Crete Interconnection. Energies. 2020; 13(21):5550. https://doi.org/10.3390/en13215550

Chicago/Turabian Style

Deligianni, Panagiota M., George J. Tsekouras, Costas D. Tsirekis, Vassiliki T. Kontargyri, Fotis D. Kanellos, and Panagiotis A. Kontaxis. 2020. "Techno-Economic Optimization Analysis of an Autonomous Photovoltaic Power System for a Shoreline Electrode Station of HVDC Link: Case Study of an Electrode Station on the Small Island of Stachtoroi for the Attica–Crete Interconnection" Energies 13, no. 21: 5550. https://doi.org/10.3390/en13215550

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop