1. Introduction
Initially motivated by fluctuating energy prices, and more recently by environmental concerns, energy efficiency remains a focus of regulations, such as the Europe 2020 goals [
1]. Industrial energy consumption accounts for 40% of the world [
2] and 26% of the European energy consumption [
3], making it one of the key sectors for increasing energy efficiency. Energy consumption in industry is mostly in the form of heat; thus, energy efficiency improvements imposed by these regulations can only be achieved by using heat more efficiently within the system.
Waste heat in industry is often defined as heat discharged to environment from the cooling systems (e.g., cooling towers) as well as the energy conversion technologies (e.g., boilers) in the form of heat losses. However, according to Bendig et al. [
4], this is classified as excess heat and waste heat is only the part which cannot be recovered within the process, by another process or by using an energy conversion system. This convention is used throughout this work.
According to Reference [
5], industrial excess heat accounts for 5–30% of the industrial energy consumption in different countries, averaging 22% in the EU which corresponds to 5–6% of the overall consumption. There are several options for valorisation of excess heat including direct heat recovery within a process, integration of energy conversion technologies (e.g., organic Rankine cycles) and heat recovery through other processes. Bendig et al. [
4] suggested that a hierarchy is required between those options. Direct heat recovery is the most preferable since it typically requires the least investment and yields the largest improvement. Following this, remaining heat can be upgraded by heat pumps (HPs), transferred to another process or converted to another form, for example by using an organic Rankine cycle.
The International Energy Agency (IEA) classifies excess heat potential into theoretical, technical and economic potential [
6]. Theoretical potential corresponds to the thermodynamic potential without considering the technologies for heat recovery. Technical potential takes into account the availability of technologies for heat recovery. For example, although the steel industry has large heat losses at high temperatures, the technical potential is low since technologies to recover heat from solids are not well developed. Finally, economic potential, leading to the heat recovery options the industries would be willing to invest in, accounts for the cost of heat recovery. Thus, when energy efficiency improvement options are considered, it is crucial to assess the technical and economic feasibility.
This paper, motivated by the high excess heat potential in industry and the importance of identifying economically feasible solutions, presents a novel methodology to determine heat and resource recovery within and between industrial processes. Instead of imposing a predefined hierarchy between the heat recovery options, the method introduces location aspects in process integration (PI) to obtain the optimal path for heat recovery under different investment cost limits on piping.
Section 2 covers the methods available in the literature for improving industrial energy efficiency,
Section 3 explains the method by going through the formulation in detail,
Section 4 presents the case study that is used as a proof of concept,
Section 5 discusses the results and
Section 6 draws the conclusions of this work.
2. State of the Art
PI is a domain in energy efficiency research which aims to increase the heat and material recovery between processes and therefore reduce external resource dependency and energy supplied by fossil fuel-based technologies such as natural gas boilers. PI has been a research-intensive field since the oil crisis in the early 1970s. Although industrial energy efficiency was the main motivation for PI, it has also been used in urban energy system design [
7], biomass conversion systems [
8] and large-scale energy planning. The methods used in PI are classified in two main groups—namely graphical and mathematical programming (MP) methods.
Graphical methods in PI are based on pinch analysis (PA), which divide the system into hot (i.e., heat source) and cold streams (i.e., heat sink), aiming to maximise the heat exchange between them to minimise the hot and cold utility requirements. PA was first developed by Linnhoff and Hindmarsh [
9] for a single industrial process. Afterwards, it was extended to total site analysis (TSA) in which the system consists of several production processes [
10]. In PA, direct heat exchange between processes is considered. However, such exchanges may be problematic because of startup and shutdown dynamics or plant layout. Using utility systems for exchanges between the processes can solve those problems, since they have more operational flexibility. Hui and Ahmad [
11] proposed a TSA method using utility systems. They considered the use of steam as an intermediate fluid for the exchange between processes. The capital cost of the heat exchanger network (HEN) was also included in their analysis while being ignored in the previous TSA methods. The design of utility systems is crucial in TSA as they commonly include centralised supply of heat and power to several plants. Pirmohamadi et al. [
12] studied the optimal design of cogeneration systems in total sites. The method was based on site utility grand composite curves and aimed at maximising the exergy efficiency of the overall system. Short-term and seasonal storage play an important role in inter-plant heat recovery in the case of multi-period problems. Liew et al. [
13] extended the TSA methodology into seasonal total site heat storage cascade to model energy flows between sites and storage systems to determine the required storage size. Exchange between multiple plants brings about other challenges, such as process control and safety. Song et al., proposed a strategy to divide large-scale TSA problems into smaller sections to cope with these issues [
14]. TSA was applied in each section to obtain the total inter-plant heat recovery. In inter-plant heat exchange, connections between plants can be in different configurations such as series, parallel or split. In their TSA-based method, Wang et al. [
15] identified the excess heat of the plants and analysed inter-plant recovery using different connection patterns. The parallel pattern yielded higher heat recovery, while coming at a higher investment cost.
When the excess heat from plants is identified manually, it is critical to decide which streams participate in inter-plant transfer. A strategy to select such streams was presented by Song et al. [
16]. They also introduced the concept of inter-plant shifted composite curves to maximise heat recovery using minimum heat capacity flowrate intermediate circuits. Hackl et al. [
17] studied heat recovery in industrial clusters using TSA and intermediate fluids. The energy consumption of the cluster was reduced by introducing a hot water loop between plants. While TSA helps to identify the targets of energy requirements of multiple processes/plants, it brings about challenges in implementation due to the variety of plants/companies involved in the exchange. A method to overcome such challenges was developed by Hackl and Harvey [
18]. In the first step of their method, TSA was used to find the total site targets, while in the second step the number of plants/companies involved in inter-plant heat integration was minimised and the investment required for the integration was split into periods. Industrial excess heat can also be valorised in a district heating network (DHN) as well as other plants. Morandin et al. [
19] considered a case with an industrial cluster and a DHN. They concluded that cluster-wide heat collection yields better integration with the DHNs than connecting each site individually. Although using TSA energy targets for several plants have been identified, most methods ignore the distance between them. Chew et al. [
20] listed layout as one of the main issues in implementing total site heat integration. They also recommended including piping cost for better analysis of inter-plant heat integration [
17] and performing heat recovery through DHNs [
19]. Liew et al. [
21] added layout aspects in TSA by considering heat losses, temperature and pressure drop. First, the heat cascade was constructed using the problem table method of [
9]. Afterwards, the corresponding heat losses, pressure and temperature drop were calculated and the streams in the problem table method were corrected accordingly. Finally, the heat cascade re-formulated with the new temperatures and heat loads.
Even though PA-based methods are effective in obtaining targets for total sites, when the number of plants and utility systems increase, they generally fail to obtain optimal solutions [
15]. MP-based methods emerged to fill this gap and now dominate the field. Most of the early work focused on utility integration [
22] and heat load distribution [
23]. As heat integration measures require modifications in the heat exchangers, HEN synthesis was also included in some of the methods [
24]. Despite the fact that inter-plant heat transfer directly with process streams is considered impractical in most studies, some methods available in the literature still considered it as an option. Zhang et al. [
25] introduced a HEN optimisation method for hot direct discharges/feeds between plants. A larger heat recovery was achieved by using process streams directly instead of intermediate fluids; however, issues regarding the implementation of such exchanges were not addressed. Direct heat exchange between processes requires more piping than using an intermediate fluid and hence a higher piping investment cost. Wang et al., studied the heat integration of direct, indirect and combined methods of multiple plants [
26]. They concluded that direct exchange is most beneficial method for short distances while combined methods are best for medium distances and indirect transfer should be used for long distances. However, the conclusion was case-dependent and could not be generalised.
The main focus in inter-plant heat integration is excess heat recovery between plants. Since different processes have different pinch temperatures, the excess heat of one plant can be useful for another one. Based on this phenomenon, Rodera and Bagajewicz developed a method for optimal integration of intermediate fluids in inter-plant heat transfer [
27]. First, the targets for inter-plant exchange were identified using linear programming (LP) and source and sink plants were determined. Then, the optimal placement of the intermediate fluid circuit was identified using a mixed integer linear programming (MILP) formulation. Afterwards, the method was extended from two plants to n-plants [
28]. When plants with similar pinch points are considered, recovering heat between them using an intermediate fluid might not be feasible. Building on previous work of Reference [
28], Bagajewicz and Barbaro developed a method which uses HPs to upgrade the temperature of the excess heat from one plant and use it elsewhere [
29].
Stijepovic and Linke also worked on optimal heat recovery in industrial zones focusing on excess heat [
30]. They identified the excess heat potential of the plants manually and calculated the maximum heat recovery potential using LP. Finally the optimal heat recovery network was found using a mixed integer non-linear programming formulation. However, intra-plant process integration and improvements through more efficient energy conversion technologies were not included in the method. The layout constraints or location aspects were considered directly or indirectly in several methods. Kantor et al. [
31] formulated the problem as a set of nodes and connections between them. The location aspects were included by adding the cost of resource transportation. Transportation methods were defined for each material sharing potential and an appropriate method for each was established as a result of the optimisation. Becker and Maréchal [
32] proposed a MILP method to divide the system into smaller subsystems based on their locations. The subsystems were allowed to exchange heat only using heat transfer systems represented by intermediate fluids. This way, direct heat exchange over long distances was prevented. Pouransari and Maréchal [
33] extended the previous problem to a heat load distribution (HLD) formulation. Implementation of sub-systems helped solving large-scale HLD problems, which are often computationally expensive. Bade and Bandyopadhyay [
34] worked on a method to minimise the flow of a hot oil circuit between two plants. Although pumping and piping costs were not considered in the objective function, they were indirectly minimised by selecting the lowest possible hot oil flowrate.
HEN synthesis is a difficult problem to solve even for single plants [
35]. When multiple plants and inter-plant heat integration are considered, it becomes even more challenging to obtain convergence. Song et al., combined the strengths of PA and MP in their work. In the first step, they divided the problem into smaller sections using an algorithm based on PA [
36]. Then they carried out HEN synthesis of each section and finally optimised the inter-plant flows taking into account the pumping and piping costs [
37]. Chang et al. [
38] also proposed a method to simultaneously optimise the HEN and heat integration between plants. To simplify the problem, they considered a case with only two plants and using only a hot water loop to realise the heat exchange between them. The method was subsequently extended to more than two plants using different options (e.g., steam, hot oil) as intermediate fluids [
39]. When a HEN is designed for more than one plant, it is important to determine the locations of the heat exchangers. Nair et al. [
40] developed a MINLP method taking into account the locations of the heat exchangers in an eco-industrial park. They assumed that the temperature difference in the heat streams is linearly correlated to the travelled distance. They also considered piping and pumping costs and their trade-off with the operating cost benefits of heat recovery. Kachacha et al. [
41] also considered the impact of plant location in the HEN problem by including piping and pumping costs. However, in order to keep the formulation linear, they made simplifying assumptions by using pre-calculated logarithmic mean temperature difference (LMTD) and pipe diameters. Laukkanen and Seppala [
42] studied using nanofluids in inter-plant HEN synthesis. They developed a method to optimise the HEN, taking into account the trade-off between enhanced heat transfer and increased pumping power requirement due to the addition of nano-particles in the heat transfer fluid. Liu et al. [
43] combined the efforts in mass integration and HEN synthesis in their heat integrated water allocation network model. Although they considered piping requirements for the water streams, they ignored heat losses and pumping requirements for transferring heat between the plants.
The literature of PI is rich in methods focused on inter-plant exchanges; however, graphical methods often neglect aspects related to plant layout. The most elaborate PA-based methods consider only heat integration using intermediate fluids and calculate heat losses and piping after integration. The MP methods address the location-based issues in inter-plant exchanges more extensively. However, most of the methods simplify the problem by considering the exchange only between two plants [
38], identifying the excess heat manually [
30] and optimising its valorisation instead of the overall system. Moreover, the integration of new utility systems was not a part of the optimisation [
41], which might cause energy efficiency improvement opportunities to be missed. Another aspect overlooked in the literature is the type of the intermediate fluid which is used in inter-plant exchange. Methods have been specifically developed for heat sharing by steam [
11], hot water [
38] or hot oil [
34]. Thus, the gaps in the literature are identified as:
not considering the simultaneous integration of energy conversion technologies and inter-plant heat and material exchange infrastructure,
only partially accounting for location aspects and
case-specific methods and lack of generalised applicability.
The work presented in this paper addresses such gaps by formulating the utility integration problem taking into account the location aspects. The method is generic and offers flexibility in integration of new technologies as well as infrastructure for inter-plant heat and material exchange and carries out their optimisation simultaneously.
6. Conclusions
This work proposes a PI method considering location aspects. Consequently, the heat cascade is reformulated to account for heat distribution losses and temperature drops, while the electricity balance is modified to include pumping work required to compensate pressure drops. The cost of the infrastructure between the plants is also considered in the form of piping cost and the resulting problem is formulated using MILP. Parametric optimisation is employed to systematically generate multiple solutions.
The method is first applied on a scenario with two chemical plants, to study the potential heat sharing between them. The results show that the lowest total cost solution is achieved by sharing 1 bar steam between the plants, with a cogeneration engine installed in one plant and a HP is integrated in each. Other solutions are also found, which prove the possibility of eliminating the main heating utility of one plant by multi-level steam sharing.
As a large-scale application of the method, parametric optimisation on eight industrial plants in geographical proximity is also completed. In this case, with small piping investment budgets, the optimal solutions favour sharing heat via high-pressure steam, since higher pressure levels require smaller pipe diameters. With larger budgets, lower pressure steam sharing options emerge, stemming from reduced heat losses. Following the same trend, above-ground pipes are preferred at low piping cost limits, while underground pipes are selected at high limits, due to the trade-off between heat losses and piping investment.
When process industries are not willing to take the risk of investing in inter-plant infrastructure, involvement of a third party can be beneficial. The third-party, making the initial investment and selling steam between plants, could be a non-profit governmental organisation or a utility company with profitability targets. In either case, solutions resulting in overall system profit are obtained, with lower system profit at higher steam price premiums. Industries benefit from such a strategy by avoiding investment risks while benefitting from a 40% reduction in steam prices (on average) with the third party profiting from a steam price premium of up to 20%.
The optimal results obtained using the proposed method lead to a 21% and 35% reduction in the total cost and CO2 emissions, respectively, compared to the baseline operation of the sites, resulting from heat and resource sharing between the sites and integrating new energy conversion systems. The theoretical optimum suggested by the targeting approach results in an even lower total cost and environmental impact; however, contrary to the work presented in this paper, it does not account for technical constraints (e.g., using commercially available technologies) or economic constraints (e.g., including the investment cost of the new technologies or the piping cost).
The present work provides a complete analysis for industrial symbiosis with heat and resource sharing as well as a set of options for investment budgets on inter-plant infrastructure. Heat losses and pumping work requirements are assumed to scale linearly with the flow for inclusion within the MILP framework. Such assumptions simplify the model solution process but may result in missing the global optimum solution. Thus, further analysis should be carried out, studying non-linearity aspects and their impact in the results. Moreover, large industrial retrofit projects, as the one presented in this work, are generally carried out over a long time horizon. Hence, future work should include investment scheduling analysis of the system, which will offer insight into the timeline of the investment in new technologies and piping as well as utility replacement requirements.