Open AccessArticle
Energies 2018, 11(9), 2429; https://doi.org/10.3390/en11092429

Transmission Expansion Planning under Uncertainty for Investment Options with Various Lead-Times

1
Department of Electric and Computer Engineering, Seoul National University, 1 Gwanak-ro, Gwanak-gu, Seoul 06974, Korea
2
Department of Energy System Engineering, Chung-Ang University, 84 Heukseok-ro, Dongjak-gu, Seoul 06974, Korea
*
Author to whom correspondence should be addressed.
Received: 23 July 2018 / Revised: 11 September 2018 / Accepted: 12 September 2018 / Published: 13 September 2018
(This article belongs to the Special Issue Electric Power Systems Research 2018)
Full-Text   |   PDF [2245 KB, uploaded 17 September 2018]   |  

Abstract

Investment options of transmission expansion planning (TEP) involve different lead times according to their length, technology, and environmental and social impacts. TEP planners can utilize the various lead times to deal with the risk of uncertainty. This paper proposes a novel framework for TEP under an uncertain environment, which includes investment options with various lead times. A multi-stage model is developed to reflect the different lead times in the planning method. The level of demand uncertainty is represented using a relative standard deviation. Demand uncertainty in the presented multi-stage model and its influence on the optimal decision are studied. The problem is formulated as a mixed integer linear problem to which stochastic programming is applied, and the proposed framework is illustrated from case studies on a modified Garver’s six-bus system. The case studies verify the effectiveness of the framework for TEP problems with a mathematically tractable model and demonstrates that the proposed method achieves better performance than other methods when the problems involve investment candidates with various lead times under uncertain conditions. View Full-Text
Keywords: transmission expansion planning; lead times; investment options; stochastic programming; multi-stage model transmission expansion planning; lead times; investment options; stochastic programming; multi-stage model
Figures

Figure 1

This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. (CC BY 4.0).
SciFeed

Share & Cite This Article

MDPI and ACS Style

Kim, W.-W.; Park, J.-K.; Yoon, Y.-T.; Kim, M.-K. Transmission Expansion Planning under Uncertainty for Investment Options with Various Lead-Times. Energies 2018, 11, 2429.

Show more citation formats Show less citations formats

Note that from the first issue of 2016, MDPI journals use article numbers instead of page numbers. See further details here.

Related Articles

Article Metrics

Article Access Statistics

1

Comments

[Return to top]
Energies EISSN 1996-1073 Published by MDPI AG, Basel, Switzerland RSS E-Mail Table of Contents Alert
Back to Top