Next Article in Journal
Numerical Study of Fracture Network Evolution during Nitrogen Fracturing Processes in Shale Reservoirs
Previous Article in Journal
Organizational and Systemic Policy Capacity of Government Organizations Involved in Energy-From-Waste (EFW) Development in Thailand
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Regional Protection Partition Strategy Considering Communication Constraints and Its Implementation Techniques

1
College of Electrical Engineering and New Energy, China Three Gorges University, Yichang 443000, China
2
School of Electrical Engineering, Chongqing University, Chongqing 400044, China
*
Author to whom correspondence should be addressed.
Energies 2018, 11(10), 2502; https://doi.org/10.3390/en11102502
Submission received: 13 August 2018 / Revised: 12 September 2018 / Accepted: 18 September 2018 / Published: 20 September 2018

Abstract

:
Regional protection based on multisource information of a regional power network depends on communication technology. A partition strategy considering communication constraints and implementation techniques must be considered to realize the regional protection of a large power grid. This paper aims at examining the technical requirements of rapid and reliable regional protection, considering the number of hops as the factor affecting communication between secondary substations and primary substations, and combining this with the equalization of substations. Then, a primary substation selection model of regional protection based on an exhaustive method is proposed using the Floyd–Warshall algorithm (an algorithm for finding shortest paths in a weighted graph). The partition model is further established according to the multifactors that affect the communication delay time for regional protection. Focusing on the N-1 channel fault in the preset region after the formation of the subregions, this paper analyzes the circuitous process of information in an interrupt channel and considers the influence of communication delay time to further improve the partition strategy. Finally, this paper puts forward techniques for partition strategy implementation based on graph theory; an example analysis of an actual power network is also given, and the conclusions of multiple partitions of the same power network are compared and analyzed. Besides this, partition suggestions and theoretical guidance considering actual engineering demands are given.

1. Introduction

The development of technology in this era has sped up the process of replacing traditional backup protection with regional protection. Traditional backup protection makes trip decisions through local information; this has some disadvantages such as difficulty in setting coordination and poor adaptability [1,2,3]. With the development of communication technology, regional protection which gathers multisource information for decision-making has been widely studied for addressing the shortcomings of traditional backup protection [4,5,6]. In order to achieve regional protection, a large power grid is divided into several regions, regional decision-making centers are set up, and multisource information in the region is collected by means of communication technology. Thereby, online setting of in situ protection is realized, or a new protection criterion is constructed based on multi-information discrimination [7,8,9]. The protection will be completely ineffective if the communication has some problem such as too long a delay, traffic in the channel, packet loss, etc. Therefore, the communication of the system is extremely important for this kind of new protection [10,11]. The rationality of partitioning directly determines the quickness and accuracy of transmitting multisource information to regional decision-making centers. Therefore, a reasonable partition strategy for the large power grid has vital significance for achieving reliable regional protection.
At present, many scholars have put forward regional protection partition ideas and implementation techniques. In reference [12], an initial primary substation was selected to divide a finite element region with a specified radius. Other primary substations were determined outside the finite element region according to the principle of primary substation selection. In reference [13], the primary substation was selected according to the qualitative principle, and a round grid search was carried out with three logical lengths as the radius. In reference [14], a regional autonomous backup protection partition scheme was proposed. The partition scheme was formulated according to the principle of a certain primary substation radius, and the partition algorithm was executed several times. The final result was determined as the scheme with fewest primary substations. In reference [15], the scholar comprehensively considered real-time, economic, and equilibrium factors to establish reference indicators, and used a genetic algorithm to perform a two-layer search to achieve partitioning. In reference [16], the scholar designated a primary substation according to geographical factors, and divided the distance from the primary substation to a region with a topological distance of less than 2. Then, some artificial optimizations were made according to the principle of optimization. Based on the adjacency matrix, the shortest path search method was used to determine the region boundary in reference [17]. Taking the boundary secondary substation as the starting point, the fuzzy comprehensive evaluation method was used to determine the location of the next primary substation. Then, the search process was repeated until the partition of the area was completed. The methods of these studies are mainly based on the electrical topology of the power network, substation geographical location, or protection principle, according to the regional finite element or grid type to divide the area. However, the partition should further consider the influence of communication constraints to make the protection regions more balanced and shorten the delay time.
The object of the partition in this paper is a regional protection communication system which takes long-term planning into account. The following are the contributions of this paper: The basic structure and how the information can be transmitted will be introduced in Section 2. Basic requirements of regional protection which must be considered when we design the strategy will also be stated in this part. The primary substation selection model, secondary substation partition model, and partition correction which formulate the strategy are presented in Section 3. The partition process will be explained in Section 4 by means of an example. Further, a real example in the eastern region of Hubei province, China, which can verify the applicability of the partition strategy to a larger system, will be tested in Section 5. The results of the partitioning and suggestions on how to choose the optimal one will be given, and a comparison of results with those from other similar studies will be done in this part. Finally, conclusions will be drawn in Section 6.

2. Basic Structure and Basic Requirements of Regional Protection

Wide-area protection, hierarchical protection, system protection, and intelligent center protection all aim to improve upon traditional backup protection. These protection strategies have some similarities. One of these similarities is that the primary substation obtains the secondary substation information of the regional power network through communication technology in order to construct protections. This kind of protection is called regional protection.
The structure of regional protection can generally be categorized into distributed structure, centralized structure, and hybrid structure [18]. Several decision-making primary substations need to be set up regardless of the structure of the protection system (each secondary substation of a distributed system can be regarded as a primary substation). Every primary substation acquires the information of multiple secondary substations in its region. Then, it makes the decision of tripping based on the multi-information it receives [12]. A communication system schematic of regional protection and the implementation of regional protection information transmission are shown in Figure 1. In each substation, an Intelligent Electronic Device (IED) collects the electrical quantity information of the system and the status information of its installation. Then, the real-time measurement information or processed information is transmitted to the substation main control unit through the process layer bus and the substation control layer bus in the form of an SV (Sampled Value) or GOOSE (Generic Object Oriented Substation Event) message. Then, the information is uploaded to the decision-making unit of the regional primary substation through a Synchronous Digital Hierarchy (SDH) optical fiber network with the help of Asynchronous Transfer Mode (ATM) communication technology. When the system fails, the primary substation decision-making unit judges the fault elements according to the collected multisource information and formulates a protection strategy. Then, it sends trip signals to the relevant secondary substation in the form of an SV message. The relevant IED then performs the protection function. There are some secondary substations sending related measurements to other regional primary substations at the same time at the junction of regions [19,20].
Some existing regional protection algorithms are based on the premise that information can be transmitted to the decision center quickly and effectively. In another word, the basic requirements of partitioning are that the communication delay is short and that channel utilizations are relatively balanced in each subregion. However, the traditional communication methods cannot meet these requirements in practice. Therefore, the communication system of a large power grid needs to be partitioned by means of a new partition strategy considering the basic requirements before regional protection is used.

3. Protection Partition Strategy

3.1. Primary Substation Selection Model

The main duty of regional protection is to realize fast identification and reliable removal of faulty components based on multisource information. Selecting the path with the shortest communication delay time to transmit the multisource information will be more favorable for the system. The influential factors of communication delay time include information transmission delay time and conversion delay time. There are two important parameters which can aid in choosing the optimal primary substation combination: one is called the minimum hops sum and the other is called the link degree sum. The optimal primary substation combination can be chosen by the Floyd–Warshall algorithm based on a model considering the above two parameters [21,22]. These two parameters will be explained by means of the example shown in Figure 2. The example has 18 substations and 27 channels.
Each communication bandwidth in the regional protection system should preferably be guaranteed to be below 50% so that the channel can stay in good operation [23]. Therefore, the average number of substations in a single region can be estimated preliminarily based on the average traffic of substations. Then, the number of primary substations can be calculated. This is shown in Equation (1):
{ n a v r = B ¯ × 50 % ÷ M ¯ n p r i = n ÷ n a v r
where n a v r is the average number of substations in each area; B ¯ is the average channel bandwidth of the system; M ¯ is the average data size of each station in the system; n is the total number of substations; and n p r i is the number of primary substations.
In practical applications, the number of primary substations can be increased or decreased by 1~2 on the basis of n p r i . The respective partition results corresponding to different numbers of primary substations are obtained. Based on these partition results, the optimal partition can be selected by considering factors that must be considered in engineering practice, such as economy, communication delay, and so on. Therefore, n p r i is 3 for the example in Figure 2.
In mathematics, an x-combination of a set Z is a subset of x distinct elements of Z. If the set has y-many elements, the number of x-combinations is equal to the binomial coefficient
C x y = y ( y 1 ) ( y x + 1 ) x ( x 1 ) 1 .
Therefore, there are C 3 18 possible primary substation combinations P ( 1 ) , P ( 2 ) , …, P ( C 3 18 ) . One of these is chosen to explain the two parameters. For example, P ( j ) including B 4 , B 10 , B 13 is selected. For secondary substation B 1 , the minimum hop counts between B 1 and B 4 , B 1 and B 10 , and B 1 and B 13 are J 1 , J 2 , and J 3 , respectively. The minimum of J 1 , J 2 , and J 3 is called the minimum minimum hop count s B 1 . It can be acquired by using the Floyd–Warshall algorithm based on the connection matrix A . The method of constructing the connection matrix based on graph theory is shown in Equation (3).
A ( g , h ) = { 1 ,                 g   and   h   are   directly   connected inf   ,       g   and   h   are   not   directly   connected 0   ,             g = h
In Equation (3), g and h are the number of substations. For example, A ( 1 , 1 ) , A ( 1 , 2 ) , and A ( 1 , 3 ) are equal to 0, 1, and Inf in this example, respectively. The minimum hops sum S P ( j ) is the sum of the minimum hop counts corresponding to all secondary substations. Another variable l i denotes the number of secondary substations connected with primary substation i . It can also be called the link degree of primary substation i . The sum L P ( j ) of all link degrees corresponding to all primary substations in P ( j ) is the link degree sum. In this example, the l 4 corresponding to B 4 is 6, and L [ B 4 , B 10 , B 13 ] is 17.
The smaller S P ( j ) is, the better the P ( j ) is. On the contrary, the bigger L P ( j ) is, the better the P ( j ) is. Therefore, the reciprocal of L P ( j ) should be chosen to build the minimum objective function Q P ( j ) . S P ( j ) and 1 / L P ( j ) should be normalized before the function is built because their dimensions are different. Therefore, for a region system having n substations whose n p r i is m , the model of the primary substation selection is shown in the following equations:
Q P ( j ) = min j = 1 C m n { ω 1 × S P ( j ) 1 + ω 2 × ( 1 / L P ( j ) ) 1 }
s i = min { J 1 , J 2 J m }
S P ( j ) = i = 1 n m s i
S P ( j ) 1 = S P ( j ) S min S max S min
L P ( j ) = i = 1 m l i
( 1 / L P ( j ) ) 1 = ( 1 / L P ( j ) ) ( 1 / L ) min ( 1 / L ) max ( 1 / L ) min .
In Equation (4), for the jth primary substation combination P ( j ) , S P ( j ) 1 and ( 1 / L j ) 1 are the minimum hops sum and link degree sum after normalizing. The weights ω 1 and ω 2 are determined by the analytic hierarchy process (AHP) [15]. In Equation (5), s i is the minimum minimum hop count, as introduced with the example in Figure 2, of secondary substation i . J 1 , J 2 , …, J m are the minimum hop counts between the secondary substation i and the m primary substations. s i is the minimum of J 1 , J 2 , …, J m . The sum of the s i values is calculated in Equation (6) and S P ( j ) is normalized in Equation (7). S max and S min are the maximum and minimum of S P ( j ) . In Equation (8), for the jth primary substation combination P ( j ) , l i is the link degree of the i th primary substation, and L P ( j ) is the sum of all l i . L j is normalized in Equation (9). ( 1 / L ) max and ( 1 / L ) min are the maximum and minimum of 1 / L j , respectively.
The primary substation combination is the best one when Q j is at a minimum. Then, the primary substations in the combination are chosen.

3.2. Secondary Substation Partition Model

The delay time of data transmission mainly consists of transmission delay time, propagation delay time, queuing delay time, and processing delay time. The transmission delay time is related to the channel bandwidth, the propagation delay time is related to the channel length, the processing delay time is related to the number of hops through the data transmission, and the queuing delay time is related to the channel utilization [18]. The chosen partition affects the communication index of the secondary substation information transmission to the primary substation. In theory, the first strategy to realize protection is to reduce the delay time of information transmission. The second strategy is to ensure relative balance among the substations as well as the conformity of information.
The effects of transmission delay time, propagation delay time, and processing delay time on secondary substation partition are considered in this paper. The bigger the bandwidth is, the shorter the communication delay is. This means that we need choose a channel with large bandwidth. Therefore, we take the channel bandwidth’s reciprocal 1 / b , the weighted sum of the channel length d , and number of hops J into consideration when building a model of secondary substation partitioning. It is necessary to normalize the three reference indices before weighted summation considering that the dimensions of the three reference indices are different. In summary, according to the influence factors of regional protection communication delay time, the secondary substation partition model is established as the following equations:
q k = i = 1 k K i = t ( ω 3 × ( 1 / b i ) 1 + ω 4 × d i 1 ) + ω 5 × J 1
( 1 / b i ) 1 = ( 1 / b i ) ( 1 / b ) min ( 1 / b ) max ( 1 / b ) min
d i 1 = d i d min d max d min
J k 1 = J k J max
M i 75 % × b i .
In the equations above,
  • K is the set of all possible paths between two substations;
  • k is any path in the set;
  • i is any channel of path k ’s t channels;
  • ω3, ω4, and ω5 are the weights of the channel bandwidth, channel length, and the number of hops after normalization. The weight can be determined using the method in reference [23];
  • 1 / b i is the ith channel’s bandwidth reciprocal;
  • (1/bi)1 is the normalized value of the ith channel’s bandwidth reciprocal;
  • (1/b)max and (1/b)min are the maximum and minimum values, respectively, of the channel bandwidth reciprocal for the entire communication network;
  • di is the length of the ith channel;
  • d i 1 is the normalized value of the ith channel’s length;
  • dmax and dmin are the maximum and minimum channel lengths, respectively, for the entire communication network.
The data transmission of the communication system usually has a certain hop limit in order to ensure that the communication delay time is within the scope of the regional protection. The communication network allows the maximum number of hops to be Jmax, usually 5 hops [18]. Jk is the number of hops the path k has passed, and J k 1 is the total hops of the path k after normalization. A constraint for ensuring information integrity is proposed in Equation (14), where Mi is the traffic on the ith channel. It is necessary to check whether the traffic on each channel meets the constraint condition, and if not, return to the primary substation selection step.
For path k between two substations, the number of channels t is equal to the number of hops J k . Therefore, Equation (10) is equal to Equation (15).
q k =     i = 1 k K t ( ω 3 × ( 1 / b i ) 1 + ω 4 × d i 1 + ω 5 × ( 1 / J max ) ) ω 5 × ( 1 / J max × t ) + ω 5 × J 1         =     i = 1 k K t ( ω 3 × ( 1 / b i ) 1 + ω 4 × d i 1 + ω 5 × ( 1 / J max ) )
To find the minimum q k of two substations more easily, a variable Q ( g , h ) should be built as in Equation (16), based on Equation (15) by means of graph theory. The Q ( g , h ) can reflect the communication delay of the channel between g and h , so we define it as the communication distance. The bandwidth matrix B and length matrix D can be built using Equations (17) and (18). Then, the minimum q k can be calculated easily by using the Floyd–Warshall algorithm based on the communication distance matrix Q including all Q ( g , h ) .
Q ( g , h ) = { ω 3 × ( 1 / B ( g , h ) ) 1 + ω 4 × D ( g , h ) 1 + ω 5 × A ( g , h ) / J max , g   and   h   are   directly   connected Inf   , g   and   h   are   not   directly   connected 0   , g = h
B ( g , h ) = { b g h ,               g   and   h   are   directly   connected inf   ,           g   and   h   are   not   directly   connected 0   ,                 g = h
D ( g , h ) = { d g h ,               g   and   h   are   directly   connected inf   ,           g   and   h   are   not   directly   connected 0   ,                 g = h
In the above equations, b g h and d g h are the channel bandwidth and channel length, respectively, between substations g and h . The calculations of ( 1 / B ( g , h ) ) 1 and D ( g , h ) 1 are similar to the methods for ( 1 / b i ) 1 and d i 1 in Equations (11) and (12).
The matrix Q k including all minimum q k between two substations can be created by using the Floyd–Warshall algorithm based on the communication distance matrix Q . Each secondary substation can find its optimal primary substation according to the matrix Q k .

3.3. Partition Correction

3.3.1. Partition Correction under an N-1 Channel Fault

If an N-1 channel fault occurs after the partitioning, it is necessary to modify the partition according to the different channel fault situations.
Principle 1: When there are circuitous paths in the region, the information on the broken channel is circuitous through the circuitous path of the region. The partition need not be changed in this case.
Principle 2: If there is no circuitous path in the area, the information on the broken channel needs to be transmitted to other regions for circuitousness. It is judged whether the delay time meets the request if the information on the broken channel is circuitous with the help of channels in other regions. If satisfied, it is bypassed by other areas and the secondary substation remains unchanged; if not, the information is transmitted to the primary substation with the smallest delay time, and the secondary substation is partitioned into the corresponding new region.
The above principles are explained in conjunction with the system shown in Figure 3. Area 1 includes secondary substations B 1 , B 2 , and B 3 , and the primary substation is B 3 . Area 2 includes secondary substations B 4 , B 5 , B 6 , and B 7 , and the primary substation is B 5 .
According to Principle 1, circuitousness should be made through channel B 7 - B 6 - B 5 when the channel between B 7 and B 5 is interrupted. This is shown in Figure 4a. When the channel between B 4 and B 5 is interrupted, according to Principle 2, it should be determined whether the communication delay time constraint is satisfied by the circuitousness through channel B 4 - B 3 - B 2 - B 6 - B 5 . If satisfied, as shown in Figure 4b, circuitousness is carried out through this circuitous channel. If not, as shown in Figure 4c, secondary substation B4 will transmit the information to the primary substation B 3 of Area 1.

3.3.2. Primary Substation Correction for Single-Point Failure

After completing the selection of the primary substation, the regional protection configuration must consider setting a dual or even triple primary substation decision unit according to the importance of the protection object. When the primary substation has serious faults such as a DC fault, it is necessary to set up other secondary substations in the area as the backup primary substation. The principle of selecting the backup primary substation is based on the connection degree of each secondary substation in the region. The secondary substation with the highest connection degree is selected as the backup primary substation. When the communication between the local secondary substation and the primary substation is interrupted, the backup primary substation will automatically switch to the primary substation to realize the function of regional protection, so as to deal with the single-point failure risk of the system.

4. Partition Process

There are 39 points in the IEEE39 node system. Each point corresponds to a bus bar. However, the multisource information is transmitted between substations. The points of the communication network should correspond to substations; therefore, bus bars in the same substation should be merged into one point. The IEEE39 node system’s communication network after merging is as shown in Figure 5 [24]. The partition strategy is explained using this network in the subsequent processes. The length and bandwidth of each channel of this system are shown in Table A1.
The partitioning steps are as follows:
(1)
The number of primary substation combinations can be determined according to Equation (1). It is 3 in this example. There are C 3 17 kinds of primary substation combinations, P ( 1 ) , P ( 2 ) , …, P ( C 3 17 ) , according to Equation (2). The collection P of them is shown below.
P = { [ 1 , 2 , 3 ] , [ 1 , 2 , 4 ] , , [ 15 , 16 , 17 ] }  
(2)
The connection matrix A can be obtained by using Equation (3) considering the topology of communication system.
A = [ 0 1 Inf Inf 1 0 Inf Inf 0 Inf Inf Inf Inf 0 ]
(3)
The optimal primary substation combination P ( j ) corresponding to the minimum Q P ( j ) can be found from P according to Equations (3)–(8). It is P ( j ) = [ 2 , 8 , 10 ] in this example. The primary substations chosen are B 2 , B 8 , and B 10 .
(4)
The bandwidth matrix B , length matrix D , and connection matrix A can be determined according to Equations (16)–(18). They are shown below.
B = [ 0 100 Inf Inf 100 0 Inf Inf 0 Inf Inf Inf Inf 0 ]
D = [ 0 64.6 Inf Inf 64.6 0 Inf Inf 0 Inf Inf Inf Inf 0 ]
(5)
In this system, ω 3 , ω 4 , and ω 5 can be determined as 0.35, 0.15, and 0.5 by the method in reference [15]. The weight matrix Q can be calculated using Equation (15) based on matrices A , B and D .
Q = [ 0 0.39 Inf Inf 0.39 0 Inf Inf 0 Inf Inf Inf Inf 0 ]
(6)
The optimal path weight q g h between any two substations is found. The matrix Q k including them all can be obtained by the Floyd–Warshall algorithm on the basis of Equations (10)–(18).
Q k = [ 0 0.39 1.86 0.39 0 2.18 1.86 2.18 0 ]
(7)
The secondary substations can be divided into the suitable regions according to the primary substations chosen in Step (3), the Q k calculated in Step (6), and the planned number of secondary substations. The preliminary partition results are shown in Table 1.
(8)
Whether there are unallocated secondary substations should be judged. If so, jump to Step (9); if not, jump to Step (10). In this example, the secondary substations B 14 and B 16 are not partitioned. So, we should jump to Step (9).
(9)
For each secondary substation not assigned to a partition, the weight set between the remaining secondary substations and the primary substations can be obtained according to the Q k in Step (5). The primary substation corresponding to the minimum weight is the optimal primary substation of the secondary substation. Then, all unassigned substations to the optimal primary substations can be assigned similarly. In this example, the weights of the remaining secondary substations between the primary substations are obtained as follows.
Q ( B 14 ) = [ 1.77 0.89 2.21 ]
Q ( B 16 ) = [ 1.33 1.38 0.79 ]
The weight between B 14 and B 8 is the minimum at 0.89, and the weight between B 16 and B 10 is the minimum at 0.79. Therefore, the secondary substation B 14 should be assigned to the corresponding region of the primary substation B 8 , and B 16 should be assigned to the corresponding region of the primary substation B 10 .
(10)
The repeated secondary substations of different regions are configured as boundary secondary substations. Then, the partition results are corrected according to the principle of partition correction under N-1 channel fault. The partition results can then be output using the MATLAB program written in accordance with the theory presented in this paper. The partition results of this example are as Table 2.
In summary, the processes of the regional protection partition strategy considering all communication constraints, such as the lengths and bandwidths of the channels, are shown in Figure A1.

5. Example Analysis

In order to further verify the effectiveness of the partition strategy in this paper, the communication system of the 220 kV power network in East Hubei, China (Figure A2), was partitioned using the partition strategy. The channel length, channel bandwidth, and other parameters of this system are shown in Table A2.
According to Equation (8), it is determined that the preliminary number of primary substations is 8. In order to give theoretical guidance and partitioning advice to the actual engineering demand, the number of regions was set to be 7, 8, and 9. The partition results are shown in Table 3, Table 4 and Table 5.
For the partitioning results in Table 3, Table 4 and Table 5, we need to determine whether the longest delay time in each region meets the rapidity requirement of the regional protection communication, and determine whether there is channel jam in each region. We can thereby determine whether the partition results meet the regional protection partitioning balance requirements. According to reference [25,26], the size of the data uploaded by each substation was set to be 21.7 Mbps . The calculation method for communication delay time is referenced in [24]. The communication indicator results of the partition are shown in Table 6.
Some conclusions can be obtained from the results in Table 6. The delay time will be longer when the number of partitions is fewer, and the more serious problem is that the channel utilization rate exceeds 50%. The channel delay time will increase nonlinearly in this case, as discussed in reference [27]. In addition, the amount of information will sharply increase when the fault occurs; thus, it will be difficult to meet the needs of regional protection. With the increase of the number of regions, the delay time of each region is obviously reduced, and the load amount tends to be more uniform. However, it also means that there are more primary substations which means higher investment costs. Therefore, according to the actual requirements of the project, considering the real-time, equilibrium, and investment economy of the system, the appropriate number of regions can be determined. For example, this system adopts 8 regions in the partition.
The communication indicators of the system partitioned by the traditional strategy from reference [28] can be acquired using the calculation method in reference [24]. The result comparison of partitioning using different strategies is shown in Table 7.
The system partitioned according to the strategy from this article performs better than that partitioned according to the traditional strategy from reference [28] in terms of communication delay and channel utilization. The most important reason for this is that only the number of hops and the topological relation are considered in reference [28]. Therefore, the partition of Region 1 is obviously unbalanced, and the transmission delay times of Region 1 and Region 3 are a little long. In this article, other factors affecting the transmission delay time such as channel distance and bandwidth are considered. A better partition can be provided by using the strategy introduced in this article.

6. Conclusions

Regional protection can solve the problems associated with traditional protection. However, it needs a lot of multisource information, so it is important to choose a suitable partition strategy. The in situ methods of partitioning focus only on the effect of hops. The effects of distance and bandwidth were also dealt with in this article. In this article, a primary substation selection model and a secondary substation partition model were established based on the regional protection communication constraints. Next, methods of corrections for N-1 channel faults and single-point failure were illustrated. Programs based on the strategy were written in MATLAB, meaning that a large number of artificial judgments and assignments of traditional strategy are not required. Finally, a comparative analysis of several partitions was conducted. Suggestions on how to choose the most suitable partition considering economy and the communication delay were given. All data can be quickly dealt with by MATLAB using the strategy from this article, and several good partitions and suggestions can be given.

Author Contributions

Conceptualization, Y.G. and Z.L.; Data curation, Y.G.; Formal analysis, Y.G. and Z.L.; Funding acquisition, Z.L.; Methodology, Y.G. and Z.L.; Resources, Z.L.; Supervision, H.T. and P.W.; Writing—original draft, Y.G.; and Writing—review and editing, Y.G., L.W., H.T. and P.L.K.

Funding

This research was funded by National Natural Science Foundation of China (No. 51607106) and key projects of the science and technology research program of the Hubei Provincial Education Department (No. Z2017037).

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A

Figure A1. The processes of the regional protection partition strategy considering all communication constraints, such as the lengths and bandwidths of channels.
Figure A1. The processes of the regional protection partition strategy considering all communication constraints, such as the lengths and bandwidths of channels.
Energies 11 02502 g0a1
Figure A2. The 220 kV grid communication system in the eastern region of Hubei province, China, to verify the applicability of the partition strategy proposed in this article under larger system conditions.
Figure A2. The 220 kV grid communication system in the eastern region of Hubei province, China, to verify the applicability of the partition strategy proposed in this article under larger system conditions.
Energies 11 02502 g0a2
Table A1. Communication system data of IEEE39.
Table A1. Communication system data of IEEE39.
Channel123456789101112
Length (km)64.612594.830.2127.430.24334.642.617.82725.6
Bandwidth (Mbit)10010010050505010010050100100100
Channel1314151617181920212223
Length (km)69.218.811.82822.425.843.47027.620.219.2
Bandwidth (Mbit)100100100100100100100100505050
Table A2. The communication system parameters of the 220 kV grid in the eastern region of Hubei, China.
Table A2. The communication system parameters of the 220 kV grid in the eastern region of Hubei, China.
ChannelL1L2L3L4L5L6L7L8L9L10L11L12L13
Length (km)1420834.663.43122312550188387
Bandwidth (Mbit)155155155155155155155155155155155155622
ChannelL14L15L16L17L18L19L20L21L22L23L24L25L26
Length (km)116104795217182543403423843
Bandwidth (Mbit)155622155155155155155155155155155155155
ChannelL27L28L29L30L31L32L33L34L35L36L37L38L39
Length (km)40.53423233017.414395532218.49
Bandwidth (Mbit)155155155155155155155155155155155155155
ChannelL40L41L42L43L44L45L46L47L48L49L50L51L52
Length (km)11252927349144194286280
Bandwidth (Mbit)155155155155155155155155155155155155155
ChannelL53L54L55L56L57L58L59L60L61L62
Length (km)75443616.5925182110.562
Bandwidth (Mbit)155155155155155155155155155155

References

  1. Wang, Z.; He, J.; Xu, Y.; Crossley, P. Multi-objective optimisation method of power grid partitioning for wide-area backup protection. IET Gener. Transm. Distrib. 2018, 12, 696–703. [Google Scholar] [CrossRef]
  2. Jena, M.K.; Samantaray, S.R.; Panigrahi, B.K. A New Wide-Area Backup Protection Scheme for Series-Compensated Transmission System. IEEE Syst. J. 2017, 11, 1877–1887. [Google Scholar] [CrossRef]
  3. Lan, T.; Li, Y.; Duan, X. Simplified Analytic Approach of Pole-to-Pole Faults in MMC-HVDC for AC System Backup Protection Setting Calculation. Energies 2018, 11, 264. [Google Scholar] [CrossRef]
  4. Li, Z.; Meng, X.; Wang, X. A wide-area relaying protection system based on multi-point measurement information. IEEJ Trans. Electr. Electron. Eng. 2018, 13, 529–536. [Google Scholar] [CrossRef]
  5. Wang, F.; Yu, M.; Bo, Z. Substation area joint defensive protection strategy based on distributed cooperative all-in-one device. J. Modern Power Syst. Clean Energy 2018, 3, 467–477. [Google Scholar]
  6. Osman, A.; Hassan, M.; Sulaiman, M. Communication-based Adaptive Protection for Distribution Systems Penetrated with Distributed Generators. Power Syst. Protect. Control 2012, 40, 1–9. [Google Scholar] [CrossRef]
  7. Zare, J.; Aminifar, F.; Sanaye-Pasand, M. Communication-Constrained Regionalization of Power Systems for Synchrophasor-Based Wide-Area Backup Protection Scheme. IEEE Trans. Smart Grid 2015, 6, 1530–1538. [Google Scholar] [CrossRef]
  8. Ivankovic, I.; Kuzle, I.; Holjevac, N. Wide Area Information-Based Transmission System Centralized Out-of-Step Protection Scheme. Energies 2017, 10, 633. [Google Scholar] [CrossRef]
  9. Li, Z.; Yin, X.; Zhang, Z. Wide-Area Protection Fault Identification Algorithm Based on Multi-Information Fusion. IEEE Trans. Power Deliv. 2013, 28, 1348–1355. [Google Scholar]
  10. Appasani, B.; Mohanta, D.K. Co-Optimal Placement of PMUs and Their Communication Infrastructure for Minimization of Propagation Delay in the WAMS. IEEE Trans. Ind. Inform. 2018, 14, 2120–2132. [Google Scholar] [CrossRef]
  11. Eissa, M.M. Developing wide area phase plane primary protection scheme “WA4PS” for complex smart grid system. Int. J. Electr. Power Energy Syst. 2018, 99, 203–213. [Google Scholar] [CrossRef]
  12. Yin, X.G.; Wang, Y.; Zhang, Z. Zone-division and tripping strategy for limited wide area protection adapting to smart grid. Proc. Chin. Soc. Electr. Eng. 2010, 30, 1–7. [Google Scholar]
  13. Ma, J.; Wang, X.; Wang, Z. Partition of protection zone with circular overlapping coverage for wide-area protection system. Electr. Power Autom. Equip. 2012, 32, 50–54. [Google Scholar]
  14. Jiang, X.; Wang, Z.; Li, C. Zoning scheme of regional autonomy backup protection. Trans. China Electrotech. Soc. 2013, 28, 234–241. [Google Scholar]
  15. He, Z.; Zhang, Z.; Yin, X. Partition model and optimization algorithm for wide-area backup protection based on centralized decision-making mode. Trans. China Electrotech. Soc. 2014, 29, 212–219. [Google Scholar]
  16. Kong, D.; Lv, F. Wide-area backup protection algorithm based on regional multi-information fusion. Power Syst. Protect. Control 2017, 4, 26–32. [Google Scholar]
  17. He, J.; Wang, Z.; Zhang, D. Wide-area backup protection partitioning based on graph theory and fuzzy evaluation. Electr. Power Autom. Equip. 2017, 37, 75–82. [Google Scholar]
  18. Drayer, E.; Kechagia, N.; Hegemann, J.; Braun, M.; Gabel, M. Distributed Self-Healing for Distribution Grids with Evolving Search Space. IEEE Trans. Power Deliv. 2018, 33, 1755–1764. [Google Scholar] [CrossRef]
  19. Serizawa, Y.; Myoujin, M.; Kitamura, K. Wide-area current differential backup protection employing broadband communications and time transfer systems. IEEE Trans. Power Deliv. 1998, 13, 1046–1052. [Google Scholar] [CrossRef]
  20. Wang, Z.P.; Zhang, Y.G.; Zhang, J.F. Recent Research Progress in Fault Analysis of Complex Electric Power Systems. Adv. Electr. Comput. Eng. 2010, 10, 28–33. [Google Scholar] [CrossRef]
  21. Chen, L.X.; Chen, Z.; Huang, X.L.; Jin, L. A Study on Price-Based Charging Strategy for Electric Vehicles on Expressways. Energies 2016, 9, 385. [Google Scholar] [CrossRef]
  22. Bielecki, W.; Kraska, K.; Klimek, T. Using basis dependence distance vectors in the modified Floyd-Warshall algorithm. J. Comb. Optim. 2015, 30, 253–275. [Google Scholar] [CrossRef]
  23. Cale, J.L.; Johnson, B.B.; Dall’Anese, E.; Young, P.M. Mitigating Communication Delays in Remotely Connected Hardware-in-the-Loop Experiments. IEEE Trans. Ind. Electron. 2018, 12, 9739–9748. [Google Scholar] [CrossRef]
  24. Xiong, X.; Tan, J.; Lin, X. Routing algorithm for communication system in wide-area protection based on MPLS. Trans. China Electrotech. Soc. 2013, 28, 257–263. [Google Scholar]
  25. Dou, X.; Quan, X.; Wu, Z. Hybrid Multi-Agent Control in Microgrids: Framework, Models and Implementations Based on IEC 61850. Energies 2015, 8, 31–58. [Google Scholar] [CrossRef]
  26. Short, M.; Abugchem, F.; Dawood, M. Tunneling Horizontal IEC 61850 Traffic through Audio Video Bridging Streams for Flexible Microgrid Control and Protection. Energies 2016, 9, 204. [Google Scholar] [CrossRef]
  27. Marzal, S.; Gonzalez-Medina, R.; Salas-Puente, R. A Novel Locality Algorithm and Peer-to-Peer Communication Infrastructure for Optimizing Network Performance in Smart Microgrids. Energies 2017, 10, 1275. [Google Scholar]
  28. Li, Z.; Yin, X.; Zhang, Z. Study on system architecture and fault identification of zone-division wide area protection. Proc. Chin. Soc. Electr. Eng. 2011, 31, 95–103. [Google Scholar]
Figure 1. A communication system schematic of regional protection and the implementation of regional protection information transmission.
Figure 1. A communication system schematic of regional protection and the implementation of regional protection information transmission.
Energies 11 02502 g001
Figure 2. An example system with 18 substations and 27 channels, which can be used to explain the minimum hops sum, the link degree sum, and the primary substation selection model.
Figure 2. An example system with 18 substations and 27 channels, which can be used to explain the minimum hops sum, the link degree sum, and the primary substation selection model.
Energies 11 02502 g002
Figure 3. The system with seven substations in two regions, which can be used to explain partition correction under an N-1 channel fault.
Figure 3. The system with seven substations in two regions, which can be used to explain partition correction under an N-1 channel fault.
Energies 11 02502 g003
Figure 4. Corrections under different situations: (a) The circuitous process of information when it is acceptable to circuit within its own region; (b) The circuitous process of information when the help of other regions is necessary to circuit; (c) The partition correction when the delay will be too long if circuiting within its own region or with the help of other regions.
Figure 4. Corrections under different situations: (a) The circuitous process of information when it is acceptable to circuit within its own region; (b) The circuitous process of information when the help of other regions is necessary to circuit; (c) The partition correction when the delay will be too long if circuiting within its own region or with the help of other regions.
Energies 11 02502 g004
Figure 5. The IEEE39 node system’s communication network after merging bus bars in the same substation as one point, which is convenient for introducing the partition strategy proposed in this article.
Figure 5. The IEEE39 node system’s communication network after merging bus bars in the same substation as one point, which is convenient for introducing the partition strategy proposed in this article.
Energies 11 02502 g005
Table 1. Results of partitioning by planning number.
Table 1. Results of partitioning by planning number.
Primary SubstationSecondary Substation
B2B1 B3 B4 B6 B15
B8B5 B6 B9 B12 B17
B10B1 B7 B11 B13 B15
Table 2. Results after the uniform distribution of secondary substations.
Table 2. Results after the uniform distribution of secondary substations.
Primary SubstationSecondary Substation
B2B1 B3 B4 B6 B15
B8B5 B6 B9 B12 B14 B17
B10B1 B7 B11 B13 B15 B16
Table 3. Results of dividing into 7 regions.
Table 3. Results of dividing into 7 regions.
RegionPrimary SubstationSecondary Substation
1FenghuangGuanshan, Yuefu, Luojia, Ye, Xunsi, Dian, Miaoshan, Shatang
2WangzhuangChaan, Lumen, Puqi, Xianning, Tangjiao, Wutian
3QiruCihu, Xialu, Sike, Jiangjia, Tieshan, Xiangjia
4HeShahu, Beiyang, Qingshan, Ya, Wudong, Gang, Huashan
5LangjiaLian, Tieshan, Xialu, Ezhou, Huarong, Zuoling
6QichunCaicheng, Cuijia, Zhangjia, Xisai
7ShibanHangshi, Xisai, Sike, Weiyuan, Cihu, Daji
Table 4. Results of dividing into 8 regions.
Table 4. Results of dividing into 8 regions.
RegionPrimary SubstationSecondary Substation
1FenghuangGuanshan, Yuefu, Luojia, Ye, Xunsi, Dian, Miaoshan, Shatang
2WangzhuangChaan, Lumen, Puqi, Xianning, Tangjiao, Wutian
3QiruCihu, Xialu, Sike, Jiangjia, Tieshan, Xiangjia
4HeShahu, Beiyang, Qingshan, Ya, Wudong
5LangjiaLian, Tieshan, Xialu, Ezhou, Huarong
6QichunCaicheng, Cuijia, Zhangjia, Xisai
7ShibanHuangshi, Xisai, Sike, Weiyuan, Daji
8HuashanWudong, Gang, Ya, Ezhou, Beiyang, Zuoling
Table 5. Results of dividing into 9 regions.
Table 5. Results of dividing into 9 regions.
RegionPrimary SubstationSecondary Substation
1FenghuangYuefu, Luojia, Ye, Dian, Miaoshan, Shatang
2WangzhuangChaan, Lumen, Puqi, Xianning, Tangjiao, Wutian
3QiruCihu, Xialu, Sike, Jiangjia, Xiangjia
4HeShahu, Beiyang, Qingshan, Ya
5LangjiaLian, Tieshan, Xialu, Ezhou, Huarong
6QichunCaicheng, Cuijia, Zhangjia
7ShibanHuangshi, Xisai, Sike, Weiyuan, Daji
8HuashanWudong, Gang, Ya, Ezhou, Zuoling
9GuanshanXunsi, Ya, Qingshan, Gang
Table 6. Result contradistinction of communication indicators.
Table 6. Result contradistinction of communication indicators.
RegionLongest Delay Time with Different Numbers of Partitions (ms)Biggest Channel Utilization with Different Numbers of Partitions
7 Regions8 Regions9 Regions7 Regions8 Regions9 Regions
12.552.552.4328%28%28%
22.492.492.4928%28%28%
33.373.373.3742%42%28%
43.792.652.6370%42%28%
53.732.522.5242%28%28%
63.063.061.9028%28%14%
72.602.302.3028%28%28%
8-2.532.53-42%28%
9--2.40--28%
Table 7. Result contradistinction of partitioning using different strategies.
Table 7. Result contradistinction of partitioning using different strategies.
StrategyLongest Delay Time (ms)Biggest Channel Utilization
Strategy from this article3.79
(7 regions)
3.37
(8 regions)
3.37
(9 regions)
70%
(7 regions)
42%
(8 regions)
28%
(9 regions)
Traditional strategy from reference [28]28.381.7%

Share and Cite

MDPI and ACS Style

Li, Z.; Gong, Y.; Wang, L.; Tan, H.; Kativu, P.L.; Wang, P. A Regional Protection Partition Strategy Considering Communication Constraints and Its Implementation Techniques. Energies 2018, 11, 2502. https://doi.org/10.3390/en11102502

AMA Style

Li Z, Gong Y, Wang L, Tan H, Kativu PL, Wang P. A Regional Protection Partition Strategy Considering Communication Constraints and Its Implementation Techniques. Energies. 2018; 11(10):2502. https://doi.org/10.3390/en11102502

Chicago/Turabian Style

Li, Zhenxing, Yang Gong, Lu Wang, Hong Tan, Prominent Lovet Kativu, and Pengfei Wang. 2018. "A Regional Protection Partition Strategy Considering Communication Constraints and Its Implementation Techniques" Energies 11, no. 10: 2502. https://doi.org/10.3390/en11102502

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop