Energies 2017, 10(2), 225; doi:10.3390/en10020225

One-Year Monitoring PV Power Plant Installed on Rooftop of Mineirão Fifa World Cup/Olympics Football Stadium

1
Graduate Program in Electrical Engineering—Federal University of Minas Gerais (PPGEE/UFMG), Belo Horizonte-MG 31270-901, Brazil
2
Group of Studies and Development of Alternatives Energy—Federal University of Pará (GEDAE/UFPA), Belém-PA 6625-972, Brazil
3
Federal Center of Technological Education of Minas Gerais (CEFET-MG), Belo Horizonte-MG 30421-169, Brazil
4
Companhia Energética de Minas Gerais (CEMIG), Belo Horizonte-MG 30190-131, Brazil
*
Author to whom correspondence should be addressed.
Received: 6 December 2016 / Accepted: 4 February 2017 / Published: 14 February 2017

Abstract

This paper presents results of one-year monitoring of AC side electrical parameters and the characterization of local solar radiation at the biggest rooftop PV Power Plant, with an installed capacity of 1.42 MWp, mounted at Mineirão Football Stadium in Brazil. This stadium is one of the sport facilities that hosted 2014 FIFA World Cup and Rio 2016 Summer Olympics Games in the country. Results showed how it is important to study and characterize the solar resource in the region of interest, based on historic data, to provide the understanding of solar radiation and thus project PV power plants with better performance. Furthermore, AC electrical data show the behavior of active, reactive and apparent powers and the influence of the PV system on the power factor at the local grid utility connection point. Finally, PV power plant performance data (as annual final yield, performance ratio and capacity factor) are also presented and compared with data from PVsyst software simulations. The results over the monitoring period were good considering the specificities of the stadium View Full-Text
Keywords: PV power plants; monitoring; rooftop; sport stadiums; power factor; performance metrics PV power plants; monitoring; rooftop; sport stadiums; power factor; performance metrics
Figures

Figure 1

This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. (CC BY 4.0).

Scifeed alert for new publications

Never miss any articles matching your research from any publisher
  • Get alerts for new papers matching your research
  • Find out the new papers from selected authors
  • Updated daily for 49'000+ journals and 6000+ publishers
  • Define your Scifeed now

SciFeed Share & Cite This Article

MDPI and ACS Style

Monteiro, L.G.; Macedo, W.N.; Torres, P.F.; Silva, M.M.; Amaral, G.; Piterman, A.S.; Lopes, B.M.; Fraga, J.M.; Boaventura, W.C. One-Year Monitoring PV Power Plant Installed on Rooftop of Mineirão Fifa World Cup/Olympics Football Stadium. Energies 2017, 10, 225.

Show more citation formats Show less citations formats

Note that from the first issue of 2016, MDPI journals use article numbers instead of page numbers. See further details here.

Related Articles

Article Metrics

Article Access Statistics

1

Comments

[Return to top]
Energies EISSN 1996-1073 Published by MDPI AG, Basel, Switzerland RSS E-Mail Table of Contents Alert
Back to Top