Next Article in Journal
TSO-DSO Coordination Schemes to Facilitate Distributed Resources Integration
Previous Article in Journal
Perspective Biomethane Potential and Its Utilization in the Transport Sector in the Current Situation of Latvia
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Construction Schedule Risk Assessment and Management Strategy for Foreign General Contractors Working in the Ethiopian Construction Industry

by
Min-Yuan Cheng
and
Mohammadzen Hasan Darsa
*
Department of Civil and Construction Engineering, National Taiwan University of Science and Technology, Taipei 106335, Taiwan
*
Author to whom correspondence should be addressed.
Sustainability 2021, 13(14), 7830; https://doi.org/10.3390/su13147830
Submission received: 17 May 2021 / Revised: 4 July 2021 / Accepted: 7 July 2021 / Published: 13 July 2021

Abstract

:
Construction project schedule delay is a worldwide concern and especially severe in the Ethiopian construction industry. This study developed a Construction Schedule Risk Assessment Model (CSRAM) and a management strategy for foreign general contractors (FGCs). 94 construction projects with schedule delay were collected and a questionnaire survey of 75 domain experts was conducted to systematically select 22 risk factors. In CSRAM, the artificial neural network (ANN) inference model was developed to predict the project schedule delay. Integrating it with the Garson algorithm (GA), the relative weights of risk factors with rankings were calculated and identified. For comparison, the Relative Importance Index (RII) method was also applied to rank the risk factors. Management strategies were developed to improve the three highest-ranked factors identified using the GA (change order, corruption/bribery, and delay in payment), and the RII (poor resource management, corruption/bribery, and delay in material delivery). Moreover, the improvement results were used as inputs for the trained ANN to conduct a sensitivity analysis. The findings of this study indicate that improvements in the factors that considerably affect the construction schedule can significantly reduce construction schedule delays. This study acts as an important reference for FGCs who plan to enter or work in the Ethiopian construction industry.

1. Introduction

Project schedule delay is a common concern in the construction industry, and many researchers have stated the severity of this problem. As Sambasivan and Soon, and Sweis et al. [1,2] stated, project schedule overrun is a global phenomenon that involves extensive delays in construction projects. Complaints and disturbances regarding the construction schedule delays frequently occur in almost all projects [3]. Aziz and Abdel-Hakam [4] also stated that a project schedule delay is a persistent event in construction projects that often converts profitable projects into losing ventures. The construction industry in Ethiopia is booming and is the largest source of employment in the country, with millions of Ethiopians engaged in full- and part-time jobs in the construction industry. However, it is not exempt from the problem of schedule delay.
The contribution of the construction industry to the gross domestic product of Ethiopia has increased considerably, from 9% in 2015/2016 to 18% in 2017/2018. Currently, numerous projects are under construction, and the government has allocated billions of dollars to the sector. Unfortunately, schedule delay beyond the contractual time is a critical problem that the industry and many construction projects are facing. Koshe and Jha [5] stated that only 8% of construction projects in Ethiopia are completed on time, whereas the remaining 92% are delayed by up to 352% of the contractual time. Tadewos and Patel [6] reported that none of the Addis Ababa highway projects were completed on time. Kebede and Zhang [7] also stated that one of the most common inefficiencies in the industry is the construction schedule delay. Zinabu [8] expressed concerns and recommended to take immediate actions for the reduction of construction schedule delays.
To improve the problem of schedule delay, the most important task is to identify the factors causing the delay. Most of the research identified the risk factors based on literature reviews and questionnaire surveys of domain experts [1,2,4,5,8,9,10,11,12,13,14,15,16,17,18,19,20,21,22,23,24]. Due to the subjective judgements of the experts, the identified factors varied from among the different research outcomes. These inconsistent findings have caused project managers some difficulties in determining the right factors to consider for schedule delay reduction. As a result, improvements are often limited and fewer than what was expected, or even insignificant. Thus, a systematic and objective method for identifying the factors has become a key issue for the improvement of schedule delays.
Following this issue, the priority of identified factors for improvement is another task for reducing the delay more efficiently and significantly. The state-of-the-art methods used to rank the factors include the RII, Importance Index, and linear regression [1,4,5,8,9,10,11,12,13,14,15,16,17,18,20,21,22,23,24,25]. In most of the proposed methods, the basic assumption is that all of the factors are linear and independent. However, considering the complexity and uncertainty of the problems, the factors in fact involve interactive relationships that cause the schedule delay. Consequently, the assumption that the factors are linear and independent may not fully stand to represent the ranking results of the analysis. Hence, identifying and including the interactive relationships of the factors in the analysis for priority ranking will be the main concern to efficiently and significantly improve the schedule delay.
Currently, the RII is the most popular method used for identifying and ranking the factors that cause schedule delay [1,4,8,10,14,15,17,20,23]. The RII uses the subjective judgment of experts, which varies among experts who participated in a questionnaire survey to rank the risk factors. There is no validation to verify whether the risk factors identified and ranked by RII are the right sequential factors causing the delay. Moreover, the inconsistent ranking of different research results confuse construction managers as to which factors should be emphasized for schedule delay improvement.
As previously mentioned, schedule delay is a serious problem in Ethiopian construction projects. The researchers Koshe and Jha [5], Zinabu [8], and Gebrehiwet and Luo [23] investigated the causes of schedule delays using the importance index and the RII respectively for Ethiopian construction projects. The analysis results show that the findings on the key causes of schedule delays were inconsistent, which may be due to the disagreement of the participants’ subjective judgments. Additionally, it was difficult for construction managers to determine and focus on the most important risk factors necessary for schedule delay control.
Summarizing the issues discussed above, the main purpose of this research was to develop an integrated approach, the CSRAM, which would reduce to a minimum the subjective judgement made by experts in risk factor identification; concurrently, the interactive relationships of these factors in the analysis process were considered in order to enhance the consistency of factor ranking. The CSRAM includes three phases of analysis: risk factor selection and database development, factor ranking using AI, and comparison and sensitivity analysis for validation.

1.1. Risk Factor Selection and Database Development

Three steps—literature review, questionnaire survey of Ethiopian domain experts, and statistical analysis—were developed to select the risk factors systematically and objectively. Based on the literature review, the initial factors were identified. A questionnaire was used to survey the experts in order to determine the influencing factors specific to Ethiopia. According to the determined factors, the historical data of Ethiopian construction projects were collected to establish the database. Three statistical methods were then applied to analyze the correlation of the factors with the schedule delay based on the database. Using the statistical measure results, the final risk factors were selected.

1.2. Factor Ranking Using AI

The ANN, an AI technique with high problem-solving capability, was applied not only to solve the interactive, dependent, and non-linear relationships between the risk factors, but also to identify the mapping relationships of input and output variables [26,27]. However, the usefulness of ANN is limited by the difficulty in interpreting the “black box” of the computation process [27]. As Ibrahim [28] stated, the RW of an input variable is its contribution that predicts the dependent variable, and ANNs give only minimal information about the influence of input variables on the dependent variable. Thus, Garson [29] developed the GA to interpret the black box of ANN and identify the relative contributions of input variables with a trained ANN [28,30,31,32,33,34]. This study integrated ANN with GA to train the network based on the collected database in the first phase and calculate the RWs of risk factors respectively. According to the obtained RWs, the priority of factors causing schedule delay was then determined. Thus, instead of relying on the subjective judgements of experts, the consistency of factor ranking was enhanced.

1.3. Comparison and Sensitivity Analysis for Validation

In this study, the RII method was also used to rank the factors for comparison and validation. Based on the top three ranked factors identified by the CSRAM and RII, management strategies were developed to address the possible causes and methods of schedule delay reductions. A sensitivity analysis was subsequently conducted to validate the impact of the improved factors on the construction project delay. The top three ranked factors were then improved with the use of a 10% arithmetic increase sequence. Each of the improved results were updated and used as inputs for both methods to calculate the delay reductions in the collected cases. By comparing the average reductions of both methods, the validation of CSRAM was then achieved in terms of objectiveness and consistency.
The parties involved in construction projects are affected by schedule delays, and general contractors may face great losses without essential measures that could reduce these delays. The problems that FGCs face may be more severe than those of local companies with regard to project delays since they lack information about the Ethiopian construction industry. Zhi, H. and Ling, F., et al. [35,36] stated that contracting outside of one’s home country is typically regarded as a high-risk endeavor. With the application of the CSRAM, FGCs may improve on the identified risk factors according to the proposed management strategy and reduce the construction schedule delays significantly. Hence, the findings of this study may serve as an important reference for schedule control for the FGCs who plan to enter or are working in the industry.

2. Literature Review

2.1. GA

According to Xu et al. [26], computing the RWs of input variables is difficult due to a lack of understanding of the black box of ANNs. This section introduces GA to reveal the black box. GA uses the following equation to interpret the black box of ANN:
R W i k = j = 1 p W i j W j k i = 1 N W i j i = 1 N j = 1 p W i j W j k i = 1 N W i j
where RWik denotes the relative weight of input factors x i on the output y k , Wij denotes the connection weight between the ith input variable and the jth hidden neuron, and Wjk denotes the connection weight between the jth hidden neuron and the kth output variables [26].
GA partitions the hidden-output connection weights of each hidden neuron into components associated with each input neuron to determine the RWs of input variables [30]. A trained ANN containing three input neurons, four hidden neurons, and one output neuron is used as example for GA to calculate the RWs of the input variables. The connection weights of the hidden layers in the ANN architecture are presented in Table 1. The computation procedures of GA are as follows:
  • For each hidden neuron i, multiply the absolute value of the hidden-output layer connection weight by the absolute value of the hidden-input layer connection weight for each input variable j, as presented in Table 2;
  • For each hidden neuron, divide p i j by the sum of all the input variables to obtain Q i j . For example, for hidden neuron 1, Q 11 = p 11 / p 11 + p 12 + p 13   =   0.266445 (see Table 3);
  • For each input neuron, add all the products S j formed from the previous computations of Q i j . For example, S 1 = Q 11 + Q 21 + Q 31 + Q 41 = 1.892973 (see Table 3);
  • Divide S j by the sum of all the input variables. The RW of an input variable is obtained as a percentage by multiplying the resulting value after the aforementioned division by 100. For example, the relative importance of input neuron 1 or input factor 1 is ( S 1     100 ) / ( S 1 + S 2 + S 3 ) = 47.3 % (see Table 4).

2.2. Identify the Risk Factors That Cause Schedule Delay

This study reviewed 20 literatures and the factors considered to have caused schedule delays are summarized in Table 5. Due to the differences in the methods of identification and the national conditions, the factors vary from one literature to another; a total of 70 factors were identified and studied to improve the construction schedule delay. The diversity of factors have resulted in the confusion of construction managers regarding which efforts and concerns should be focused on and emphasized in order to improve schedule control. Thus, this study identified the factors shown at a frequency of three times or more in the literature reviews as the initial risk factors. A total of 26 factors, shown in Table 5, were identified at this stage. Two questionnaire surveys and three statistical analyses, illustrated in the following section, were conducted to select the final influencing factors specific to Ethiopia.

3. Research Methodology

3.1. Research Processes

The general procedures used to achieve the objectives of this study are displayed in Figure 1.

3.2. Data Collection and Establishment of the Initial Database

Two questionnaire surveys were used to collect data in this study. The data collection process involved two phases. In the first phase, a pilot questionnaire survey based on the 26 identified risk factors was conducted to determine whether the factors were relevant to this study area; to add risk factors not included in the survey. Fallahnejad [18] consulted 10 experts and Chan et al. [13] consulted 7 experts to determine the risk factors of construction schedule delays. Similarly, 10 Ethiopian domain experts from clients, contractors, and consultants were invited to participate in the pilot questionnaire survey of the study. They have a minimum of 11 years of experience on site with an average of 14.6 years in experience; their academic level and project locations were also considered. The experts suggested 18 additional risk factors and eliminated 3 identified risk factors. Therefore, on the basis of the experts’ feedback, a total of 41 risk factors specific to Ethiopia were determined.
In the second phase of data collection, a questionnaire survey was conducted to determine the impacts and the occurrence frequencies of the input risk factors as well as the output (i.e., project schedule delay). The adopted questionnaire consisted of three parts. The first part comprised questions on the background, including the years of experience and education level, of the participants (see Table 6).
The second part of the questionnaire survey comprised questions on the impact of the 41 determined risk factors. The experts indicated the impact of a particular risk factor by using a 5-point Likert scale with the following responses: very high, high, moderate, low, and very low. A total of 100 copies of the questionnaire survey were distributed online and offline, and 75 valid responses were obtained (response rate = 75%). The third part of the questionnaire survey comprised questions on the occurrences of the input risk factors as well as the output (project schedule delay). Researchers use subjective judgments to determine the occurrence of risk factors [5,11,13,18,19,24]. However, with subjective judgments, distinguishing risk factors that occur frequently (frequency-based factors) from risk factors that may occur only once in a project (binary-based factors) is difficult. For instance, “change orders” may occur several times in a single project and can thus be considered a frequency-based risk factor. However, “inappropriate type of project bidding and award” may occur only once during the bidding process and cannot occur in other stages. The risk factors of this type are called binary-based risk factors. Mohammed and Suliman [25] regarded all risk factors as binary-based and did not distinguish the risk factors that occur frequently in a project from those that occur only once. The risk factors determined in this study were categorized according to the frequency of their occurrence and labeled as frequency-based (26 factors) and binary-based (15 factors). Data on the occurrences of risk factors of 94 completed construction projects were collected from the field and relevant government offices. The schedule delay data of these 94 projects, including their planned and actual completion times, were also collected. The contractual time of the aforementioned construction projects ranged from 1 to 4 years, and the percentage of schedule delay ranged from 10% to 200%.

Data Preparation to Establish the Initial Database

To establish the database, the impacts and occurrence frequencies of input risk factors collected from the questionaire were used to calculate the input values of risk factors. The average risk factor impact assigned by the experts was calculated using Equation (2). Based on Equation (3), the product of the average impact and the occurrence of risk factors was obtained and used as input for the database. For example, if “change order” occurs five times in a project, its input value in the database is five times the average impact value. The input value of a binary-based risk factor was calculated as the average impact of the risk factor times 1, if the risk factor occurred in a project, and 0, if otherwise. The percentage of delay was the output value in the database and computed using Equation (4). For instance, if the project contractual time is 2 years and the time used to complete the project is 3 years, the output value (i.e., percentage of schedule delay) is computed as follows: (3/2–1) × 100% = 50%. For all 41 risk factors and 94 construction project cases, the same procedure was used to calculate the input and output values of the database. The developed database contains 41 input factors, 1 output, and 94 construction project cases. This database was established to be able to select the risk factors that have strong relationships with the project schedule delay.
The average risk factor impact is calculated as follows:
X ¯ m = 1 n r = 1 n X m r
where X ¯ is the average impact value, m represents the input factors, X represents the impact assigned to each factor by experts (ranging from 1 to 5), n is the total number of experts (75 in this study), and r is the number assigned to each of the experts (from 1 to 75).
The product of the average impact and the occurrence of risk factors is calculated using the following equation:
I m = o m j     X ¯ m
where I is the input value, o is the occurrence of risk factors, j is the number of projects (1 to 94), and m represents the input factors.
The percentage of delay is calculated as follows:
y j   =   A T j P T j 1     100
where AT is the actual time used to complete construction, PT is the planned time for construction, and y is the percentage of schedule delay.

3.3. Selection of Risk Factors with a Strong Influence on Schedule Delays in Ethiopian Construction Projects

Different risk factors have different influences on construction schedule delays. Doloi et al. [14] stated that the identification of critical factors that influence construction schedule delays is a crucial step in the accomplishment of a study. In this work, some of the 41 determined risk factors may have a strong influence on the percentage of the schedule delay (i.e., the output variable). Selecting these factors is essential for the success of this research. To select the risk factors that have a strong relationship with the output variable [37], three statistical methods—univariate selection, feature importance selection, and a correlation matrix with a heat map—were used [38]. Based on the statistical analysis results, shown in Table 7, the factor passing two out of the three statistical measures was selected as the final risk factor for this study. A total of 22 risk factors that have strong correlation relationship with the output of construction schedule delay were selected.

3.4. Establishment of the Final Database as well as ANN Training, Validation, and Testing

The final database contains 22 key contributing input factors, 1 output, and 94 historical cases were established. The information in this database was normalized [31,39] using Equation (5) to increase the prediction accuracy of ANN model training [31]. The data were then randomly split into training set and testing set. Subsequently, the ANN was used for training and testing the data sets. The training, validation, and testing processes were displayed in Figure 2. The figure illustrates a 10-fold cross-validation approach [26,39] that was used during the training and validation processes. Firstly, 90% of data (85 pieces) in the database were divided into 10 folds such that 90% of the data were used for training and the remaining 10% were used for validation. For each fold, the accuracy was measured using the coefficient of correlation, the root mean square error [37], the mean absolute percentage error, and the mean absolute error to assess the network quality for training and validation. Secondly, the remaining 10% of the data (9 pieces) were used for model testing. The parameters were also used to determine the testing performance.
X i n o r = X i X m i n X m a x X m i n
where X i n o r is the normalized value of a factor; X i is the actual value of a factor; and X m a x and X m i n are the maximum and minimum values of a factor, respectively.

3.5. Computing the RWs of Risk Factors Using GA

After training was completed, GA was used to determine the RWs of the risk factors by partitioning the connection weights of the trained ANN to rank the risk factors according to the following procedure:
  • Determine p i j of the selected risk factors by multiplying the absolute values of the hidden-output layer connection weights by hidden-input layer connection weights.
  • Then the Q i j of the 22 selected risk factors were computed by dividing p i j by the sum of all the input factors; for input factor 1, Q 11 is calculated as follows:
    Q 11 = p 11 / p 11 + p 12 + p 13 + p 14 + p 15 + p 16 + p 17 + p 18 + p 19 + p 110 + p 111 + p 112 + p 113 + p 114 + p 115 + p 116 + p 117 + p 118 + p 119 + p 120 + p 121 + p 122
  • The S 1 of the risk factor is computed with the following formula, which is calculated from the previous computations of Q i j .
    S 1 = Q 11 + Q 21 + Q 31 + Q 41 + Q 51 + Q 61 + Q 71 + Q 81 + Q 91 + Q 101 + Q 111
  • Finally, the input neuron 1 (F1), which is expressed as a percentage, is computed as follows:
    F 1 = ( S 1     100 ) / S 1 + S 2 + S 3 + S 4 + S 5 + S 6 + S 7 + S 8 + S 9 + S 10 + S 11 + S 12 + S 13 + S 14 + S 15 + S 16 + S 17 + S 18 + S 19 + S 20 + S 21 + S 22

3.6. Determining the RII of Risk Factors

The RII is a popular technique that is applied by researchers to prioritize factors that cause construction schedule delays [1,4,10,14,15,17,20,23]. The following equation (Equation (9)) is used to determine the RII of the selected risk factors, and the factors with a higher RII have a greater influence on the project schedule.
R I I = W A     N
In Equation (9), W is the weight assigned to each factor by the respondents (ranging from 1 to 5), A is the highest weight (5 in this study), and N is the total number of respondents (75 in this study).

3.7. Development of Management Strategies

Management strategies were developed in this study to improve the risk factors related to the owner, A/E, and contractor. Construction managers may implement the management strategies to reduce schedule delays in construction projects. The developed management strategies were used to improve the top three ranked risk factors identified by the GA and RII. A performance sensitivity analysis was then conducted using the improved risk factors.

3.8. Sensitivity Analysis

A sensitivity analysis was performed to detect the effect of risk factors on the output by assessing their sensitivity to the output. Mrzygłód et al. [40] stated that sensitivity analyses can be applied to identify the effects of the input factors of an ANN model on its output factor. The effects of the risk factors on the output was assessed in this study by improving the factors by 10%, 20%, 30%, and 40%. The sensitivity analysis was conducted using the output obtained from the trained ANN connection weight.

4. Model Implementation

The proposed CSRAM was implemented on the data collected from the fields and government offices. A total of 41 risk factors were determined on the basis of a literature review and a pilot questionnaire survey; after performing three statistical method analyses, 22 risk factors were selected to establish the final database using the 94 historical cases (see Table 8). The number of neurons is a crucial parameter in ANN model training. Overfitting might occur with an increase in the number of hidden neurons. This phenomenon reduces the RMSE in the training stage, but not in the validation stage [31]. Therefore, the optimum number of hidden neurons must be determined through trial and error [26]. In this study, the RMSEs of training and validation had minimum values when the number of hidden neurons was 11. Therefore, an ANN architecture with 22 input neurons that corresponded to 22 risk factors, 11 hidden neurons, and 1 output neuron was used (Figure 3). A 10-fold cross-validation approach was used during the training and validation processes, yielding average RMSE values of 0.1097 and 0.1108, respectively. After data training was completed, the GA was used to determine RWs by partitioning the connection weight of the ANN to rank the risk factors. The risk factors were also ranked according to the RII for comparison. Management strategies were developed to improve the top three ranked risk factors identified using the GA and RII. A sensitivity analysis was then performed using the improved risk factors. Finally, the CSRAM identified change orders, corruption/bribery, and delays in payment as the risk factors with the strongest influences on schedule delays.

4.1. Calculation of the RWs of the Selected Risk Factors by Using the GA

After ANN training was completed, the GA was employed to determine the RWs of the 22 selected risk factors. These factors were then ranked according to their RWs. The higher the RW of a risk factor, the higher the influence of the risk factor on schedule delay. The following procedure is performed to determine the RWs of the selected risk factors:
  • The P 11 is calculated as shown below. The absolute values of connection weights for all selected risk factors are presented in Table 9, while the results computed for pij are presented in Table 10.
    P 11 = 3.967     1.246 = 4.941 P 12 = 7.521     1.246 = 9.369
  • Q 11 is calculated using Equation (6), and Table 11 presents the results of Q i j for all selected factors.
    Q 11 = 4.941 / ( 4.941 + 9.369 + 0.088 + 1.153 + 1.501 + 4.548 + 0.949 +   0.087 + 0.763 + 0.083 + 0.764 + 0.396 + 1.884 + 1.221 +   0.507 + 0.899 + 0.260 + 2.127 + 0.525 + 2.694 + 0.453 +   3.438 ) = 0.128
  • S 1 is calculated using Equation (7), and Table 11 presents the results computed for S i .
    S 1 = 0.128 + 0.147 + 0.122 + 0.086 + 0.169 + 0.145   + 0.120   + 0.120 + 0.240 + 0.188 + 0.189 = 1.654
  • For input neuron 1 (F1), the RW is 15.031%, as per Equation (8).
    F 1   =   1.654     100 / ( 1.654 + 1.877 + 0.248 + 0.180 + 0.253 + 1.783 + 0.352 +   0.226 + 0.278 + 0.402 + 0.283 + 0.373 + 0.298 + 0.349 +   0.302 + 0.259 + 0.251 + 0.379 + 0.241 + 0.264 + 0.395 +   0.357 ) = 15.031 %
The RWs of 22 selected risk factors are shown in Table 12, which were obtained in the same manner.
The results of GA indicate that delays in material delivery have the weakest influence on schedule delay, whereas change orders have the strongest influence, followed by corruption/bribery and delays in payment (Table 12 and Figure 4). Change orders in a construction project can disturb the relationship between the owner and the contractor. Change orders may be reduced if clients and contractors appropriately manage these during the bidding process. Establishing a superior financial system can also minimize the causes of corruption. Contractors, especially those facing financial difficulties in implementing projects, may face problems due to delays in payment and may need to work with financial institutions to overcome these problems. Thus, a weak financial system and financial difficulties in the organization implementing the project can cause change orders, corruption, and delays in payment.

4.2. Calculation of the RII of the Selected Risk Factors

RII of the risk factor is calculated using Equation (9). The RII results indicate that construction method has the weakest influence on schedule delays. Moreover, poor resource management, corruption/bribery, and delays in material delivery were the top three factors influencing schedule delays (Table 12 and Figure 5). Many contractors with limited experience are currently engaged in the country, perhaps resulting in poor resource management due to a lack of contractor experience. Corruption has the second-strongest influence on schedule delays according to the GA and RII results. Gebrehiwet and Luo [23] also identified corruption as a major cause of construction project schedule delays in Ethiopia. The source of corruption in the construction sector is complex; this corruption not only reduces the construction quality but may also cause project failure. A lack of trust and accountability may be the cause of corruption, and strong law enforcement is a crucial mechanism in its reduction; all stakeholders must work to combat corruption in the Ethiopian construction industry.

4.3. Develop Management Strategies for Improving the Top Three Ranked Risk Factors

Management strategies addressing the possible causes and methods for reducing change orders, corruption/bribery, delays in payment, poor resource management, and delays in material delivery were developed (Table 13). For example, “owner interest to replace with other materials” may be the cause for a change order that is related to the owner, and the proposed improvement is “owners must decide the materials before bidding”. FGCs currently working in the industry can implement the developed management strategies to maintain project schedules. Based on the management strategies, the factors were improved and then compared in order to identify the risk factors with the highest influence on construction schedule delays through a sensitivity analysis. The analysis results validate whether the GA or RII is more accurate in indicating the risk factors that have strong influences on construction schedule delays in Ethiopian construction projects.

4.4. Sensitivity Analysis

The GA results indicate that change order, corruption, and delay in payment are the top three factors affecting construction schedule delays, and the RII results indicate that poor resource management, corruption, and delay in material delivery are the top three factors affecting schedule delays in Ethiopian construction projects (Table 12). Different risk factors had different rankings in the GA and RII results, as displayed in Figure 4 and Figure 5. In the GA results, change orders and delays in payment had the highest and third-highest RWs, respectively, for schedule delays; however, in the RII results, these factors ranked in 9th and 19th. Conversely, poor resource management and delays in material delivery were ranked first and third in the RII results but had nonsignificant RWs in the GA results. Only corruption is in the top three ranked risk factors in both the GA and RII results. Therefore, it is important to further compare the influences of the risk factors to identify which order of the risk factors is correct. To facilitate this comparison, a sensitivity analysis was performed after improving the risk factors in order to identify the risk factors that strongly influence construction schedule delays.
In Table 14, the average percentage schedule delay of the 94 cases, without improvements in the top three ranked risk factors, was 102.85%. A sensitivity analysis was performed using the improved risk factors in the database without changing the input values of the others, and the schedule delay was predicted with the output of the trained ANN. The risk factors were assumed to improve (i.e., decrease) by 10%, 20%, 30%, and 40%. These changes in input values can affect the output. Gevrey [30] stated that the input factors whose changes affect the output the most have the greatest influence on the output. First, a 10% improvement in the top three risk factors ranked by GA (F2, F10, and F1) were updated in the database, and the schedule delays of the 94 cases were predicted. This process was repeated for the 20%, 30%, and 40% improvements in the top three factors. For each improvement level, the average percentage of schedule delay was noted. For 10%, 20%, 30%, and 40% improvements of the top three risk factors ranked by GA, the average schedule delays of the 94 cases were 92.25%, 89.7%, 87.72%, and 86.08%, respectively. The aforementioned steps were also performed for the top three risk factors in the RII results (F23, F10, and F7). For 10%, 20%, 30%, and 40% improvements of these factors, the average schedule delays were 100.52%, 98.62%, 96.95%, and 95.50%, respectively.
Taking the 10% improvement as an example, the top three ranked risk factors in the GA and RII analyses resulted in the reduction of the average schedule delay from 102.85% to 92.25% and from 102.85% to 100.52%, respectively (Table 14). The schedule delay obtained from the 10% improvement of the top-ranked risk factors in the GA analysis was lower than that obtained from the 40% improvement in the top three ranked risk factors in the RII analysis. Figure 6 displays the decreasing trends of the average percentage of schedule delay (represented by sloped lines) after improvements in the risk factors. The sloped line representing the improvement in the top three ranked risk factors in the GA results is considerably lower than that of the RII results. Thus, the top three ranked risk factors identified by GA were more sensitive to the schedule delay than the factors identified by RII. This finding validates that the proposed method is more practical and can accurately identify the main risk factors that cause construction schedule delays in Ethiopia.

5. Conclusions

In this study, the integrated method, CSRAM, was developed to systematically and objectively identify and rank the risk factors for the improvement of construction schedule delay. By applying CSRAM, the subjective judgement of experts for risk factor identification was reduced to a minimum; likewise, the interactive relationships of the factors in the analysis process were considered and measured in order to enhance the consistency of factor ranking. CSRAM includes these three phases of analysis: risk factor selection and database development, factor ranking using AI, and comparison and sensitivity analysis for validation.
In the phase of risk factor selection and database development, three steps—literature review, two questionnaire surveys of Ethiopian domain experts, and three statistical analyses—were developed to select the risk factors for this study. The initial 26 factors were identified according to the literature reviews. A total of 41 influencing factors specific to Ethiopia were determined though the pilot questionnaire survey of experts, whereas information on 94 construction projects was collected to establish the database. In total, 75 expert questionnaire surveys were conducted to identify the impacts of the factors. Three statistical methods, including univariate selection, feature importance selection, and a correlation matrix with a heat map, were applied to analyze the correlation of the factors with the schedule delay. A total of 22 final risk factors were selected for the factor ranking analysis.
Secondly, ANN was integrated with GA, thus solving the interactive and non-linear relationships of the risk factors, was developed to train the network and calculate the RWs of the risk factors with ranking. The top three ranked factors identified were change order, corruption/bribery, and delay in payment.
Thirdly, the RII method was also used for the factor ranking comparison and was able to identify the factors of poor resource management, corruption/bribery, and delay in material delivery in sequence. According to the identified factors, the management strategies related to the possible causes and methods of schedule delay control were addressed. Moreover, a sensitivity analysis with a 10% arithmetic increase sequence of the top three ranked factors was conducted to validate the sensitivities of the impact of improved factors to the construction project delay. For 10%, 20%, 30%, and 40% improvements in the top three risk factors ranked by GA, the average schedule delays in 94 cases were 92.25%, 89.7%, 87.72%, and 86.08%, respectively. For RII, the average schedule delays were 100.52%, 98.62%, 96.95%, and 95.50%, respectively. The 92.25% schedule delay obtained from the 10% improvement in the GA analysis was lower than that obtained from the 40% improvement in the RII analysis, which was at 95.5%. The improvements in the top three ranked risk factors identified by GA proved to be more sensitive and significant to the schedule delay reductions, whereas the validation of CSRAM in terms of objectiveness and consistency was achieved.
Schedule delay is a serious and essential problem in the Ethiopian construction industry. However, through CSRAM, this study is able to provide an objective and consistent approach for identifying the key causes of schedule delays. Thus, construction managers can spend their effort focusing on the critical risk factors for substantially improving the schedule delay. Moreover, for FGCs suffering project delays due to the lack of information on the Ethiopian construction industry, this study not only provides management strategies as guidelines for the reduction of schedule delays, but also serves as an important reference in schedule control for the FGCs who plan to enter or are working in the Ethiopian construction industry. The database of 94 construction projects collected in this study is also a valuable resource for future studies related to the issue of construction delay.

Author Contributions

Conceptualization, M.-Y.C.; data curation, M.H.D.; formal analysis, M.-Y.C. and M.H.D.; investigation, M.H.D.; methodology, M.-Y.C. and M.H.D.; resources, M.-Y.C.; software, M.H.D.; supervision, M.-Y.C.; validation, M.-Y.C.; visualization, M.H.D.; writing—original draft, M.H.D.; writing—review & editing, M.-Y.C. Finally, all authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data presented in this study are available upon reasonable request from the corresponding author. The data are not publicly available due to the data also collected from government offices for research use only.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

AIArtificial Intelligence
ANNArtificial Neural Network
CSRAMConstruction Schedule Risk Assessment Model
FGCForeign General Contractors
A/EArchitectural and Engineering
GAGarson Algorithm
RWRelative Weight
RIIRelative Importance Index
RMSERoot Mean Square Error

References

  1. Sambasivan, M.; Soon, Y.W. Causes and effects of delays in Malaysian construction industry. Int. J. Project Manag. 2007, 25, 517–526. [Google Scholar] [CrossRef]
  2. Sweis, G.; Sweis, R.; Abu Hammad, A.; Shboul, A. Delays in construction projects: The case of Jordan. Int. J. Project Manag. 2008, 26, 665–674. [Google Scholar] [CrossRef]
  3. Orangi, A.; Palaneeswaran, E.; Wilson, J. Exploring Delays in Victoria-Based Australian Pipeline Projects. In Proceedings of the Twelfth East Asia-Pacific Conference on Structural Engineering and Construction Procedia Engineering, Hong Kong, China, 26–28 January 2011; Volume 14, pp. 874–881. [Google Scholar]
  4. Aziz, R.F.; Abdel-Hakam, A.A. Exploring delay causes of road construction projects in Egypt. Alex. Eng. J. 2016, 55, 1515–1539. [Google Scholar] [CrossRef] [Green Version]
  5. Koshe, W.; Jha, N.K. Investigating Causes of Construction Delay in Ethiopian Construction Industries. J. Civ. Constr. Environ. Eng. 2016, 1, 18–29. [Google Scholar]
  6. Tadewos, S.G.; Patel, D. Factors influencing Time and Cost Overruns in Road Construction Projects: Addis Ababa, Ethiopian Scenario. Int. J. Eng. Technol. 2018, 5, 177–180. [Google Scholar]
  7. Kebede, S.D.; Zhang, T. Enforcement of legal remedies against construction projects time overrun in Ethiopia: A critical appraisal. Heliyon 2020, 6, e05126. [Google Scholar] [CrossRef]
  8. Zinabu, T.Z. Construction Projects Delay and Their Antidotes: The Case of Ethiopian Construction Sector. Int. J. Econ. Bus. Res. 2016, 5, 113–122. [Google Scholar]
  9. Al-Momani, A.H. Construction delay: A quantitative analysis. Int. J. Project Manag. 2000, 18, 51–59. [Google Scholar] [CrossRef]
  10. Odeh, A.M.; Battaineh, H.T. Causes of Construction delay: Traditional contracts. Int. J. Project Manag. 2002, 20, 67–73. [Google Scholar] [CrossRef]
  11. Assaf, S.A.; Al-Hejji, S. Causes of delay in large construction projects. Int. J. Project Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
  12. El-Razek, M.E.A.; Bassioni, H.A.; Mobarak, A.M. Causes of Delay in Building Construction Projects in Egypt. J. Constr. Eng. Manag. 2008, 134, 831–841. [Google Scholar] [CrossRef] [Green Version]
  13. Chan, D.W.M.; Chan, A.P.C.; Lam, P.T.I.; Yeung, J.Y.; Chan, J.H.L. Risk ranking and analysis in target cost contracts: Empirical evidence from the construction industry. Int. J. Project Manag. 2011, 29, 751–763. [Google Scholar] [CrossRef] [Green Version]
  14. Doloi, H.; Sawhney, A.; Iyer, K.C.; Rentala, S. Analysing factors affecting delays in Indian construction projects. Int. J. Project Manag. 2012, 30, 479–489. [Google Scholar] [CrossRef]
  15. Kazaz, A.; Ulubeyli, S.; Tuncbilekli, N.A. Causes of Delays in Construction Projects in Turkey. J. Civ. Eng. Manag. 2012, 18, 426–435. [Google Scholar] [CrossRef] [Green Version]
  16. Alinaitwe, H.; Apolot, R.; Tindiwensi, D. Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects. J. Constr. Dev. 2013, 18, 33–47. [Google Scholar]
  17. Aziz, R.F. Ranking of delay factors in construction projects after Egyptian revolution. Alex. Eng. J. 2013, 52, 387–406. [Google Scholar] [CrossRef] [Green Version]
  18. Fallahnejad, M.H. Delay causes in Iran gas pipeline projects. Int. J. Project Manag. 2013, 31, 136–146. [Google Scholar] [CrossRef]
  19. Kuo, Y.-C.; Lu, S.-T. Using fuzzy multiple criteria decision making approach to enhance risk assessment for metropolitan construction projects. Int. J. Project Manag. 2013, 31, 602–614. [Google Scholar] [CrossRef]
  20. Gardezi, S.S.S.; Manarvi, I.A.; Gardezi, S.J.S. Time Extension Factors in Construction Industry of Pakistan. In Proceedings of the Fourth International Symposium on Infrastructure Engineering in Developing Countries, Karachi, Pakistan, 11–13 December 2013; Volume 77, pp. 196–204. [Google Scholar]
  21. Marzouk, M.M.; El-Rasas, T.I. Analyzing delay causes in Egyptian construction projects. J. Adv. Res. 2014, 5, 49–55. [Google Scholar] [CrossRef] [Green Version]
  22. Al-Hazim, N.; Salem, Z.A.; Ahmad, H. Delay and Cost Overrun in Infrastructure Projects in Jordan. In Proceedings of the 7th International Conference on Engineering, Project, and Production Management, Bialystok, Poland, 21–23 September 2017; Volume 182, pp. 18–24. [Google Scholar]
  23. Gebrehiwet, T.; Luo, H. Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study. In Proceedings of the Creative Construction Conference 2017, CCC 2017, Primosten, Croatia, 19–22 June 2017; Volume 196, pp. 366–374. [Google Scholar]
  24. Ibrahim, M. Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects. Int. J. Archit. Eng. Constr. 2017, 6, 51–58. [Google Scholar]
  25. Mohammed, R.M.M.; Suliman, S.M.A. Delay in Pipeline Construction Projects in the Oil and Gas Industry: Part 2 (Prediction Models). Int. J. Constr. Eng. Manag. 2019, 8, 37–45. [Google Scholar]
  26. Xu, M.; Wong, T.C.; Chin, K.S. Modeling daily patient arrivals at Emergency Department and quantifying the relative importance of contributing variables using artificial neural network. Decis. Support Syst. 2013, 54, 1488–1498. [Google Scholar] [CrossRef]
  27. Zhang, Z.; Beck, M.W.; Winkler, D.A.; Huang, B.; Sibanda, W.; Goyal, H. Opening the black box of neural networks: Methods for interpreting neural network models in clinical applications. Ann. Transl. Med. 2018, 6, 216. [Google Scholar] [CrossRef]
  28. Ibrahim, O.M. A comparison of methods for assessing the relative importance of input variables in artificial neural networks. JASR 2013, 9, 5692–5700. [Google Scholar]
  29. Garson, G.D. Interpreting neural network connection weights. Artif. Intell. Expert 1991, 6, 47–51. [Google Scholar]
  30. Gevrey, M.; Dimopoulos, I.; Lek, S. Review and comparison of methods to study the contribution of variables in artificial neural network models. Ecol. Modell. 2003, 160, 249–264. [Google Scholar] [CrossRef]
  31. Chen, J.; Chen, W. Diagnostic analysis of a small-scale incinerator by the Garson index. Inf. Sci. 2008, 178, 4560–4570. [Google Scholar] [CrossRef]
  32. Baruah, D.; Baruah, D.C.; Hazarika, M.K. Artificial neural network based modeling of biomass gasification in fixed bed downdraft gasifiers. Biomass Bioenergy. 2017, 98, 264–271. [Google Scholar] [CrossRef]
  33. Korteby, Y.; Kristó, K.; Sovány, T.; Regdon, G. Use of machine learning tool to elucidate and characterize the growth mechanism of an in-situ fluid bed melt granulation. Powder Technol. 2018, 331, 286–295. [Google Scholar] [CrossRef] [Green Version]
  34. Zhang, Y.; Gao, X.; Smith, K.; Inial, G.; Liue, S.; Conil, L.B.; Pan, B. Integrating water quality and operation into prediction of water production in drinking water treatment plants by genetic algorithm enhanced artificial neural network. Water Res. 2019, 164, 114888. [Google Scholar] [CrossRef]
  35. Zhi, H. Risk management for overseas construction projects. Int. J. Project Manag. 1995, 13, 231–237. [Google Scholar] [CrossRef]
  36. Ling, F.Y.Y.; Low, S.P.; Wang, S.Q.; Lim, H.H. Key project management practices affecting Singaporean firms’ project performance in China. Int. J. Project Manag. 2009, 27, 59–71. [Google Scholar] [CrossRef]
  37. Cheng, M.-Y.; Wu, Y.-W.; Syu, R.-F. Seismic Assessment of Bridge Diagnostic in Taiwan Using the Evolutionary Support Vector Machine Inference Model (ESIM). Appl. Artif. Intell. 2014, 28, 449–469. [Google Scholar] [CrossRef]
  38. Dogan, G.; Alotaibi, N.; Sahin, E.; Ertas, S.S.; Cay, I.; Keskin, S.R.; Heijnen, M.J.; Ricanek, K. Using Artificial Intelligence to Predict Fall-risk During Adaptive Locomotion in Humans. In Proceedings of the International Conference on Artificial Intelligence & Modern Assistive Technology (ICAIMAT), Riyadh, Saudi Arabia, 24–26 November 2020; pp. 1–7. [Google Scholar]
  39. Cheng, M.-Y.; Cao, M.-T. Accurately predicting building energy performance using evolutionary multivariate adaptive regression splines. Appl. Soft Comput. 2014, 22, 178–188. [Google Scholar] [CrossRef]
  40. Mrzygłód, B.; Hawryluk, M.; Janik, M.; Wożeńska, I. Sensitivity analysis of the artificial neural networks in a system for durability prediction of forging tools to forgings made of C45 steel. Int. J. Adv. Manuf. Technol. 2020, 109, 1385–1395. [Google Scholar] [CrossRef]
Figure 1. Research flowchart.
Figure 1. Research flowchart.
Sustainability 13 07830 g001
Figure 2. Flowchart for ANN training, validation, and testing.
Figure 2. Flowchart for ANN training, validation, and testing.
Sustainability 13 07830 g002
Figure 3. ANN architecture used in this study.
Figure 3. ANN architecture used in this study.
Sustainability 13 07830 g003
Figure 4. RWs of the selected factors obtained using the GA.
Figure 4. RWs of the selected factors obtained using the GA.
Sustainability 13 07830 g004
Figure 5. Rankings of the selected risk factors according to their RIIs.
Figure 5. Rankings of the selected risk factors according to their RIIs.
Sustainability 13 07830 g005
Figure 6. Sloped lines of the GA and RII sensitivity analysis.
Figure 6. Sloped lines of the GA and RII sensitivity analysis.
Sustainability 13 07830 g006
Table 1. Connection weights of the hidden layers in the ANN architecture.
Table 1. Connection weights of the hidden layers in the ANN architecture.
Hidden NeuronsWeights
Input 1Input 2Input 3Output
Hidden 1−1.676243.290221.324664.57857
Hidden 2−0.51874−0.22921−0.25526−0.48815
Hidden 3−4.017642.12486−0.08168−5.73901
Hidden 4−1.75691−1.447020.58286−2.65221
Table 2. Product of the absolute values of the hidden-output and hidden-input layer connection weights ( P i j ).
Table 2. Product of the absolute values of the hidden-output and hidden-input layer connection weights ( P i j ).
Input 1Input 2Input 3
Hidden 1 P 11 = 1.67624 × 4.57857 P 12 = 3.29022 × 4.57857 P 13 = 1.32466 × 4.57857
Hidden 2 P 21 = 0.51874 × 0.48815 P 22 = 0.22921 × 0.48815 P 23 = 0.25526 × 0.48815
Hidden 3 P 31 = 4.01764 × 5.73901 P 32 = 2.12486 × 5.73901 P 33 = 0.08168 × 5.73901
Hidden 4 P 41 = 1.75691 × 2.65221 P 42 = 1.44702 × 2.65221 P 43 = 0.58286 × 2.65221
Table 3. Division of the product connection weight ( P i j ) by the sum of all the input variables to obtain ( Q i j ).
Table 3. Division of the product connection weight ( P i j ) by the sum of all the input variables to obtain ( Q i j ).
Input 1Input 2Input 3
Hidden 1 Q 11 = 0.266445 Q 12 = 0.522994 Q 13 = 0.210560
Hidden 2 Q 21 = 0.517081 Q 22 = 0.228478 Q 23 = 0.254441
Hidden 3 Q 31 = 0.645489 Q 32 = 0.341388 Q 33 = 0.013123
Hidden 4 Q 41 = 0.463958 Q 42 = 0.382123 Q 43 = 0.153919
Sum S 1 = 1.892973 S 2 = 1.474983 S 3 = 0.632044
Table 4. Relative weights of input variables.
Table 4. Relative weights of input variables.
Input 1Input 2Input 3
Relative weight (%)47.336.915.8
Table 5. Literature reviews of risk factors causing construction schedule delays.
Table 5. Literature reviews of risk factors causing construction schedule delays.
Sn.FactorsLiteratures
[1][2][3][4][5][6][8][14][20][23][11][12][17][21][24][10][22][9][15][16]Frq.
1Improper planning and scheduling 14
2Variation/Change order 13
3Financial difficulties 11
4Delays in payment 11
5Problem/ Poor Site management 10
6Increase of Material price 6
7Defective design/incorrect/error 6
8Equipment availability and failure 6
9Problem in Sub-contractors works 6
10Mistakes and rework 6
11Inadequate contractor experience 5
12Shortage in material 5
13Unrealistic contract duration and requirements imposed 4
14Delay in material delivery 4
15Poor labor productivity 4
16Shortage of labor supply 4
17Inflation 4
18Inappropriate type of project bidding and award 3
19Lack of skilled workers 3
20lack of effective communication between parties 3
21Waiting time for approval and inspection 3
22Management problem 3
23Slow decision making 3
24Skill of technical staff problem/unqualified 3
25Adverse Weather conditions 3
26Difficulties in obtaining work permit/land acquisition 3
27Bribe/corruption 2
28Lack of clarity in scope Sustainability 13 07830 i001 2
68Emergency works 1
69unavailability of utilities at site 1
70Global financial crisis 1
Note: Frq. = frequency; Sn. = serial number.
Table 6. Background of the participants in the second stage of the questionnaire survey.
Table 6. Background of the participants in the second stage of the questionnaire survey.
Experience (in Years)Frequency Educational LevelFrequency
More than 208College graduate17
11 to 1546BSc.22
6 to 1015MSc.25
Less than 56PhD.11
Table 7. Statistical analysis for selecting risk factors.
Table 7. Statistical analysis for selecting risk factors.
SymbolRisk FactorsCategory of Risk FactorsUnivariate SelectionFeature Importance Correlation MatrixStatus
F1Delays in paymentFBO
F2Variation/Change orderFBO
F3Shortage in materialFB O
F4Problem in sub-contractor workFB X
F5Mistakes and reworkFB X
F6Waiting time for approval and inspectionFB X
F7Delay in material deliveryFB O
F8Conflict among partiesFB X
F9Lack of peace and securityFB O
F10Corruption and BriberyFBO
F11Scarcity of foreign exchange and rate fluctuation FB O
F12Disputes on landFB X
F13Poor implementation of plan (poor performance)FBO
F14Strike, revolution, riot, protestFB O
F15Construction methodsFB O
F16Political insecurity and instabilityFB O
F17Slow decision makingFB O
F18Defective design/incorrect/errorFBO
F19Increase of material price, price fluctuationFB O
F20Lack of skilled workersFB X
F21Poor labor productivityFB O
F22RebellionFB O
F23Poor resource managementFB O
F24Unavailability of utility at site (electricity, water)FB O
F25Skill of technical staff problemFB X
F26Labor absenteeismFB X
F27Improper planning and schedulingBB O
F28Financial difficultiesBB X
F29Unrealistic contract duration and requirements imposedBB O
F30Inadequate contractor experienceBB X
F31Management problemBB X
F32Lack of effective communication between partiesBB X
F33Inappropriate type of project bidding and awardBB O
F34InflationBB X
F35Difficulties in obtaining work permitsBB X
F36Transportation problem to site locationBB X
F37Labor culture of work/ attitudeBB X
F38Lack of commitment of general contractor BB X
F39Problem/ Poor Site managementBB X
F40Inadequate modern equipmentBB O
F41Project site location (boundary problem)BB X
Note: O: Selected; X: Not selected; FB = Frequency-based; BB = Binary-based.
Table 8. Established historical cases of the construction projects.
Table 8. Established historical cases of the construction projects.
Proj #Input FactorsOutput
F1F2F3F7F9F10F11F13F14F15F16F17F18F19F21F22F23F24F27F29F33F40Delay%
10.500.400.000.330.331.000.900.500.000.500.500.500.500.500.000.000.000.501.001.000.001.000.63
20.500.300.400.330.330.400.200.500.300.200.200.300.100.500.400.200.000.401.001.000.001.000.88
31.000.101.000.000.000.301.001.000.000.000.501.000.501.001.000.000.001.001.001.000.001.000.35
40.400.200.300.000.000.400.100.400.000.000.000.100.200.300.300.000.000.001.001.000.000.000.67
50.100.000.300.440.440.300.100.100.900.100.500.100.200.200.000.900.000.200.000.000.000.000.50
60.301.001.000.220.220.400.200.300.000.100.200.500.601.001.000.000.220.801.000.000.001.000.50
70.000.300.001.001.000.000.000.001.000.900.900.300.000.000.300.200.000.000.000.001.001.000.34
80.500.400.000.330.330.000.500.500.000.500.500.500.500.500.000.000.110.501.001.000.001.000.50
90.500.500.500.000.000.100.000.500.000.500.500.501.001.000.501.000.000.001.000.000.000.000.44
100.300.300.300.000.000.400.100.300.100.200.000.300.100.100.200.200.000.201.000.000.001.000.75
110.100.200.200.220.220.200.200.100.100.000.100.100.100.200.200.100.000.201.001.001.000.000.34
120.500.600.000.000.000.500.000.500.000.000.000.000.201.000.200.000.220.301.001.001.000.000.50
130.500.600.000.000.000.500.000.500.000.000.000.000.200.900.200.000.440.301.001.001.000.000.32
140.600.400.000.000.000.200.000.600.000.000.000.000.201.000.400.000.330.801.001.000.000.000.50
151.000.901.000.440.440.400.601.000.600.000.600.300.100.100.200.200.110.201.000.000.001.000.34
160.001.000.500.560.560.200.000.000.000.200.200.200.500.500.000.500.330.501.000.001.000.000.75
170.500.500.500.560.560.801.000.500.500.501.000.501.000.500.500.500.110.501.000.001.000.000.75
180.501.001.000.330.330.900.500.500.300.300.500.300.901.000.500.200.560.201.001.001.001.000.75
191.000.001.000.560.560.800.101.000.500.500.500.500.800.101.000.500.220.001.000.001.000.000.75
200.500.500.500.000.000.700.000.500.000.500.500.501.001.000.501.000.560.001.000.000.000.000.50
Sustainability 13 07830 i002
911.000.700.000.000.000.900.000.300.000.000.100.100.200.000.000.700.000.001.001.000.001.000.48
921.000.101.000.000.000.201.001.000.000.000.500.100.500.000.000.000.110.101.001.000.001.000.05
930.600.500.000.000.330.200.000.600.300.200.000.000.200.200.400.000.220.101.001.001.001.000.44
940.500.600.500.000.330.700.000.500.300.500.500.500.100.500.500.600.780.001.001.001.001.000.75
Table 9. Absolute values of the connection weights obtained from trained ANN.
Table 9. Absolute values of the connection weights obtained from trained ANN.
Weights
F1F2F3F7F9F10F11F13F14F15F16F17F18F19F21F22F23F24F27F29F33F40Output
Hidden 13.9677.5210.0700.9251.2053.6510.7620.0700.6120.0670.6130.3181.5120.9800.4070.7220.2091.7070.4212.1620.3642.7601.246
Hidden 23.1982.4490.6400.6940.3294.2360.0280.1380.3610.6431.2761.5720.4230.5141.6240.0850.5790.4750.6190.9780.5050.3291.230
Hidden 32.9923.4551.9820.0570.5683.8660.5181.7810.1800.0930.5660.2190.9991.2100.6970.8140.6181.1830.5420.7521.4370.0561.807
Hidden 42.8215.1630.5490.4721.6504.1781.1980.3310.8952.6620.4783.1780.7580.3190.8720.4030.5231.6631.1650.8072.0760.4901.749
Hidden 54.3533.1000.1260.4860.1264.0240.2700.6820.0341.3290.7110.3540.6350.8880.5600.1562.3671.0240.8220.0562.6340.9571.145
Hidden 64.0644.2520.5460.2030.7823.0371.2830.5311.1900.9500.7081.0170.3471.0881.6242.5140.3940.4880.0860.1450.6922.1881.739
Hidden 74.0655.7711.6841.5580.7552.9432.7360.8180.1260.4460.5031.4422.0972.2290.3110.7190.5240.4120.9540.4281.1262.1881.668
Hidden 84.2303.7560.1380.1721.0743.6161.3541.1002.0793.6081.2150.8680.7901.2561.8500.1301.2552.7701.7210.1310.3341.6682.088
Hidden 93.2882.3040.0260.1960.0844.1170.3630.3190.3640.3300.4380.4130.0130.0910.1350.0020.0180.2480.3170.3650.2540.0200.064
Hidden 103.4804.5180.7020.1380.5363.0620.4200.0040.7820.6700.3150.3400.3780.4810.0250.8050.1380.1150.0080.6940.7220.1501.017
Hidden 113.8555.3340.0060.0790.0815.4030.8330.2370.6570.4570.2840.3960.4760.5020.1150.4750.2280.6370.1060.0780.1940.0060.468
Table 10. Product of the absolute values of hidden-output and absolute values of hidden-input layers connection weights (pij).
Table 10. Product of the absolute values of hidden-output and absolute values of hidden-input layers connection weights (pij).
F1F2F3F7F9F10F11F13F14F15F16F17F18F19F21F22F23F24F27F29F33F40
Hidden 14.9419.3690.0881.1531.5014.5480.9490.0870.7630.0830.7640.3961.8841.2210.5070.8990.2602.1270.5252.6940.4533.438
Hidden 23.9343.0120.7870.8530.4055.2100.0350.1700.4450.7911.5691.9330.5200.6321.9980.1040.7120.5840.7611.2030.6210.404
Hidden 35.4056.2423.5800.1031.0256.9840.9353.2170.3260.1691.0230.3951.8042.1861.2601.4711.1172.1360.9791.3592.5960.100
Hidden 44.9349.0300.9600.8262.8867.3072.0960.5801.5654.6560.8375.5581.3260.5581.5240.7050.9152.9092.0371.4123.6310.858
Hidden 54.9853.5500.1440.5560.1444.6090.3090.7810.0391.5220.8150.4060.7271.0170.6420.1782.7111.1720.9410.0653.0171.096
Hidden 67.0677.3930.9490.3541.3595.2802.2300.9242.0691.6511.2321.7680.6031.8912.8234.3710.6860.8480.1500.2521.2043.804
Hidden 76.7789.6242.8082.5981.2594.9074.5621.3640.2100.7430.8392.4043.4973.7170.5181.1990.8730.6871.5910.7141.8783.648
Hidden 88.8317.8410.2880.3602.2417.5502.8262.2974.3407.5332.5381.8121.6492.6223.8630.2722.6205.7833.5930.2750.6973.482
Hidden 90.2090.1470.0020.0130.0050.2620.0230.0200.0230.0210.0280.0260.0010.0060.0090.0000.0010.0160.0200.0230.0160.001
Hidden 103.5394.5940.7140.1400.5463.1140.4270.0040.7950.6810.3200.3460.3840.4890.0250.8180.1400.1170.0080.7050.7340.153
Hidden 111.8052.4980.0030.0370.0382.5300.3900.1110.3070.2140.1330.1850.2230.2350.0540.2220.1070.2980.0500.0370.0910.003
Table 11. Product connection weight (pij) divided by the sum of all input variables to obtain ( Q i j ).
Table 11. Product connection weight (pij) divided by the sum of all input variables to obtain ( Q i j ).
F1F2F3F7F9F10F11F13F14F15F16F17F18F19F21F22F23F24F27F29F33F40
Hidden 10.1280.2420.0020.0300.0390.1180.0250.0020.0200.0020.0200.0100.0490.0320.0130.0230.0070.0550.0140.0700.0120.089
Hidden 20.1470.1130.0300.0320.0150.1950.0010.0060.0170.0300.0590.0720.0200.0240.0750.0040.0270.0220.0290.0450.0230.015
Hidden 30.1220.1410.0810.0020.0230.1570.0210.0720.0070.0040.0230.0090.0410.0490.0280.0330.0250.0480.0220.0310.0580.002
Hidden 40.0860.1580.0170.0140.0510.1280.0370.0100.0270.0820.0150.0970.0230.0100.0270.0120.0160.0510.0360.0250.0640.015
Hidden 50.1690.1210.0050.0190.0050.1570.0110.0270.0010.0520.0280.0140.0250.0350.0220.0060.0920.0400.0320.0020.1030.037
Hidden 60.1450.1510.0190.0070.0280.1080.0460.0190.0420.0340.0250.0360.0120.0390.0580.0890.0140.0170.0030.0050.0250.078
Hidden 70.1200.1710.0500.0460.0220.0870.0810.0240.0040.0130.0150.0430.0620.0660.0090.0210.0150.0120.0280.0130.0330.065
Hidden 80.1200.1070.0040.0050.0310.1030.0390.0310.0590.1030.0350.0250.0220.0360.0530.0040.0360.0790.0490.0040.0100.047
Hidden 90.2400.1680.0020.0140.0060.3000.0270.0230.0270.0240.0320.0300.0010.0070.0100.0000.0010.0180.0230.0270.0190.001
Hidden 100.1880.2440.0380.0070.0290.1660.0230.0000.0420.0360.0170.0180.0200.0260.0010.0440.0070.0060.0000.0380.0390.008
Hidden 110.1890.2610.0000.0040.0040.2640.0410.0120.0320.0220.0140.0190.0230.0250.0060.0230.0110.0310.0050.0040.0090.000
Sum (S)1.6541.8770.2480.180.2531.7830.3520.2260.2780.4020.2830.3730.2980.3490.3020.2590.2510.3790.2410.2640.3950.357
Table 12. RWs and RIIs of the selected risk factors.
Table 12. RWs and RIIs of the selected risk factors.
SymbolRisk FactorsRelative Weight by Garson AlgorithmRelative Importance IndexRank of Risk Factors by RII
F1Delays in payment15.031%0.66666719
F2Variation/Change order17.062%0.6986679
F3Shortage in material2.249%0.69866710
F7Delay in material delivery1.649%0.7786673
F9Lack of peace and security2.294%0.69600011
F10Corruption and Bribery16.210%0.7920002
F11Scarcity of foreign exchange and rate fluctuation 3.174%0.68800013
F13Poor implementation of plan (poor performance)2.065%0.7066678
F14Strike, revolution, riot, protest2.533%0.7253335
F15Construction methods3.647%0.58133322
F16Political insecurity and instability2.559%0.65333320
F17Slow decision making3.401%0.68000017
F18Defective design/incorrect/error2.712%0.7173336
F19Increase of material price, price fluctuation,3.149%0.67733318
F21Poor labor productivity2.738%0.68533314
F22Rebellion2.363%0.64800021
F23Poor resource management2.290%0.8106671
F24Unavailability of utility at site (electricity, water)3.452%0.69333312
F27Improper planning and scheduling2.189%0.7280004
F29Unrealistic contract duration and requirements imposed2.380%0.7173337
F33Inappropriate type of project bidding and award3.583%0.68533315
F40Inadequate modern equipment3.258%0.68266716
Table 13. Developed management strategies.
Table 13. Developed management strategies.
List of Risk FactorsPossible Causes of the Risk FactorsIf Implemented, the Following Can Improve the Risk Factors
OwnerA/EContractorOwnerA/EContractor
Change order
Owner interest to replace with other materials
Change in the scope and plan of the project
Change of owners’ schedule
Escalation of costs and financial difficulties
Order for additional work
Slow decision-making
Selection of the lowest bidder
Lack of job site investigation
Tender drawing related problems/errors
Poor bidding preparation, and drawing error or omission
Misunderstanding of the client’s needs
Complex design, omission of crucial elements, and design changes
Errors in specification and estimation
Poorly qualified consultant engineer
Late delivery of materials
Failure to understand the client’s needs (contractor hired by the client)
Unavailable materials
Failure to cross-check the design
Ill-defined or changed scope
Failure to schedule for the materials
Inappropriate construction method
Owners must decide the materials before bidding
Owners must negotiate the terms strictly during the bid
The client is responsible for increased material costs
Working with financial institutes
Must agree to the performance of additional work
Decisions must be made on time
Select the bidder based on fair costs rather than lowest bidder
Perform detailed site investigation for project feasibility
Check all documents before opening a tender
Make a clear and correct design for the bidder according to the client’s needs
Have a detailed discussion with the owner before staring the design process
Cross-check for error
and omission of drawing
Cross-check for specification and estimated cost
Hire a qualified consultant
Plan and schedule appropriately for material delivery
Understand the clients’ needs comprehensively
Carefully plan for imported materials
Confirm design error before executing the project
Check the design and negotiate the terms strictly on the bidding process
Plan for materials according to the WBS
Use a better construction method
Corruption or Bribery
Poor professional ethical standards and poor accountability
Bribes for obtaining a work permit
Bribing officials to certify projects
Withhold payments for a “gift”
The decision on the overall budget
Illegal use of land
Pursuing bribes of the tender evaluation committee
Weak legislative system
Creating opportunities for relatives in the bidding process
Allocating excessive cost
Passing confidential information to prospective bidders
Bribes during inspection
Project design to favor certain individuals
Inadequacies in design and specification
Hiring of unqualified engineers
Bids not compatible with design specifications
Bribe to win the bid, reduce quality, and create smooth relationships
Poor procurement system
Wastage of materials in the warehouse
Corruption in selecting suppliers and partners
Fraud in underground work
Stealing of materials
Bribes for obtaining a license
Establish a clear system
Strong law enforcement
Organize separate design, tendering, and evaluation teams
Perform random supervision by a third party
Decision based on detailed information
Check whether the land is legal
Third party can audit the work of the tender committee
Check the weighted value on the bid
Disseminate information through electronic means
Have a third party audit the inspection result
Check the similarity with design specifications
Hire experienced A/E or provide training
Should hire qualified A/E
Check the design and specification on the bid
Be competent, perform quality work, and control the performance of the project
Make strong systematic procurements
Store materials as the order of installation
Conduct third-party cross-checks for selected suppliers and partners
Supervise during underground work
Hire a sufficient
number of guards
Check the legality of
the obtained license
Weak legislative system
Creating opportunities for relatives in the bidding process
Strong government system
The regulatory body must create fair, open, and free competition for bidding
Delays in payment
The bureaucracy of the client organization
Wrongfully withholds the payment
Budget allocation problem in the planning stage
Conflict among the parties
Change order during construction
Slow decision-making
Suspension of works
Shortage of budget (community-dependent project)
Security problems
Poor financial management
Protest, revolution, and riot
Unsuitable project cost
and financing
Quality of consultancy service rendered
Delay in payment certification
Turnover of consultants
Delay in approving documents, design, inspection, and testing
Complex design
Consultant work
overload
Incorrect field
supervision
Late submission of the payment request
Poor preparation of payment certificates or misunderstanding
Delay in the completion of the contract
Reworking due to error or the work done is different from the specifications
Conflict within parties
Dispute on the amount to be paid
Financial difficulty
Poor financial system
Insufficient documentation
Ensure the smooth functioning of the bureaucracy
Check the smooth
flow of the payment
Ensure that the
allocated budget is
fair
Organize a committee that can solve conflicts
between the parties
Change orders should
be according to the agreement during
the bid process
Make decisions on time as much as possible
Assume responsibility
for cost differences
Work with financial institutions
Hire additional guards
Make a better financial system
Owners can’t solve this problem
Check for fair project cost estimate
Hire a qualified consultancy
Prepare payment certification on time
Develop a better working environment
Provide all the necessary permissions on time
Ensure that the design is clear enough to implement
Hire equivalent number of consultancy
Perform detailed field supervision
Submit payment requests on time
Draw clear payment certificates and accept payments regularly according to the bid agreement
Abide by the schedule
Perform work carefully
Solve conflicts as soon as possible
Ensure that the payment amount complies with the agreement
Improve the financial background, work with financial institutions, and enter into a partnership agreement with other firms
Develop a better financial system
Perform well-organized documentation
Poor resource management
Staff turnover
Failure to manage legal issues
Inability to unite the team
Hiring of unsuitable people
Low worker morale
Changes in the quantity
of materials
Material estimation
problem
Inability to understand
the scope of the project
Poor project time
estimate
Poor execution
estimates
Poor allocation of resources
Poor project management, Poor understanding of projects, and lack of experience
Shortage of skilled labor
Poor planning and scheduling
Late delivery of materials
Outdated workflow (e.g., manual processes)
Poor time management
Absence of a risk management strategy
Failure to back up important resources
Hiring of labor on short-period contracts
Develop an attractive work environment
Follow all legal procedures
Unite the entire team to enhance performance
Hire qualified people
Work closely with workers and create a conducive work environment
The quantity of the materials should be according to the detailed design
Perform estimations using a detailed procedure
Understand the project before commencing design
Base time estimates on WBS for project duration
Check the project execution in previously completed projects
Allocate the resource as a project execution
Hire an experienced project manager or provide fair training
Manage the labor experience carefully
Continually check the schedule
Follows up the materials on the site
Provide training to resource managers
Stick to the schedule delay
Organize a risk management group
Buck up resources
Reduce labor turnover
Delay in material delivery
Transportation
problems to the site
Strikes, revolutions,
riots, or protests
Slow decision-making
Shortage of raw
materials
Change orders
Delays in payment
Insufficient planning or scheduling for materials
Changes in material types
Poor estimation of required amounts of materials
Poor scheduling and management
Lack of hard currency to import materials
Shortage of materials in the country
Selection of inappropriate suppliers
Poor material quality
Poor procurement system
The construction of temporary roads may be essential; if so, a suitable agreement must be made during the bid
The problem should be considered during the planning
The required decision should be made as early as possible
The schedule should consider the availability of materials
Change orders should be based on the bid agreement
Establish a better financial system and arrange regular payment times
Plan appropriately according to the material installation procedure
Strictly negotiate on change order during the bid process
The amount of materials should be estimated according to a detailed design
Plan appropriately for the delivery of materials
Work with financial institutes
Plan appropriately for importing materials
Consider the suppliers credit standing, ability to fulfill the supply materials, and geographical location
Before purchasing the materials, conduct inspections and tests
Create a better financial system
Table 14. Sensitivity analysis of GA and RII.
Table 14. Sensitivity analysis of GA and RII.
Top-3 Ranked
Risk Factors by
Before
Improvement
Improved by 10%Improved by 20%Improved by 30%Improved by 40%
Garson Algorithm102.8592.2589.787.7286.08
Relative Importance Index102.85100.5298.6296.9595.50
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Cheng, M.-Y.; Darsa, M.H. Construction Schedule Risk Assessment and Management Strategy for Foreign General Contractors Working in the Ethiopian Construction Industry. Sustainability 2021, 13, 7830. https://doi.org/10.3390/su13147830

AMA Style

Cheng M-Y, Darsa MH. Construction Schedule Risk Assessment and Management Strategy for Foreign General Contractors Working in the Ethiopian Construction Industry. Sustainability. 2021; 13(14):7830. https://doi.org/10.3390/su13147830

Chicago/Turabian Style

Cheng, Min-Yuan, and Mohammadzen Hasan Darsa. 2021. "Construction Schedule Risk Assessment and Management Strategy for Foreign General Contractors Working in the Ethiopian Construction Industry" Sustainability 13, no. 14: 7830. https://doi.org/10.3390/su13147830

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop